Offshore wind power installation platform and fan component hoisting method
Through the combination of four-chord truss pile legs and pile-wound pile cranes, the low efficiency and high cost of offshore wind power installation platforms in deep water and remote sea environments are solved, and more efficient fan lifting and load bearing are achieved, reducing construction Difficulty and cost.
Patent Information
- Application Number
- CN202411121803.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-15
- Publication Date
- 2024-11-26
AI Technical Summary
The existing offshore wind power installation platform has low fan installation efficiency, long lifting operation time, and difficult pile legs to build, resulting in insufficient loading capacity and high cost.
Four-chord truss pile legs and pile-winding cranes are used to drive the pile legs to lift and lower them through the lifting system and the pile-fixed crane. The ring base of the pile-winding crane is fixed on the pile-fixed crane to shorten the lifting path and reduce piles. Legs with outer diameter and occupancy of deck area to improve load bearing capacity.
It effectively shortens the lifting time of fan components, improves installation efficiency, reduces the difficulty of pile legs construction and platform cost, and increases loading capacity.
Smart Images

Figure CN119021174A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of offshore engineering platforms, and in particular to an offshore wind power installation platform and a method for hoisting wind turbine components. Background Art
[0002] The support of clean energy policies and the continuous increase in investment by countries around the world have driven the rapid growth of offshore wind power. With the implementation of GW-class offshore wind farms and large-capacity wind turbines of 15MW and above, the trend of large-scale offshore wind turbines, deep-water and offshore wind turbines has accelerated, and the large-scale wind power installation platforms have become a development trend.
[0003] As the crane capacity of wind power installation platforms increases, the operating water depth increases, and the loading capacity increases, higher requirements are placed on the strength of the pile legs. Currently, the thickness of the rack plate and the construction of the pile legs have reached their limits. If the loading capacity of the wind power installation platform is further increased, the production of thicker rack plates and the construction of pile legs will become more difficult, and the overall cost of the platform will be higher.
[0004] The planning of offshore wind farms is accelerating towards deep water and offshore development. The cycle for wind power installation ships to travel between wind turbine terminals and wind farms has become longer. The harsh sea conditions in deep water areas where offshore wind turbines are installed have also shortened the window period for wind turbine installation operations, affecting the efficiency of wind turbine installation. The installation and hoisting methods of cranes responsible for wind turbine installation play a vital role in the efficiency of wind turbine installation. Summary of the invention
[0005] One purpose of the present invention is to solve the deficiencies in the prior art and provide an offshore wind power installation platform. To solve the above technical problems, the present invention adopts the following technical solutions:
[0006] An offshore wind power installation platform, comprising:
[0007] Platform main hull;
[0008] Four-chord truss pile legs, the four-chord truss pile legs can be vertically slidably arranged on the main hull of the platform, and the four-chord truss pile legs are distributed at the four corners of the main hull of the platform;
[0009] A pile frame, the pile frame corresponding to the four-chord truss pile legs is arranged on the top deck of the platform main hull, and the pile frame is used to drive the four-chord truss pile legs to rise and fall through the lifting system; and
[0010] A pile-encircling crane comprises a base, which is fixed on a pile frame located on the side of the ship at the stern of the platform main hull. The base is supported above the top deck of the platform main hull by the pile frame. A height gap is formed between the bottom of the base and the top deck of the platform main hull. A channel for the pile-encircling crane to lift wind turbine components is formed between the two pile frames at the stern of the platform main hull.
[0011] In one embodiment, the bottom of the base is connected to the top of the pile frame, and the projection of the circumferential outer edge of the bottom of the base on the main hull of the platform does not exceed the projection of the circumferential outer edge of the pile frame on the main hull of the platform.
[0012] In one embodiment, the four-chord truss pile leg is in the form of a regular quadrilateral pile leg, and the four-chord truss pile leg includes four main chords;
[0013] The pile fixing frame includes four main frame bodies, and the four main frame bodies are arranged corresponding to four main chord rods;
[0014] The base is an annular base, and the base support is arranged at the top of the four main frames. The projection of the circumferential outer edge of the base on the main hull of the platform does not exceed the projection of the circumscribed circular surface of the four main frames on the main hull of the platform.
[0015] In one embodiment, the pile fixing frame further comprises a supporting frame body, which is connected between two adjacent main frames, and each main frame body and each supporting frame body are connected to form a pile fixing frame with an annular structure.
[0016] In one embodiment, the base is a uniform cross-section structure along the axial direction of the four-chord truss-type pile leg.
[0017] In one embodiment, the four-chord truss pile leg includes a pile shoe connected to the bottom end of the four-chord truss pile leg;
[0018] A receiving space for receiving the pile shoe is provided at the bottom of the main hull of the platform. When the pile shoe is received in the receiving space, the pile shoe does not extend beyond the bottom of the main hull of the platform.
[0019] In one embodiment, the spud is in the form of an octagonal spud.
[0020] In one embodiment, the lifting system includes a driving motor, a driving gear and a rack. The driving motor is arranged on the pile fixing frame, the driving gear is installed on the output shaft of the driving motor, and the rack is arranged on the four-chord truss pile leg and meshes with the driving gear.
[0021] In one embodiment, a storage area for storing wind turbine components is provided on the main hull of the platform, and the shortest path from the storage area to the installation position of the wind turbine components passes between two pile frames at the rear of the main hull of the platform.
[0022] One object of the present invention is to provide a method for hoisting wind turbine components, using any of the above offshore wind power installation platforms for construction, the hoisting method comprising:
[0023] Start the pile-encircling crane to lift the wind turbine components;
[0024] The pile-encircling crane drives the wind turbine components through the space between the two pile frames at the rear of the platform's main hull;
[0025] A pile-encircling crane places the wind turbine components on the pile foundation.
[0026] In one embodiment, before the step of starting the pile-encircling crane to lift the wind turbine component, the method further includes:
[0027] Drive the offshore wind power installation platform to a preset position near the pile foundation, and make the stern of the platform main hull close to the pile foundation.
[0028] It can be seen from the above technical solution that the present invention has at least the following advantages and positive effects:
[0029] In the present invention, the offshore wind power installation platform adopts a four-chord truss pile leg. Under the same environmental force and empty ship weight, the side length of the chord of the four-chord truss pile leg is smaller than the side length of the chord of the traditional three-chord pile leg, so that the diameter of the circumscribed circle of the four-chord truss pile leg is correspondingly reduced. The pile frame is arranged on the top deck of the main hull of the platform corresponding to the four-chord truss pile leg. Since the outer diameter of the four-chord truss pile leg is reduced, the outer diameter of the pile frame is also reduced accordingly, thereby reducing the unobstructed working deck area occupied by the pile leg.
[0030] In addition, the four-chord truss pile leg can enable the platform to bear a larger load. Under the same load conditions, the load borne by the four-chord truss pile leg is shared by the four main chords, so the thickness of the rack plate on each main chord can be reduced accordingly, reducing the difficulty of rack plate production and pile leg construction, and reducing the platform construction cost.
[0031] In addition, the base of the pile-circling crane is fixedly installed on the pile frame, and the base does not need to occupy the deck area, so the effective utilization space between the two pile legs at the rear of the hull is increased, which is conducive to the wind turbine tower being directly hoisted to the preset installation position through the space between the two pile legs at the rear of the hull, without having to go around the outside of the ship for hoisting, and the hoisting path is greatly shortened. Therefore, hoisting and constructing wind turbine components through the offshore wind power installation platform of this application can effectively save wind turbine hoisting time, improve hoisting operation efficiency, and help improve wind turbine installation efficiency. BRIEF DESCRIPTION OF THE DRAWINGS
[0032] Figure 1 It is a schematic front view of an offshore wind power installation platform according to one embodiment of the present invention.
[0033] Figure 2 yes Figure 1 Schematic top view of the structure shown.
[0034] Figure 3 yes Figure 1Schematic diagram of the structure shown during lifting construction as viewed from the stern side.
[0035] Figure 4 yes Figure 1 Schematic diagram of the top view of the four-chord truss pile leg in the structure shown.
[0036] Figure 5 yes Figure 1 Schematic diagram of the pile shoe extension in the structure shown.
[0037] Figure 6 yes Figure 1 Schematic diagram of pile shoe retraction in the structure shown.
[0038] Figure 7 yes Figure 4 A top view of the four-chord truss pile legs in the structure shown without the pile shoes.
[0039] Figure 8 It is a flowchart of the steps of a method for hoisting wind turbine components according to one embodiment of the present invention.
[0040] The following are the descriptions of the reference numerals:
[0041] 10- fan parts;
[0042] 100- platform main hull; 110- receiving space; 120- storage area;
[0043] 200-four-chord truss pile leg; 210-main chord; 220-support rod; 230-pile shoe;
[0044] 300- pile fixing frame; 310- main frame; 320- supporting frame;
[0045] 400-lifting system;
[0046] 500- pile encircling crane; 510- base;
[0047] 600-Pile foundation. DETAILED DESCRIPTION
[0048] Typical embodiments that embody the features and advantages of the present invention will be described in detail in the following description. It should be understood that the present invention can have various changes in different embodiments without departing from the scope of the present invention, and the descriptions and illustrations therein are essentially used for illustration purposes rather than for limiting the present invention.
[0049] In the description of the present application, it should be understood that in the embodiments shown in the drawings, the indications of directions or positional relationships (such as up, down, left, right, front and back, etc.) are only for the convenience of describing the present application and simplifying the description, rather than indicating or implying that the devices or elements referred to must have a specific orientation, be constructed and operate in a specific orientation. These descriptions are appropriate when these elements are in the positions shown in the drawings. If the descriptions of the positions of these elements change, the indications of these directions also change accordingly.
[0050] In addition, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Thus, the features defined as "first" and "second" may explicitly or implicitly include one or more of the features. In the description of this application, the meaning of "plurality" is two or more, unless otherwise clearly and specifically defined.
[0051] See also Figure 1 As shown, the offshore wind power installation platform according to the embodiment of the present invention includes a platform main hull 100 , a four-chord truss pile leg 200 , a pile fixing frame 300 and a pile-circling crane 500 .
[0052] The four-chord truss pile legs 200 can be vertically slidably arranged on the platform main hull 100, and the four-chord truss pile legs 200 are distributed at the four corners of the platform main hull 100. The pile fixing frame 300 is arranged on the deck of the platform main hull 100 corresponding to the four-chord truss pile legs 200, and the pile fixing frame 300 is used to drive the four-chord truss pile legs 200 to rise and fall through the lifting system 400.
[0053] The pile-encircling crane 500 includes a base 510, which is fixed to a pile frame 300 located on the side of the ship at the rear of the platform main hull 100. The base 510 is supported above the top deck of the platform main hull 100 by the pile frame 300, and a height interval is formed between the bottom of the base 510 and the top deck of the platform main hull 100. A passage for the pile-encircling crane 500 to hoist the wind turbine component 10 is formed between the two pile frames 300 at the rear of the platform main hull 100.
[0054] In the embodiment of the present application, the wind turbine component 10 mainly refers to the wind turbine tower. Since the wind turbine tower has the largest size, when the wind turbine tower is successfully installed through the platform and the hoisting method of the embodiment of the present application, other wind turbine components can be hoisted more efficiently.
[0055] The offshore wind power installation platform of the present application adopts a four-chord truss pile leg 200. Under the same environmental force and empty ship weight, the side length of the chord of the four-chord truss pile leg 200 is smaller than the side length of the chord of the traditional three-chord pile leg, so that the diameter of the circumscribed circle of the four-chord truss pile leg 200 is correspondingly reduced. The pile frame 300 is arranged on the top deck of the platform main hull 100 corresponding to the four-chord truss pile leg 200. Since the outer diameter of the four-chord truss pile leg 200 is reduced, the outer diameter of the pile frame 300 is also reduced accordingly, thereby reducing the unobstructed working deck area occupied by the pile leg.
[0056] In addition, the four-chord truss pile leg 200 can enable the platform to bear a larger load. Under the same load conditions, the load borne by the four-chord truss pile leg 200 is shared by the four main chords 210, so the thickness of the rack plate on each main chord 210 can be reduced accordingly, reducing the difficulty of producing the rack plate 210 and the pile leg construction, and reducing the platform construction cost.
[0057] In addition, the base 510 of the pile-circling crane 500 is fixedly installed on the pile frame 300, and the base 510 does not need to occupy the deck area, so the effective utilization space between the two pile legs at the rear of the hull is increased, which is conducive to the wind turbine tower being directly hoisted to the preset installation position through the space between the two pile legs at the rear of the hull, without having to go around the outside of the ship for hoisting, and the hoisting path is greatly shortened. Therefore, the offshore wind power installation platform of the present application can effectively save the wind turbine hoisting time, improve the hoisting operation efficiency, and help improve the wind turbine installation efficiency.
[0058] The offshore wind power installation platform of the present application can use a fully welded steel hull as the main hull 100 of the platform. Figure 2 As shown, the platform main hull 100 may adopt a streamlined vertical bow and a square stern. The streamlined vertical bow and the square stern may increase the anchor and mooring deck area at the bow and stern, which is convenient for equipment arrangement.
[0059] The platform main hull 100 may be provided with a double bottom deck, which can increase the survivability of the platform after a cabin is breached.
[0060] The main hull 100 of the platform can be provided with a double-layer top deck. The double-layer top deck can increase the hull strength. When installing different types of wind turbines, it is necessary to modify the installation base of the wind turbine component 10 without additional protection of the equipment in the cabin of the main hull 100, and welding and cutting and other construction operations can be carried out directly.
[0061] See also Figure 2 In one embodiment, a storage area 120 for storing the wind turbine component 10 is provided on the platform main hull 100. For example, a mounting base for mounting the wind turbine component 10 may be provided in the storage area 120. Figure 2As shown, the storage area 120 may be arranged in the middle of the platform main hull 100 near the starboard side of the stern.
[0062] Furthermore, the shortest path from the storage area 120 to the installation position of the wind turbine component 10 passes between the two pile frames 300 at the rear of the platform main hull 100. For example, Figure 2 As shown, a pile foundation 600 for installing the wind turbine component 10 is provided at the installation position of the wind turbine component 10. When the wind turbine component 10 needs to be hoisted and installed, the offshore wind power installation platform is driven to the vicinity of the pile foundation 600, and the tail of the platform main hull 100 is close to the pile foundation 600. In addition, the center line between the storage area 120 and the pile foundation 600 can pass between the two pile fixing frames 300 at the tail of the platform main hull 100.
[0063] In this embodiment, when the wind turbine component 10 needs to be hoisted, the pile-circling crane 500 can directly hoist the wind turbine component 10 from the storage area 120 to the pile foundation 600 through the passage between the two pile fixing frames 300 at the rear of the platform main hull 100 along the shortest straight path. This can effectively save the hoisting time of the wind turbine component 10 and improve the hoisting operation efficiency.
[0064] like Figure 1 and Figure 2 As shown, the offshore wind power installation platform of the present application may include four four-chord truss pile legs 200. The four four-chord truss pile legs 200 are respectively arranged at the four corners of the platform main hull 100.
[0065] See also Figure 1 and Figure 2 In one embodiment, the four-chord truss leg 200 is in the form of a regular quadrilateral leg. The four-chord truss leg 200 includes four main chords 210. In this embodiment, each main chord 210 is a main component structure of the four-chord truss leg 200. Each main chord 210 is used to set a rack plate for lifting.
[0066] Considering the overall structural strength of the four-chord truss leg 200, the four-chord truss leg 200 further includes a plurality of support rods 220 disposed between two adjacent main chords 210. The main chords 210 are connected by the support rods 220 to form a regular quadrilateral leg.
[0067] In the present application, since the four-chord truss pile leg 200 includes four main chords 210, it can bear a greater load than the traditional three-chord pile leg. Under the same load conditions, the load borne by each four-chord truss pile leg 200 is shared by the four main chords 210, so the thickness of the rack plate on each main chord 210 can be reduced accordingly, reducing the difficulty of rack plate production and pile leg construction, and reducing the platform construction cost.
[0068] See also Figure 1 and Figure 2 In one embodiment, the pile fixing frame 300 includes four main frames 310, and the four main frames 310 are arranged corresponding to the four main chords 210. In this embodiment, each main frame 310 is a main component structure of the pile fixing frame 300. Each main frame 310 is used to set a driving motor and a driving gear for realizing lifting.
[0069] Considering the overall structural strength of the pile fixing frame 300, in one embodiment, the pile fixing frame 300 further includes a support frame 320 disposed between two adjacent main frames 310. For example, the support frame 320 may include a crossbeam connecting the top ends of the two adjacent main frames 310, and a support rod body connected below each crossbeam and connected to the two adjacent main frames 310. Each main frame 310 and each support frame 320 are connected to form a pile fixing frame 300 of an annular structure.
[0070] In the embodiment of the present application, the pile-encircling crane 500 is a 360° full-slewing crane. The pile-encircling crane 500 is fixed to the top of the pile frame 300 via a base 510. The pile-encircling crane 500 can rotate 360° around the central axis of the four-chord truss pile leg 200.
[0071] See also Figure 2 In one embodiment, the base 510 is an annular base, and the base 510 is supported and arranged at the top of the four main frames 310. Among them, the base 510 can be a circular ring base. In this embodiment, the base 510 is supported by the four main frames 310, and its stability is high. Since the outer diameter of the four-chord truss pile leg 200 is reduced, the outer diameter of the pile frame 300 is also reduced accordingly, so the outer diameter of the base 510 can also be designed to be smaller. This is conducive to reducing the diameter size of the slewing bearing of the pile-winding crane 500, reducing the weight of the pile-winding crane 500, and increasing the variable load of the platform.
[0072] like Figure 1 As shown, the top of the base 510 is connected to the bottom of the main body of the pile-encircling crane 500. The bottom of the base 510 is fixedly connected to the top of the pile fixing frame 300. Specifically, the base 510 and the pile fixing frame 300 can be connected by welding.
[0073] In one embodiment, the projection of the circumferential outer edge of the bottom of the base 510 on the platform main hull 100 does not exceed the projection of the circumferential outer edge of the pile frame 300 on the platform main hull 100. In this embodiment, the circumferential outer edge of the bottom of the base 510 does not exceed the circumferential outer edge of the pile frame 300, that is, the cross-sectional dimension of the bottom of the base 510 is not greater than the cross-sectional dimension of the pile frame 300. Therefore, the end of the connection between the base 510 and the pile frame 300 will not occupy the effectively utilized space between the two pile legs at the stern of the hull, ensuring that there is enough spacing between the two pile legs at the stern of the hull to hoist the wind turbine tower.
[0074] Further, the projection of the circumferential outer edge of the base 510 on the platform main hull 100 does not exceed the projection of the circumferential outer edge of the pile frame 300 on the platform main hull 100. The circumferential outer edge of the pile frame 300 may be the circumscribed circumferential surface of the four main frame bodies 310. That is, the projection of the circumferential outer edge of the base 510 on the platform main hull 100 does not exceed the projection of the circumscribed circumferential surface of the four main frame bodies 310 on the platform main hull 100.
[0075] In this embodiment, in the axial direction of the four-chord truss pile leg 200, the size of any cross section of the base 510 from the top to the bottom is not greater than the cross section of the pile frame 300. That is, no matter how the base 510 changes, its peripheral outer edge does not exceed the peripheral outer edge of the pile frame 300, so that the base 510 as a whole will not occupy the effective space between the two pile legs at the stern of the hull, ensuring that there is enough space between the two pile legs at the stern of the hull to hoist the wind turbine tower.
[0076] See also Figure 1 and Figure 3 In one embodiment, the base 510 is a uniform cross-sectional structure along the axial direction of the four-chord truss pile leg 200. In this embodiment, since the base 510 is a uniform cross-sectional structure and the cross-sectional dimension of its bottom is always not greater than the cross-sectional dimension of the pile frame 300, the cross-sectional dimension of the base 510 as a whole can be designed to be smaller. This is conducive to reducing the diameter of the slewing bearing of the pile-encircling crane 500, reducing the weight of the pile-encircling crane 500, and increasing the variable load of the platform.
[0077] It is understood that in other embodiments, the base 510 may also be a variable cross-section structure. For example, the cross-sectional dimension of the top of the base 510 may be greater than the cross-sectional dimension of the bottom of the base 510. Alternatively, the cross-sectional dimension of the base 510 may gradually decrease from the top to the bottom. No matter how the appearance of the base 510 changes, it is sufficient to ensure that the cross-sectional dimension of the bottom of the base 510 is always smaller than the cross-sectional dimension of the pile fixing frame 300, so that the circumferential outer edge of the bottom of the base 510 does not exceed the circumferential outer edge of the pile fixing frame 300.
[0078] Compared with the traditional crane base of the wind power installation platform, which surrounds the pile legs and is set on the platform deck, the base 510 of the pile-circling crane 500 of the present application is fixed on the top of the pile frame 300. While the height of the base 510 is reduced, the total weight of the platform can be reduced. In addition, the base 510 does not occupy the deck area, so that the effective use of space between the two pile legs at the rear of the hull is increased, which is conducive to the hoisting of the wind turbine component 10 along the shortest hoisting path.
[0079] See also Figure 1 In one embodiment, the four-chord truss pile leg 200 includes a pile shoe 230, and the pile shoe 230 is connected to the bottom end of the four-chord truss pile leg 200. Figure 4 As shown, the pile shoe 230 is in the form of an octagonal pile shoe. Specifically, the cross-sectional shape of the pile shoe 230 is a regular octagon.
[0080] like Figure 1 As shown, in one embodiment, a receiving space 110 for receiving the pile shoe 230 is provided at the bottom of the platform main hull 100. Specifically, when the pile shoe 230 is received in the receiving space 110, the pile shoe 230 does not exceed the bottom of the platform main hull 100.
[0081] In this embodiment, the pile shoe 230 can be both extended and retracted. Figure 5 As shown, the pile shoe 230 is in a state of being extended outward relative to the bottom of the platform main hull 100. When the platform is sailing, the pile shoe 230 is extended outward to reduce the sailing resistance of the ship. Figure 6 As shown, the pile shoe 230 is in a state of being retracted relative to the bottom of the platform main hull 100. When the platform is docked at a pier, the pile shoe 230 can be retracted to adapt to different pier water depth requirements. Therefore, the pile shoe 230 of this embodiment can help increase the speed of the platform, reduce the sailing cycle, and improve the platform's adaptability to the pier water depth.
[0082] See also Figure 2 In the embodiment of the present application, the lifting system 400 is disposed between the pile fixing frame 300 and the four-chord truss pile leg 200, and is used to drive the four-chord truss pile leg 200 to rise and fall. Specifically, the lifting system 400 is disposed between the main chord 210 and the corresponding main frame body 310.
[0083] In one embodiment, the lifting system 400 includes a driving motor, a driving gear and a rack. The driving motor is arranged on the pile fixing frame 300. Specifically, the driving motor is arranged on the main frame body 310. The driving gear is installed on the output shaft of the driving motor.
[0084] The rack is arranged on the four-chord truss pile leg 200 and meshes with the driving gear. Specifically, the rack is arranged on the main chord 210 corresponding to the driving gear.
[0085] In this embodiment, due to the use of four-chord truss pile legs 200, under the same load conditions, the load borne by each pile leg is shared by the four main chord rods 210. That is, the lifting force of the entire platform is also shared by the four lifting systems 400 between the four main chord rods 210 of each pile leg and the corresponding main frame 310. Therefore, the lifting capacity of each lifting system 400 can also be reduced accordingly. Thereby, the number of layers of each lifting system 400 can be reduced, the height of each pile frame 300 can be reduced, the length of each pile leg can be reduced, and the construction cost of the platform can be reduced.
[0086] Under the assumption that the offshore wind power installation platform of the present application bears the same load as the traditional three-chord pile-leg wind power installation platform:
[0087] like Figure 1 and Figure 2 As shown, the offshore wind power installation platform of the present application has four four-chord truss pile legs 200. The four four-chord truss pile legs 200 are symmetrically arranged on the left and right sides of the platform main hull 100. The bottom of each four-chord truss pile leg 200 is connected to a pile shoe 230. Figure 4 As shown, the pile shoe 230 is designed to be octagonal. The octagonal pile shoe 230 is evenly symmetrical with the quadrilateral four-chord truss pile leg 200, so that the chord and the pile shoe 230 are evenly loaded.
[0088] When the pile shoe is deeply embedded in the mud and the pile shoe bearing capacity per square meter is required to be small, a large pile shoe design is required. In order to make the pile shoe and the three-chord force uniform and facilitate the pile shoe structure design, the traditional three-chord truss pile leg can only be designed as a hexagonal pile shoe. Figure 4 Compared with the conventional hexagonal pile shoe, when the inscribed circle diameter D1 of the octagonal pile shoe 230 of the present application is 17.5 meters, the dimension L of the octagonal pile shoe 230 in the longitudinal direction of the platform is about 17.5 meters. The dimension L of the conventional hexagonal pile shoe in the longitudinal direction of the platform is about 20.2 meters. That is, the design of the octagonal pile shoe 230 of the present application saves 2.7 meters of the longitudinal dimension of the well, which is conducive to increasing the buoyancy of the hull and the cargo carrying capacity of the platform.
[0089] The four-chord truss pile leg 200 of the present application is calculated to have a side length of 8 meters and a rack plate thickness of 177.8 mm in the SACS position analysis software. Under the same environmental force and lifting force conditions, the traditional three-chord pile leg is calculated in the SACS position analysis software to have a side length of 10 meters and a rack plate thickness of 203.2 mm. By comparison, the side length of the four-chord truss pile leg 200 of the present application is reduced by 1 meter, and the rack plate thickness is reduced from 8 inches to 7 inches. The small side length of the pile leg and the small thickness of the rack plate can greatly reduce the difficulty of rack plate production and pile leg construction, and reduce the cost of platform construction.
[0090] The lifting system 400 of the present application is connected to the four-chord truss pile leg 200 through gear rack meshing. Under the condition of calculating the same lifting weight, the normal lifting capacity of the lifting system 400 of the present application is 265 tons per leg for 5 layers; while the normal lifting capacity of the traditional three-chord pile leg lifting system is 265 tons per leg for 7 layers. By comparison, the lifting system 400 of the present application can be reduced by two layers compared with the traditional three-chord pile leg lifting system. Since the floor height of the lifting system 400 is about 1.6 meters per floor, the pile leg length can be reduced by about 3 meters, thereby greatly reducing the platform construction cost.
[0091] Compared with the traditional three-chord pile leg, the four-chord truss pile leg 200 of the present application has a Figure 7 As shown, the diameter D2 of the circumscribed circle of the four-chord truss pile leg 200 is about 12 meters; while the diameter of the circumscribed circle of the conventional three-chord pile leg is about 12.4 meters. When the pile encircling crane 500 rotates around the four-chord truss pile leg 200 of the present application, the pile encircling crane 500 can reduce the pile bearing diameter by 0.4 meters. Figure 2 When the lateral center distance W of the pile legs is 38.75 meters, the lateral available space between the two four-chord truss pile legs 200 of the present application is increased by 0.4 meters compared with the available space between the two traditional three-chord truss pile legs.
[0092] Since the base 510 of the pile-circling crane 500 of the present application is fixedly installed on the top of the pile frame 300, the base 510 does not need to occupy the deck area. Figure 3 As shown, the transversely available space S between the two four-chord truss pile legs 200 of the present application is about 26.5 meters, while the transversely available space S between the two traditional three-chord truss pile legs is about 23.1 meters.
[0093] When the platform is equipped with a 10MW wind turbine tower with a bottom diameter of 8.5 meters, and the wind turbine pile foundation 600 is located at the stern of the platform main hull 100, the space required for the 10MW wind turbine tower is 4.25 meters plus the minimum lifting radius of the pile crane 500 is 19 meters, which equals 23.25 meters. Since the horizontally available space S between the two four-chord truss pile legs 200 at the stern of the platform main hull 100 of the present application is about 26.5 meters. Therefore, if Figure 2 As shown, when the platform of the present application is hoisting the wind turbine tower, the pile-circling crane 500 can make the wind turbine tower directly pass through the two pile legs at the rear of the hull from the right side of the crane to reach the position of the pile foundation 600. Unlike the traditional three-chord pile-leg platform, it is not necessary to rotate the crane to the left to the port side of the main hull 100 of the platform and then go around to the position of the pile foundation 600. Therefore, the offshore wind power installation platform of the present application can greatly save the hoisting operation time and improve the hoisting operation efficiency.
[0094] The offshore wind power installation platform of the present application solves the problems of long hoisting time, low efficiency and short operation window of the traditional wind power installation platform. The offshore wind power installation platform of the present application adopts a four-chord truss pile leg 200, which can reduce the side length of the pile leg, reduce the thickness of the rack plate, and reduce the number of layers of the lifting system 400, which is conducive to increasing the buoyancy of the platform and improving the loading capacity of the platform.
[0095] See also Figure 8 In one embodiment of the present invention, a method for hoisting wind turbine components is also provided, which is constructed using the offshore wind power installation platform of any of the above embodiments.
[0096] The hoisting method comprises:
[0097] S10, start the pile-circling crane 500 to lift the wind turbine component 10. The wind turbine component 10 mainly refers to the wind turbine tower.
[0098] S20, the pile-encircling crane 500 drives the wind turbine component 10 to pass through the two pile frames 300 at the rear of the platform main hull 100. In this step, the pile-encircling crane 500 can directly hoist the wind turbine tower from the storage area 120 through the passage between the two pile frames 300 at the rear of the platform main hull 100 along the shortest straight path to the pile foundation base 600. This greatly saves the hoisting time of the wind turbine tower and improves the hoisting operation efficiency.
[0099] S30, the pile-encircling crane 500 places the wind turbine component 10 on the pile foundation 600. In this step, the pile-encircling crane 500 hoists the wind turbine tower to the top of the pile foundation 600, and can place the wind turbine tower on the pile foundation 600. After that, the construction personnel can connect the wind turbine tower and the pile foundation 600.
[0100] See also Figure 8 In one embodiment, before S10, the method further includes:
[0101] S11, driving the offshore wind power installation platform to a preset position near the pile foundation 600, and making the tail of the platform main hull 100 close to the pile foundation 600. For example, Figure 2 As shown, the center line between the storage area 120 and the pile foundation 600 can pass through the two pile frames 300 at the rear of the platform main hull 100. When the wind turbine component 10 needs to be hoisted, the pile-wrapping crane 500 can directly hoist the wind turbine component 10 from the storage area 120 to the pile foundation 600 through the passage between the two pile frames 300 at the rear of the platform main hull 100 along the shortest straight path. This can effectively save the hoisting time of the wind turbine component 10 and improve the hoisting efficiency.
[0102] The method for hoisting the offshore wind power installation platform and wind turbine components of the embodiment of the present application adopts the design of a four-chord truss pile leg 200. Under the same environmental force and the condition that the lifting weight of the empty ship remains unchanged, the four-chord truss pile leg 200 has a small side length and a small rack plate thickness, which can reduce the construction cost; the four-chord truss pile leg 200 can enable the platform to carry a larger load, and the four-chord truss pile leg 200 occupies a reduced deck area, which can increase the main deck operating area; the four-chord truss pile leg 200 has a small outer diameter, which reduces the size of the pile leg enclosure, increases the platform buoyancy, increases the deck load and variable load, and improves the loading capacity; at the same time, it can reduce the number of lifting system 400 layers, reduce the height of the pile frame 300, and reduce the length of the pile leg.
[0103] In the offshore wind power installation platform and the method for hoisting wind turbine components of the embodiment of the present application, the base 510 of the pile-circling crane 500 is connected to the top of the pile frame 30. The base 510 does not need to occupy the deck area, so the effective utilization space between the two pile legs at the rear of the hull is increased, which is conducive to the wind turbine tower being directly hoisted to the preset installation position through the space between the two pile legs at the rear of the hull, greatly shortening the hoisting path, saving the wind turbine hoisting time, and improving the hoisting operation efficiency.
[0104] In the method for hoisting the offshore wind power installation platform and wind turbine components of the embodiment of the present application, the base 510 of the pile-circling crane 500 is connected to the top of the pile frame 30. The outer diameter of the base 510 is not greater than the outer diameter of the pile frame 300. Since the outer diameter of the four-chord truss pile leg 200 is reduced, the outer diameter of the pile frame 300 is also reduced accordingly, so the outer diameter of the base 510 can also be designed to be smaller. This is conducive to reducing the diameter of the slewing bearing of the pile-circling crane 500, reducing the weight of the pile-circling crane 500, and increasing the variable load of the platform. Compared with the traditional base of the pile leg surrounded by a round earth and a square earth, the base 510 of the present application has a simple construction process, a reduced height, and a reduced weight, which is conducive to reducing the difficulty of platform construction and reducing construction costs.
[0105] In the offshore wind power installation platform and the method for hoisting wind turbine components of the embodiment of the present application, the pile shoes 230 are designed to be both extended and retractable. When the platform is sailing, the pile shoes 230 are extended to increase the navigation speed, reduce the period of the platform going back and forth between the wind turbine dock and the wind farm, and improve the operation efficiency; when the platform is docked at the dock, the pile shoes 230 are retracted so that the platform can adapt to various dock water depths.
[0106] The offshore wind power installation platform and the method for hoisting wind turbine components in the embodiment of the present application can be used for both floating hoisting and standing hoisting. The platform design meets the transportation requirements of the entire wind turbine tower, meets the operation requirements in European waters, and meets the installation requirements of deep-sea wind turbines in Chinese waters.
[0107] The above embodiments are merely exemplary descriptions of the structures. The structures in the embodiments are not fixed combination structures. In the absence of structural conflicts, the structures in multiple embodiments can be used in any combination.
[0108] Although the present invention has been described with reference to several typical embodiments, it should be understood that the terms used are illustrative and exemplary, rather than restrictive. Since the present invention can be embodied in a variety of forms without departing from the spirit or essence of the invention, it should be understood that the above embodiments are not limited to any of the foregoing details, but should be interpreted broadly within the spirit and scope defined by the appended claims, so all changes and modifications falling within the scope of the claims or their equivalents should be covered by the appended claims.
Claims
1. An offshore wind power installation platform, characterized in that: include: Platform main hull; Four-chord truss pile legs, the four-chord truss pile legs can be vertically slidably arranged on the main hull of the platform, and the four-chord truss pile legs are distributed at the four corners of the main hull of the platform; A pile fixing frame, the pile fixing frame is arranged on the top deck of the platform main hull corresponding to the four-chord truss pile legs, and the pile fixing frame is used to drive the four-chord truss pile legs to rise and fall through a lifting system; and A pile-encircling crane comprises a base, wherein the base is fixed on the pile frame located on the side of the ship at the stern of the platform main hull, and the base is supported above the top deck of the platform main hull by the pile frame, and a height gap is formed between the bottom of the base and the top deck of the platform main hull, and a channel for the pile-encircling crane to lift wind turbine components is formed between the two pile frames at the stern of the platform main hull.
2. The offshore wind power installation platform according to claim 1, characterized in that: The bottom of the base is connected to the top of the pile frame, and the projection of the circumferential outer edge of the bottom of the base on the main hull of the platform does not exceed the projection of the circumferential outer edge of the pile frame on the main hull of the platform.
3. The offshore wind power installation platform according to claim 2, characterized in that: The four-chord truss pile leg adopts a regular quadrilateral pile leg form, and the four-chord truss pile leg includes four main chords; The pile fixing frame comprises four main frame bodies, and the four main frame bodies are arranged corresponding to the four main chord rods; The base is an annular base, and the base support is arranged on the top ends of the four main frames. The projection of the circumferential outer edge of the base on the main hull of the platform does not exceed the projection of the circumscribed circular surfaces of the four main frames on the main hull of the platform.
4. The offshore wind power installation platform according to claim 3, characterized in that: The pile fixing frame further comprises a supporting frame body, wherein the supporting frame body is connected between two adjacent main frame bodies, and the main frame body and the supporting frame body are connected to form the pile fixing frame of an annular structure.
5. The offshore wind power installation platform according to claim 1, characterized in that: Along the axial direction of the four-chord truss pile leg, the base is a uniform cross-section structure.
6. The offshore wind power installation platform according to claim 1, characterized in that: The four-chord truss pile leg comprises a pile shoe, and the pile shoe is connected to the bottom end of the four-chord truss pile leg; A receiving space for receiving the pile shoe is provided at the bottom of the main hull of the platform. When the pile shoe is received in the receiving space, the pile shoe does not extend beyond the bottom of the main hull of the platform.
7. The offshore wind power installation platform according to claim 6, characterized in that: The pile shoe is in the form of an octagonal pile shoe.
8. The offshore wind power installation platform according to claim 1, characterized in that: The lifting system includes a driving motor, a driving gear and a rack. The driving motor is arranged on the pile fixing frame, the driving gear is installed on the output shaft of the driving motor, and the rack is arranged on the four-chord truss pile leg and meshes with the driving gear.
9. The offshore wind power installation platform according to claim 1, characterized in that: The platform main hull is provided with a storage area for storing wind turbine components, and the shortest path from the storage area to the installation position of the wind turbine components passes between the two pile frames at the rear of the platform main hull.
10. A method for hoisting a fan component, characterized in that: The offshore wind power installation platform according to any one of claims 1 to 9 is used for construction, and the hoisting method comprises: Start the pile-encircling crane to lift the wind turbine components; The pile-encircling crane drives the wind turbine components through the space between the two pile frames at the rear of the platform's main hull; A pile-encircling crane places the wind turbine components on the pile foundation.
11. The method for hoisting fan components according to claim 10, characterized in that: Before starting the pile-encircling crane to lift the wind turbine components, the following steps are also required: Drive the offshore wind power installation platform to a preset position near the pile foundation, and make the stern of the platform main hull close to the pile foundation.