Construction method for reinforcing and transforming super-large-span dragging beam and dismounting column

Through bottom-up reinforcement and real-time monitoring technology, combined with the scaffolding and slow bonding prestressed steel strands, the problems of structural deformation control difficulties and insufficient durability in traditional methods are solved, and the column reinforcement transformation of ultra-large span drag beams is realized Safety, reliability and durability.

CN119021502APending Publication Date: 2024-11-26WUHAN KEZHENG ENG TECH CO LTD
View PDF 0 Cites 2 Cited by

Patent Information

Application Number
CN202411177120.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-26
Publication Date
2024-11-26

AI Technical Summary

Technical Problem

In the renovation of building drag beams and columns, it is difficult for traditional methods to accurately control the structural displacement, settlement and stress during column load unloading, resulting in unstable structural deformation and affecting the durability and safety of the building after transformation, especially in pursuit of It is more prominent when it is overspan.

Method used

The bottom-up reinforcement method is adopted to monitor and control structural deformation in real time through displacement and stress and strain monitoring marks, and set up a scaffolding support system to transfer the load to the foundation bearing, and use slow bonding prestressed steel strands and fully automatic loading instruments. Accurate control of the removal process to ensure structural integrity and durability.

Benefits of technology

It effectively reduces damage to the original structure, realizes precise control during column load unloading, ensures the safety, reliability and durability of the modified building structure, and avoids cracking problems caused by accumulation of vertical deformation.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119021502A_ABST
    Figure CN119021502A_ABST
Patent Text Reader

Abstract

The invention relates to a construction method for reinforcement and transformation through super-large-span beam dragging and column dismantling. The construction method comprises the following steps that firstly, reserved columns and columns to be dismantled of a building to be transformed are determined; 2, determining a reinforcement construction monitoring scheme, arranging displacement and stress-strain monitoring identifiers, and collecting initial values; and 3, the size of the lower bearing platform of the reserved column is increased and reinforced, and a plurality of anchor rod static pressure piles are supplemented for foundation reinforcement to form a foundation bearing platform. According to the method, reinforcement treatment is conducted from bottom to top, the design is economical and reasonable, safety and reliability are achieved, real-time monitoring is achieved through displacement, stress and strain monitoring marks, damage to an original structure is reduced in the transformation process, and displacement, sedimentation, stress and the like of the original structure are accurately controlled in the column load unloading process; particularly, when the column needs to be completely disconnected, the stress of the supporting structure and the deformation of the beam are accurately tested and controlled.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of building drag beam removal and column reinforcement and reconstruction, and in particular to a construction method for super-large span drag beam removal and column reinforcement and reconstruction. Background Art

[0002] At present, my country is transitioning from a period of rapid development of real estate to a period of stability, and is in a period of urban renewal and development of old city reconstruction. How to make full use of existing buildings, avoid or reduce large-scale demolition and construction through reasonable reconstruction technology, and let existing buildings play a new vitality. The change of the use function of some buildings, such as a building changed from general commercial use to a banquet hall, conference room, etc., requires the pursuit of ultra-large span space. The owner needs to reinforce and renovate the existing building and remove a certain number of columns or walls to achieve the purpose of ultra-large span space.

[0003] Traditional column extraction renovation projects generally remove a single column or a span, pursuing simple minor modifications, and generally do not require high reinforcement and renovation technology, such as using only partial steel pipe supports, I-beams plus jacks, simple prestressed steel beams, etc. These methods may be applicable to simple local minor modifications, but for ultra-large span renovations or large-volume building renovations of existing buildings, the following problems still need to be solved: First, how to reduce damage to the original structure during the renovation process. During the column load unloading process, the displacement, settlement, stress, etc. of the original structure will be difficult to accurately control, especially when the column needs to be completely disconnected, the force of the supporting structure and the deformation of the beam cannot be accurately tested and to be controlled; second, in the method of removing columns and renovating the original building structure by adopting the traditional single additional structure method, in the process of transferring the upper load of the column to be removed to the temporary supporting structure and then transferring it from the temporary supporting structure to the additional structure, the undemolished part of the original building structure adjacent to the upper part of the additional structure will inevitably produce accumulated vertical deformation. If the accumulation of such vertical deformation exceeds a certain limit, it will often cause cracks in the undemolished part of the original building structure on the upper part of the additional structure, thereby affecting the use function and safety of the undemolished part of the original building structure on the upper part of the additional structure. In addition, the durability of the structure after the renovation cannot be guaranteed.

[0004] In order to solve the above problems, the present invention proposes a construction method for the reinforcement and reconstruction of a super-large span drag beam by removing columns. Summary of the invention

[0005] The purpose of the present invention is to overcome the deficiencies of the prior art, meet actual needs, and provide a construction method for the reinforcement and reconstruction of an ultra-large span drag beam by removing columns to solve the above-mentioned technical problems.

[0006] In order to achieve the purpose of the present invention, the technical solution adopted by the present invention is:

[0007] A construction method for the reinforcement and reconstruction of a super-large span drag beam by removing columns comprises the following steps:

[0008] Step 1, determine the columns to be retained and the columns to be removed of the building to be renovated;

[0009] Step 2: Determine the reinforcement construction monitoring plan, arrange displacement, stress and strain monitoring signs, and collect initial values;

[0010] Step 3, enlarging and reinforcing the size of the lower cap of the retained column, and adding a number of anchor static pressure piles to reinforce the foundation to form a foundation cap;

[0011] Step 4: The retained columns are reinforced by increasing their cross-sections, and a full-height scaffolding support system is set up along the reinforced area to transfer the load of the columns to be removed from the top to the foundation pedestal through the full-height scaffolding support system;

[0012] Step 5, bury the slow-bonding prestressed steel strands in the main beam, lay out the reinforced steel template in the cross section, and pour the main beam concrete;

[0013] Step 6: drill holes on the top of the column to be removed to form holes, install jacks and apply pressure accordingly;

[0014] Step 7: For the columns to be removed, the concrete around the holes is chiseled out one by one and the steel bars are cut off. At this time, the columns to be removed are completely disconnected from the main beam, and the upper load is transferred to the lower column and the foundation pedestal through the jack;

[0015] Step 8, tensioning the slow-bonding prestressed steel strands, and anchoring the slow-bonding prestressed steel strands after reaching the designed locking value;

[0016] Step 9, remove the jacks, remove all remaining columns to be removed, reinforce the secondary beams, plates and columns with steel wrapping and steel bonding, and after they are stable, remove the full-floor scaffolding support system.

[0017] Furthermore, the building to be renovated includes a plurality of original structural columns and main beams arranged on top of the original structural columns, and the columns to be removed are parts of the original structural columns.

[0018] Furthermore, the locations for arranging displacement and stress-strain monitoring marks in step 2 include: main beams, original structural columns and top plates.

[0019] Furthermore, the installation of the jack in step 6 includes: chiseling the upper and lower parts of the hole flat and laying a 10 mm steel plate; and setting I-beam supports around the jack to prevent sudden failure of the jack's hydraulic pressure.

[0020] Furthermore, the tensioning of the slow-bonding prestressed steel strands described in step 8 is divided into two or three tensioning operations.

[0021] Furthermore, the full-floor scaffolding support system comprises a scaffolding body, a scaffolding top support is arranged on the top of the scaffolding body, and wooden planks are arranged inside the scaffolding top support for support.

[0022] Furthermore, the jack is connected to the full-automatic real-time loading instrument through a full-automatic real-time loading instrument control line.

[0023] Beneficial effects:

[0024] A. In the present invention, the reinforcement treatment is carried out from bottom to top, the design is economical, reasonable, safe and reliable, and real-time monitoring is achieved by using displacement and stress-strain monitoring marks to reduce damage to the original structure during the transformation process. During the column load unloading process, the displacement, settlement, stress, etc. of the original structure are accurately controlled. In particular, when the column needs to be completely disconnected, the force of the supporting structure and the deformation of the beam are accurately tested and controlled.

[0025] B. In the present invention, during the reinforcement process, the jack is controlled in real time by a fully automatic loader to reduce the impact of column removal on the original structure. Prestress is applied to the beam by using slow-bonding prestressed steel strands, and the impact of the reinforcement construction on the undemolished part of the original building structure is strictly controlled, thus completely solving the problem of the durability of the building structure after renovation and reinforcement cannot be guaranteed. BRIEF DESCRIPTION OF THE DRAWINGS

[0026] Figure 1 It is a schematic diagram of the structure of the construction method flow chart of the present invention;

[0027] Figure 2 It is a schematic diagram of the plan structure of the construction method of the present invention;

[0028] Figure 3 It is a schematic diagram of the cross-sectional structure of the full-floor scaffolding support system of the present invention;

[0029] Figure 4 It is a structural schematic diagram of the top support of the scaffolding of the present invention;

[0030] Figure 5 It is a schematic diagram of the layout structure of the slow-bonding prestressed tendons of the present invention;

[0031] Figure 6 It is a structural schematic diagram of the jack of the present invention.

[0032] The reference numerals are as follows:

[0033] 1. Displacement, stress and strain monitoring signs; 2. Lower pedestal; 3. Anchor static pressure piles; 4. Foundation pedestal; 5. Full-floor scaffolding support system; 501. Scaffolding body; 502. Scaffolding top support; 503. Wooden planks; 6. Main beam; 7. Slow-bonding prestressed steel strand; 8. Jack; 9. Original structural column; 10. Fully automatic real-time loading instrument; 11. I-beam; 12. Fully automatic real-time loading instrument control line; 13, 14, 15, 16, 17, 18, 19, 20. Columns to be removed; 21, 22, 23, 24, 25, 26. Retained columns; 27. Columns; 28. Beams. DETAILED DESCRIPTION

[0034] The present invention discloses a construction method for the removal and reinforcement of a super-large span drag beam. Figure 1-6 The present invention is further described in the following embodiments: the building to be renovated comprises a plurality of original structural columns 9 and a main beam 6 arranged on the top of the original structural columns 9, and the steps are as follows:

[0035] Step 1: Determine the columns to be retained and removed in the building to be renovated. Figure 2 As shown, it is determined that two main beams 6 and columns 13, 14, 15, 16, 17, 18, 19, 20 to be removed are to be dismantled, and the original span of 6 meters is expanded to 18 meters. The relevant software is used for modeling and calculation to determine the final construction plan. The relevant software here is Yingjianke software or PKPM software.

[0036] Step 2, determine the reinforcement construction monitoring plan, arrange displacement, stress and strain monitoring marks 1, and collect initial values. The arrangement positions are important parts such as the main beam 6, the original structural column 9 and the top plate. By using the displacement, stress and strain monitoring marks 1, real-time monitoring is achieved to reduce the damage to the original structure during the transformation process. During the column load unloading process, the displacement, settlement, stress, etc. of the original structure are accurately controlled. In particular, when it is necessary to completely disconnect the columns 13, 14, 15, 16, 17, 18, 19, and 20 to be removed, the force of the supporting structure and the deformation of the beam are accurately tested and controlled.

[0037] Step 3, enlarge the size of the lower support 2 of the six columns 21, 22, 23, 24, 25, and 26, such as Figure 2 As shown, the foundation of the lower pedestal 2 is expanded to form a foundation pedestal 4, and a number of anchor static pressure piles 3 are added to reinforce the foundation. The reinforcement process is carried out from bottom to top, and the design is economical, reasonable, safe and reliable.

[0038] Step 4: After the foundation reinforcement is completed and the foundation acceptance is passed, Figure 2 and Figure 3As shown in the figure, a full-height scaffolding support system 5 is erected along the reinforced area, and the loads of the columns 13, 14, 15, 16, 17, 18, 19, 20 to be removed are transferred from the top to the foundation pedestal 4 through the full-height scaffolding support system 5, and the full-height scaffolding support system 5 also serves as a formwork support system. The full-height scaffolding support system 5 includes a scaffolding body 501, and a scaffolding top support 502 is arranged on the top of the scaffolding body 501. Wooden squares 503 are arranged in the scaffolding top support 502 for support. At the same time, the cross-sectional areas of the six columns 21, 22, 23, 24, 25, 26 that have not been removed are enlarged, and the column 27 is formed after the enlargement.

[0039] Step 5, bury the slow-bonding prestressed steel strands 7 in the two main beams 6, lay out the cross-section reinforcement steel template, and pour the beam concrete, such as Figure 2 As shown, beam 28 is formed after reinforcement.

[0040] Step 6, such as Figure 4 Holes are drilled on the tops of columns 13, 14, 15, 16, 17, 18, 19, and 20 to be removed. The size of the holes is determined to ensure that the jacks 8 selected for the design corresponding loads can be installed. The jacks 8 are installed, the upper and lower parts of the holes are chiseled flat, and 10 mm steel plates are laid. I-beams 11 are set around the jacks 8 to prevent sudden hydraulic failure of the jacks 8. The jacks 8 are connected to the full-automatic real-time loader 10 through the full-automatic real-time loading instrument control line 12. The full-automatic real-time loader 10 quantitatively controls the load according to the design requirements. The displacement, stress and strain monitoring mark 1 is convenient for the monitoring team to monitor in real time and strictly control the deformation of the beam body. During the reinforcement process, the full-automatic real-time loader 10 controls the jacks 8 in real time to reduce the impact of column removal on the original structure.

[0041] Step 7, when the age of beam 28 is reached, the concrete around the holes of columns 13, 14, 15, 16, 17, 18, 19, 20 to be removed is chiseled out one by one and the steel bars are cut off, and the edge concrete is chiseled out cleanly. At this time, columns 13, 14, 15, 16, 17, 18, 19, 20 to be removed are completely disconnected from the main beam 6, and the upper load is transferred to the lower column and the foundation pedestal 4 through the jack 8.

[0042] Step 8, tensioning the slow-bonding prestressed steel strands 7, and tensioning is performed in two to three times, and the slow-bonding prestressed steel strands 7 are locked when the designed locking value is reached. The tensioning process monitoring team monitors the displacement and stress-strain monitoring mark 1 in real time to strictly control the deformation of the beam body. By using the slow-bonding prestressed steel strands 7 to apply prestress to the beam, the influence of the reinforcement construction on the undemolished part of the original building structure is strictly controlled, and the problem that the durability of the building structure cannot be guaranteed after the reconstruction and reinforcement is completely solved.

[0043] Step 9, successively dismantle the jack 8, the fully automatic real-time loader 10, and the I-beam 11, and completely dismantle the remaining columns of the columns to be dismantled 13, 14, 15, 16, 17, 18, 19, 20, and reinforce some secondary beams, plates, and columns with steel wrapping and adhesive reinforcement. The monitoring team monitors the displacement in real time, and the stress-strain monitoring mark 1 continues to monitor the deformation of the beams and columns to ensure the reinforcement effect. After the deformation stabilizes, dismantle the full-floor scaffolding support system 5, and the entire reinforcement construction is completed.

[0044] The embodiments of the present invention disclose preferred embodiments, but are not limited thereto. A person skilled in the art can easily understand the spirit of the present invention based on the above embodiments and make different extensions and changes. However, as long as they do not deviate from the spirit of the present invention, they are all within the protection scope of the present invention.

Claims

1. A construction method for the reinforcement and reconstruction of a super-large span drag beam by removing columns, characterized in that: The following steps are involved: Step 1, determine the columns to be retained and the columns to be removed of the building to be renovated; Step 2: determine the reinforcement construction monitoring plan, arrange displacement, stress and strain monitoring signs (1), and collect initial values; Step 3, increasing and reinforcing the size of the lower cap (2) of the retained column, and adding a number of anchor static pressure piles (3) to reinforce the foundation to form a foundation cap (4); Step 4, the retained column is reinforced by increasing the cross section, and a full-height scaffolding support system (5) is set up along the reinforced area, and the load of the column to be removed is transferred from the top to the foundation pedestal (4) through the full-height scaffolding support system (5); Step 5, burying the slow-bonding prestressed steel strands (7) in the main beam (6), laying out the reinforced steel template in the cross section, and pouring the main beam concrete; Step 6, drilling holes on the top of the column to be removed to form holes, installing jacks (8) and applying pressure accordingly; Step 7, the concrete around the holes of the columns to be removed is chiseled out one by one and the steel bars are cut off. At this time, the columns to be removed are completely disconnected from the main beam (6), and the upper load is transferred to the lower column and the foundation pedestal (4) through the jack (8); Step 8, tensioning the slow-bonding prestressed steel strand (7), and anchoring the slow-bonding prestressed steel strand (7) after reaching the designed locking value; Step 9, remove the jack (8), remove all the remaining columns to be removed, reinforce the secondary beams, plates and columns with steel wrapping and steel bonding, and after they are stable, remove the full-floor scaffolding support system (5).

2. The construction method for the super-large span drag beam removal and reinforcement reconstruction as claimed in claim 1 is characterized by: The building to be renovated comprises a plurality of original structural columns (9) and a main beam (6) arranged on top of the original structural columns (9), and the columns to be removed are parts of the original structural columns.

3. The construction method for the super-large span drag beam removal and reinforcement reconstruction as claimed in claim 1 is characterized by: The locations where the displacement, stress and strain monitoring marks (1) are arranged in step 2 include: the main beam (6), the original structural column (9) and the top plate.

4. The construction method for the super-large span drag beam removal and reinforcement reconstruction as claimed in claim 1 is characterized by: The installation of the jack (8) in step 6 includes: chiseling the top and bottom of the hole flat and laying a 10 mm steel plate; arranging I-beams (11) around the jack (8) to support it to prevent the jack (8) from suddenly failing due to hydraulic pressure.

5. The construction method for the super-large span drag beam removal and reinforcement reconstruction as claimed in claim 1 is characterized by: The tensioning of the slow-bonding prestressed steel strand (7) described in step 8 is divided into two or three times of tensioning.

6. The construction method for the reinforcement and reconstruction of a super-large span drag beam by removing columns as claimed in claim 1, characterized in that: The full-floor scaffolding support system (5) comprises a scaffolding body (501), a scaffolding top support (502) is arranged on the top of the scaffolding body (501), and wooden beams (503) are arranged inside the scaffolding top support (502) for support.

7. The construction method for the super-large span drag beam removal and reinforcement reconstruction as claimed in claim 1 is characterized by: The jack (8) is connected to the fully automatic real-time loading instrument (10) via a fully automatic real-time loading instrument control line (12).

Citation Information

Cited By

  • Method for intelligently monitoring unsupported prestressed tendon space bionic fish belly linear reinforcing transfer beam column disassembly

    CN121593604A

  • Intelligent monitoring of column-removed method of prestressed tendon space biomimetic fish abdomen linear shaped reinforced transfer beam

    CN121593604B