Auxiliary device for overall lifting formwork surveying and setting-out and construction method

By using angle steel frames and sliding ruler components to form secondary reference points on the overall lifting mold frame, the problems of unstable and large deviations in the traditional measurement and line laying method are solved, and more accurate and reliable axis control is achieved, suitable for Construction of super high-rise buildings in high altitude environment.

CN118980360AActive Publication Date: 2024-11-19SHANGHAI CONSTRUCTION FOURTH CONSTRUCTION GROUP CO LTD
View PDF 5 Cites 0 Cited by

Patent Information

Application Number
CN202410968901.3
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-19
Publication Date
2024-11-19
Estimated Expiration
2044-07-19

AI Technical Summary

Technical Problem

In the construction of super high-rise buildings, the traditional method of measuring and laying the line of the overall lifting mold frame has problems such as unstable temporary reference points, prone to deviations, review and correction difficulties, and the marking points are easily affected by wind loads in high altitude environments, resulting in measurement Inaccurate.

Method used

A measurement and line laying auxiliary device including angle steel frame, angle steel column, laser receiving target and sliding ruler assembly is designed. The secondary reference point is formed through vertically crossed sliding ruler assembly, and the axis control line is controlled by using a thin rope to surround the closed pattern. Pulling, simplifies the measurement process and improves stability.

Benefits of technology

It realizes a more intuitive and stable axis control reference point, which facilitates review and adjustment in high altitude environments, simplifies the installation process, and improves measurement accuracy and reusability.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118980360A_ABST
    Figure CN118980360A_ABST
Patent Text Reader

Abstract

The invention provides an auxiliary device for overall lifting formwork surveying and setting-out and a construction method.The auxiliary device comprises an angle steel frame, three angle steel stand columns, a laser receiving target, a first sliding rule assembly and a second sliding rule assembly, the three angle steel stand columns are welded and fixed to the three corners of the angle steel frame correspondingly, and the three angle steel stand columns are welded and fixed to the three corners of the angle steel frame correspondingly; the laser receiving target is arranged on the upper surface of the angle steel frame; the first sliding rule assembly and the second sliding rule assembly are vertically crossed, two ends of the first sliding rule assembly are detachably fastened on two opposite first side edges of the angle steel frame respectively, and the first sliding rule assembly can move along the first side edges of the angle steel frame; the two ends of the second sliding rule assembly are detachably fastened to the two opposite second side edges of the angle steel frame respectively and can move along the second side edges of the angle steel frame. The auxiliary device assists the overall lifting formwork in surveying and setting-out, and the problems existing in a surveying and setting-out method in the prior art can be solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of building construction measurement, and in particular to an auxiliary device for measuring and setting out an integral lifting formwork and a construction method. Background Art

[0002] In the construction of super high-rise buildings, construction measurement and control is a very important link, which is related to the accuracy of the plane positioning and elevation control of the building structure, and can effectively avoid the problems of excessive up and down misalignment, tilt, torsion, etc. of the building. Integral lifting formwork such as climbing formwork, top formwork, steel platform, etc. are often used in the construction of super high-rise building structures. They usually integrate functional systems such as lifting system, work frame system, structural formwork system, safety protection system, work platform system, etc. Some are also equipped with concrete pouring equipment, construction elevators, tower cranes and other mechanical equipment, which makes the shape and working environment of the overall lifting formwork more complicated, bringing greater difficulties and challenges to the measurement and control of high-altitude construction. One of the more important measurement and control links is the measurement and setting of the axis control line. The axis control line can be used to review the plane deviation of the constructed structure, and the structure to be constructed can be positioned.

[0003] At present, the measurement and layout of the axis control line on the integral lifting formwork is mostly carried out by using the traditional floor ink line drawing method. The process is as follows:

[0004] S1', select the measuring position: In the early stage of the overall lifting mold frame design and processing, select the appropriate axis control reference point measuring position.

[0005] S2', reserved measuring holes: when designing and processing the overall lifting mold frame, reserved measuring holes that penetrate from top to bottom according to the selected measuring position.

[0006] S3', install the laser receiving target: fix a semi-transparent laser receiving target in the measuring hole at the top of the integral lifting mold frame.

[0007] S4', measure the axis control reference point: from the reference point below the integral lifting mold frame, use a plumb line to vertically project the laser beam to the corresponding laser target on the integral lifting mold frame, and mark the receiving light spot on the laser target. After calibration, a temporary reference point is obtained.

[0008] S5', measure the axis control line marking point: measure the temporary reference point on the laser target again to the fixed object around it. The measurement method is to use a steel ruler, tape measure or measuring tape to make a mark on a solid object after offsetting a fixed distance through the temporary reference point in the direction roughly perpendicular and parallel to the axis. The mark point can be welded with steel nails, or painted with a marker pen, colored paint, etc.

[0009] S6', draw the axis control line: when the axis control line is needed, draw an ink line or draw an ink line between two marking points on the same control line. Both the ink line and the ink line can be used as the axis control line, and the plumb bob, tape measure and other tools are used to complete the measurement verification and positioning work.

[0010] As mentioned above, this traditional measurement and layout method has the following shortcomings:

[0011] 1) The temporary reference point obtained by the first measurement is located on the laser target which is a translucent thin plate. The laser target is not a solid fixed object, and its temporary reference point is not convenient to be used directly to fix the control line and serve as the end point of the control line. Therefore, it is necessary to lead it to the side again to make a mark or draw an ink line. The method of leading it to the side again is relatively rough and prone to large deviations.

[0012] 2) The integral lifting formwork is lifted layer by layer as the structure is constructed. The axis control point marks are always repeatedly erased and painted in a small range around the measuring hole. If steel nails are welded, the changes will be more troublesome, and the old marks are easy to be misused if they are not cleaned in time.

[0013] 3) The integral lifting formwork is affected by wind loads at high altitudes and is prone to large deviations. To review and correct this deviation, it is necessary to re-measure, mark, and draw control lines.

[0014] In view of the shortcomings of the measurement and laying-out methods in the prior art, those skilled in the art have been looking for solutions. Summary of the invention

[0015] The purpose of the present invention is to provide an auxiliary device and a construction method for measuring and setting out an integral lifting formwork, so as to solve the problems existing in the measuring and setting out method in the prior art.

[0016] In order to solve the above technical problems, the present invention provides an auxiliary device for measuring and laying out an integral lifting formwork, and the auxiliary device for measuring and laying out an integral lifting formwork comprises: an angle steel frame, three angle steel columns, a laser receiving target, a first slide rule assembly and a second slide rule assembly, the three angle steel columns are respectively welded and fixed on the three corners of the angle steel frame, and the laser receiving target is arranged on the upper surface of the angle steel frame; the first slide rule assembly and the second slide rule assembly are vertically intersected, and the two ends of the first slide rule assembly are respectively detachably fastened to the two opposite first side edges of the angle steel frame, and both can be moved along the first side edge of the angle steel frame; the two ends of the second slide rule assembly are respectively detachably fastened to the two opposite second side edges of the angle steel frame, and both can be moved along the second side edge of the angle steel frame.

[0017] Optionally, in the auxiliary device for measuring and laying out the integral lifting formwork, the four sides of the angle steel frame are provided with long holes opened along the direction of the frame.

[0018] Optionally, in the auxiliary device for measuring and laying out the integral lifting formwork, the first slide rule assembly includes: a first slide rule, a first slide rule large bracket, a first slide rule small bracket, a first slide rule bolt group and a first slide rule bolt, and the two ends of the first slide rule are respectively welded and fixed to the first slide rule large bracket and the first slide rule small bracket; the first slide rule large bracket is detachably fastened to a first side edge of the angle steel frame based on the first slide rule bolt group, and the first slide rule small bracket is detachably fastened to the other first side edge of the angle steel frame based on the first slide rule bolt.

[0019] Optionally, in the auxiliary device for measuring and laying out the integral lifting formwork, the first slide rule bolt group includes: at least two bolts and matching nuts, all of the bolts penetrate through and can be moved along the long holes on the first side, and the first slide rule large bracket is removably fastened to the first side of the angle steel frame in cooperation with the nuts; the first slide rule bolt penetrates through and can be moved along the long holes on the other first side, and the first slide rule small bracket is removably fastened to the other first side of the angle steel frame in cooperation with the nuts.

[0020] Optionally, in the auxiliary device for measuring and setting out the integral lifting formwork, the second slide rule assembly includes: a second slide rule, a second slide rule large bracket, a second slide rule small bracket, a second slide rule bolt group and a second slide rule bolt, and the two ends of the second slide rule are respectively welded and fixed to the second slide rule large bracket and the second slide rule small bracket; the second slide rule large bracket is removably fastened to a second side edge of the angle steel frame based on the second slide rule bolt group, and the second slide rule small bracket is removably fastened to the other second side edge of the angle steel frame based on the second slide rule bolt.

[0021] Optionally, in the auxiliary device for measuring and laying out the integral lifting formwork, the second slide rule bolt group includes: at least two bolts and matching nuts, all of the bolts penetrate through and can be moved along the long holes on the second side, and the second slide rule large bracket is removably fastened to the second side of the angle steel frame in cooperation with the nuts; the second slide rule bolt penetrates through and can be moved along the long holes on the other second side, and the second slide rule small bracket is removably fastened to the other second side of the angle steel frame in cooperation with the nuts.

[0022] The present invention also provides a construction method for measuring and setting out an integral lifting formwork, the construction method for measuring and setting out an integral lifting formwork comprising:

[0023] S1. Select the measuring position: In the early stage of the overall lifting mold frame design and processing, select a suitable axis control reference point measuring position; wherein the axis control line formed by the axis control reference point is a closed figure and encloses most of the main structure;

[0024] S2. Reserved measuring holes: When designing and processing the overall lifting mold frame, reserve measuring holes that penetrate up and down according to the selected measuring position;

[0025] S3. Install several auxiliary devices as described in any one of claims 1 to 6: After the assembly of the integral lifting formwork is completed, select appropriate measuring holes on the top surface of the integral lifting formwork to install the auxiliary devices, and test each auxiliary device after installation to ensure that the first slide assembly and the second slide assembly can slide and lock along the side of the angle steel frame;

[0026] S4. Measuring the axis control reference point: At the reference point below the integral lifting mold frame, use a plumb line to vertically project a laser beam to the laser receiving target of the auxiliary device, mark the receiving light spot on the laser receiving target, and obtain a temporary reference point of the laser receiving target after calibration by the rotation method;

[0027] S5, obtaining a secondary reference point: adjusting the first sliding ruler assembly and the second sliding ruler assembly of the auxiliary device so that the two slide ruler assemblies are away from the outer edge of the enclosure structure and intersect above the temporary reference point. At this time, the intersection of the two slide ruler assemblies is the secondary reference point;

[0028] S6. Pulling the axis control line: select a thin rope with a length greater than the distance between two adjacent auxiliary devices, and the pulling path of the thin rope is as follows: the first end of the thin rope passes through the surface where the secondary reference point on the first auxiliary device is located, goes down to its lower right diagonal intersection, and is pulled to the bolt on the first auxiliary device for winding and knotting to fix; the second end of the thin rope is pulled to the adjacent second auxiliary device, the second end of the thin rope passes through the secondary reference point on the second auxiliary device and goes up from below its diagonal intersection, and is pulled to the bolt on the second auxiliary device for winding and knotting to fix; the remaining auxiliary devices are pulled with the thin rope in the same way, and finally the thin ropes pulled between adjacent auxiliary devices together form a closed figure;

[0029] S7. Complete measurement review and positioning work.

[0030] Optionally, in the construction method for measuring and setting out the integral lifting formwork, in S4, the process of obtaining a temporary reference point after calibration by the rotation method includes the following steps:

[0031] Rotate the plumb line 90° several times to obtain four marks in total;

[0032] Use the four marker centroids as temporary reference points after calibration.

[0033] Optionally, in the construction method for measuring and setting out the integral lifting formwork, S5 comprises the following steps:

[0034] Loosen the first slide bolt group and the first slide bolt of the first slide assembly;

[0035] Adjusting the first sliding ruler assembly so that the first sliding ruler is away from the outer edge of the enclosed structure and is located directly above the temporary reference point of the laser receiving target;

[0036] Loosen the second slide bolt group and the second slide bolt of the second slide assembly;

[0037] Adjusting the second sliding ruler assembly so that the second sliding ruler is away from the outer edge of the enclosed structure and is located directly above the temporary reference point of the laser receiving target;

[0038] Under the premise of keeping the outer edges of the first slider and the second slider not deviating from the temporary reference point, the first slider and the second slider are locked, and the intersection of the outer edges of the first slider and the second slider is used as the secondary reference point.

[0039] Optionally, in the construction method for measuring and setting out the integral lifting formwork, S7 comprises the following steps:

[0040] Use a plumb bob and tape measure to carry out measurement verification and positioning work.

[0041] The auxiliary device and construction method for measuring and setting out the integral lifting formwork provided by the present invention have the following beneficial effects:

[0042] 1) The auxiliary device can transfer the temporary reference point on the laser receiving target to the two slides to form a secondary reference point, so as to obtain a more intuitive, stable and easy-to-use axis control reference point;

[0043] 2) Since the secondary reference point is located by the intersection of two sliding scales, it has an adjustable property, which is convenient for reviewing and adjusting the overall lifting formwork in case of deviation after high-altitude strong winds;

[0044] 3) It integrates the functions of receiving the axis control reference point of the guided measurement and setting the physical axis control line. It has a compact and simple shape, can be customized, and is easy to install on the overall lifting mold frame;

[0045] 4) The solid thin wire is used as the axis control line to be stretched on the auxiliary equipment to form the axis control line. It is not limited by the irregular shape of the overall lifting mold frame, holes, etc., and has the properties of being reusable and easy to replace, thereby improving the problem that the reference point is difficult to use directly and the control line is not easy to stretch in the traditional axis control line measurement and layout method. BRIEF DESCRIPTION OF THE DRAWINGS

[0046] The above and other objects, features and advantages of the present disclosure will become more apparent through a more detailed description of exemplary embodiments of the present disclosure in conjunction with the accompanying drawings, wherein like reference numerals generally represent like components throughout the exemplary embodiments of the present disclosure.

[0047] Figure 1 It is a schematic plan view of an auxiliary device for measuring and setting out an integrally lifted formwork in one embodiment of the present invention;

[0048] Figure 2 yes Figure 1 Side view in the middle AA direction;

[0049] Figure 3 It is a closed figure formed by the arrangement of multiple auxiliary devices during the construction process of measuring and setting out the overall lifting formwork in one embodiment of the present invention.

[0050] Figure 4 yes Figure 3 A partial enlarged schematic diagram of part B;

[0051] Figure 5 is a schematic diagram of a laser receiving target receiving a light spot after marking in one embodiment of the present invention;

[0052] Figure 6 is a schematic diagram of the first sliding ruler and the second sliding ruler, which are separated from the outer edge of the enclosed structure and intersect above the temporary reference point after executing step S5;

[0053] Figure 7 is a partial schematic diagram after the axis control line is set after executing step S6;

[0054] Figure 8 It is a flow chart of the construction method for measuring and laying out the overall lifting formwork.

[0055] In the figure:

[0056] 1, 2, 3-three angle steel columns; 4-angle steel frame; 4-1-long hole; 5-laser receiving target; 6-first slide large bracket; 7-first slide small bracket; 8-first slide bolt group; 9-first slide bolt; 10-first slide; 11-second slide large bracket; 12-second slide small bracket; 13-second slide bolt group; 14-second slide bolt; 15-second slide. DETAILED DESCRIPTION

[0057] The following is a further detailed description of the auxiliary device and construction method for measuring and setting out the integral lifting formwork proposed by the present invention in combination with the accompanying drawings and specific embodiments. The advantages and features of the present invention will become clearer according to the following description and claims. It should be noted that the accompanying drawings are all in a very simplified form and are not in precise proportions, and are only used to conveniently and clearly assist in explaining the purpose of the embodiments of the present invention.

[0058] The present invention will now be described in further detail with reference to the accompanying drawings. These drawings are simplified schematic diagrams, which only illustrate the basic structure of the present invention in a schematic manner, and therefore only show the components related to the present invention.

[0059] In the description of the invention, it is necessary to understand that the terms “center”, “longitudinal”, “lateral”, “length”, “width”, “thickness”, “up”, “down”, “front”, “back”, “left”, “right”, “vertical”, “horizontal”, “top”, “bottom”, “inside”, “outside”, “clockwise”, “counterclockwise”, etc., indicating the orientation or position relationship, are based on the orientation or position relationship shown in the drawings, and are only for the convenience of describing the invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the invention.

[0060] In addition, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Therefore, a feature defined as "first" or "second" may explicitly or implicitly include one or more of the features. In the description of the invention, the meaning of "plurality" is two or more, unless otherwise clearly and specifically defined.

[0061] In the invention, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", "fixed" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be an indirect connection through an intermediate medium, or it can be the internal communication of two elements. For ordinary technicians in this field, the specific meanings of the above terms in the invention can be understood according to the specific circumstances.

[0062] Please refer to Figure 1 and Figure 2 , Figure 1 It is a schematic plan view of an auxiliary device for measuring and setting out an integrally lifted formwork in one embodiment of the present invention; Figure 2 yes Figure 1 Side view in the AA direction. Figure 1 and Figure 2As shown, the auxiliary device for measuring and laying out the integral lifting formwork includes: an angle steel frame 4, three angle steel columns 1, 2, 3, a laser receiving target 5, a first slide rule assembly and a second slide rule assembly, the three angle steel columns 1, 2, 3 are respectively welded and fixed on the three corners of the angle steel frame 4, and the laser receiving target 5 is arranged on the upper surface of the angle steel frame 4; the first slide rule assembly is vertically crossed with the second slide rule assembly, and the two ends of the first slide rule assembly are respectively detachably fastened to the two opposite first side edges of the angle steel frame 4, and both can be moved along the first side edge of the angle steel frame 4; the two ends of the second slide rule assembly are respectively detachably fastened to the two opposite second side edges of the angle steel frame 4, and both can be moved along the second side edge of the angle steel frame 4.

[0063] For further information, please refer to Figure 2 In order to support the first slide rule assembly and the second slide rule assembly to move their positions / slide relative to each other along the sides of the angle steel frame 4 (a total of four sides, a pair of first sides and a pair of second sides), the four sides of the angle steel frame 4 are provided with long holes 4-1 opened along the direction of the frame. Preferably, the long holes 4-1 are square long holes, and the two ends are preferably semicircular.

[0064] Please continue to refer to Figure 1 The first slider assembly includes: a first slider 10, a first slider large bracket 6, a first slider small bracket 7, a first slider bolt group 8 and a first slider bolt 9, and the two ends of the first slider 10 are respectively welded and fixed to the first slider large bracket 6 and the first slider small bracket 7; the first slider large bracket 6 is detachably fastened to a first side of the angle steel frame 4 based on the first slider bolt group 8, and the first slider small bracket 7 is detachably fastened to the other first side of the angle steel frame 4 based on the first slider bolt 9; wherein the first slider bolt group 8 includes: at least two bolts and nuts matched therewith, all of which penetrate and can be moved along the long holes 4-1 on the first side, and cooperate with the nuts to detachably fasten the first slider large bracket 6 to the first side of the angle steel frame 4; the first slider bolt 9 penetrates and can be moved along the long holes 4-1 on the other first side, and cooperates with the nuts to detachably fasten the first slider small bracket 7 to the other first side of the angle steel frame 4.

[0065] Please continue to refer to Figure 2The second slider assembly includes: a second slider 15, a second slider large bracket 11, a second slider small bracket 12, a second slider bolt group 13 and a second slider bolt 14. The two ends of the second slider 15 are respectively welded and fixed to the second slider large bracket 11 and the second slider small bracket 12; the second slider large bracket 11 is detachably fastened to a second side of the angle steel frame 4 based on the second slider bolt group 13, and the second slider small bracket 12 is detachably fastened to the other side of the angle steel frame 4 based on the second slider bolt 14. On the second side; wherein, the second slide bolt group 13 includes: at least two bolts and matching nuts, all of which penetrate and can be moved along the long holes 4-1 on the second side, and cooperate with the nuts to removably fasten the second slide large bracket 11 to the second side of the angle steel frame 4; the second slide bolt 14 penetrates and can be moved along the long holes 4-1 on the other second side, and cooperates with the nuts to removably fasten the second slide small bracket 12 to the other second side of the angle steel frame 4.

[0066] Correspondingly, this embodiment also provides a construction method for measuring and setting out the overall lifting formwork. Figures 1 to 8 The construction method for measuring and setting out the integral lifting formwork described in this embodiment is described in detail.

[0067] First, execute step S1 to select the measuring position: in the early stage of the overall lifting mold frame design and processing, select a suitable axis control reference point measuring position; wherein the axis control line formed by the axis control reference point is a closed figure and encloses most of the main structure.

[0068] Next, execute step S2 to reserve measuring holes: when designing and processing the integral lifting mold frame, reserve measuring holes that penetrate from top to bottom according to the selected measuring positions.

[0069] Next, please refer to Figure 1 and Figure 2 , execute step S3, install several auxiliary devices: after the assembly of the integral lifting formwork is completed, select a suitable measuring hole on the top surface of the integral lifting formwork (usually select the point obtained by offsetting the intersection of the closed intersecting building axes outward by an appropriate operating distance) to install the auxiliary device, and test each auxiliary device after installation to ensure that the first slide assembly and the second slide assembly can slide and lock along the side of the angle steel frame 4. Specifically, the auxiliary device is fixed by welding the angle steel columns (1, 2, 3) to the top steel beam surface of the integral lifting formwork.

[0070] Next, please refer to Figure 5, execute step S4, measure the axis control reference point: at the reference point below the integral lifting mold frame, use a plumb line to vertically project a laser beam to the laser receiving target 5 of the auxiliary device, mark the receiving light spot / spot on the laser receiving target 5, and obtain a temporary reference point of the laser receiving target 5 after calibration by a rotation method; specifically, rotate the plumb line 90° multiple times to obtain four marks in total, and use the centroids of the four marks as temporary reference points after calibration.

[0071] Next, please refer to Figure 6 , execute step S5, obtain the secondary reference point: adjust the first slide assembly and the second slide assembly of the auxiliary device so that the two intersect above the temporary reference point away from the outer edge of the enclosure structure. At this time, the intersection of the two is the secondary reference point. By transferring the temporary reference point on the laser receiving target to the two slides to form a secondary reference point, a more intuitive, stable and easy-to-use axis control reference point is obtained. Since the secondary reference point is located by the intersection of the two slides, it has an adjustable property, which is convenient for reviewing and adjusting in response to the possibility of deviation of the overall lifting formwork after high-altitude strong winds.

[0072] Specifically, S5 includes the following steps:

[0073] S51, loosening the first slide bolt group 8 and the first slide bolt 9 of the first slide assembly;

[0074] S52, adjusting the first sliding ruler assembly so that the first sliding ruler 10 is away from the outer edge of the enclosed structure and is located directly above the temporary reference point of the laser receiving target 5;

[0075] S53, loosening the second slide bolt group 13 and the second slide bolt 14 of the second slide assembly;

[0076] S54, adjusting the second slide ruler assembly so that the second slide ruler 15 is away from the outer edge of the enclosed structure and is located directly above the temporary reference point of the laser receiving target 5;

[0077] S55. On the premise that the outer edges of the first slide 10 and the second slide 15 do not deviate from the temporary reference point, the first slide 10 and the second slide 15 are locked. The intersection of the two can form four intersection points, and the intersection points of the outer edges of the first slide 10 and the second slide 15 are used as secondary reference points.

[0078] Next, please refer to Figure 3 , Figure 4 and Figure 7, execute step S6, pull and set the axis control line: select a thin rope with a length greater than the distance between two adjacent auxiliary devices (named as the first auxiliary device and the second auxiliary device here), and the pulling path of the thin rope is: the first end of the thin rope passes through the surface where the secondary reference point on the first auxiliary device is located, goes down to its lower right diagonal intersection, and is pulled to the bolt on the first auxiliary device for winding and knotting to fix; the second end of the thin rope is pulled to the adjacent second auxiliary device, the second end of the thin rope passes through the secondary reference point on the second auxiliary device and goes up from under its diagonal intersection, and is pulled to the bolt on the second auxiliary device for winding and knotting to fix; the remaining auxiliary devices are pulled with the same method, such as Figure 3 As shown, the thin ropes pulled between adjacent auxiliary devices finally form a closed figure. It combines the functions of receiving the axis control reference point of the measurement and pulling the physical axis control line. It is small and simple in shape, can be customized and processed, and is easy to install on the overall lifting formwork. The solid thin wire is used as the axis control line to be pulled on the auxiliary equipment to form the axis control line. It is not limited by the irregular shape and holes of the overall lifting formwork, and has the properties of being reusable and easy to replace, thereby improving the problem that the reference point is difficult to use directly and the control line is not easy to pull in the traditional axis control line measurement and layout method.

[0079] Then, step S7 is executed to complete the measurement verification and positioning work. Specifically, a plumb bob and a tape measure are used to perform the measurement verification and positioning work. After the measurement is completed, the thin rope can be disassembled and stored for next use.

[0080] It should be noted that, for the aforementioned method embodiments, for the sake of simplicity, they are all expressed as a series of action combinations, but those skilled in the art should be aware that the present application is not limited by the described order of actions, because according to the present application, certain steps can be performed in other orders or simultaneously. Secondly, those skilled in the art should also be aware that the embodiments described in the specification are all preferred embodiments, and the actions and modules involved are not necessarily required by the present application.

[0081] In the above embodiments, the description of each embodiment has its own emphasis. For parts that are not described in detail in a certain embodiment, reference can be made to the relevant descriptions of other embodiments.

[0082] The present invention has the following advantages:

[0083] 1) The auxiliary device can transfer the temporary reference point on the laser receiving target to the two slides to form a secondary reference point, so as to obtain a more intuitive, stable and easy-to-use axis control reference point;

[0084] 2) Since the secondary reference point is located by the intersection of two sliding scales, it has an adjustable property, which is convenient for reviewing and adjusting the overall lifting formwork in case of deviation after high-altitude strong winds;

[0085] 3) It integrates the functions of receiving the axis control reference point of the guided measurement and setting the physical axis control line. It has a compact and simple shape, can be customized, and is easy to install on the overall lifting mold frame;

[0086] 4) The solid thin wire is used as the axis control line to be stretched on the auxiliary equipment to form the axis control line. It is not limited by the irregular shape of the overall lifting mold frame, holes, etc., and has the properties of being reusable and easy to replace, thereby improving the problem that the reference point is difficult to use directly and the control line is not easy to stretch in the traditional axis control line measurement and layout method.

[0087] The above description is only a description of the preferred embodiments of the present invention, and is not intended to limit the scope of the present invention. Any changes or modifications made by a person skilled in the art in the field of the present invention based on the above disclosure shall fall within the scope of protection of the claims.

Claims

1. An auxiliary device for measuring and setting out the overall lifting formwork, characterized in that: include: An angle steel frame (4), three angle steel columns (1, 2, 3), a laser receiving target (5), a first slide ruler assembly (6, 7, 8, 9, 10) and a second slide ruler assembly (11, 12, 13, 14, 15), the three angle steel columns (1, 2, 3) are respectively welded and fixed on the three corners of the angle steel frame (4), the laser receiving target (5) is arranged on the upper surface of the angle steel frame (4); the first slide ruler assembly (6, 7, 8, 9, 10) and the second slide ruler assembly (11, 12, 13, 14, 15) are respectively welded and fixed on the three corners of the angle steel frame (4), the laser receiving target (5) is arranged on the upper surface of the angle steel frame (4); the first slide ruler assembly (6, 7, 8, 9, 10) and the second slide ruler assembly (11 1, 12, 13, 14, 15) are vertically crossed, the two ends of the first sliding ruler assembly (6, 7, 8, 9, 10) are respectively detachably fastened to the two opposite first side edges of the angle steel frame (4), and both can be moved along the first side edge of the angle steel frame (4); the two ends of the second sliding ruler assembly (11, 12, 13, 14, 15) are respectively detachably fastened to the two opposite second side edges of the angle steel frame (4), and both can be moved along the second side edge of the angle steel frame (4).

2. The auxiliary device for measuring and setting out the integral lifting formwork according to claim 1, characterized in that: The four side edges of the angle steel frame (4) are all provided with long holes (4-1) opened along the frame direction.

3. The auxiliary device for measuring and setting out the integral lifting formwork according to claim 2, characterized in that: The first slide rule assembly (6, 7, 8, 9, 10) comprises: a first slide rule (10), a first slide rule large bracket (6), a first slide rule small bracket (7), a first slide rule bolt group (8) and a first slide rule bolt (9); two ends of the first slide rule (10) are respectively welded and fixed to the first slide rule large bracket (6) and the first slide rule small bracket (7); the first slide rule large bracket (6) is detachably fastened to a first side edge of the angle steel frame (4) based on the first slide rule bolt group (8); the first slide rule small bracket (7) is detachably fastened to the other first side edge of the angle steel frame (4) based on the first slide rule bolt (9).

4. The auxiliary device for measuring and setting out the integral lifting formwork according to claim 3, characterized in that: The first slide rule bolt group (8) comprises: at least two bolts and nuts matched therewith, all the bolts penetrate through the elongated holes (4-1) on the first side and can be moved along the position, and cooperate with the nuts to detachably fasten the first slide rule large bracket (6) to the first side of the angle steel frame (4); the first slide rule bolt (9) penetrates through the elongated holes (4-1) on the other first side and can be moved along the position, and cooperate with the nuts to detachably fasten the first slide rule small bracket (7) to the other first side of the angle steel frame (4).

5. The auxiliary device for measuring and setting out the integral lifting formwork according to claim 2, characterized in that: The second slide rule assembly (11, 12, 13, 14, 15) comprises: a second slide rule (15), a second slide rule large bracket (11), a second slide rule small bracket (12), a second slide rule bolt group (13) and a second slide rule bolt (14); two ends of the second slide rule (15) are respectively welded and fixed to the second slide rule large bracket (11) and the second slide rule small bracket (12); the second slide rule large bracket (11) is detachably fastened to a second side edge of the angle steel frame (4) based on the second slide rule bolt group (13); and the second slide rule small bracket (12) is detachably fastened to another second side edge of the angle steel frame (4) based on the second slide rule bolt (14).

6. The auxiliary device for measuring and setting out the integral lifting formwork according to claim 5, characterized in that: The second slide bolt group (13) comprises: at least two bolts and nuts matched therewith, all the bolts penetrate through the elongated holes (4-1) on the second side and can be moved along the position, and cooperate with the nuts to detachably fasten the second slide large bracket (11) to the second side of the angle steel frame (4); the second slide bolt (14) penetrates through the elongated holes (4-1) on the other second side and can be moved along the position, and cooperate with the nuts to detachably fasten the second slide small bracket (12) to the other second side of the angle steel frame (4).

7. A construction method for measuring and setting out the overall lifting formwork, characterized in that: include: S1. Select the measuring position: In the early stage of the overall lifting mold frame design and processing, select a suitable axis control reference point measuring position; wherein the axis control line formed by the axis control reference point is a closed figure and encloses most of the main structure; S2. Reserved measuring holes: When designing and processing the overall lifting mold frame, reserve measuring holes that penetrate up and down according to the selected measuring position; S3. Installing a plurality of auxiliary devices as described in any one of claims 1 to 6: After the assembly of the integral lifting formwork is completed, selecting appropriate measuring holes on the top surface of the integral lifting formwork to install the auxiliary devices, and testing each auxiliary device after installation to ensure that the first slide assembly (6, 7, 8, 9, 10) and the second slide assembly (11, 12, 13, 14, 15) can slide and lock along the side of the angle steel frame (4); S4, measuring the axis control reference point: at the reference point below the integral lifting mold frame, use a plumb line to vertically project a laser beam to the laser receiving target (5) of the auxiliary device, mark the receiving light spot on the laser receiving target (5), and obtain a temporary reference point of the laser receiving target (5) after calibration by a rotation method; S5, obtaining a secondary reference point: adjusting the first sliding ruler component (6, 7, 8, 9, 10) and the second sliding ruler component (11, 12, 13, 14, 15) of the auxiliary device so that the two components, facing away from the outer edge of the enclosed structure, intersect above the temporary reference point, and the intersection of the two components is the secondary reference point; S6. Pulling the axis control line: select a thin rope with a length greater than the distance between two adjacent auxiliary devices, and the pulling path of the thin rope is as follows: the first end of the thin rope passes through the surface where the secondary reference point on the first auxiliary device is located, goes down to its lower right diagonal intersection, and is pulled to the bolt on the first auxiliary device for winding and knotting to fix; the second end of the thin rope is pulled to the adjacent second auxiliary device, the second end of the thin rope passes through the secondary reference point on the second auxiliary device and goes up from below its diagonal intersection, and is pulled to the bolt on the second auxiliary device for winding and knotting to fix; the remaining auxiliary devices are pulled with the thin rope in the same way, and finally the thin ropes pulled between adjacent auxiliary devices together form a closed figure; S7. Complete measurement review and positioning work.

8. The construction method for measuring and setting out the integral lifting formwork according to claim 7, characterized in that: In S4, the process of obtaining a temporary reference point after calibration by the rotation method comprises the following steps: Rotate the plumb line 90° several times to obtain four marks in total; Use the four marker centroids as temporary reference points after calibration.

9. The construction method for measuring and setting out the integral lifting formwork according to claim 7, characterized in that: The S5 comprises the following steps: Loosening the first slide bolt group (8) and the first slide bolt (9) of the first slide assembly (6, 7, 8, 9, 10); Adjusting the first sliding ruler assembly (6, 7, 8, 9, 10) so that the first sliding ruler (10) is away from the outer edge of the enclosed structure and is located directly above the temporary reference point of the laser receiving target (5); Loosening the second slide bolt group (13) and the second slide bolt (14) of the second slide assembly (11, 12, 13, 14, 15); The second sliding ruler assembly (11, 12, 13, 14, 15) is adjusted so that the second sliding ruler (15) is away from the outer edge of the enclosed structure and is located directly above the temporary reference point of the laser receiving target (5); Under the premise of keeping the outer edges of the first slide ruler (10) and the second slide ruler (15) from deviating from the temporary reference point, the first slide ruler (10) and the second slide ruler (15) are locked, and the intersection of the outer edges of the first slide ruler (10) and the second slide ruler (15) is used as the secondary reference point.

10. The construction method for measuring and setting out the integral lifting formwork according to claim 7, characterized in that: The S7 comprises the following steps: Use a plumb bob and tape measure to carry out measurement verification and positioning work.

Citation Information

Patent Citations

  • Paying-off construction method for arc-shaped cantilever structure

    CN112084554A

  • Constructional engineering wall surface paying-off auxiliary device

    CN211923588U

  • Constructional engineering wall surface paying-off auxiliary device

    CN212027172U

  • Laser-assisted pay-off device capable of translating

    CN218779987U

  • Adjustable fit laser-projecting reference tool

    US6823600B1