Construction method of frost heaving prevention prefabricated bottom anchor foundation

Through the combination of precast concrete structure and sand-water mixed mortar materials, the impact of concrete hydration heat on permafrost is solved, the stability and safety of building foundations are improved, and the segmented prefabricated and temperature-controlled ventilation structures are further improved. The anti-frost and swelling capacity and construction efficiency of buildings in frozen soil areas.

CN118997211APending Publication Date: 2024-11-22GEOLOGICAL & NATURAL DISASTER PREVENTION & CONTROL INST GANSU ACADEMY OF SCI
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411287114.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-13
Publication Date
2024-11-22

AI Technical Summary

Technical Problem

In permafrost areas, the hydration heat during concrete foundation construction has a heat impact on the permafrost, resulting in foundation instability, and the degradation of the permafrost affects building safety and stability.

Method used

Precast concrete structure and sand-water mixed mortar material are used instead of cement mortar, and freeze and fix it through the building foundation through the anchor rod to avoid the impact of hydration heat on the frozen soil. High-strength cement mortar is used to fix the anchor rod, which is divided into two upper and lower The prefabricated foundation is used to slow down freezing and enhance the bearing capacity.

Benefits of technology

It effectively avoids the impact of concrete hydration heat on frozen soil, improves the stability and safety of the foundation, reduces freezing and deformation, improves construction efficiency, and actively cools down through the unpowered temperature-controlled ventilation structure to maintain a frozen state.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118997211A_ABST
    Figure CN118997211A_ABST
Patent Text Reader

Abstract

The invention discloses an anti-frost heaving prefabricated bottom anchor foundation construction method which is characterized in that a building foundation of a concrete structure is prefabricated in advance, and during site construction, after the building foundation is placed in a foundation pit, an anchor rod penetrates through the building foundation to achieve anchoring downwards; and a sand-water mixed mortar material is adopted in the anchor rod hole to replace cement mortar so as to realize freezing fixation of the anchor rod. The method has the advantages that thermal disturbance of hydration heat generated by concrete pouring to frozen soil can be better avoided, and the thermal stability of the foundation can be better maintained.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of building construction, and in particular to a construction method for a frost-proof prefabricated bottom anchor foundation. Background Art

[0002] Permafrost, also known as permanent frozen soil, refers to soil and rock layers that remain frozen for two years or more. Building foundation engineering can enhance the bearing capacity of natural sites and has been widely used in permafrost areas. Shallow foundations such as cone-column foundations are shallower than pile foundations and are often constructed using open cut and backfill methods. They are mainly used as tower foundations in power transmission line projects.

[0003] In permafrost areas, the bearing capacity of building foundations mainly depends on the freezing force between the foundation and the surrounding permafrost. Generally speaking, the lower the temperature, the greater the freezing force. However, recently, due to the influence of global warming, the frozen soil has shown a gradual degradation trend. Under this condition, the frozen soil layer shows characteristics such as warming, increased thickness of the active layer, and upward movement of the lower limit of the frozen soil. The foundation is usually made of concrete, and its construction is often cast on site. In this way, the hydration heat generated during the hardening of the concrete will have a great thermal impact on the frozen soil, which will cause the foundation to be easily unstable. In addition, since concrete has relatively good thermal conductivity, when used as the foundation of projects such as transmission line towers, the upper end will be exposed to the air. Therefore, the foundation of the concrete structure itself will become a heat transfer channel for the lower frozen soil. When the surface temperature is high during the day or in summer, the heat will be introduced into the frozen soil below the foundation, causing the frozen soil to warm up or even thaw, which greatly affects the safety and stability of the upper structure.

[0004] Therefore, for technical personnel in this field, how to develop a foundation construction method that can better avoid the impact of concrete hydration heat on permafrost heat, improve the ability to prevent frost heave and deformation, and better maintain the safety of buildings in permafrost areas has become a problem to be considered and solved. Summary of the invention

[0005] In view of the above-mentioned deficiencies in the prior art, the technical problem to be solved by the present invention is: how to provide a frost-proof prefabricated bottom anchor foundation construction method that can better avoid the thermal disturbance of frozen soil caused by the hydration heat generated by concrete pouring, improve the ability to prevent frost heave deformation, and better maintain the thermal stability of the foundation.

[0006] In order to solve the above technical problems, the present invention adopts the following technical solutions:

[0007] A method for constructing a prefabricated bottom anchor foundation to prevent frost heave is characterized in that a building foundation of a prefabricated concrete structure is prepared in advance, and during on-site construction, the building foundation is placed in a foundation pit and anchored downwardly through an anchor rod, and a mortar material mixed with sand and water is used in the anchor rod hole instead of cement mortar to freeze and fix the anchor rod.

[0008] Thus, in this scheme, the building foundation is prefabricated, and the anchor hole uses a mortar material mixed with sand and water instead of cement mortar to freeze and fix the anchor. Therefore, the influence of the hydration heat of cast-in-place concrete on the frozen soil is avoided, and the mortar material replacing cement mortar can also avoid the influence of the thermal conductivity of cement mortar on the frozen soil below, thus greatly improving the stability and safety of the foundation.

[0009] Furthermore, the method comprises the following steps: a. a building foundation of a prefabricated concrete structure is prepared in advance in a factory, wherein the lower part of the building foundation has a base which expands outward in the horizontal direction on all sides, and anchor holes are arranged vertically on the base; b. a foundation pit is excavated on site, a coarse-grained soil cushion layer is arranged under the foundation pit, and then holes are drilled downward at the design positions of the corresponding anchor holes to obtain anchor holes; c. the building foundation is placed above the coarse-grained soil cushion layer, and the upper end of the building foundation is kept above the ground surface so that the anchor holes and the anchor holes are aligned, the anchor rods are inserted into the anchor holes and the anchor holes, and the anchor holes are grouted with a mortar material mixed with sand and water, and after the mortar material is frozen, the anchor holes are grouted with high-strength cement mortar to complete the fixation; d. the foundation pit is backfilled with backfill soil.

[0010] Therefore, this method is more convenient and efficient for on-site construction, and can effectively avoid the impact of concrete hydration heat on frozen soil, and improve the safety and stability of building foundations in frozen soil areas. Among them, the mortar material, which is only a mixture of sand and water, is generally made in the ratio of sand: ratio = (3.5~6.5): 1. The specific ratio can be determined according to the engineering requirements and construction environment, ensuring that the slurry has good fluidity and no obvious stratification after standing for 10 minutes after grouting. If a small amount of stratification occurs, dry sand is added to the design elevation to ensure that the anchor rod is wrapped with saturated medium and coarse sand.

[0011] The building foundation structure obtained by this method includes a building foundation, which is buried in a foundation pit (backfilled with soil) and its upper end protrudes above the ground surface. The building foundation is a prefabricated concrete component. The lower part of the building foundation has a base that expands horizontally on all sides. Anchor holes are vertically arranged on the base. The anchor holes and anchor holes vertically arranged in the soil below the base are directly connected to each other. Anchor holes are vertically connected to the anchor holes and anchor rods are arranged in the anchor holes. Mortar materials mixed with sand and water are frozen and fixed in the anchor holes. High-strength cement mortar is poured in the anchor holes to fix the upper end of the anchor rods.

[0012] In this way, the applicant creatively changed the anchor holes under the foundation to use a mortar material that is only a mixture of sand and water, which can be well integrated with the frozen soil after freezing, and the anchor holes inside the foundation use high-strength cement mortar to achieve reliable fixation of the upper end of the anchor. This will neither generate hydration heat to cause thermal disturbance during construction, nor form a downward heat transfer channel to affect the stability of the foundation; therefore, the safety and stability of the foundation are greatly improved. In addition, the building foundation itself uses prefabricated concrete components, which can also minimize thermal disturbances to permafrost during foundation construction and improve construction efficiency.

[0013] Furthermore, the building foundation includes a prefabricated base at the bottom and a prefabricated conical column at the top. The prefabricated base includes a lower base and a straight arm section of a cylindrical structure located in the middle position above the base. The prefabricated conical column is truncated cone-shaped and the lower end has the same diameter as the straight arm section and is fixedly connected by a docking structure.

[0014] In this way, the building foundation is divided into two parts for prefabrication, which is convenient for transportation and construction and installation. In specific implementation, the prefabricated cone column is a truncated cone structure, and its main function is to slow down the tangential frost heave force generated during the freezing of the active layer. The buried depth of the cone column needs to be greater than the upper limit of the natural frozen soil, and its length ,in The upper limit of natural permafrost burial depth, is a coefficient that needs to be determined according to specifications or numerical simulation calculations. The value should not be too large or too small. If it is too large, the base part will be too large, and if it is too small, it will not be able to play its anti-freeze heave effect well. It is usually recommended to take a value of 7.2°. The prefabricated base is an extended base (i.e., base) and a straight arm section cast in one piece. The extended base is a prism shape, which is designed to form a slope to prevent moisture from gathering on the side surface of the foundation. Symmetrical anchor holes are reserved around the base.

[0015] Furthermore, the docking structure includes a steel embedded connector, the lower half of which is pre-cast and fixed vertically in the middle of the upper end surface of the straight arm section, the embedded connector is a columnar structure as a whole and a transverse connection hole is arranged at the upper end, and the upper end surface of the straight arm section around the embedded connector is also pre-cast and fixed with a plurality of longitudinal ribs extending vertically upward; the docking structure also includes a connector installation cavity located in the middle of the lower end of the prefabricated cone column and corresponding to the embedded connector, the diameter of the connector installation cavity is larger than the diameter of the embedded connector, and the connector installation cavity A bolt hole is provided at the upper end corresponding to the connecting hole of the embedded connecting piece, and a longitudinal reinforcement installing cavity is vertically provided around the connecting piece installing cavity corresponding to the longitudinal reinforcement position, and a grouting port is provided at the lower part and the upper end of the connecting piece installing cavity and each longitudinal reinforcement installing cavity; the upper end of the embedded connecting piece is inserted into the connecting piece installing cavity and the gap is filled with (micro-expansion high-strength) cement mortar, and connecting bolts are correspondingly installed and fixed in the bolt hole and the connecting hole, and the upper end of the longitudinal reinforcement is inserted into the longitudinal reinforcement installing cavity and the gap is filled with (micro-expansion high-strength) cement mortar.

[0016] In this way, the embedded connectors and longitudinal reinforcements are precast and fixed on the upper end of the straight arm section of the prefabricated base. When docking, it is only necessary to insert the embedded connectors and the upper end of the longitudinal reinforcement into the corresponding connector installation cavity and the longitudinal reinforcement installation cavity, and fix the bolts to the bolt holes and the connection holes therein, and then inject grouting into the connector installation cavity and the longitudinal reinforcement installation cavity through the grouting port below respectively until mortar flows out of the grouting port above, and the grouting is completed. Therefore, docking is convenient, and multiple docking strength guarantees are formed by relying on longitudinal reinforcement, embedded connectors, connecting bolts and injected cement mortar, which greatly improves the docking strength and ensures the reliability of the foundation.

[0017] Furthermore, a sink groove is provided on the upper end surface of the straight arm section at the opening of the ventilation duct and a sealing ring is installed to ensure the sealing effect during grouting.

[0018] Furthermore, the longitudinal reinforcement is obtained by using threaded steel bars, which can better improve the fixing effect.

[0019] Furthermore, a U-shaped ventilation duct is arranged inside the building foundation, and two openings at the upper end of the ventilation duct are located on both sides of the supporting device installation position on the upper end surface of the building foundation. One opening of the ventilation duct is an air inlet, and the other opening is an air outlet. An air-inducing device for drawing air into the ventilation duct is arranged at any opening position at the upper end of the ventilation duct.

[0020] In this way, when the temperature is lower than the preset temperature at night or in winter (the preset temperature is generally equal to or lower than the temperature at the lower end of the building foundation), the ventilation device can be turned on to draw air into the ventilation duct, and the cold air on the ground surface can be introduced into the lower end of the building foundation to supplement the cold air that is exported to the ground surface by the building foundation during the day, so as to better maintain the freezing state of the lower end of the building foundation and maintain the stability of the upper structure. During implementation, a layer of coarse-grained soil cushion is set at the bottom of the foundation pit, and its thickness should not be less than 20cm, in order to facilitate the leveling of the base and prevent the accumulation of moisture in the base from causing uneven frost heave deformation.

[0021] Furthermore, the ventilation duct is a U-shaped PVC pipe prefabricated and cast in the building foundation, making it convenient to produce.

[0022] Furthermore, the induced draft device comprises an induced draft impeller mounted on an impeller shaft, the impeller shaft can be horizontally rotatably mounted in the middle of the air outlet so that the induced draft impeller is located above the air outlet, the induced draft impeller is rotated by the horizontal wind flow and can induce the air below to flow upward, the impeller shaft is connected to an automatic rotation and stop temperature control device mounted at the air outlet, the automatic rotation and stop temperature control device comprises a rotation and stop control rod, the rotation and stop control rod is horizontally fixed on an extension section downward from the lower end of the impeller shaft, and the automatic rotation and stop temperature control device also comprises a vertically arranged impeller control memory alloy spring Spring, one end of the memory alloy spring for impeller control is fixed on the inner wall of the air outlet, and the other end is a free end and is fixedly provided with a start-stop latch, the start-stop latch can be slidably installed in a vertical directional groove, the directional groove is used to limit the horizontal movement of the start-stop latch, when the surface air temperature is higher than the transformation temperature (i.e., the preset value) of the memory alloy spring for impeller control, the start-stop latch is located on the rotation path of the stop control rod, when the surface air temperature is lower than the transformation temperature of the memory alloy spring for impeller control, the memory alloy spring for impeller control is deformed to make the start-stop latch disengage from the rotation path of the stop control rod.

[0023] In this way, when the night temperature drops to a preset value (the preset value can usually be set to -3°C during implementation), the memory alloy spring for impeller control is deformed and drives the start-stop latch to disengage from the rotation path of the stop control lever, releasing the lock on the impeller shaft. At this time, the induced draft impeller can rotate and produce a suction effect under the blowing of natural wind flow, driving the airflow in the ventilation duct below to flow upward from the air outlet, so that a wind flow is naturally formed in the ventilation duct, and the cold air on the ground surface is introduced into the lower end of the building foundation for supplementary cooling. The induced draft impeller structure itself is a prior art, and the function of extracting air upward while the wind blows and rotates can be achieved by simply setting the blades to a vortex shape inclined in the same direction. The memory alloy spring itself is also a prior art, which can deform when the temperature drops to the transition temperature, elongate or shorten, and recover after the temperature rises. In this way, the induced draft device can automatically detect the surface temperature to control the wind flow in the ventilation duct, so that the entire device does not need to consume additional power energy, and achieves energy saving, environmental protection, automatic control and long-lasting use. As another method during implementation, the induced draft can be achieved by directly installing an electric fan at the opening. This is simpler to implement but has the disadvantage of being dependent on electricity.

[0024] Furthermore, the air induction device also includes an air outlet tube, the impeller shaft, the memory alloy spring for impeller control, the directional groove and the start-stop latch are all installed in the air outlet tube, and the air outlet tube is pre-cast and fixed at the air outlet.

[0025] In this way, the induced draft device can be produced separately and directly embedded and fixed at the air outlet when the building foundation is poured, which is convenient for production implementation.

[0026] Furthermore, a horizontal support frame is arranged in the air outlet cylinder, and the extension section of the impeller shaft is rotatably mounted on the support frame by means of a bearing.

[0027] This makes it easier to install and fix the impeller shaft.

[0028] Furthermore, an air outlet valve device is installed in the air outlet duct, and the air outlet valve device includes a horizontally arranged air outlet valve, one end of the air outlet valve is vertically rotatably installed on a horizontally arranged air outlet valve shaft, and the other end of the air outlet valve is placed on an air outlet valve limit block provided on the corresponding inner wall of the air outlet duct and is in a closed state. The air outlet valve device also includes a memory alloy spring for air outlet control, one end of the memory alloy spring for air outlet control is fixed to the inner wall of the air outlet duct, and the other end is connected to the air outlet valve. When the surface temperature is lower than the transition temperature of the memory alloy spring for air outlet control (i.e., the preset value), the memory alloy spring for air outlet control is deformed to cause the air outlet valve to rotate to a vertical state.

[0029] In this way, when the surface temperature is higher than the preset value, the air outlet valve is placed on the air outlet valve limit block and is in a closed state; when the surface temperature is lower than the preset value, the air outlet control memory alloy spring is deformed, so that when the induced draft device is turned on, the air outlet valve is also opened for ventilation, and the cold air on the ground surface is introduced into the lower end of the building foundation for supplementary cooling. Therefore, the structure of the air outlet valve device ensures that when the surface temperature does not drop to the preset value, the wind flow can be completely blocked from entering the ventilation duct.

[0030] Furthermore, a reset torsion spring acting on the air outlet valve is also arranged on the air outlet valve rotating shaft.

[0031] In this way, relying on the reset torsion spring can better ensure that after the temperature rises above the preset value, the air outlet valve can be better reset and restored to the closed state.

[0032] Furthermore, an air inlet valve device is provided at the air inlet, and the structure of the air inlet valve device is the same as that of the air outlet valve device, so as to ensure that when the surface temperature does not drop to a preset value, the wind flow can be completely shielded from entering the ventilation duct.

[0033] Furthermore, an air inlet cylinder is provided at the air inlet, the air inlet cylinder is prefabricated and fixed at the air inlet, and the air inlet valve device is installed in the air inlet cylinder, which is more conducive to installation.

[0034] Furthermore, a drainage top in the shape of a cone cover facing upward is suspended and supported above the air inlet to prevent rainwater from entering the ventilation duct.

[0035] Therefore, the above scheme has the following characteristics. 1 The building foundation is divided into two sections, the upper cone column section mainly plays the role of reducing the tangential frost heave force, and the lower section mainly plays the role of enhancing the vertical bearing capacity and anchoring of the foundation. 2 The use of a non-powered temperature-controlled ventilation structure can actively cool the foundation. 3 The prefabricated foundation bottom anchor structure can make full use of the freezing force between the frozen soil under the foundation and the anchor rod to improve the foundation's resistance to frost heave and upward load. At the same time, the anchor rod filling material adopts a cement-free configuration, that is, a medium-coarse sand mortar with good fluidity is used. Without introducing hydration heat, it fully utilizes the freezing effect of the low temperature environment of permafrost on the surrounding soil-filling material-anchor rod to improve the anchoring capacity.

[0036] In summary, the present invention has the advantages of being able to better avoid the thermal impact of concrete hydration heat on frozen soil, improve its anti-frost expansion ability, and better maintain the safety and stability of the building. BRIEF DESCRIPTION OF THE DRAWINGS

[0037] Figure 1 This is a schematic diagram of the building foundation structure obtained by the method of the present invention, and detailed structures such as the air induction device are not shown in the figure.

[0038] Figure 2 for Figure 1Top view of the separate building foundation and coarse-grained soil cushion.

[0039] Figure 3 for Figure 1 Schematic diagram of the docking structure at the upper end of the separately prefabricated base.

[0040] Figure 4 for Figure 1 Schematic diagram of the lower end docking structure of the separately prefabricated conical column.

[0041] Figure 5 It is a structural schematic diagram of a separate air induced device and an air outlet valve device.

[0042] Figure 6 It is a top view of the cooperation point of the separate directional slot and the start-stop latch in the induced draft device.

[0043] Figure 7 It is a structural schematic diagram of a separate air inlet valve device. DETAILED DESCRIPTION

[0044] The present invention is further described in detail below in conjunction with specific implementation modes.

[0045] Optimal implementation method: A method for constructing a prefabricated bottom anchor foundation to prevent frost heave, which is characterized in that a building foundation of a prefabricated concrete structure is prepared in advance. During on-site construction, the building foundation is placed in a foundation pit and anchored downwardly through the building foundation using anchor rods. A mortar material mixed with sand and water is used in the anchor rod hole instead of cement mortar to freeze and fix the anchor rod.

[0046] Thus, in this scheme, the building foundation is prefabricated, and the anchor hole uses a mortar material mixed with sand and water instead of cement mortar to freeze and fix the anchor. Therefore, the influence of the hydration heat of cast-in-place concrete on the frozen soil is avoided, and the mortar material replacing cement mortar can also avoid the influence of the thermal conductivity of cement mortar on the frozen soil below, thus greatly improving the stability and safety of the foundation.

[0047] Specifically, the method comprises the following steps: a. prefabricating a building foundation of a concrete structure in a factory in advance, wherein the lower part of the building foundation has a base which expands outward in the horizontal direction on all sides, and anchor holes are vertically arranged on the base; b. completing the excavation of the foundation pit on site, setting a coarse-grained soil cushion layer under the foundation pit, and then drilling downward at the corresponding anchor hole design position to obtain the anchor hole; c. placing the building foundation above the coarse-grained soil cushion layer, keeping the upper end of the building foundation above the ground surface, so that the anchor hole and the anchor hole are aligned, inserting the anchor rod into the anchor hole and the anchor hole, and grouting the anchor hole with a mortar material mixed with sand and water, and then grouting the anchor hole with high-strength cement mortar after it is frozen to complete the fixation; d. backfilling the foundation pit with backfill soil.

[0048] Therefore, the on-site construction of this method is more convenient and efficient, and it can effectively avoid the influence of concrete hydration heat on frozen soil, improve its ability to prevent frost heave and deformation, and improve the safety and stability of building foundations in frozen soil areas. Among them, the mortar material composed only of sand and water is generally mixed in a ratio of sand: ratio = (3.5~6.5): 1. The specific ratio can be determined according to the engineering requirements and construction environment. It is sufficient to ensure that the slurry has good fluidity and no obvious stratification after standing for 10 minutes after grouting. If a small amount of stratification occurs, dry sand is added to the design elevation to ensure that the anchor rod is wrapped with saturated medium and coarse sand.

[0049] Specifically, see Figure 1-7 As shown, the building foundation structure in the present method includes a building foundation 1, which is buried in a foundation pit 2 (backfilled with soil) and the upper end of which protrudes from the ground surface. The building foundation 1 is a prefabricated concrete component. The lower part of the building foundation 1 has a base 21 that expands outward in the horizontal direction on all sides. Anchor holes 22 are vertically arranged on the base 21. The anchor holes 22 and anchor holes 23 vertically arranged in the soil below the base are directly connected to each other. Anchor holes 24 are vertically connected in the anchor holes 22 and 23. Mortar materials mixed with sand and water are frozen and fixed in the anchor holes. High-strength cement mortar is poured in the anchor holes to fix the upper ends of the anchors.

[0050] In this way, the applicant creatively changed the anchor holes under the foundation to use a mortar material that is only a mixture of sand and water, which can be well integrated with the frozen soil after freezing, and the anchor holes inside the foundation use high-strength cement mortar to achieve reliable fixation of the upper end of the anchor. This will neither generate hydration heat to cause thermal disturbance during construction, nor form a downward heat transfer channel to affect the stability of the foundation; therefore, the safety and stability of the foundation are greatly improved. In addition, the building foundation itself uses prefabricated concrete components, which can also minimize thermal disturbances to permafrost during foundation construction and improve construction efficiency.

[0051] In this embodiment, the building foundation 1 includes a prefabricated base 25 at the bottom and a prefabricated conical column 26 at the top. The prefabricated base 25 includes a lower base 21 and a straight arm section of a cylindrical structure located in the middle position above the base. The prefabricated conical column 26 is truncated cone-shaped and the lower end has the same diameter as the straight arm section and is fixedly connected by a docking structure.

[0052] In this way, the building foundation is divided into two parts for prefabrication, which is convenient for transportation and construction and installation. In specific implementation, the prefabricated cone column is a truncated cone structure, and its main function is to slow down the tangential frost heave force generated during the freezing of the active layer. The buried depth of the cone column needs to be greater than the upper limit of the natural frozen soil, and its length ,in The upper limit of natural permafrost burial depth, is a coefficient that needs to be determined according to specifications or numerical simulation calculations. The value should not be too large or too small. If it is too large, the base part will be too large, and if it is too small, it will not be able to play its anti-freeze heave effect well. It is usually recommended to take a value of 7.2°. The prefabricated base is an extended base (i.e., base) and a straight arm section cast in one piece. The extended base is a prism shape, which is designed to form a slope to prevent moisture from gathering on the side surface of the foundation. Symmetrical anchor holes are reserved around the base.

[0053] The docking structure includes a steel embedded connector 28, the lower half of which is pre-cast and fixed vertically in the middle of the upper end surface of the straight arm section. The embedded connector 28 is a columnar structure as a whole and a transverse connection hole 29 is arranged at the upper end. The upper end surface of the straight arm section around the embedded connector is also pre-cast and fixed with a plurality of longitudinal ribs 30 extending vertically upward. The docking structure also includes a connector installation cavity 31 located in the middle of the lower end of the prefabricated cone column 26 and corresponding to the embedded connector. The diameter of the connector installation cavity 31 is larger than the diameter of the embedded connector 28. A bolt hole 32 is provided at the upper end of 31 corresponding to the connection hole of the embedded connector, and a longitudinal reinforcement installation cavity 33 is vertically provided around the connector installation cavity corresponding to the longitudinal reinforcement position. The connector installation cavity and each longitudinal reinforcement installation cavity are respectively provided with a grouting port 34 at the lower part and the upper end; the upper end of the embedded connector is inserted into the connector installation cavity and the gap is filled with (micro-expansion high-strength) cement mortar, and connecting bolts (not shown in the figure) are correspondingly installed and fixed in the bolt hole and the connection hole, and the upper end of the longitudinal reinforcement is inserted into the longitudinal reinforcement installation cavity and the gap is filled with (micro-expansion high-strength) cement mortar.

[0054] In this way, the embedded connectors and longitudinal reinforcements are precast and fixed on the upper end of the straight arm section of the prefabricated base. When docking, it is only necessary to insert the embedded connectors and the upper end of the longitudinal reinforcement into the corresponding connector installation cavity and the longitudinal reinforcement installation cavity, and fix the bolts to the bolt holes and the connection holes therein, and then inject grouting into the connector installation cavity and the longitudinal reinforcement installation cavity through the grouting port below respectively until mortar flows out of the grouting port above, and the grouting is completed. Therefore, docking is convenient, and multiple docking strength guarantees are formed by relying on longitudinal reinforcement, embedded connectors, connecting bolts and injected cement mortar, which greatly improves the docking strength and ensures the reliability of the foundation.

[0055] Among them, a sink groove is arranged on the upper end surface of the straight arm section at the opening of the ventilation duct and a sealing ring 35 is installed to ensure the sealing effect during grouting.

[0056] Among them, the longitudinal reinforcement is made of threaded steel bars to better improve the fixing effect.

[0057] During implementation, a U-shaped ventilation duct 3 is provided inside the building foundation 1, and two openings at the upper end of the ventilation duct 3 are located on both sides of the supporting device installation position on the upper end surface of the building foundation. One opening of the ventilation duct 3 is an air inlet, and the other opening is an air outlet. An air ducting device for drawing air into the ventilation duct is provided at any opening position at the upper end of the ventilation duct 3.

[0058] In this way, when the transmission line tower and other projects in permafrost areas are constructed with the above-mentioned building foundation device for support, at night when the temperature is lower than the preset temperature (the preset temperature is generally equal to or lower than the temperature at the lower end of the building foundation), the wind device can be turned on to draw air into the ventilation duct, and the cold air on the surface is introduced into the lower end of the building foundation to supplement the cold air that is exported to the surface by the building foundation during the day, so as to better maintain the frozen state of the lower end of the building foundation and maintain the stability of the upper structure. During implementation, a coarse-grained soil cushion layer 20 is set at the bottom of the foundation pit, and its thickness should not be less than 20 cm, in order to facilitate the leveling of the base and prevent the accumulation of moisture in the base from causing uneven frost heave deformation.

[0059] The ventilation duct 3 is a U-shaped PVC pipe prefabricated and cast in the building foundation, making it convenient to produce.

[0060] Wherein, the wind inducing device, see Figure 5-Figure 6 , including an induced draft impeller 4 installed on an impeller shaft 5, the impeller shaft 5 can be horizontally rotatably installed in the middle of the air outlet so that the induced draft impeller 4 is located above the air outlet, and the induced draft impeller is rotated by the horizontal wind flow to induce the air below to flow upward, the impeller shaft 5 is connected to an automatic rotation and stop temperature control device installed at the air outlet, the automatic rotation and stop temperature control device includes a rotation and stop control rod 6, the rotation and stop control rod 6 is horizontally fixed on an extension section 7 at the lower end of the impeller shaft downward, the automatic rotation and stop temperature control device also includes a vertically arranged impeller control memory alloy spring 8, the impeller control One end of the memory alloy spring 8 is fixed to the inner wall of the air outlet, and the other end is a free end and is fixedly provided with a start-stop latch 9. The start-stop latch 9 can be slidably installed in a vertical directional groove 10. The directional groove 10 is used to limit the horizontal movement of the start-stop latch 9. When the surface air temperature is higher than the transformation temperature of the memory alloy spring for impeller control (i.e., the preset value), the start-stop latch 9 is located on the rotation path of the stop control rod 6. When the surface air temperature is lower than the transformation temperature of the memory alloy spring for impeller control, the memory alloy spring 8 for impeller control is deformed so that the start-stop latch is separated from the rotation path of the stop control rod.

[0061] In this way, when the temperature drops to a preset value at night or in winter (the preset value can usually be set to -3°C during implementation), the memory alloy spring for impeller control is deformed and drives the start-stop latch to disengage from the rotation path of the stop control lever, releasing the lock on the impeller shaft. At this time, the induced draft impeller can rotate and produce a suction effect under the blowing of natural wind flow, driving the air flow in the ventilation duct below to flow upward from the air outlet, so that a wind flow is naturally formed in the ventilation duct, and the cold air on the ground surface is introduced into the lower end of the building foundation for supplementary cooling. The induced draft impeller structure itself is a prior art, and the function of extracting air upward while the wind blows and rotates can be achieved by simply setting the blades to a vortex shape inclined in the same direction. The memory alloy spring itself is also a prior art, which can deform when the temperature drops to the transition temperature, elongate or shorten, and recover after the temperature rises. In this way, the induced draft device can automatically detect the surface temperature to control the wind flow in the ventilation duct, so that the entire device does not need to consume additional power energy, and achieves energy saving, environmental protection, automatic control and long-lasting use. As another method during implementation, an electric fan can be directly installed at the opening to achieve air induction. This is simpler to implement but has the disadvantage of relying on electricity.

[0062] The air induction device further comprises an air outlet 11, wherein the impeller shaft, the memory alloy spring for impeller control, the directional groove and the start-stop latch are all installed in the air outlet 11, and the air outlet 11 is pre-cast and fixed at the air outlet.

[0063] In this way, the induced draft device can be produced separately and directly embedded and fixed at the air outlet when the building foundation is poured, which is convenient for production implementation.

[0064] A horizontal support frame 12 is provided in the air outlet tube 11, and the extension section 7 of the impeller shaft is rotatably mounted on the support frame 12 by means of a bearing.

[0065] This makes it easier to install and fix the impeller shaft.

[0066] Among them, the air outlet cylinder 11 is also equipped with an air outlet valve device, see Figure 5 The air outlet valve device includes a horizontally arranged air outlet valve 13, one end of the air outlet valve 13 is vertically rotatably mounted on a horizontally arranged air outlet valve shaft 14, the other end of the air outlet valve 13 is placed on an air outlet valve limit block 15 arranged on the inner wall of the corresponding air outlet cylinder and is in a closed state, the air outlet valve device also includes a memory alloy spring 16 for air outlet control, one end of the air outlet control memory alloy spring 16 is fixed to the inner wall of the air outlet cylinder 11, and the other end is connected to the air outlet valve 13, when the surface temperature is lower than the transformation temperature (i.e., the preset value) of the air outlet control memory alloy spring, the air outlet control memory alloy spring is deformed so that the air outlet valve rotates to a vertical state.

[0067] In this way, when the surface temperature is higher than the preset value, the air outlet valve is placed on the air outlet valve limit block and is in a closed state; when the surface temperature is lower than the preset value, the air outlet control memory alloy spring is deformed, so that when the induced draft device is turned on, the air outlet valve is also opened for ventilation, and the cold air on the ground surface is introduced into the lower end of the building foundation for supplementary cooling. Therefore, the structure of the air outlet valve device ensures that when the surface temperature does not drop to the preset value, the wind flow can be completely blocked from entering the ventilation duct.

[0068] The air outlet valve shaft 14 is also provided with a reset torsion spring (not shown in the figure) acting on the air outlet valve.

[0069] In this way, relying on the reset torsion spring can better ensure that after the temperature rises above the preset value, the air outlet valve can be better reset and restored to the closed state.

[0070] Among them, an air inlet valve device 17 is also provided at the air inlet, see Figure 7 The structure of the air inlet valve device 17 is the same as that of the air outlet valve device, which will not be described in detail. It is used to ensure that when the ground surface temperature does not drop to a preset value, the wind flow can be completely shielded from entering the ventilation duct.

[0071] Among them, an air inlet cylinder is also arranged at the air inlet, the air inlet cylinder is prefabricated and fixed at the air inlet, and the air inlet valve device is installed in the air inlet cylinder. This is more conducive to installation.

[0072] Among them, a drainage top 18 with a cone cover shape upward is suspended and supported above the air inlet to prevent rainwater from entering the ventilation duct.

[0073] Therefore, the above scheme has the following characteristics. 1 The building foundation is divided into two sections, the upper cone column section mainly plays the role of reducing the tangential frost heave force, and the lower section mainly plays the role of enhancing the vertical bearing capacity and anchoring of the foundation. 2 The use of a non-powered temperature-controlled ventilation structure can actively cool the foundation. 3 The prefabricated foundation bottom anchor structure can make full use of the freezing force between the frozen soil under the foundation and the anchor rod to improve the foundation's resistance to frost heave and upward load. At the same time, the anchor rod filling material adopts a cement-free configuration, that is, a medium-coarse sand mortar with good fluidity is used. Without introducing hydration heat, it fully utilizes the freezing effect of the low temperature environment of permafrost on the surrounding soil-filling material-anchor rod to improve the anchoring capacity.

Claims

1. A method for constructing a frost-proof prefabricated bottom anchor foundation, characterized in that: The building foundation of the prefabricated concrete structure is placed in the foundation pit during on-site construction. Anchor rods are passed through the building foundation downward to anchor it, and a mortar material mixed with sand and water is used in the anchor rod hole instead of cement mortar to freeze and fix the anchor rod.

2. The anti-freezing prefabricated bottom anchor foundation construction method according to claim 1, characterized in that: The method comprises the following steps: a) prefabricating a building foundation of a concrete structure in a factory in advance, wherein the lower part of the building foundation has a base which expands outward in the horizontal direction on all sides, and anchor holes are vertically arranged on the base; b) completing the excavation of the foundation pit on site, arranging a coarse-grained soil cushion layer under the foundation pit, and then drilling downward at the corresponding anchor hole design position to obtain the anchor hole; c) placing the building foundation above the coarse-grained soil cushion layer, keeping the upper end of the building foundation above the ground surface, so that the anchor hole and the anchor hole are aligned, inserting the anchor rod into the anchor hole and the anchor hole, and grouting the anchor hole with a mortar material mixed with sand and water, and then grouting the anchor hole with high-strength cement mortar after it is frozen to complete the fixation; d) backfilling the foundation pit with backfill soil.

3. The anti-freezing prefabricated bottom anchor foundation construction method according to claim 2, characterized in that: The building foundation includes a prefabricated pedestal at the bottom and a prefabricated conical column at the top. The prefabricated pedestal includes a lower base and a straight arm section of a cylindrical structure located in the middle position above the base. The prefabricated conical column is truncated cone-shaped and the lower end has the same diameter as the straight arm section and is fixedly connected by a docking structure.

4. The anti-freezing prefabricated bottom anchor foundation construction method according to claim 3, characterized in that: The docking structure comprises a steel embedded connector, the lower half of which is pre-cast and fixed vertically in the middle position of the upper end surface of the straight arm section, the embedded connector is a columnar structure as a whole and a transverse connecting hole is arranged at the upper end, and a plurality of longitudinal bars extending vertically upward are distributed and pre-cast and fixed on the upper end surface of the straight arm section around the embedded connector; the docking structure also comprises a connector installation cavity arranged in the middle of the lower end of the prefabricated cone column corresponding to the embedded connector, the diameter of the connector installation cavity is larger than the diameter of the embedded connector, a bolt hole is arranged at the upper end of the connector installation cavity corresponding to the connecting hole of the embedded connector, longitudinal bar installation cavities are arranged vertically around the connector installation cavity corresponding to the longitudinal bar positions, and grouting ports are arranged at the lower part and the upper end of the connector installation cavity and each longitudinal bar installation cavity; the upper end of the embedded connector is inserted into the connector installation cavity and the gaps are filled with cement mortar, connecting bolts are correspondingly installed and fixed in the bolt holes and the connection holes, the upper end of the longitudinal bar is inserted into the longitudinal bar installation cavity and the gaps are filled with cement mortar.

5. The anti-freezing prefabricated bottom anchor foundation construction method according to claim 4, characterized in that: A sink groove is arranged on the upper end surface of the straight arm section at the opening of the ventilation duct and a sealing ring is installed.

6. The anti-freezing prefabricated bottom anchor foundation construction method according to claim 4, characterized in that: The longitudinal reinforcement is made of threaded steel bars to better improve the fixing effect.

7. The anti-freezing prefabricated bottom anchor foundation construction method according to claim 2, characterized in that: A U-shaped ventilation duct is arranged inside the building foundation. The two openings at the upper end of the ventilation duct are located on both sides of the supporting device installation position on the upper end surface of the building foundation. One opening of the ventilation duct is an air inlet, and the other opening is an air outlet. An air ducting device for drawing air into the ventilation duct is arranged at any opening position at the upper end of the ventilation duct.

8. The anti-freezing prefabricated bottom anchor foundation construction method according to claim 7, characterized in that: The ventilation duct is a U-shaped PVC pipe prefabricated and cast in the building foundation.