Sludge solar drying system with sludge temporary storage facility and operation method

By introducing sludge temporary storage facilities into the sludge solar drying system and adjusting the sludge treatment volume based on environmental data, the seasonal fluctuations in the sludge drying capacity are solved, and the efficiency and quality of sludge drying are improved.

CN119019075AActive Publication Date: 2024-11-26CHINA THREE GORGES CORPORATION +1
View PDF 5 Cites 0 Cited by

Patent Information

Application Number
CN202411242013.X
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-05
Publication Date
2024-11-26
Estimated Expiration
2044-09-05

AI Technical Summary

Technical Problem

In sludge solar energy drying technology, sludge treatment capacity fluctuates within the year, resulting in low winter capacity and high summer processing capacity, and the inability to maximize solar energy utilization.

Method used

A sludge solar drying system with sludge temporary storage facilities was designed. By obtaining the ambient temperature, humidity and solar radiation intensity of the day, the ideal sludge moisture evaporation and processing capacity were calculated, and whether it was necessary to store it in the temporary storage facilities. Or take out the sludge for drying and optimize the sludge drying scheme.

Benefits of technology

It effectively solves the seasonal fluctuations in the drying capacity of sludge, improves the efficiency and quality of sludge drying, and ensures treatment under suitable climatic conditions.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119019075A_ABST
    Figure CN119019075A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of sludge drying, and discloses a sludge solar drying system with a sludge temporary storage facility and an operation method, in the sludge solar drying system with the sludge temporary storage facility, the design of the storage volume of the sludge temporary storage facility is based on local climate conditions, mainly temperature, humidity and solar radiation intensity. According to the operation method, the ideal sludge evaporation capacity and the sludge treatment capacity of the day are calculated by obtaining the average environment temperature, the average environment humidity and the average solar radiation intensity of the day, and whether sludge is stored in the temporary storage facility or taken out of the temporary storage facility to be dried or not is judged. According to the invention, the problem that the drying capability of a sludge solar drying technology in winter or rainy seasons is not uniformly distributed is effectively solved, and the sludge can be dried under proper weather conditions, so that the sludge drying efficiency and quality are improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of sludge drying, and in particular to a sludge solar drying system with sludge temporary storage facilities and an operation method. Background Art

[0002] Solar sludge drying method uses solar energy as the main energy source and combines it with traditional greenhouse drying technology to dry and stabilize sludge. This method has the advantages of low energy consumption, low operating costs, simple operation, and stable operation. Solar drying devices usually consist of ground structures, greenhouses, and mud turning machines, and some are also equipped with fans to accelerate water evaporation.

[0003] In the prior art, the daily sludge intake or processing volume of the sludge drying greenhouse fluctuates slightly and is generally a fixed value. In order to maximize the use of solar energy and increase processing capacity, the designed processing volume is generally based on the average daily processing volume throughout the year. However, sludge solar drying technology uses solar energy as an energy source, and its processing capacity is closely related to weather conditions, so the sludge processing capacity often fluctuates throughout the year, that is, the sludge capacity is low in winter and the sludge drying does not meet the standards; the sludge processing capacity is high in summer, but the amount of sludge available for drying is insufficient, resulting in the failure to maximize the use of solar energy. Summary of the invention

[0004] In view of this, the present invention provides a sludge solar drying system and operation method with sludge temporary storage facilities to solve the problem in existing sludge solar drying technology that the sludge treatment capacity fluctuates within the year, resulting in the failure to maximize the utilization of solar energy.

[0005] In a first aspect, the present invention provides an operation method of a sludge solar drying system with a sludge temporary storage facility, comprising:

[0006] Obtain the average ambient temperature, average ambient humidity, and average solar radiation intensity for the day;

[0007] Calculate the ideal sludge water evaporation amount and sludge treatment capacity of the day, and obtain the amount of sludge that needs to be treated on the day;

[0008] Determine whether to store sludge in a sludge temporary storage facility in a sludge solar drying system or to take out sludge from the sludge temporary storage facility for drying;

[0009] If the difference between the sludge treatment capacity and the amount of sludge that needs to be treated on the day is a negative value, the sludge will be stored in the sludge temporary storage facility;

[0010] If the difference between the sludge treatment capacity and the amount of sludge that needs to be treated on the day is a positive value, the sludge will be taken out from the sludge temporary storage facility for drying.

[0011] Beneficial effect: The present invention calculates the sludge treatment capacity of the sludge solar drying system with sludge temporary storage facilities and the amount of sludge that needs to be treated on the day, and judges the difference so as to adjust the sludge storage amount or the drying amount, so as to optimize the sludge drying plan, and effectively solves the problem of uneven distribution of drying capacity of sludge solar drying technology in winter or rainy season, and ensures that the sludge can be dried under suitable climatic conditions, thereby improving the efficiency and quality of sludge drying.

[0012] In an optional implementation, it also includes:

[0013] Calculate the sludge storage capacity and sludge processing capacity of the sludge solar drying system with sludge temporary storage facilities;

[0014] Among them, the method for calculating the storage capacity of the sludge temporary storage facility in the sludge solar drying system with the sludge temporary storage facility includes:

[0015] Obtain the local average temperature and average humidity for each month over the years, and obtain the monthly average solar radiation intensity;

[0016] Calculate the ideal monthly sludge water evaporation;

[0017] Calculate the annual average reference daily evaporation based on the monthly ideal sludge water evaporation;

[0018] Calculate the design daily evaporation of the sludge solar drying system with sludge temporary storage facilities, and set the design daily evaporation to be no greater than the annual average reference daily evaporation;

[0019] Calculate the ratio of the ideal sludge water evaporation in each month of the year to the designed daily evaporation, and calculate the evaporation compensation coefficient of each month, and then calculate the sum of the evaporation compensations of multiple consecutive months in the year, and select the maximum value;

[0020] The reference storage capacity and design storage capacity of the sludge storage facility are calculated based on the maximum value of the evaporation compensation amount for multiple consecutive months throughout the year.

[0021] Beneficial effect: The present invention calculates the reference storage capacity in the sludge storage system according to the local average temperature, average humidity and average solar radiation intensity month by month over the years, so as to match the storage capacity of the sludge temporary storage facility with the drying capacity, avoid excessive accumulation of sludge or insufficient moisture content before leaving the factory, and optimize the sludge drying plan.

[0022] In an optional embodiment, the design daily evaporation is set to 0.8 to 1 times the annual average reference daily evaporation.

[0023] Beneficial effect: The present invention sets the designed daily evaporation to be no greater than the annual average reference daily evaporation, which can ensure the stability of the operation of the sludge solar drying system with sludge temporary storage facilities.

[0024] In an optional embodiment, the designed storage capacity of the sludge temporary storage facility is not less than 120% of the reference storage capacity.

[0025] Beneficial effect: The present invention sets a certain redundancy for the design storage capacity of the sludge solar drying system with sludge temporary storage facilities, which can improve the stability of the sludge solar drying system with sludge temporary storage facilities and avoid the sludge solar drying system with sludge temporary storage facilities from being affected by unexpected severe weather.

[0026] In a second aspect, the present invention further provides a sludge solar drying system with a sludge temporary storage facility, to cooperate with the above-mentioned operation method of the sludge solar drying system with a sludge temporary storage facility, comprising:

[0027] Greenhouse: the greenhouse is equipped with sludge temporary storage facilities and sludge drying platform, and the greenhouse is equipped with air inlets and outlets;

[0028] A first sludge conveying pipe, the first sludge conveying pipe is connected to the sludge temporary storage facility and the sludge drying platform;

[0029] Mud turning equipment, which is movably arranged on the drying platform.

[0030] In an optional embodiment, the sludge temporary storage facility is arranged below the sludge drying platform.

[0031] Beneficial effects: The present invention arranges the sludge temporary storage facility under the sludge drying platform, which reduces the land occupied by the sludge solar drying system with the sludge temporary storage facility, makes the sludge drying equipment more integrated, facilitates the allocation of sludge storage and drying, and improves the efficiency of sludge drying.

[0032] In an optional embodiment, the bottom of the sludge temporary storage facility is a curved surface or a slope.

[0033] Beneficial effects: The present invention makes the bottom of the sludge temporary storage facility an arc surface or an inclined surface, so that the sludge stored in the sludge temporary storage facility can slide to the bottom, making it easy to take the sludge out of the sludge temporary storage facility.

[0034] In an optional embodiment, the sludge solar drying system with the sludge temporary storage facility further includes load-bearing columns, and a plurality of load-bearing columns are arranged between the sludge temporary storage facility and the sludge drying platform.

[0035] Beneficial effect: According to the present invention, a load-bearing column is arranged between the sludge temporary storage facility and the sludge drying platform to improve the stability of the sludge drying platform.

[0036] In an optional embodiment, a cleaning device is provided in the sludge temporary storage facility.

[0037] Beneficial effect: The present invention facilitates flushing and cleaning of the interior of the sludge temporary storage facility by providing a cleaning piece.

[0038] In an optional embodiment, the mud turning device includes:

[0039] Tracks, multiple tracks are arranged in parallel on the sludge drying platform;

[0040] A crossbeam, which is movably arranged on a track;

[0041] Rollers, which are movably mounted on the crossbeam and movably connected to the track;

[0042] Mud turning teeth, a plurality of mud turning teeth are arranged at the bottom of the crossbeam;

[0043] A mud spreading bucket is movably arranged on the crossbeam.

[0044] Beneficial effect: The present invention can improve the support capacity of the crossbeam by arranging the crossbeam on multiple tracks, and avoid uneven spreading of the sludge by the mud turning teeth due to excessive deflection of the crossbeam when laying and turning the sludge on the sludge drying platform.

[0045] In an optional embodiment, the greenhouse includes walls and a roof, the walls are suitable for being vertically set on the building ground, the air inlet and the air outlet are set on two opposite walls, the air outlet is lower than the air inlet, the air outlet is located above the sludge drying platform, and the roof is set on the top of the wall.

[0046] Beneficial effect: The present invention sets the height of the air outlet to be lower than the height of the air inlet. When the external air is blown into the greenhouse, a strong turbulence can be created on the sludge surface, thereby accelerating the drying of the sludge.

[0047] In an optional embodiment, the sludge solar drying system with sludge temporary storage facilities also includes a fan, and the fan is arranged on the air inlet and / or the air outlet. BRIEF DESCRIPTION OF THE DRAWINGS

[0048] In order to more clearly illustrate the specific implementation methods of the present invention or the technical solutions in the prior art, the drawings required for use in the specific implementation methods or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are some implementation methods of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0049] Figure 1 It is a structural schematic diagram of a sludge solar drying system with sludge temporary storage facilities according to an embodiment of the present invention;

[0050] Figure 2 This is a schematic structural diagram of a sludge solar drying system with sludge temporary storage facilities in an embodiment of the present invention, with the roof and walls removed;

[0051] Figure 3 The present invention is a schematic structural diagram of a sludge temporary storage facility and a sludge drying platform in a sludge solar drying system with a sludge temporary storage facility according to an embodiment of the present invention.

[0052] Description of reference numerals:

[0053] 1. Greenhouse; 101. Sludge temporary storage facility; 102. Sludge drying platform; 103. Air inlet; 104. Air outlet; 105. Wall; 106. Roof;

[0054] 2. The first mud pipe;

[0055] 3. Mud turning equipment; 301. Track; 302. Crossbeam; 303. Roller; 304. Mud turning teeth; 305. Mud spreading bucket; 306. Pump body;

[0056] 4. Load-bearing columns;

[0057] 5. Cleaning parts;

[0058] 6. The second mud pipe. DETAILED DESCRIPTION

[0059] In order to make the purpose, technical solution and advantages of the embodiments of the present invention clearer, the technical solution in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative work are within the scope of protection of the present invention.

[0060] Combine the following Figures 1 to 3 , describing an embodiment of the present invention.

[0061] According to an embodiment of the present invention, on the one hand, a method for operating a sludge solar drying system with a sludge temporary storage facility is provided, comprising:

[0062] Obtain the average ambient temperature, average ambient humidity, and average solar radiation intensity for the day;

[0063] Calculate the ideal sludge water evaporation amount and sludge treatment capacity of the day, and obtain the amount of sludge that needs to be treated on the day;

[0064] Determine whether to store sludge in a sludge temporary storage facility 101 in a sludge solar drying system with a sludge temporary storage facility or to take out sludge from the sludge temporary storage facility 101 for drying;

[0065] If the difference between the sludge treatment capacity and the amount of sludge to be treated on that day is a negative value, the sludge is stored in the sludge temporary storage facility 101;

[0066] If the difference between the sludge treatment capacity and the amount of sludge that needs to be treated on that day is a positive value, the sludge is taken out from the sludge temporary storage facility 101 for drying.

[0067] Specifically, in this embodiment, the average ambient temperature of the day is t, the average ambient humidity is RH, the average solar radiation intensity is E, and the ideal sludge water evaporation amount of the day is m v , reference water evaporation is m f , the sludge treatment capacity on that day is m fs .

[0068] In this embodiment, the ideal sludge water evaporation amount m on that day is calculated according to the following formula (1): v .

[0069] m v =0.055×t-0.029×RH+0.0046×E+0.94 (1)

[0070] From the perspective of stable system operation, the reference water evaporation volume m f Not greater than the ideal sludge water evaporation volume m v .

[0071] m f ≤εm v (2)

[0072] Among them, ε is the design coefficient, and the value range of ε is 0.8 to 1.

[0073] Greenhouse 1 daily sludge treatment capacity m fs And the reference water evaporation of greenhouse 1 on the same day m f There are the following relationships:

[0074]

[0075] Among them, W in is the moisture content of the incoming sludge, unit: kilograms of water per kilogram of dry sludge;

[0076] W o The moisture content of sludge at discharge, unit: kilograms of water per kilogram of dry sludge;

[0077] S is the design area of ​​the sludge solar drying system with sludge temporary storage facilities, unit: square meters.

[0078] The actual amount of sludge on that day is the sludge treatment capacity m s , the amount of sludge that needs to be stored m c for:

[0079] m c =m fs -m s (4)

[0080] If m c If it is a negative number, it means that sludge m is stored in the sludge temporary storage facility 101 on that day. c kg, otherwise, the stored sludge m is taken from the sludge temporary storage facility 101 c Kg for drying.

[0081] The present invention calculates the sludge treatment capacity of a sludge solar drying system with a sludge temporary storage facility and obtains the amount of sludge that needs to be treated on the day, and judges the difference so as to adjust the sludge storage amount or the drying amount, thereby optimizing the sludge drying plan, and effectively solves the problem of uneven distribution of drying capacity of sludge solar drying technology in winter or rainy season, ensuring that the sludge can be dried under suitable climatic conditions, thereby improving the efficiency and quality of sludge drying.

[0082] In one embodiment, the operation method of the sludge solar drying system with sludge temporary storage facilities further includes:

[0083] Calculate the sludge storage capacity and sludge processing capacity of the sludge solar drying system with sludge temporary storage facilities;

[0084] The method for calculating the storage capacity of the sludge temporary storage facility 101 in the sludge solar drying system with the sludge temporary storage facility includes:

[0085] Obtain the local average temperature and average humidity for each month over the years, and obtain the monthly average solar radiation intensity;

[0086] Calculate the ideal monthly sludge water evaporation;

[0087] Calculate the annual average reference daily evaporation based on the monthly ideal sludge water evaporation;

[0088] Calculate the design daily evaporation of the sludge solar drying system with sludge temporary storage facilities, and set the design daily evaporation to be no greater than the annual average reference daily evaporation;

[0089] Calculate the ratio of the ideal sludge water evaporation in each month of the year to the designed daily evaporation, and calculate the evaporation compensation coefficient of each month, and then calculate the sum of the evaporation compensations of multiple consecutive months in the year, and select the maximum value;

[0090] The reference storage capacity and the designed storage capacity of the sludge temporary storage facility 101 are calculated according to the maximum value of the evaporation compensation amount and the evaporation compensation amount for a plurality of consecutive months throughout the year.

[0091] The reference storage capacity and the designed storage capacity of the sludge temporary storage facility 101 are calculated according to the maximum value of the evaporation compensation amount and the evaporation compensation amount for a plurality of consecutive months throughout the year.

[0092] Specifically, in this embodiment, S1: the local monthly average temperature t i and average humidity RH i , as the temperature t of the air inlet 103 of the greenhouse 1 in and humidity RH in The monthly average solar radiation intensity is E i .

[0093] Where i refers to the month, with a value from 1 to 12;

[0094] S2: Calculate the ideal daily evaporation of sludge per month m according to the following formula (5): vi .

[0095]

[0096] Among them, t i is the average temperature in month i, in degrees Celsius;

[0097] RH i is the average humidity in month i;

[0098] E i is the average solar radiation intensity in month i, in watts per square meter;

[0099] m vi is the ideal daily evaporation of sludge water in month i, unit: kilograms per square meter per day;

[0100] S3: Annual average reference daily evaporation The calculation method is:

[0101]

[0102] When designing the sludge solar drying system, it is necessary to consider the local climate conditions and the annual average reference daily evaporation calculated under these conditions. From the perspective of stable operation of the system, the design evaporation should not be greater than the annual average reference daily evaporation.

[0103]

[0104] in, is the annual average reference daily evaporation, unit: kilograms per square meter per day;

[0105] D i is the number of days in month i;

[0106] m h is the design daily evaporation, unit: kilograms per square meter per day;

[0107] ε is the design coefficient.

[0108] S4: Calculate the ideal sludge water evaporation volume m for 12 months vi Design daily evaporation m h The ratio is α i , and calculate the evaporation compensation coefficient for each month as 1-α i , coefficient 1-α i When it is a positive number, the monthly drying capacity of the sludge solar drying system with sludge temporary storage facilities is insufficient, and sludge storage is required. Take N as 1 to 6, calculate the sum of the evaporation compensation for N consecutive months in 12 months, and select the maximum value Mv.

[0109] The actual sludge treatment capacity generally does not change much over time and can be regarded as the designed sludge treatment capacity. The relationship between the sludge treatment capacity of greenhouse 1 and the designed daily evaporation capacity of greenhouse 1 is as follows:

[0110]

[0111] Since the moisture content of the sludge entering and leaving the greenhouse 1 is related to the sludge treatment process and is generally a fixed value for a specific greenhouse 1, the designed daily processing capacity of the greenhouse 1 is directly proportional to the designed daily evaporation capacity of the greenhouse 1.

[0112] The reference storage capacity M of the sludge temporary storage facility 101 is:

[0113] M=30×Mv×m s (9)

[0114] The designed storage capacity Md of the sludge temporary storage facility 101 is:

[0115] Md=M*η (10)

[0116] Wherein, S is the design area of ​​the sludge solar drying system with sludge temporary storage facilities, unit: square meters;

[0117] M is the reference storage volume of sludge, unit: kg;

[0118] Md is the designed storage capacity of sludge, unit: kg;

[0119] η is a reference coefficient greater than 1.

[0120] W in is the moisture content of the incoming sludge, unit: kilograms of water per kilogram of dry sludge;

[0121] W o The moisture content of sludge at discharge, unit: kilograms of water per kilogram of dry sludge;

[0122] m s It is the sludge treatment capacity, unit: kilogram per square meter per day.

[0123] In this embodiment, the amount of sludge that needs to be stored is m c Not greater than the designed sludge storage capacity Md.

[0124] The present invention calculates the reference storage capacity in the sludge storage system according to the local average temperature, average humidity and average solar radiation intensity month by month over the years, so as to ensure that the storage capacity and drying capacity of the sludge are matched when the sludge solar drying system with sludge temporary storage facilities is in operation throughout the year, avoid insufficient drying capacity due to excessive sludge accumulation or insufficient sludge drying capacity due to insufficient sludge storage, and optimize the sludge drying plan.

[0125] In one embodiment, the designed evaporation capacity is set to 0.8 to 1 times the annual average reference daily evaporation capacity.

[0126] In this embodiment, the preferred design evaporation capacity is set to 0.8 times the annual average reference daily evaporation capacity.

[0127] The present invention sets the designed evaporation capacity to be no greater than the annual average reference daily evaporation capacity, which can ensure the stability of the operation of the sludge solar drying system with sludge temporary storage facilities.

[0128] In one embodiment, the designed storage capacity of the sludge temporary storage facility 101 is not less than 120% of the reference storage capacity, and is preferably designed to be 120% of the reference storage capacity.

[0129] The present invention sets a certain redundancy for the design storage capacity of the sludge solar drying system with sludge temporary storage facilities, which can improve the stability of the sludge solar drying system with sludge temporary storage facilities and avoid the sludge solar drying system with sludge temporary storage facilities being affected by unexpected severe external climate.

[0130] In this embodiment, it is assumed that the ambient temperature, humidity and solar radiation of a certain place are as shown in Table 1 below, and the construction area of ​​the greenhouse 1 is 20,000 square meters. According to the above calculation method, the following results can be obtained:

[0131]

[0132] Table 1 Monthly average temperature, humidity and solar radiation in a certain place

[0133] According to the above formulas (1) to (10), the annual average reference daily evaporation is 44.7t, and the design daily evaporation is 35.8t. As shown in Table 1, from November to February of the following year, the monthly evaporation is less than the reference evaporation. At this time, the calculated M v It is 1.02, considering the abundance is 20%, that is, the sludge temporary storage equipment needs to meet the storage capacity of at least 1.22 months.

[0134] According to an embodiment of the present invention, on the other hand, Figures 1 to 3 As shown, a sludge solar drying system with a sludge temporary storage facility is also provided, which is used to cooperate with the operation method of the above-mentioned sludge solar drying system with a sludge temporary storage facility, including a greenhouse 1, a first mud conveying pipe 2 and a mud turning device 3. A sludge temporary storage facility 101 and a sludge drying platform 102 are provided in the greenhouse 1, and an air inlet 103 and an air outlet 104 are provided on the greenhouse 1. The first mud conveying pipe 2 connects the sludge temporary storage facility 101 and the sludge drying platform 102, and the mud turning device 3 is movably arranged on the drying platform.

[0135] Specifically, the greenhouse 1 is not specifically limited in this embodiment. To conform to the actual situation, the greenhouse 1 in this embodiment adopts a shed body with a transparent structure on the top, and the transparent top allows solar radiation to dry the sludge on the sludge drying platform 102.

[0136] In this embodiment, the sludge temporary storage facility 101 and the sludge drying platform 102 are both arranged inside the greenhouse 1. The sludge temporary storage facility 101 and the sludge drying platform 102 are connected by a first sludge delivery pipe 2. The first sludge delivery pipe 2 is provided with a pump body 306 for pumping the sludge in the sludge temporary storage facility 101 to the sludge drying platform 102. This embodiment does not specifically limit the pump body 306. In order to conform to the actual situation, the pump body 306 in this embodiment can adopt a plunger pump.

[0137] In this embodiment, the greenhouse 1 is provided with an air inlet 103 and an air outlet 104. External air enters the greenhouse 1 through the air inlet 103 and is then output from the greenhouse 1 through the air outlet 104. During the air flow, the evaporated water vapor in the greenhouse 1 can be taken away, thereby accelerating the sludge drying.

[0138] In this embodiment, the mud turning device 3 can be operated movably on the drying platform, so as to flatten and turn the sludge output through the first mud conveying pipe 2 on the sludge drying platform 102, thereby accelerating the sludge drying process.

[0139] The present invention arranges the sludge temporary storage facility 101 and the sludge drying platform 102 in the same greenhouse 1, thereby reducing the land and other resources occupied by the additional construction of the sludge temporary storage facility 101, and at the same time facilitates the allocation of sludge storage and drying, thereby improving the efficiency of sludge drying.

[0140] In one embodiment, Figures 1 to 3 As shown, the sludge temporary storage facility 101 is arranged below the sludge drying platform 102 .

[0141] Specifically, in this embodiment, the sludge temporary storage facility 101 is arranged at the bottom of the greenhouse 1, and the sludge drying platform 102 is arranged above the sludge temporary storage facility 101. In this embodiment, a sunken space can be arranged at the bottom of the greenhouse 1 as the sludge temporary storage facility 101, and the sludge drying platform 102 is suspended in the space above the sludge temporary storage facility 101. The first mud pipe 2 is vertically arranged in the greenhouse 1, and one end of the first mud pipe 2 extends to the sludge temporary storage facility 101, and the other end extends to the sludge drying platform 102.

[0142] In this embodiment, a second sludge delivery pipe 6 is further provided in the greenhouse 1 , and the second sludge delivery pipe 6 is used to input external sludge and store it in the sludge temporary storage facility 101 .

[0143] The present invention arranges the sludge temporary storage facility 101 below the sludge drying platform 102, thereby reducing the land occupied by the sludge solar drying system with the sludge temporary storage facility and making the sludge drying equipment more integrated.

[0144] In one embodiment, Figures 1 to 3 As shown, the bottom of the sludge temporary storage facility 101 is a curved surface or an inclined surface.

[0145] Specifically, in this embodiment, the bottom of the sludge temporary storage facility 101 is an arc surface, which is concave downward and inclined toward the side of the first sludge pipe 2. When sludge is stored in the sludge temporary storage facility 101, the sludge slides to the side of the first sludge pipe 2 under its own gravity, making it easier for the first sludge pipe 2 to be pumped to the sludge drying platform 102 through the pump body 306.

[0146] In the present invention, the bottom of the sludge temporary storage facility 101 is an arc surface or an inclined surface, so that the sludge stored in the sludge temporary storage facility 101 can slide to the bottom, making it easy to take the sludge out of the sludge temporary storage facility 101.

[0147] In one embodiment, Figures 1 to 3 As shown, the sludge solar drying system with sludge temporary storage facilities also includes load-bearing columns 4 , and a plurality of load-bearing columns 4 are arranged between the sludge temporary storage facility 101 and the sludge drying platform 102 .

[0148] Specifically, in this embodiment, one side of the sludge drying platform 102 is connected to the inner wall of the greenhouse 1, and the other side is cantilevered above the sludge temporary storage facility 101. A number of load-bearing columns 4 are provided at the bottom of one side of the cantilevered sludge drying platform 102. The bottom of the load-bearing columns 4 is supported in the sludge temporary storage facility 101, which can support the sludge drying platform 102.

[0149] In this embodiment, an upper mud inlet is reserved between the sludge drying platform 102 and the sludge temporary storage facility 101, and the first mud delivery pipe 2 is arranged at the position of the upper mud inlet.

[0150] In the present invention, a load-bearing column 4 is arranged between the sludge temporary storage facility 101 and the sludge drying platform 102 to improve the stability of the sludge drying platform 102 .

[0151] In one embodiment, Figure 3 As shown, a cleaning unit 5 is provided in the sludge temporary storage facility 101 .

[0152] Specifically, in this embodiment, the cleaning component 5 is not specifically limited. In order to conform to the actual situation, in this embodiment, the cleaning component 5 is a plurality of high-pressure nozzles arranged on the inner wall of the sludge temporary storage facility 101. The water outlet direction of the high-pressure nozzle is toward the bottom arc surface of the sludge temporary storage facility 101. The high-pressure nozzle can spray high-pressure water when cleaning the inside of the sludge temporary storage facility 101 to flush the wall surface of the sludge temporary storage facility 101. The flushing waste water can be pumped out by a plunger pump.

[0153] The present invention provides a cleaning member 5 to facilitate flushing and cleaning of the interior of the sludge temporary storage facility 101 .

[0154] In one embodiment, Figure 1 and Figure 2 As shown, the mud turning device 3 includes a track 301, a beam 302, a roller 303, mud turning teeth 304 and a mud spreading bucket 305. A plurality of tracks 301 are arranged in parallel on the sludge drying platform 102. The beam 302 is movably arranged on the track 301. The roller 303 is movably installed on the beam 302. The roller 303 is movably connected to the track 301. A plurality of mud turning teeth 304 are arranged at the bottom of the beam 302. The mud spreading bucket 305 is movably arranged on the beam 302.

[0155] Specifically, the number of rails 301 is not specifically limited in this embodiment. In order to reduce the deflection of the beam 302, three rails 301 are arranged in this embodiment, which are respectively located on both sides of the greenhouse 1 and on the sludge drying platform 102 near the mud outlet of the sludge temporary storage facility 101. The three rails 301 are arranged in parallel, and the height of the rails 301 located on both sides of the greenhouse 1 is slightly higher than the height of the rails 301 set on the sludge drying platform 102.

[0156] In this embodiment, the beam 302 is perpendicular to the track 301, and three rollers 303 are correspondingly arranged at the bottom of the beam 302. The rollers 303 are correspondingly movably connected to the track 301. By moving the rollers 303 on the track 301, the mud bucket 305 on the beam 302 can be driven to move on the sludge drying platform 102.

[0157] In this embodiment, the mud bucket 305 is movably arranged on the beam 302 and can move back and forth in the horizontal direction along the beam 302. The mud bucket 305 is funnel-shaped, and the top opening is used to receive the sludge from the first mud delivery pipe 2, and the bottom opening can spread the sludge onto the sludge drying platform 102.

[0158] In this embodiment, a plurality of mud turning teeth 304 are vertically provided on the cross beam 302, and the bottom of the mud turning teeth 304 can be inserted into the sludge on the sludge drying platform 102. By moving the cross beam 302, the mud turning teeth 304 can turn over the sludge spread on the sludge drying platform 102 and spread it evenly to speed up the sludge drying.

[0159] The present invention arranges the crossbeam 302 on a plurality of tracks 301 to improve the support capacity of the crossbeam 302 and prevent the mud turning teeth 304 from spreading the sludge unevenly due to excessive deflection of the crossbeam 302 when the sludge is laid on the sludge drying platform 102 and turned over.

[0160] In one embodiment, Figure 1 As shown, the greenhouse 1 includes a wall 105 and a roof 106. The wall 105 is suitable for being vertically arranged on the building ground. The air inlet 103 and the air outlet 104 are arranged on two opposite walls 105. The height of the air outlet 104 is lower than that of the air inlet 103. The air outlet 104 is located above the sludge drying platform 102. The roof 106 is arranged on the top of the wall 105.

[0161] Specifically, in the present embodiment, the greenhouse 1 is surrounded by walls 105 and has a roof 106 on the top. The roof 106 is made of a transparent material, such as glass, transparent plastic, or the like.

[0162] In this embodiment, the air inlet 103 and the air outlet 104 are arranged on two walls 105 parallel to the track 301. The height of the air outlet 104 is at least 1 meter lower than the height of the air inlet 103, and the height of the air outlet 104 is not higher than 0.5 meters from the upper surface of the sludge drying platform 102. Such an arrangement can create a stronger turbulence on the sludge surface.

[0163] In the present invention, the height of the air outlet 104 is set to be lower than the height of the air inlet 103. When the external air is blown into the greenhouse 1, a strong turbulence can be created on the sludge surface, thereby accelerating the drying of the sludge.

[0164] In one embodiment, the sludge solar drying system with sludge temporary storage facilities further includes a fan, which is disposed on the air inlet 103 and / or the air outlet 104 .

[0165] Specifically, in this embodiment, an air supply fan is arranged at the air inlet 103 to blow external air into the greenhouse 1, and a fan may not be arranged at the air outlet 104.

[0166] Although the embodiments of the present invention have been described in conjunction with the accompanying drawings, those skilled in the art may make various modifications and variations without departing from the spirit and scope of the present invention, and such modifications and variations are all within the scope defined by the appended claims.

Claims

1. A method for operating a sludge solar drying system with a sludge temporary storage facility, characterized in that: include: Obtain the average ambient temperature, average ambient humidity, and average solar radiation intensity for the day; Calculate the ideal sludge water evaporation amount and sludge treatment capacity of the day, and obtain the amount of sludge that needs to be treated on the day; Determining whether to store sludge in a sludge temporary storage facility (101) in a sludge solar drying system with a sludge temporary storage facility or to remove sludge from the sludge temporary storage facility (101) for drying; If the difference between the sludge treatment capacity and the amount of sludge that needs to be treated on that day is a negative value, the sludge is stored in the sludge temporary storage facility (101); If the difference between the sludge treatment capacity and the amount of sludge that needs to be treated on that day is a positive value, the sludge is taken out from the sludge temporary storage facility (101) for drying.

2. The method for operating the sludge solar drying system with sludge temporary storage facilities according to claim 1, characterized in that: Also includes: Calculate the sludge storage capacity and sludge processing capacity of the sludge solar drying system with sludge temporary storage facilities; The method for calculating the storage capacity of the sludge temporary storage facility (101) in the sludge solar drying system with the sludge temporary storage facility includes: Obtain the local average temperature and average humidity for each month over the years, and obtain the monthly average solar radiation intensity; Calculate the ideal monthly sludge water evaporation; Calculate the annual average reference daily evaporation based on the monthly ideal sludge water evaporation; Calculate the design daily evaporation of the sludge solar drying system with sludge temporary storage facilities, and set the design daily evaporation to be no greater than the annual average reference daily evaporation; Calculate the ratio of the ideal sludge water evaporation in each month of the year to the designed daily evaporation, and calculate the evaporation compensation coefficient of each month, and then calculate the sum of the evaporation compensations of multiple consecutive months in the year, and select the maximum value; The reference storage capacity and design storage capacity of the sludge solar drying system with sludge temporary storage facilities are calculated based on the maximum value of the evaporation compensation amount and the maximum value of the evaporation compensation amount for multiple consecutive months throughout the year.

3. The method for operating the sludge solar drying system with sludge temporary storage facilities according to claim 2, characterized in that: The designed daily evaporation is set to 0.8 to 1 times the annual average reference daily evaporation.

4. The method for operating the sludge solar drying system with sludge temporary storage facilities according to claim 2, characterized in that: The designed storage capacity of the sludge storage facility shall not be less than 120% of the reference storage capacity.

5. A sludge solar drying system with sludge temporary storage facilities, in conjunction with the operation method of the sludge solar drying system with sludge temporary storage facilities as claimed in any one of claims 1 to 4, characterized in that: include: A greenhouse (1), wherein a sludge temporary storage facility (101) and a sludge drying platform (102) are provided in the greenhouse (1), and an air inlet (103) and an air outlet (104) are provided on the greenhouse (1); A first sludge conveying pipe (2), the first sludge conveying pipe (2) connecting the sludge temporary storage facility (101) and the sludge drying platform (102); A mud turning device (3), wherein the mud turning device (3) is movably arranged on the drying platform.

6. The sludge solar drying system with sludge temporary storage facilities according to claim 5 is characterized in that: The sludge temporary storage facility (101) is arranged below the sludge drying platform (102).

7. The sludge solar drying system with sludge temporary storage facilities according to claim 6, characterized in that: The bottom of the sludge temporary storage facility (101) is a curved surface or an inclined surface.

8. The sludge solar drying system with sludge temporary storage facilities according to claim 5, characterized in that: Also includes: A load-bearing column (4), wherein a plurality of the load-bearing columns (4) are arranged between the sludge temporary storage facility (101) and the sludge drying platform (102).

9. The sludge solar drying system with sludge temporary storage facilities according to claim 5, characterized in that: The sludge temporary storage facility (101) is provided with a cleaning unit (5).

10. The sludge solar drying system with sludge temporary storage facilities according to claim 5, characterized in that: The mud turning device (3) comprises: Tracks (301), a plurality of tracks (301) are arranged in parallel on the sludge drying platform (102); A crossbeam (302), wherein the crossbeam (302) is movably arranged on the track (301); A roller (303), wherein the roller (303) is movably mounted on the crossbeam (302), and the roller (303) is movably connected to the track (301); Mud-turning teeth (304), a plurality of mud-turning teeth (304) are arranged at the bottom of the crossbeam (302); A mud distributing bucket (305), wherein the mud distributing bucket (305) is movably arranged on the crossbeam (302).

11. The sludge solar drying system with sludge temporary storage facilities according to claim 5, characterized in that: The greenhouse (1) comprises: A wall (105), wherein the wall (105) is suitable for being vertically arranged on the ground of a building, the air inlet (103) and the air outlet (104) are arranged on two opposite walls (105), the height of the air outlet (104) is lower than that of the air inlet (103), and the air outlet (104) is located above the sludge drying platform (102); A roof (106), wherein the roof (106) is arranged on the top of the wall (105).

12. The sludge solar drying system with sludge temporary storage facilities according to claim 5, characterized in that: Also includes: A fan, wherein the fan is arranged on the air inlet (103) and / or the air outlet (104).

Citation Information

Patent Citations

  • Sludge drying system combining sewage source heat pump with solar energy

    CN103359904A

  • Solar sludge drying device, sludge drying system and sludge drying method

    CN117003463A

  • Operation method of sludge drying system and sludge drying system

    CN118184096A

  • Utilization of digested sewage sludge in a fluidized bed combustion system

    DE102018007810A1

  • Utilization of digested sewage sludge in a fluidized bed plant

    DE102020000818A1