Simple steel pipe pile pulling-out construction method
Through the sinking and drainage buoyancy assisting the vibration hammer tension, the problem of steel pipe piles being difficult to remove under complex geological conditions is solved, and the cost saving and construction progress is improved. It is suitable for steel pipe piles that are difficult to remove.
Patent Information
- Application Number
- CN202310599112.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2023-05-23
- Publication Date
- 2024-11-26
AI Technical Summary
The prior art is difficult to remove steel pipe piles placed in soil, especially in complex geological conditions, which leads to hindering the construction progress.
A simple steel pipe pile removal construction method is adopted, and the steel sleeve box and crawler crane are used to cooperate with the vibration hammer. The steel sleeve box sinking and drainage buoyancy assists the vibration hammer tension, and the steel pipe piles that are difficult to remove are gradually removed.
It effectively solves the problem of difficult to remove steel pipe piles, reduces investment in replacing large hydraulic pile pulling equipment, saves construction costs, and the steel sleeve box can be recycled and is suitable for complex geological conditions.
Smart Images

Figure CN119021216A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the field of bridge erection, and in particular to a simple steel pipe pile removal construction method. Background Art
[0002] At present, the main method for removing steel pipe piles is crawler crane combined with hydraulic vibratory hammer. When using this method to remove steel pipe piles, if they have been left in the soil for too long or the geological conditions are relatively complex, the soil around the piles has already been dense, consolidated, and hardened, forming a whole with the piles, making it difficult to remove the steel pipe piles, which seriously hinders the progress of construction.
[0003] The invention with application number CN201410228716.7 discloses a method for removing steel pipe piles for temporary underwater bridge projects. First, the model of a vibrating hammer and a lifting equipment are selected through calculation, and a transport barge is prepared and brought to the working area; then the top of the steel pipe pile is leveled; after that, the lifting equipment arrives at the working area and is anchored in place according to the boom length and the working radius, and at the same time, the vibrating hammer and the transport barge are also in place near the steel pipe pile; the vibrating hammer is started to sink the steel pipe pile, and then the pile is vibrated and pulled out, and after the steel pipe pile rises, the lifting equipment directly pulls out the pile until the steel pipe pile is separated from the mud surface; finally, the steel pipe pile falls on the transport barge, and the vibrating hammer loosens the pile to complete the pile pulling; but in actual construction, there are very few steel pipe piles that are difficult to pull out. For such steel pipe piles that are difficult to pull out, the technology and equipment disclosed in the above documents cannot effectively pull out the difficult-to-pull steel pipe piles. Summary of the invention
[0004] In view of this, the object of the present invention is to provide a simple steel pipe pile removal construction method, the equipment used in the method has a simple structure and can be recycled, and is also conducive to removing steel pipe piles that are difficult to remove.
[0005] In order to solve the above technical problems, the technical solution of the present invention is:
[0006] A simple steel pipe pile removal construction method comprises the following steps:
[0007] S1. Steel casing prefabrication:
[0008] S11. The steel casing is manufactured in advance according to the outline size specifications. There are circular holes in the center of the top and bottom surfaces of the steel casing, and a circular water outlet is also provided on the top surface;
[0009] S12, using a crawler crane and a flatbed truck to transport the steel casing prepared in step S11 to the pipe pulling pile construction area for standby use;
[0010] S2. Dismantling the trestle structure above the steel pipe piles: After the crawler crane cooperates with the flatbed truck to transfer the steel casing, it further removes the handrails, water pipes and cable facilities attached to the trestle and platform. After the removal is completed, the bridge deck is separated from the distribution beam by manual cutting, and the whole is transformed into modules for easy lifting. The dismantled bridge deck is transported to the backyard for storage via the trestle by a flatbed truck, and the distribution beam is lifted and hoisted span by span, and then transported to the backyard for storage by a flatbed truck. The connection system between the piles is cut, and then it is hoisted onto the flatbed truck and transported to the backyard for storage via the trestle;
[0011] S3, the steel pipe pile is pulled out until it is difficult to lift: after completing step S2, a vibrating hammer is installed on the crawler crane. After the vibrating hammer is installed, the vibrating hammer clamps the steel pipe pile through a clamp and starts to pull out the pile. During the pile pulling process, the steel pipe pile must be vibrated for 1 to 2 minutes to liquefy the soil around the steel pipe pile before lifting the vibrating hammer to start pulling out the pile. During the pile pulling process, the pulling force is gradually increased and cannot be increased suddenly until it cannot be pulled out;
[0012] S4, lower the steel casing to the water surface, and fill it with water to sink it: After completing step S3, use a crawler crane to lift the prefabricated steel casing, align the circular hole in the center of the bottom surface with the top of the steel pipe pile, and slowly lower the steel casing to the water surface. Place a water pump 8 outside the steel casing 1, and draw the water injection pipe of the water pump 8 into the water inlet 12 on the top of the steel casing 1, and fill it with water to sink the steel casing;
[0013] S5. Clean the silt on the steel pipe pile and weld the stiffening steel plate: When the top surface of the steel casing is about to be lowered to the water surface, stop the water injection work of the water pump, clean the silt and debris on the steel pipe pile, and then weld a circle of stiffening steel plate on the steel pipe pile. The bottom height of the stiffening steel plate is slightly above the top surface of the steel casing to ensure that the steel casing can be tightly pressed against the stiffening steel plate after the steel casing is drained;
[0014] S6. Draining the steel casing with a vibrating hammer to pull out the pile: gradually drain the water inside the steel casing by using a water pump placed inside the steel casing, control the steel casing and the stiffening steel plate to be pressed tightly together, and after the pressing is completed, start the vibrating hammer, and at the same time use the water pump placed inside the steel casing to drain all the water, and use the buoyancy of the water on the steel casing and the pulling force of the vibrating hammer to pull out the steel pipe pile until the steel pipe pile is completely pulled out;
[0015] S7. Storage of steel pipe piles: After the steel pipe piles are removed by crawler crane in step S6, the steel pipe piles are stored in the backyard.
[0016] Furthermore, in S3, the process of pile pulling requires continuous debugging of the vibratory hammer and the boom of the crawler crane to obtain various technical parameters during pile pulling and provide optimal operating parameters for the subsequent pile pulling.
[0017] Further, the calculation of pile pulling force:
[0018] The outline dimensions of the steel casing are 2.5m long, 2.5m wide and 2m high. The diameter of the circular holes in the center of the top and bottom of the steel casing is φ800mm, and the diameter of the circular water outlet on the top is φ300mm.
[0019] Mechanical technical parameters of vibratory hammer: Maximum pile pulling force is 254KN;
[0020] The total weight of the steel casing and stiffening plate is calculated to be N weight = 7.27t;
[0021] After water injection, the steel casing sinks completely, and the buoyancy provided by water is: Fbuoyancy = Grow = ρwater * Vwater, so Fbuoyancy = 1000kg / m3*2.5m*2.5m*2m=12500kg=125KN, where Fbuoyancy is the buoyancy of the steel casing when it is completely immersed in water, Grow is the gravity of the water after the steel casing is completely immersed in water, ρwater is the density of the water displaced by the steel casing, and Vwater is the volume of the water displaced by the steel casing;
[0022] After deducting its own weight, the upward pulling force that the steel casing process can provide is: F pull = F float - N weight = 125-72.7 = 52.3KN.
[0023] The present invention first uses a crawler crane in conjunction with a vibratory hammer to perform pile pulling construction, until the steel pipe pile cannot be pulled out any more, a steel casing is put on the pile body of the steel pipe pile, and water is poured into the steel casing to make it sink, and then it is connected to the steel sleeve, and then the steel casing is drained and floated, and the buoyancy of the steel casing when drained is used to assist in pile pulling construction. Compared with the currently commonly used hydraulic vibratory hammer construction method, the present invention reduces the investment in replacing large-scale hydraulic pile pulling equipment and saves construction costs. In addition, the steel material of the steel casing is easily available on the construction site, is simple to make, can be recycled, can be processed and expanded as needed, and can be recycled after use. At the same time, it can also be used to remove steel pipe piles that are difficult to remove. BRIEF DESCRIPTION OF THE DRAWINGS
[0024] Figure 1 It is a structural diagram of a steel casing in a simple steel pipe pile extraction construction method of the present invention;
[0025] Figure 2 It is a state schematic diagram of step 3 of the present invention;
[0026] Figure 3 This is one of the state diagrams of step 4 of the present invention;
[0027] Figure 4 This is the second state diagram of step 4 of the present invention;
[0028] Figure 5 is a structural diagram of the stiffening steel plate used in step 5 of the present invention;
[0029] Figure 6It is a state schematic diagram of step 5 of the present invention;
[0030] Figure 7 It is a state diagram of step 6 of the present invention. DETAILED DESCRIPTION
[0031] The specific implementation modes of the present invention are further described below in conjunction with the accompanying drawings to make the technical solutions of the present invention easier to understand and grasp.
[0032] In this embodiment, it should be understood that the terms "middle", "upper", "lower", "top", "right", "left end", "above", "back", "middle", etc. indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present invention.
[0033] In addition, in this specific embodiment, if the connection or fixing method between components is not specifically described, the connection or fixing method can be through bolt fixing or pin fixing, or pin shaft connection and the like commonly used in the prior art, and therefore, it is not described in detail in this embodiment.
[0034] A simple steel pipe pile removal construction method comprises the following steps:
[0035] S1, steel casing 1 prefabrication:
[0036] S11, such as Figure 1 As shown, the steel casing 1 is made in advance according to the outline size specifications, and the center of the top and bottom surfaces of the steel casing 1 are respectively provided with circular holes 11, and the top surface is also provided with a circular water outlet 12;
[0037] S12, using a crawler crane 2 in conjunction with a flatbed truck to transport the steel casing 1 prepared in step S11 to a pipe pulling pile construction area for standby use;
[0038] S2, dismantling the trestle 4 structure above the steel pipe piles 3: After the crawler crane 2 cooperates with the flatbed truck to transfer the steel casing 1, it further removes the trestle 4, the railings, water pipes and cable facilities attached to the platform, and after the removal is completed, the bridge deck 5 is separated from the distribution beam 6 by manual cutting, and the whole is changed into a module to facilitate lifting. The dismantled bridge deck 5 is transported to the backyard for storage by a flatbed truck through the trestle 4, and the distribution beam 6 is lifted and hoisted span by span, and then transported to the backyard for storage by a flatbed truck, and the connection system between the piles is cut, and then hoisted onto the flatbed truck and transported to the backyard for storage by the trestle 4;
[0039] S3, such as Figure 2As shown, the steel pipe pile is pulled to a state where it is difficult to lift: after completing step S2, the vibrating hammer 7 is installed on the crawler crane 2. After the vibrating hammer 7 is installed, the vibrating hammer 7 clamps the steel pipe pile 3 through the clamp and starts to pull out the pile. During the pile pulling process, the steel pipe pile 3 must be vibrated for 1 to 2 minutes to liquefy the soil around the steel pipe pile 3 before lifting the vibrating hammer 7 to start pulling out the pile. During the pile pulling process, the pile pulling force is gradually increased and cannot be increased suddenly until it cannot be pulled out;
[0040] S4, lower the steel casing 1 to the water surface, fill it with water and sink it: After completing step S3, use the crawler crane 2 to lift the prefabricated steel casing 1, such as Figure 3-4 As shown, align the circular hole 11 in the center of the bottom surface with the top of the steel pipe pile 3, slowly lower the steel casing 1 to the water surface, place the water pump 8 outside the steel casing 1, and draw the water injection pipe of the water pump 8 into the water inlet 12 on the top of the steel casing 1 to inject water and sink the steel casing 1;
[0041] S5, clean the silt on the steel pipe pile 3 and weld the reinforcing steel plate 9: Figure 6 As shown, when the top surface of the steel casing 1 is about to be lowered to the water surface, the water pump 8 is stopped from injecting water, the silt and debris on the steel pipe pile 3 are cleaned, and then a circle of reinforcing steel plate 9 is welded on the steel pipe pile 3. Figure 5 As shown, the bottom height of the stiffening steel plate 9 is slightly above the top surface of the steel casing 1, so as to ensure that the steel casing 1 can be tightly pressed against the stiffening steel plate 9 after the steel casing 1 is drained;
[0042] S6, steel casing 1 drains water and vibrating hammer 7 completes pile extraction: Figure 7 As shown, the water inside the steel casing 1 is gradually discharged by the water pump 8 placed inside the steel casing 1, and the steel casing 1 and the stiffening steel plate 9 are controlled to be pressed tightly. After the pressing is completed, the vibrating hammer 7 is started, and the water pump 8 placed inside the steel casing 1 is used to completely drain the water. The buoyancy of the water on the steel casing 1 and the pulling force of the vibrating hammer 7 are used to complete the removal of the steel pipe pile 3 until the steel pipe pile 3 is completely removed.
[0043] S7. Storage of the steel pipe piles 3: After the steel pipe piles 3 are removed by the crawler crane 2 in step S6, the steel pipe piles 3 are stored in the backyard.
[0044] In S3, the pile pulling process requires continuous debugging of the vibrating hammer 7 and the boom of the crawler crane 2 to obtain various technical parameters for pile pulling and provide optimal operating parameters for later pile pulling.
[0045] Calculation of pile pull force:
[0046] The outline dimensions of the steel casing 1 are set to be 2.5m long, 2.5m wide and 2m high, the diameter of the circular holes 11 in the center of the top and bottom surfaces of the steel casing 1 is φ800mm, and the diameter of the circular water inlet 12 opened on the top surface is φ300mm;
[0047] Mechanical technical parameters of vibratory hammer: Maximum pile pulling force is 254KN;
[0048] The total weight of the steel casing and stiffening plate is calculated to be N weight = 7.27t;
[0049] After water injection, the steel casing sinks completely, and the buoyancy provided by water is: Fbuoyancy = Grow = ρwater * Vwater, so Fbuoyancy = 1000kg / m3*2.5m*2.5m*2m=12500kg=125KN, where Fbuoyancy is the buoyancy of the steel casing when it is completely immersed in water, Grow is the gravity of the water after the steel casing is completely immersed in water, ρwater is the density of the water displaced by the steel casing, and Vwater is the volume of the water displaced by the steel casing;
[0050] After deducting its own weight, the upward pulling force that the steel casing process can provide is: F pull = F float - N weight = 125-72.7 = 52.3KN.
[0051] The present invention first uses a crawler crane in conjunction with a vibratory hammer to perform pile pulling construction, until the steel pipe pile cannot be pulled out any more, a steel casing is put on the pile body of the steel pipe pile, and water is poured into the steel casing to make it sink, and then it is connected to the steel sleeve, and then the steel casing is drained and floated, and the buoyancy of the steel casing when drained is used to assist in pile pulling construction. Compared with the currently commonly used hydraulic vibratory hammer construction method, the present invention reduces the investment in replacing large-scale hydraulic pile pulling equipment and saves construction costs. In addition, the steel material of the steel casing is easily available on the construction site, is simple to make, can be recycled, can be processed and expanded as needed, and can be recycled after use. At the same time, it can also be used to remove steel pipe piles that are difficult to remove.
[0052] Of course, the above are only typical examples of the present invention. In addition, the present invention may also have many other specific implementations. All technical solutions formed by equivalent replacement or equivalent transformation fall within the scope of protection required by the present invention.
Claims
1. A simple steel pipe pile removal construction method, characterized in that: The following steps are involved: S1. Steel casing prefabrication: S11. The steel casing is manufactured in advance according to the outline size specifications. There are circular holes in the center of the top and bottom surfaces of the steel casing, and a circular water outlet is also provided on the top surface; S12, using a crawler crane and a flatbed truck to transport the steel casing prepared in step S11 to the pipe pulling pile construction area for standby use; S2. Dismantling the trestle structure above the steel pipe piles: After the crawler crane cooperates with the flatbed truck to transfer the steel casing, it further removes the handrails, water pipes and cable facilities attached to the trestle and platform. After the removal is completed, the bridge deck is separated from the distribution beam by manual cutting, and the whole is transformed into modules for easy lifting. The dismantled bridge deck is transported to the backyard for storage via the trestle by a flatbed truck, and the distribution beam is lifted and hoisted span by span, and then transported to the backyard for storage by a flatbed truck. The connection system between the piles is cut, and then it is hoisted onto the flatbed truck and transported to the backyard for storage via the trestle; S3, the steel pipe pile is pulled out until it is difficult to lift: after completing step S2, a vibrating hammer is installed on the crawler crane. After the vibrating hammer is installed, the vibrating hammer clamps the steel pipe pile through a clamp and starts to pull out the pile. During the pile pulling process, the steel pipe pile must be vibrated for 1 to 2 minutes to liquefy the soil around the steel pipe pile before lifting the vibrating hammer to start pulling out the pile. During the pile pulling process, the pulling force is gradually increased and cannot be increased suddenly until it cannot be pulled out; S4, lowering the steel casing to the water surface, and filling it with water to sink it: After completing step S3, use a crawler crane to lift the prefabricated steel casing, align the circular hole in the center of the bottom surface with the top of the steel pipe pile, slowly lower the steel casing to the water surface, place a water pump outside the steel casing, and draw the water injection pipe of the water pump into the water inlet on the top of the steel casing to sink the steel casing with water; S5. Clean the silt on the steel pipe pile and weld the stiffening steel plate: When the top surface of the steel casing is about to be lowered to the water surface, stop the water injection work of the water pump, clean the silt and debris on the steel pipe pile, and then weld a circle of stiffening steel plate on the steel pipe pile. The bottom height of the stiffening steel plate is slightly above the top surface of the steel casing to ensure that the steel casing can be tightly pressed against the stiffening steel plate after the steel casing is drained; S6. Draining the steel casing with a vibrating hammer to pull out the pile: gradually drain the water inside the steel casing by using a water pump placed inside the steel casing, control the steel casing and the stiffening steel plate to be pressed tightly together, and after the pressing is completed, start the vibrating hammer, and at the same time use the water pump placed inside the steel casing to drain all the water, and use the buoyancy of the water on the steel casing and the pulling force of the vibrating hammer to pull out the steel pipe pile until the steel pipe pile is completely pulled out; S7. Storage of steel pipe piles: After the steel pipe piles are removed by crawler crane in step S6, the steel pipe piles are stored in the backyard.
2. The simple steel pipe pile removal construction method according to claim 1 is characterized in that: In S3, the pile pulling process requires continuous debugging of the vibratory hammer and the boom of the crawler crane to obtain various technical parameters for pile pulling and provide the best operating parameters for subsequent pile pulling.
3. The simple steel pipe pile removal construction method according to claim 1 is characterized in that: Calculation of pile pull force: The outline dimensions of the steel casing are 2.5m long, 2.5m wide and 2m high. The diameter of the circular holes in the center of the top and bottom of the steel casing is φ800mm, and the diameter of the circular water outlet on the top is φ300mm. Mechanical technical parameters of vibratory hammer: Maximum pile pulling force is 254KN; The total weight of the steel casing and stiffening plate is calculated to be N weight = 7.27t; After water injection, the steel casing sinks completely, and the buoyancy provided by water is: Fbuoyancy = Grow = ρwater * Vwater, so Fbuoyancy = 1000kg / m3*2.5m*2.5m*2m=12500kg=125KN, where Fbuoyancy is the buoyancy of the steel casing when it is completely immersed in water, Grow is the gravity of the water after the steel casing is completely immersed in water, ρwater is the density of the water displaced by the steel casing, and Vwater is the volume of the water displaced by the steel casing; After deducting its own weight, the upward pulling force that the steel casing process can provide is: F pull = F float - N weight = 125-72.7 = 52.3KN.