Mobile coating unit for producing variable coated proppants with ai option configuration and method of use

By using mobile coating units at the well site to produce customized coated proppant, the problems of uneven material distribution and transportation and storage during hydraulic fracturing have been solved, enabling efficient and environmentally friendly downhole operations and improving the efficiency and economy of oil and gas well development.

CN119013372APending Publication Date: 2024-11-22AQUASMART ENTERPRISES LLC
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202280093367.5
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2022-01-20
Publication Date
2024-11-22

AI Technical Summary

Technical Problem

Existing technologies for hydraulic fracturing in oil and gas wells suffer from problems such as uneven material distribution, large land area required for transportation and storage, high risk of chemical spills, high logistics and loading/unloading costs, and inability to adapt to changes in downhole conditions in real time, resulting in low efficiency and waste of resources.

Method used

Customized coated proppant is produced at the well site using a mobile coating unit. The coating formula is dynamically adjusted according to downhole conditions through a real-time data-driven system, reducing transportation and storage requirements and improving material utilization efficiency and downhole adaptability.

Benefits of technology

This achieves efficient and uniform distribution of materials, reduces transportation and storage costs, decreases the amount of chemicals used, improves the flexibility and efficiency of downhole operations, and reduces waste and environmental impact.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119013372A_ABST
    Figure CN119013372A_ABST
Patent Text Reader

Abstract

A method and mobile coating unit for improving the performance of a hydraulic fracturing process in the field of petroleum production wherein a modifiable coated proppant for fracturing fluids is produced on a wellsite. Various types of coated proppants may be produced based on real-time downhole information obtained and utilized at the wellsite. The mobile coating unit includes: a platform having a proximal end and a distal end; a liquid additive dispenser supported by the platform; a volumetric powder dispenser supported by the platform; a coating mixer supported by the platform; and a control unit supported by the platform and operably connected to the liquid additive dispenser, the volumetric powder dispenser and the coating mixer and controlling the movement of the control unit to produce a first coated proppant product using the first formulation programmed into the control unit and transfer the first coated proppant to the blender.
Need to check novelty before this filing date? Find Prior Art

Description

[0001] CROSS-REFERENCE TO RELATED APPLICATIONS

[0002] This application claims the benefit of U.S. Provisional Patent Application No. 63 / 139,913, filed on January 21, 2021, which is incorporated herein by reference in its entirety. Technical Field

[0003] The present invention relates to oil and gas field and oil and gas well development, and more particularly, to new systems and methods for providing coated proppant at a well site for hydraulic fracturing and propping fractures in oil and gas containing formations. Background Art

[0004] There have been over a hundred years of extensive engineering and chemical improvements in oil and gas well development, designed to address the various problems that may occur between wells and within a single well. There is a great deal of variability between individual wells. This variability is based on, but not limited to, the following factors: the location of the well, which basin; the type of well, which formation; the type of water used, fresh water, produced water, mixed water; the depth of the well; the temperature of the well; the typical treatment pressure of the well; the pore pressure gradient; and the ease with which the formation accepts proppant.

[0005] There is also great variability within a single well. This variability is based on, but not limited to, the following factors: the heel stage of the completion, which is closer to the vertical portion of the well and generally has lower treatment pressures and less distance for proppant delivery;

[0006] and the toe stage of the completion well, which is remote from the vertical portion of the well and typically has higher treatment pressures and much greater distances for delivering proppant (ie, approximately 3 miles or more).

[0007] There can also be great variability depending on the well completion design. This variability is based on, but is not limited to, factors such as: barrels of water per foot; pounds of sand per foot; stage length in linear feet; number and spacing of clusters; pump rate in barrels per minute; sand loading in pounds per gallon; sand pump rate; and friction reducer dosage in gallons or pounds per thousand gallons.

[0008] Various methods have been developed for increasing the production of wells associated with oil and gas reservoirs. Different types of processes may require various treatments. Generally, well production can be improved by fracturing the formation. Fracturing is usually performed by pumping a fluid filled with a large proportion of water into the formation and pressurizing the fluid so as to apply large surface forces to portions of the formation. These large surface forces induce stresses and, due to the large areas involved, can produce extremely high forces and stresses in the rock formation.

[0009] As a result, the rock formations tend to break up, increasing porosity and providing space for the produced oil and gas to pass through the formation toward the wellbore for extraction. In addition, various techniques exist to further improve the fracture network, such as acidizing. However, as previously implied, the process is not simple, and incorporating various materials into the mix requires a great deal of time, money, energy, and other resources. Nevertheless, these mixtures are critical to the task of delivering proppant into the fractures to prop open the formation and provide a path for the oil and gas to migrate back into the wellbore.

[0010] It would be an advancement in the art if these resources could be used more efficiently through the use of improved compositions and methods for incorporating materials into mixtures.

[0011] In addition, hydraulic fracturing has a fairly complex process to add the various components to the fracturing fluid. Not only must proppant be added, but also various other chemicals must be added. During the fracturing process, the materials need to be stirred to produce the working fluid or "slurry" for fracturing. This stirring requires quite large equipment, thereby occupying a significant floor space throughout the well site.

[0012] In addition, such equipment requires manpower and maintenance of numerous receiving and storage areas. These are required for the various component products that will eventually be added to the working fluid. All of these processes for mixing auxiliary materials into the fluid will result in time delays. For example, it may prove difficult to incorporate powdered materials.

[0013] Especially for small particles, surface tension tends to cause these materials to float on the surface of the liquid, and substantial mixing and associated time are required. Many solids must be pre-mixed in oils, emulsions, etc., increasing the impact of any spillage. At the same time, adding chemicals to the fracturing flow necessarily results in uneven distribution of the additive. For example, when a component is added to the fracturing flow, the component is in very high concentration near the wellhead. At the same time, the newly added component is completely absent elsewhere. Therefore, the ability to distribute the material thoroughly or even well throughout the incoming fluid has proven to be difficult.

[0014] Similarly, transporting the individual component chemicals and materials to the well site requires multiple vehicles dedicated to different types of materials and stages. For example, some materials are fluids, some are solids, some use water solvents, some use petroleum-based solvents, and these materials must be handled, transported, and handled in different ways with their own appropriate storage, handling, and transportation equipment.

[0015] Various complaints are encountered with large quantities of hydrocarbons, such as various emulsions, chemical additives, etc., including materials such as diesel fuel that are often used. With such liquid chemicals on site, there is an increased risk of surface contamination due to chemical spills of such materials. Even when contained in smaller containers, these materials are at risk of spills carried by water, wind and other weather, as well as the possibility of spills during transportation, loading and unloading or feeding and mixing.

[0016] At the same time, the operational footprint required for storage, mixing systems, receiving, shipping, etc. increases the total operational footprint of the well site. In addition, the cost of money, labor and time for the process of receiving, preparing, storing, handling and finally mixing the materials that will be added to the fracturing fluid is considerable.

[0017] It would therefore be an advance in the art to provide a system and method that would eliminate many of the handling, equipment, floor space, transportation, and other problems inherent in existing material and mixing systems for servicing fracturing fluids.

[0018] One approach for addressing many of these issues is to use coated proppant products, several of which are available on the market. Typically, these coated proppant products are resin-coated proppants that can have several different types of functionality. These coated proppant products are typically produced off-site and then transported to their field of use. This forces the consumer to select which product functionality they want before using the product, and once these products are coated, there is no opportunity to change their functionality. As a result, the consumer or operator company may try to predetermine what conditions these products are most likely to encounter at a particular well site, and try to select the necessary functionality to address all aspects of the predetermined range of variability. Another option under this system is to select a product that addresses the worst case scenario, which can result in the use of an over-engineered product, which wastes the ingredients of the active input and drives up the cost of using such a product.

[0019] Coating the proppant product off-site adds certain logistics and handling costs, because the most vulnerable time of the coated proppant product is during the logistics and handling process. The proppant is usually transported to the well site by pneumatic trucks or some kind of box system. The proppant delivered by pneumatic trucks is unloaded into a sand silo on site, which feeds the blender. The proppant delivered by box is unloaded directly into the blender by a conveyor belt. Generally, all proppant must be kept dry before being introduced into the blender. The coated proppant product will activate when it comes into contact with moisture, which will destroy some products and cause on-site deterioration with other products when trying to load the blender.

[0020] Given the various factors involved, it is unlikely that coated proppants produced off-site will effectively and efficiently provide the necessary performance characteristics in the face of a specific situation that cannot be changed or adapted to address.

[0021] Therefore, it would be an advancement in the art to provide a system and method of use that is physically and electrically connected to existing hydraulic fracturing fleet equipment, driven by real-time data from a field data vehicle, and utilizes information from the data vehicle to produce an optimal coated proppant product. Furthermore, it would be an advancement in the art to provide a system and method that can produce a variety of coated proppant products to address specific real-time downhole conditions at a wellsite. Still further, the system can be tuned to provide coated proppant at substantially the same rate as associated downhole conditions change.

[0022] It would be a substantial advance in the art to provide a system and method that would optimize the use of various materials used as additives in fracturing fluids and provide real-time adjustments to the coated proppant product, and therefore the fracturing fluid, based on current well conditions. Furthermore, this could be done in the field just prior to adding the newly produced coated proppant product to the mixer. Summary of the invention

[0023] In view of the foregoing, in accordance with the present invention as embodied and broadly described herein, a method, apparatus, and composition are disclosed in certain embodiments in accordance with the present invention.

[0024] Not surprisingly, oil and gas wells often cost millions of dollars. As a result, an inordinate amount of time and planning is invested in the "completion" process of an oil and gas well. The completion process can involve multiple processes, including hydraulic fracturing, or fracking. Hydraulic fracturing is a highly planned process. The plan used during a specific hydraulic fracturing process for a given well may be referred to as a "frac design" or "frac plan."

[0025] The development of a fracturing design is a detailed and time consuming process. Extensive analysis is performed on existing wells within a reasonable geographic area. Comparisons and / or contrasts can be narrowed by basin and formation so that information on what has worked previously or has not worked can be utilized to maximize the return on investment that the "operator" company can achieve from each well.

[0026] Completion and reservoir engineers evaluate the available data and perform the necessary analysis to develop a fracturing design for a given well. The fracturing design typically divides the completion process into separate "stages," and modern fracturing designs may include sixty or more such stages. Each stage will have a PAD phase that is only liquid. The purpose of the PAD is to initiate fractures. After the PAD, the completion crew begins adding sand and / or proppant to the liquid. The amount of sand is slowly increased according to the schedule followed until the desired amount of sand for that stage has been placed. To complete the stage, a "flush" is usually pumped. A flush is simply a liquid and is primarily used to remove any excess sand from the wellbore.

[0027] A kind of mobile coating unit or on-site intelligent coating system can produce customized coated proppant at well site.Usually, coated proppant includes substrate and the coating of substrate.Substrate can be formed by sand, rock product, pottery sand, gravel, fiber or other similar materials.When used in this article, any mention of proppant or sand generally refers to any or all of these used according to the present invention.These coated proppant can comprise one or more of the following items in powder or liquid form: friction reducer, surfactant, scale inhibitor, biocide, tackifier (such as but not limited to guar gum (guar), HEC, polysaccharide, xanthan gum), crushing agent, cross-linking agent, buffer, clay stabilizer etc.

[0028] The on-site aspect of such a mobile coating unit is highly advantageous, even necessary, due to the logistical constraints and costs to the consumer associated with coating proppant products at any off-site location. Furthermore, the ability to vary coatings based on real-time downhole conditions experienced during the fracturing process in order to create the most efficient and productive completion is of great value. Since many fracturing inputs depend on sand volume, the introduction of these and sand volume driven coatings allows for greater efficiency and better overall control. For some large operators using green sand mined near the fracturing site, a robust and reliable system that can be efficiently introduced into the sand silo feed or green sand feed creates value and simplicity that did not exist before.

[0029] A mobile coating unit for producing customized coated proppants at a wellsite or fracturing site can be inserted between a sand source and a mixer at the wellsite. The mobile coating unit can receive data input and operating instructions from either or both of the wellsite fracturing truck or the mobile coating unit's PLC control unit. Such input can provide a throughput rate that the system can use to determine its input rate to produce the desired coated proppants. The throughput rate is variable, as are the inputs and input rates. The mobile coating unit can accommodate both wet and dry proppants, which enables previously unavailable flexibility when considering proppant supply options.

[0030] Including multiple necessary fracturing inputs in a manner balanced by proppant volume and in response to real-time conditions ensures that only necessary chemicals are introduced downhole. For example, an operator company using the mobile coating unit and operating methods described herein can reduce the volume of chemical fluids placed downhole by more than five million pounds over the course of a year. The ESG (environmental, social and governance) benefits of this reduction can accumulate rapidly. The economic benefits are significant. All hydraulic fracturing operations may include tumultuous peaks and quiet valleys. The coating methods described herein can cope with these fluctuations, but the ability to customize the coated proppant during operation adds another level of specificity and efficiency to control downhole conditions, thereby minimizing waste and maximizing well health.

[0031] Utilizing a mobile coating unit as described herein provides many benefits. Since the coated proppant is produced at the well site, there are no additional logistics or transportation costs and handling issues associated with coated proppant products produced off-site. This can also reduce traffic on the well site and usually on the road, because the chemicals or additives used by the mobile coating unit can be contained in the mobile coating unit or connected to the mobile coating unit. The mobile coating unit can use proppant or sand from the well site, which allows the operator company to use sand from any mine they choose, and eliminates any need to transport raw sand from one mine to another for coating, and eliminates the need to establish a coating operation at each sand mine. The transportation and logistics costs associated with moving sand may be significant, so the mobile coating unit on the well site can almost eliminate these costs. The mobile coating unit can mainly use powder additives, which can almost eliminate the use of liquids and the space, handling and efficiency issues associated therewith. The coated proppant from the mobile coating unit can carry more precise doses of the required chemicals, which can reduce waste and reduce the total amount of chemicals entering the well. The mobile coating unit can run the desired fracturing design and tweak the process as available real-time data informs the coating process. The ability to modify or completely change the coating formula for the coated proppant based on real-time downhole conditions eliminates the need for a "one coating fits all" option and can help induce the best completion phase for the well. Moreover, from a licensing and procedural perspective, using a mobile coating unit is relatively easy. A fixed-location coating facility may take 6 to 12 months, cost thousands of dollars, and require the completion of multiple in-depth studies. For the period of time that the mobile coating unit is on site, adding a mobile coating unit may simply require and supplement an existing license from the operator's company or manufacturer.

[0032] In one embodiment, a method for producing a coated proppant may include: providing a mobile coating unit, wherein the mobile coating unit includes a platform having a proximal end and a distal end, a liquid additive dispenser supported by the platform, a volumetric powder dispenser supported by the platform, a coating mixer supported by the platform, and a control unit supported by the platform and operably connected to the liquid additive dispenser, the volumetric powder dispenser, and the coating mixer; positioning the mobile coating unit on a well site; at the proximal end of the platform, feeding proppant to the mobile coating unit; coating the proppant according to a first recipe programmed into the control unit to produce a first coated proppant; at the distal end of the platform, dispensing the first coated proppant from the mobile coating unit the first coated proppant; transferring the first coated proppant to a mixer located at the well site; adding the first coated proppant to a first fracturing fluid; pumping the first fracturing fluid into a wellhead in less than five (5) days from the completion of applying the first coated proppant; applying the proppant according to a second formula programmed into a control unit to produce a second coated proppant; dispensing the second coated proppant from a mobile coating unit at a remote end of the platform; transferring the second coated proppant to a mixer located at the well site; adding the second coated proppant to a second fracturing fluid; and, pumping the second fracturing fluid into the wellhead in less than five (5) days from the completion of applying the second coated proppant.

[0033] In one embodiment, a method for coating a proppant may include: providing a mobile coating unit, wherein the mobile coating unit includes a platform having a proximal end and a distal end, one or more liquid additive dispensers supported by the platform, one or more volumetric powder dispensers supported by the platform, one or more coating mixers supported by the platform, and a control unit supported by the platform and operably connected to the liquid additive dispensers, the volumetric powder dispensers, and the coating mixer; feeding proppant to the mobile coating unit at the proximal end of the platform; coating a first portion of the proppant according to a first recipe programmed into the control unit to produce a first coated proppant; dispensing the first coated proppant from the mobile coating unit at the distal end of the platform; coating a second portion of the proppant according to a second recipe programmed into the control unit to produce a second coated proppant; and dispensing the second coated proppant from the mobile coating unit at the distal end of the platform within less than twelve (12) hours after completing coating of the first coated proppant.

[0034] Also, the method may further include: after completing the coating of the first coated proppant, transferring the first coated proppant to a mixer located on the well site; adding the first coated proppant to the first fracturing fluid; pumping the first fracturing fluid into the wellhead within less than 48 hours from the completion of coating the first coated proppant; after completing the coating of the second coated proppant, transferring the second coated proppant to a mixer located on the well site; adding the second coated proppant to the second fracturing fluid; and pumping the second fracturing fluid into the wellhead within less than 48 hours from the completion of coating the second coated proppant.

[0035] In one embodiment, a method for controlling a proppant coating process at a well site may include: providing a fracturing truck at the well site, wherein the fracturing truck includes a fracturing control system that monitors real-time downhole conditions in the well and is programmed with a fracturing plan for the well site; providing a mobile coating unit at the well site, wherein the mobile coating unit is operably connected to the fracturing control system and includes a platform having a proximal end and a distal end, one or more liquid additive dispensers supported by the platform, one or more volumetric powder dispensers supported by the platform, one or more coating mixers supported by the platform, and a mobile coating unit supported by the platform and operably connected to the liquid additive dispenser; The invention relates to a method of controlling a coating operation of the mobile coating unit and a control unit for a proppant dispenser, a volumetric powder dispenser and a coating mixer; positioning the mobile coating unit on the well site between the proppant source and the mixer, with the proximal end of the platform facing the proppant source and the distal end of the platform facing the mixer; controlling the coating operation of the mobile coating unit based on real-time downhole conditions monitored by the fracturing control system, wherein the fracturing control system selects a first formulation communicated to the control unit of the mobile coating unit and produces a first coated proppant; and adjusting the coating operation of the mobile coating unit based on real-time downhole conditions monitored by the fracturing control system, wherein the fracturing control system selects a second formulation communicated to the control unit of the mobile coating unit and produces a second coated proppant. BRIEF DESCRIPTION OF THE DRAWINGS

[0036] The foregoing features of the present invention will become more apparent from the following description and appended claims, taken in conjunction with the accompanying drawings. Understanding that these drawings depict only typical embodiments of the invention and are therefore not to be considered limiting of its scope, the invention will be described with additional specificity and detail through the use of the accompanying drawings, in which:

[0037] Figure 1 It is a schematic diagram of a typical well site;

[0038] Figure 2 is a schematic diagram of a well site using a mobile coating unit according to the present invention;

[0039] Figure 3is a schematic top plan view of a mobile coating unit according to the present invention;

[0040] Figure 4 is a schematic side view of a mobile coating unit according to the present invention, wherein some dotted lines are used to better illustrate other parts of the mobile coating unit;

[0041] Figure 5a is a schematic diagram showing a testing procedure for evaluating the erosion driven weight loss of certain proppants;

[0042] Figure 5b are graphs and tables showing the results of a testing procedure used to evaluate the erosion driven weight loss of certain proppants;

[0043] Figure 6a is a schematic diagram showing a testing process for evaluating the pressure changes of certain proppants;

[0044] Figure 6b is a graph showing the results of a testing procedure for evaluating the pressure variation of certain proppants;

[0045] Figure 6c is a graph showing the results of a testing procedure for evaluating the pressure variation of certain proppants;

[0046] Figure 6d is a graph showing the results of a testing procedure used to evaluate the pressure variation of certain proppants; and

[0047] Figure 7 is a flow chart illustrating a method of use according to the present invention. DETAILED DESCRIPTION

[0048] It will be readily appreciated that the components of the present invention, as generally described and illustrated in the drawings herein, may be arranged and designed in a variety of different configurations. Therefore, the following more detailed description of the embodiments of the systems and methods of the present invention, as represented in the drawings, is not intended to limit the scope of the claimed invention, but is merely representative of various embodiments of the present invention. The illustrated embodiments of the present invention will be best understood by reference to the drawings, wherein like components are represented by like reference numerals throughout.

[0049] Oil and gas wells may have various equipment arranged at the well site in various configurations. Such configurations may vary from well site to well site and depend on the type of well, the topography of the well site, the equipment and materials required, and other similar factors.

[0050] refer to Figure 1, a conventional or typical wellsite configuration 10 is depicted in a schematic diagram. The wellsite configuration 10 may include silos or boxes for sand storage 12 or proppant storage 12. Sand is a typical proppant material, but any material suitable for use as a proppant may be used. Suitable proppants or substrates may include sand (dry or wet, with a moisture content ranging from 0% to 15%), ceramic proppants, resin-coated proppants, fibers, and the like.

[0051] The sand conveyor 14 may be operably connected at one end to a silo of the sand storage 12 and at the other end to the mixer 20 by any suitable means capable of transferring sand from the sand storage 12 to the mixer 20. The sand conveyor 14 may be a belt-scale that can weigh the sand conveyed from the sand storage 12 to the mixer 20.

[0052] The mixer 20 may be used to mix and prepare sand and fracturing fluid to be delivered to the manifold 22. The mixer 20 may be operably connected to any materials needed or used in the process of preparing the fracturing fluid to be delivered to the wellhead 26. For example, but not by way of limitation, the mixer 20 may be operably connected to a suitable supply of water 18 (fresh water, produced water, or blending water), acid 16, and / or other chemicals 17.

[0053] The manifold 22 may be used to distribute or pump the fracturing fluid to the wellhead 26. The manifold 22 may be a fracturing manifold 22 that may include an arrangement of flow fittings and valves installed downstream of a fracturing pump output header and upstream of each fracturing tree being serviced. Any manifold 22 suitable for the intended purpose may be used in an appropriate configuration.

[0054] The fracturing vehicle 24 or fracturing truck 24 can be used to monitor, display and control the hydraulic fracturing equipment and process. The fracturing vehicle 24 can be operably connected to all other equipment used in the hydraulic fracturing process, including, but not limited to, the sand storage 12, the sand conveyor 14, the mixer 20 and its accompanying water 18, acid 16 and chemical 17 materials, and the manifold 22. The fracturing vehicle 24 can include a monitoring system, a display system and a control system so that engineers and / or crew members can monitor and control the fracturing process from the fracturing vehicle 24. The fracturing vehicle 24 can include a fracturing control system that can monitor, display and control the hydraulic fracturing equipment and process at the well site.

[0055] refer to Figure 2, the mobile coating unit 30 may be disposed between the sand storage 12 and the mixer 20. The mobile coating unit may be positioned along or in the path from the sand storage 12 to the mixer 20 in such a manner that the sand is conveyed from the sand storage 12 through the mobile coating unit 30 and then to the mixer 20 by the sand conveyor 14. The mobile coating unit 30 may be positioned at a suitable angle according to the available space at the well site. The setting of the mobile coating unit 30 may be adjusted according to the needs of a specific well site.

[0056] The mobile coating unit 30 can be described as having a proximal end and a distal end. Sand or proppant from the sand storage 12 can be conveyed along the sand conveyor 14 to the proximal end of the mobile coating unit 30, where the sand or proppant can be deposited into a hopper 34 on the mobile coating unit 30. The sand then goes through a coating process and exits the mobile coating unit 30 at the distal end of the mobile coating unit 30. When the coated proppant or coated sand exits the distal end of the mobile coating unit, the coated proppant can be deposited into the mixer 20, or the sand conveyor 14 can be used to convey the coated proppant to the mixer 20.

[0057] The mobile coating unit 30 can be operably connected to the coating additive 28. The coating additive 28 can include any suitable type of additive (i.e., friction reducer, biocide, breaker, viscosity enhancer, antiscalant, etc.), and the additive can be in any desired form (i.e., liquid or powder). The coating additive 28 is connected to an appropriate structure on the mobile coating unit 30. For example, the liquid coating additive can be stored in any suitable storage mechanism, including but not limited to a hopper, a tank, a tote, a chemical transport vehicle, or a silo and connected to the liquid additive dispenser 40 or the sprayer 40. Similarly, the powder coating additive can be stored in any suitable storage mechanism, including but not limited to a hopper, a bulk bag, a pneumatic tank, a chemical transport vehicle, or a silo and connected to a volumetric powder dispenser 60 that dispenses by volume or weight.

[0058] refer to Figure 3 and Figure 4, the mobile coating unit 30 may include multiple structures and equipment to provide the ability to coat the proppant or sand at the well site. A suitable platform 70 or trailer 70 may be used to support and transport the equipment including the mobile coating unit 30. The platform 70 may be made of any suitable material and may have any suitable size and dimensions, as long as it can properly support the mobile coating unit 30 and its associated equipment and is of course movable and transportable. The platform may be appropriately connected to a chassis with wheels 72, or a skid (not shown) so that the mobile coating unit 30 can be transported to the well site. The platform 70 may include one or more supports 74, which may provide additional stability to the mobile coating unit 30 when the mobile coating unit 30 is running at the well site, but which may be removable or retractable when the mobile coating unit 30 is transported. Being mounted on a skid or trailer means that the mobile coating unit 30 may be located at the site of a well or sand mine, thereby providing flexibility to balance economic considerations, space availability, and throughput requirements.

[0059] Typically, the mobile coating unit 30 includes at least a PLC control unit 32, a liquid additive dispenser 40, a volumetric powder dispenser 60, and a coating agitator 50 or a coating mixer 50. Other structures may be included in the mobile coating unit 30, or may be at the well site and may be used by the mobile coating unit 30. The structures associated with a given mobile coating unit 30 may be distributed in any effective manner to allow sufficient space to accommodate all components and to enable efficient processing by separate unit structures. If desired, the unit structures may be independent and / or protected from weather influences.

[0060] For example, an inbound sand storage unit 34 or loading hopper 34 may store sand received from the sand storage 12 at the well site prior to use of the sand in the mobile coating unit 30. Similarly, an outbound sand conveyor 36 may be used to convey the resulting coated proppant or coated sand from the mobile coating unit 30 to the mixer 20, or to another section of the sand conveyor 14, and then to the mixer 20.

[0061] The mobile coating unit 30 may be operably connected to one or more powder additive silos 62 where the powder additive is delivered to the mobile coating unit 30 via one or more powder additive conveyors 64. The primary purpose of the powder additive silos 62 may be to keep the volumetric powder dispenser 60 full of available powder additive.

[0062] The mobile coating unit 30 may include a dryer at nearly any stage to dry the proppant or remove excess water from the proppant. The mobile coating unit 30 may be configured to accept and successfully coat a variety of proppants, such as wet sand, dry sand, ceramic proppants, resin-coated proppants, wet fiber, dry fiber, etc. The mobile coating unit 30 may include some or all of these equipment components, depending on the desired design and intended functionality.

[0063] A typical process for applying sand, ceramic, resin, fiber or another proppant at a well site using the mobile coating unit 30 can be described as follows. First, it should be understood that the PLC control unit 32 is operably connected to other equipment components of the mobile coating unit 30 in a manner that allows the PLC control unit 32 to monitor and control the coating process of the mobile coating unit. This operative connection can be described as including electronic and physical connections, because the PLC control unit 32 can monitor and control the amount of proppant moving through the mobile coating unit 30, and control the amount and time of the coating additive 28 used. The PLC control unit 32 can be pre-programmed with any desired formula or formulation for the coated proppant, and can provide the formula or formulation and process sequence required for producing the desired coated proppant product. The PLC control unit can also be started by independent operation, triggered by input from an external source (such as a fracturing truck 24), or remotely controlled.

[0064] It should also be understood that the PLC control unit 32 can be operably connected to the control system of the fracturing truck 24 at the well site, so that engineers in the fracturing truck 24 or those engineers working remotely for monitoring and control can control the hydraulic fracturing process typically associated with the well site (i.e., monitoring and controlling the sand conveyor 14, the mixer 20, the manifold 22, etc.), as well as controlling the coating process on the mobile coating unit 30 (i.e., one or more liquid additive dispensers 40, one or more volumetric powder dispensers 60, the coating mixer 50, etc.).

[0065] The PLC control unit 32 may include one or more programs that the control unit 32 uses to control the mobile coating unit 30 and produce the desired coated proppant. These programs can be described as formulas or formulations for producing the desired coated proppant. The formula or formulation can provide a very wide range of coated proppant that can be produced by the mobile coating unit 30, which is limited only by the number of additives 28 available to the unit 30. For example and not as a limitation, the mobile coating unit 30 can be used to produce coated proppant with only liquid coating or only powder coating or multiples and combinations of any type of coating. The formula can also be adjusted according to the proppant used (dry sand, wet sand, fiber, etc.). Moreover, different formulas or formulations can be utilized during different stages of the hydraulic fracturing process.

[0066] The PLC control unit 32 on the mobile coating unit 30 is a monitor and controller of the coating sand process. The PLC control unit can follow a pre-programmed formulation driven by a belt scale, where sand is moved from a loading hopper 34 or surge hopper 34 on the mobile coating unit 30 into the coating section of the mobile coating unit. Based on this weight, the PLC control unit 32 instructs all other inputs to the feeders (i.e., one or more liquid additive dispensers 40 and one or more volumetric powder dispensers 60) how much additive to dispense, and the PLC control unit can do this in real time at the well site. The engineer or user can select the coated sand from the pre-programmed options, or the engineer can change the formulation by adding one or more separate inputs. For example, the system can be programmed to appropriately add a tackifier if the polymer loading is increased.

[0067] The coating section of the mobile coating unit 30 can be used as a continuous flow mechanism where the coated proppant product can exit the coating section of the unit 30 and proceed on a conveyor belt that is already part of any standard, current well site configuration toward the blender 20. The operating specifications of the mobile coating unit 30 can be adjusted to accommodate the desired throughput.

[0068] The mobile coating unit 30 may be part of a "fracking fleet" that will serve the wells of a single operator company. The operator company may have the ability to utilize wet sand or dry sand, but generally cannot utilize both. The operator company may have a philosophical inclination or preference for wet sand or dry sand. The pre-programmed formulation on the mobile coating unit 30 may take into account the condition of the sand, whether it is wet or dry. Also, any type of formulation can utilize both liquid and / or powder additives as needed. Although the mobile coating unit 30 may be able to adapt to wet and / or dry proppants, it can be programmed to utilize one or the other. Although unlikely, the mobile coating unit 30 can be constructed and programmed to adapt to wet and / or dry proppants at a given well site. Similarly, if necessary, the mobile coating unit 30 can be constructed and programmed to adapt to or use fresh water and / or produced water or a mixture thereof at a given well site. For example, the liquid additive dispenser 40 can be configured to use fresh water and / or produced water as part of a liquid additive (such as a tackifier).

[0069] Sometimes, the mobile coating unit 30 may not process or coat the proppant at all as it passes through the mobile coating unit 30. For example, if it is only desired to transport proppant or sand from the sand storage 12 to the mixer 20, the mobile coating unit 30 may effectively function as a conveyor of proppant without adding any additives 28.

[0070] Any suitable proppant, such as sand or fiber, may be deposited in a sand storage unit 34 or hopper 34 located proximal to the mobile coating unit 30. The proppant may then be conveyed or moved through a liquid additive dispenser 40 or sprayer 40. The hopper 34 may include a conveyor belt with a scale that moves the sand at a specific rate and volume into the coating mixer 50. Before the sand is deposited into the coating mixer 50, the sand is exposed to the liquid additive, which is sprayed onto the sand as it falls into the coating mixer 50.

[0071] Typically, the liquid additive dispenser 40 will include a sprayer that sprays a predetermined amount of a selected liquid additive onto the proppant as the proppant advances through the liquid additive dispenser 40 and / or as the proppant falls into the coating mixer 50. Any device suitable for performing this function as part of the mobile coating unit 30 at the well site may be used accordingly. For example, produced water may be used as part of a viscosity enhancer mixture sprayed onto the proppant, or for any other suitable purpose. The liquid additive dispenser 40 may include a temperature controller to maintain the liquid additive at a desired temperature. The temperature control box may be used to produce a uniform blend of various chemical fluids and evenly distribute these fluids through an atomizing outlet system to optimally introduce the fluids into the mixing process. The PLC control unit 32 may monitor and / or control factors required to provide the desired liquid coating proppant that will leave the liquid additive dispenser 40. For example, the PLC control unit 32 may monitor the amount of sand entering the liquid additive dispenser 40 and the rate of entry of the proppant to determine how much liquid additive needs to be dispensed or sprayed onto the proppant. Also, one or more liquid additives may be sprayed onto the proppant, as determined by the PLC control unit 32. The liquid additive dispenser 40 may be generally described as a component that dispenses or sprays the liquid additive onto the proppant. The equipment used to store and / or mix the liquid additives may or may not be part of the liquid additive dispenser 40 itself or part of the mobile coating unit 30. For example, a truck may be used to provide one or more liquid additives to the liquid additive dispenser 40, or the liquid additive dispenser 40 may be operably connected to a source of liquid additives (such as friction reducers, etc.) already at the well site.

[0072] As the proppant leaves the liquid additive dispenser 40, the proppant is typically deposited into the coating mixer 50. There may be approximately 7 to 10 seconds before the desired powder additive is dispensed into the coating mixer 50 by the volumetric powder dispenser 60. The type of powder additive and the amount dispensed are predetermined by the recipe or formulation selected by the engineer and controlled by the PLC control unit 32. The mobile coating unit 30 may include one or more volumetric powder dispensers 60. All ingredients are coated in the coating mixer 50 for a predetermined residence time. A typical residence time is approximately fifteen (15) seconds. The resulting coated proppant may then be delivered to the mixer 20 by the outbound sand conveyor 36.

[0073] The volumetric powder dispenser 60 can be manufactured to handle a variety of mesh sizes, and the powder mixer uniformly mixes various dry powder additives to produce a fine, proprietary powder mixture that is introduced into the coating process via a time-activated dispensing unit.

[0074] The volumetric powder dispenser 60 can be kept full by a powder additive silo 62 and a powder additive conveyor 64 used only for this purpose. The powder additive can be obtained from the powder additive silo 62 or any other suitable container. The powder additive can be transported to the volumetric powder dispenser 60 by an operably connected powder additive conveyor 64 to transport the powder additive from the powder additive silo 62 to the dispenser 60. The dispenser 60 can add the powder additive to the proppant in any suitable manner (including but not limited to pouring, spraying, shaking, etc.). One or more powder additives can be added to the proppant by the dispenser 60 in the manner described. The PLC control unit 32 can monitor and / or control the factors required for providing the desired powder-coated proppant that will leave the coating mixer 50. For example, the PLC control unit 32 can monitor the amount of sand entering the coating mixer 50 and the entry rate of the proppant to determine how much powder additive needs to be distributed or added to the proppant. Similarly, the PLC control unit 32 can monitor and control the amount of powder additive moved from the powder additive silo 62 to the dispenser 60, for example, by using a powder additive conveyor 64 of the belt scale type. The volumetric powder dispenser 60 can be described primarily as a component that dispenses the powder additive onto the proppant. The equipment for storing and / or mixing the powder additive may or may not be part of the volumetric powder dispenser 60 itself or part of the mobile coating unit 30. For example, a truck or box may be used to provide one or more powder additives to the volumetric powder dispenser 60, or the volumetric powder dispenser 60 may be operably connected to a source of powder additives already at the well site.

[0075] Coating mixer 50 can be any equipment suitable for mixing or stirring the coated proppant mixture, for example, coating mixer 50 can be described as a twin shaft mixer, or a twin shaft ribbon mixer, or a ribbon mixer with a blade attached to the ribbon at appropriate intervals, etc. Coating mixer 50 can be used for surface activation process (surface activation process) and surface layering process. Coating mixer can have standard ribbons, as usually present in similar stirring units, or coating mixer can be different due to customized increased blades, and the increased blades are positioned at specific positions to enhance both performance and efficacy. Any coating mixer 50 that can perform the desired function (mixing or stirring the coated proppant mixture) can be used.

[0076] Typically, the ingredients or components of the coated proppant product may spend about 15 seconds, which may be described as a residence time, in the mixer 50 before the coated proppant product is delivered to the blender 20. The residence time may be adjusted based on the additives 28 used to produce the coated proppant, the needs of the well site, and / or similar factors. The residence time may be in the range of about 5 seconds to about 5 minutes.

[0077] After the coated proppant product is completed and leaves the coating mixer 50, the time between the application of the proppant and the delivery of the coated proppant product to the wellhead 26 can vary significantly depending on certain factors and can include any time less than ten (10) days after the application of the proppant. This delivery time range can be adjusted based on the specific coated proppant product, the needs of the wellsite, the desire to address real-time situations, and / or similar factors. This delivery time range can also take into account work stoppages that may occur at the wellsite due to any number of reasons. For example, if the wellsite is operating as expected, the coated proppant product can be delivered to the wellhead in less than 1 minute of the proppant application. If the wellsite experiences some delays or difficulties, the delivery time may be longer and depends greatly on when operations can be resumed.

[0078] The coating mixer 50 and other conveying structures associated with the mobile coating unit 30 can be designed and implemented to accommodate the relatively high real-time throughput requirements of the well site. A single mobile coating unit 30 can be configured to provide a throughput of approximately 450 tons / hour or in the range of approximately 250 tons / hour to 600 tons / hour. The mobile coating unit 30 can be configured in various ways and include various equipment components to meet the needs of a specific well site or the preferences of a specific operator company.

[0079] As a whole, the mobile coating unit 30 can be configured to provide a throughput of coated proppant similar to the throughput of a fixed-location plant, but without the significant cost and lack of flexibility of such a plant. A fixed-location plant may operate at less than optimal throughput rates, which means that the plant is not fully utilized. Operating a fixed-location plant at a higher than optimal throughput rate may stress the equipment, or may be simply impossible. The mobile coating unit 30 can have a range of possible throughputs. If additional throughput is required, two or more mobile coating units 30 can be added to the well site to obtain the desired throughput without significantly increasing the operational footprint at the well site.

[0080] In addition, a properly functional mobile coating unit 30 can be configured to occupy a significantly smaller space, which is highly advantageous at both the sand mine and the well site. A relatively small mobile unit is less likely to interrupt or hinder traffic and other operations at the sand mine or well site. The mobile coating unit 30 can have dimensions of approximately 40 feet by 9 feet, so that it can be strategically placed, moved a few feet without significantly interrupting the mobile coating unit 30, or even moved off-site if necessary.

[0081] Various alternative configurations can be used for the mobile coating unit 30, so that the functionality of the mobile coating unit can be increased as required for a given well site. For example, a dryer can be used at almost any stage of the coating process to dry the proppant or remove excess moisture. A dryer can be included so that the proppant is dried before entering the liquid additive dispenser 40 or before entering the coating mixer 50. This will be useful if the wet proppant at the well site needs to be dried before being used by the mobile coating unit 30, or if a very dry proppant is desired for a given recipe or formulation to produce a given coated proppant. Before the proppant continues to move during the coating process, a dryer can be included after the liquid additive dispenser 40 to dry the liquid coated proppant if necessary. If it is desired to dry the coated proppant during mixing, the dryer can be included in the coating mixer 50. Similarly, a dryer can be beneficial at various stages, depending on the proppant, wet sand, dry sand, fiber, etc. These examples are not provided as limiting examples, but as illustrative or various possible configurations.

[0082] In one embodiment, the mobile coating unit 30 can receive all necessary information from the wellsite fracturing truck 24. The mobile coating unit 30 can then use an integration algorithm to convert the received information in real time into the coating type and coating rate required for producing the customized coated proppant as needed at the wellsite. During the fracturing operation, the coating type and coating rate required for producing the customized coated proppant can be adjusted based on the real-time information received from the fracturing truck 24.

[0083] In one embodiment, the mobile coating unit 30 can know the distance to the sand storage and know how long it will take to receive the proppant or substrate based on a given rate and at what time the coating process will need to be initiated. The completed coated proppant product can come out of the mobile coating unit 30 and be fed directly into the mixer 20 at the well site and then function as usual. The added time to complete the customized coating process can be automatically calculated by the PLC control unit 32 and allow the fracturing truck 24 to know at which specific time the mixer 20 will begin agitation.

[0084] The proppant can arrive at the well site by any suitable mechanism, i.e., pneumatic trucks or boxes, and unload into sand storage silos / boxes on site. The proppant can leave these silos / boxes at an appropriate rate to keep the loading hopper 34 on the mobile coating unit 30 full. The proppant can enter the hopper on the mobile coating unit 30 and be metered out at an appropriate rate to achieve the sand loading expected in the fracturing fluid based on the fracturing design. The proppant can be coated with chemicals or additives 28 as specified in the fracturing design, making any necessary changes to the design made and informed by information from the fracturing truck 24 or data car 24. The selected coated proppant can leave the mobile coating unit 30 and be transported to the mixer 20 at the well site, or be deposited directly from the coating unit 30 into the mixer 20, where the coated proppant can be mixed and pumped downhole.

[0085] There may be a connection between the fracturing truck 24, the mobile coating unit 30, and the silo / box 12 at the site. The fracturing design may be programmed into the fracturing truck 24 system and is typically completed before the fracturing truck 24 is operably connected to the mobile coating unit 30. The fracturing truck 24 may communicate with the mobile coating unit 30 to instruct the coating unit hopper 34 to release enough sand to be processed in the coating unit 30 to keep up with the fracturing design, wherein a typical rate for dispensing sand may vary from about 100 TPH (tons per hour) to about 350 TPH. The mobile coating unit 30 may communicate with the sand storage silo / box 12 at the site to ensure that the loading hopper 34 remains full. Based on the information about the downhole conditions processed by the fracturing truck 24, the fracturing truck 24 may communicate with the feeders (i.e., the liquid additive dispenser 40 and the volumetric powder dispenser 60) on the mobile coating unit 30 to determine what chemicals or additives 28 will constitute the coating of the coated proppant produced at that particular time in what amounts. The coated proppant may exit the mobile coating unit 30 at an appropriate rate and be delivered to the blender 20. The coated proppant may be produced in the mobile coating unit 30, delivered to the blender 20 and pumped into the wellhead 26 in a range of about 10 to 20 seconds, or about ten (10) seconds to about three (3) hours, or even within ten (10) days.

[0086] The recipe or formulation for a desired coating can be changed based on real-time downhole conditions monitored by the fracturing vehicle 24. Thus, the mobile coating unit 30 can produce a first coated proppant at one time and then switch to producing a second, separate coated proppant at another time. Such changes can be made to account for real-time changes in downhole conditions throughout the hydraulic fracturing process.

[0087] Using coated proppants in fracturing fluids can provide a variety of benefits. The various types of coating additives 28 available make coated proppant products an effective way to modify downhole conditions to aid in the completion process.

[0088] refer to Figure 5a , which shows a test procedure for determining the erosion driven weight loss of a proppant. For this test procedure, a stainless steel coupon was weighed and its initial weight was recorded. The opening diameter of the insert was measured and recorded. The steel coupon was placed in an erosion cell and a mixer was filled with 75 gallons of water and 150 pounds of uncoated sand. The proppant-laden fluid was then flowed through the system at a flow rate of 57 gpm to 60 gpm with the aid of a triplex pump. The stainless steel coupon was removed from the erosion cell every 30 minutes and the weight was recorded. During the time that the steel coupon insert was removed from the erosion cell, the fluid was bypassed and continued through the flow loop. This test procedure was based on the Pressure Testing Research Cooperative TM (PressureTesting Research Cooperative TM ) guidelines.

[0089] refer to Figure 5b , which shows the results of the erosion driven weight loss comparison. As observed, the environmental erosion is significantly reduced due to the use of self-suspended coated proppants compared to common industrial methods. The coated proppants are proppants coated with hydrophilic linear polyacrylamide (non-crosslinked) compared to high viscosity friction reducer based systems.

[0090] refer to Figure 6a , which shows a test procedure used to evaluate the effect of certain products on pumping pressure. For the test procedure using a high viscosity friction reducer, the high viscosity friction reducer was added to the water in the mixing drum. The fluid was pumped at flow rates of 25 gpm, 41.5 gpm, and 65 gpm. Proppant was added at concentrations of 0.5 PPA, 1.0 PPA, 2.0 PPA, and 3.0 PPA, and a pump rate change was performed and the dP was recorded before proceeding to the next proppant concentration. The slurry was poured and the next polymer concentrate was mixed in. These steps were repeated as needed. For the test procedure using a proppant coated with a hydrophilic linear polyacrylamide (uncrosslinked), the coated proppant was added at concentrations of 0.5 PPA, 1.0 PPA, 2.0 PPA, and 3.0 PPA, and a pump rate change was performed and the dP was recorded before proceeding to the next proppant concentration. The slurry was poured and the next polymer concentrate was mixed in. These steps were repeated as needed. This test procedure was based on the Pressure Testing Research Cooperative. TM Guided by.

[0091] refer to Figure 6b to Figure 6d , these graphs show the results of the effect on pumping pressure. As observed, the use of coated proppants helps to reduce the pumping pressure compared to commonly used industrial products.

[0092] The use of hydrophilic linear polyacrylamide (uncrosslinked) coated proppants was also evaluated in a tortuous path test compared to common commercial products. A tortuous path was designed with a column of 4 feet in height, 8 feet in length, constant width throughout, and two flow path changes within the column.

[0093] First, the behavior of frac sand with slick water (a common type of fracturing fluid) was evaluated. It was determined that frac sand pumped with slick water would create a defined recirculation zone from the inlet, causing most of the last proppant to enter the wall to settle near the inlet. Both types of sand formed significant mounds in the first half of the structure, albeit sequentially. The speed at which the mound formed depended on the order of the proppant. The 40 / 70 mesh tail formed a larger mound closer to the inlet. This was possible because the coarser particles could not travel over the mound. The 100 mesh tail allowed the proppant to travel to the end of the structure and ultimately place more proppant in the effluent tank. The finer particles of the 100 mesh could better travel over the mound and into the effluent tank.

[0094] The behavior of frac sand with increased viscosity, 2.5 gpt HVFR and 4.0 gpt HVFR was also evaluated. The use of 2.5 gpt HVFR greatly improved the transport of proppant compared to slick water. There was rapid settling of the proppant suspension immediately upon entering the wall. Twice the amount of proppant traveled to the effluent tank with increased viscosity (2.5 gpt HVFR). Unlike slick water, most of the proppant traveled efficiently across the mound / bed upon entering the wall, allowing the last proppant to enter the pool to move away from the inlet / wellbore. When the fluid viscosity was increased to 2.5 HVFR at 100 mesh, the mound peak disappeared. When 2.5 HVFR was pumped at 40 / 70, the mound peak was still formed.

[0095] refer to Figure 7 , describes an evaluation process 80 or evaluation 80 that can be performed at a well site to determine whether adjustments to the hydraulic fracturing process, the fracturing fluid, or the coated proppant are desirable. Although many adjustments can be made in the hydraulic fracturing process, this example primarily describes possible changes to the coated proppant product used in the fracturing fluid.

[0096] The initial conditions 82 of the well site can include multiple factors, including, but not limited to, the fracturing design or fracturing plan for the particular site, available equipment, etc. The initial conditions 82 can also be described as a starting point for the monitoring process. The fracturing truck 24 can be configured to include, monitor, and display all necessary information about the initial conditions 82.

[0097] The current downhole conditions 84 at the well site can be monitored by the fracturing truck 24 and its control system. The fracturing truck 24 can monitor a number of downhole conditions or parameters, including but not limited to: the total amount of sand, or the number of pounds of sand used per stage; the sand loading, or the number of pounds of sand per gallon of fracturing fluid ("PPG"); the sand ramp schedule; schedule), which describes a steady incremental increase in sand loading (i.e., 0.5 lb / gal for 10 tons, 0.75 lb / gal for 7 tons, 1.0 lb / gal for 10 tons, etc.); total fluid volume, or barrels per minute ("BBLS"); pump rate, or barrels per minute ("BPM"); maximum pressure, or psi, which is determined by the equipment (i.e., pipe, stack, etc.); friction reducer concentration, which may be described as gallons of friction reducer per 1000 gallons of fracturing fluid ("GPT") if a liquid friction reducer is used, or pounds of friction reducer per 1000 gallons of fracturing fluid ("PPT") if a powdered friction reducer is used; other chemical loadings, including biocides, scale inhibitors, surfactants, buffers, etc., which may be described in GPT or PPT, as appropriate; and water quality ("water quality"). quality), or parts per million ("PPM") of chloride and certain other divalent ions.

[0098] Typically, an engineer or engineering team in the fracturing truck 24 can monitor all necessary parameters via a display screen that tracks or plots the parameters in real time using multiple lines (usually with different colors) to show the progress of the fracturing process while displaying the status of various parameters. The main monitored conditions or parameters in the fracturing truck 24 are typically pressure, friction reducer concentration, pump rate, and sand loading.

[0099] Based on this evaluation 80 and monitoring process, the engineer may encounter a situation where a decision must be made regarding possible adjustments 86 in the fracturing process. Certain changes or fluctuations in downhole parameters are expected, and may not require any changes, nor is it advisable to use a different coated proppant to change the downhole conditions. If no adjustments are needed or desired, the evaluation 80 and monitoring process can simply continue as before. However, certain changes or fluctuations in downhole conditions may necessitate or even necessarily require a change in the coated proppant to achieve the change in downhole conditions.

[0100] The engineer can order a modified coated proppant 88. The engineer can send a signal to the PLC control unit 32 on the mobile coating unit 30 with instructions for the specific coated proppant that the engineer wishes to add to the fracturing fluid. This modified coated proppant can be a coated proppant that is significantly different from the coated proppant currently used by the system. For example, the engineer can switch from using a coated proppant with a friction reducer coating to a coated proppant with a breaker coating. Based on real-time data from the fracturing vehicle 24, the modified coated proppant can also result in the use of more or less coatings. For example, the engineer can switch from a coated proppant with a high level of friction reducer to a coated proppant with a lower level of friction reducer. The engineer can also utilize a coated proppant with multiple coatings of different levels. The variations of the coated proppant products available to the engineer can be almost unlimited.

[0101] Thus, engineers can respond to nearly any downhole condition with an appropriate coated proppant and deliver that coated proppant to the wellhead 26 within minutes of noticing the condition. After any changes or adjustments are made, the evaluation process 80 can continue as before.

[0102] In one embodiment, an artificial intelligence unit can be used to monitor and control the described evaluation process 80. The artificial intelligence unit can be programmed to machine learn the evaluation process 80, including analyzing the fracturing design, monitoring the downhole conditions, and making adjustments based on a predetermined set of parameter changes or based on its own learning. For example, artificial intelligence or reasoning can be used to create a decision tree based on past hydraulic fracturing experience or based on engineer input. The artificial intelligence unit can be pre-programmed with a decision tree based on previous hydraulic fracturing processes and experience with fluctuations in downhole conditions. The artificial intelligence unit can also learn from field engineer responses. The artificial intelligence unit can be programmed to assist the field engineer, or virtually control the evaluation process 80 described herein.

[0103] As previously mentioned, a "frac design" or "frac plan" is typically developed for a specific well site. The development of a frac design is a detailed and time-consuming process. Extensive analysis is performed on existing wells within a reasonable geographic area. Comparisons and / or contrasts can be narrowed by basin and formation so that information about what has worked or has not worked previously can be utilized to maximize the return on investment that the operator company can achieve from each well.

[0104] The completion and reservoir engineers evaluate the available data and perform the necessary analysis to develop a fracturing design for a given well. The fracturing design typically divides the completion process into separate "stages," and modern fracturing designs may include sixty or more such stages. Each stage will have a PAD phase that is only liquid. The purpose of PAD is to initiate fractures. After PAD, the completion crew begins adding sand and / or proppants to the liquid. The amount of sand is slowly increased according to the schedule followed until the desired amount of sand for that stage is placed. To complete the stage, a "flush" is usually pumped. The flush is only liquid and is primarily used to remove any excess sand from the wellbore.

[0105] A typical fracturing design can be based on multiple parameters. For example, but not by way of limitation, relative parameters evaluated in a fracturing design can include the following: total sand volume, or pounds of sand used per stage; sand loading, or pounds of sand per gallon of fracturing fluid ("PPG"); sand ramp schedule, which describes a steady incremental increase in sand loading (i.e., 0.5 lb / gal for 10 tons, 0.75 lb / gal for 7 tons, 1.0 lb / gal for 10 tons, etc.); total fluid volume, or barrels per minute ("BBLS"); pump rate, or barrels per minute ("BPM"); maximum pressure, or psi, which is determined by the equipment (i.e., pipes); friction reducer concentration, which may be described as gallons of friction reducer per 1000 gallons of fracturing fluid ("GPT") if a liquid friction reducer is used, or as pounds of friction reducer per 1000 gallons of fracturing fluid ("PPT") if a powdered friction reducer is used; other chemical loadings, including biocides, scale inhibitors, surfactants, buffers, etc., which may be described as GPT or PPT, as appropriate; and water quality, or parts per million ("PPM") concentration of chlorides and other certain divalent ions.

[0106] These parameters are evaluated and established, leading to the "well completion" process. Based on the fracture design used to complete the well, the operator company can select the desired coated proppant as the "base product" to be used and pumped in the established fracture design.

[0107] The PLC control unit 32 is the "brain" of the mobile coating unit 30 and is connected to the feeders for sand, tackifier, friction reducer ("FR") and other chemicals. The recipe for this "base product" design is present in the PLC control unit 32 on the mobile coating unit 30 along with any other "standard" product recipes that the operator company may use.

[0108] When a stage begins and sand is needed, the sand is transported along the conveyor belt 14 from the silos 12 present on site (part of each fracturing site) and is deposited in the loading hopper 34 on the mobile coating unit 30. The sand leaves the loading hopper 34 on the belt scale. The weight of the sand measured by the belt scale allows the PLC control unit 32 to communicate correctly with the other feeders and calculate the appropriate addition amounts of tackifier, FR and other chemicals to produce the "base product".

[0109] The frac truck 24 or frac truck 24 is the brain of the well site. The frac truck 24 on the current well site controls the sand silo 12 on site, the conveyor belt 14 that takes the sand out of the silo to the mixer 20, the mixer itself, and other on-site equipment. The main monitored parameters in the frac truck 24 are pressure, friction reducer concentration, pump rate, and sand loading. Pressure is the main driver of friction reducer. Other additives are usually kept fixed, and in most cases, the amount of these additives added is changed only to keep them proportional and entering the system in the correct amount.

[0110] In one embodiment of the present invention, a mobile coating unit 30 is inserted between the sand silo 12 and the mixer 20 at the site. The PLC 32 on the mobile coating unit 30 is connected to and controlled by the fracturing truck 24. Inside the fracturing truck 24, engineers and sometimes fracturing consultants diligently monitor screens that provide real-time readings of several parameters, including at least the following: total sand volume, sand loading, pump rate, pressure, and friction reducer concentration.

[0111] If the phase is running smoothly, the frac design is operating as planned, and the mobile coating unit 30 can produce the base product in the amount required to meet the frac design. If the phase is not running smoothly, as is often the case, the mobile coating unit 30 can make adjustments and produce a specific coated proppant that helps better meet the frac design despite the change in planned conditions.

[0112] While ensuring that the fracturing design is being followed, one of the main concerns in the fracturing truck 24 is the pressure reading. The pressure reading is an indication of several things. Generally, the pressure reading is an indication of how well the formation is taking up sand. This is important because one of the most expensive and time-consuming events that can occur during the completion phase is called a "screen out." A "screen out" is when the sand does not pass through the perforations in the casing and into the fractures, leaving sand in the wellbore. In the case of a "screen out," the entire job may be stopped for several hours, and a coil tubing unit must be brought in to clean up the sand. Depending on where in the completion the "screen out" occurs, the cost of remediating the "screen out" can be significant (i.e., approximately $100,000 or more).

[0113] If the pressure readings begin to approach the maximum pressure threshold, engineers will evaluate and decide which change or changes need to be made. Typically, the first thing to do is add a friction reducer.

[0114] In one embodiment of the present invention, such adjustments can be made by an engineer in the fracturing truck 24 communicating with the PLC control unit 32 of the mobile coating unit 30 that the friction reducer portion of the coating needs to be increased by a certain specified percentage. Upon receiving this message, the PLC control unit 32 will communicate with the friction reducer feeder and make the necessary increase in the amount of friction reducer added based on the belt scale reading of the sand being used at a given time, as dictated by the fracturing design.

[0115] A possible second adjustment would be to cut back or reduce the pump rate. As described above, this adjustment would produce a real-time change in the formulation. Cutting back or reducing the pump rate would indicate that less sand would be needed in the same amount of time, even with the same sand loading. Thus, a communication from the engineer in the fracturing truck 24 to the PLC control unit 32 to cut back on the pump rate would slow down the sand flow, which in turn would reduce the viscosifier, friction reducer, and other chemical additives entering the mobile coating unit 30 while maintaining the integrity of the formulation.

[0116] The final adjustment will be to reduce the sand loading. Likewise, this communication by the engineer from the fracturing truck 24 to the PLC control unit 32 will cause an adjustment in the sand demand, which will result in real-time adjustments to the feeders of viscosifiers, friction reducers and other chemicals.

[0117] As has been described, the mobile coating unit 30 may be designed and constructed to produce a modifiable coated proppant at the wellsite and make real-time adjustments based on downhole conditions at the wellsite.

[0118] In some cases, even when a phase is proceeding as planned, engineers are able to make changes that are not in response to a problem but are more proactive in the completion process, potentially saving time and cost. One possible adjustment could be an adjustment to the pump rate. The engineer may adjust the pump rate because the formation is very receptive to sand. In this case, the same adjustment process will occur. The engineer will communicate from the fracturing truck 24 to the PLC control unit 32 to increase the rate, and the PLC control unit 32 will make adjustments to the amount of sand entering the system, which in turn will adjust the feeders for the other input products.

[0119] In another embodiment of the present invention, data from the fracturing truck 24 is captured, recorded and stored to facilitate "machine learning". In particular, the capture software will be programmed to "learn" what specific real-time factors, as observed by the engineers in the fracturing truck 24, will lead the engineers to change the coating, and what changes to make. After a satisfactory amount of data has been captured, recorded and analyzed, the fracturing truck 24 control can be driven by programming developed from "machine learning" to make real-time adjustments to the coating based on a comparison of the current actual data with the programming instructions, ranges and limits. The fracturing truck controller communicates the necessary changes to the PLC control unit 32 to adjust the formulation in the same manner as the previous embodiment. The fracturing crew responsible for the fracturing truck control is on site to solve major problems or problems that fall outside the programming instructions or parameters.

[0120] Leveraging “machine learning” in this way would be an improvement over current systems for a number of reasons. The field engineers who control the fracturing truck 24 work as part of a crew. Each crew traditionally has a day shift and a night shift. Each shift has an engineer responsible for the control of the fracturing truck. During the fracturing design process, there are often several different engineers controlling the fracturing truck. These independent engineers bring different personalities, knowledge, experience, and risk tolerance to the fracturing truck. As a result, independent engineers may respond differently to the information monitored in the fracturing truck 24. Some engineers may be able to make adjustments quickly, while others may be slower to react. Using a program based on “machine learning” or “artificial intelligence” can ensure that normal fluctuations in the fracturing process receive a consistent response, providing a more consistent response and process across all shifts and crews.

[0121] The typical response to a pressure problem in a fracturing truck 24 is to increase the friction reducer dosage, cut or reduce the pump rate and ultimately cut or reduce the sand loading. There is a cost factor for each response. By standardizing the response to normal fluctuations, time reduction and cost reduction are possible. At the very least, the consistency that can be achieved using the "machine learning" process will help the operator company predict and estimate the "spending authorization" costs on each well in the same oil field, or in other words, the itemized bill for the completion process.

[0122] Due to the precision pre-programmed into the "machine learning" controller, the formulation of the coated proppant produced by the mobile coating unit 30 and subsequently pumped into the well can be constantly adjusted. As a result, predetermined best possible fracturing design parameters can be followed with less risk of human error. This is not possible with a human engineer at the control equipment, as a human engineer cannot constantly increase and decrease the applicable parameters, i.e. the friction reducer concentration. This real-time optimization means that no more chemicals have to be used than necessary, which saves costs and improves the ESG (environmental, social and governance) impact of the project.

[0123] The present invention may be implemented in other specific forms without departing from its spirit or essential features. The described embodiments should be considered in all respects to be illustrative only and not restrictive. Therefore, the scope of the present invention is indicated by the appended claims rather than by the preceding description. All changes within the equivalent meaning and scope of the claims will be included within their scope.

[0124] What the patent claims and intends to protect is:

Claims

1. A method for producing a coated proppant, the method comprising: A mobile coating unit (30) is provided, wherein the mobile coating unit (30) includes a platform (70) having a proximal end and a distal end, a liquid additive dispenser (40) supported by the platform (70), a volumetric powder dispenser (60) supported by the platform (70), a coating mixer (50) supported by the platform (70), and a control unit (32) supported by the platform (70) and operably connected to the liquid additive dispenser (40), the volumetric powder dispenser (60) and the coating mixer (50); Positioning the mobile coating unit (30) on the well site; At the proximal end of the platform, feeding proppant to the mobile coating unit (30); coating the proppant according to a first recipe programmed into the control unit (32) to produce a first coated proppant; and The first coated proppant is dispensed from the mobile coating unit (30) at the distal end of the platform.

2. The method according to claim 1, further comprising: transferring the first coated proppant to a mixer (20) located at the well site; adding the first coated proppant to a first fracturing fluid; as well as The first fracturing fluid is pumped into a wellhead (26) within less than five days from the completion of coating of the first coated proppant.

3. The method according to claim 2, further comprising: coating the proppant according to a second recipe programmed into the control unit (32) to produce a second coated proppant; as well as The second coated proppant is dispensed from the mobile coating unit (30) at the distal end of the platform.

4. The method according to claim 3, further comprising: transferring the second coated proppant to the mixer (20) located at the well site; adding the second coated proppant to a second fracturing fluid; as well as The second fracturing fluid is pumped into the wellhead (26) within less than five days from the completion of the coating of the second coated proppant.

5. The method according to claim 1, wherein: The first coated proppant includes at least one additive (28) selected from the group consisting of friction reducers, surfactants, biocides, viscosifiers, scale inhibitors, crosslinkers, breakers, buffers, polymers, and clay stabilizers.

6. The method according to claim 3, wherein: The second coated proppant includes at least one additive (28) selected from the group consisting of friction reducers, surfactants, biocides, viscosifiers, scale inhibitors, crosslinkers, breakers, buffers, polymers, and clay stabilizers.

7. The method according to claim 1, further comprising: The proppant is dried before being fed into the mobile coating unit (30) at the proximal end of the platform.

8. The method according to claim 1, wherein: The proppant is sand.

9. The method according to claim 4, wherein: The control unit (32) selects the first recipe and the second recipe based on real-time downhole information provided to the control unit (32) by a fracturing vehicle (24) at the well site.

10. The method according to claim 9, wherein: The selection is performed based on a machine learning program programmed into the fracturing control system (24).

11. A mobile coating unit (30), comprising: a platform (70) having a proximal end and a distal end; a liquid additive dispenser (40) supported by the platform (70); a volumetric powder dispenser (60) supported by the platform (70); a coating mixer (50) supported by the platform (70); as well as A control unit (32) is supported by the platform (70) and is operably connected to the liquid additive dispenser (40), the volumetric powder dispenser (60) and the coating mixer (50), and the control unit controls the mobile control unit (30) to produce a first coated proppant product using a first recipe programmed into the control unit (32) and transfer the first coated proppant to the blender (20).

12. The mobile coating unit (30) according to claim 11, further comprising: A fracturing control system (24), wherein the fracturing control system (24) controls the addition of the first coated proppant to a first fracturing fluid and controls the pumping of the first fracturing fluid into a wellhead (26) in less than five days from the completion of the application of the first coated proppant.

13. The method according to claim 12, wherein: The control unit (32) controls the mobile coating unit (30) to produce a second coated proppant using a second recipe programmed into the control unit (32) and transfer the second coated proppant to the blender (20).

14. The method according to claim 13, wherein: The fracturing control system (24) controls the addition of the second coated proppant to a second fracturing fluid and controls the pumping of the second fracturing fluid into a wellhead (26) in less than five days from the completion of the application of the second coated proppant.

15. The mobile coating unit (30) according to claim 11, wherein: The first coated proppant includes at least one additive (28) selected from the group consisting of friction reducers, surfactants, biocides, viscosifiers, scale inhibitors, crosslinkers, breakers, buffers, polymers, and clay stabilizers.

16. The mobile coating unit (30) according to claim 13, wherein: The second coated proppant includes at least one additive (28) selected from the group consisting of friction reducers, surfactants, biocides, viscosifiers, scale inhibitors, crosslinkers, breakers, buffers, polymers, and clay stabilizers.

17. The mobile coating unit according to claim 16, further comprising: A dryer dries the proppant before feeding the proppant into the mobile coating unit (30) at the proximal end of the platform.

18. The mobile coating unit according to claim 11, wherein: The proppant is sand.

19. The mobile coating unit (30) according to claim 14, wherein: The control unit (32) selects the first recipe and the second recipe based on real-time downhole information provided to the control unit (32) by the fracturing control system (24) at the well site.

20. The mobile coating unit according to claim 19, wherein: The selection is performed based on a machine learning program programmed into the fracturing control system (24).