Tunnel engineering anti-freezing structure in high and cold frozen earth area
By designing water barriers, insulation layers and antifreeze pipes in tunnel projects in high and frozen areas, using magnets and friction plates to generate heat, and controlling temperature with heating pipes, the problem of water freezing in the drainage pipes is solved and the tunnel structure is ensured The stability and safety of the tunnel extend the service life of the tunnel.
Patent Information
- Application Number
- CN202411129334.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-16
- Publication Date
- 2024-11-22
AI Technical Summary
In high-altitude areas, water is prone to freezing in the drainage pipes, resulting in concentrated expansion pressure and failure of the drainage system, which in severe cases endanger driving safety, and the repeated freeze-thawing of the tunnel drainage ditches affects the durability of the tunnel structure.
A tunnel engineering antifreeze structure in high-altitude frozen areas was designed, including the outer layer of the tunnel and the foundation, the water barrier, the insulation layer and the antifreeze pipe. It is connected through longitudinal, central and transverse drainage pipes, and uses magnets and friction plates to generate heat to prevent The water freezes, and the temperature in the vertical drain pipe is controlled through the heating pipe to ensure that the water flow does not freeze.
It effectively prevents the freezing of water in the drainage system, reduces the impact of freezing force on the tunnel structure, ensures the stability and safety of the tunnel structure, and extends the service life of the tunnel.
Smart Images

Figure CN118997805A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of tunnel engineering, and in particular to an antifreeze structure for tunnel engineering in high-cold frozen soil areas. Background Art
[0002] Alpine frozen soil areas refer to areas located at high latitudes or high altitudes where the permafrost layer under the soil does not melt all year round. The design and construction of antifreeze structures for tunnel projects in alpine frozen soil areas are crucial. Effective antifreeze measures can prevent repeated freezing and thawing of the frozen soil outside the tunnel, and avoid cracking, deformation, and even damage to the tunnel lining.
[0003] After searching, the Chinese patent number CN218780368U discloses a tunnel thermal insulation and antifreeze structure, which relates to the field of tunnel engineering technology, and solves the problem that the temperature in the tunnel is relatively low and relatively humid, which may cause freezing damage to the tunnel structure and the surrounding rock and soil after a long time, resulting in structural instability and partial or overall collapse. The structure comprises a foundation, one side of the foundation is fixedly connected to the outer layer of the tunnel, one side of the outer layer of the tunnel is fixedly connected to a waterproof layer, one side of the waterproof layer is fixedly connected to a secondary lining, one side of the secondary lining is fixedly connected to an insulation layer, one side of the insulation layer is fixedly connected to a fireproof layer, and one side of the fireproof layer is fixedly connected to the inner layer of the tunnel.
[0004] Compared with the prior art, the Chinese patent number CN218780368U has a waterproof layer in the tunnel insulation and antifreeze structure that is tightly attached to one side of the secondary lining, and the insulation layer is tightly attached to the secondary lining, making the tunnel structure have good waterproof and antifreeze effects. The lightweight concrete used in the outer and inner layers of the tunnel is a flexible structure with high compressive strength and elastic modulus, which can effectively reduce the frost heave deformation of the secondary lining. There are a large number of gaps inside the lightweight concrete, which can form a non-circulating air insulation body, which has a thermal insulation and antifreeze effect.
[0005] However, during the use of the above-mentioned device, in high-altitude and cold areas, especially in winter, water is easy to freeze in the drainage pipe, which will generate expansion pressure, causing local stress concentration, drainage system failure and other problems, and even endangering driving safety in severe cases. In addition, the repeated freezing and thawing of the tunnel drainage ditch will affect the durability of the tunnel structure. Therefore, an anti-freeze structure for tunnel engineering in high-altitude and frozen soil areas is proposed. Summary of the invention
[0006] The purpose of the present invention is to solve the shortcomings of the prior art that in high-altitude cold areas, especially in winter, water is easy to freeze in the drainage pipe, which will generate expansion pressure, causing local stress concentration, drainage system failure and other problems, which may even endanger driving safety in severe cases, and repeated freezing and thawing of the tunnel drainage ditch will affect the durability of the tunnel structure. An anti-freezing structure for tunnel engineering in high-altitude frozen soil areas is proposed.
[0007] In order to achieve the above object, the present invention adopts the following technical solutions:
[0008] An antifreeze structure for a tunnel project in a high-cold frozen soil area, comprising a tunnel outer layer and a foundation, a waterproof layer fixedly connected to the inner part of the tunnel outer layer, a secondary lining arranged on the side of the waterproof layer away from the tunnel outer layer, a thermal insulation layer arranged on the side of the secondary lining away from the waterproof layer, and a tunnel inner layer arranged on the side of the thermal insulation layer away from the secondary lining;
[0009] A longitudinal drain pipe and a central drain pipe are arranged inside the foundation, the longitudinal drain pipe and the central drain pipe are connected via a transverse drain pipe, a vertical drain pipe for collecting water in the cable trench is arranged outside the transverse drain pipe, a rotating shaft is arranged outside the vertical drain pipe for rotation connection, a heavy head block and a baffle are fixedly connected outside the rotating shaft, and a control rod for controlling the heating pipe to heat the vertical drain pipe is fixedly connected outside the rotating shaft;
[0010] A friction plate is slidably connected inside the central drain pipe and can generate heat by friction with the central drain pipe. A control magnet is arranged on the side of the friction plate close to the transverse drain pipe. A rotating magnet is rotatably connected inside the transverse drain pipe, and a rotating fan blade is fixedly connected outside the rotating magnet.
[0011] The above technical solution further includes:
[0012] The insulation layer is made of polyurethane board, a fireproof layer is added between the insulation layer and the inner layer of the tunnel, the waterproof layer is made of waterproof board, and the secondary lining adopts a concrete mix ratio of "cement 475kg, sand 324kg, crushed stone 1080kg", retarder 3%, early strength agent 2%, phosphate water expansion agent 1.2%, and silicone-based anti-weathering agent 1%.
[0013] The outer layer of the tunnel is provided with an antifreeze pipe, which is arranged between the secondary lining and the waterproof layer, so that the antifreeze pipe can be closely combined with the tunnel structure, effectively playing the role of heat exchange and thermal insulation. In seasonal frozen areas or severe cold areas, the water in the tunnel surrounding rock will freeze and expand at low temperatures, generating frost heave force on the tunnel structure. By setting up the antifreeze pipe and using the air or medium inside it for heat exchange, the heat inside the surrounding rock can be transferred to the inside of the tunnel, so that the water in the surrounding rock remains in a liquid or slightly frozen state, thereby reducing the generation of frost heave force. At the same time, the antifreeze pipe can also play the role of thermal insulation, reduce the impact of the temperature difference between the inside and outside of the tunnel on the tunnel structure, and further protect the stability and safety of the tunnel structure.
[0014] The heavy block and the baffle are in a balanced state, a control circuit is arranged outside the vertical drain pipe, a closing switch for closing the control circuit is fixedly connected to one side of the control rod close to the control rod, and the control circuit heats the control heating tube.
[0015] A thermal insulation layer for heat preservation is arranged outside the vertical drain pipe.
[0016] A filler is arranged outside the central drainage pipe, and a protective outer pipe is arranged outside the filler.
[0017] An acting force is generated between the rotating magnet and the control magnet.
[0018] The water flow inside the vertical drain pipe flows through the gap formed between the control baffle plate and the vertical drain pipe when the baffle plate rotates downward.
[0019] The present invention has the following beneficial effects:
[0020] 1. In the present invention, part of the water flow will flow into the interior of the central drain pipe through the transverse drain pipe, the water flow will drive the rotating fan blades to rotate, the magnetic field formed by the rotating magnet will change after the rotation, the control magnet will receive the corresponding magnetic force in the changing magnetic field, and then it will move, the control magnet movement drives the friction plate to move, at this time the friction plate will rub against the inner wall of the central drain pipe, the continuous friction between the friction plate and the central drain pipe will generate a certain amount of heat, so that the temperature of part of the water flow in the central drain pipe itself will increase, to a certain extent, prevent the water inside the central drain pipe from freezing.
[0021] 2. In the present invention, when water flows through the inside of the vertical drain pipe, the baffle rotates downward, the heavy head block rotates upward, the rotation of the rotating shaft drives the control rod to rotate, and the rotation of the control rod drives the closing switch to move upward, thereby closing the switch and the control circuit to contact, so that the control circuit closes the loop, and the control circuit controls the heating tube to work for heating, thereby reducing the possibility of water seepage and freezing in the vertical drain pipe. BRIEF DESCRIPTION OF THE DRAWINGS
[0022] Figure 1 This is a schematic diagram of the structure of an antifreeze structure for tunnel engineering in high-cold frozen soil areas proposed by the present invention;
[0023] Figure 2 It is a schematic diagram of the structure of the first part of the present invention;
[0024] Figure 3 It is a schematic structural diagram of the second part of the present invention;
[0025] Figure 4 It is a schematic structural diagram of the third part of the present invention;
[0026] Figure 5It is a schematic structural diagram of the fourth part of the present invention;
[0027] Figure 6 for Figure 2 The enlarged schematic diagram at A in the middle;
[0028] Figure 7 for Figure 3 The enlarged schematic diagram of point B in the middle;
[0029] Figure 8 for Figure 4 The enlarged schematic diagram at C in the middle;
[0030] Fig. 9 for Figure 5 Enlarged schematic diagram at point D in the middle.
[0031] In the figure: 1. Tunnel outer layer; 2. Foundation; 3. Longitudinal drainage pipe; 4. Central drainage pipe; 5. Horizontal drainage pipe; 6. Vertical drainage pipe; 7. Cable trench; 8. Tunnel inner layer; 9. Insulation layer; 10. Secondary lining; 11. Waterproof layer; 12. Antifreeze pipe; 13. Insulation layer; 14. Heating pipe; 15. Rotating shaft; 16. Heavy block; 17. Baffle; 18. Control circuit; 19. Control lever; 20. Closing switch; 21. Friction plate; 22. Control magnet; 23. Rotating fan blades; 24. Rotating magnet; 25. Filling; 26. Protective outer tube. DETAILED DESCRIPTION
[0032] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0033] See also Figure 1-9 As shown, the present invention is an antifreeze structure for tunnel engineering in high-cold frozen soil areas, comprising a tunnel outer layer 1 and a foundation 2, a waterproof layer 11 is fixedly connected inside the tunnel outer layer 1, a secondary lining 10 is arranged on the side of the waterproof layer 11 away from the tunnel outer layer 1, a thermal insulation layer 9 is arranged on the side of the secondary lining 10 away from the waterproof layer 11, and a tunnel inner layer 8 is arranged on the side of the thermal insulation layer 9 away from the secondary lining 10;
[0034] A longitudinal drainage pipe 3 and a central drainage pipe 4 are arranged inside the foundation 2, and the longitudinal drainage pipe 3 and the central drainage pipe 4 are connected through a transverse drainage pipe 5. A vertical drainage pipe 6 for collecting water in the cable trench 7 is arranged outside the transverse drainage pipe 5. A rotating shaft 15 is arranged outside the vertical drainage pipe 6 for rotation connection. A heavy block 16 and a baffle 17 are fixedly connected outside the rotating shaft 15. A control rod 19 for controlling the heating pipe 14 to heat the vertical drainage pipe 6 is fixedly connected outside the rotating shaft 15.
[0035] A friction plate 21 is slidably connected inside the central drain pipe 4 and can generate heat by friction with the central drain pipe 4. A control magnet 22 is provided on the side of the friction plate 21 close to the transverse drain pipe 5. A rotating magnet 24 is rotatably connected inside the transverse drain pipe 5, and a rotating fan blade 23 is fixedly connected to the rotating magnet 24 outside.
[0036] In one embodiment, for the above-mentioned insulation layer 9, a polyurethane board is selected for the insulation layer 9, a fireproof layer is added between the insulation layer 9 and the tunnel inner layer 8, a waterproof board is selected for the water-proof layer 11, and the concrete mix ratio used for the secondary lining 10 is "475kg of cement, 324kg of sand, 1080kg of crushed stone", 3% of retarder, 2% of early strength agent, 1.2% of phosphate water expansion agent, and 1% of silicone-based anti-weathering agent.
[0037] In one embodiment, for the above-mentioned antifreeze pipe 12, an antifreeze pipe 12 is arranged outside the outer layer 1 of the tunnel, and the antifreeze pipe 12 is arranged between the secondary lining 10 and the waterproof layer 11, so that the antifreeze pipe 12 can be closely combined with the tunnel structure, and effectively play the role of heat exchange and thermal insulation. In seasonal frozen areas or severe cold areas, the water in the tunnel surrounding rock will freeze and expand at low temperatures, generating frost heave force on the tunnel structure. By setting the antifreeze pipe 12 and using the air or medium inside it for heat exchange, the heat inside the surrounding rock can be transferred to the inside of the tunnel, so that the water in the surrounding rock remains in a liquid or slightly frozen state, thereby reducing the generation of frost heave force. At the same time, the antifreeze pipe 12 can also play the role of thermal insulation, reduce the impact of the temperature difference between the inside and outside of the tunnel on the tunnel structure, and further protect the stability and safety of the tunnel structure.
[0038] In one embodiment, for the above-mentioned heavy block 16, the heavy block 16 and the baffle 17 are in a balanced state, a control circuit 18 is arranged outside the vertical drain pipe 6, and a closing switch 20 for closing the control circuit 18 is fixedly connected to the side of the control rod 19 close to the control rod 19, and the control circuit 18 controls the heating tube 14 to heat it.
[0039] In one embodiment, for the vertical drain pipe 6 , a thermal insulation layer 13 for heat preservation is disposed outside the vertical drain pipe 6 .
[0040] In one embodiment, for the central drain pipe 4 , a filler 25 is disposed outside the central drain pipe 4 , and a protective outer pipe 26 is disposed outside the filler 25 .
[0041] In one embodiment, for the rotating magnet 24 , a force is generated between the rotating magnet 24 and the control magnet 22 .
[0042] In one embodiment, for the vertical drain pipe 6 , water flows inside the vertical drain pipe 6 through a gap formed when the baffle plate 17 rotates downward and controls the vertical drain pipe 6 .
[0043] The working principle of the antifreeze structure of a tunnel engineering in a high-cold frozen soil area proposed by the present invention is to use a specific concrete mix ratio to construct a secondary lining 10, including 475kg of cement, 324kg of sand, 1080kg of crushed stone, etc., and add an appropriate amount of retarder, early strength agent, phosphate water-expanding agent and silicone-based anti-weathering agent. The retarder is used to delay the setting time of concrete and improve construction efficiency. The early strength agent is used to improve the early strength of concrete. The phosphate water-expanding agent can form tiny pores inside the concrete to increase its impermeability. The silicone-based anti-weathering agent can improve the durability and weathering resistance of the concrete. The concrete is poured onto the waterproof layer 11 according to the construction requirements, and is fully vibrated and maintained to ensure the compactness and strength of the secondary lining 10.
[0044] A polyurethane board is selected as the material of the thermal insulation layer 9, which has excellent thermal insulation performance and low thermal conductivity. The polyurethane board is evenly laid on the side of the secondary lining 10 away from the waterproof layer 11 to ensure that the thermal insulation layer 9 and the secondary lining 10 are tightly fitted without gaps. A fireproof layer is added between the thermal insulation layer 9 and the tunnel inner layer 8 to improve the fireproof performance of the tunnel. The tunnel inner layer 8 is constructed on the fireproof layer to ensure that the inner layer surface is flat and smooth. An antifreeze pipe 12 is set between the secondary lining 10 and the waterproof layer 11 to insulate the tunnel in cold seasons and prevent freezing damage caused by low temperature.
[0045] When groundwater flows through the longitudinal drainage pipe 3, part of the water will flow through the transverse drainage pipe 5 to the inside of the central drainage pipe 4. When the water flows through the rotating blades 23 and the rotating magnets 24, the water will drive the rotating blades 23 to rotate. The rotation of the rotating blades 23 will drive the rotating magnets 24 to rotate. After the rotating magnets 24 rotate, the magnetic field formed by them will change, and then a changing magnetic field will be generated. The control magnets 22 will receive corresponding magnetic forces in the changing magnetic field, and then they will move. The movement of the control magnets 22 will drive the friction plate 21 to move. At this time, the friction plate 21 will rub against the inner wall of the central drainage pipe 4. Under the continuous friction between the friction plate 21 and the central drainage pipe 4, a certain amount of heat will be generated, so that the temperature of part of the water in the central drainage pipe 4 will increase, which will prevent the water inside the central drainage pipe 4 from freezing to a certain extent.
[0046] When water accumulates in the cable trench 7, the water flow put into the inside will pass through the vertical drain pipe 6. When it passes through the drain pipe 6, since there is more water above the baffle 17 than above the heavy block 16, the normal space between the heavy block 16 and the baffle 17 is broken, and the baffle 17 rotates downward, and the heavy block 16 rotates upward. The rotation of the heavy block 16 and the baffle 17 drives the rotating shaft 15 to rotate, and the rotation of the rotating shaft 15 drives the control rod 19 to rotate. The rotation of the control rod 19 drives the closing switch 20 to move upward, and then the closing switch 20 contacts the control circuit 18, so that the control circuit 18 closes the loop, and the control circuit 18 controls the heating tube 14 to work for heating, thereby reducing the possibility of water seepage and freezing in the vertical drain pipe 6.
[0047] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. A tunnel engineering antifreeze structure in a high-cold frozen soil area, comprising a tunnel outer layer (1) and a foundation (2), characterized in that: A waterproof layer (11) is fixedly connected to the interior of the tunnel outer layer (1); a secondary lining (10) is arranged on the side of the waterproof layer (11) away from the tunnel outer layer (1); a thermal insulation layer (9) is arranged on the side of the secondary lining (10) away from the waterproof layer (11); and a tunnel inner layer (8) is arranged on the side of the thermal insulation layer (9) away from the secondary lining (10); A longitudinal drainage pipe (3) and a central drainage pipe (4) are arranged inside the foundation (2); the longitudinal drainage pipe (3) and the central drainage pipe (4) are connected via a transverse drainage pipe (5); a vertical drainage pipe (6) for collecting water in the cable trench (7) is arranged outside the transverse drainage pipe (5); a rotating shaft (15) is arranged outside the vertical drainage pipe (6) for rotation connection; a heavy block (16) and a baffle (17) are fixedly connected outside the rotating shaft (15); and a control rod (19) for controlling a heating pipe (14) to heat the vertical drainage pipe (6) is fixedly connected outside the rotating shaft (15); The central drain pipe (4) is slidably connected to a friction plate (21) capable of generating heat by friction with the central drain pipe (4), a control magnet (22) is provided on a side of the friction plate (21) close to the transverse drain pipe (5), a rotating magnet (24) is rotatably connected to the inside of the transverse drain pipe (5), and a rotating fan blade (23) is fixedly connected to the outside of the rotating magnet (24).
2. The antifreeze structure for tunnel engineering in high-cold frozen soil areas according to claim 1 is characterized in that: The insulation layer (9) is made of polyurethane board, a fireproof layer is added between the insulation layer (9) and the tunnel inner layer (8), the waterproof layer (11) is made of waterproof board, and the secondary lining (10) uses a concrete mix ratio of "cement 475kg, sand 324kg, crushed stone 1080kg", retarder 3%, early strength agent 2%, phosphate water expansion agent 1.2%, and silicone-based anti-weathering agent 1%.
3. The antifreeze structure for tunnel engineering in high-cold frozen soil areas according to claim 1 is characterized in that: An antifreeze pipe (12) is arranged outside the outer layer (1) of the tunnel, and the antifreeze pipe (12) is arranged between the secondary lining (10) and the waterproof layer (11).
4. The antifreeze structure for tunnel engineering in high-cold frozen soil areas according to claim 1, characterized in that: The heavy block (16) and the baffle (17) are in a balanced state, a control circuit (18) is arranged outside the vertical drain pipe (6), a closing switch (20) for closing the control circuit (18) is fixedly connected to a side of the control rod (19) close to the control rod (19), and the control circuit (18) controls the heating pipe (14) to heat.
5. The antifreeze structure for tunnel engineering in high-cold frozen soil areas according to claim 1, characterized in that: The vertical drain pipe (6) is provided with a thermal insulation layer (13) for heat preservation outside.
6. The antifreeze structure for tunnel engineering in high-cold frozen soil areas according to claim 1, characterized in that: A filler (25) is arranged outside the central drainage pipe (4), and a protective outer pipe (26) is arranged outside the filler (25).
7. The antifreeze structure for tunnel engineering in high-cold frozen soil areas according to claim 1, characterized in that: An acting force is generated between the rotating magnet (24) and the control magnet (22).
8. The antifreeze structure for tunnel engineering in high-cold frozen soil areas according to claim 1, characterized in that: The water flow inside the vertical drain pipe (6) flows through the gap formed by the control baffle (17) rotating downward and the vertical drain pipe (6).