Regional rail transit-oriented regulation and control integrated operation system and method
Through the integrated regulation and control operation system for regional rail transit, the scheduling command, parallel deduction and operation control modules are used to solve the problem of low efficiency in cross-standard rail transit operation planning and emergency response, and efficient resource allocation and coordinated management are achieved, improving the efficiency of resource allocation and coordinated management. The overall operating efficiency of rail transit.
Patent Information
- Application Number
- CN202411092821.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-09
- Publication Date
- 2024-11-26
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
The existing technology is difficult to uniformly plan cross-standard rail transit operation, resulting in low efficiency of timetable connection and transfer between lines, and the ability to achieve optimal resource allocation within the time and space range, and the efficiency of information acquisition and dispatching command issuance in emergency response is not high. .
Provide an integrated regulation and control operation system for regional rail transit, including dispatching command module, parallel deduction module and operation control module. By compiling cross-standard train operation diagrams based on train historical operation data, passenger flow and driving data deductions are performed, and the operation plan is determined. , and control train operation in stations in the dispatching system of each region, and use dynamic adjustment algorithms and emergency response plans to improve operational efficiency.
It has realized networked collaborative management and control with multiple operating entities and multiple standards, improved the matching degree of passenger flow and traffic in regional rail transit, optimized the resource allocation within the network, reduced the time for passenger transfers, and improved the cross-standard regional rail transit Coordinated management efficiency and scheduling control efficiency in emergency scenarios.
Smart Images

Figure CN119018206A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the field of rail transit technology, and in particular to a control-integrated operation system and method for regional rail transit. Background Art
[0002] With the continuous development of urban agglomerations and metropolitan areas, passenger flows between cities and between towns in megacities continue to rise, and the corresponding rail transit construction of different systems such as urban rail, suburban and intercity lines has gradually formed a network, forming regional rail transit. At present, the lines in the regional rail transit network of different systems are operated by multiple operators, and the timetable connection and transfer efficiency between lines need to be improved; at the same time, the systems of multiple lines are different, and the trains between the lines only support single-line operation, which cannot effectively support the interconnection and interoperability of cross-line and shared lines, and cannot achieve the best resource allocation within the time and space range; and the cross-system rail transit operation relies more on the experience of dispatchers and drivers in emergency response, and the efficiency of obtaining information under faults and issuing dispatching orders needs to be improved. Therefore, it is urgent to propose a new regional rail transit control method to uniformly plan the operation of cross-system trains. Summary of the invention
[0003] The present application provides a regional rail transit control integrated operation system and method to solve the defect of the prior art that it is difficult to uniformly plan cross-system rail transit operations.
[0004] In a first aspect, the present application provides a control and integrated operation system for regional rail transit, including: a dispatching and command module, a parallel simulation module and an operation control module; The dispatching and commanding module is used to determine a cross-standard train operation diagram based on historical train operation data; input the cross-standard train operation diagram into the parallel deduction module, and obtain the operation plan of the different-standard regional rail transit output by the parallel deduction module; and send the operation plan of the different-standard regional rail transit to the operation control module; The parallel deduction module is used to obtain driving data; perform deduction based on the driving data and the cross-standard train operation diagram to determine the operation plan of the rail transit in different standards areas; The operation control module is used to control the train operation based on the operation plans of the regional rail transit of different standards and the dispatching system stations of each area.
[0005] In one embodiment, the historical train operation data includes historical operation data of trains on multiple lines; The dispatching and commanding module is specifically used for: Based on the historical operation data of the trains on the multiple lines, a unified train operation diagram is compiled; the unified train operation diagram includes operation plans of the trains on the multiple lines; The unified train operation diagram is split into multiple cross-standard train operation diagrams; the cross-standard train operation diagram includes the operation plan of trains on a single line.
[0006] In one embodiment, the parallel deduction module is specifically used to: Based on the cross-standard train operation diagram, passenger flow simulation and train operation simulation are performed on the driving data to determine the spatiotemporal distribution prediction information of passenger flow and the spatiotemporal distribution prediction information of trains; The passenger flow temporal and spatial distribution prediction information is matched with the train temporal and spatial distribution prediction information to determine the operation plan.
[0007] In one embodiment, the operation control module is further used to: In the first interference situation, a dynamic adjustment algorithm is used to determine an adjustment plan; Based on the adjustment plan, adjusting the running speed of the disturbed train; In the second interference situation, the driving situation is deduced based on the fault type, section location and time period information; Determine an emergency response plan based on the driving situation; Based on the emergency response plan, adjust the operation of the disturbed train; The interference degree of the second interference situation is higher than that of the first interference situation.
[0008] In one embodiment, the operation control module is specifically used to: In the case where a turnout exists or a platform exists or both a turnout and a platform exist, the dispatching system station based on the respective areas controls the train to operate in a fixed block mode; In the absence of a turnout and a platform, the train operation mode is determined based on the distance to the preceding vehicle.
[0009] In one embodiment, when there is no turnout and no platform, the operation control module is specifically used to: When the leading vehicle is beyond the sight range, control the train to run at the preset speed; Under the condition that the preceding vehicle is within the sight range, determine the current position of the train, obstacle detection results and the current status of the signal; Determining movement authorization based on the obstacle detection result and the current state of the signal; Determining a train speed curve based on the current position of the train, the movement authorization and the train emergency braking running distance; The train operation is controlled based on the train speed profile.
[0010] In one embodiment, when the preceding vehicle is within the sight range, the operation control module is specifically configured to: When there are no obstacles and no traffic lights within the sight range, or when there is only a traffic light and the current state of the traffic light is a preset state, the movement authorization end point is determined based on the far end of the sight range; When only an obstacle exists within the sight range, or when both the obstacle and the signal light exist and the signal light state is the preset state, determining the movement authorization end point based on the position of the obstacle; When there is only a traffic light within the sight range and the current state of the traffic light is a non-preset state, determining the movement authorization end point based on the position of the traffic light; When both the obstacle and the signal light exist within the sight range and the current state of the signal light is a non-preset state, the movement authorization end point is determined based on the positions of the obstacle and the signal light.
[0011] In one embodiment, when the preceding vehicle is within the sight range, the operation control module is specifically configured to: Determine the train emergency braking running distance based on the train emergency braking initial speed, the train emergency braking delay time, the train traction acceleration, the train coasting time, the train emergency braking terminal speed and the train emergency braking rate; and determine the train safe braking distance based on the train current position and the movement authorization; When the train emergency braking distance is less than or equal to the train safety braking distance, the train speed curve is determined based on the train emergency braking distance.
[0012] In one embodiment, the train emergency braking distance is calculated as follows:
[0013] in, is the emergency braking distance of the train, is the initial emergency braking speed of the train, is the train emergency braking delay time, is the train traction acceleration, is the train coasting time, is the final emergency braking speed of the train, is the emergency braking rate of the train.
[0014] In a second aspect, the present application further provides a method for integrated control and operation of regional rail transit, which is applied to an integrated control and operation system for regional rail transit, wherein the integrated control and operation system for regional rail transit includes a dispatching command module, a parallel deduction module and an operation control module; The method comprises: Determine the cross-system train operation diagram based on historical train operation data; Determine the operation plan of regional rail transit of different systems by performing deduction based on the driving data and the cross-system train operation diagram; Based on the operation plans of the regional rail transit of different standards and the dispatching system stations in each area, the train operation is controlled.
[0015] In a third aspect, the present application further provides an electronic device, comprising a memory, a processor, and a computer program stored in the memory and executable on the processor, wherein the processor implements the method described in the second aspect when executing the program.
[0016] In a fourth aspect, the present application further provides a non-transitory computer-readable storage medium having a computer program stored thereon, which, when executed by a processor, implements the method described in the second aspect.
[0017] In a fifth aspect, the present application also provides a computer program product, including a computer program, which implements the method described in the second aspect when executed by a processor.
[0018] The integrated control and operation system and method for regional rail transit provided in the embodiments of the present application can adapt to the travel needs of diverse passengers by compiling a cross-system train operation diagram and performing deductions based on driving data and the cross-system train operation diagram, thereby determining the operation plan and controlling the train to operate according to the operation plan. It can achieve networked collaborative control of multiple operating entities and multiple systems, improve the matching degree of passenger flow and vehicle flow in regional rail transit, optimize the resource allocation within the line network, reduce passenger transfers and shorten travel time, effectively improve the collaborative control efficiency of cross-system regional rail transit, and at the same time effectively improve the dispatching and control efficiency in emergency scenarios. BRIEF DESCRIPTION OF THE DRAWINGS
[0019] In order to more clearly illustrate the technical solutions in the present application or the prior art, a brief introduction will be given below to the drawings required for use in the embodiments or the description of the prior art. Obviously, the drawings described below are some embodiments of the present application. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying any creative work.
[0020] Figure 1 It is a structural schematic diagram of the integrated control and operation system for regional rail transit provided by this application; Figure 2 It is a schematic diagram of the interaction between the modules of the integrated control operation system provided by this application; Figure 3 It is a schematic diagram of the mobile authorization end point and train speed curve provided by this application; Figure 4 It is a flow chart of the integrated control and operation method for regional rail transit provided by this application; Figure 5 It is a schematic diagram of the structure of the electronic device provided by this application. DETAILED DESCRIPTION
[0021] In order to make the purpose, technical solutions and advantages of this application clearer, the technical solutions in this application will be clearly and completely described below in conjunction with the drawings in this application. Obviously, the described embodiments are part of the embodiments of this application, not all of them. Based on the embodiments in this application, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of this application.
[0022] Figure 1 Schematic diagram of the structure of the integrated control and operation system for regional rail transit provided in the embodiment of the present application. Figure 1 The integrated control and operation system for regional rail transit provided in the embodiment of the present application may include: a dispatching and commanding module 110, a parallel simulation module 120 and an operation control module 130; The dispatching and commanding module 110 is used to determine the cross-standard train operation diagram based on the historical train operation data; input the cross-standard train operation diagram into the parallel deduction module, and obtain the operation plan of the regional rail transit of different standards output by the parallel deduction module; and send the operation plan of the regional rail transit of different standards to the operation control module; The parallel deduction module 120 is used to obtain driving data; perform deduction based on the driving data and the cross-standard train operation diagram to determine the operation plan of rail transit in different standards; The operation control module 130 is used to control the train operation based on the operation plans of regional rail transit of different standards and the dispatching system stations of each area.
[0023] There are multiple types of regional rail transit, including urban rail, suburban rail, and intercity rail. Compared with a single urban rail system, cross-system rail transit differs in operating modes, technical standards, equipment and facilities. During operation command, it is necessary to formulate unified operating strategies and management measures for different systems, coordinate the connection and conversion between different systems, and deal with passenger flow fluctuations and peak passenger flow pressure between different systems.
[0024] For the unified command of cross-system operations, this application constructs a unified integrated control and operation system for regional rail transit, which conducts unified dispatching and command of passenger flow, trains, stations, train sections and other resources of all lines in the region, including the preparation of line operation diagrams in the region, daily organization and command, passenger flow dispatching, emergency dispatching, etc., so as to improve the connection and transfer efficiency between different systems.
[0025] Specifically, the integrated control and operation system adopts a compatible design. For existing lines, it can use standard interfaces based on existing systems such as the Automatic Train Supervision (ATS) and Centralized Traffic Control (CTC) to achieve high coordination between lines. For newly built lines, it has the function of directly accessing field-level equipment to carry out dispatching and command.
[0026] The daily organization and command, passenger flow dispatching, and emergency dispatching functions of the dispatching and commanding module 110 are based on an integrated control and operation system with networked collaborative capabilities. The system can flexibly control zoning, adapt to the adjustment of dispatching personnel, and share and interconnect resources with existing lines and extended lines.
[0027] Specifically, the dispatching and commanding module 110 can obtain historical train operation data and compile a cross-standard train operation diagram based on the historical train operation data. By uniformly coordinating and compiling a cross-standard train operation diagram in an online network or region, the operation of trains of different standards can be uniformly dispatched, and further, the automatic adjustment capability can be obtained under weak interference conditions.
[0028] After compiling the cross-standard train operation diagram, the dispatching command module 110 can input the cross-standard train operation diagram into the parallel simulation module 120 for verification to determine whether the cross-standard train operation diagram can be used as the actual train operation plan.
[0029] The parallel deduction module 120 can obtain driving data based on the dispatching and commanding module 110 and the operation control module 130. Specifically, the driving data may include passenger flow data and train data. Train data may include train operation data, operation diagrams, signal system and other data. When a train fails, the train data may also include fault information. The parallel deduction module 120 can perform parallel deduction based on driving data and cross-system train operation diagrams, optimize and iterate the deduction results, and finally determine the operation plan of rail transit in different systems and transmit it to the dispatching and commanding module 110. Among them, the operation plan may include the spatiotemporal distribution prediction information of the train.
[0030] After acquiring the operation plan, the dispatching command module 110 sends the operation plan to the operation control module 130. The operation control module 130 can control the train operation according to the operation plan based on the dispatching system stations in each area.
[0031] Specifically, the operation control module center can use equipment from the same manufacturer, and the regional networked dispatching system stations can be set up according to regions (manufacturers), thus breaking the limitations of a single manufacturer.
[0032] The connection between each module of the integrated control operation system is as follows Figure 2 As shown in the figure, the dispatching and commanding module is responsible for the unified dispatching of resources of all lines in the area under its jurisdiction, and can also handle emergencies. During daily operation, the regional dispatching and commanding system is mainly used to issue operation plans and conduct comprehensive monitoring. When abnormalities or emergencies occur, dispatchers also use the system to handle on-site. The big data platform and deduction system provide data support and auxiliary decision-making support for daily dispatching and emergency handling for the dispatching and commanding module.
[0033] The integrated control and operation system for regional rail transit provided in the embodiment of the present application can adapt to the diverse travel needs of passengers by compiling a cross-system train operation diagram and performing deductions based on driving data and the cross-system train operation diagram, thereby determining the operation plan and controlling the train to run according to the operation plan. It can achieve networked collaborative control of multiple operating entities and multiple systems, improve the matching degree of passenger flow and vehicle flow in regional rail transit, optimize the resource allocation within the line network, reduce passenger transfers and shorten travel time, effectively improve the collaborative control efficiency of cross-system regional rail transit, and at the same time effectively improve the dispatching and control efficiency in emergency scenarios.
[0034] In one embodiment, the historical train operation data includes historical operation data of trains on multiple lines; The dispatching and commanding module is specifically used for: Based on the historical operation data of trains on multiple lines, a unified train operation diagram is compiled; the unified train operation diagram includes the operation plans of trains on multiple lines; The unified train operation diagram is split into multiple cross-standard train operation diagrams; the cross-standard train operation diagram includes the operation plan of trains on a single line.
[0035] Specifically, this application can consider two independently operated lines and design multiple cross-standard train operation diagram compilation schemes to achieve the interconnection of operation plans and support cross-line operation. The specific schemes are as follows: Solution 1: The dispatching and commanding module uniformly compiles the operation plans of trains on multiple lines to obtain a unified train operation diagram. Specifically, the unified train operation diagram includes the operation plan of each line. In order to more efficiently dispatch a single line, the dispatching and commanding module can split the unified train operation diagram into two cross-standard train operation diagrams and issue them to each line for execution.
[0036] Plan 2: The two lines first determine the cross-line train operation plan, and each line plans cross-line trains based on the cross-line train plan. Then the two lines each compile train operations within their respective areas, and finally send the plan map information to the other party's line mapping system according to the information transmitted between them, so that their respective dispatching centers can grasp the train operation plan.
[0037] The integrated control and operation system for regional rail transit provided in the embodiment of the present application can realize networked collaborative control of multiple operating entities and multiple standards by compiling a cross-standard train operation diagram and controlling the train to run according to the operation plan, optimize the resource allocation within the line network, and effectively improve the efficiency of collaborative control of cross-standard regional rail transit.
[0038] In one embodiment, the parallel deduction module 120 is specifically used to: Based on the cross-standard train operation diagram, passenger flow and train operation data are simulated to determine the spatiotemporal distribution prediction information of passenger flow and trains; The passenger flow temporal and spatial distribution forecast information is matched with the train temporal and spatial distribution forecast information to determine the operation plan.
[0039] In this application, a key data interface for a standard station is first established. The key data mainly includes data of multiple dimensions such as train control data, perception data, electronic maps, weather data, passenger flow data, and perception verification platform data. The key data can be obtained from the data sharing platform. Then a standard station data model is constructed. Specifically, the standard station design can be carried out based on the multi-dimensional data provided by the data sharing platform. The standard station design mainly combines the station yard type, various types of connecting lines, elevated / underground and other different operating lines, topology, perception, equipment status and other multi-dimensional data of the standard station data model, provides data full set management services and related interfaces, and provides standard data input for parallel deduction related applications. Finally, through the modeling and simulation of the key elements of the line, a data-centric, multi-dimensional data fusion simulation test model is built and connected to the parallel deduction module 120 to realize the mapping of physical entities and virtual devices.
[0040] After the mapping between the real equipment and the virtual simulation model is established, the parallel simulation function can be realized. The parallel simulation module 120 can perform passenger flow simulation and driving simulation on the driving data based on the cross-standard train operation diagram, and the two can interact and iterate. The passenger flow simulation provides the driving simulation module with the passenger flow analysis prediction results and the preset disposal plan (based on the historical passenger flow). The driving simulation formulates the operation plan and performs virtual simulation, which is also the basis for passenger flow simulation. On the basis of the driving model composed of stations, trains, operation diagrams and other subjects, by inputting the current train operation plan, passenger flow distribution, and disposal plan, the next step of passenger flow spatiotemporal distribution prediction information, train spatiotemporal distribution prediction information, etc. can be deduced. By matching the passenger flow spatiotemporal distribution prediction information with the train spatiotemporal distribution prediction information, and continuously iterating based on the cross-standard train operation diagram, the real environment such as the collected standard station data and the pilot base is combined with the virtual and real, the synchronous linkage and feedback function of the real scene and the virtual environment is realized, and the application effect of the parallel simulation in the actual environment is verified, so as to determine the operation plan. This application can also realize typical application scenarios such as train limit tracking testing and realize the prediction of future operating conditions.
[0041] The integrated control and operation system for regional rail transit provided in the embodiment of the present application can realize multi-standard networked collaborative control by performing passenger flow and train driving simulation on driving data, determining passenger flow temporal and spatial distribution prediction information and train temporal and spatial distribution prediction information, and then determining the operation plan, thereby improving the matching degree of passenger flow and vehicle flow in regional rail transit and effectively improving the collaborative control efficiency of regional rail transit.
[0042] In one embodiment, the operation control module is further configured to: In the first interference situation, a dynamic adjustment algorithm is used to determine an adjustment plan; Adjust the running speed of the affected trains based on the adjustment plan; In the second interference situation, the driving situation is deduced based on the fault type, section location and time period information; Determine an emergency response plan based on the driving situation; Based on the emergency response plan, the operation of the affected train is adjusted.
[0043] Furthermore, the integrated control and operation system for regional rail transit can also handle emergencies. Emergency handling mainly requires dispatchers, drivers, station attendants, etc. to respond quickly to abnormalities and failures in the system, and quickly deal with abnormalities and failures to avoid / reduce the impact of abnormalities and failures on operations. Usually, emergency handling can be divided into weak interference, i.e. the first interference situation (interference duration is less than 2 minutes and the impact range is small) and strong interference, i.e. the second interference situation (interference time is greater than 2 minutes, or the impact range is large) according to the duration of the impact.
[0044] The integrated control and operation system integrates and shares data resources of passenger flow, stations, trains, sections and yards of all rail transit in the region by building a data sharing platform. On this basis, it conducts high-speed parallel simulations of passenger flow and train operation to provide auxiliary decision-making support information for emergency response.
[0045] Specifically, in the case of weak interference, that is, the first interference situation, the integrated control operation system can adopt a dynamic adjustment algorithm to adjust the operation of the affected trains. The trains automatically receive and execute the dispatching adjustment instructions to resume orderly operation as soon as possible. During the recovery process, the trains can accurately adjust the running speed according to the operation plan to ensure punctuality. The dispatching department can conduct micro-verification of the dispatching instructions based on the results of the driving simulation. Once a large deviation is predicted, it needs to be adjusted immediately.
[0046] In the case of strong interference, that is, the second interference, the integrated control operation system quickly predicts the impact and performance of passenger flow and traffic in future time periods based on the type of fault, section location, time period and other information, and provides auxiliary decision-making support information based on the emergency response plan to improve the response efficiency of dispatchers, drivers, station attendants and other roles.
[0047] The integrated control and operation system for regional rail transit provided in the embodiment of the present application can adjust the train operation under different interference conditions, control the train to run according to the operation plan, realize the networked collaborative control of multiple operating entities and multiple systems, and effectively improve the dispatching and control efficiency in emergency scenarios. In one embodiment, the operation control module 130 is specifically used to: In the case where a turnout exists or a platform exists or both a turnout and a platform exist, the dispatching system station based on the respective areas controls the train to operate in a fixed block mode; In the absence of a turnout and a platform, the train operation mode is determined based on the distance to the preceding vehicle.
[0048] In order to enhance the ability of regional rail transit trains to support cross-system interconnection and interoperability, this application adopts a train operation control system with perception as the core. The system uses heterogeneous high-precision laser radar and other multi-source data fusion driving environment perception equipment to identify and analyze the trains, tracks, obstacles, signal lights, etc. in front of the train, and independently decide on the driving authorization of the train based on this; further, according to the central-level dispatching command, the train is autonomously controlled to complete the operation plan.
[0049] The operation control module 130 can support cross-line and co-line operation with cross-standard interconnection. When a train needs to cross the line to run on a line of another standard, the operation control module 130 only needs to calibrate and self-learn the map and vehicle characteristics of the new line to support the cross-line operation without adding new equipment and interfaces; when the train needs to run on the same line with other standard trains, due to the independence of its own driving authorization, it can ensure driving safety and spacing without communicating with other standard trains.
[0050] When the train does not cross lines / standards and no failure occurs, the operation control module 130 controls the train operation through the main system. When the train needs to cross lines / standards, or when the train is in a degraded mode (such as a train-to-ground wireless communication failure), the operation control module 130 can seamlessly switch to a backup mode based on perception and autonomous operation. During the backup mode operation, the mobile authorization is calculated and safety protection is performed in the section according to the principle of "how far you see, how far you run", and the switch area operates according to the open state of the signal. After the main system fault is repaired, the train no longer needs to perform complex operations such as screening. After meeting the main system operation conditions, it can be directly upgraded to the main system operation. This system can greatly improve the operating efficiency under faults and maintain a certain quality of passenger service.
[0051] Specifically, when the train needs to cross lines / systems, or is in the train degradation mode, the operation control module 130 will determine the current normal conditions of the on-board sensing equipment and the effective conditions of the sensing movement authority (MA) based on the automatic train protection system (Automatic Train Protection, ATP). After the on-board sensing equipment is in normal conditions, the train will switch from RM mode to ABL mode, and enter the sensing automatic driving mode (ABL-AM) after the driver confirms.
[0052] The operation control module 130 dispatches / station services to sense the route of the train, which is specifically sent by the Automatic Train Supervision (ATS) system to the route control (RC). RC controls the signal status according to the route attributes.
[0053] There are two types of route attributes: routes with no switches and no platforms, and routes with switches, platforms, or both switches and platforms.
[0054] For the former, ATS automatically handles the traceable route, and the sensing train can directly operate in moving block mode according to the sensing MA. Specifically, the movement authorization is determined by the distance to the preceding train; For the latter, the train speed curve is calculated and operated according to the fixed block tracking with the end of the route as the MA end.
[0055] For example, when there is a turnout in the route ahead of train 1, the end point of the route for train 1 is the beginning of the section where the turnout is located. At this time, the train runs in a fixed block and calculates the emergency brake intervention curve (EBI) according to the end point of the route to ensure that the train can stop in front of the turnout. When the turnout signal enters the recognition range of the Intelligent Train Eyes (ITE) system, train 1 determines whether to pass the turnout area based on the recognized signal status.
[0056] The integrated control and operation system for regional rail transit provided in the embodiment of the present application determines the train operation mode by means of turnout and platform conditions, thereby improving the train operation efficiency, ensuring the train operation safety, enhancing the train's ability to support cross-standard interconnected operation, and improving the coordinated control efficiency of regional rail transit.
[0057] In one embodiment, when there is no turnout and no platform, the operation control module is specifically used to: When the leading vehicle is beyond the sight range, control the train to run at the preset speed; Under the condition that the preceding vehicle is within the sight range, determine the current position of the train, obstacle detection results and the current status of the signal; Determine movement authorization based on obstacle detection results and the current status of the signal; Determine the train speed profile based on the train's current position, movement authorization, and train emergency braking distance; Control train operation based on the train speed profile.
[0058] The operation control module 130 can obtain a table corresponding to sight distance and train speed, and control the train to run at a preset speed when the leading vehicle exceeds the sight distance range. The preset speed is the speed in the table corresponding to sight distance and train speed.
[0059] When the front vehicle does not exceed the visual range, the operation control module 130 can obtain the current position of the train, the obstacle detection results and the current state of the signal. Specifically, the operation control module 130 can obtain a large amount of real-time sensor data by scanning the line environment through a laser radar, and use the laser simultaneous localization and mapping (SLAM) technology and sensor fusion technology to build a high-precision point cloud map of the line through environmental feature matching, train motion state estimation, loop detection and other processes. During the operation of the train, the operation control module 130 can scan the front of the train through a laser radar, obtain the point cloud of the front operation area, and match it with the stored high-precision map to calculate the high-precision position of the train. In order to further improve the positioning accuracy, a signboard can be set up on the trackside to correct and update the current position of the train.
[0060] The operation control module 130 can perform a clearance detection. Specifically, the operation control module 130 uses a variety of optical sensor devices such as camera vision and laser radar to identify trains, maintenance personnel, signal lights, obstacles that invade the limit (such as trees, cables, billboards), etc. Then, through image acquisition, image preprocessing, track area recognition, point cloud screening, target classification and other processes, the obstacles in the track area ahead of the train are detected and classified to obtain the obstacle detection results.
[0061] The operation control module 130 can identify the state of the signal. The operation control module 130 first calculates whether the signal is included in the sight range and the position of the signal in the picture according to the current position and running direction of the train and the electronic map; when the visual module recognizes the signal and its position is consistent with the expectation, the anti-interference algorithm processes the real-time collected picture to identify the current state of the signal (whether it is lit, the color of the light, etc.).
[0062] The operation control module 130 can determine the end point of the movement authorization based on the obstacle detection result and the current state of the signal, and then calculate the safe braking distance of the distressed vehicle based on the current position of the train and the movement authorization, and compare it with the emergency braking running distance of the train, so as to determine the train speed curve (EBI curve), and control the train operation based on the train speed curve. That is, ensuring that the actual running speed of the train does not exceed the EBI curve can ensure the operation safety.
[0063] For example, when Train 2 is running on a route without branches or platforms, it can operate according to the moving block system and is allowed to track the preceding vehicle. However, when the preceding vehicle is beyond the sight range, it operates according to the sight speed table. If the preceding vehicle enters the sight range, it is necessary to calculate the EBI curve with the position of the preceding vehicle's rear end offset by a safe distance as the MA end point, and operate according to the EBI curve.
[0064] The integrated control and operation system for regional rail transit provided in the embodiment of the present application can improve the train operation efficiency, ensure that the train runs at a safe speed, and ensure the coordinated control of regional rail transit by determining the train operation mode based on the distance to the preceding vehicle in the absence of switches and platforms.
[0065] In one embodiment, when the preceding vehicle is within the sight range, the operation control module 130 is specifically configured to: When there are no obstacles and no traffic lights within the sight range, or when there is only a traffic light and the current state of the traffic light is a preset state, the movement authorization end point is determined based on the far end of the sight range; When only an obstacle exists within the sight range, or when both the obstacle and the signal exist and the signal is in the preset state, the movement authorization end point is determined based on the position of the obstacle; When there is only a traffic light within the sight range and the current state of the traffic light is not a preset state, the movement authorization end point is determined based on the position of the traffic light; When both obstacles and traffic lights exist within the sight range and the current state of the traffic light is not a preset state, the authorized end point of movement is determined based on the positions of the obstacles and the traffic light.
[0066] like Figure 3 As shown, when there is no obstacle and no signal within the sight range, or when there is only a signal and the current state of the signal is a preset state, the operation control module 130 offsets the far end of the sight range toward the end close to the train by a safety margin as the movement authorization end point. When there is only an obstacle within the sight range, or when both the obstacle and the signal exist and the state of the signal is a preset state, or when there is only a signal within the sight range and the current state of the signal is a non-preset state, or when both the obstacle and the signal exist within the sight range and the current state of the signal is a non-preset state, the operation control module 130 can sort the obstacle and / or the signal according to the distance from the train, and use the position with the closest distance as the movement authorization end point.
[0067] The integrated control and operation system for regional rail transit provided in the embodiment of the present application determines the authorized moving end point based on the obstacle detection result and the current state of the signal in the absence of a turnout and a platform. The train speed curve can be determined based on the authorized moving end point to control the train operation, thereby improving the train operation efficiency while ensuring the safety of the train and ensuring the coordinated control of regional rail transit.
[0068] In one embodiment, when the preceding vehicle is within the sight range, the operation control module 130 is specifically configured to: Determine the train emergency braking distance based on the train running speed, train emergency braking delay time, train traction acceleration, train coasting time, train emergency braking terminal speed and train emergency braking rate; and determine the train safe braking distance based on the train current position and movement authorization; When the train emergency braking distance is less than or equal to the train safety braking distance, the train speed curve is determined based on the train emergency braking distance.
[0069] like Figure 3 As shown in the figure, the train emergency braking process can be divided into three stages (corresponding to ①②③ in the figure): In the first stage, the train continues to accelerate at the maximum traction acceleration. The acceleration time includes the onboard reaction delay before emergency braking and the time delay of vehicle traction cutoff. The total delay time, i.e. the train emergency braking delay time, is recorded as .
[0070] In the second stage, traction has been cut off, but the emergency braking force has not yet reached the nominal value. The train coasts within the equivalent time of emergency braking establishment. The coasting time is recorded as .
[0071] In the third stage, the train implements emergency braking and runs in a straight line with uniform acceleration. The speed-distance curve can be calculated by determining the train's emergency braking acceleration.
[0072] Based on the above assumptions, if the current position of the train, the authorized end point, the delay and coasting time, and the maximum traction and braking acceleration of the train are known, the speed-distance equation can be used to calculate the train's current position and the distance between the train and the destination. The distance traveled during initial velocity emergency braking is the distance traveled during train emergency braking.
[0073] Safety conditions according to the braking model: Train emergency braking distance ( )≤Train safe braking distance
[0074] Train safe braking distance = actual distance between train and obstacle ( ) – Safety distance ( ).
[0075] in, is the distance between the current position of the train and the end point of the movement authorization, The safety distance is set.
[0076] Therefore, a train speed curve can be calculated according to the train position, namely the emergency brake trigger curve (EBI curve) shown in the figure. The actual running speed of the train can be guaranteed not to exceed the EBI curve to ensure operation safety.
[0077] The integrated control and operation system for regional rail transit provided in the embodiment of the present application determines the train speed curve and controls the train operation by calculating and comparing the train emergency braking distance and the train safety braking distance when the leading vehicle does not exceed the sight range, thereby improving the train operation efficiency while ensuring the safety of the train and ensuring the coordinated control of regional rail transit.
[0078] In one embodiment, the train emergency braking distance is calculated as follows:
[0079] in, is the train emergency braking distance, is the initial speed of the train during emergency braking, is the train emergency braking delay time, is the train traction acceleration, is the train coasting time, is the train emergency braking terminal speed, is the train emergency braking rate.
[0080] Specifically, The possible value is 0.
[0081] Based on the safe braking distance of the train, we can obtain ,in
[0082] The integrated control and operation system for regional rail transit provided in the embodiment of the present application can determine the train speed curve and control the train operation by calculating the emergency braking running distance of the train when the leading vehicle does not exceed the sight range. This can improve the train operation efficiency while ensuring the safety of the train and ensure the coordinated control of regional rail transit.
[0083] Based on the records of the above embodiments, the integrated control operation system proposed in this application, on the one hand, realizes unified command of cross-standard dispatching; on the other hand, it supports cross-standard interconnected operation; in particular, in emergency response, dispatching and train operation control are coordinated and optimized, and the two are deeply integrated into a linkage response strategy. This application combines unified dispatching and command of the line network, autonomous train operation control with perception as the core, and parallel deduction of passenger flow and driving under emergency response to provide auxiliary decision support information, and based on this deep integration, generates a linkage response strategy for dispatching and control systems under emergency response, thereby effectively improving the efficiency of coordinated management and control of regional rail transit.
[0084] In daily operations, the dispatching and commanding module realizes efficient train dispatching through networked mapping and other means, while the autonomous operation control module based on perception provides dispatching with flexible cross-line and co-line operation capabilities, improving the level of interconnection and interoperability. The specific process is as follows: (1) The dispatching and command module obtains passenger flow data from the data platform and realizes regional passenger flow prediction through passenger flow prediction; (2) The parallel simulation module loads passenger flow data, line information, signal system and other information to compile the operation plan and operation plan diagram (cross-line and cross-system operation diagram). The operation plan is issued to the trains on each line in the region, and the dispatcher of each line is responsible for organizing the trains on the line. When the trains run across lines, the hub station takes over the control. (3) Trains run on the line according to the operation plan. When cross-line operation is involved, the train switches to the perception operation mode and relies on line-of-sight perception to achieve cross-line operation.
[0085] During this process, the data platform receives train and passenger flow information for simulation and to determine the operating status and potential risks. The system can input pre-designed operating plans, expected passenger flows, management and control plans, etc. for the scenarios to be simulated, simulate the entire scenario, calculate statistical indicators, and display the indicator statistical results of the current plan in a visual way.
[0086] In emergency situations, the parallel simulation module obtains the data required for passenger flow and train driving simulation from the data platform (collected and uploaded by the dispatching command module and the operation control module), including real-time passenger flow data, train operation data, operation diagrams, fault information, etc. The parallel simulation module supports the injection of fault types and impact ranges as well as the adjustment plan input by the dispatcher. It simulates the operation results in a certain period of time in the future based on the adjusted operation plan, and displays the indicator statistical results of the current plan in a visual way, providing accurate situation prediction for dispatchers and personnel. By comparing multiple adjustment plans, it assists dispatchers in making emergency decisions, optimizing emergency plans, and improving emergency response efficiency.
[0087] On the other hand, the train's autonomous sensing operation can improve operating efficiency under fault degradation. When a train is degraded due to an emergency such as a communication failure, it can switch to the sensing operation mode under the conditions of meeting safety conditions to avoid section stops or low-speed manual driving. At the same time, it can be taken offline in time or the operation plan can be adjusted in combination with emergency dispatch commands, greatly reducing the impact of the fault.
[0088] Therefore, this solution has built a unified cross-system integrated dispatching and command platform, and combined with hub stations, it has greatly improved the transfer connection capabilities between different systems and regional lines, and improved the throughput capacity of transfer stations. By combining the perception operation system with flexible group dispatching, the operating efficiency of trains under faults is improved, while cross-line operation is provided to improve flexibility, alleviate the problem of uneven passenger flow distribution to a certain extent, and increase line capacity. In emergencies, the efficiency and scientificity of decision-making are improved through deduction, and predictive auxiliary suggestions are provided to commanders, which improves the efficiency of emergency command and disposal.
[0089] The integrated control and operation method for regional rail transit provided in the present application is described below. The integrated control and operation method for regional rail transit described below and the integrated control and operation system for regional rail transit described above can be referenced to each other.
[0090] Figure 4 Schematic diagram of the integrated control operation method for regional rail transit provided in the embodiment of the present application. Figure 4The embodiment of the present application provides a method for integrated control and operation of regional rail transit, which is applied to an integrated control and operation system for regional rail transit. The integrated control and operation system for regional rail transit includes a dispatching command module, a parallel deduction module and an operation control module. The method may include: Step 410: Determine a cross-system train operation diagram based on historical train operation data; Step 420: Determine the operation plan of regional rail transit of different standards by performing deduction based on the driving data and the cross-standard train operation diagram; Step 430: Control the operation of trains based on the operation plans of the regional rail transit of different standards and the dispatching system stations of each area.
[0091] The integrated control and operation method for regional rail transit provided in the embodiment of the present application determines the operation plan by compiling a cross-system train operation diagram and deduce it based on driving data and the cross-system train operation diagram, and controls the train to run according to the operation plan. It can adapt to the travel needs of diverse passengers and realize networked collaborative control of multiple operating entities and multiple systems, improve the matching degree of passenger flow and vehicle flow in regional rail transit, optimize the resource allocation within the line network, reduce passenger transfers and shorten travel time, effectively improve the collaborative control efficiency of cross-system regional rail transit, and at the same time can effectively improve the dispatching control efficiency in emergency scenarios.
[0092] It should be noted here that the integrated control and operation method for regional rail transit provided in the embodiment of the present application can achieve the same technical effect based on the above-mentioned integrated control and operation system for regional rail transit. The parts and beneficial effects of this embodiment that are the same as those in the system embodiment will not be described in detail here.
[0093] Figure 5 An example of a physical structure diagram of an electronic device is shown in FIG. Figure 5 As shown, the electronic device may include: a processor 510, a communications interface 520, a memory 530 and a communication bus 540, wherein the processor 510, the communications interface 520 and the memory 530 communicate with each other through the communication bus 540. The processor 510 may call the logic instructions in the memory 530 to execute the integrated control operation method for regional rail transit, for example, including: Determine the cross-system train operation diagram based on historical train operation data; Determine the operation plan of regional rail transit of different systems by performing deduction based on the driving data and the cross-system train operation diagram; Based on the operation plans of the regional rail transit of different standards and the dispatching system stations in each area, the train operation is controlled.
[0094] In addition, the logic instructions in the above-mentioned memory 530 can be implemented in the form of a software functional unit and can be stored in a computer-readable storage medium when it is sold or used as an independent product. Based on this understanding, the technical solution of the present application can be essentially or partly embodied in the form of a software product that contributes to the prior art. The computer software product is stored in a storage medium, including several instructions to enable a computer device (which can be a personal computer, a server, or a network device, etc.) to perform all or part of the steps of the method described in each embodiment of the present application. The aforementioned storage medium includes: U disk, mobile hard disk, read-only memory (ROM), random access memory (RAM), disk or optical disk, etc., various media that can store program codes.
[0095] On the other hand, the present application also provides a non-transitory computer-readable storage medium having a computer program stored thereon, which, when executed by a processor, implements the steps of the integrated control operation method for regional rail transit provided by the above methods, for example, including: Determine the cross-system train operation diagram based on historical train operation data; Determine the operation plan of regional rail transit of different systems by performing deduction based on the driving data and the cross-system train operation diagram; Based on the operation plans of the regional rail transit of different standards and the dispatching system stations in each area, the train operation is controlled.
[0096] In another aspect, the present application further provides a computer program product, the computer program product comprising a computer program, the computer program may be stored on a non-transitory computer-readable storage medium, and when the computer program is executed by a processor, the computer can execute the steps of the integrated control operation method for regional rail transit provided by the above methods, for example, including: Determine the cross-system train operation diagram based on historical train operation data; Determine the operation plan of regional rail transit of different systems by performing deduction based on the driving data and the cross-system train operation diagram; Based on the operation plans of the regional rail transit of different standards and the dispatching system stations in each area, the train operation is controlled.
[0097] The device embodiments described above are merely illustrative, wherein the units described as separate components may or may not be physically separated, and the components displayed as units may or may not be physical units, that is, they may be located in one place, or they may be distributed on multiple network units. Some or all of the modules may be selected according to actual needs to achieve the purpose of the scheme of this embodiment. Ordinary technicians in this field can understand and implement it without paying creative labor.
[0098] Through the description of the above implementation methods, those skilled in the art can clearly understand that each implementation method can be implemented by means of software plus a necessary general hardware platform, and of course, can also be implemented by hardware. Based on this understanding, the above technical solution is essentially or the part that contributes to the prior art can be embodied in the form of a software product, and the computer software product can be stored in a computer-readable storage medium, such as ROM / RAM, a disk, an optical disk, etc., including a number of instructions for a computer device (which can be a personal computer, a server, or a network device, etc.) to execute the methods described in each embodiment or some parts of the embodiments.
[0099] It should also be noted that the terms "first", "second", etc. in the embodiments of the present application are used to distinguish similar objects, and are not used to describe a specific order or sequence. It should be understood that the terms used in this way can be interchangeable under appropriate circumstances, so that the embodiments of the present application can be implemented in an order other than those illustrated or described here, and the objects distinguished by "first" and "second" are generally of the same type, and the number of objects is not limited. For example, the first object can be one or more.
[0100] In the embodiments of the present application, the term "and / or" describes the association relationship of the associated objects, indicating that three relationships may exist. For example, A and / or B may represent: A exists alone, A and B exist at the same time, and B exists alone. The character " / " generally indicates that the associated objects before and after are in an "or" relationship.
[0101] "Determine B based on A" in the embodiments of the present application means that the factor A should be considered when determining B. It is not limited to "B can be determined based on A alone", but should also include: "Determine B based on A and C", "Determine B based on A, C and E", "Determine C based on A, and further determine B based on C", etc. In addition, it can also include taking A as a condition for determining B, for example, "When A meets the first condition, use the first method to determine B"; for another example, "When A meets the second condition, determine B", etc.; for another example, "When A meets the third condition, determine B based on the first parameter", etc. Of course, it can also be a condition that takes A as a factor for determining B, for example, "When A meets the first condition, use the first method to determine C, and further determine B based on C", etc.
[0102] In the embodiments of the present application, the term "plurality" refers to two or more than two, and other quantifiers are similar.
[0103] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present application, rather than to limit it. Although the present application has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or make equivalent replacements for some of the technical features therein. However, these modifications or replacements do not deviate the essence of the corresponding technical solutions from the spirit and scope of the technical solutions of the embodiments of the present application.
Claims
1. A control and integrated operation system for regional rail transit, characterized in that: include: Dispatching command module, parallel simulation module and operation control module; The dispatching and commanding module is used to determine a cross-standard train operation diagram based on historical train operation data; input the cross-standard train operation diagram into the parallel deduction module, and obtain the operation plan of the different-standard regional rail transit output by the parallel deduction module; and send the operation plan of the different-standard regional rail transit to the operation control module; The parallel deduction module is used to obtain driving data; perform deduction based on the driving data and the cross-standard train operation diagram to determine the operation plan of the rail transit in different standards areas; The operation control module is used to control the train operation based on the operation plans of the regional rail transit of different standards and the dispatching system stations of each area.
2. The integrated control and operation system for regional rail transit according to claim 1 is characterized in that: The train historical operation data includes historical operation data of trains on multiple lines; The dispatching and commanding module is specifically used for: Based on the historical operation data of the trains on the multiple lines, a unified train operation diagram is compiled; the unified train operation diagram includes operation plans of the trains on the multiple lines; The unified train operation diagram is split into multiple cross-standard train operation diagrams; the cross-standard train operation diagram includes the operation plan of trains on a single line.
3. The integrated control and operation system for regional rail transit according to claim 1 is characterized in that: The parallel deduction module is specifically used for: Based on the cross-standard train operation diagram, passenger flow simulation and train operation simulation are performed on the driving data to determine the spatiotemporal distribution prediction information of passenger flow and the spatiotemporal distribution prediction information of trains; The passenger flow temporal and spatial distribution prediction information is matched with the train temporal and spatial distribution prediction information to determine the operation plan.
4. The integrated control and operation system for regional rail transit according to claim 1 is characterized in that: The operation control module is also used for: In the first interference situation, a dynamic adjustment algorithm is used to determine an adjustment plan; Based on the adjustment plan, adjusting the running speed of the disturbed train; In the second interference situation, the driving situation is deduced based on the fault type, section location and time period information; Determine an emergency response plan based on the driving situation; Based on the emergency response plan, adjust the operation of the disturbed train; The interference degree of the second interference situation is higher than that of the first interference situation.
5. The integrated control and operation system for regional rail transit according to claim 1 is characterized in that: The operation control module is specifically used for: In the case where a turnout exists or a platform exists or both a turnout and a platform exist, the dispatching system station based on the respective areas controls the train to operate in a fixed block mode; In the absence of a turnout and a platform, the train operation mode is determined based on the distance to the preceding vehicle.
6. The integrated control and operation system for regional rail transit according to claim 5 is characterized in that: In the case where there is no turnout and no platform, the operation control module is specifically used to: When the leading vehicle is beyond the sight range, control the train to run at the preset speed; Under the condition that the preceding vehicle is within the sight range, determine the current position of the train, obstacle detection results and the current status of the signal; Determining movement authorization based on the obstacle detection result and the current state of the signal; Determining a train speed curve based on the current position of the train, the movement authorization and the train emergency braking running distance; The train operation is controlled based on the train speed profile.
7. The integrated control and operation system for regional rail transit according to claim 6 is characterized in that: When the vehicle ahead is within the sight range, the operation control module is specifically used to: When there are no obstacles and no traffic lights within the sight range, or when there is only a traffic light and the current state of the traffic light is a preset state, the movement authorization end point is determined based on the far end of the sight range; When only an obstacle exists within the sight range, or when both the obstacle and the signal light exist and the signal light state is the preset state, determining the movement authorization end point based on the position of the obstacle; When there is only a traffic light within the sight range and the current state of the traffic light is a non-preset state, determining the movement authorization end point based on the position of the traffic light; When both the obstacle and the signal light exist within the sight range and the current state of the signal light is a non-preset state, the movement authorization end point is determined based on the positions of the obstacle and the signal light.
8. The integrated control and operation system for regional rail transit according to claim 6 is characterized in that: When the vehicle ahead is within the sight range, the operation control module is specifically used to: Determine the train emergency braking running distance based on the train emergency braking initial speed, the train emergency braking delay time, the train traction acceleration, the train coasting time, the train emergency braking terminal speed and the train emergency braking rate; and determine the train safe braking distance based on the train current position and the movement authorization; When the train emergency braking distance is less than or equal to the train safety braking distance, the train speed curve is determined based on the train emergency braking distance.
9. The integrated control and operation system for regional rail transit according to claim 8 is characterized in that: The calculation method of the train emergency braking running distance is as follows: in, is the emergency braking distance of the train, is the initial emergency braking speed of the train, is the train emergency braking delay time, is the train traction acceleration, is the train coasting time, is the final emergency braking speed of the train, is the emergency braking rate of the train.
10. A method for integrated control and operation of regional rail transit, characterized in that: Applied to the integrated control and operation system for regional rail transit, the integrated control and operation system for regional rail transit includes a dispatching command module, a parallel deduction module and an operation control module; The method comprises: Determine the cross-system train operation diagram based on historical train operation data; Determine the operation plan of regional rail transit of different systems by performing deduction based on the driving data and the cross-system train operation diagram; Based on the operation plans of the regional rail transit of different standards and the dispatching system stations in each area, the train operation is controlled.
Citation Information
Patent Citations
Rail transit parallel deduction system and method
CN112308332A
Adjusting method and device for train working diagram and train
CN114298669A
Driving command decision-making system and scheduling method of driving command decision-making system
CN115027535A
Method and device for determining operation adjustment scheme
CN115471049A
Regional multi-line dispatching system based on cloud architecture and train thereof
CN115837928A
Cited By
Multi-system rail transit integrated automatic adjusting device, method, equipment and medium
CN119928955A