Unloading control method for pebble-bed modular high-temperature gas cooled reactor
Through logic control and real-time monitoring system, the problem of the risk of negative pressure change rate protection during loading and unloading of ball bed modular high-temperature gas-cooled reactors is solved, preventing helium leakage and gas series, ensuring the safe operation of the reactor.
Patent Information
- Application Number
- CN202411122513.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-15
- Publication Date
- 2024-11-22
AI Technical Summary
During the loading and unloading process of ball bed modular high-temperature gas-cooled relay, it is easy to cause the protection risk of negative change rate of the first circuit pressure during the loading and unloading process, and there is a risk of helium leakage and gas serialization.
Logically control the opening and locking of the unloading pipeline, monitor the pressure difference and atmosphere type in real time, and automatically lock the relevant pipelines to prevent helium leakage and series of gas. Multiple pipelines are used to connect and monitor systems, including pressure monitoring, The valve status monitoring and atmosphere detection device is automatically operated according to preset logic using the control module.
It effectively prevents the negative pressure rate protection caused by improper operation, prevents helium leakage and gas series, and ensures safe and stable operation in the reactor.
Smart Images

Figure CN119008057A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of safe operation of high-temperature gas-cooled reactors, and in particular to a method for controlling the unloading of a pebble bed modular high-temperature gas-cooled reactor. Background Art
[0002] The Pebble Bed Modular High Temperature Gas-Cooled Reactor (HTR-PM) is a modular nuclear power plant consisting of two reactor units. Each reactor unit is equipped with a corresponding fuel loading and unloading system to facilitate fuel loading and unloading operations. In addition, the nuclear power plant is also equipped with two unloading temporary storage devices for temporary storage of fuel unloaded from the reactor unit.
[0003] In order to achieve smooth transportation of fuel, the external loading device is connected to the two temporary unloading storage devices through a primary unloading pipeline. At the same time, the two temporary unloading storage devices are also connected to the two reactor units through secondary unloading pipelines. This design allows the fuel to be efficiently transferred between the various parts. However, since the reactor unit is filled with helium atmosphere and the external environment is air atmosphere, there is a risk of gas cross-talk between the two stacks or leakage of high-pressure helium due to improper operation during the unloading process, thereby triggering the risk of negative rate of change protection of the primary pressure. Summary of the invention
[0004] Therefore, the technical problem to be solved by the present invention is to overcome the defect of the prior art pebble bed modular high temperature gas-cooled reactor that there is a risk of triggering a negative change rate protection of the pressure in the first circuit due to improper operation during the loading and unloading process, thereby providing a pebble bed modular high temperature gas-cooled reactor unloading control method.
[0005] In order to solve the above technical problems, the present invention provides a pebble bed modular high temperature gas-cooled reactor unloading control method, the pebble bed modular high temperature gas-cooled reactor comprises a first reactor, a second reactor, a first unloading temporary storage device, a second unloading temporary storage device and a secondary unloading device, the first reactor is connected with the first unloading temporary storage device and the second unloading temporary storage device through a first unloading pipeline, the second reactor is connected with the first unloading temporary storage device and the second unloading temporary storage device through a second unloading pipeline, the first unloading temporary storage device and the secondary unloading device are connected with a first secondary unloading pipeline, and the second unloading temporary storage device and the secondary unloading device are connected with a second secondary unloading pipeline;
[0006] Discharge control methods include:
[0007] When the first discharge pipeline is opened and the first reactor discharges to the first discharge temporary storage device or the second discharge temporary storage device, and / or when the second discharge pipeline is opened and the second reactor discharges to the first discharge temporary storage device or the second discharge temporary storage device, the first secondary discharge pipeline and the second secondary discharge pipeline are locked;
[0008] When the first secondary unloading pipeline is opened and the first unloading temporary storage device discharges materials to the secondary unloading device, and / or when the second secondary unloading pipeline is opened and the second unloading temporary storage device discharges materials to the secondary unloading device, the first unloading pipeline and the second unloading pipeline are locked.
[0009] Optionally, when the first unloading pipeline between the first reactor and the first unloading temporary storage device is opened, the first unloading pipeline between the first reactor and the second unloading temporary storage device is locked;
[0010] When the first unloading pipeline between the first reactor and the second unloading temporary storage device is opened, the first unloading pipeline between the first reactor and the first unloading temporary storage device is locked.
[0011] Optionally, when the second unloading pipeline between the second reactor and the first unloading temporary storage device is opened, the second unloading pipeline between the second unloading temporary storage device and the second reactor is locked;
[0012] When the second unloading pipeline between the second reactor and the second unloading temporary storage device is opened, the second unloading pipeline between the second unloading temporary storage device and the first reactor is locked.
[0013] Optionally, when the first unloading pipeline between the first unloading temporary storage device and the first reactor is opened, the pressure difference between the first unloading temporary storage device and the first reactor is monitored in real time, and when the pressure difference is greater than a preset threshold, the first unloading pipeline between the first unloading temporary storage device and the first reactor is closed.
[0014] Optionally, when the first unloading pipeline between the second unloading temporary storage device and the first reactor is opened, the pressure difference between the second unloading temporary storage device and the first reactor is monitored in real time. When the pressure difference is greater than a preset threshold, the first unloading pipeline between the second unloading temporary storage device and the first reactor is closed.
[0015] Optionally, when the second unloading pipeline between the first unloading temporary storage device and the second reactor is opened, the pressure difference between the first unloading temporary storage device and the second reactor is monitored in real time, and when the pressure difference is greater than a preset threshold, the second unloading pipeline between the first unloading temporary storage device and the second reactor is closed.
[0016] Optionally, when the second unloading pipeline between the second unloading temporary storage device and the second reactor is opened, the pressure difference between the second unloading temporary storage device and the second reactor is monitored in real time, and when the pressure difference is greater than a preset threshold, the second unloading pipeline between the second unloading temporary storage device and the second reactor is closed.
[0017] Optionally, the gas atmosphere in the first unloading temporary storage device is monitored in real time. If it is a helium atmosphere, the first and second unloading pipelines are prohibited from opening. If it is an air atmosphere, the first unloading pipeline and the second unloading pipeline are prohibited from opening.
[0018] Optionally, the gas atmosphere in the second unloading temporary storage device is monitored in real time. If it is a helium atmosphere, the second secondary unloading pipeline is prohibited from opening; if it is an air atmosphere, the first unloading pipeline and the second unloading pipeline are prohibited from opening.
[0019] Optionally, a pair of control valves are installed on the first secondary unloading pipeline, the second secondary unloading pipeline, the first unloading pipeline and the second unloading pipeline.
[0020] The technical solution of the present invention has the following advantages:
[0021] 1. The present invention provides a pebble bed modular high temperature gas-cooled reactor unloading control method. When the first unloading pipeline or the second unloading pipeline is opened, during the primary unloading process of the first reactor or the second reactor, the first unloading temporary storage device and the second unloading temporary storage device are respectively connected to the secondary unloading device to prevent helium in the first reactor or the second reactor from leaking out. When the first secondary unloading pipeline or the second secondary unloading pipeline is opened, during the secondary unloading process, the first unloading temporary storage device or the second unloading temporary storage device will lock the first unloading pipeline and the second unloading pipeline of the primary unloading to prevent helium in the first reactor or the second reactor from leaking out through the first unloading temporary storage device or the second unloading temporary storage device. By logically controlling the opening and closing states of multiple pipelines of the pebble bed modular high temperature gas-cooled reactor during the unloading process, it is prevented that the negative rate of change protection of the primary pressure is triggered due to improper operation of the unloading temporary storage device.
[0022] 2. The present invention provides a method for controlling the unloading of a pebble bed modular high-temperature gas-cooled reactor. During an unloading process, when the first unloading temporary storage device or the second unloading temporary storage device is unloading to one reactor, the unloading pipeline connected to the other reactor is locked to prevent gas cross-talk between the two reactors. BRIEF DESCRIPTION OF THE DRAWINGS
[0023] In order to more clearly illustrate the specific implementation methods of the present invention or the technical solutions in the prior art, the drawings required for use in the specific implementation methods or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are some implementation methods of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0024] Figure 1 It is a schematic structural diagram of a pebble bed modular high temperature gas-cooled reactor provided in an embodiment of the present invention.
[0025] Description of reference numerals: 1. first reactor; 2. second reactor; 3. first temporary storage device for unloading; 4. second temporary storage device for unloading; 5. secondary unloading device; 6. first unloading pipeline; 7. second unloading pipeline; 8. first and second unloading pipelines; 9. second and second unloading pipelines; 10. control valve; DETAILED DESCRIPTION
[0026] The technical solution of the present invention will be described clearly and completely below in conjunction with the accompanying drawings. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0027] In the description of the present invention, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", etc., indicating the orientation or positional relationship, are based on the orientation or positional relationship shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as limiting the present invention. In addition, the terms "first", "second", and "third" are used for descriptive purposes only, and cannot be understood as indicating or implying relative importance.
[0028] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0029] In addition, the technical features involved in the different embodiments of the present invention described below can be combined with each other as long as they do not conflict with each other.
[0030] Example
[0031] This embodiment provides a method for controlling the unloading of a pebble bed modular high temperature gas-cooled reactor. Figure 1As shown, the pebble bed modular high temperature gas-cooled reactor comprises a first reactor 1, a second reactor 2, a first unloading temporary storage device 3, a second unloading temporary storage device 4 and a secondary unloading device 5. The first reactor 1 is connected to the first unloading temporary storage device 3 and the second unloading temporary storage device 4 through a first unloading pipeline 6, the second reactor 2 is connected to the first unloading temporary storage device 3 and the second unloading temporary storage device 4 through a second unloading pipeline 7, a first secondary unloading pipeline 8 is connected between the first unloading temporary storage device 3 and the secondary unloading device 5, and a second secondary unloading pipeline 9 is connected between the second unloading temporary storage device 4 and the secondary unloading device 5. A pair of control valves 10 are installed on the first secondary unloading pipeline 8, the second secondary unloading pipeline 9, the first unloading pipeline 6 and the second unloading pipeline 7. In order to realize automatic control and make the control logic provided in the pebble bed modular high temperature gas-cooled reactor unloading control method run automatically, the pebble bed modular high temperature gas-cooled reactor also includes a pressure monitoring device, a valve state monitoring device, an atmosphere detection device and a control module, wherein the pressure monitoring device is used to monitor the internal air pressure of the first unloading temporary storage device 3, the second unloading temporary storage device 4, the first reactor 1 and the second reactor 2 in real time. The valve state monitoring device is used to monitor the open or closed state of multiple control valves 10 in real time. The atmosphere detection device is used to monitor the internal gas atmosphere of the first unloading temporary storage device 3 and the second unloading temporary storage device 4 in real time. The control module is used to control the operation of the valve 10 according to the preset safety logic in the pebble bed modular high temperature gas-cooled reactor unloading control method provided in this embodiment.
[0032] The unloading control method of the pebble bed modular high temperature gas-cooled reactor includes:
[0033] When the first unloading pipeline 6 is opened and the first reactor 1 is unloading to the first unloading temporary storage device 3 or the second unloading temporary storage device 4, and when the second unloading pipeline 7 is opened and the second reactor 2 is unloading to the first unloading temporary storage device 3 or the second unloading temporary storage device 4, the first secondary unloading pipeline 8 and the second secondary unloading pipeline 9 are blocked. When the first secondary unloading pipeline 8 is opened and the first unloading temporary storage device 3 is unloading to the secondary unloading device 5, and when the second secondary unloading pipeline 9 is opened and the second unloading temporary storage device 4 is unloading to the secondary unloading device 5, the first unloading pipeline 6 and the second unloading pipeline 7 are blocked.
[0034] Specifically, when the first unloading pipeline 6 between the first reactor 1 and the first temporary unloading storage device 3 is opened, the first unloading pipeline 6 between the first reactor 1 and the second temporary unloading storage device 4 is blocked; when the first unloading pipeline 6 between the first reactor 1 and the second temporary unloading storage device 4 is opened, the first unloading pipeline 6 between the first reactor 1 and the first temporary unloading storage device 3 is blocked. When the second unloading pipeline 7 between the second reactor 2 and the first temporary unloading storage device 3 is opened, the second unloading pipeline 7 between the second temporary unloading storage device 4 and the second reactor 2 is blocked; when the second unloading pipeline 7 between the second reactor 2 and the second temporary unloading storage device 4 is opened, the second unloading pipeline 7 between the second temporary unloading storage device 4 and the first reactor 1 is blocked.
[0035] When the first unloading pipeline 6 between the first unloading temporary storage device 3 and the first reactor 1 is opened, the pressure difference between the first unloading temporary storage device 3 and the first reactor 1 is monitored in real time. When the pressure difference is greater than a preset threshold, the first unloading pipeline 6 between the first unloading temporary storage device 3 and the first reactor 1 is closed. When the first unloading pipeline 6 between the second unloading temporary storage device 4 and the first reactor 1 is opened, the pressure difference between the second unloading temporary storage device 4 and the first reactor 1 is monitored in real time. When the pressure difference is greater than a preset threshold, the first unloading pipeline 6 between the second unloading temporary storage device 4 and the first reactor 1 is closed. When the second unloading pipeline 7 between the first unloading temporary storage device 3 and the second reactor 2 is opened, the pressure difference between the first unloading temporary storage device 3 and the second reactor 2 is monitored in real time. When the pressure difference is greater than a preset threshold, the second unloading pipeline 7 between the first unloading temporary storage device 3 and the second reactor 2 is closed. When the second unloading pipeline 7 between the second unloading temporary storage device 4 and the second reactor 2 is opened, the pressure difference between the second unloading temporary storage device 4 and the second reactor 2 is monitored in real time, and when the pressure difference is greater than a preset threshold, the second unloading pipeline 7 between the second unloading temporary storage device 4 and the second reactor 2 is closed. In this embodiment, the preset threshold is 0.3MPa, and the pressure monitoring device monitors the pressure of the two unloading temporary storage devices and the pressure of the two reactors in real time, and sends the pressure difference between the two to the control module; when the difference is greater than 0.3MPa, the control module automatically locks the unloading pipeline in the open state to avoid the unloading process triggering the primary circuit pressure negative change rate protection.
[0036] Monitor the gas atmosphere in the first temporary unloading storage device 3 in real time. If it is a helium atmosphere, the first and second unloading pipelines 8 are prohibited from opening. If it is an air atmosphere, the first unloading pipeline 6 and the second unloading pipeline 7 are prohibited from opening. Monitor the gas atmosphere in the second temporary unloading storage device 4 in real time. If it is a helium atmosphere, the second and second unloading pipelines 9 are prohibited from opening. If it is an air atmosphere, the first unloading pipeline 6 and the second unloading pipeline 7 are prohibited from opening. When the atmosphere detection device detects that there is a helium atmosphere in a temporary unloading storage device and the device is connected to the outside world, the control module automatically locks the secondary unloading pipeline to prevent the negative change rate protection of the first circuit pressure from being triggered due to helium leakage. When the atmosphere detection device detects that there is an air atmosphere in a temporary unloading storage device and the device is connected to the reactor, the control module automatically locks the corresponding first unloading pipeline 6 or second unloading pipeline 7 to prevent helium gas leakage in the reactor.
[0037] Obviously, the above embodiments are merely examples for the purpose of clear explanation, and are not intended to limit the implementation methods. For those skilled in the art, other different forms of changes or modifications can be made based on the above description. It is not necessary and impossible to list all the implementation methods here. The obvious changes or modifications derived therefrom are still within the scope of protection of the invention.
Claims
1. A method for controlling the unloading of a pebble bed modular high temperature gas-cooled reactor, characterized in that: The pebble bed modular high temperature gas-cooled reactor comprises a first reactor (1), a second reactor (2), a first temporary unloading storage device (3), a second temporary unloading storage device (4) and a secondary unloading device (5); the first reactor (1) is connected to the first temporary unloading storage device (3) and the second temporary unloading storage device (4) via a first unloading pipeline (6); the second reactor (2) is connected to the first temporary unloading storage device (3) and the second temporary unloading storage device (4) via a second unloading pipeline (7); a first secondary unloading pipeline (8) is connected between the first temporary unloading storage device (3) and the secondary unloading device (5); and a second secondary unloading pipeline (9) is connected between the second temporary unloading storage device (4) and the secondary unloading device (5); The unloading control method comprises: When the first unloading pipeline (6) is opened and the first reactor (1) discharges material into the first unloading temporary storage device (3) or the second unloading temporary storage device (4), and / or when the second unloading pipeline (7) is opened and the second reactor (2) discharges material into the first unloading temporary storage device (3) or the second unloading temporary storage device (4), the first secondary unloading pipeline (8) and the second secondary unloading pipeline (9) are locked; When the first secondary unloading pipeline (8) is opened and the first unloading temporary storage device (3) discharges the secondary material to the secondary unloading device (5), and / or when the second secondary unloading pipeline (9) is opened and the second unloading temporary storage device (4) discharges the secondary material to the secondary unloading device (5), the first unloading pipeline (6) and the second unloading pipeline (7) are locked.
2. The method for controlling the unloading of a pebble bed modular high-temperature gas-cooled reactor according to claim 1, characterized in that: When the first discharge pipeline (6) between the first reactor (1) and the first discharge temporary storage device (3) is opened, the first discharge pipeline (6) between the first reactor (1) and the second discharge temporary storage device (4) is locked; When the first unloading pipeline (6) between the first reactor (1) and the second unloading temporary storage device (4) is opened, the first unloading pipeline (6) between the first reactor (1) and the first unloading temporary storage device (3) is locked.
3. The method for controlling the unloading of a pebble bed modular high temperature gas-cooled reactor according to claim 1, characterized in that: When the second unloading pipeline (7) between the second reactor (2) and the first unloading temporary storage device (3) is opened, the second unloading pipeline (7) between the second unloading temporary storage device (4) and the second reactor (2) is locked; When the second unloading pipeline (7) between the second reactor (2) and the second unloading temporary storage device (4) is opened, the second unloading pipeline (7) between the second unloading temporary storage device (4) and the first reactor (1) is locked.
4. The method for controlling the unloading of a pebble bed modular high temperature gas-cooled reactor according to any one of claims 1 to 3, characterized in that: When the first unloading pipeline (6) between the first unloading temporary storage device (3) and the first reactor (1) is opened, the pressure difference between the first unloading temporary storage device (3) and the first reactor (1) is monitored in real time, and when the pressure difference is greater than a preset threshold, the first unloading pipeline (6) between the first unloading temporary storage device (3) and the first reactor (1) is closed.
5. The method for controlling the unloading of a pebble bed modular high temperature gas-cooled reactor according to any one of claims 1 to 3, characterized in that: When the first unloading pipeline (6) between the second unloading temporary storage device (4) and the first reactor (1) is opened, the pressure difference between the second unloading temporary storage device (4) and the first reactor (1) is monitored in real time, and when the pressure difference is greater than a preset threshold, the first unloading pipeline (6) between the second unloading temporary storage device (4) and the first reactor (1) is closed.
6. The method for controlling the unloading of a pebble bed modular high temperature gas-cooled reactor according to any one of claims 1 to 3, characterized in that: When the second unloading pipeline (7) between the first unloading temporary storage device (3) and the second reactor (2) is opened, the pressure difference between the first unloading temporary storage device (3) and the second reactor (2) is monitored in real time, and when the pressure difference is greater than a preset threshold, the second unloading pipeline (7) between the first unloading temporary storage device (3) and the second reactor (2) is closed.
7. The method for controlling the unloading of a pebble bed modular high temperature gas-cooled reactor according to any one of claims 1 to 3, characterized in that: When the second unloading pipeline (7) between the second unloading temporary storage device (4) and the second reactor (2) is opened, the pressure difference between the second unloading temporary storage device (4) and the second reactor (2) is monitored in real time, and when the pressure difference is greater than a preset threshold, the second unloading pipeline (7) between the second unloading temporary storage device (4) and the second reactor (2) is closed.
8. The method for controlling the unloading of a pebble bed modular high temperature gas-cooled reactor according to any one of claims 1 to 3, characterized in that: The gas atmosphere in the first unloading temporary storage device (3) is monitored in real time. If it is a helium atmosphere, the first and second unloading pipelines (8) are prohibited from opening. If it is an air atmosphere, the first unloading pipeline (6) and the second unloading pipeline (7) are prohibited from opening.
9. The method for controlling the unloading of a pebble bed modular high temperature gas-cooled reactor according to any one of claims 1 to 3, characterized in that: The gas atmosphere in the second unloading temporary storage device (4) is monitored in real time. If it is a helium atmosphere, the second secondary unloading pipeline (9) is prohibited from opening. If it is an air atmosphere, the first unloading pipeline (6) and the second unloading pipeline (7) are prohibited from opening.
10. The method for controlling the unloading of a pebble bed modular high temperature gas-cooled reactor according to any one of claims 1 to 3, characterized in that: A pair of control valves are installed on each of the first secondary discharge pipeline (8), the second secondary discharge pipeline (9), the first discharge pipeline (6) and the second discharge pipeline (7).