Construction device and method for paving steel-polypropylene composite fiber concrete on steel bridge deck
By designing construction devices and methods for steel-polypropylene composite fiber concrete on steel bridge decks, the uniform distribution of fibers in concrete is achieved, the problem of strength reduction caused by uneven fiber distribution is solved, and the load facing the bridge is improved withstand capacity and service life.
Patent Information
- Application Number
- CN202410940620.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-15
- Publication Date
- 2024-11-19
AI Technical Summary
The steel bridge deck paving layer reduces the concrete strength due to uneven fiber distribution, which is prone to cracks and pits and other diseases, affecting the safety and durability of the bridge deck.
A construction device and method for steel-polypropylene composite fiber concrete paving steel-polypropylene composite fiber concrete was designed. Through the cooperation of vertical casting and leveling mechanisms, the fibers are formed uniformly in the concrete by using electromagnet teeth and scrapers. Distribution, the fibers are arranged obliquely within the concrete layer, enhancing the tensile strength and impact resistance of the concrete.
It effectively improves the strength and service life of concrete, prevents cracks and pits on the bridge surface, and enhances the bridge's ability to withstand the vehicle load.
Smart Images

Figure CN118979423A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of steel-polypropylene composite fiber concrete construction, and in particular to a steel-polypropylene composite fiber concrete construction device and method for steel bridge deck paving. Background Art
[0002] At present, the construction of highway bridges is gradually tending towards the characteristics of high strength, large span, long life and sustainable development. Among them, steel box girders can effectively exert the bearing capacity of steel plates, and have the advantages of high strength, light weight and convenient construction. They have become a more commonly used type in large-span bridge projects. However, due to the high flexibility of steel bridge decks, they will produce large deformations under the influence of driving, wind, temperature, etc., and the thickness of the pavement layer is limited. If traditional concrete is used, the high rigidity of the concrete itself combined with the flexible steel bridge deck will cause cracks, potholes and other defects in the bridge deck pavement layer, thereby affecting the safety, durability and performance of the steel bridge.
[0003] Steel fiber and polypropylene fiber are added to concrete. Steel fiber has strong rigidity. Due to its long length, it can improve the curvature and roughness of concrete cracks from a macro perspective. Polypropylene fiber is easier to melt into the concrete due to its small size and large elastic modulus, making the concrete agglomerate, thereby improving the working performance of concrete from a micro perspective. Through the synergistic effect of the two fibers, the tensile strength of the cement matrix is improved, the production of micro cracks in cement-based materials is hindered, and the generation of new cracks is prevented, thereby enhancing the ability of cement-based materials to resist deformation and improving the toughness and impact resistance of the materials.
[0004] The loads on the bridge deck concrete are mainly the horizontal thrust generated by the vehicle during driving and the gravity of the vehicle itself. According to research, when the fiber direction is parallel to the load direction, the reinforcement efficiency of the concrete is the highest; and in the process of pouring steel-polypropylene composite fiber concrete, due to the interaction between the vibration force and the gravity of the fiber, the fiber is redistributed in the concrete in a random manner, and the fiber moves and concentrates to the lower part of the concrete, forming a random distribution of fibers in the concrete that is sparse on the top and dense on the bottom. The fiber distribution is uneven and the fibers are easily agglomerated, which reduces the overall strength of the concrete.
[0005] Therefore, it is necessary to provide a new steel-polypropylene composite fiber concrete construction device and method for steel bridge deck paving to solve the above technical problems. Summary of the invention
[0006] The technical problem solved by the present invention is to provide a construction device and method for steel-polypropylene composite fiber concrete for steel bridge deck paving, which can orient the distribution of some fibers, increase the uniformity of fiber distribution inside concrete, and improve the strength of concrete.
[0007] In order to solve the above technical problems, the present invention provides a steel-polypropylene composite fiber concrete construction device for steel bridge deck paving, comprising: a paving mechanism, one end of which is equipped with a feeding mechanism for vertically pouring steel-polypropylene composite fiber concrete, and the side wall of the paving mechanism is equipped with a driving lifting mechanism for driving a leveling mechanism and an adjusting mechanism to move up and down; the leveling mechanism for leveling and vibrating the concrete surface is located on one side of the adjusting mechanism, and the adjusting mechanism comprises a fixing rod, a supporting shaft and a fixing shaft, the fixing rod is fixed to the side wall of the driving lifting mechanism, the bottom end of the fixing rod is fixedly connected to the fixing shaft, and the side wall of the fixing shaft is rotated The support shaft is dynamically connected; a plurality of scrapers with arc-shaped side walls are symmetrically installed on the side walls of the support shaft, and a plurality of electromagnet teeth with trapezoidal cross-sections are installed at one end of the scraper; the side walls of the scraper are fixedly connected to a connecting rod, and the interior of the connecting rod is slidably connected to a metal rod, and a spring is installed inside the connecting rod, one end of the spring is connected to the metal rod, and the metal rod is slidably connected to the fixed shaft, the first metal sheet, and the second metal sheet; the side walls of the fixed shaft are symmetrically installed with a plurality of the first metal sheets and the second metal sheets, and the first metal sheet and the second metal sheet are electrically connected to the electromagnet teeth through the metal rod.
[0008] Preferably, the paving mechanism includes a traction head, a rear box is installed at one end of the traction head, a rotating shaft and a push plate are rotatably connected inside the bottom end of the rear box, and a plurality of push plates are installed at an inclined and equidistant manner on the side wall of the rotating shaft.
[0009] Preferably, a discharge port is installed at one end of the rear box, and the height of the push plate gradually decreases along the direction of the traction head toward the discharge port.
[0010] Preferably, the unloading mechanism includes a unloading plate, a first roller and a second roller, the top of the unloading plate with a funnel-shaped top is installed at the top of the discharge port, and the inside of the discharge port is rotatably connected to the first roller and the second roller; the side walls of the first roller and the second roller are both obliquely and equidistantly installed with multiple extrusion rings.
[0011] Preferably, the side walls of the first roller and the second roller are fixedly connected to gears, and the gears are meshed with each other; the two gears are identical and rotate in opposite directions.
[0012] Preferably, the driving lifting mechanism includes a motor, a hydraulic rod and a guide rail, the guide rail and the hydraulic rod are fixed to the side wall of the rear box, the side wall of the guide rail is slidably connected to the support frame, and the support frame is connected to the hydraulic rod; the support frame and the side wall of the traction head are both equipped with the motor, and the motor on the side wall of the traction head is connected to the rotating shaft; the support shaft, one of the gears and the side wall of the other motor are all equipped with belt shafts, and the belt shafts are connected by belts.
[0013] Preferably, the leveling mechanism includes an embossing roller and a vibrating ruler, the bottom end of the support frame is rotatably connected to the embossing roller, and a plurality of pressure rings are equidistantly installed on the side wall of the embossing roller; two support rods are fixedly connected between the vibrating ruler and the support frame, the side walls of the support rods are equipped with shock-absorbing springs, and the side walls of the vibrating ruler are installed with a vibration motor.
[0014] Preferably, the bottom end of the support shaft, the bottom end of the embossing roller, and the bottom surface of the vibrating ruler are located on the same straight line, and the side wall cross-section of the scraper located on the side wall of the support shaft is an arc-shaped structure.
[0015] A construction method for steel-polypropylene composite fiber concrete for steel bridge deck paving, specifically comprising the following steps: Step 1: According to the mass parts and proportions, 390 parts of cement, 153 parts of water, 715 parts of sand, 715 parts of crushed stone, 10 parts of steel fiber, 0.5 parts of polypropylene fiber, 90 parts of fly ash, and 9.5 parts of water reducer are mixed evenly to form steel-polypropylene composite fiber concrete, and the mixed steel-polypropylene composite fiber concrete is poured into the interior of the rear box; Step 2: operate the motor to drive the push plate to rotate and push the concrete inside the rear box into the inside of the discharge port; after the concrete enters the inside of the discharge port, it contacts the discharge mechanism, and the discharge mechanism changes the movement direction of the fiber and the concrete, so that the fiber and the concrete fall vertically downward, so that the fiber is vertically and disorderly distributed in the concrete layer, which is convenient for changing the position of the fiber later; Step 3: The driving lifting mechanism operates to make the leveling mechanism and the adjusting mechanism move downward to contact the concrete layer, and the adjusting mechanism moves inside the concrete layer to bring the steel fibers floating on the surface of the concrete layer downward and retain them in the upper layer of the concrete layer, thereby bringing the steel fibers at the bottom layer of the concrete layer into and retaining them in the middle layer of the concrete layer; at the same time, the direction of some steel fibers is adjusted to drive the steel fibers to move leftward and up and down, thereby changing the distribution of the steel fibers inside the concrete layer, so that the steel fibers are obliquely located inside the concrete layer; Step 4: The concrete with adjusted steel fibers contacts the leveling mechanism, and the leveling mechanism makes the steel fibers inside the concrete layer move downward and rotate downward, so that the steel fibers are tilted in the horizontal and vertical directions, and at the same time, the uniformity of the distribution of the steel fibers inside the concrete layer is increased, so that the steel fibers, polypropylene fibers and concrete can better withstand the horizontal thrust generated during the driving of the vehicle and the gravity of the vehicle itself, effectively preventing the concrete surface from cracking and increasing the service life of the concrete.
[0016] Compared with the related art, the steel-polypropylene composite fiber concrete construction device and method for steel bridge deck paving provided by the present invention have the following beneficial effects: The present invention provides a construction device and method for steel bridge deck paving steel-polypropylene composite fiber concrete. When the fiber and concrete fall vertically onto the surface of the steel bridge, the scraper drives the electromagnet hanging tooth to enter the concrete layer, and the metal rod corresponding to the electromagnet hanging tooth rotates to contact the first metal sheet on the side wall of the fixed shaft, and the spring inside the connecting rod is always in a compressed state, so that the spring squeezes the metal rod and the metal rod slides close to the side wall of the first metal sheet. The first metal sheet is externally connected to a power supply, so that the circuit passes through the first metal sheet and the metal rod into the electromagnet hanging tooth, so that the The electromagnetic hanging tooth generates a magnetic shape to generate suction for the steel fiber. When the electromagnet enters the interior of the concrete layer, it drives the steel fiber on the surface of the concrete layer to enter the interior of the concrete layer to prevent the steel fiber from remaining on the surface of the concrete layer. When the electromagnetic hanging tooth rotates 20°, the metal rod on one side of the electromagnetic hanging tooth is separated from the first metal sheet, and the electromagnetic hanging tooth loses its magnetism after the power supply is disconnected. The electromagnetic hanging tooth no longer attracts the steel fiber inside the concrete layer, thereby attracting the steel fiber downward and retaining it in the upper layer of the concrete layer. As the electromagnetic hanging tooth continues to rotate 20° to enter the lower layer of the concrete layer, the corresponding electromagnetic hanging tooth The metal rod rotates and contacts the second metal sheet on the side wall of the fixed shaft, and the electromagnet hanging tooth generates magnetism. As the electromagnet hanging tooth rotates, the steel fibers in the lower layer of the concrete layer are attracted upward. When the electromagnet hanging tooth rotates 60°, the metal rod on one side of the electromagnet hanging tooth is separated from the second metal sheet, thereby bringing the steel fibers in the bottom layer of the concrete layer into the middle layer of the concrete layer. As the electromagnet hanging tooth and the scraper rotate inside the concrete layer, the direction of some steel fibers inside the concrete layer is adjusted, driving the steel fibers to move leftward and up and down. At the same time, the scraper is tilted on the side wall of the support shaft. The scraper drives the steel fibers to move slightly backward, thereby changing the distribution of the steel fibers inside the concrete layer, so that the steel fibers are obliquely located inside the concrete layer; the steel fibers are contacted with the concrete vibrating mechanism after the angle is adjusted, and the vibrating mechanism vibrates the concrete, so that the steel fibers inside the concrete layer move downward and rotate downward at the same time, so that the steel fibers are tilted in the horizontal and vertical directions, and at the same time, the uniform distribution of the steel fibers inside the concrete layer is increased, so that the steel fibers, polypropylene fibers, and concrete can better withstand the horizontal thrust generated during the driving of the vehicle and the gravity of the vehicle itself, effectively preventing the cracking of the concrete surface and increasing the service life of the concrete. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] Figure 1A structural schematic diagram of a preferred embodiment of a construction device and method for steel bridge deck paving steel-polypropylene composite fiber concrete provided by the present invention; Figure 2 for Figure 1 The schematic diagram of the internal structure of the rear box shown; Figure 3 for Figure 1 An enlarged schematic diagram of the structure at A shown; Figure 4 for Figure 2 An enlarged schematic diagram of the structure at B shown; Figure 5 for Figure 4 An enlarged schematic diagram of the structure at position C is shown; Figure 6 for Figure 5 An enlarged schematic diagram of the structure at D shown; Figure 7 for Figure 5 The schematic diagram of the internal structure of the support shaft shown; Figure 8 for Figure 4 A top view of the first roller and the second roller structure shown; Fig. 9 for Figure 1 The rear box structure is shown in right view; Fig.10 for Figure 3 Schematic diagram of the scraper structure shown.
[0018] Numbers in the figure: 1, paving mechanism, 11, traction head, 12, rear box, 13, rotating shaft, 14, push plate, 15, discharge port, 2, steel bridge, 21, concrete layer, 22, steel fiber, 3, driving lifting mechanism, 31, motor, 32, hydraulic rod, 33, guide rail, 34, support frame, 35, belt, 36, belt shaft, 4, leveling mechanism, 41, embossing roller, 42, pressure ring, 43, vibrating ruler, 44, Vibration motor, 45, support rod, 46, shock-absorbing spring, 5, adjustment mechanism, 51, fixed rod, 52, support shaft, 53, scraper, 54, electromagnet hanging tooth, 55, fixed shaft, 56, first metal sheet, 57, second metal sheet, 58, metal rod, 59, connecting rod, 510, spring, 6, unloading mechanism, 61, unloading plate, 62, first roller, 63, second roller, 64, extrusion ring, 65, gear. DETAILED DESCRIPTION
[0019] The present invention will be further described below in conjunction with the accompanying drawings and implementation modes.
[0020] See also Figures 1 to 10 , Figure 1A structural schematic diagram of a preferred embodiment of a construction device and method for steel bridge deck paving steel-polypropylene composite fiber concrete provided by the present invention; Figure 2 for Figure 1 The schematic diagram of the internal structure of the rear box shown; Figure 3 for Figure 1 An enlarged schematic diagram of the structure at A shown; Figure 4 for Figure 2 An enlarged schematic diagram of the structure at B shown; Figure 5 for Figure 4 An enlarged schematic diagram of the structure at position C is shown; Figure 6 for Figure 5 An enlarged schematic diagram of the structure at D shown; Figure 7 for Figure 5 The schematic diagram of the internal structure of the support shaft shown; Figure 8 for Figure 4 A top view of the first roller and the second roller structure shown; Fig. 9 for Figure 1 The rear box structure is shown in right view; Fig.10 for Figure 3 The scraper structure schematic diagram is shown. The construction device for steel bridge deck paving steel-polypropylene composite fiber concrete includes: a paving mechanism 1, the paving mechanism 1 includes a traction head 11, one end of the traction head 11 is installed with a rear box 12, the bottom end of the rear box 12 is internally rotatably connected with a rotating shaft 13 and a push plate 14, and the side wall of the rotating shaft 13 is inclined and equidistantly installed with a plurality of the push plates 14. A discharge port 15 is installed at one end of the rear box 12; when paving the surface of the steel bridge 2, first pour the evenly cast steel-polypropylene composite fiber concrete into the interior of the rear box 12, and at this time the motor 31 drives the rotating shaft 13 and the push plate 14 to rotate, and the push plate 14 pushes the concrete inside the rear box 12 into the interior of the discharge port 15, and the height of the push plate 14 gradually decreases along the direction of the traction head 11 toward the discharge port 15, in order to facilitate the contact area between the push plate 14 and the concrete to gradually increase along the direction of the discharge port 15 toward the traction head 11, so as to facilitate pushing the concrete into the discharge port 15.
[0021] One end of the paving mechanism 1 is equipped with a feeding mechanism 6 for vertically pouring steel-polypropylene composite fiber concrete. The feeding mechanism 6 includes a feeding plate 61, a first roller 62, and a second roller 63. The top of the discharge port 15 is equipped with the feeding plate 61 with a funnel-shaped top. The inside of the discharge port 15 is rotatably connected to the first roller 62 and the second roller 63; the side walls of the first roller 62 and the second roller 63 are both obliquely and equidistantly equipped with multiple extrusion rings 64. When the concrete enters the inside of the discharge port 15 and contacts the feeding plate 61, the concrete moves downward along the feeding plate 61 and contacts the first roller 62 and the second roller 63. The side walls of the first roller 62 and the second roller 63 are fixedly connected with gears 65, and the gears 65 are meshed with each other; the two gears 65 are identical and have opposite directions. The first roller 62 and the second roller 63 have the same rotation speed and opposite directions, so that the first roller 62 and the second roller 63 rotate downward to push the concrete to run, change the direction of concrete movement, and make the concrete fall vertically downward to the surface of the bridge deck 2; the first roller 6 2 and the second roller 63 rotate, the inclined extrusion ring 64 is driven to rotate, and the rotation of the extrusion ring 64 pushes the concrete to be evenly distributed on the surfaces of the first roller 62 and the second roller 63, and the movement direction of the concrete pushed by the extrusion ring 64 on the surface of the first roller 62 is opposite to the movement direction of the concrete pushed by the extrusion ring 64 on the surface of the second roller 63. When the concrete falls downward from between the adjacent extrusion rings 64, the concrete at the edge is pushed by the extrusion ring 64 to move toward the center, thereby squeezing the fibers inside the concrete, causing the fibers to fall vertically downward, and causing the fibers to be randomly distributed in the concrete layer 21.
[0022] The side wall of the paving mechanism 1 is installed with a driving lifting mechanism 3 that drives the leveling mechanism 4 and the adjusting mechanism 5 to move up and down; the driving lifting mechanism 3 includes a motor 31, a hydraulic rod 32 and a guide rail 33, the guide rail 33 and the hydraulic rod 32 are fixed to the side wall of the rear box 12, the side wall of the guide rail 33 is slidably connected to the support frame 34, and the support frame 34 is connected to the hydraulic rod 32; the support frame 34 and the side wall of the traction head 11 are both installed with the motor 31, and the motor 31 on the side wall of the traction head 11 is connected to the rotating shaft 13; the support shaft 52, one of the gears 65 and the side wall of the other motor 31 are all installed with a belt shaft 36, and the belt shafts 36 are connected by a belt 35 is connected; when it is necessary to change the height of the adjusting mechanism 5 and the leveling mechanism 4, the hydraulic rod 32 is opened, and the hydraulic rod 32 drives the support frame 35 to move downward along the side wall of the guide rail 33, so that the support shaft 52, the embossing roller 41 and the vibrating ruler 43 are in contact with the surface of the concrete layer 21, thereby facilitating the processing of the concrete; and the motor 31 on the side wall of the support frame 34 is opened, and the motor 31 drives the belt shaft 36, the belt 35, the support shaft 52, the gear 65, the first roller 62 and the second roller 63 to rotate, the support shaft 52 and the first roller 62 rotate clockwise, and the second roller 63 rotates counterclockwise.
[0023] The leveling mechanism 4 for leveling and vibrating the concrete surface is located on one side of the adjusting mechanism 5, and the adjusting mechanism 5 includes a fixing rod 51, a supporting shaft 52 and a fixing shaft 55. The fixing rod 51 is fixed to the side wall of the driving lifting mechanism 3, and the bottom end of the fixing rod 51 is fixedly connected to the fixing shaft 55, and the side wall of the fixing shaft 55 is rotatably connected to the supporting shaft 52; a plurality of scrapers 53 with arc-shaped side walls are obliquely and symmetrically installed on the side wall of the supporting shaft 52, and a plurality of electromagnet hanging teeth 54 with trapezoidal cross-sections are installed at one end of the scraper 53; the side wall of the scraper 53 is fixedly connected to the connecting rod 59, and the inside of the connecting rod 59 is slidably connected to the metal rod 58, A spring 510 is installed inside the connecting rod 59, and one end of the spring 510 is connected to the metal rod 58. The metal rod 58 is slidably connected to the fixed shaft 55, the first metal sheet 56, and the second metal sheet 57; the side walls of the fixed shaft 55 are symmetrically installed with multiple first metal sheets 56 and second metal sheets 57, and the first metal sheets 56 and the second metal sheets 57 are electrically connected to the electromagnet hanging teeth 54 through the metal rod 58. When the concrete falls onto the surface of the steel bridge 2, the belt 35 drives the belt shaft 36 and the support shaft 52 to rotate clockwise, and the support shaft 52 rotates on the side wall of the fixed shaft 55. The support shaft 52 drives the scraper 53, the electromagnet hanging tooth 53, the connecting rod 59 and the metal rod 58 to rotate. When the scraper 53 drives the electromagnet hanging tooth 53 to enter the concrete layer 21, the metal rod 58 corresponding to the electromagnet hanging tooth 53 rotates and contacts the first metal sheet 56 on the side wall of the fixed shaft 55. The spring 510 inside the connecting rod 59 is always in a compressed state, so that the spring 510 squeezes the metal rod 58, so that the metal rod 58 slides close to the side wall of the first metal sheet 56. The first metal sheet 56 is externally connected to a power source, so that the circuit passes through the first metal sheet 56, the The metal rod 58 enters the electromagnet hanging tooth 54, so that the electromagnet hanging tooth 54 generates a magnetic shape to generate suction force on the steel fiber. When the electromagnet enters the interior of the concrete layer 21, it drives the steel fiber on the surface of the concrete layer 21 to enter the interior of the concrete layer 21, so as to prevent the steel fiber from remaining on the surface of the concrete layer 21. When the electromagnet hanging tooth 54 rotates 20°, the metal rod 58 on one side of the electromagnet hanging tooth 54 is separated from the first metal sheet 56, and the electromagnet hanging tooth 54 loses its magnetism after the power is disconnected. The electromagnet hanging tooth 54 no longer attracts the steel fiber inside the concrete layer 21, so as to attract the steel fiber downward and retain it in the upper layer of the concrete layer 21.As the electromagnetic tooth 54 continues to rotate 20° and enters the lower layer of the concrete layer 21, the metal rod 58 corresponding to the electromagnetic tooth 53 rotates and contacts the second metal sheet 57 on the side wall of the fixed shaft 55, and the electromagnetic tooth 53 generates magnetism. As the electromagnetic tooth 54 rotates, the steel fibers in the lower layer of the concrete layer 21 are attracted upward. When the electromagnetic tooth 54 rotates 60°, the metal rod 58 on one side of the electromagnetic tooth 54 is separated from the second metal sheet 57, thereby the concrete layer 21 is moved upward. The steel fibers at the bottom layer 21 are brought into the middle layer of the concrete layer 21; and as the electromagnet hanging teeth 54 and the scraper 53 rotate inside the concrete layer 21, the direction of some of the steel fibers inside the concrete layer 21 is adjusted, driving the steel fibers to move leftward and up and down. At the same time, the scraper 53 is inclined at the side wall of the support shaft 52, and the scraper 53 drives the steel fibers to move slightly backward, thereby changing the distribution of the steel fibers inside the concrete layer 21, so that the steel fibers 22 are obliquely located inside the concrete layer 21 (as shown in the attached; Figure 4 As shown), it is convenient for the steel fiber 22 to withstand the horizontal thrust generated during the vehicle's travel and the gravity of the vehicle itself, thereby improving the overall strength of the concrete layer 21.
[0024] The leveling mechanism 4 includes an embossing roller 41 and a vibrating ruler 43. The bottom end of the support frame 34 is rotatably connected to the embossing roller 41, and a plurality of pressure rings 42 are equidistantly installed on the side wall of the embossing roller 41; two support rods 45 are fixedly connected between the vibrating ruler 43 and the support frame 34, and the side walls of the support rods 45 are provided with shock-absorbing springs 46, and a vibration motor 44 is installed on the side wall of the vibrating ruler 43. After the angle of the steel fiber 22 is adjusted, the concrete contacts the rotating embossing roller 41 and the pressure ring 42, and the embossing roller 41 and the pressure ring 42 press the steel fibers remaining on the surface of the concrete into the interior of the concrete layer 21; at the same time, the operation of the vibration motor 44 drives the vibrating ruler 43 to vibrate on the surface of the concrete layer 21, vibrates the concrete, and makes the steel fibers 22 inside the concrete layer 21 move downward while rotating downward, so that the steel fibers are tilted in the horizontal and vertical directions (as shown in the attached figure). Figure 4 As shown in the figure, the steel fiber, polypropylene fiber and concrete can better withstand the horizontal thrust generated during the driving of the vehicle and the gravity of the vehicle itself, effectively prevent the concrete surface from cracking and increase the service life of the concrete.
[0025] The bottom end of the support shaft 52, the bottom end of the embossing roller 41, and the bottom surface of the vibrating ruler 43 are located on the same straight line. In order to facilitate the support shaft 52, the embossing roller 41 and the vibrating ruler 43 to move downward and contact the surface of the concrete layer 21; the side wall section of the scraper 53 located on the side wall of the support shaft 52 is an arc-shaped structure (as shown in the attached figure). Fig.10As shown in the figure, when the scraper 53 rotates inside the concrete, the concrete slides over the side wall of the scraper 53, thereby preventing a large amount of concrete from remaining on the surface of the scraper 53.
[0026] A construction method for steel-polypropylene composite fiber concrete for steel bridge deck paving, specifically comprising the following steps: Step 1: According to the mass parts and proportions, 390 parts of cement, 153 parts of water, 715 parts of sand, 715 parts of crushed stone, 10 parts of steel fiber, 0.5 parts of polypropylene fiber, 90 parts of fly ash, and 9.5 parts of water reducer are mixed evenly to form steel-polypropylene composite fiber concrete, and the mixed steel-polypropylene composite fiber concrete is poured into the interior of the rear box 12; Step 2: Connect the motor 31 and the hydraulic rod 32 to an external power source to make them operate, driving the rotating shaft 13 and the push plate 14, the belt shaft 36, the belt 35, the support shaft 52, the gear 65, the first roller 62 and the second roller 63 to rotate; the traction head 11 drives the rear box 11 to move on the surface of the steel bridge 2; the rotating shaft 13 and the push plate 14 rotate to contact with the concrete, and the push plate 14 pushes the concrete inside the rear box 12 into the inside of the discharge port 15; after the concrete enters the inside of the discharge port 15, it contacts the discharge plate 61, and the concrete moves downward along the discharge plate 61 and contacts the first roller 62 and the second roller 63, and the first roller 62 and the second roller 63 rotate in opposite directions to push the concrete downward The soil moves, changing the movement direction of the concrete, so that the concrete falls vertically downward to the surface of the bridge deck 2; during the rotation of the first roller 62 and the second roller 63, the inclined extrusion ring 64 is driven to rotate, and the rotation of the extrusion ring 64 pushes the concrete to be evenly distributed on the surfaces of the first roller 62 and the second roller 63, and the movement direction of the concrete pushed by the extrusion ring 64 on the surface of the first roller 62 is opposite to the movement direction of the concrete pushed by the extrusion ring 64 on the surface of the second roller 63. When the concrete falls downward from between the adjacent extrusion rings 64, the concrete at the edge is pushed by the extrusion ring 64 to move toward the center, thereby squeezing the fibers inside the concrete, causing the fibers to fall vertically downward, and causing the fibers to be randomly distributed in the concrete layer 21, which is convenient for changing the fiber position later.
[0027] Step 3: The hydraulic rod 32 drives the support frame 35 to move downward along the side wall of the guide rail 33, so that the support shaft 52, the embossing roller 41 and the vibrating ruler 43 are in contact with the surface of the concrete layer 21; the support shaft 52 rotates clockwise to drive the scraper 53, the electromagnet hanging tooth 53, the connecting rod 59 and the metal rod 58 to rotate. When the scraper 53 drives the electromagnet hanging tooth 53 to enter the concrete layer 21, the metal rod 58 corresponding to the electromagnet hanging tooth 53 rotates and contacts the first metal sheet 56 on the side wall of the fixed shaft 55, and the spring 510 inside the connecting rod 59 is always in The first metal sheet 56 is in a compressed state, so that the spring 510 squeezes the metal rod 58, so that the metal rod 58 slides close to the side wall of the first metal sheet 56. The first metal sheet 56 is externally connected to a power source, so that the circuit passes through the first metal sheet 56 and the metal rod 58 into the electromagnet hanging tooth 54, so that the electromagnet hanging tooth 54 generates a magnetic shape to generate suction to the steel fiber. When the electromagnet enters the interior of the concrete layer 21, it drives the steel fiber on the surface of the concrete layer 21 to enter the interior of the concrete layer 21, avoiding that the steel fiber remains on the surface of the concrete layer 21. When the electromagnet hanging tooth 54 rotates 20°, the magnet on one side of the electromagnet hanging tooth 54 The metal rod 58 is separated from the first metal sheet 56, and the electromagnet hanging tooth 54 loses its magnetism when the power is disconnected. The electromagnet hanging tooth 54 no longer attracts the steel fibers inside the concrete layer 21, thereby attracting the steel fibers downward and retaining them in the upper layer of the concrete layer 21; as the electromagnet hanging tooth 54 continues to rotate 20° to enter the lower layer of the concrete layer 21, the metal rod 58 corresponding to the electromagnet hanging tooth 53 rotates and contacts the second metal sheet 57 on the side wall of the fixed shaft 55, and the electromagnet hanging tooth 53 generates magnetism. As the electromagnet hanging tooth 54 rotates, the steel fibers in the lower layer of the concrete layer 21 are attracted upward. When the electromagnet hanging tooth 54 rotates After moving 60°, the metal rod 58 on one side of the electromagnet hanging tooth 54 is separated from the second metal sheet 57, thereby bringing the steel fibers in the bottom layer of the concrete layer 21 into the middle layer of the concrete layer 21; and as the electromagnet hanging tooth 54 and the scraper 53 rotate inside the concrete layer 21, the direction of some steel fibers inside the concrete layer 21 is adjusted, driving the steel fibers to move leftward and up and down, and at the same time, the scraper 53 is inclined on the side wall of the support shaft 52, and the scraper 53 drives the steel fibers to move slightly backward, thereby changing the distribution of the steel fibers inside the concrete layer 21, so that the steel fibers 22 are obliquely located inside the concrete layer 21; Step 4: After adjusting the angle of the steel fiber 22, the concrete contacts the rotating embossing roller 41 and the pressing ring 42, and the embossing roller 41 and the pressing ring 42 press the steel fibers remaining on the surface of the concrete into the interior of the concrete layer 21; at the same time, the vibration motor 44 drives the vibrating ruler 43 to vibrate on the surface of the concrete layer 21, vibrating the concrete, so that the steel fibers 22 inside the concrete layer 21 move downward and rotate downward, so that the steel fibers are tilted in the horizontal and vertical directions, so that the steel fibers, polypropylene fibers, and concrete can better withstand the horizontal thrust generated during the driving of the vehicle and the gravity of the vehicle itself, effectively preventing the concrete surface from cracking and improving the service life of the concrete.
[0028] The above descriptions are merely embodiments of the present invention and are not intended to limit the patent scope of the present invention. Any equivalent structure or equivalent process transformation made using the contents of the present invention specification and drawings, or directly or indirectly applied in other related technical fields, are also included in the patent protection scope of the present invention.
Claims
1. A construction device for steel bridge deck paving with steel-polypropylene composite fiber concrete, characterized in that: include: A paving mechanism (1), wherein a feeding mechanism (6) for vertically pouring steel-polypropylene composite fiber concrete is installed at one end of the paving mechanism (1), and a driving lifting mechanism (3) for driving a leveling mechanism (4) and an adjusting mechanism (5) to move up and down is installed on a side wall of the paving mechanism (1); The leveling mechanism (4) for leveling and vibrating the concrete surface is located on one side of the adjusting mechanism (5). The adjusting mechanism (5) comprises a fixing rod (51), a supporting shaft (52) and a fixing shaft (55). The fixing rod (51) is fixed to the side wall of the driving lifting mechanism (3). The bottom end of the fixing rod (51) is fixedly connected to the fixing shaft (55). The side wall of the fixing shaft (55) is rotatably connected to the supporting shaft (52). A plurality of scrapers (53) with arc-shaped side walls are obliquely and symmetrically mounted on the side wall of the supporting shaft (52). A plurality of electromagnet hanging teeth (54) with trapezoidal cross sections are mounted on one end of the scrapers (53). The side wall of the scrapers (53) is provided with a plurality of electromagnet hanging teeth (54) with trapezoidal cross sections. The wall is fixedly connected to a connecting rod (59), the interior of the connecting rod (59) is slidably connected to a metal rod (58), a spring (510) is installed inside the connecting rod (59), one end of the spring (510) is connected to the metal rod (58), and the metal rod (58) is slidably connected to the fixed shaft (55), the first metal sheet (56), and the second metal sheet (57); a plurality of the first metal sheets (56) and the second metal sheets (57) are symmetrically installed on the side walls of the fixed shaft (55), and the first metal sheets (56) and the second metal sheets (57) are electrically connected to the electromagnet hanging teeth (54) through the metal rod (58).
2. The steel-polypropylene composite fiber concrete construction device for steel bridge deck paving according to claim 1 is characterized in that: The paving mechanism (1) comprises a traction head (11), one end of which is mounted a rear box (12), the bottom end of the rear box (12) is internally rotatably connected to a rotating shaft (13) and a push plate (14), and a plurality of push plates (14) are equidistantly mounted on the side wall of the rotating shaft (13).
3. The steel-polypropylene composite fiber concrete construction device for steel bridge deck paving according to claim 2 is characterized in that: A discharge port (15) is installed at one end of the rear box (12), and the height of the push plate (14) gradually decreases along the direction of the traction machine head (11) toward the discharge port (15).
4. The steel-polypropylene composite fiber concrete construction device for steel bridge deck paving according to claim 3 is characterized in that: The unloading mechanism (6) comprises an unloading plate (61), a first roller (62) and a second roller (63); the unloading plate (61) having a funnel-shaped top is installed at the top of the discharge port (15); the inside of the discharge port (15) is rotatably connected to the first roller (62) and the second roller (63); and the side walls of the first roller (62) and the second roller (63) are both obliquely and equidistantly installed with a plurality of extrusion rings (64).
5. The steel-polypropylene composite fiber concrete construction device for steel bridge deck paving according to claim 4 is characterized in that: The side walls of the first roller (62) and the second roller (63) are both fixedly connected to gears (65), and the gears (65) are meshed with each other; the two gears (65) are identical and rotate in opposite directions.
6. The steel-polypropylene composite fiber concrete construction device for steel bridge deck paving according to claim 5 is characterized in that: The driving lifting mechanism (3) comprises a motor (31), a hydraulic rod (32) and a guide rail (33); the guide rail (33) and the hydraulic rod (32) are fixed to the side wall of the rear box (12); the side wall of the guide rail (33) is slidably connected to a support frame (34); the support frame (34) is connected to the hydraulic rod (32); the motor (31) is installed on the support frame (34) and the side wall of the traction head (11); the motor (31) on the side wall of the traction head (11) is connected to the rotating shaft (13); the support shaft (52), one of the gears (65) and the side wall of the other motor (31) are all installed with a belt shaft (36); the belt shafts (36) are connected to each other via a belt (35).
7. The steel-polypropylene composite fiber concrete construction device for steel bridge deck paving according to claim 6 is characterized in that: The leveling mechanism (4) comprises an embossing roller (41) and a vibrating ruler (43); the bottom end of the support frame (34) is rotatably connected to the embossing roller (41); a plurality of pressure rings (42) are equidistantly mounted on the side wall of the embossing roller (41); two support rods (45) are fixedly connected between the vibrating ruler (43) and the support frame (34); a shock-absorbing spring (46) is mounted on the side wall of the support rod (45); and a vibration motor (44) is mounted on the side wall of the vibrating ruler (43).
8. The steel-polypropylene composite fiber concrete construction device for steel bridge deck paving according to claim 7 is characterized in that: The bottom end of the support shaft (52), the bottom end of the embossing roller (41), and the bottom surface of the vibrating ruler (43) are located on the same straight line, and the side wall cross-section of the scraper (53) located on the side wall of the support shaft (52) is an arc-shaped structure.
9. The steel-polypropylene composite fiber concrete construction device for steel bridge deck paving according to claim 8, characterized in that: A construction method for steel-polypropylene composite fiber concrete for steel bridge deck paving includes the following steps: Step 1: According to the mass parts and proportions, 390 parts of cement, 153 parts of water, 715 parts of sand, 715 parts of crushed stone, 10 parts of steel fiber, 0.5 parts of polypropylene fiber, 90 parts of fly ash, and 9.5 parts of water reducing agent are mixed evenly to form steel-polypropylene composite fiber concrete, and the mixed steel-polypropylene composite fiber concrete is poured into the interior of the rear box (12); Step 2: operate the motor (31) to drive the push plate (14) to rotate and push the concrete inside the rear box (12) into the inside of the discharge port (15); after the concrete enters the inside of the discharge port (15), it contacts the discharge mechanism (6), and the discharge mechanism (6) changes the movement direction of the fiber and the concrete, so that the fiber and the concrete fall vertically downward, so that the fiber is vertically and disorderly distributed in the concrete layer (21), which is convenient for changing the position of the fiber later; Step 3: The driving and lifting mechanism (3) operates to cause the leveling mechanism (4) and the adjusting mechanism (5) to move downward and contact the concrete layer (21); the adjusting mechanism (5) moves inside the concrete layer (21), bringing the steel fibers floating on the surface of the concrete layer (21) downward and retaining them in the upper layer of the concrete layer (21), thereby bringing the steel fibers at the bottom layer of the concrete layer (21) into and retaining them in the middle layer of the concrete layer (21); at the same time, the direction of some of the steel fibers is adjusted to drive the steel fibers to move leftward and up and down, thereby changing the distribution of the steel fibers inside the concrete layer (21), so that the steel fibers (22) are obliquely located inside the concrete layer (21); Step 4: The concrete with the adjusted steel fibers (22) contacts the leveling mechanism (4), and the leveling mechanism (4) causes the steel fibers (22) inside the concrete layer (21) to move downward while rotating downward, so that the steel fibers are tilted in the horizontal and vertical directions, and at the same time, the uniformity of the distribution of the steel fibers inside the concrete layer (21) is increased, so that the steel fibers, polypropylene fibers, and concrete can better withstand the horizontal thrust generated during the driving of the vehicle and the gravity of the vehicle itself, effectively preventing the concrete surface from cracking and increasing the service life of the concrete.