Assembly type concrete structure viscous damper mounting method
By adopting systematic embedded parts installation and concrete pouring methods in prefabricated concrete structures, combined with hoisting devices, the problems of low installation efficiency and poor quality of traditional viscous dampers are solved, and the seismic performance of prefabricated concrete structures is improved and installation quality.
Patent Information
- Application Number
- CN202411432108.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-10-14
- Publication Date
- 2024-11-26
AI Technical Summary
Prefabricated concrete structures may produce large interlayer displacements under earthquake action, affecting structural safety, and traditional viscous dampers are inefficient in installation efficiency and lack standard procedures, which affects installation quality and seismic resistance.
A method for installing a prefabricated concrete structure viscous damper, including installation of the lower cantilever wall and upper cantilever wall embedded parts and concrete pouring, combining lifting devices and adjustment devices to ensure the rapid installation and correct position fixation of the damper.
It improves the installation efficiency of the damper and the shock resistance of the structure, ensures the effective working and installation quality of the damper, and enhances the stability and shock resistance of the overall structure.
Smart Images

Figure CN119021481A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of building construction, and in particular to a method for installing a viscous damper of an assembled concrete structure. Background Art
[0002] Prefabricated concrete structures are widely used in construction projects due to their good construction efficiency, energy saving and environmental protection, which greatly improves the speed and quality of construction. However, prefabricated concrete structures may produce large inter-layer displacement under earthquakes, thus affecting structural safety.
[0003] In order to improve the seismic performance of buildings, energy dissipation devices can be used to absorb most of the seismic energy. Viscous dampers are widely used in practical engineering. Their working principle is to dissipate energy and reduce the vibration response of the structure through shear deformation of internal viscous materials when the structure undergoes relative motion.
[0004] In prefabricated concrete structures, due to the characteristics of the building itself, multiple viscous dampers are often required to be installed in order to achieve better seismic performance. However, when installing viscous dampers, the traditional method often lacks a standard process during the installation process, which is inefficient and prone to deviations, affecting the final installation quality and seismic performance. Summary of the invention
[0005] In order to improve the installation efficiency and quality of viscous dampers in prefabricated concrete buildings, the present application provides a method for installing viscous dampers in prefabricated concrete structures.
[0006] The present application provides a method for installing a prefabricated concrete structure viscous damper, which adopts the following technical solution: A method for installing a prefabricated concrete structure viscous damper comprises the following steps: S1, installation of lower cantilever wall embedded parts: tie the lower cantilever wall reinforcement and fix the lower cantilever wall embedded parts on the upper surface of the lower cantilever wall reinforcement according to the design requirements; S2, lower cantilever concrete pouring: a lower cantilever wall formwork is set around the lower cantilever wall reinforcement, and concrete is poured into the lower cantilever wall formwork to complete the pouring of the lower cantilever wall; S3, installation of upper cantilever wall embedded parts: install part of the upper cantilever wall formwork, and fix the upper cantilever wall embedded parts in the upper cantilever wall formwork according to the design requirements; S4, upper cantilever concrete pouring: tie the upper cantilever wall steel bars in the upper cantilever wall formwork, close the upper cantilever wall formwork, and pour concrete to complete the pouring of the upper cantilever wall; S5, upper node plate fixing: the upper node plate is welded and fixed to the lower surface of the upper cantilever wall embedded part according to the design drawing requirements; S6, damper installation: connect one end of the damper to the lower node plate through a pin, hoist the damper through a hoisting device, and put the damper on the adjustment device between the upper cantilever and the lower cantilever, adjust the damper to a predetermined height through the adjustment device, and move the damper so that the other end of the damper is inserted into the upper node plate and connected to the upper node plate through a pin; S7, fix the lower node plate: weld and fix the lower node plate to the upper surface of the lower cantilever wall embedded part according to the requirements of the design drawings.
[0007] By adopting the above technical solution, the installation and concrete pouring of the upper cantilever wall embedded parts and the lower cantilever wall embedded parts improve the seismic performance of the structure; the fixing method between the damper and the upper cantilever wall embedded parts and the lower cantilever wall embedded parts can quickly install the damper, while ensuring the stability of the structure and the correct position of the damper. The effect after implementation is to improve the installation efficiency of the damper, while improving the seismic performance of the structure and ensuring the effective operation of the damper.
[0008] Optionally, in step S1, the specific method for fixing the lower cantilever embedded part on the lower cantilever wall steel bar is as follows: S11, inserting the anchor bar below the lower cantilever wall embedded part downward into the lower cantilever wall steel bar; S12, adjusting the height of the lower cantilever wall embedded part up and down according to the requirements of the design drawing, and pre-fixing the lower cantilever wall embedded part by means of fixing parts; S13, after verifying that the plane position, elevation and horizontality of the lower cantilever wall embedded part are qualified, spot welding the anchor bar to the lower cantilever wall steel bar.
[0009] By adopting the above technical scheme, during the installation process of the lower cantilever wall embedded parts, the stability and precise position of the lower cantilever wall embedded parts are ensured by inserting anchor bars and fixing them by spot welding; at the same time, the force transmission between the lower cantilever wall embedded parts and the lower cantilever wall is ensured, thereby ensuring the energy dissipation and earthquake resistance effect.
[0010] Optionally, in step S2, the specific method for pouring the lower cantilever concrete is as follows: S21, setting a lower cantilever wall formwork along the circumference of the lower cantilever wall reinforcement to enclose a pouring space; S22, setting transverse reinforcement rods and longitudinal reinforcement rods on the outside of the lower cantilever wall formwork, and the longitudinal reinforcement rods and transverse reinforcement rods are cross-connected to support the lower cantilever wall formwork; S23, wrapping the lower cantilever wall embedded parts with protective materials; S24, pouring concrete into the lower cantilever wall formwork, and vibrating it with a vibrating rod; S25, after the concrete is fixed, removing the lower cantilever wall formwork, transverse reinforcement rods, longitudinal reinforcement rods and protective materials.
[0011] By adopting the above technical solution, the lower cantilever concrete pouring method ensures the uniformity and density of concrete pouring by setting up formwork, reinforcing rods and vibrating rods; this pouring method improves the strength and durability of the concrete structure and provides solid support for the damper.
[0012] Optionally, in step S3, the specific method for installing the upper cantilever wall embedded parts is as follows: S31, setting an upper cantilever wall formwork under the building beam body, wherein the upper cantilever wall formwork completes the installation of the bottom formwork, two side formworks in the width direction of the upper cantilever wall, and the outer bottom formwork in the length direction of the upper cantilever wall; S32, placing the upper cantilever wall embedded parts in the upper cantilever wall formwork according to the design drawings, and hammering nails into both sides of the upper cantilever wall embedded parts to fix the position of the upper cantilever embedded parts.
[0013] By adopting the above technical solution, the installation method of the upper cantilever wall embedded parts ensures the correct position and stability of the embedded parts by placing and fixing the embedded parts in the template, thereby improving the construction efficiency.
[0014] Optionally, in step S4, the specific method for pouring the upper cantilever concrete is as follows: S41, tying the upper cantilever wall steel bars in the upper cantilever formwork; S42, reviewing the position of the upper cantilever wall embedded parts and adjusting them to a preset position; S43, spot welding the anchor bars above the upper cantilever wall embedded parts to the upper cantilever wall steel bars, and wrapping the upper cantilever wall embedded parts with protective materials; S44, installing the inner bottom formwork in the length direction of the upper cantilever wall, closing the upper cantilever wall formwork, setting transverse reinforcement rods and longitudinal reinforcement rods on the outside of the upper cantilever wall formwork, and pouring concrete; S45, after the concrete is fixed, removing the upper cantilever wall formwork and protective materials.
[0015] By adopting the above technical solution, the upper cantilever concrete pouring method ensures the structural integrity of the upper cantilever wall by checking the position of embedded parts, fixing anchor bars and pouring concrete. This pouring method helps to improve the overall stability and bearing capacity of the structure.
[0016] Optionally, in step S41, when tying the upper cantilever wall reinforcement, the upper end of the upper cantilever wall reinforcement extends upward and is inserted into the building beam reinforcement, and the lower end abuts against the upper cantilever wall embedded part, so that the anchor bar of the upper cantilever wall embedded part is inserted into the upper cantilever wall reinforcement; in step S44, when pouring concrete, the upper cantilever wall body and the building beam body are poured together.
[0017] By adopting the above technical solution, when tying the upper cantilever wall reinforcement, the upper cantilever wall reinforcement is inserted into the building beam reinforcement, and at the same time, the reinforcement on the upper cantilever wall embedded parts is inserted into the upper cantilever wall reinforcement. When pouring concrete, the upper cantilever wall is poured together with the building beam body, thereby enhancing the stability and seismic resistance of the overall structure.
[0018] Optionally, in the step S5, the specific method for installing the upper node plate is as follows: S51, cleaning the surface of the upper cantilever wall embedded parts, and grinding the rust on the surface of the upper cantilever wall embedded parts; S52, marking the axis position of the upper node plate to be installed on the lower surface of the upper cantilever wall embedded parts; S53, placing the upper node plate at the corresponding position, and temporarily fixing the upper node plate by jacking; S54, correcting the plane position and verticality of the upper node plate, and then welding and fixing the upper node plate to the upper cantilever wall embedded parts.
[0019] By adopting the above technical solution, the installation method of the upper node plate ensures the precise position and stability of the upper node plate through cleaning, marking, temporary fixation and welding fixation; this installation method improves the accuracy of the structure and the installation quality of the damper.
[0020] Optionally, in step S54, when the upper node plate is welded and fixed to the upper cantilever wall embedded part, a segmented welding method is adopted.
[0021] By adopting the above technical solution and fixing the upper node plate by segmented welding, the thermal stress and deformation during welding can be reduced, and the welding quality and structural stability can be improved.
[0022] Optionally, the following steps are also included: S8, anti-rust treatment of the damper: clean the pollutants on the surface of the damper, and clean the debris on the surface of the upper node plate and the lower node plate weld. After cleaning, the damper, the upper node plate welding point and the lower node plate welding point are subjected to anti-rust treatment.
[0023] By adopting the above technical solution, the damper anti-rust treatment step protects the damper and welding parts from corrosion by cleaning and coating anti-rust paint, thereby extending the service life of the structure.
[0024] Optionally, in step S8, the specific method for performing anti-rust treatment on the damper, the upper node plate welding point and the lower node plate welding point is: S1, applying anti-rust paint on the damaged positions of the damper, the upper node plate welding point and the lower node plate welding point; S2, after the anti-rust paint is dry, continue to spray the topcoat.
[0025] By adopting the above technical solution, the anti-rust treatment on the damper, upper node plate weld and lower node plate weld is enhanced by re-applying anti-rust paint and spraying topcoat to enhance the corrosion resistance of these key parts and ensure long-term performance and appearance.
[0026] In summary, the present application includes at least one of the following beneficial effects: 1. Through a reasonable installation process and the transportation and positioning tools for the dampers, the installation efficiency of the dampers in prefabricated buildings is improved; 2. At the same time, through precise installation of embedded parts and concrete pouring, the accuracy of the installation process is improved, the effective operation of the damper is ensured, the installation quality of the damper is guaranteed, and the seismic performance of the prefabricated concrete structure is improved. BRIEF DESCRIPTION OF THE DRAWINGS
[0027] Figure 1 This is a schematic diagram of the structure after the damper is installed; Figure 2 Schematic diagram of the internal structure of the upper cantilever wall and the lower cantilever wall; Figure 3 It is a schematic diagram of the structure of the lifting device; Figure 4 is a schematic diagram of the structure of the regulating device; Explanation of the reference numerals in the accompanying drawings: 1. lower cantilever wall; 11. embedded parts of lower cantilever wall; 12. steel bars of lower cantilever wall; 13. lower node plate; 2. upper cantilever wall; 21. embedded parts of upper cantilever wall; 22. steel bars of upper cantilever wall; 23. upper node plate; 3. damper; 4. building beam; 41. steel bars of building beam; 5. lifting device; 51. supporting frame; 52. pulley; 53. lifting ring; 54. manual lifting chain; 55. lifting rope; 6. adjusting device; 61. supporting seat; 62. fixing member; 63. positioning seat; 64. driving member. DETAILED DESCRIPTION
[0028] The following is combined with Figure 1-4 This application is described in further detail.
[0029] The present application embodiment discloses a method for installing a prefabricated concrete structure viscous damper. Figure 1 and Figure 2 The installation method includes the following steps: S1, installation of the lower cantilever wall embedded part 11: tie the lower cantilever wall steel bar 12 at the corresponding position in the building according to the design drawings, and fix the lower cantilever wall embedded part 11 to the upper surface of the lower cantilever wall steel bar 12. Among them, the specific method of fixing the cantilever wall embedded part is as follows: S11, select the corresponding model of the lower cantilever wall embedded part 11 according to the design drawings, first insert the anchor bar specified on the lower surface of the lower cantilever wall embedded part 11 downward into the lower cantilever wall steel bar 12; S12, first adjust the plane position of the lower cantilever wall embedded part according to the requirements of the design drawings, then adjust the elevation position of the top surface of the lower cantilever embedded part, and pre-fix the lower cantilever wall embedded part 11 through the fixing part 62; Among them, the fixing part 62 can be selected from iron wire, cable tie, etc.; S13, after verifying that the plane position, elevation, and horizontality of the lower cantilever wall embedded part 11 are qualified, the anchor bar and the lower cantilever wall steel bar 12 are spot welded and fixed. When welding, it is necessary to pay attention to multi-point welding and avoid moving the position of the lower cantilever embedded part.
[0030] S2, pouring lower cantilever concrete: S21, setting the lower cantilever wall formwork along the circumference of the lower cantilever wall reinforcement 12 to enclose a pouring space. It should be noted that when setting the lower cantilever wall formwork, it is necessary to check whether the plane position and elevation of the lower cantilever wall embedded parts 11 are accurate, and then close the lateral formwork of the lower cantilever wall 1 after meeting the design requirements; the lower cantilever wall formwork material can be a rod formwork or a wooden formwork; S22, transverse reinforcement rods and longitudinal reinforcement rods are set on the outside of the lower cantilever wall formwork, and the longitudinal reinforcement rods and transverse reinforcement rods are cross-connected to support the lower cantilever wall formwork; S23, before pouring the lower cantilever wall concrete, the lower cantilever wall embedded parts 11 must be wrapped with protective materials, wherein the protective materials can be plastic films; S24, pour concrete into the lower cantilever wall formwork, and vibrate with a vibrator; when vibrating, it is necessary to avoid displacement of the lower cantilever wall embedded plate; S25, after the concrete is fixed, remove the lower cantilever wall formwork, transverse reinforcement rods, longitudinal reinforcement rods and protective materials.
[0031] S3, installation of the upper cantilever wall embedded parts 21: S31, first set the upper cantilever wall formwork. It should be noted that the upper cantilever wall formwork needs to be fixed below the building beam 4, so as to effectively transmit the energy dissipation effect of the damper 3 on the building; the upper cantilever wall formwork first completes the installation of the bottom formwork at the lower end, the two side forms in the width direction of the upper cantilever wall, and the outer bottom formwork in the length direction of the upper cantilever wall; after the formwork is installed, it is necessary to check the plane position of the formwork, and the plane positions of the upper cantilever wall 2 and the lower cantilever wall 1 should be aligned. At the same time, when setting the upper cantilever wall formwork, it is necessary to pay attention to connecting the upper end of the upper cantilever wall formwork with the formwork cast by the building beam 4.
[0032] S32, after the upper cantilever wall formwork is installed, the placement position of the upper cantilever wall embedded part 21 is determined according to the design drawing, and then the edge line of the upper cantilever wall embedded part 21 is drawn with a red and blue pencil or an ink fountain, and the upper cantilever wall embedded part 21 is placed at the position corresponding to the edge line. After re-measurement to determine that the position and size are consistent with the design drawing, nails are driven into both sides of the upper cantilever wall embedded part 21 to fix the position of the embedded part, so as to avoid the position displacement of the embedded part during the steel bar binding and concrete pouring.
[0033] S4, pouring of upper cantilever concrete: S41, tying the upper cantilever wall steel bars 22 in the upper cantilever formwork. When tying, the upper end of the upper cantilever wall steel bars 22 extends upward and is inserted into the building beam steel bars 41, and the lower end abuts against the upper cantilever wall embedded part 21, and the anchor bars on the upper cantilever wall embedded part 21 are inserted into the upper cantilever wall steel bars 22; S42, checking and verifying the position of the upper cantilever wall embedded part 21 and the fit with the bottom formwork. If the upper cantilever wall embedded part 21 is warped or the formwork is warped and deformed, it should be corrected, adjusted to the preset position, and re-fixed firmly; S43, the upper part of the upper cantilever wall embedded part 21 is The anchor bars are spot welded to the upper cantilever wall reinforcement bars 22, and at the same time, the upper ends of the upper cantilever wall reinforcement bars 22 are also spot welded to the building beam reinforcement bars 41; then, the upper cantilever wall embedded parts 21 are wrapped with protective materials; S44, the inner bottom formwork in the length direction of the upper cantilever wall 2 is installed, the upper cantilever wall formwork is closed, and transverse reinforcement rods and longitudinal reinforcement rods are arranged on the outer side of the upper cantilever wall formwork, and finally concrete is poured; it should be noted that the upper cantilever wall 2 should be poured together with the upper building beam body 4 to enhance the stability and seismic performance of the overall structure; S45, after the concrete is fixed, the upper cantilever wall formwork and protective materials are removed.
[0034] S5, fix the upper node plate 23: S51, first clean the mortar, garbage, etc. on the surface of the upper cantilever wall embedded part 21, and grind the rust on the surface of the upper cantilever wall embedded part 21; S52, according to the requirements of the design drawings, mark the axis position of the upper node plate 23 to be installed on the lower surface of the upper cantilever wall embedded part 21; S53, place the upper node plate 23 at the corresponding position, and temporarily fix the upper node plate 23 by jacking; S54, correct the plane position and verticality of the upper node plate 23, and then weld the upper node plate 23 to the upper cantilever wall embedded part 21. It should be noted that when welding the upper node plate 23, it is preferably a segmented welding method to reduce thermal stress and deformation during welding and improve welding quality and structural stability.
[0035] S6, installation of damper 3: S61, connect one end of damper 3 to the lower node plate 13 through a pin shaft, hoist damper 3 through hoisting device 5, and place damper 3 on the adjusting device 6 between the upper cantilever and the lower cantilever; S62, adjust damper 3 up and down to a predetermined height through the adjusting device 6, and move damper 3 in the horizontal direction so that the other end of damper 3 is inserted into the upper node plate 23 and connected to the upper node plate 23 through a pin shaft.
[0036] Reference Figure 3In step S61, the hoisting device 5 includes a support frame 51, a pulley 52, a lifting ring 53, a manual lifting chain 54 and a lifting rope 55. Specifically, the main structure of the support frame 51 is composed of two vertically arranged longitudinal steel pipes and two transverse steel pipes welded and fixed between the two longitudinal steel pipes; a first oblique steel pipe is fixed obliquely downward on the side wall of the longitudinal steel pipe, and a stable steel pipe is connected between the first oblique steel pipe and the corresponding longitudinal steel pipe; and a second oblique steel pipe is also fixed at both ends of the transverse steel pipe at the upper end between the longitudinal steel pipes.
[0037] The pulleys 52 are respectively arranged at the lower ends of the two longitudinal steel pipes and the two first oblique steel pipes, so as to facilitate the movement of the support frame 51. The pulleys 52 are provided with foot brakes, so as to facilitate the fixing of the support frame 51. The lifting ring 53 is fixedly installed in the middle position of the horizontal steel pipe located above. The upper end of the manual lifting chain 54 has a hook, which is hooked on the lifting ring 53; the two ends of the lifting rope 55 are respectively connected to the metal rings at the two ends of the damper 3. The manual lifting chain 54 is provided with a chain, and the two ends of the chain are linked to each other. One end of the chain is hooked to the middle position of the lifting rope 55, and the other end is suspended in the air, so that the damper 3 can be driven to move up and down by pulling the lifting chain.
[0038] The above hoisting device 5 is mainly welded with steel pipe materials commonly found on construction sites, and is easy to install. In other embodiments, the damper 3 may also be hoisted using structures such as electric hoists.
[0039] Reference Figure 4 In steps S61 and S62, the adjusting device 6 includes a support seat 61, a fixing member 62 for fixing the support seat 61 to the lower cantilever wall 1, a positioning seat 63 provided on the support seat 61 that moves up and down, and a driving member 64 for driving the support seat 61 to move up and down. Among them, the support seat 61 is composed of a transverse plate and a longitudinal plate, the longitudinal plate is fixed to the lower surface of the horizontal plate, and is respectively provided on both sides of the horizontal plate; the fixing member 62 is a fixing bolt threadedly connected to the longitudinal plate. When in use, the transverse plate abuts against the upper surface of the lower cantilever wall 1, and the longitudinal plates are respectively located on both sides of the lower cantilever wall 1. By rotating the fixing bolts, the ends of the fixing bolts on both sides are respectively pressed against the side walls of the lower cantilever wall 1, and the support seat 61 can be fixed to the lower cantilever wall 1.
[0040] The positioning seat 63 is a rectangular seat body, and the driving member 64 is preferably a cylinder. The cylinder is fixed on the support seat 61 and is respectively arranged on both sides of the support seat 61. The telescopic axis of the cylinder passes through the support seat 61 upward and is fixedly connected to the lower surface of the positioning seat 63. A positioning groove is provided in the middle of the upper surface of the positioning seat 63. The positioning groove is an arc groove, which can be used to place the positioning damper 3. When in use, the damper 3 is placed in the positioning groove on the positioning seat 63. At this time, the damper 3 is located exactly in the middle position of the lower cantilever wall 1 along the width direction; then the two cylinders are started synchronously to drive the damper 3 to slowly move upward to an appropriate height, and then the damper 3 is moved along the extension direction of the positioning groove so that one end of the damper 3 is aligned with the opening position on the upper node plate 23, and the upper node plate 23 and the damper 3 are connected by a pin shaft.
[0041] S7, fix the lower node plate 13: S71, clean the surface of the lower cantilever wall embedded part 11, and adjust the position of the lower node plate 13 according to the design drawing requirements to ensure that it meets the requirements of the design drawings; S72, comprehensively check the specifications, models, positions, horizontality, verticality, etc. of the node plate and damper 3, and make timely adjustments if there are deviations; S73, weld and fix the lower node plate 13 to the upper cantilever wall embedded part 21. It should be noted that when welding the lower node plate 13, it is also preferred to use a segmented welding method. After the welding of the lower node plate 13 is completed, first start the cylinder and move the positioning seat 63 downward so that the positioning seat 63 is separated from the damper 3, and then move the adjustment device 6 along the direction of the upper node plate 23 to remove it.
[0042] S8, anti-rust treatment of damper 3: S81, clean the pollutants on the surface of damper 3, and clean the debris on the surface of the weld of upper node plate 23 and lower contact plate; S82, apply anti-rust paint on the damaged position of the surface of damper 3 and the welding place of upper node plate 23 and lower node plate 13; S83, after the anti-rust paint is dry, continue to spray the topcoat.
[0043] The implementation principle of the method for installing a viscous damper for a prefabricated concrete structure in the embodiment of the present application is as follows: by reasonably setting and fixing the embedded parts in various ways, combined with precise casting and positioning, the installation process of the prefabricated concrete structure is optimized, the installation steps of the viscous damper 3 are simplified, and the installation efficiency is improved; at the same time, combined with the standard inspection process, the stability and safety of the overall structure are also improved. During the installation process, by using the lifting device 5 and the adjusting device 6 in combination, the labor intensity can be reduced and the installation efficiency can be improved. At the same time, the adjusting device 6 can also assist in accurately positioning the position of the damper 3, ensuring that the damper 3 is installed horizontally and improving the installation quality.
[0044] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, any equivalent changes made according to the structure, shape, and principle of the present application should be included in the protection scope of the present application.
Claims
1. A method for installing a viscous damper of an assembled concrete structure, characterized in that: The following steps are involved: S1, installation of the lower cantilever wall embedded part (11): tying the lower cantilever wall reinforcement (12), and fixing the lower cantilever wall embedded part (11) to the upper surface of the lower cantilever wall reinforcement (12) according to design requirements; S2, pouring lower cantilever concrete: setting a lower cantilever wall formwork around the lower cantilever wall reinforcement (12), pouring concrete into the lower cantilever wall formwork, and completing the pouring of the lower cantilever wall (1); S3, installation of the upper cantilever wall embedded part (21): installing a portion of the upper cantilever wall formwork, and fixing the upper cantilever wall embedded part (21) in the upper cantilever wall formwork according to design requirements; S4, pouring upper cantilever concrete: tying the upper cantilever wall steel bars (22) in the upper cantilever wall formwork, closing the upper cantilever wall formwork, and pouring concrete to complete the pouring of the upper cantilever wall (2); S5, fixing the upper node plate (23): welding and fixing the upper node plate (23) to the lower surface of the upper cantilever wall embedded part (21) according to the design drawing requirements; S6, installing the damper (3): connecting one end of the damper (3) to the lower node plate (13) via a pin, hoisting the damper (3) via a hoisting device (5), and placing the damper (3) on an adjusting device (6) between the upper cantilever wall (2) and the lower cantilever wall (1), adjusting the damper (3) to a predetermined height via the adjusting device (6), and moving the damper (3) so that the other end of the damper (3) is inserted into the upper node plate (23) and connected to the upper node plate (23) via a pin; S7, fixing the lower node plate (13): welding and fixing the lower node plate (13) to the upper surface of the lower cantilever wall embedded part (11) according to the requirements of the design drawing.
2. The method for installing a prefabricated concrete structure viscous damper according to claim 1, characterized in that: In the step S1, the specific method for fixing the lower cantilever wall embedded part (11) to the lower cantilever wall steel bar (12) is as follows: S11, inserting the anchor bar below the lower cantilever wall embedded part (11) downward into the lower cantilever wall steel bar (12); S12, adjusting the height of the lower cantilever wall embedded part (11) up and down according to the requirements of the design drawing, and pre-fixing the lower cantilever wall embedded part (11) by means of the fixing part (62); S13, after checking that the plane position, elevation and horizontality of the lower cantilever wall embedded part (11) are qualified, spot welding the anchor bar to the lower cantilever wall steel bar (12) to fix it.
3. The method for installing a prefabricated concrete structure viscous damper according to claim 1, characterized in that: In step S2, the specific method for pouring the lower cantilever concrete is as follows: S21, arranging a lower cantilever wall formwork along the circumference of the lower cantilever wall reinforcement (12) to enclose a pouring space; S22, arranging a transverse reinforcement rod and a longitudinal reinforcement rod on the outer side of the lower cantilever wall formwork, wherein the longitudinal reinforcement rod and the transverse reinforcement rod are cross-connected to support the lower cantilever wall formwork; S23, wrapping the lower cantilever wall embedded part (11) with protective material; S24, pouring concrete into the lower cantilever wall formwork and vibrating it with a vibrating rod; S25, after the concrete is fixed, removing the lower cantilever wall formwork, the transverse reinforcement rod, the longitudinal reinforcement rod and the protective material.
4. The method for installing a prefabricated concrete structure viscous damper according to claim 3 is characterized in that: In the step S3, the specific method for installing the upper cantilever wall embedded part (21) is as follows: S31, setting an upper cantilever wall formwork below the building beam body (4), wherein the upper cantilever wall formwork completes the installation of a bottom formwork, two side forms in the width direction of the upper cantilever wall, and an outer bottom formwork in the length direction of the upper cantilever wall; S32, placing the upper cantilever wall embedded part (21) in the upper cantilever wall formwork according to the design drawing, and driving nails into the two sides of the upper cantilever wall embedded part (21) to fix the position of the upper cantilever embedded part.
5. The method for installing a prefabricated concrete structure viscous damper according to claim 4, characterized in that: In the step S4, the specific method for pouring the upper cantilever concrete is as follows: S41, tying the upper cantilever wall steel bars (22) in the upper cantilever formwork; S42, checking the position of the upper cantilever wall embedded part (21) and adjusting it to a preset position; S43, spot welding the anchor bars above the upper cantilever wall embedded part (21) to the upper cantilever wall steel bars (22), and wrapping the upper cantilever wall embedded part (21) with protective material; S44, installing the inner bottom formwork in the length direction of the upper cantilever wall body (2), closing the upper cantilever wall formwork, arranging transverse reinforcement rods and longitudinal reinforcement rods on the outer side of the upper cantilever wall formwork, and pouring concrete; S45, after the concrete is fixed, removing the upper cantilever wall formwork and the protective material.
6. The method for installing a prefabricated concrete structure viscous damper according to claim 5, characterized in that: In the step S41, when the upper cantilever wall reinforcement (22) is tied, the upper end of the upper cantilever wall reinforcement (22) extends upward and is inserted into the building beam reinforcement (41), and the lower end abuts against the upper cantilever wall embedded part (21), so that the anchor bar of the upper cantilever wall embedded part (21) is inserted into the upper cantilever wall reinforcement (22); in the step S44, when pouring concrete, the upper cantilever wall body (2) is poured together with the building beam body (4).
7. The method for installing a prefabricated concrete structure viscous damper according to claim 1, characterized in that: In the step S5, the specific method for installing the upper node plate (23) is as follows: S51, cleaning the surface of the upper cantilever wall embedded component (21), and grinding the rust on the surface of the upper cantilever wall embedded component (21); S52, marking the axis position of the upper node plate (23) to be installed on the lower surface of the upper cantilever wall embedded component (21); S53, placing the upper node plate (23) at a corresponding position, and temporarily fixing the upper node plate (23) by jacking; S54, correcting the plane position and verticality of the upper node plate (23), and then welding and fixing the upper node plate (23) to the upper cantilever wall embedded component (21).
8. The method for installing a prefabricated concrete structure viscous damper according to claim 7, characterized in that: In the step S54, when the upper node plate (23) is welded and fixed to the upper cantilever wall embedded part (21), a segmented welding method is adopted.
9. The method for installing a prefabricated concrete structure viscous damper according to claim 1, characterized in that: The following steps are also included: S8, rust prevention treatment of the damper (3): clean the pollutants on the surface of the damper (3), and clean the debris on the surface of the weld of the upper node plate (23) and the lower node plate (13). After the cleaning is completed, the damper (3), the welding part of the upper node plate (23) and the welding part of the lower node plate (13) are subjected to rust prevention treatment.
10. The method for installing a prefabricated concrete structure viscous damper according to claim 9, characterized in that: In step S8, the specific method of performing anti-rust treatment on the damper (3), the upper node plate (23) welding point and the lower node plate (13) welding point is: first, anti-rust paint is applied to the damaged position of the damper (3) and the upper node plate (23) welding point and the lower node plate (13) welding point; and after the anti-rust paint is dried, the topcoat is sprayed.
Citation Information
Cited By
Viscous damping device based on displacement amplification
CN119531517A
VFD viscous damper installation construction equipment
CN120026769A
Wall type damper cantilever wall construction device and construction method
CN121066362A