Bridge main pier construction method suitable for complex embankment area of tidal river channel
By adopting the combination of Lassen steel sheet pile cofferdam-retaining support pile composite and drilling pile support system in complex embankments in the tidal river channel, the problems of soil collapse and construction work in flood control wall are solved, and the main The safety and economicality of pier construction have been improved.
Patent Information
- Application Number
- CN202410719473.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-05
- Publication Date
- 2024-11-26
AI Technical Summary
During construction in complex embankments in tidal rivers, the existing technology is difficult to effectively prevent soil from collapse around flood control walls, and it is difficult to meet the safety and economic requirements of the main pier construction, especially in the complex geology of soft soil layers and weathered rock layers. Under conditions.
The Lassen steel sheet pile cofferdam-retaining support pile composite is adopted, and the U-shaped Lassen steel sheet pile cofferdam-retaining support pile is formed by combining the drilling pile support system and the Lassen steel sheet pile cofferdam system. The composite body ensures the stability of the soil around the flood control wall, and uses technical means such as trestles and high-pressure rotary spray piles to prevent soil collapse during the construction process.
It effectively prevents the collapse of soil around the flood control wall, improves the safety and economy of the main pier construction work, and ensures the smooth progress and quality of construction.
Smart Images

Figure CN119021251A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to a method for constructing a main bridge pier suitable for a complex embankment area of a tidal river channel, and belongs to the technical field of bridge construction. Background Art
[0002] When designing the super-large bridge across Fenghua River in Section IV of the Yinzhou Avenue Expressway (Airport Road-Yinheng Line) project in Ningbo, Zhejiang, the main pier on the east side was designed in the embankment area of the main stream of Fenghua River based on the following considerations:
[0003] ① The Yinzhou Avenue Expressway adopts a split structure of upper and lower sections when crossing the Fenghua River, that is, river crossing passages are set up on both sides of the existing Yinzhou Bridge, so the elevated road is bifurcated;
[0004] ② The main bridge is a steel truss, which should be kept as straight as possible to reduce bending, so the total length of the main bridge should not exceed 400m;
[0005] ③ The main span crosses the Fenghua River, the west side span crosses the Hengba River, and the east side span crosses the Xiku River. The main span is not less than 150m due to flood control and navigation requirements, and the main pier is aligned with the old bridge pier as much as possible; the side span is not more than 80% of the main span, not less than 60% of the main span, and try to keep a gap of 3 to 4m with the old bridge - considering that the span of the old bridge is only 100m, if the west main pier is aligned with the old bridge, the east main pier will be in the Xiku River, and the east side span will overlap with the existing bridge, which is unacceptable.
[0006] Note: The elevated route cannot be adjusted to either side because the south side is permanent farmland and the north side involves 110kV power pipelines.
[0007] The embankment of the main stream of Fenghua River is different from that of conventional river channels. The embankment conditions in this section are extremely complex (see Appendix Figure 1 ), which is reflected in the following 6 points:
[0008] 1) The mainstream of Fenghua River is a typical tidal river channel with a high-tidal and low-tidal level difference of up to 3.74m. Therefore, when constructing a cofferdam in this area, the load state of the cofferdam varies greatly;
[0009] 2) The Fenghua River embankment is a typical embankment separation structure, and the distance between embankments is small, less than 5.0m;
[0010] 3) Due to architectural design requirements, the main pier is located outside the flood control embankment, and 1 / 2 of the main pier is located in the mainstream, and 1 / 2 is located in the river bank, so the target abutment of the main pier coincides with the existing bank wall. Therefore, the existing embankment structure must be cleared before the pier is implemented;
[0011] 4) The bank wall is located in the scour area and has been built many times, including riprap to squeeze out silt, pinewood piles, etc.;
[0012] 5) The flood control wall must not be damaged during the construction period, especially the inclination caused by foundation settlement, otherwise it will not meet the requirements of water conservancy flood control - during the obstacle clearing stage, it may cause the flood control embankment to slide (the flood control embankment adopts an expanded foundation and has extremely poor lateral resistance);
[0013] 6) Complex geological conditions, such as Figure 2 As shown in the figure, the surface layer of 10m is silty clay, which is a typical soft soil layer; 18m to 22m below the riverbed is a medium-weathered rock layer, which is not only impossible for temporary steel sheet piles or lock-mouth steel pipe piles to invade (which means that the setting depth of the cofferdam is only 18 to 22m below the riverbed), but also difficult for GPS drilling rigs to enter the rock - if impact drilling rigs are used, the construction efficiency will be greatly reduced, the construction cost will be greatly increased, and it is not suitable for the existing retaining support structure. In the riverbank area, cement mixing piles are used in some areas due to the need for previous embankment construction.
[0014] In order to ensure the completion of the construction of the main pier cap and columns under the above conditions, the conventional steel box cofferdam solution was adopted. With the help of the steel box cofferdam's own bearing capacity and rigidity, the coordination site faced many difficulties and challenges:
[0015] 1. Conventional steel casing operations require the use of completed bored piles (steel casing) to achieve sinking. Because the main pier cap overlaps with the existing embankment, the bored piles cannot be implemented without clearing the existing embankment.
[0016] 2. The steel box cofferdam is usually divided into several sections along the height direction, and the height of a single section is usually 4.0m to 7.5m. If calculated based on 4.0m, the weight of a single section exceeds 65 tons, and the operating radius is 21m, a 500-ton crawler crane is required for lifting (the waterfront section is a scouring area with frequent ship traffic, so a floating crane cannot be used);
[0017] 3. Before the existing bank wall is cleaned, it is affected by riprap, pine piles, etc., so a long-arm excavator is required to clear and sink at the same time;
[0018] 4. The existing abutment has Fenghua River channel on one side, Yinzhou Bridge on the other, park road between flood control wall and bank wall on one side (only for long-arm excavator operation, not capable of 500-ton crawler crane), and flood control wall and Xiku River on one side. Crawler crane can only rely on trestle (across Xiku River and terminate at flood control wall) as operating platform. At present, there is no trestle in China that meets the 170-ton single pile bearing capacity operation requirements.
[0019] In summary, it is necessary to develop a new support system to meet the actual needs of engineering construction. Summary of the invention
[0020] The purpose of the present invention is to provide a bridge main pier construction method suitable for complex embankment areas of tidal rivers, which can effectively prevent the surrounding soil of the flood control wall from collapsing toward the shore wall during the main pier construction operation, ensure the safety of the main pier construction operation, and improve the economy of the main pier construction operation.
[0021] In order to achieve the above technical objectives, the present invention will adopt the following technical solutions:
[0022] A method for constructing a main bridge pier in a complex embankment area of a tidal river channel, which relies on a Larsen steel sheet pile cofferdam-retaining support pile complex for construction operations, wherein a quay wall and a flood control wall are arranged in the complex embankment area of the tidal river channel, and the method for constructing a main bridge pier in a complex embankment area of the tidal river channel comprises the following steps:
[0023] Step 1: Plan and determine the construction location of the cofferdam support complex:
[0024] According to the construction drawings, the construction location of the cofferdam support complex for the Larsen steel sheet pile cofferdam-retaining support pile complex was planned in the complex embankment area of the tidal river channel;
[0025] The cofferdam support complex construction position includes a cofferdam construction position for constructing a Larsen steel sheet pile cofferdam system and a support pile construction position for constructing a bored cast-in-place pile support system;
[0026] The cofferdam construction position is set at the water side of the complex embankment area of the tidal river channel; the support pile construction position is set between the cofferdam construction position and the flood control wall and is arranged close to the cofferdam construction position, and the cofferdam construction position and the support pile construction position are independent of each other;
[0027] Step 2: Trestle construction:
[0028] Build a trestle bridge as a temporary access to the construction site of the cofferdam support complex;
[0029] Step 3: Construction of Larsen steel sheet pile cofferdam-retaining support pile complex:
[0030] Step 3.1: Construction of bored pile support system:
[0031] According to the construction drawings, at the support pile construction position planned in step 1, the construction work of each retaining support bored cast-in-place pile is first carried out one by one, and then the cap beam is cast on the pile top of each retaining support bored cast-in-place pile, so that each retaining support bored cast-in-place pile can be connected as a whole, improving the integrity of the retaining support bored cast-in-place pile, and finally, high-pressure rotary jet pile construction is carried out between two adjacent retaining support bored cast-in-place piles to block the soil between the two adjacent retaining support bored cast-in-place piles, so as to prevent the soil collapse on the bank side of the bored cast-in-place pile support system during the construction of the Larsen steel sheet pile cofferdam system;
[0032] Step 3.2, Larsen steel sheet pile cofferdam system construction:
[0033] After the bored cast-in-place pile support system constructed in step 3.1 reaches the designed strength, the bored cast-in-place piles of each main pier are constructed one by one at the cofferdam construction position planned in step 1, and then Larsen steel sheet piles are driven at the preset Larsen steel sheet pile positions to construct U-shaped Larsen steel sheet piles at the cofferdam construction position; among the U-shaped Larsen steel sheet piles, the Larsen steel sheet piles at the closed end are arranged on the water side of the cofferdam construction position, and the Larsen steel sheet piles at the two side arms are arranged toward the bored cast-in-place pile support system, and the ends of the Larsen steel sheet piles at the two side arms are aligned with the bored cast-in-place pile support system. The protection system is sealed; then the soil is excavated to the bottom of the foundation pit in the area surrounded by the U-shaped Larsen steel sheet pile and the bored cast-in-place pile support system. In this process, the soil is excavated layer by layer and the surrounding purlin is built layer by layer. When the soil is excavated to the installation position of the surrounding purlin support, the surrounding purlin support system is first built and the concrete turning block is poured, so that the surrounding purlin is sequentially connected to the surrounding purlin support system, the concrete turning block and the bored cast-in-place pile support system into one, and then the soil excavation is continued until the bottom of the foundation pit; finally, the bottom sealing concrete construction is carried out at the bottom of the foundation pit, so as to obtain the Larsen steel sheet pile cofferdam-retaining support pile complex;
[0034] Step 4: Construction of main pier cap and columns:
[0035] The main pier cap and column construction is completed in the area enclosed by the Larsen steel sheet pile cofferdam-retaining support pile complex formed in step 3 and above the main pier bored piles;
[0036] Step 5: Rebuild the shore wall.
[0037] After the construction of the main pier cap and main pier columns is completed in step 4, the Larsen steel sheet pile cofferdam-retaining support pile complex is removed, and the quay wall is rebuilt at the original quay wall location.
[0038] Preferably, the construction process of the bored pile support system in step 3.1 specifically includes the following steps:
[0039] Step 3.1.1: Construction of bored piles for retaining support:
[0040] According to the construction drawings, the retaining support bored cast-in-place piles are constructed one by one at the pile positions of each retaining support bored cast-in-place pile in the support pile construction position, so as to form a retaining pipe gallery between the cofferdam construction position and the flood control wall, so as to prevent the soil in the area enclosed by the Larsen steel sheet pile cofferdam-retaining support pile complex from causing the soil collapse on the side of the flood control wall during the excavation stage;
[0041] During the construction process, all construction equipment, except for the excavator working at the shore wall, were working on the pier.
[0042] Step 3.1.2, crown beam construction:
[0043] After the bored cast-in-place piles for retaining support constructed in step 3.1 are inspected and accepted, the crown beam edge line is laid out according to the construction drawings, the crown beam position is excavated by an excavator, the steel bars are tied and the formwork is supported, and finally concrete is poured to form the crown beam, so that the pile tops of the bored cast-in-place piles for retaining support are connected into one through the crown beam;
[0044] Step 3.1.3, high pressure jet grouting pile construction:
[0045] After the bored piles reach the designed strength, a crane is used to lower the high-pressure jet grouting machine on the trestle to carry out high-pressure jet grouting pile construction operations at the construction locations of each high-pressure jet grouting pile.
[0046] Through the construction work of steps 3.1.1-3.1.3, the bored cast-in-place pile support system can be constructed at the target construction location.
[0047] Preferably, the cofferdam construction site is set at the location of the quay wall in the complex embankment area of the tidal river channel.
[0048] Preferably, the construction process of the Larsen steel sheet pile cofferdam system in step 3.2 specifically includes the following steps:
[0049] Step 3.2.1: After the bored pile support system constructed in step 3.1 reaches the designed strength, the existing shore wall structure and obstacles at the cofferdam construction location are cleared;
[0050] Step 3.2.2, set up the drilling platform with the help of the trestle;
[0051] Step 3.2.3, place the pile boring machine on the drilling platform and carry out bored pile construction of the main pier;
[0052] Step 3.2.4: After the bored cast-in-place piles of the main pier are accepted, Larsen steel sheet piles are driven one by one at the pile positions of the Larsen steel sheet piles planned at the construction site, and the Larsen steel sheet piles are enclosed to form a U-shaped Larsen steel sheet pile, and the ends of the U-shaped Larsen steel sheet piles are sealed with the bored cast-in-place pile support system;
[0053] Step 3.2.5, after the U-shaped Larsen steel sheet pile and bored cast-in-place pile support system are closed and ensured to be watertight, start excavating the soil to the bottom of the foundation pit in the area surrounded by the U-shaped Larsen steel sheet pile and bored cast-in-place pile support system. In this process, excavate the soil layer by layer and build the purlin layer by layer. When the soil is excavated to the installation position of the purlin support system, first build the purlin support system and pour the concrete turning block, so as to connect the purlin through the purlin support system, the concrete turning block and the bored cast-in-place pile support system in sequence, and then continue to excavate the soil until the bottom of the foundation pit;
[0054] Step 3.2.6: After the foundation pit bottom is accepted, carry out bottom concrete construction.
[0055] Preferably, in step 3.2.5, there are two purlin support systems constructed, corresponding to the first and second purlin support systems, and the first purlin support system is located above the second purlin support system;
[0056] After the bottom concrete reaches the design strength, the second purlin support system needs to be removed.
[0057] Preferably, in step 3.2.5, the concrete turning block is cast and formed by the following steps:
[0058] Step 3.2.5.1, weld the embedded steel plate on the outside of the purlin;
[0059] Step 3.2.5.2, tie the embedded steel cage, and set the first connecting bar on one side of the embedded steel cage and the second connecting bar on the other side;
[0060] Step 3.2.5.3, connect the first connecting bar to the bored pile of retaining support at the corresponding position by planting bars, and weld the second connecting bar to the embedded steel plate;
[0061] Step 3.2.5.4: Pour concrete to form concrete turning blocks to connect the purlins with the retaining support bored piles.
[0062] Preferably, in step 3.2.4, after the end of the U-shaped Larsen steel sheet pile is sealed with the bored pile support system, a corner reinforcement pile is arranged outside the sealing position of the U-shaped Larsen steel sheet pile and the bored pile support system.
[0063] Preferably, the construction process of the main pier cap and the columns described in step 4 specifically includes the following steps:
[0064] Step 5.1, tie the cap steel bars, set up the formwork and pour the cap concrete to form the main pier cap;
[0065] Step 5.2: After the cap concrete reaches the design strength, backfill the two sides with coarse sand, and set a temporary plate support at the top of the main pier cap to connect the main pier cap with the corresponding position of the U-shaped Larsen steel sheet pile and bored cast-in-place pile support system;
[0066] Step 5.3: dismantle the first purlin support system; and carry out column construction on the main pier cap.
[0067] Preferably, in step 3.2, after the second purlin support system is erected, concrete is poured and filled between two adjacent retaining support bored piles on one side of the adjacent purlin, so that the Larsen steel sheet pile cofferdam system and the bored pile support system are connected as one.
[0068] Based on the above technical objectives, the present invention has the following advantages over the prior art:
[0069] The bridge main pier construction method suitable for complex embankment areas of tidal rivers described in the present invention comprises the following steps: before the main pier construction operation is carried out, a bored cast-in-place pile support system is first arranged between the main pier construction operation position (i.e., the cofferdam construction position) and the flood control wall. The bored cast-in-place pile support system is a pipe gallery formed by evenly arranging a number of retaining support bored cast-in-place piles, thereby supporting the soil around the flood control wall. By optimizing the existing Larsen steel sheet pile cofferdam system, the bored cast-in-place pile support system and the Larsen steel sheet pile cofferdam system are structurally integrated to form a Larsen steel sheet pile cofferdam-retaining support pile complex, further ensuring the ability to support the soil around the flood control wall, effectively preventing the soil around the flood control wall from collapsing toward the cofferdam construction position during the excavation of the Larsen steel sheet pile cofferdam system, improving the safety of the cofferdam construction, and ensuring the safety of the main pier construction. BRIEF DESCRIPTION OF THE DRAWINGS
[0070] Figure 1 It is a common example of complex embankment in tidal rivers;
[0071] Figure 1 Middle: 1-flood control wall; 2-railing; 3-bank wall; 4-long pine piles; 5-ground beam; 6-riprap accumulation area;
[0072] Figure 2 It is a common geological cross-section structural map of riverbank areas;
[0073] Figure 2 Middle: 1-flood control wall; 2-railing; 3-bank wall; 4-long pine pile; 5-ground beam; 6-riprap accumulation area; 71, miscellaneous fill layer; 72, plain fill layer; 73, silty clay layer; 74, silty clay layer; 75, moderately weathered silty mudstone;
[0074] Figure 3It is a structural elevation diagram of a deep-water composite cofferdam system (foundation pit excavation stage) suitable for complex embankment areas of tidal rivers according to the present invention;
[0075] Figure 4 It is a structural elevation diagram of a deep-water composite cofferdam system (column construction stage) suitable for complex embankment areas of tidal rivers according to the present invention;
[0076] Figure 5 It is a plan view of the deep-water composite cofferdam system suitable for complex embankment areas of tidal rivers according to the present invention;
[0077] Figure 6 It is an enlarged structural schematic diagram of the concrete turning block between the perimeter purlin support system and the bored cast-in-place pile support system;
[0078] Figure 3-6 Middle: 81-U-shaped Larsen steel sheet pile; 82-Purlin; 821-Purlin reinforcement; 822-Corner reinforcement; 83-Purlin support system; 84-Main pier column; 85-Main pier bored pile; 86-Main pier cap; 87-Cap bottom cushion; 9-bored pile support system; 91-retaining support bored pile; 92-high-pressure jet grouting pile; 93-concrete caulking; 101-corner reinforcement pile; 102-concrete turning block; 103-first connecting bar;
[0079] Figure 7 It is a flow chart of the main pier construction method of the bridge suitable for complex embankment areas of tidal rivers according to the present invention. DETAILED DESCRIPTION
[0080] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all the embodiments. The following description of at least one exemplary embodiment is actually only illustrative and is by no means any limitation to the present invention and its application or use. Based on the embodiments in the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention. Unless otherwise specified, the relative arrangement, expressions and numerical values of the components and steps described in these embodiments do not limit the scope of the present invention. The techniques, methods and equipment known to ordinary technicians in the relevant fields may not be discussed in detail, but in appropriate cases, the techniques, methods and equipment should be regarded as part of the specification. In all examples shown and discussed here, any specific value should be interpreted as merely exemplary, rather than as a limitation. Therefore, other examples of the exemplary embodiments may have different values.
[0081] For ease of description, spatially relative terms such as "above", "above", "on the upper surface of", "above", etc. may be used here to describe the spatial positional relationship between a device or feature and other devices or features as shown in the figure. It should be understood that spatially relative terms are intended to include different orientations of the device in use or operation in addition to the orientation described in the figure. For example, if the device in the accompanying drawings is inverted, the device described as "above other devices or structures" or "above other devices or structures" will be positioned as "below other devices or structures" or "below other devices or structures". Thus, the exemplary term "above" can include both "above" and "below". The device can also be positioned in other different ways (rotated 90 degrees or in other orientations).
[0082] Example 1
[0083] like Figures 3 to 6 As shown, a Larsen steel sheet pile cofferdam-soil retaining support pile complex is disclosed, which is used to assist the main pier construction of the bridge in the complex embankment area of the tidal river channel. The complex embankment area of the tidal river channel is provided with a quay wall 3 and a flood control wall 1, and a railing 2 is provided on the quay wall 3. The Larsen steel sheet pile cofferdam-soil retaining support pile complex includes a Larsen steel sheet pile cofferdam system, a bored cast-in-place pile support system 91 and a concrete turning block 102, wherein:
[0084] The Larsen steel sheet pile cofferdam system is arranged on the water side (i.e., the river side, adjacent to the river) of the complex embankment area of the tidal river channel. In fact, based on the actual construction drawings, the Larsen steel sheet pile cofferdam system is designed at the location of the quay wall 3 in the complex embankment area of the tidal river channel, and the bored cast-in-place pile support system 9 is arranged between the Larsen steel sheet pile cofferdam system and the flood control wall 1.
[0085] The purpose of arranging the bored cast-in-place pile support system 9 in the present invention is to ensure the overall stability of the existing flood control wall 1 when clearing obstacles in the pier area.
[0086] To this end, the bored pile support system 9 needs to meet the following requirements in terms of function:
[0087] 1) It has sufficient bearing capacity to resist the uneven lateral earth pressure on both sides of the bored pile support system 9, and at the same time bear the lateral earth pressure generated by the operating machinery on the side of the flood control wall 1;
[0088] 2) It has sufficient rigidity to ensure that the lateral displacement of the flood control wall 1 is no more than 5 mm, avoid cracking and damage of the original concrete flood control wall 1 caused by foundation deviation, and maintain the original flood control function;
[0089] 3) The construction of bored pile support system 9 has little impact on the existing flood control wall 1, and the ground acceleration during construction should not exceed 5m / s2 . Reduce the vibration damage of the original concrete flood control wall 1 caused by acceleration.
[0090] Based on the above functional requirements, the present invention transforms the bored cast-in-place pile support system 9 into a pipe gallery composed of a plurality of retaining support bored cast-in-place piles 91 .
[0091] Since the present invention arranges a bored cast-in-place pile support system 9 used as retaining support between the Larsen steel sheet pile cofferdam system and the existing flood control wall 1, it basically breaks through the restrictions on the construction of deep-water cofferdam systems at the construction site. However, in view of the geological conditions of the construction site itself (such as the small bedrock depth and poor geological conditions of the overburden), how to ensure that the bored cast-in-place pile support system 9 formed by the construction meets the above-mentioned functional requirements is a technical problem that the present invention needs to solve.
[0092] Based on the construction site of the present invention, without considering the influence of the Larsen steel sheet pile cofferdam system, the boundary conditions of the bored pile support system 9 are determined, mainly including the following points:
[0093] 1) Determine the design elevation of the top of the bored pile 91 for retaining support:
[0094] The top design elevation of the bored pile 91 for retaining support is +2.60m, 80cm higher than the navigation water level +1.83m (to resist the influence of astronomical tides, not floods), and is set according to the requirements of "bank wall 3";
[0095] 2) Determine the ground elevation of the bored pile support system 9:
[0096] The ground elevation of the bored pile support system 9 is the existing ground elevation, calculated as +3.50m, that is, no soil is unloaded or piled, and the original state is maintained;
[0097] 3) Determine the construction location of the bored pile support system 9:
[0098] The bored cast-in-place pile support system 9 is arranged as close as possible to the construction area of the Larsen steel sheet pile cofferdam system and away from the existing flood control wall 1; during actual construction, the net distance between the bored cast-in-place pile support system 9 and the Larsen steel sheet pile cofferdam system can be set to 0.5m.
[0099] 4) Determine the downstream bottom elevation of the bored pile support system 9:
[0100] According to the preliminary exploration data, the bottom elevation of the original quay wall 3 structural layer is about -0.50m. Considering the over-excavation effect of the construction work, the downstream bottom elevation of the bored pile support system 9 is calculated as -0.70m.
[0101] 5) Determine the lowest water level in tidal rivers:
[0102] The lowest water level in the tidal river channel is about -1.76m, and if it is unfavorable, it will be calculated as -1.8m.
[0103] Based on the boundary conditions of the bored pile support system 9, it can be seen that the pile length of the retaining support bored pile 91 of the present invention is limited. Therefore, when designing the bored pile support system 9, the following contents need to be paid attention to:
[0104] 1) Pile diameter and spacing of bored cast-in-place piles 91 for retaining support:
[0105] The larger the bored pile diameter, the higher the single pile bearing capacity and stiffness, and the corresponding larger spacing (lateral earth pressure within the subordinate width range); conversely, the smaller the pile diameter, the lower the single pile bearing capacity and stiffness, and the spacing needs to be reduced to reduce the lateral earth pressure allocated to the single pile. Therefore, under the condition of meeting the functional requirements, economic indicators (concrete volume and corresponding steel bar usage, where the steel bar configuration must meet both the bored pile's own bearing capacity requirements and crack width limit requirements) are the key factors in evaluating technical solutions.
[0106] Preliminary analysis shows that the overall stability of the Φ0.8m@1.5m type, Φ1.0m@2.0m type, Φ1.2m@2.5m type, and Φ1.5m@3.3m type is relatively close. After carrying capacity evaluation and economic analysis of these four types of layouts, the pile diameter and spacing of the bored cast-in-place retaining piles 91 are selected as follows:
[0107] The single pile diameter of the retaining bored cast-in-place pile 91 is 1.5m, the pile spacing is 3.3m, the pile top elevation is +2.60m, the pile bottom elevation is -19.4m, and the single pile length is 22m.
[0108] 2) Retaining problems of 91 bored piles:
[0109] Due to the need for a certain distance between bored piles in the hole-making process to prevent the soil layer on the side of the hole from collapsing, it is inevitable that there will be a certain distance between bored piles. After the bored piles reach the designed strength, the soil layer behind the pile body will flow into the foundation pit along the gap between the bored piles. For this reason, high-pressure rotary jet piles 92 are installed between the bored piles to prevent the soil layer from flowing and to stop water.
[0110] The retaining support bored pile 91 is 2.25m away from the cap near the river channel, that is, assuming that the width of the Larsen steel sheet pile cofferdam system is 0.75m, the inner edge of the Larsen steel sheet pile cofferdam system is 1.0m away from the edge of the cap. A 0.5m gap is reserved between the retaining support bored pile 91 and the outer edge of the cofferdam.
[0111] A high-pressure jet grouting pile 92 with a diameter of 0.6 m and a depth of 22 m is driven between the retaining support bored piles 91 . The top and bottom elevations of the high-pressure jet grouting pile 92 are consistent with those of the retaining support bored piles 91 .
[0112] 3) The integrity problem between the bored cast-in-place piles 91 for retaining support. The present invention arranges a crown beam on the top layer of each bored cast-in-place pile 91 for retaining support, so that each bored cast-in-place pile 91 for retaining support is connected to form a whole. The design basis of the crown beam includes: ① The top elevation should be flush with the original soil elevation at the three existing bank walls, that is, the top elevation of the retaining support system should not be higher than the original ground elevation at the three existing bank walls, because it is useless and wasteful; ② The bottom elevation should depend on the seepage effect of the highest tidal water level during construction (the highest water level of the tidal river channel within 30 days is different), that is, during the construction stage of the crown beam (excavation of the working surface, removal of the pile head, steel bar binding, formwork support, concrete pouring, etc.), the working surface should be kept dry; ③ The width of the crown beam is usually "extended 200mm to 250mm on both sides of the pile diameter" - in essence, the crown beam is only a structural requirement, and its calculation and design requirements are relatively low, so the determination of its bottom elevation is particularly critical. According to calculations, the width of the crown beam is 2.0m, the height is 1.5m, and the bottom elevation of the crown beam is +1.10m, which can meet the seepage stability requirements.
[0113] In addition, the present invention also connects the two adjacent earth retaining support bored cast-in-place piles 91 to the purlin 82 on one side adjacent to the purlin 82 through concrete caulking 93, thereby solving the integrity of the connection between the Larsen steel sheet pile cofferdam system and the bored cast-in-place pile support system 9.
[0114] After the above-mentioned bored pile support system 9 is completed, the construction machinery can operate on the rear side of the retaining support bored piles 91, clear the obstacles within the target foundation range, and then deploy a conventional drilling operation platform, using the conventional positive cycle rotary drilling process to complete the operation of 9 1.5m main pier bored piles 85.
[0115] Since the Larsen steel sheet pile has a low rigidity, the Larsen steel sheet pile cofferdam system itself cannot transmit tidal water pressure. Therefore, it is necessary to optimize the existing Larsen steel sheet pile cofferdam system so that it can be integrated with the bored cast-in-place pile support system 9 to form an integral structure. Specifically:
[0116] The Larsen steel sheet pile cofferdam system described in the present invention includes a U-shaped Larsen steel sheet pile 81 and an internal support system, that is, the present invention changes the existing rectangular Larsen steel sheet pile into a U-shaped Larsen steel sheet pile 81, so that the closed end of the U-shaped Larsen steel sheet pile 81 is arranged on the water side of the complex embankment area of the tidal river channel, and the two side arms of the U-shaped Larsen steel sheet pile 81 point to the bored cast-in-place pile support system 9, and the two side arm ends of the U-shaped Larsen steel sheet pile 81 are respectively sealed with the two ends of the bored cast-in-place pile support system 9. It can be seen that the Larsen steel sheet pile cofferdam system described in the present invention cancels the Larsen steel sheet pile on the side adjacent to the bored cast-in-place pile support system 9, and is only supported by three sides of Larsen steel sheet piles, and together with the retaining support bored cast-in-place pile 91 support system 9, it constitutes the cofferdam body. The structure of the internal support system is similar to that of the internal support system in the existing Larsen steel sheet pile cofferdam system, which is arranged on the inner side of the U-shaped Larsen steel sheet pile 81 and located in the upper area of the U-shaped Larsen steel sheet pile 81, including the purlin 82 and the purlin support system 83; the purlin support system 83 and the purlin 82 are connected as a whole through the purlin reinforcement 821. The number of purlin support systems 83 can be one (one layer) or two (layers). When the number of purlin support systems 83 is two, the two purlin support systems correspond to the first and second purlin support systems, and the first purlin support system is located above the second purlin support system, that is, the second purlin support system is adjacent to the main pier cap 86. Each purlin support system includes four purlin supports, and both ends of each purlin support are connected to a group of corresponding adjacent edges of the purlin 82 through purlin reinforcements 821 to form a whole.
[0117] In order to achieve the transmission of tidal water pressure, the bored cast-in-place pile support system 9 described in the present invention is connected to the purlin 82 at the same height as the purlin support system through a concrete turning block 102. The concrete turning block 102 is set by the "rebar embedding method". Specifically, the concrete turning block 102 includes a pre-embedded steel cage and concrete cast into one piece with the pre-embedded steel cage, and a pre-embedded steel plate is arranged on the outer side of the purlin 82 to serve as a support point for the purlin 82. The pre-embedded steel cage is arranged between the pre-embedded steel plate and the retaining support bored cast-in-place pile 91, and a first connecting rib 103 is arranged at one end of the pre-embedded steel cage to connect with the retaining support bored cast-in-place pile 91 at the corresponding position through the first connecting rib 103, and then the concrete can be poured to form the concrete turning block 102 to connect the purlin support and the retaining support bored cast-in-place pile 91 into one piece.
[0118] The purlin 82 is rectangular in shape as a whole and is connected at the corners by corner stiffeners 822 .
[0119] There is usually a module mismatch at the junction (intersection) of the side arm end of the U-shaped Larsen steel sheet pile 81 and the retaining support bored pile 91 - even if the matching is perfect in the design stage, the coupling between the side arm end of the U-shaped Larsen steel sheet pile 81 and the retaining support bored pile 91 is difficult to fit perfectly. Considering that the length of the retaining support bored pile 91 exceeds the side arm end of the U-shaped Larsen steel sheet pile 81, 1 to 2 Larsen steel sheet piles are added outside the corner point formed by the intersection of the side arm end of the U-shaped Larsen steel sheet pile 81 and the retaining support bored pile 91 as a water-stop curtain. It should be noted here that the load at the corner point is shared by the purlin 82 and the purlin support, and the focus is on preventing leakage.
[0120] The main pier is constructed in the area enclosed by the Larsen steel sheet pile cofferdam system and the bored cast-in-place pile support system 9, including the main pier bored cast-in-place piles 85, the main pier cap 86 arranged above the top of the main pier bored cast-in-place piles 85, and the main pier columns 84 arranged above the main pier cap 86; the main pier cap 86 is connected to each side of the U-shaped Larsen steel sheet pile 81 by a first temporary plate support, and is connected to the bored cast-in-place pile support system 9 by a second temporary plate support.
[0121] The design principles of the Larsen steel sheet pile cofferdam system in the preliminary design (not considering the influence of the retaining support system for the time being, and considering it as a conventional cofferdam system) specifically include the following:
[0122] 1) Consider the highest tidal water level without considering the flood control water level, that is, it is assumed that the Larsen steel sheet pile cofferdam system is submerged during floods. Specifically, the design water level of the Larsen steel sheet pile cofferdam system is calculated as high tide water level + 2.00m, and the cofferdam top elevation is calculated as + 2.5m.
[0123] 2) According to the conventional Larsen steel sheet pile cofferdam system, the base elevation is -3.80m, the maximum excavation depth is 6.6m, the ratio of embedded depth to excavation depth in the preliminary design stage is 2:1, and the total height of the cofferdam is allowed to be 18m.
[0124] 3) A clear distance of 1.0m is reserved between the inner wall of the cofferdam and the main pier cap 86 as working space for the cap construction;
[0125] 4) Two inner support systems and one bottom concrete are set in a single Larsen steel sheet pile cofferdam system, and the average spacing between the two inner support systems is about 2.5m. The bottom concrete can form the main pier cap cushion 87.
[0126] 5) Larsen steel sheet piles use Larsen IV type steel sheet piles.
[0127] In the actual construction process, the retaining support bored pile 91 has three use conditions:
[0128] 1) Working condition 1 (first construction stage): the state after the original bank wall 3 is removed and before the cofferdam is constructed. At this time, the fill elevation behind the bored pile support system 9 is +2.60m, that is, the fill elevation on the shore side of the bored pile support system 9 is +2.60m, and the soil layer elevation after excavation in front of the bored pile support system 9 is -0.70m, that is, the soil layer elevation on the water side of the bored pile support system 9 is -0.70m, so the cantilever length of the bored pile support system 9 is 3.3m.
[0129] 2) Working condition 2 (second construction stage): the cofferdam is excavated to the bottom layer (the bottom elevation of the bottom concrete is -4.10m at this time), and before the bottom concrete is poured, the nominal excavation depth of the bored pile support system 9 reaches 6.6m. At this time, the Larsen steel sheet pile cofferdam system has the first and second internal support systems;
[0130] 3) Working condition three (third construction stage): After the construction of the main pier column 84 is completed and the internal support system is removed, although the nominal excavation depth of the bored pile support system 9 remains basically unchanged at 6.3m (bottom concrete top elevation -3.80m), only the bottom concrete remains at this stage and the second internal support has been removed.
[0131] Based on the analysis of the above three operating conditions, it can be seen that:
[0132] 1) The retaining height on the side of the bored pile support system 9 is much greater than the retaining height on the side of the Larsen steel sheet pile cofferdam system;
[0133] 2) The bored pile support system 9 has already borne the active earth pressure of the first stage (working condition 1) before the Larsen steel sheet pile cofferdam system is subjected to stress; in the second stage (working condition 2), the active earth pressure borne by the bored pile support system 9 increases accordingly due to the increase in the support height;
[0134] 3) The soil pressure increment borne by the bored cast-in-place pile support system 9 in the second stage is lower than the soil pressure increment on the Larsen steel sheet pile cofferdam system side. The reason is that the soil pressure increment of the bored cast-in-place pile support system 9 comes from the part from -0.70m (the soil layer elevation after the shore wall 3 is removed) to -4.1m (the bottom elevation of the bottom concrete seal in the cofferdam), and the soil pressure increment of the Larsen steel sheet pile cofferdam system comes from the part from +2.00m (high tide water level elevation) to -4.1m (the bottom elevation of the bottom concrete seal in the cofferdam).
[0135] Based on the above analysis, in order to ensure that the bored pile support system 9 meets the required stability requirements, the coupling effect of the Larsen steel sheet pile cofferdam system and the bored pile support system 9 must be considered during the implementation of the Larsen steel sheet pile cofferdam system. In other words, the design load of the bored pile support system 9 should be based on the first stage, and the increment of the second stage should be balanced by the increment on the Larsen steel sheet pile cofferdam system side.
[0136] It can be seen that the Larsen steel sheet pile cofferdam-soil retaining support pile complex constructed by the present invention has the following characteristics:
[0137] 1. Since the Larsen steel sheet pile itself has a small stiffness, it cannot effectively transfer the water and soil loads on the river side by itself, so it is necessary to set up a strong purlin support inside the cofferdam.
[0138] 2. After the construction of the pedestal is completed, the column position needs to be avoided when arranging the purlin support, and the second purlin support needs to be removed after the construction of the pedestal is completed, and the first purlin support needs to be retained.
[0139] 3. The water and soil pressure on the river side is directly transmitted to the steering block through the cofferdam itself and the internal purlin support, and then transmitted to the bored pile support system 9 by the steering block, so the force is more direct and clear.
[0140] 4. The river side and adjacent side of the U-shaped Larsen steel sheet pile 81 can be closed on three sides by locking buckles, but on the bored pile side, a row of 0.6m diameter high-pressure rotary jet piles 92 water-stop curtains are needed to prevent water and soil from pouring into the pit. At the same time, a high-pressure rotary jet pile 92 needs to be driven on the contact surface between the U-shaped Larsen steel sheet pile 81 and the bored pile to strengthen the plugging.
[0141] Example 2
[0142] like Figure 7 As shown, based on the above-mentioned Larsen steel sheet pile cofferdam-soil retaining support pile complex, the present invention provides a bridge main pier construction method suitable for complex embankment areas of tidal rivers, which specifically includes the following steps:
[0143] Step 1: Plan and determine the construction location of the cofferdam support complex:
[0144] According to the construction drawings, the construction location of the cofferdam support complex for the Larsen steel sheet pile cofferdam-retaining support pile complex was planned in the complex embankment area of the tidal river channel;
[0145] The cofferdam support complex construction position includes a cofferdam construction position for constructing a Larsen steel sheet pile cofferdam system and a support pile construction position for constructing a bored cast-in-place pile support system 91;
[0146] The cofferdam construction position is set on the water side of the complex embankment area of the tidal river channel. Specifically, the cofferdam construction position is set at the location of the shore wall 3 in the complex embankment area of the tidal river channel; the support pile construction position is set between the cofferdam construction position and the flood control wall 1 and is arranged close to the cofferdam construction position, and the cofferdam construction position and the support pile construction position are independent of each other.
[0147] Step 2: Trestle construction:
[0148] Since the main pier is located near the river and there is no existing road that can directly reach it, it is necessary to build a trestle bridge as a temporary access construction channel to the construction location of the cofferdam support complex;
[0149] Step 3: Construction of Larsen steel sheet pile cofferdam-retaining support pile complex:
[0150] Step 3.1, construction of bored pile support system 91:
[0151] According to the construction drawings, at the supporting pile construction position planned in step 1, the construction work of each retaining support bored cast-in-place pile 91 is first carried out one by one, and then a crown beam is cast on the pile top of each retaining support bored cast-in-place pile 91, so that each retaining support bored cast-in-place pile 91 can be connected into a whole, thereby improving the integrity of the retaining support bored cast-in-place pile 91, and finally, high-pressure rotary jet pile 92 is constructed between two adjacent retaining support bored cast-in-place piles 91 to block the soil between the two adjacent retaining support bored cast-in-place piles 91, so as to prevent the soil collapse on the bank side of the bored cast-in-place pile support system 91 during the construction of the Larsen steel sheet pile cofferdam system.
[0152] Specifically, the construction process of the bored pile support system 91 in this step includes the following steps:
[0153] Step 3.1.1, construction of earth retaining support bored piles 91:
[0154] According to the construction drawings, the retaining support bored cast-in-place piles 91 are constructed one by one at the pile positions of the retaining support bored cast-in-place piles 91 in the support pile construction position, so as to form a retaining pipe gallery between the cofferdam construction position and the flood control wall 1, so as to prevent the soil in the area enclosed by the Larsen steel sheet pile cofferdam-retaining support pile complex from causing the soil on the side of the flood control wall 1 to collapse during the excavation stage;
[0155] During the construction process, all construction equipment, except for the excavator working at three locations on the shore wall, were working on the pier;
[0156] Step 3.1.2, crown beam construction:
[0157] After the bored piles 91 constructed in step 3.1 are inspected and accepted, the crown beam edge line is laid out according to the construction drawing, the crown beam position is excavated by an excavator, the steel bars are tied and the formwork is set up, and finally concrete is poured to form the crown beam, so that the tops of the bored piles 91 are connected into one by the crown beam;
[0158] Step 3.1.3, construction of high pressure jet grouting pile 92:
[0159] After the bored piles reach the designed strength, a crane is used to lower the high-pressure jet grouting pile machine 92 on the trestle to perform high-pressure jet grouting pile construction operations one by one at the construction locations of each high-pressure jet grouting pile 92;
[0160] Through the construction work of steps 3.1.1-3.1.3, the bored cast-in-place pile support system 91 can be constructed at the target construction location.
[0161] Step 3.2, Larsen steel sheet pile cofferdam system construction:
[0162] After the bored cast-in-place pile support system 91 constructed in step 3.1 reaches the designed strength, the bored cast-in-place piles 85 of each main pier are constructed one by one at the cofferdam construction position planned in step 1, and then Larsen steel sheet piles are driven at the preset Larsen steel sheet pile positions to construct and form U-shaped Larsen steel sheet piles 81 at the cofferdam construction position; among the U-shaped Larsen steel sheet piles 81, the Larsen steel sheet piles at the closed end are arranged on the water side of the cofferdam construction position, and the Larsen steel sheet piles at the two side arms are arranged toward the bored cast-in-place pile support system 91, and the ends of the Larsen steel sheet piles at the two side arms are aligned with the bored cast-in-place pile support system 91. 1 is sealed; then, the soil is excavated to the bottom of the foundation pit in the area surrounded by the U-shaped Larsen steel sheet pile 81 and the bored pile support system 91. In this process, the soil is excavated layer by layer and the surrounding purlin 82 is built layer by layer. When the soil is excavated to the installation position of the surrounding purlin support, the surrounding purlin support system is first built and the concrete turning block 102 is poured, so that the surrounding purlin 82 is sequentially connected to the bored pile support system 91 through the surrounding purlin support system, the concrete turning block 102, and then the soil excavation is continued until the bottom of the foundation pit; finally, the bottom sealing concrete construction is carried out at the bottom of the foundation pit, so as to obtain the Larsen steel sheet pile cofferdam-retaining support pile complex.
[0163] Specifically, the construction process of the Larsen steel sheet pile cofferdam system in this step includes the following steps:
[0164] Step 3.2.1, after the bored pile support system 91 constructed in step 3.1 reaches the designed strength, the existing shore wall 3 structure and obstacles at the cofferdam construction location are cleared;
[0165] Step 3.2.2, set up the drilling platform with the help of the trestle;
[0166] Step 3.2.3, placing a pile boring machine on the drilling platform and constructing bored piles 85 for the main pier;
[0167] Step 3.2.4: After the main pier bored cast-in-place piles 85 are accepted, Larsen steel sheet piles are driven one by one at the pile positions of the Larsen steel sheet piles planned at the construction site, and the Larsen steel sheet piles are made to enclose to form a U-shaped Larsen steel sheet pile 81, and at the same time, the ends of the U-shaped Larsen steel sheet piles 81 are sealed to the bored cast-in-place pile support system 91.
[0168] In this step, after the end of the U-shaped Larsen steel sheet pile 81 is sealed with the bored pile support system 91 , a corner reinforcement pile 101 is arranged outside the sealing position between the U-shaped Larsen steel sheet pile 81 and the bored pile support system 91 .
[0169] In order to ensure that the end of the U-shaped Larsen steel sheet pile 81 is sealed with the bored pile support system 91, the present invention adds 1 to 2 steel sheet piles outside the intersection of the end of the U-shaped Larsen steel sheet pile 81 and the bored pile support system 91 as a water-stop curtain.
[0170] It should be noted here that the main purpose of the water-stop curtain is to prevent seepage.
[0171] Step 3.2.5, after the U-shaped Larsen steel sheet pile 81 and the bored pile support system 91 are closed and ensured to be watertight, start excavating the soil to the bottom of the foundation pit in the area surrounded by the U-shaped Larsen steel sheet pile 81 and the bored pile support system 91. In this process, the soil is excavated layer by layer and the surrounding purlin 82 is built layer by layer. When the soil is excavated to the installation position of the surrounding purlin support system, the surrounding purlin support system is first built and the concrete turning block 102 is poured, so that the surrounding purlin 82 is sequentially connected to the bored pile support system 91 through the surrounding purlin support system, the concrete turning block 102, and then the soil excavation is continued until the bottom of the foundation pit;
[0172] There are two purlin support systems built in this step, corresponding to the first and second purlin support systems, and the first purlin support system is located above the second purlin support system.
[0173] In this step, after the second purlin support system is erected, concrete filling 93 is poured between two adjacent retaining support bored piles 91 on one side of the adjacent purlin 82 to connect the Larsen steel sheet pile cofferdam system and the bored pile support system 91 into one.
[0174] In this step, the concrete turning block 102 is cast and formed by the following steps:
[0175] Step 3.2.5.1, welding the embedded steel plate on the outside of the purlin 82;
[0176] Step 3.2.5.2, tying the embedded steel cage, and setting the first connecting rib 103 on one side of the embedded steel cage, and setting the second connecting rib on the other side;
[0177] Step 3.2.5.3, connecting the first connecting bar 103 to the earth retaining support bored pile 91 at the corresponding position by planting reinforcement, and welding the second connecting bar to the embedded steel plate;
[0178] Step 3.2.5.4: pour concrete to form a concrete turning block 102 to achieve the connection between the surrounding purlin 82 and the retaining support bored piles 91.
[0179] Step 3.2.6: After the foundation pit bottom is accepted, carry out bottom concrete construction.
[0180] Step 4: Construction of main pier cap 86 and columns:
[0181] The main pier cap 86 and columns are constructed in the area enclosed by the Larsen steel sheet pile cofferdam-retaining support pile complex formed in step 3 and above the main pier bored piles 85.
[0182] In this step, the construction process of the main pier cap 86 and the columns specifically includes the following steps:
[0183] Step 5.1, tying the cap steel bars, supporting the formwork and pouring the cap concrete to form the main pier cap 86;
[0184] Step 5.2, after the cap concrete reaches the design strength, coarse sand is backfilled on both sides, and a temporary plate support is set at the upper opening of the main pier cap 86 to connect the main pier cap 86 with the corresponding positions of the U-shaped Larsen steel sheet pile 81 and the bored pile support system 91;
[0185] Step 5.3, dismantle the first purlin support system; and perform column construction on the main pier cap 86.
[0186] Step 5: Reconstruct the shore wall 3.
[0187] After the construction of the main pier cap 86 and the main pier column 84 is completed in step 4, the Larsen steel sheet pile cofferdam-retaining support pile complex is removed, and the shore wall 3 is rebuilt at the original shore wall 3 position.
Claims
1. A method for constructing a bridge main pier suitable for a complex embankment area of a tidal river, relying on a Larsen steel sheet pile cofferdam-retaining support pile complex for construction operations, wherein a quay wall and a flood control wall are arranged in the complex embankment area of the tidal river, and characterized in that: The main pier construction method for bridges in complex embankment areas of tidal rivers includes the following steps: Step 1: Plan and determine the construction location of the cofferdam support complex: According to the construction drawings, the construction location of the cofferdam support complex for the Larsen steel sheet pile cofferdam-retaining support pile complex was planned in the complex embankment area of the tidal river channel; The cofferdam support complex construction position includes a cofferdam construction position for constructing a Larsen steel sheet pile cofferdam system and a support pile construction position for constructing a bored cast-in-place pile support system; The cofferdam construction position is set at the water side of the complex embankment area of the tidal river channel; the support pile construction position is set between the cofferdam construction position and the flood control wall and is arranged close to the cofferdam construction position, and the cofferdam construction position and the support pile construction position are independent of each other; Step 2: Trestle construction: Build a trestle bridge as a temporary access to the construction site of the cofferdam support complex; Step 3: Construction of Larsen steel sheet pile cofferdam-retaining support pile complex: Step 3.1: Construction of bored pile support system: According to the construction drawings, at the support pile construction position planned in step 1, the construction work of each retaining support bored cast-in-place pile is first carried out one by one, and then the cap beam is cast on the pile top of each retaining support bored cast-in-place pile, so that each retaining support bored cast-in-place pile can be connected as a whole, improving the integrity of the retaining support bored cast-in-place pile, and finally, high-pressure rotary jet pile construction is carried out between two adjacent retaining support bored cast-in-place piles to block the soil between the two adjacent retaining support bored cast-in-place piles, so as to prevent the soil collapse on the bank side of the bored cast-in-place pile support system during the construction of the Larsen steel sheet pile cofferdam system; Step 3.2, Larsen steel sheet pile cofferdam system construction: After the bored cast-in-place pile support system constructed in step 3.1 reaches the designed strength, the bored cast-in-place piles of each main pier are constructed one by one at the cofferdam construction position planned in step 1, and then Larsen steel sheet piles are driven at the preset Larsen steel sheet pile positions to construct U-shaped Larsen steel sheet piles at the cofferdam construction position; among the U-shaped Larsen steel sheet piles, the Larsen steel sheet piles at the closed end are arranged on the water side of the cofferdam construction position, and the Larsen steel sheet piles at the two side arms are arranged toward the bored cast-in-place pile support system, and the ends of the Larsen steel sheet piles at the two side arms are aligned with the bored cast-in-place pile support system. The protection system is sealed; then the soil is excavated to the bottom of the foundation pit in the area surrounded by the U-shaped Larsen steel sheet pile and the bored cast-in-place pile support system. In this process, the soil is excavated layer by layer and the surrounding purlin is built layer by layer. When the soil is excavated to the installation position of the surrounding purlin support, the surrounding purlin support system is first built and the concrete turning block is poured, so that the surrounding purlin is sequentially connected to the surrounding purlin support system, the concrete turning block and the bored cast-in-place pile support system into one, and then the soil excavation is continued until the bottom of the foundation pit; finally, the bottom sealing concrete construction is carried out at the bottom of the foundation pit, so as to obtain the Larsen steel sheet pile cofferdam-retaining support pile complex; Step 4: Construction of main pier cap and columns: The main pier cap and column construction is completed in the area enclosed by the Larsen steel sheet pile cofferdam-retaining support pile complex formed in step 3 and above the main pier bored piles; Step 5: Rebuild the shore wall. After the construction of the main pier cap and main pier columns is completed in step 4, the Larsen steel sheet pile cofferdam-retaining support pile complex is removed, and the quay wall is rebuilt at the original quay wall location.
2. The method for constructing a main bridge pier suitable for complex embankment areas of tidal rivers according to claim 1, characterized in that: The construction process of the bored pile support system in step 3.1 specifically includes the following steps: Step 3.1.1: Construction of bored piles for retaining support: According to the construction drawings, the retaining support bored cast-in-place piles are constructed one by one at the pile positions of each retaining support bored cast-in-place pile in the support pile construction position, so as to form a retaining pipe gallery between the cofferdam construction position and the flood control wall, so as to prevent the soil in the area enclosed by the Larsen steel sheet pile cofferdam-retaining support pile complex from causing the soil collapse on the side of the flood control wall during the excavation stage; During the construction process, all construction equipment, except for the excavator working at the shore wall, were working on the pier. Step 3.1.2, crown beam construction: After the bored cast-in-place piles for retaining support constructed in step 3.1 are inspected and accepted, the crown beam edge line is laid out according to the construction drawings, the crown beam position is excavated by an excavator, the steel bars are tied and the formwork is supported, and finally concrete is poured to form the crown beam, so that the pile tops of the bored cast-in-place piles for retaining support are connected into one through the crown beam; Step 3.1.3, high pressure jet grouting pile construction: After the bored piles reach the designed strength, a crane is used to lower the high-pressure jet grouting machine on the trestle to carry out high-pressure jet grouting pile construction operations at the construction locations of each high-pressure jet grouting pile. Through the construction work of steps 3.1.1-3.1.3, the bored cast-in-place pile support system can be constructed at the target construction location.
3. The method for constructing a main bridge pier suitable for complex embankment areas of tidal rivers according to claim 1, characterized in that: The cofferdam construction position is set at the location of the bank wall in the complex embankment area of the tidal river channel.
4. The method for constructing a main bridge pier suitable for complex embankment areas of tidal rivers according to claim 3, characterized in that: The construction process of the Larsen steel sheet pile cofferdam system in step 3.2 specifically includes the following steps: Step 3.2.1: After the bored pile support system constructed in step 3.1 reaches the designed strength, the existing shore wall structure and obstacles at the cofferdam construction location are cleared; Step 3.2.2, set up the drilling platform with the help of the trestle; Step 3.2.3, place the pile boring machine on the drilling platform and carry out bored pile construction of the main pier; Step 3.2.4: After the bored cast-in-place piles of the main pier are accepted, Larsen steel sheet piles are driven one by one at the pile positions of the Larsen steel sheet piles planned at the construction site, and the Larsen steel sheet piles are enclosed to form a U-shaped Larsen steel sheet pile, and the ends of the U-shaped Larsen steel sheet piles are sealed with the bored cast-in-place pile support system; Step 3.2.5, after the U-shaped Larsen steel sheet pile and bored cast-in-place pile support system are closed and ensured to be watertight, start excavating the soil to the bottom of the foundation pit in the area surrounded by the U-shaped Larsen steel sheet pile and bored cast-in-place pile support system. In this process, excavate the soil layer by layer and build the purlin layer by layer. When the soil is excavated to the installation position of the purlin support system, first build the purlin support system and pour the concrete turning block, so as to connect the purlin through the purlin support system, the concrete turning block and the bored cast-in-place pile support system in sequence, and then continue to excavate the soil until the bottom of the foundation pit; Step 3.2.6: After the foundation pit bottom is accepted, carry out bottom concrete construction.
5. The method for constructing a main bridge pier suitable for complex embankment areas of tidal rivers according to claim 4, characterized in that: In step 3.2.5, there are two purlin support systems built, corresponding to the first and second purlin support systems, and the first purlin support system is located above the second purlin support system; After the bottom concrete reaches the design strength, the second purlin support system needs to be removed.
6. The method for constructing a main bridge pier suitable for complex embankment areas of tidal rivers according to claim 5, characterized in that: In step 3.2.5, the concrete turning block is cast and formed by the following steps: Step 3.2.5.1, weld the embedded steel plate on the outside of the purlin; Step 3.2.5.2, tie the embedded steel cage, and set the first connecting bar on one side of the embedded steel cage and the second connecting bar on the other side; Step 3.2.5.3, connect the first connecting bar to the bored pile of retaining support at the corresponding position by planting bar, and weld the second connecting bar to the embedded steel plate; Step 3.2.5.4: Pour concrete to form concrete turning blocks to connect the purlins with the bored cast-in-place piles of retaining support.
7. The method for constructing a main bridge pier suitable for complex embankment areas of tidal rivers according to claim 5, characterized in that: In step 3.2.4, after the end of the U-shaped Larsen steel sheet pile is sealed with the bored cast-in-place pile support system, a corner reinforcement pile is arranged outside the sealing position of the U-shaped Larsen steel sheet pile and the bored cast-in-place pile support system.
8. The method for constructing a main bridge pier suitable for complex embankment areas of tidal rivers according to claim 5, characterized in that: The construction process of the main pier cap and the columns described in step 4 specifically includes the following steps: Step 5.1, tie the cap steel bars, set up the formwork and pour the cap concrete to form the main pier cap; Step 5.2: After the concrete of the cap reaches the designed strength, backfill the two sides with coarse sand and set up temporary plate support at the top of the main pier cap. To connect the main pier cap with the corresponding position of the U-shaped Larsen steel sheet pile and bored pile support system; Step 5.3, dismantle the first purlin support system; And column construction is carried out on the main pier cap.
9. The method for constructing a main bridge pier suitable for complex embankment areas of tidal rivers according to claim 5, characterized in that: In step 3.2, after the second purlin support system is erected, concrete is poured between two adjacent retaining support bored piles on one side of the adjacent purlin to fill the gap, so that the Larsen steel sheet pile cofferdam system and the bored pile support system are connected as one.