Anti-seismic high-toughness shear wall structure and construction method thereof

By using transverse hoop reinforcement and longitudinal reinforcement components in the shear wall structure, combined with the connection between fixing screws and expansion bolts, the problems of insufficient seismic toughness and construction deformation of the shear wall are solved, and higher seismic performance is achieved and stability.

CN119021396APending Publication Date: 2024-11-26LVYI CONSTR GRP CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411156525.4
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-22
Publication Date
2024-11-26

AI Technical Summary

Technical Problem

The existing shear wall structure is simple in structure, insufficient seismic toughness and stability, and there is a risk of brittle damage and looseness between welding and expansion bolt connections. The uneven pouring of concrete during construction leads to deformation, affecting seismic effect.

Method used

A seismic and high toughness shear wall structure is designed, using transverse hoop reinforcement and longitudinal reinforcement components, ensuring the connection is stable through fixing screws and expansion bolts, and the concrete pouring interval and vibration compaction are controlled during construction, and the concrete is regularly monitored. Deform to prevent cracks and stress concentration.

Benefits of technology

It improves the seismic toughness and stability of the shear wall, avoids the impact of bolt loosening, ensures the stability and reliability of the building, and reduces deformation caused by concrete shrinkage and creep, improving seismic effect.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119021396A_ABST
    Figure CN119021396A_ABST
Patent Text Reader

Abstract

The invention discloses an anti-seismic high-toughness shear wall structure and a construction method thereof.The anti-seismic high-toughness shear wall structure comprises a shear wall body, a reinforcing assembly and a connecting assembly, first longitudinal ribs are arranged on a base of the shear wall body, the first longitudinal ribs are evenly sleeved with transverse hoop reinforcing bars, and the transverse hoop reinforcing bars are evenly sleeved with first stirrups and second stirrups. The first stirrup and the second stirrup are used for preliminarily reinforcing the stability of the shear wall, and then the reinforcing assembly is used for secondary reinforcement, so that the anti-seismic toughness of the shear wall is effectively improved; the shear wall structures are connected through the connecting assemblies, and the situation that the stability and reliability of the shear wall are affected due to bolt looseness is avoided; the concrete is vibrated compactly after being poured, it is ensured that the concrete is compact and free of bubbles, deformation caused by shrinkage and creep of the concrete is reduced, parameters such as perpendicularity, flatness and displacement of a wall are monitored, it is found that deformation exceeds an allowable range or abnormity exists, treatment can be conducted in time, and the situation that the subsequent construction or the anti-seismic effect of a shear wall is affected is avoided.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of building structures, and in particular to an earthquake-resistant high-toughness shear wall structure and a construction method thereof. Background Art

[0002] Shear wall, also known as wind-resistant wall, earthquake-resistant wall or structural wall, is a wall in a house or structure that mainly bears horizontal and vertical loads caused by wind load or earthquake. Its main purpose is to prevent structural shear damage. According to the size, number and arrangement of the openings on the shear wall, it can be divided into integral wall, small-opening integral wall, connected limb wall, frame-supported shear wall, wall frame, etc.

[0003] Shear walls are mainly used in reinforced concrete frames, flat plates and beamless floor structures to enhance the overall stability and seismic performance of the structure. The existing shear wall structure basically meets the requirements, but there are still certain shortcomings. First, the existing shear wall structure is simple in construction and is usually reinforced at the base. The seismic toughness and stability of the shear wall itself are still at a general level; second, the existing prefabricated shear wall structure is often connected by welding or expansion bolts. Welding and expansion bolt connections have the risk of brittle failure and bolt loosening, affecting the stability and reliability of the building; third, the existing shear wall may be deformed during construction due to uneven concrete pouring, improper subsequent processing and monitoring, etc., affecting the seismic effect of the shear wall; therefore, it is necessary to design a seismic-resistant and highly tough shear wall structure and its construction method. Summary of the invention

[0004] The object of the present invention is to provide a seismic-resistant and high-toughness shear wall structure and a construction method thereof, so as to solve the problems raised in the above-mentioned background technology.

[0005] To achieve the above-mentioned purpose, the present invention provides the following technical solutions: an earthquake-resistant and high-toughness shear wall structure, comprising a shear wall, a reinforcement assembly and a connection assembly, wherein a first longitudinal rib is arranged on the base of the shear wall, a transverse hoop reinforcement is evenly sleeved on the first longitudinal rib, a first hoop reinforcement and a second hoop reinforcement are evenly sleeved on the transverse hoop reinforcement, a third hoop reinforcement is evenly sleeved on the first longitudinal rib, and a reinforcement piece in the reinforcement assembly is sleeved on the first longitudinal rib, a reinforcement piece, a fixing hole is provided on the reinforcement piece, a fixing screw is sleeved on the fixing hole, a fixing column in the connection assembly is arranged inside the shear wall, a connecting plate is fixedly connected to one end of the fixing column, a first connecting piece is arranged on the connecting plate, a first expansion bolt is sleeved in a through hole provided on one side of the first connecting piece, the first expansion bolt is sleeved in a through hole provided on one side of the connecting piece, the first connecting piece and the connecting piece are connected to each other through the first expansion bolt, a second connecting piece is arranged on one side of the first connecting piece, a sleeve is sleeved in the through hole provided on the second connecting piece, and the first longitudinal rib is sleeved on the sleeve.

[0006] As a further technical solution of the present invention, the reinforcement component is composed of a reinforcement piece, a fixing hole, a fixing screw and a fixing nut, and one end of the fixing screw is threadedly connected to the fixing nut.

[0007] As a further technical solution of the present invention, the connection assembly consists of a fixing plate, a fixing column, a connecting plate, a first connecting piece, a first expansion bolt, a second connecting piece, a sleeve, and an expansion screw, and one end of the fixing column is fixedly connected to the fixing plate.

[0008] As a further technical solution of the present invention, an expansion screw is connected to the first expansion bolt.

[0009] As a further technical solution of the present invention, the connecting column is arranged inside the reinforced base, and a first reinforcing rib is arranged on the bottom plate of the reinforced base. A transverse reinforcing hoop and a longitudinal reinforcing hoop are sleeved on the first reinforcing rib, and reinforcing tie bars are evenly arranged on the transverse reinforcing hoop.

[0010] As a further technical solution of the present invention, the first reinforcing rib is sleeved in the sleeve, and one end of the first reinforcing rib is fixedly connected to the first longitudinal rib.

[0011] As a further technical solution of the present invention, a second longitudinal rib and a third longitudinal rib are arranged on the base of the shear wall, one end of the second longitudinal rib is fixedly connected to the second reinforcing rib, one end of the third longitudinal rib is fixedly connected to the third reinforcing rib, and the second reinforcing rib and the third reinforcing rib are both arranged on the bottom plate of the reinforced base.

[0012] A method for constructing a seismic-resistant and high-toughness shear wall structure, comprising the following steps: step one, design and scheme confirmation; step two, material preparation; step three, construction site layout; step four, foundation treatment; step five, formwork and steel bar layout; step six, concrete pouring; step seven, subsequent treatment; step eight, acceptance and quality control;

[0013] In the above step 1, confirm according to the architectural drawings and construction plan to ensure that all details are accurate and determine the location and size of the shear wall;

[0014] In the above step 2, the required concrete, steel bars, formwork and other materials are prepared according to the construction plan, and quality inspection is carried out to ensure compliance with standards and requirements;

[0015] In the above step 3, the construction site is cleaned up to ensure that the site is flat, necessary safety measures are set up, such as fences, warning signs, etc., and construction personnel are trained and given safety education to ensure that they are familiar with the construction process and operating specifications;

[0016] In the above step 4, according to the design requirements, the foundation is processed, including backfilling, compaction, etc., to ensure the stability of the foundation, and then the concrete foundation is poured according to the design drawings, and the necessary foundation reinforcement is installed;

[0017] In the above step 5, the steel bars are arranged and the wall formwork is assembled according to the design requirements;

[0018] In the above step 6, after the formwork and reinforcement are arranged, the concrete is poured, and the concrete is vibrated and compacted at any time during the pouring process to avoid the generation of gaps and bubbles;

[0019] In the above step 7, after pouring, it is necessary to maintain a moist environment to prevent wall cracks and shrinkage, and remove the formwork when the concrete strength reaches the standard;

[0020] In the above step eight, after the construction is completed, the construction materials and construction process are inspected and accepted by the engineer.

[0021] As a further technical solution of the present invention, in the step five, the specific operation of steel bar arrangement is to confirm the specific position of the shear wall according to the drawings, and then arrange the steel bars. First, adjust the position of the longitudinal steel bars as required to ensure that the steel bar spacing, row spacing, etc. meet the requirements of the drawings, and use welding and other methods to extend the longitudinal steel bars. Tie the hidden main and door and window lintel steel bars according to the design requirements, and then tie the horizontal steel bars of the wall. The horizontal steel bars should intersect with the longitudinal steel bars vertically and be tied firmly point by point, and then set hooks and pads to fix the steel bar position and ensure the thickness of the protective layer; the specific operation of the template assembly is to confirm the template position line and the template control line according to the design drawings, and then paste the sponge rubber strip on the position line, which mainly plays a buffering role to prevent the steel template from damaging the floor, and then fix the template, strengthen the fixation of the template by tension bolts, triangular supports, etc., and then pour five centimeters thick cement mortar to prevent the shear wall from rotting.

[0022] As a further technical solution of the present invention, in step six, the specific operation during concrete pouring is to pre-arrange the location of the concrete unloading point and the number of vibrator operators according to the size of the shear wall, transport the concrete from the mixing site to the pouring site, and control it within one hour. The pouring is carried out continuously, and the pouring interval is controlled within two hours. The moving spacing of the vibrator rod is less than fifty centimeters, and the duration of each vibration point is based on the presence of floating slurry on the concrete surface to ensure that the concrete is dense and free of bubbles, and reduce deformation caused by concrete shrinkage and creep. At the same time, regular maintenance is carried out after the pouring is completed to keep the wall surface moist and effectively prevent cracking and stress concentration. During the shear wall construction process, the verticality, flatness, displacement and other parameters of the wall are regularly monitored. If the deformation exceeds the allowable range or there is an abnormality, it can be handled in time to avoid affecting the subsequent construction or the stability of the shear wall.

[0023] Compared with the prior art, the beneficial effects of the present invention are as follows: the seismic-resistant and high-toughness shear wall structure and its construction method firstly strengthen the stability of the shear wall by means of the first and second stirrups sleeved on the transverse hoop reinforcement, then fix the transverse hoop reinforcement by means of the reinforcing piece sleeved on the first longitudinal reinforcement, and then lock by means of fixing screws and fixing nuts, so that the first longitudinal reinforcement and the transverse hoop reinforcement are fixed and locked to each other, thereby effectively improving the seismic toughness of the shear wall; by sleeve-fitting the connecting column arranged on the reinforcing base on the first connecting piece, and then fixing it by means of expansion bolts and expansion screws, the fixing plate and the fixing column fixedly connected to the first connecting piece are both arranged inside the shear wall, thereby ensuring the stability of the connection, and the first connecting piece is fixed by means of the sleeve sleeved on the second connecting piece. The first longitudinal reinforcement and the first reinforcing reinforcement are connected to complete the connection and fixation of the shear wall, avoiding the stability and reliability of the shear wall due to loose bolts; the pouring interval during concrete pouring is controlled within two hours, the moving interval of the vibrating rod is less than fifty centimeters, and the duration of each vibration point is based on the presence of floating slurry on the concrete surface, ensuring that the concrete is dense and free of bubbles, reducing deformation caused by concrete shrinkage and creep, and at the same time, regular maintenance is carried out after pouring to keep the wall surface moist, effectively preventing cracking and stress concentration, and regularly monitoring the verticality, flatness, displacement and other parameters of the wall during the shear wall construction process. If the deformation exceeds the allowable range or there is an abnormality, it can be dealt with in time to avoid affecting the subsequent construction or the seismic effect of the shear wall. BRIEF DESCRIPTION OF THE DRAWINGS

[0024] Figure 1 It is a three-dimensional diagram of the overall structure of the present invention;

[0025] Figure 2 It is a structural schematic diagram of the reinforcement component in the present invention;

[0026] Figure 3 for Figure 2 Schematic diagram of the structure of the middle A area;

[0027] Figure 4 It is a partial structural schematic diagram of the present invention;

[0028] Figure 5 It is a schematic diagram of the position structure of the expansion bolts in the present invention;

[0029] Figure 6 for Figure 5 Schematic diagram of the structure of the middle B area;

[0030] Figure 7 It is a schematic diagram of the position structure of the fixing plate in the present invention;

[0031] Figure 8 is a flow chart of the method of the present invention;

[0032] In the figure: 1. reinforced base; 2. shear wall; 3. first longitudinal rib; 4. transverse hoop reinforcement; 5. first hoop; 6. second hoop; 7. third hoop; 8. reinforcement assembly; 9. connection assembly; 10. connection column; 11. first reinforcing rib; 12. transverse reinforcing hoop; 13. longitudinal reinforcing hoop; 14. reinforcing tie bar; 15. second longitudinal rib; 16. third longitudinal rib; 17. second reinforcing rib; 18. third reinforcing rib; 81. reinforcement member; 82. fixing hole; 83. fixing screw; 84. fixing nut; 91. fixing plate; 92. fixing column; 93. connection plate; 94. first connecting member; 95. expansion bolt; 96. second connecting member; 97. sleeve; 98. expansion screw. DETAILED DESCRIPTION

[0033] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0034] Please see attached Figure 1 -Attached Figure 7The present invention provides an embodiment: a seismic resistant and high-toughness shear wall structure, comprising a shear wall body 2, a reinforcement assembly 8 and a connection assembly 9, wherein a first longitudinal rib 3 is arranged on the base of the shear wall body 2, a transverse hoop reinforcement 4 is evenly sleeved on the first longitudinal rib 3, a first hoop reinforcement 5 and a second hoop reinforcement 6 are evenly sleeved on the transverse hoop reinforcement 4, a third hoop reinforcement 7 is evenly sleeved on the first longitudinal rib 3, and a reinforcement piece 81 in the reinforcement assembly 8 is sleeved on the first longitudinal rib 3, a fixing hole 82 is opened on the reinforcement piece 81, and a fixing screw 83 is sleeved on the fixing hole 82, and the shear wall body 2 is provided with a first longitudinal rib 3. 2 is provided with a fixing column 92 in the connecting assembly 9, one end of the fixing column 92 is fixedly connected to a connecting plate 93, a first connecting member 94 is provided on the connecting plate 93, a first expansion bolt 95 is sleeved in a through hole opened on one side of the first connecting member 94, the first expansion bolt 95 is sleeved in a through hole opened on one side of the connecting column 10, the first connecting member 94 and the connecting column 10 are connected to each other through the first expansion bolt 95, a second connecting member 96 is provided on one side of the first connecting member 94, a sleeve 97 is sleeved in the through hole opened on the second connecting member 96, and a first longitudinal rib 3 is sleeved on the sleeve 97, The reinforcement component 8 is composed of a reinforcement member 81, a fixing hole 82, a fixing screw 83 and a fixing nut 84. One end of the fixing screw 83 is connected to the fixing nut 84 by a thread. The connection component 9 is composed of a fixing plate 91, a fixing column 92, a connecting plate 93, a first connecting member 94, a first expansion bolt 95, a second connecting member 96, a sleeve 97, and an expansion screw 98. One end of the fixing column 92 is fixedly connected to the fixing plate 91, and the first expansion bolt 95 is matched with the expansion screw 98. The connecting column 10 is arranged inside the reinforcement base 1, and a first reinforcement rib is arranged on the bottom plate of the reinforcement base 1. 11, a transverse reinforcing hoop 12 and a longitudinal reinforcing hoop 13 are sleeved on the first reinforcing rib 11, and reinforcing tie bars 14 are evenly arranged on the transverse reinforcing hoop 12. The first reinforcing rib 11 is sleeved in the sleeve 97, and one end of the first reinforcing rib 11 is fixedly connected to the first longitudinal rib 3, and a second longitudinal rib 15 and a third longitudinal rib 16 are arranged on the base of the shear wall 2, one end of the second longitudinal rib 15 is fixedly connected to the second reinforcing rib 17, and one end of the third longitudinal rib 16 is fixedly connected to the third reinforcing rib 18, and the second reinforcing rib 17 and the third reinforcing rib 18 are both arranged on the bottom plate of the reinforced base 1.

[0035] Please see attached Figure 8 , an embodiment provided by the present invention: a method for constructing a seismic resistant and high-toughness shear wall structure, comprising the following steps: step one, design and scheme confirmation; step two, material preparation; step three, construction site layout; step four, foundation treatment; step five, formwork and steel bar layout; step six, concrete pouring; step seven, subsequent treatment; step eight, acceptance and quality control;

[0036] In the above step 1, confirm according to the architectural drawings and construction plan to ensure that all details are accurate and determine the location and size of the shear wall;

[0037] In the above step 2, the required concrete, steel bars, formwork and other materials are prepared according to the construction plan, and quality inspection is carried out to ensure compliance with standards and requirements;

[0038] In the above step 3, the construction site is cleaned up to ensure that the site is flat, necessary safety measures are set up, such as fences, warning signs, etc., and construction personnel are trained and given safety education to ensure that they are familiar with the construction process and operating specifications;

[0039] In the above step 4, according to the design requirements, the foundation is processed, including backfilling, compaction, etc., to ensure the stability of the foundation, and then the concrete foundation is poured according to the design drawings, and the necessary foundation reinforcement is installed;

[0040] Among them, in the above step five, the arrangement of steel bars and the assembly of wall formwork are carried out according to the design requirements; the specific operation of steel bar arrangement is to confirm the specific position of the shear wall according to the drawings, and then arrange the steel bars. First, adjust the position of the longitudinal steel bars as required to ensure that the spacing and row spacing of the steel bars meet the requirements of the drawings, and use welding and other methods to extend the longitudinal steel bars. According to the design requirements, tie the hidden main and door and window lintel steel bars, and then tie the horizontal steel bars of the wall. The horizontal steel bars should intersect with the longitudinal steel bars vertically and be tied firmly point by point, and then set hooks and pads to fix the position of the steel bars and ensure the thickness of the protective layer; the specific operation of the formwork assembly is to confirm the formwork position line and formwork control line according to the design drawings, and then paste the sponge strip on the position line, which mainly plays a buffering role to prevent the steel formwork from damaging the floor, and then fix the formwork, strengthen the fixation of the formwork by tension bolts, triangular supports, etc., and then pour five centimeters thick cement mortar to prevent the shear wall from rotting;

[0041] Among them, in the above step six, concrete pouring is carried out after the formwork and steel bars are arranged, and the concrete is vibrated and compacted at any time during the pouring process to avoid the generation of gaps and bubbles; the specific operation during concrete pouring is to pre-arrange the location of the concrete unloading point and the number of vibrator operators according to the size of the shear wall, transport the concrete from the mixing site to the pouring site, and control it within one hour. The pouring is carried out continuously, and the pouring interval is controlled within two hours. The moving spacing of the vibrator rod is less than fifty centimeters, and the duration of each vibration point is the degree when the concrete surface presents floating slurry, ensuring that the concrete is dense and free of bubbles, reducing deformation caused by concrete shrinkage and creep, and at the same time, regular maintenance is carried out after the pouring is completed to keep the wall surface moist, effectively prevent cracking and stress concentration, and regularly monitor the verticality, flatness, displacement and other parameters of the wall during the shear wall construction process. If the deformation exceeds the allowable range or there is an abnormality, it can be handled in time to avoid affecting the subsequent construction or the stability of the shear wall;

[0042] In the above step 7, after pouring, it is necessary to maintain a moist environment to prevent wall cracks and shrinkage, and remove the formwork when the concrete strength reaches the standard;

[0043] In the above step eight, after the construction is completed, the construction materials and construction process are inspected and accepted by the engineer.

[0044] Working principle: When in use, firstly, the stability of the shear wall is initially strengthened by the first hoop reinforcement 5 and the second hoop reinforcement 6 sleeved on the transverse hoop reinforcement 4, and then the transverse hoop reinforcement 4 is fixed by the reinforcing piece 81 sleeved on the first longitudinal reinforcement 3, and then the fixing screws 83 and the fixing nuts 84 are used to lock the first longitudinal reinforcement 3 and the transverse hoop reinforcement 4 to each other, which effectively improves the seismic toughness of the shear wall; by sleeve-fitting the connecting column 10 set on the reinforced base 1 on the first connecting piece 94, and then fixing it with expansion bolts 95 and expansion screws 98, the fixing plate 91 and the fixing column 92 fixedly connected to the first connecting piece 94 are both arranged inside the shear wall to ensure the stability of the connection, and the first connecting piece 96 is fixed by the sleeve 97 sleeved on the second connecting piece 96. The longitudinal reinforcement 3 and the first reinforcement 11 are sleeved to complete the connection and fixation of the shear wall, avoiding the stability and reliability of the shear wall affected by the loose bolts; the pouring interval during concrete pouring is controlled within two hours, the moving interval of the vibrator is less than fifty centimeters, and the duration of each vibration point is based on the floating slurry on the concrete surface, ensuring that the concrete is dense and free of bubbles, reducing the deformation caused by concrete shrinkage and creep, and at the same time, regular maintenance is carried out after the pouring is completed to keep the wall surface moist, effectively preventing cracking and stress concentration, and regularly monitoring the verticality, flatness, displacement and other parameters of the wall during the shear wall construction process. If the deformation exceeds the allowable range or there is an abnormality, it can be dealt with in time to avoid affecting the subsequent construction or the seismic effect of the shear wall.

[0045] It will be apparent to those skilled in the art that the invention is not limited to the details of the exemplary embodiments described above and that the invention can be implemented in other specific forms without departing from the spirit or essential features of the invention. Therefore, the embodiments should be considered exemplary and non-limiting in all respects, and the scope of the invention is defined by the appended claims rather than the foregoing description, and it is intended that all variations falling within the meaning and scope of the equivalent elements of the claims be included in the invention. Any reference numeral in a claim should not be considered as limiting the claim to which it relates.

Claims

1. A seismic-resistant and high-toughness shear wall structure, comprising a shear wall body (2), a reinforcement assembly (8) and a connection assembly (9), characterized in that: The base of the shear wall (2) is provided with a first longitudinal rib (3), a transverse hoop reinforcement (4) is evenly sleeved on the first longitudinal rib (3), a first hoop reinforcement (5) and a second hoop reinforcement (6) are evenly sleeved on the transverse hoop reinforcement (4), a third hoop reinforcement (7) is evenly sleeved on the first longitudinal rib (3), and a reinforcing member (81) in a reinforcing assembly (8) is sleeved on the first longitudinal rib (3), a fixing hole (82) is provided on the reinforcing member (81), a fixing screw (83) is sleeved on the fixing hole (82), and a fixing column (92) in a connecting assembly (9) is provided inside the shear wall (2). One end of the fixed column (92) is fixedly connected to a connecting plate (93), a first connecting member (94) is arranged on the connecting plate (93), a first expansion bolt (95) is sleeved in a through hole opened on one side of the first connecting member (94), the first expansion bolt (95) is sleeved in a through hole opened on one side of the connecting column (10), the first connecting member (94) and the connecting column (10) are connected to each other through the first expansion bolt (95), a second connecting member (96) is arranged on one side of the first connecting member (94), a sleeve (97) is sleeved in a through hole opened on the second connecting member (96), and a first longitudinal rib (3) is sleeved on the sleeve (97).

2. The seismic-resistant high-toughness shear wall structure according to claim 1, characterized in that: The reinforcement component (8) is composed of a reinforcement piece (81), a fixing hole (82), a fixing screw (83) and a fixing nut (84), and one end of the fixing screw (83) is connected to the fixing nut (84) via a thread.

3. The seismic-resistant and high-toughness shear wall structure according to claim 1 is characterized in that: The connection assembly (9) is composed of a fixing plate (91), a fixing column (92), a connecting plate (93), a first connecting piece (94), a first expansion bolt (95), a second connecting piece (96), a sleeve (97), and an expansion screw (98); one end of the fixing column (92) is fixedly connected to the fixing plate (91).

4. The seismic-resistant high-toughness shear wall structure according to claim 3 is characterized in that: The first expansion bolt (95) is connected with an expansion screw (98).

5. The seismic-resistant and high-toughness shear wall structure according to claim 1 is characterized in that: The connecting column (10) is arranged inside the reinforcing base (1), and a first reinforcing rib (11) is arranged on the bottom plate of the reinforcing base (1). A transverse reinforcing hoop (12) and a longitudinal reinforcing hoop (13) are sleeved on the first reinforcing rib (11), and reinforcing tie bars (14) are evenly arranged on the transverse reinforcing hoop (12).

6. The seismic-resistant high-toughness shear wall structure according to claim 5, characterized in that: The first reinforcing rib (11) is sleeved in the sleeve (97), and one end of the first reinforcing rib (11) is fixedly connected to the first longitudinal rib (3).

7. The seismic-resistant and high-toughness shear wall structure according to claim 1 is characterized by: A second longitudinal rib (15) and a third longitudinal rib (16) are arranged on the base of the shear wall (2); one end of the second longitudinal rib (15) is fixedly connected to a second reinforcing rib (17); one end of the third longitudinal rib (16) is fixedly connected to a third reinforcing rib (18); and the second reinforcing rib (17) and the third reinforcing rib (18) are both arranged on the bottom plate of the reinforced base (1).

8. A method for constructing a seismic-resistant and high-toughness shear wall structure, comprising the following steps: Step 1: design and scheme confirmation; Step 2: material preparation; Step 3: construction site layout; Step 4: foundation treatment; Step 5: formwork and steel bar layout; Step 6: concrete pouring; Step 7: subsequent processing; Step 8: acceptance and quality control; It is characterized by: In the above step 1, confirm according to the architectural drawings and construction plan to ensure that all details are accurate and determine the location and size of the shear wall; In the above step 2, the required concrete, steel bars, formwork and other materials are prepared according to the construction plan, and quality inspection is carried out to ensure compliance with standards and requirements; In the above step 3, the construction site is cleaned up to ensure that the site is flat, necessary safety measures are set up, such as fences, warning signs, etc., and construction personnel are trained and given safety education to ensure that they are familiar with the construction process and operating specifications; In the above step 4, according to the design requirements, the foundation is processed, including backfilling, compaction, etc., to ensure the stability of the foundation, and then the concrete foundation is poured according to the design drawings, and the necessary foundation reinforcement is installed; In the above step 5, the steel bars are arranged and the wall formwork is assembled according to the design requirements; In the above step 6, after the formwork and reinforcement are arranged, the concrete is poured, and the concrete is vibrated and compacted at any time during the pouring process to avoid the generation of gaps and bubbles; In the above step 7, after pouring, maintenance is required to maintain a moist environment to prevent wall cracks and shrinkage, and the formwork is removed when the concrete strength reaches the standard; In the above step eight, after the construction is completed, the construction materials and construction process are inspected and accepted by the engineer.

9. The construction method of a seismic-resistant high-toughness shear wall structure according to claim 8, characterized in that: In the step five, the specific operation of steel bar arrangement is to confirm the specific position of the shear wall according to the drawings, and then arrange the steel bars. First, adjust the position of the longitudinal steel bars as required to ensure that the steel bar spacing, row spacing, etc. meet the requirements of the drawings, and use welding and other methods to extend the longitudinal steel bars. Tie the hidden main and door and window lintel steel bars according to the design requirements, and then tie the horizontal steel bars of the wall. The horizontal steel bars should intersect with the longitudinal steel bars vertically and be tied firmly point by point. Then set hooks and pads to fix the position of the steel bars and ensure the thickness of the protective layer; the specific operation of the template assembly is to confirm the template position line and template control line according to the design drawings, and then paste sponge strips on the position line, which mainly play a buffering role to prevent the steel template from damaging the floor. Then fix the template and strengthen the fixation of the template by tension bolts, triangular supports, etc., and then pour five centimeters thick cement mortar to prevent the shear wall from rotting.

10. The construction method of a seismic-resistant high-toughness shear wall structure according to claim 8, characterized in that: In the step six, the specific operation during concrete pouring is to pre-arrange the location of the concrete unloading point and the number of vibrator operators according to the size of the shear wall, transport the concrete from the mixing site to the pouring site, and control it within one hour. The pouring is carried out continuously, and the pouring interval is controlled within two hours. The moving spacing of the vibrator rod is less than fifty centimeters, and the duration of each vibration point is based on the presence of floating slurry on the concrete surface to ensure that the concrete is dense and free of bubbles, and reduce deformation caused by concrete shrinkage and creep. At the same time, regular maintenance is carried out after the pouring is completed to keep the wall surface moist and effectively prevent cracking and stress concentration. During the shear wall construction process, the verticality, flatness, displacement and other parameters of the wall are regularly monitored. If the deformation exceeds the allowable range or there is an abnormality, it can be handled in time to avoid affecting the subsequent construction or the stability of the shear wall.