Fabricated anti-seismic underground comprehensive pipe gallery

Through prefabricated seismic design, the combination of prefabricated and cast-in-place concrete is used to dislocate the steel bars and shock absorbers, forming multiple lines of defense to resist transverse loads, solving the problem of insufficient seismic resistance of the existing underground comprehensive pipeline corridor and improving the seismic resistance of the structure Performance and stability ensure safety and service life under strong earthquake conditions.

CN118979519APending Publication Date: 2024-11-19XIONGAN LVYAN INSPECTION & CERTIFICATION CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411399935.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-09
Publication Date
2024-11-19

AI Technical Summary

Technical Problem

The existing underground comprehensive pipeline corridors have shortcomings in earthquake resistance, which are difficult to effectively resist damage caused by strong earthquakes, and lack of buffering and shock absorption protection measures, which affects the use cycle and the safety of residents' lives.

Method used

The prefabricated seismic underground comprehensive pipeline design is adopted, and the steel bars and cast-in-place concrete are arranged in a misaligned manner through prefabricated gallery body, bottom and top prefabricated plates, curved plates, support columns, rectangular plates, spiral shock absorbers and rubber elastic plates. Combining the spiral shock absorber and rubber elastic plate, multiple lines of defense are formed to resist lateral loads, enhancing overall stability and seismic resistance.

Benefits of technology

The earthquake resistance of the underground comprehensive pipeline corridor is improved, the resistance to lateral loads is enhanced, the service life is extended, and the structural stability and safety under strong earthquake conditions are ensured.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118979519A_ABST
    Figure CN118979519A_ABST
Patent Text Reader

Abstract

The invention discloses a fabricated anti-seismic underground comprehensive pipe gallery, and belongs to the technical field of fabricated buildings. A plurality of prefabricated gallery bodies are longitudinally connected to form a pipe gallery main body, bottom prefabricated slabs and top prefabricated slabs are arranged at the joints of the gallery bodies, and grouting holes are formed in the top prefabricated slabs; extending horizontal longitudinal bars and vertical longitudinal bars are pre-buried in the corridor bodies, and the corresponding horizontal longitudinal bars and vertical longitudinal bars in every two adjacent corridor bodies are arranged in a staggered mode and fixedly connected through steel bar binding wires; a plurality of supporting plates are fixed to the connecting faces of the corridor bodies, a rectangular plate is fixed to each supporting plate, the rectangular plates on the adjacent corridor bodies are connected through spiral shock absorbers, rubber elastic plates are arranged on the two sides of each spiral shock absorber, and arc-shaped plates are arranged above the corridor bodies through supporting columns. And cast-in-place concrete is carried out through the grouting holes in the top prefabricated slab, and installation is completed. The underground comprehensive pipe gallery is combined with a fabricated building and an anti-seismic design, so that the mounting convenience can be realized, the anti-seismic property of the underground comprehensive pipe gallery can be guaranteed, and the service life is prolonged.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to an underground integrated pipe gallery, in particular to an assembled earthquake-resistant underground integrated pipe gallery, and belongs to the technical field of assembled buildings. Background Art

[0002] The underground utility corridor is a tunnel space built underground in the city, integrating various engineering pipelines such as electricity, communications, gas, heating, water supply and drainage, etc. It is equipped with special inspection ports, lifting ports and monitoring systems, and is uniformly planned, designed, constructed and managed. It is an important infrastructure and guarantee for the operation of the city. The top plate, bottom plate and lateral wall panels on the top of the underground utility corridor directly bear dynamic loads and static loads. The wall panels on both sides must not only bear the dynamic loads and static loads of the top plate, but also the lateral loads of the side soil layer. Therefore, in order to enhance the strength, rigidity and stability of the underground utility corridor, cast-in-place concrete not only requires high strength, but also requires a large amount of concrete. Prefabricated buildings refer to the transfer of on-site concrete pouring work to the factory, where components and accessories such as floor slabs, wall panels, and stairs are prefabricated and processed in advance, and then transported to the construction site, and assembled and installed on site through reliable connection methods.

[0003] At the same time, underground utility corridors should set higher seismic fortification standards. Seismic resistance refers to the ability of a building to resist damage caused by a certain degree of earthquake through a certain structure. Earthquake transverse waves (also known as shear waves) propagate slowly, at 3 to 4 kilometers per second, and can cause horizontal shaking of the ground. The vibration direction of the transverse wave is perpendicular to the direction of the wave's advance, while the vibration direction of the longitudinal wave is consistent with the propagation direction. The amplitude of the transverse wave is larger than that of the longitudinal wave, and the destructive power is greater. The horizontal shaking force of the transverse wave is the main cause of building damage. General ordinary underground utility corridors can only withstand various ground load impacts for a short period of time, and it is difficult to achieve long-term seismic resistance. The structural stiffness, strength and stability of ordinary utility corridors are obviously not able to resist strong earthquakes when designed. Once a strong earthquake occurs, the consequences of their own strength problems will not only affect the operation of the entire public transportation and municipal administration, but also threaten the safety of residents' lives.

[0004] In order to reduce the damage caused by earthquakes, especially seismic shear waves to buildings, it is necessary to carry out seismic reinforcement of underground integrated pipeline corridors. On the basis of using prefabricated components to ensure costs, the strength and rigidity should be maximized to minimize losses. Summary of the invention

[0005] The present invention aims to provide an assembled underground utility corridor, which is prefabricated in a factory, prepared in advance, transported to the site for assembly, and poured with a small amount of concrete at the joints. At the same time, ordinary underground utility corridors do not have buffering and shock-absorbing protection measures. When subjected to repeated lateral shear forces, the corridor and the wire pipes inside the corridor are easily damaged, thereby affecting the service life of the underground utility corridor. The present invention aims to improve the comprehensive seismic resistance of the corridor, with an emphasis on resisting lateral loads, and a secondary emphasis on longitudinal loads.

[0006] Based on the above requirements, the basic ideas of the present invention are as follows:

[0007] 1) An assembled underground integrated pipe gallery should integrate various engineering pipelines such as communication, gas, heating, water supply and drainage like ordinary underground integrated pipe gallery, and also have the characteristics of quick prefabrication, convenient installation and high stability. The assembled underground integrated pipe gallery can be prefabricated at any time and directly transported to the site for installation when needed.

[0008] 2) When an earthquake occurs, the amplitude of transverse waves is larger than that of longitudinal waves, and the destructive power is greater. The horizontal shaking force of transverse waves is the main cause of building damage. Therefore, when designing prefabricated and assembled underground comprehensive pipeline corridors, the focus is on considering the resistance of horizontal loads, namely shear forces, and also the resistance of vertical loads is also considered secondarily.

[0009] In order to achieve the above technical objectives, the present invention adopts the following technical solutions:

[0010] An assembled seismic-resistant underground integrated pipe gallery comprises a prefabricated gallery body, a bottom prefabricated plate, a top prefabricated plate, an arc plate, a support column, a support plate, a rectangular plate, a rubber elastic plate, a spiral shock absorber and a steel bar binding wire, wherein a plurality of gallery bodies are longitudinally connected to form a pipe gallery body, the bottom prefabricated plate and the top prefabricated plate are located at the gallery body connection, and a grouting hole for pouring concrete on site is provided on the top prefabricated plate; extended horizontal longitudinal bars and vertical longitudinal bars are pre-embedded in the gallery body, and the corresponding horizontal longitudinal bars and vertical longitudinal bars in two adjacent gallery bodies are staggeredly arranged, and the steel bars are connected to the gallery body by the steel bars. The connection is fixed by binding wire; a plurality of support plates are evenly distributed and fixed on the connection surface of the corridor, and a rectangular plate is fixedly connected to each support plate; the two ends of the spiral shock absorber are respectively fixedly connected to the rectangular plates on the two connected corridors, and the two sides of each spiral shock absorber are rubber elastic plates, and the two ends of the rubber elastic plates are fixedly connected to the rectangular plates; the support columns are prefabricated on the top surface of the corridor, and the arc plates are completely arranged above the corridor along the longitudinal direction of the corridor through the support columns; the installation of the underground comprehensive pipe corridor is completed by pouring concrete on site through the grouting holes on the top prefabricated plate.

[0011] Furthermore, horizontal rectangular partition plates and / or vertical rectangular partition plates are arranged inside the gallery to divide the space for use by different engineering pipelines.

[0012] Preferably, bolts are embedded in the corresponding positions of the support plate of the corridor, and the support plate is fixed by the bolts; the rectangular plate is fixed to the support plate by welding; holes are reserved on the rectangular plate, and the spiral shock absorber is welded and fixed to the rectangular plate through the holes; both ends of the rubber elastic plate are bonded to the rectangular plate by high-strength glue, and preferably, both ends of the elastic rubber plate are further fixedly connected to the rectangular plate by bolts.

[0013] Typically, the corridor, bottom prefabricated plate, top prefabricated plate, curved plate and supporting columns are prefabricated reinforced concrete structures; the supporting plates and rectangular plates are anti-corrosion treated steel plates.

[0014] Preferably, the top prefabricated plate is prefabricated at the front end of the corridor, and the bottom prefabricated plate is prefabricated at the rear end of the corridor, or vice versa, that is, the bottom prefabricated plate is prefabricated at the front end of the corridor, and the top prefabricated plate is prefabricated at the rear end of the corridor; during assembly, the top prefabricated plate and the bottom prefabricated plate are used to support the adjacent corridor.

[0015] The present invention also provides an on-site installation method of the above-mentioned assembled earthquake-resistant underground integrated pipe gallery, comprising:

[0016] 1) Place the gallery longitudinally, with the top prefabricated panels and the bottom prefabricated panels between the gallery bodies, and completely arrange the curved panels on the top of the gallery bodies along the longitudinal direction of the gallery bodies through supporting columns;

[0017] 2) Connect the staggered horizontal and vertical longitudinal bars through steel bar binding wires;

[0018] 3) Fix the support plate to the connecting surface of the gallery, and then fix the rectangular plate to the support plate;

[0019] 4) The opposite rectangular plates on the two corridors are connected by spiral shock absorbers, and the rubber elastic plates are fixed on the rectangular plates;

[0020] 5) The installation of the pipe gallery is completed by pouring on-site through the grouting holes on the top precast plate.

[0021] The present invention combines the underground utility corridor with prefabricated buildings and earthquake-resistant design, which can not only realize the convenience of installation of the underground utility corridor, but also ensure the earthquake resistance of the underground utility corridor and improve its service life. The main innovations include:

[0022] 1) By setting the top precast plate and the bottom precast plate, the connection between the corridors is strengthened, and it can also serve as a template during construction to save materials. When pouring concrete in place, only the side formwork needs to be supported, and then the concrete can be poured from the grouting holes of the top precast plate. The connection between the corridors is further strengthened by setting staggered steel bars, support plates, rectangular plates, spiral shock absorbers and rubber elastic plates.

[0023] 2) During on-site construction, workers only need to work from the middle of the corridor to both sides when using binding wire to tie steel bars, install spiral shock absorbers, install rectangular plates, and install support plates, which makes installation convenient.

[0024] 3) By setting staggered horizontal longitudinal bars, vertical longitudinal bars and cast-in-place concrete, it becomes the first line of defense against earthquakes; by setting rubber elastic plates, it becomes the second line of defense against earthquakes; by setting spiral shock absorbers, it becomes the third line of defense against earthquakes. And the above three lines of defense do not work alone when subjected to horizontal loads, but resist the loads synchronously. And by setting up curved plates, the static and dynamic loads from the ground can be dispersed in non-earthquake situations, and the influence of longitudinal waves on the corridor can be dispersed when an earthquake occurs.

[0025] In summary, the assembled seismic-resistant underground integrated pipe gallery provided by the present invention has the following technical advantages:

[0026] 1) The underground comprehensive pipe gallery of the present invention adopts the idea of ​​assembled structure, prefabricates the gallery body, and transports it to the site as an assembled underground comprehensive pipe gallery, which is easy to install, saving time and effort;

[0027] 2) The underground integrated pipe gallery of the present invention further strengthens the connection between the corridors through prefabricated top plates, bottom plates, cast-in-place concrete, steel bars, and seismic components, thereby increasing the overall stability of the assembled underground integrated pipe gallery;

[0028] 3) The arrangement of the support plate, rectangular plate, spiral shock absorber and rubber elastic plate can not only improve the seismic performance of the prefabricated underground comprehensive pipe gallery, but also improve its overall stability and connection performance;

[0029] 4) The application of curved plates can not only bear and disperse daily static loads and dynamic loads, but also disperse the impact of seismic longitudinal forces on prefabricated underground integrated pipeline corridors during earthquakes. BRIEF DESCRIPTION OF THE DRAWINGS

[0030] Figure 1 It is a front view of the assembled earthquake-resistant underground comprehensive pipe gallery of the present invention;

[0031] Figure 2 It is a side view of the assembled earthquake-resistant underground comprehensive pipe gallery of the present invention;

[0032] Figure 3 It is a top view of the assembled earthquake-resistant underground comprehensive pipe gallery of the present invention;

[0033] Figure 4 It is a schematic diagram of the seismic structure of the assembled seismic-resistant underground comprehensive pipe gallery of the present invention;

[0034] Figure 5 This is a connection diagram between corridors of the assembled earthquake-resistant underground comprehensive pipe gallery of the present invention;

[0035] In the figure: 1-corridor, 2-bottom precast plate, 3-vertical rectangular partition plate, 4-horizontal longitudinal reinforcement, 5-horizontal rectangular partition plate, 6-rectangular plate, 7-vertical longitudinal reinforcement, 8-bolts, 9-support plate, 10-arc plate, 11-support column, 12-top precast plate, 13-grouting hole, 14-cast-in-place concrete, 15-rubber elastic plate, 16-spiral shock absorber, 17-rebar binding wire. DETAILED DESCRIPTION

[0036] The technical solution of the present invention is further described in detail below through embodiments in conjunction with the accompanying drawings. The accompanying drawings are all simplified schematic diagrams, which schematically illustrate the basic structure and implementation method of the assembled earthquake-resistant underground comprehensive pipe gallery of the present invention.

[0037] like Figure 1-Figure 3 As shown, the underground utility corridor of this embodiment is composed of a corridor body 1, a bottom prefabricated plate 2, a top prefabricated plate 12, an arc plate 10, a support column 11, horizontal longitudinal ribs 4, vertical longitudinal ribs 7, horizontal rectangular partition plates 5 and vertical rectangular partition plates 3 to form a main structure. Figure 4 As shown, the seismic resistant structure of the underground integrated pipe gallery includes a support plate 9, a rectangular plate 6, bolts 8, a rubber elastic plate 15, a spiral shock absorber 16 and a steel bar binding wire 17.

[0038] The assembled seismic-resistant underground integrated pipe gallery has horizontal rectangular partition plates 5 and vertical rectangular partition plates 3 arranged in the middle, the arc plate 10 is connected to the gallery body 1 through the support column 11, and the support plate 9 is connected to the gallery body 1 through the embedded bolts 8 ( Figure 1 and Figure 2 The top precast plate 12 is provided with two grouting holes 13 for pouring the cast-in-place concrete 14 ( Figure 3 ), the gallery 1 is provided with horizontal longitudinal ribs 4 and vertical longitudinal ribs 7 in the horizontal and vertical directions, and a support plate 9 is arranged under the top prefabricated plate 12. When the gallery 1 is prefabricated in the factory, Figure 1 Bolts 8 are embedded in the corresponding positions shown. When the plate is subsequently transported to the site for installation, the support plate 9 is fixed by the bolts 8, and then the rectangular plate 6 is welded, and the rubber elastic plate 15 is fixed to the rectangular plate 6 by high-strength glue.

[0039] like Figure 3 and Figure 4 As shown, in the seismic structure of the assembled seismic-resistant underground comprehensive pipe gallery, the horizontal longitudinal reinforcement 4 and the vertical longitudinal reinforcement 7 are arranged in a staggered manner and fixed by steel bar binding wires 17, the support plate 9 is connected and fixed by bolts 8 pre-buried in advance in the gallery body 1, the rectangular plate 6 is welded to the support plate 9, the rubber elastic plate 15 is glued to the rectangular plate 6, and the spiral shock absorber 16 is welded and fixed through the 5-10 cm holes reserved in the rectangular plate 6.

[0040] When the corridors of the assembled earthquake-resistant underground comprehensive pipe gallery are connected to each other, the top prefabricated plate 12 and the bottom prefabricated plate 2 are against the other corridor, and the horizontal longitudinal reinforcement 4 and the vertical longitudinal reinforcement 7 are arranged in a staggered manner below the top prefabricated plate 12, and the two are connected and fixed by the steel bar binding wire 17 after being transported to the site, and the steel bars are provided with the support plate 9 fixed by the embedded bolts 8, and the support plate 9 is arranged with the rectangular plate 6 welded after being transported to the site, the rubber elastic plate 15 and the glued spiral shock absorber 16. At the same time, the arc plate 10 is arranged above the corridor to resist the vertical static load and dynamic load, and is evenly dispersed and transmitted to the corridor 1. The arc plate 10 is completely arranged along the longitudinal direction of the corridor 1, and is connected to the pipe gallery as a whole through the support column 11 prefabricated together with the corridor 1.

[0041] The working principle of the assembled seismic-resistant underground integrated pipe gallery is as follows:

[0042] 1. Assembly principle: Each gallery can be regarded as a unit. The gallery is connected through the top precast plate 12 and the bottom precast plate 2, and is also connected through the staggered horizontal longitudinal reinforcement 4 and vertical longitudinal reinforcement 7, and is also connected through the support plate 9, rectangular plate 6 and spiral shock absorber 16. In the subsequent formwork casting, the top precast plate 12 and the bottom precast plate 2 also act as templates, and the cast-in-place concrete 14 is poured on site through the grouting holes 13 on the top precast plate 12. At the same time, the arc plate 10 above the gallery 1 is also located above each gallery 1, and its length is consistent with the longitudinal length of the gallery 1, and the arc plate 10 is not set at the connection between the gallery and the gallery.

[0043] 2. Anti-seismic principle: The support plate 9 is connected and fixed by bolts 8 pre-buried in the corridor 1, the rubber elastic plate 15 is glued to the rectangular plate 6, and the spiral shock absorber 16 is welded and fixed through the 5-10 cm holes reserved in the rectangular plate 6. The arc plate 10 is completely arranged along the longitudinal direction of the corridor 1, and is connected to the pipe gallery as a whole through the support column 11 prefabricated with the corridor 1. When an earthquake occurs, the greatest damage to the structure is its transverse wave. When the underground comprehensive pipe gallery is subjected to horizontal load, the connection between the corridors is most likely to be damaged. The first line of defense against transverse waves is the horizontal longitudinal reinforcement 4 and vertical longitudinal reinforcement 7 arranged in a dislocated manner and the cast-in-place concrete 14. The second line of defense against transverse waves is the rubber elastic plate 15, and the third line of defense against transverse waves is the spiral shock absorber 16. And the above three lines of defense do not work alone when subjected to horizontal loads, but resist the load synchronously. The second is the longitudinal wave of the earthquake. Since the longitudinal wave is similar to the direction of gravity, the damage to the structure is weaker than the transverse wave, but it cannot be ignored. Therefore, the arc-shaped plate 10 is arranged above the corridor 1, which can disperse the static load and dynamic load from the ground in non-earthquake conditions, and can also disperse the influence of longitudinal waves on the corridor when an earthquake occurs.

[0044] The description of the above embodiments is only used to help understand the structure and core ideas of the present invention, and its purpose is to enable those skilled in the art to understand the content of the present invention and implement it accordingly, and it cannot be used to limit the scope of protection of the present invention. Various equivalent modifications or substitutions made without violating the spirit of the present invention are included in the scope defined by the attached claims.

Claims

1. An assembled seismic-resistant underground integrated pipe gallery, comprising a prefabricated gallery body, a bottom prefabricated plate, a top prefabricated plate, an arc plate, a support column, a support plate, a rectangular plate, a rubber elastic plate, a spiral shock absorber and a steel bar binding wire, wherein: A plurality of corridors are longitudinally connected to form the main body of the pipe gallery. The bottom precast plate and the top precast plate are located at the connection of the corridors. Grouting holes for pouring concrete on site are provided on the top precast plate. Extended horizontal longitudinal reinforcements and vertical longitudinal reinforcements are pre-embedded in the corridor, and the corresponding horizontal longitudinal reinforcements and vertical longitudinal reinforcements in two adjacent corridors are staggered and fixedly connected by steel bar binding wires. A plurality of support plates are evenly distributed and fixed on the connection surface of the corridor, and a rectangular plate is fixedly connected to each support plate. The two ends of the spiral shock absorber are respectively fixedly connected to the rectangular plates on the two connected corridors, and the two sides of each spiral shock absorber are rubber elastic plates, and the two ends of the rubber elastic plate are fixedly connected to the rectangular plates. The support column is precast on the top surface of the corridor, and the arc plate is completely arranged above the corridor along the longitudinal direction of the corridor through the support column; concrete is poured on site through the grouting holes on the top precast plate to complete the installation of the underground comprehensive pipe gallery.

2. The assembled seismic-resistant underground comprehensive pipe gallery according to claim 1 is characterized in that: Horizontal rectangular partition plates and / or vertical rectangular partition plates are arranged inside the gallery.

3. The assembled seismic-resistant underground comprehensive pipe gallery according to claim 1 is characterized in that: The corridor body is pre-embedded with bolts at corresponding positions of the support plates, and the support plates are fixed by the bolts.

4. The assembled seismic-resistant underground comprehensive pipe gallery according to claim 1 is characterized in that: The rectangular plate is fixed on the supporting plate by welding.

5. The assembled seismic-resistant underground comprehensive pipe gallery according to claim 1 is characterized in that: The rectangular plate is provided with a hole, through which the spiral shock absorber is welded and fixed to the rectangular plate.

6. The assembled seismic-resistant underground comprehensive pipe gallery according to claim 1 is characterized in that: The two ends of the rubber elastic plate are bonded to the rectangular plate by high-strength glue, and / or fixed to the rectangular plate by bolts.

7. The assembled seismic-resistant underground comprehensive pipe gallery according to claim 1 is characterized in that: The corridor, bottom prefabricated plate, top prefabricated plate, curved plate and supporting column are prefabricated reinforced concrete structures; the supporting plate and rectangular plate are steel plates treated with anti-corrosion.

8. The assembled seismic-resistant underground comprehensive pipe gallery according to claim 1 is characterized in that: The top prefabricated plate is prefabricated at the front end of the gallery, and the bottom prefabricated plate is prefabricated at the rear end of the gallery, or vice versa; during assembly, the top prefabricated plate and the bottom prefabricated plate are used to support the adjacent gallery.

9. The on-site installation method of the assembled seismic-resistant underground integrated pipe gallery according to any one of claims 1 to 8, comprising: 1) Place the gallery longitudinally, with the top prefabricated panels and the bottom prefabricated panels between the gallery bodies, and completely arrange the curved panels on the top of the gallery bodies along the longitudinal direction of the gallery bodies through supporting columns; 2) Connect the staggered horizontal and vertical longitudinal bars through steel bar binding wires; 3) Fix the support plate to the connecting surface of the gallery, and then fix the rectangular plate to the support plate; 4) The opposite rectangular plates on the two corridors are connected by spiral shock absorbers, and the two ends of the rubber elastic plate are fixed on the rectangular plates; 5) The installation of the pipe gallery is completed by pouring on-site through the grouting holes on the top precast plate.