Control method of energy storage power distribution cabinet

By constructing a discharge time period prediction model, combining the capacity and electricity consumption type of the energy storage and distribution cabinet, the charging and discharge strategies of the energy storage and distribution cabinet are optimized, and the technical problem of reducing load during peak power consumption of the power grid is solved, and the power grid is realized Effective peak-cutting treatment of load.

CN119029968AActive Publication Date: 2024-11-26ZHEJIANG FONDA CONTROL TECH
View PDF 4 Cites 0 Cited by

Patent Information

Application Number
CN202410950908.2
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-16
Publication Date
2024-11-26
Estimated Expiration
2044-07-16

AI Technical Summary

Technical Problem

The existing energy storage and distribution cabinets lack precise and reasonable control methods for reducing load during peak power consumption of power grids.

Method used

By obtaining sample data, including peak and valley electricity price meter, capacity electricity price meter, electricity usage time meter and energy storage distribution cabinet capacity, a discharge time period prediction model is constructed, and the optimal time period for charging and discharging of energy storage distribution cabinet is calculated. The power type is fine-tuned to reduce grid load.

Benefits of technology

The charging and discharging strategies for energy storage and distribution cabinets in different power consumption environments are realized, and peak-cutting treatment is effectively performed to reduce the load during peak power consumption of the power grid.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119029968A_ABST
    Figure CN119029968A_ABST
Patent Text Reader

Abstract

The invention relates to a control method for an energy storage power distribution cabinet, and the method comprises the steps: carrying out the analysis of data of different power utilization types, and carrying out the calculation through combining with the specific capacity of the energy storage power distribution cabinet, so as to control the energy storage power distribution cabinet to carry out the charging and discharging in environments of different power utilization types, and carrying out the peak clipping of the power utilization peak of different power utilization types. Therefore, the load of the power grid during the power utilization peak period is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of energy storage distribution cabinets, and in particular to a control method for energy storage distribution cabinets. Background Art

[0002] The distribution cabinet is divided into power distribution cabinet, lighting distribution cabinet and metering cabinet. It is the final equipment of the power distribution system. The distribution cabinet is a general term for the motor control center. The distribution cabinet is used in places where the load is relatively dispersed and there are fewer circuits; the motor control center is used in places where the load is concentrated and there are more circuits. They distribute the power of a circuit of the upper-level distribution equipment to the nearest load. This level of equipment should provide protection, monitoring and control for the load.

[0003] The existing electricity consumption types are mainly divided into peak-valley electricity price pricing type and capacity electricity price pricing type. Both types of electricity consumption will increase the load on the power grid during the peak period of power consumption. At present, the coordinated use of energy storage distribution cabinets and power grid distribution cabinets is mostly used to reduce the load of the power grid during peak periods of power consumption. However, there is a lack of accurate and reasonable control methods for the control of energy storage distribution cabinets. Summary of the invention

[0004] Based on this, it is necessary to provide a control method for energy storage distribution cabinets in view of the problem that the traditional method of using energy storage distribution cabinets and power grid distribution cabinets in coordination to reduce the load during peak power consumption periods of the power grid, but there is a lack of accurate and reasonable control methods for the control of energy storage distribution cabinets.

[0005] The present application provides a control method for an energy storage distribution cabinet, comprising:

[0006] Obtain sample data of multiple samples, where the sample data of each sample includes a peak-valley electricity price table or a capacity electricity price table, a peak-valley electricity usage time table or a capacity electricity usage time table, and the capacity of the energy storage distribution cabinet;

[0007] Calculate the target peak-valley electricity consumption period for each sample data based on the peak-valley electricity price table and the peak-valley electricity consumption time table in the sample data of each sample, and calculate the expected discharge time period based on the target peak-valley electricity consumption period for all sample data;

[0008] Based on each sample data, each peak-valley electricity consumption schedule and the target peak-valley electricity consumption period of each sample data, a discharge time period prediction model is constructed;

[0009] Obtain a sample data to be tested, and obtain the electricity usage type of the sample data to be tested;

[0010] When the electricity consumption type of the sample data to be tested is the peak-valley pricing type, obtain the peak-valley electricity price table to be tested, the peak-valley electricity consumption time table to be tested, and the capacity of the energy storage distribution cabinet in the sample data to be tested, input the peak-valley electricity price table to be tested and the peak-valley electricity consumption time table to be tested into the discharge time period prediction model, start the discharge time period prediction model, and obtain the predicted discharge time period output by the discharge time period prediction model;

[0011] Based on the peak-valley electricity price table and the peak-valley electricity consumption schedule, calculate the optimal time period for charging the energy storage distribution cabinet;

[0012] When the electricity consumption type of the sample data to be tested is the capacity pricing type, obtain the electricity price table of the capacity to be tested, the electricity consumption time table of the capacity to be tested, and the capacity of the energy storage distribution cabinet in the sample data to be tested, and obtain at least one capacity electricity consumption peak period based on the electricity consumption time table of the capacity to be tested and the preset electricity consumption, and fine-tune the preset electricity consumption so that the energy storage distribution cabinet discharges with the optimal strategy during each capacity electricity consumption peak period.

[0013] The present application relates to a control method for an energy storage distribution cabinet, which analyzes data of different types of electricity consumption and calculates the specific capacity of the energy storage distribution cabinet to control the energy storage distribution cabinet to charge and discharge in environments with different types of electricity consumption, and then performs peak shaving processing on peak periods of electricity consumption of different types of electricity consumption to reduce the load on the power grid during peak periods of electricity consumption. BRIEF DESCRIPTION OF THE DRAWINGS

[0014] Figure 1 A schematic flow chart of a control method for an energy storage distribution cabinet provided in one embodiment of the present application. DETAILED DESCRIPTION

[0015] In order to make the purpose, technical solution and advantages of the present application more clearly understood, the present application is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present application and are not used to limit the present application.

[0016] like Figure 1 As shown, in one embodiment of the present application, the control method of the energy storage distribution cabinet includes the following S100 to S700:

[0017] S100, obtaining sample data of a plurality of samples, wherein the sample data of each sample includes a peak-valley electricity price table or a capacity electricity price table, a peak-valley electricity usage time table or a capacity electricity usage time table, and the capacity of an energy storage distribution cabinet.

[0018] Specifically, the sample data of each sample will have certain differences according to the different types of electricity consumption. The specific electricity consumption type refers to the type of electricity price billing method. The specific electricity price billing methods include peak-valley electricity billing and capacity electricity price billing. Therefore, the data in the sample data of each sample will include a set of peak-valley electricity price tables and peak-valley electricity usage time tables or a set of capacity electricity price tables and capacity electricity usage time tables; the capacity of the energy storage distribution cabinet refers to the capacity of the internal energy storage part of the energy storage distribution cabinet used; the peak-valley electricity price table and capacity electricity price table can be obtained from the latest published electricity price information, while the peak-valley electricity usage time table can be obtained from the historical operation data records, and the capacity electricity usage time table can be obtained from the electricity consumption data published by the same type or the same industry.

[0019] S200, calculating the target peak-valley electricity consumption peak period of each sample data based on the peak-valley electricity price table and the peak-valley electricity consumption time table in the sample data of each sample, and calculating the expected discharge time period based on the target peak-valley electricity consumption peak period of all sample data.

[0020] Specifically, data corresponding to power consumption and time in the peak-valley power consumption time table are counted and analyzed to obtain the peak-valley power consumption peak time period during which the specific power consumption in the peak-valley power consumption time table is the highest.

[0021] S300, constructing a discharge time period prediction model based on each sample data, each peak-valley power consumption time table and the target peak-valley power consumption period of each sample data.

[0022] Specifically, the peak time period of peak-valley electricity consumption is obtained for each peak-valley electricity consumption time table, and the multiple peak time periods of peak-valley electricity consumption are statistically analyzed and calculated to obtain data with a specific time period, and the logic of the specific time period acquisition process is used as the underlying logic for constructing a discharge time period prediction model. Then, each sample data, each peak-valley electricity price table, each peak-valley electricity consumption time table, and each peak-valley electricity consumption peak time period are used as training data to train the discharge time period prediction model, and a discharge time period prediction model with the function of predicting the discharge time period is obtained after training.

[0023] S400, obtaining a sample data to be tested, and obtaining the electricity usage type of the sample data to be tested.

[0024] Specifically, firstly, the electricity consumption type of the sample to be tested, whether it is the peak-valley electricity price or the capacity electricity price, is obtained to facilitate different data processing.

[0025] S500, when the electricity consumption type of the sample data to be tested is the peak-valley pricing type, obtain the peak-valley electricity price table to be tested, the peak-valley electricity consumption time table to be tested and the capacity of the energy storage distribution cabinet in the sample data to be tested, input the peak-valley electricity price table to be tested and the peak-valley electricity consumption time table to be tested into the discharge time period prediction model, start the discharge time period prediction model, and obtain the predicted discharge time period output by the discharge time period prediction model.

[0026] Specifically, under the premise that the electricity consumption type is peak-valley pricing, the peak-valley electricity price table to be tested, the peak-valley electricity consumption time table to be tested and the capacity of the energy storage distribution cabinet in the sample data to be tested are obtained, and the peak-valley electricity price table to be tested and the peak-valley electricity consumption time table to be tested are input into the discharge time period prediction model, the discharge time period prediction model is started, and the discharge time period prediction function of the discharge time period prediction model is used to obtain the specific predicted discharge time period.

[0027] S600, based on the peak-valley electricity price table and the peak-valley electricity consumption time table, calculate the optimal time period for charging the energy storage distribution cabinet.

[0028] Specifically, the low-power consumption time period in the peak-valley power consumption time table is used as the time period for charging the energy storage distribution cabinet to avoid the peak power consumption period, and the electricity prices in multiple peak-valley electricity price tables are obtained during the low-power consumption time period, and the lowest electricity price among the multiple electricity prices obtained is selected, and the time period corresponding to the lowest electricity price is queried according to the peak-valley electricity price table, and this time period is used as the optimal charging time period.

[0029] S700, when the electricity consumption type of the sample data to be tested is the capacity pricing type, obtain the electricity price table of the capacity to be tested, the electricity consumption time table of the capacity to be tested, and the capacity of the energy storage distribution cabinet in the sample data to be tested, obtain at least one capacity electricity consumption peak period based on the electricity consumption time table of the capacity to be tested and the preset electricity consumption, and fine-tune the preset electricity consumption so that the energy storage distribution cabinet discharges with the optimal strategy under each capacity electricity consumption peak period.

[0030] Specifically, under the premise that the electricity consumption type is capacity pricing, the electricity price table of the capacity to be tested, the electricity consumption schedule of the capacity to be tested, and the capacity of the energy storage distribution cabinet in the sample data to be tested are obtained, and the data analysis of the electricity consumption schedule of the capacity to be tested based on the preset electricity consumption is performed to obtain at least one peak electricity consumption period with the largest capacity above the preset electricity consumption, and then the preset electricity consumption is continuously adjusted to make the total electricity consumption above the preset electricity consumption in the peak electricity consumption period with the largest capacity adapt to the capacity of the energy storage distribution cabinet, so as to obtain the optimal strategy discharge of the energy storage distribution cabinet, and the optimal strategy refers to On the basis that the capacity of the energy storage distribution cabinet and the capacity of the distribution cabinet with actual power consumption are known, the energy storage distribution cabinet and the distribution cabinet with actual power consumption are enabled at the same time during the peak power consumption period, and the capacity of the energy storage distribution cabinet and the part of the distribution cabinet load that exceeds the actual power consumption are accurately calculated for adaptability, so that the part of the distribution cabinet load that exceeds the actual power consumption is provided by the energy storage distribution cabinet, thereby reducing the load during the peak power consumption period; the preset power consumption is set based on the maximum unit time power consumption of the power consumption schedule of the capacity to be tested, and the preset power consumption is less than the maximum unit time power consumption of the power consumption schedule of the capacity to be tested.

[0031] In one embodiment of the present application, the optimal time period for charging the energy storage distribution cabinet is calculated based on the peak-valley electricity price table and the peak-valley electricity consumption time table, including the following S601 to S607:

[0032] S601, selecting sample data of a sample.

[0033] S602, parsing the sample data to obtain a peak-valley electricity price table and a peak-valley electricity usage time table contained in the sample data.

[0034] S603, extracting multiple peak-valley electricity consumption time periods and multiple peak-valley electricity consumption low time periods from the peak-valley electricity consumption time table; each peak-valley electricity consumption time period corresponds to an electricity price, and each peak-valley electricity consumption low time period corresponds to an electricity price.

[0035] S604: Record the time period with the lowest electricity price among the peak-valley and off-valley electricity consumption time periods as the target charging time periods.

[0036] S605: Record the electricity price during the target charging time period as the target electricity price.

[0037] S606: Output the target charging time period as the optimal time period for charging the energy storage distribution cabinet.

[0038] S607, returning to the step of selecting a sample data, until each sample data has been selected once.

[0039] Specifically, the peak-valley electricity price list is the actual electricity price list released during the current time period, and the peak-valley electricity consumption time table is the historical electricity consumption data of the power distribution cabinet described by the electrical load.

[0040] In this embodiment, the electricity prices occurring in all the low-power consumption time periods are counted, and the lowest electricity price is used as the target charging electricity price, and the time period of the target charging electricity price is used as the target charging time period, during which the energy storage distribution cabinet is charged.

[0041] In one embodiment of the present application, extracting a plurality of peak-valley power consumption time periods and a plurality of peak-valley power consumption low time periods from the peak-valley power consumption time table includes the following S603a to S603k:

[0042] S603a, selecting a peak and valley electricity usage schedule.

[0043] S603b, analyzing the peak-valley electricity usage time table to obtain a curve of unit electricity usage-time in the peak-valley electricity usage time table.

[0044] S603c: Obtain a preset first power consumption.

[0045] S603d: If a portion of the curve of the unit time electricity consumption-time in the peak-valley electricity consumption time table that is higher than the first electricity consumption has a peak, the time period corresponding to the peak is used as the peak-valley electricity consumption peak period.

[0046] S603e, obtaining the number of peak-valley electricity consumption peak periods in the curve of unit time electricity consumption-time in the peak-valley electricity consumption time table.

[0047] S603f, determining whether the number of peak-valley electricity consumption peak periods in the curve of unit time electricity consumption-time in the peak-valley electricity consumption time table is equal to 1.

[0048] S603g: If the number of peak-valley power consumption peak periods in the curve of power consumption per unit time-time in the peak-valley power consumption time table is not equal to 1, a preset change amount is added to the first power consumption to obtain an updated first power consumption.

[0049] S603h: Obtain the number of peak and valley power consumption peak periods in the power consumption per unit time-time curve based on the updated first power consumption.

[0050] S603i, returning to the step of determining whether the number of peak periods of peak-valley electricity consumption in the curve of unit time electricity consumption-time in the peak-valley electricity consumption time table is equal to 1.

[0051] S603j: If the number of peak-valley electricity consumption peak periods in the curve of unit time electricity consumption-time in the peak-valley electricity consumption time table is equal to 1, then the peak-valley electricity consumption peak period is recorded as the target peak-valley electricity consumption peak period.

[0052] S603k, returning to the process of selecting a peak-valley electricity usage schedule until each peak-valley electricity usage schedule has been selected once.

[0053] Specifically, the preset first power consumption is set based on the highest power consumption per unit time of the peak-valley power consumption schedule, and the preset first power consumption is less than the highest power consumption per unit time of the peak-valley power consumption schedule.

[0054] In this embodiment, based on a preset first power consumption, a peak-valley power consumption time table may have multiple peaks, and the multiple peaks need to be screened to obtain a peak with the highest peak value. By using the underlying logic of screening the peaks when adjusting the preset first power consumption, when the number of peaks obtained is one, the time period defined by the time axis information of the two intersections of the final preset first power consumption and the unit time power consumption-time curve in the peak-valley power consumption time table is used as the peak-valley power consumption peak time period of the target peak-valley power consumption peak period.

[0055] In one embodiment of the present application, the discharge time period prediction model is constructed based on each sample data, each peak-valley electricity price table, each peak-valley electricity consumption time table, and each peak-valley electricity consumption peak time period, including the following S301 to S306:

[0056] S301, selecting a target peak-valley electricity consumption period.

[0057] S302, analyzing the target peak-valley electricity consumption peak period to obtain at least one peak-valley electricity consumption peak time period corresponding to the target peak-valley electricity consumption peak period.

[0058] S303, returning to the step of selecting a target peak-valley electricity consumption peak period, until each target peak-valley electricity consumption peak period has been selected once, thereby obtaining a plurality of peak-valley electricity consumption peak time periods.

[0059] S304, calculating the time union of all peak-valley power consumption time periods, and recording the time union of all peak-valley power consumption time periods as the expected discharge time period.

[0060] S305, constructing a discharge time period prediction model.

[0061] S306, using each sample data, each peak-valley electricity consumption time table, each target peak-valley electricity consumption peak period, each peak-valley electricity consumption peak time period corresponding to the target peak-valley electricity consumption peak period, each unit time electricity consumption-time curve, the first electricity consumption, the preset change, and the expected discharge time period as training data to train the discharge time period prediction model, and obtain the trained discharge time period prediction model.

[0062] In this embodiment, sample data refers to power consumption data of a load within a set unit time. The peak-valley power consumption peak time periods corresponding to the obtained multiple peak-valley power consumption peak periods are statistically analyzed, and the time period union of the peak-valley power consumption peak time periods corresponding to all peak-valley power consumption peak periods is calculated. The time union of all peak-valley power consumption peak time periods is recorded as the expected discharge time period. A discharge time period prediction model is constructed based on the calculation logic. Each sample data, each peak-valley power consumption time table, each target peak-valley power consumption peak period, the peak-valley power consumption peak time period corresponding to each target peak-valley power consumption peak period, each unit time power consumption-time curve, the first power consumption, the preset change, and the expected discharge time period of each sample data are used as training data to train the discharge time period prediction model to obtain the trained discharge time period prediction model.

[0063] In one embodiment of the present application, when the electricity consumption type of the sample data to be tested is a capacity pricing type, obtaining a capacity electricity price table to be tested, a capacity electricity consumption time table to be tested, and the capacity of the energy storage distribution cabinet in the sample data to be tested, obtaining at least one capacity electricity consumption peak period based on each capacity electricity consumption time table to be tested and the preset electricity consumption, and fine-tuning the preset electricity consumption so that the energy storage distribution cabinet discharges with an optimal strategy during each capacity electricity consumption peak period, including the following S701 to S708:

[0064] S701, parsing the sample data to be tested to obtain a capacity power usage schedule in the sample data to be tested.

[0065] S702, parsing the capacity power consumption time table to be measured, and obtaining a curve of power consumption per unit time-time in the capacity power consumption time table to be measured.

[0066] S703: Obtain a preset second power consumption, where the second power consumption is less than a maximum power consumption per unit time.

[0067] S704, draw a horizontal line in the unit time power consumption-time curve in the capacity power consumption time table to be measured, whose horizontal axis changes with time and whose vertical axis is constant as the second power consumption, and define the horizontal line as the second power consumption horizontal line.

[0068] S705, calculating the area of ​​each closed figure enclosed by the second power consumption horizontal line and the curve of the power consumption per unit time-time of the capacity power consumption time table to be measured.

[0069] S706: Filter out closed figures located above the second power consumption horizontal line as candidate closed figures.

[0070] S707, comparing the area of ​​each candidate closed figure, obtaining the candidate closed figure with the largest area, and taking it as the target closed figure, and the time period corresponding to each target closed figure is a capacity power consumption peak period.

[0071] S708, returning the sample data of the selected sample until each sample data has been selected once.

[0072] Specifically, the preset second power consumption is set based on the highest power consumption per unit time in the power consumption time table of the capacity to be measured, and the second power consumption is less than the maximum value of the power consumption per unit time in the power consumption time table of the capacity to be measured; the area of ​​the closed figure in the power consumption time table of the capacity to be measured may contain two or more closed figures with the same area.

[0073] In this embodiment, on the basis of the unit time electricity consumption-time curve of the capacity electricity consumption time table to be measured, a preset second electricity consumption is set to obtain a closed figure enclosed by the preset second electricity consumption and the unit time electricity consumption-time curve of the capacity electricity consumption time table, and the closed figure with the largest area among the multiple closed figures obtained is used as the target closed figure.

[0074] In one embodiment of the present application, when the electricity consumption type of the sample data to be tested is a capacity pricing type, the electricity price table of the capacity to be tested, the electricity consumption time table of the capacity to be tested, and the capacity of the energy storage distribution cabinet in the sample data to be tested are obtained, and at least one capacity electricity consumption peak period is obtained based on each capacity electricity consumption time table and the preset electricity consumption, and the preset electricity consumption is fine-tuned so that the energy storage distribution cabinet discharges with the optimal strategy during each capacity electricity consumption peak period, and also includes the following S709 to S716:

[0075] S709, selecting a target closed graph corresponding to the capacity power consumption peak period.

[0076] S710, converting the area of ​​the target closed figure into a to-be-determined capacity.

[0077] S711, compare the to-be-determined capacity with the capacity of the energy storage distribution cabinet to determine whether the to-be-determined capacity is greater than the capacity of the energy storage distribution cabinet.

[0078] S712: If the to-be-determined capacity is greater than the capacity of the energy storage distribution cabinet, the difference between the to-be-determined capacity and the capacity of the energy storage distribution cabinet is calculated to determine whether the difference is less than a preset threshold.

[0079] S713, if the difference is greater than the preset threshold, the first fine-tuning strategy is adopted to fine-tune the preset second power consumption until the difference between the fine-tuned pending capacity and the capacity of the energy storage distribution cabinet is less than the preset threshold, and the target second power consumption is obtained and output.

[0080] S714: If the to-be-determined capacity is less than the capacity of the energy storage distribution cabinet, the difference between the to-be-determined capacity and the capacity of the energy storage distribution cabinet is calculated to determine whether the difference is less than a preset threshold.

[0081] S715, if the difference is greater than the preset threshold, a second fine-tuning strategy is adopted to fine-tune the preset second power consumption until the difference between the fine-tuned pending capacity and the capacity of the energy storage distribution cabinet is less than the preset threshold, and the target second power consumption is obtained and output.

[0082] S716, returning to the step of selecting a target closed figure, until each target closed figure has been selected once.

[0083] Specifically, the area of ​​the target closed figure is equivalent to the pending capacity, and the area of ​​the target closed figure is the electricity consumption within a certain period of time; the preset threshold refers to the limited range of the difference between the pending capacity and the capacity of the energy storage distribution cabinet.

[0084] In this embodiment, the size of the to-be-determined capacity and the capacity of the energy storage distribution cabinet is first determined, and different adjustment strategies are performed on the second power consumption based on the determination result. The purpose of the adjustment strategy is to make the difference between the to-be-determined capacity and the capacity of the energy storage distribution cabinet smaller than a preset threshold, and the adjusted second power consumption is output as the target second power consumption.

[0085] In one embodiment of the present application, if the difference is greater than a preset threshold, a first fine-tuning strategy is adopted to fine-tune the preset second power consumption until the difference between the fine-tuned pending capacity and the capacity of the energy storage distribution cabinet is less than the preset threshold, and the target second power consumption is obtained and output, including the following S713a to S713g:

[0086] S713a, adjusting the first unit change value based on the difference between the to-be-determined capacity and the capacity of the energy storage distribution cabinet; the first unit change value has a first preset initial value.

[0087] S713b, calculating the value of the second power consumption before fine-tuning plus the first unit change value, and obtaining the second power consumption after being updated toward the first direction.

[0088] S713c: Calculate an updated pending capacity based on the second power consumption updated in the first direction.

[0089] S713d, calculating the difference between the updated pending capacity and the capacity of the energy storage distribution cabinet.

[0090] S713e, determining whether the difference between the updated pending capacity and the capacity of the energy storage distribution cabinet is less than the preset threshold.

[0091] S713f, if the difference between the updated pending capacity and the capacity of the energy storage distribution cabinet is greater than the preset threshold, the difference between the pending capacity and the capacity of the energy storage distribution cabinet is returned to adjust the first unit change value.

[0092] S713g: If the difference between the updated pending capacity and the capacity of the energy storage distribution cabinet is less than the preset threshold, the second power consumption updated in the first direction is recorded as the target second power consumption output.

[0093] Specifically, the first direction can be understood as the direction in which the second power consumption moves, that is, the positive or negative value of the first unit change value.

[0094] In this embodiment, the second power consumption is updated or adjusted by adjusting the first unit change value as the variable of the second power consumption, thereby obtaining the difference between the updated pending capacity and the capacity of the energy storage distribution cabinet, and a logical judgment is made on whether the difference between the updated pending capacity and the capacity of the energy storage distribution cabinet is less than a preset threshold value, until the difference between the updated pending capacity and the capacity of the energy storage distribution cabinet is less than the preset threshold value, thereby obtaining the final target second power consumption.

[0095] In one embodiment of the present application, if the difference is greater than a preset threshold, a second fine-tuning strategy is adopted to fine-tune the preset second power consumption until the difference between the fine-tuned to-be-determined capacity and the capacity of the energy storage distribution cabinet is less than the preset threshold, and the target second power consumption is obtained and output, including the following S715a to S715g:

[0096] S715a, adjusting the second unit change value based on the difference between the to-be-determined capacity and the capacity of the energy storage distribution cabinet; the second unit change value has a second preset initial value.

[0097] S715b, calculating the value of the second power consumption before fine-tuning minus the second unit change value, and obtaining the second power consumption after being updated toward the second direction.

[0098] S715c: Calculate the updated pending capacity based on the second power consumption updated in the second direction.

[0099] S715d, calculating the difference between the updated pending capacity and the capacity of the energy storage distribution cabinet.

[0100] S715e, determining whether the difference between the updated pending capacity and the capacity of the energy storage distribution cabinet is less than the preset threshold.

[0101] S715f, if the difference between the updated pending capacity and the capacity of the energy storage distribution cabinet is greater than the preset threshold, the difference between the pending capacity and the capacity of the energy storage distribution cabinet is returned to adjust the second unit change value.

[0102] S715g: If the difference between the updated pending capacity and the capacity of the energy storage distribution cabinet is less than the preset threshold, the second power consumption updated in the second direction is recorded as the target second power consumption output.

[0103] Specifically, the second direction can be understood as the direction in which the second power consumption moves, that is, the positive or negative value of the first unit change value.

[0104] In this embodiment, the second power consumption is updated or adjusted by adjusting the second unit change value as the variable of the second power consumption, thereby obtaining the difference between the updated to-be-determined capacity and the capacity of the energy storage distribution cabinet, and a logical judgment is made on whether the difference between the updated to-be-determined capacity and the capacity of the energy storage distribution cabinet is less than a preset threshold value, until the difference between the updated to-be-determined capacity and the capacity of the energy storage distribution cabinet is less than the preset threshold value, to obtain the final target second power consumption; wherein the first direction and the second direction are two opposite directions, and the first direction and the second direction are selected based on the size of the to-be-determined capacity and the capacity of the energy storage distribution cabinet.

[0105] In one embodiment of the present application, adjusting the first unit change value based on the difference between the to-be-determined capacity and the capacity of the energy storage distribution cabinet includes the following steps S013a to S313a:

[0106] S013a, adjusting the area of ​​the target closed figure to adjust the to-be-determined capacity.

[0107] S113a, obtaining the difference between the adjusted pending capacity and the capacity of the energy storage distribution cabinet; obtaining two power consumption time nodes corresponding to the second power consumption before fine-tuning.

[0108] S213a, arranging the two power consumption time nodes corresponding to the second power consumption before fine-tuning in chronological order, and taking the time period between the two power consumption time nodes corresponding to the second power consumption before fine-tuning as the time period to be fine-tuned.

[0109] S313a, calculating the ratio of the difference between the to-be-determined capacity and the capacity of the energy storage distribution cabinet to the time span of the time period to be fine-tuned, and recording the ratio as the first unit change value.

[0110] Specifically, the first unit change value is the ratio of the difference between the to-be-determined capacity and the capacity of the energy storage distribution cabinet (the difference between the area of ​​the closed figure with the largest area and the capacity of the energy storage distribution cabinet) to the time period to be fine-tuned corresponding to the second power consumption before fine-tuning.

[0111] In this embodiment, the logic for obtaining the first unit change value or the second unit change value is defined by dividing the difference between the to-be-determined capacity and the capacity of the energy storage distribution cabinet by the time period to be fine-tuned corresponding to the second power consumption before fine-tuning, and then continuously adjusting the second power consumption, and further obtaining the difference between the adjusted to-be-determined capacity and the capacity of the energy storage distribution cabinet, until the difference between the adjusted to-be-determined capacity and the capacity of the energy storage distribution cabinet is less than a preset threshold value, at which time the second power consumption is stopped from being updated, and the adjusted second power consumption is used as the target second power consumption.

[0112] In one embodiment of the present application, when the electricity consumption type of the sample data to be tested is a capacity pricing type, the electricity price table of the capacity to be tested, the electricity consumption time table of the capacity to be tested, and the capacity of the energy storage distribution cabinet in the sample data to be tested are obtained, and at least one capacity electricity consumption peak period is obtained based on each capacity electricity consumption time table and the preset electricity consumption, and the preset electricity consumption is fine-tuned so that the energy storage distribution cabinet discharges with the optimal strategy during each capacity electricity consumption peak period, and also includes the following S717 to S719:

[0113] S717, obtaining a curve of power consumption per unit time-time in the power consumption time table of the capacity to be measured.

[0114] S718: Based on the target second power consumption, obtain at least one discharge time period of a curve of power consumption per unit time-time of the power consumption schedule of the capacity to be measured.

[0115] S719, after the energy storage distribution cabinet is powered on, a discharge operation is performed on the energy storage distribution cabinet in each discharge time period.

[0116] Specifically, the discharge time period is the peak power consumption time period of the power consumption schedule of the capacity to be measured; the target second power consumption is the optimal actual maximum load of the distribution cabinet calculated based on the power consumption schedule of the capacity to be measured and the capacity of the energy storage distribution cabinet.

[0117] In this embodiment, the optimal actual maximum load of the distribution cabinet is calculated based on the power consumption schedule of the capacity to be measured and the capacity of the energy storage distribution cabinet, and then one or more discharge time periods that exist in the part that exceeds the actual maximum load of the distribution cabinet are the working time periods of the energy storage distribution cabinet.

[0118] The technical features of the above-described embodiments may be arbitrarily combined, and the execution order of the method steps is not limited. To make the description concise, not all possible combinations of the technical features in the above-described embodiments are described. However, as long as there is no contradiction in the combination of these technical features, they should be considered to be within the scope of this specification.

[0119] The above-described embodiments only express several implementation methods of the present application, and the descriptions thereof are relatively specific and detailed, but they cannot be understood as limiting the scope of the present application. It should be pointed out that, for a person of ordinary skill in the art, several variations and improvements can be made without departing from the concept of the present application, and these all belong to the protection scope of the present application. Therefore, the protection scope of the present application shall be subject to the attached claims.

Claims

1. A control method for an energy storage distribution cabinet, characterized in that: The control method of the energy storage distribution cabinet includes: Obtain sample data of multiple samples, where the sample data of each sample includes a peak-valley electricity price table or a capacity electricity price table, a peak-valley electricity usage time table or a capacity electricity usage time table, and the capacity of the energy storage distribution cabinet; Calculate the target peak-valley electricity consumption period for each sample data based on the peak-valley electricity price table and the peak-valley electricity consumption time table in the sample data of each sample, and calculate the expected discharge time period based on the target peak-valley electricity consumption period for all sample data; Based on each sample data, each peak-valley electricity consumption schedule and the target peak-valley electricity consumption period of each sample data, a discharge time period prediction model is constructed; Obtain a sample data to be tested, and obtain the electricity usage type of the sample data to be tested; When the electricity consumption type of the sample data to be tested is the peak-valley pricing type, obtain the peak-valley electricity price table to be tested, the peak-valley electricity consumption time table to be tested, and the capacity of the energy storage distribution cabinet in the sample data to be tested, input the peak-valley electricity price table to be tested and the peak-valley electricity consumption time table to be tested into the discharge time period prediction model, start the discharge time period prediction model, and obtain the predicted discharge time period output by the discharge time period prediction model; Based on the peak-valley electricity price table and the peak-valley electricity consumption schedule, calculate the optimal time period for charging the energy storage distribution cabinet; When the electricity consumption type of the sample data to be tested is the capacity pricing type, obtain the electricity price table of the capacity to be tested, the electricity consumption time table of the capacity to be tested, and the capacity of the energy storage distribution cabinet in the sample data to be tested, and obtain at least one capacity electricity consumption peak period based on the electricity consumption time table of the capacity to be tested and the preset electricity consumption, and fine-tune the preset electricity consumption so that the energy storage distribution cabinet discharges with the optimal strategy during each capacity electricity consumption peak period.

2. The control method of the energy storage distribution cabinet according to claim 1, characterized in that: The calculation of the optimal time period for charging the energy storage distribution cabinet based on the peak-valley electricity price table and the peak-valley electricity consumption time table includes: Select a sample of sample data; Parse the sample data to obtain a peak-valley electricity price table and a peak-valley electricity usage time table contained in the sample data; Extract multiple peak-valley electricity consumption time periods and multiple peak-valley electricity consumption low time periods from the peak-valley electricity consumption time table; each peak-valley electricity consumption time period corresponds to an electricity price, and each peak-valley electricity consumption low time period corresponds to an electricity price; The time period with the lowest electricity price among the peak-valley and off-valley electricity consumption periods is recorded as the target charging time period; Recording the electricity price during the target charging time period as the target electricity price; Outputting the target charging time period as the optimal time period for charging the energy storage distribution cabinet; Return to the step of selecting a sample data until each sample data has been selected once.

3. The control method of the energy storage distribution cabinet according to claim 2 is characterized in that: The step of extracting a plurality of peak-valley electricity consumption time periods and a plurality of peak-valley electricity consumption time periods from the peak-valley electricity consumption time table includes: Select a peak and valley electricity usage schedule; Analyze the peak-valley electricity consumption schedule to obtain a curve of unit electricity consumption-time in the peak-valley electricity consumption schedule; Obtaining a preset first power consumption; If there is a peak in the portion of the curve of unit time power consumption-time in the peak-valley power consumption time table that is higher than the first power consumption, the time period corresponding to the peak is regarded as the peak power consumption period; Obtain the number of peak-valley electricity consumption peak periods in the curve of unit time electricity consumption-time in the peak-valley electricity consumption time table; Determine whether the number of peak-valley electricity consumption peak periods in the curve of unit time electricity consumption-time in the peak-valley electricity consumption time table is equal to 1; If the number of peak periods of peak-valley electricity consumption in the curve of unit-time electricity consumption-time in the peak-valley electricity consumption time table is not equal to 1, a preset change amount is added to the first electricity consumption to obtain an updated first electricity consumption; Based on the updated first power consumption, obtain the number of peak and valley power consumption peak periods in the power consumption per unit time-time curve; Returning to the step of determining whether the number of peak-valley electricity consumption peak periods in the curve of unit time electricity consumption-time in the peak-valley electricity consumption time table is equal to 1; If the number of peak-valley electricity consumption peak periods in the curve of unit time electricity consumption-time in the peak-valley electricity consumption timetable is equal to 1, then the peak-valley electricity consumption peak period is recorded as the target peak-valley electricity consumption peak period; Return to the process of selecting a peak-valley electricity usage schedule until each peak-valley electricity usage schedule has been selected once.

4. The control method of the energy storage distribution cabinet according to claim 3 is characterized in that: The discharge time period prediction model is constructed based on each sample data, each peak-valley electricity price table, each peak-valley electricity consumption time table, and each peak-valley electricity consumption peak time period, including: Select a target peak electricity consumption period; Analyze the peak-valley electricity consumption period to obtain at least one peak-valley electricity consumption time period corresponding to the target peak-valley electricity consumption period; Returning to the step of selecting a target peak-valley electricity consumption peak period, until each target peak-valley electricity consumption peak period has been selected once, and obtaining multiple peak-valley electricity consumption peak time periods; Calculate the time union of all peak-valley power consumption time periods, and record the time union of all peak-valley power consumption time periods as the expected discharge time period; Construct a discharge time period prediction model; Each sample data, each peak-valley electricity consumption time table, each target peak-valley electricity consumption peak period, each peak-valley electricity consumption peak time period corresponding to each target peak-valley electricity consumption peak period, each unit time electricity consumption-time curve, the first electricity consumption, the preset change, and the expected discharge time period are used as training data to train the discharge time period prediction model to obtain the trained discharge time period prediction model.

5. The control method of the energy storage distribution cabinet according to claim 4, characterized in that: When the electricity consumption type of the sample data to be tested is a capacity pricing type, obtaining the electricity price table of the capacity to be tested, the electricity consumption time table of the capacity to be tested, and the capacity of the energy storage distribution cabinet in the sample data to be tested, obtaining at least one capacity electricity consumption peak period based on each capacity electricity consumption time table and the preset electricity consumption, and fine-tuning the preset electricity consumption so that the energy storage distribution cabinet discharges with an optimal strategy during each capacity electricity consumption peak period, including: Parsing the sample data to be tested to obtain a power consumption schedule of the capacity to be tested in the sample data to be tested; Analyze the capacity power consumption time table to be measured, and obtain a curve of power consumption per unit time-time in the capacity power consumption time table to be measured; Acquire a preset second power consumption, where the second power consumption is less than a maximum power consumption per unit time; Draw a horizontal line whose abscissa changes with time and whose ordinate is constant as the second power consumption in the curve of power consumption per unit time-time in the power consumption time table of the capacity to be measured, and define the horizontal line as the second power consumption horizontal line; Calculate the area of ​​each closed figure enclosed by the second power consumption horizontal line and the curve of power consumption per unit time-time of the power consumption time table of the capacity to be measured; Selecting a closed figure located above the second power consumption horizontal line as a candidate closed figure; Compare the area of ​​each candidate closed figure, obtain the candidate closed figure with the largest area, and use it as the target closed figure. The time period corresponding to each target closed figure is a capacity power consumption peak period; The sample data of the selected sample is returned until each sample data has been selected once.

6. The control method of the energy storage distribution cabinet according to claim 5, characterized in that: When the electricity consumption type of the sample data to be tested is a capacity pricing type, obtaining the electricity price table of the capacity to be tested, the electricity consumption time table of the capacity to be tested, and the capacity of the energy storage distribution cabinet in the sample data to be tested, obtaining at least one capacity electricity consumption peak period based on each capacity electricity consumption time table and the preset electricity consumption, and fine-tuning the preset electricity consumption so that the energy storage distribution cabinet discharges with the optimal strategy during each capacity electricity consumption peak period, further comprising: Select a target closed graph corresponding to the peak period of capacity electricity consumption; Convert the area of ​​the target closed figure into the undetermined capacity; Compare the pending capacity with the capacity of the energy storage distribution cabinet to determine whether the pending capacity is greater than the capacity of the energy storage distribution cabinet; If the to-be-determined capacity is greater than the capacity of the energy storage distribution cabinet, the difference between the to-be-determined capacity and the capacity of the energy storage distribution cabinet is calculated to determine whether the difference is less than a preset threshold; If the difference is greater than the preset threshold, the first fine-tuning strategy is adopted to fine-tune the preset second power consumption until the difference between the fine-tuned pending capacity and the capacity of the energy storage distribution cabinet is less than the preset threshold, and the target second power consumption is obtained and output; If the to-be-determined capacity is less than the capacity of the energy storage distribution cabinet, the difference between the to-be-determined capacity and the capacity of the energy storage distribution cabinet is calculated to determine whether the difference is less than a preset threshold; If the difference is greater than the preset threshold, a second fine-tuning strategy is adopted to fine-tune the preset second power consumption until the difference between the fine-tuned pending capacity and the capacity of the energy storage distribution cabinet is less than the preset threshold, and the target second power consumption is obtained and output; Return to selecting a target closed figure until each target closed figure has been selected once.

7. The control method of the energy storage distribution cabinet according to claim 6, characterized in that: If the difference is greater than the preset threshold, the first fine-tuning strategy is adopted to fine-tune the preset second power consumption until the difference between the fine-tuned pending capacity and the capacity of the energy storage distribution cabinet is less than the preset threshold, and the target second power consumption is obtained and output, including: Based on the difference between the to-be-determined capacity and the capacity of the energy storage distribution cabinet, adjusting the first unit change value; the first unit change value has a first preset initial value; Calculate the second power consumption before fine-tuning plus the first unit change value to obtain the second power consumption after updating toward the first direction; Calculate the updated pending capacity based on the second power consumption updated in the first direction; Calculate the difference between the updated pending capacity and the capacity of the energy storage distribution cabinet; Determine whether the difference between the updated pending capacity and the capacity of the energy storage distribution cabinet is less than the preset threshold; If the difference between the updated pending capacity and the capacity of the energy storage distribution cabinet is greater than the preset threshold, the difference between the pending capacity and the capacity of the energy storage distribution cabinet is returned, and the first unit change value is adjusted; If the difference between the updated pending capacity and the capacity of the energy storage distribution cabinet is less than the preset threshold, the second power consumption updated in the first direction is recorded as the target second power consumption output.

8. The control method of the energy storage distribution cabinet according to claim 7, characterized in that: If the difference is greater than the preset threshold, a second fine-tuning strategy is adopted to fine-tune the preset second power consumption until the difference between the fine-tuned pending capacity and the capacity of the energy storage distribution cabinet is less than the preset threshold, and the target second power consumption is obtained and output, including: Based on the difference between the to-be-determined capacity and the capacity of the energy storage distribution cabinet, adjusting the second unit change value; the second unit change value has a second preset initial value; Calculate the value of the second power consumption before fine-tuning minus the second unit change value to obtain the second power consumption after updating in the second direction; Calculate the updated pending capacity based on the second power consumption updated in the second direction; Calculate the difference between the updated pending capacity and the capacity of the energy storage distribution cabinet; Determine whether the difference between the updated pending capacity and the capacity of the energy storage distribution cabinet is less than the preset threshold; If the difference between the updated pending capacity and the capacity of the energy storage distribution cabinet is greater than the preset threshold, the difference between the pending capacity and the capacity of the energy storage distribution cabinet is returned, and the second unit change value is adjusted; If the difference between the updated pending capacity and the capacity of the energy storage distribution cabinet is less than the preset threshold, the second power consumption updated in the second direction is recorded as the target second power consumption output.

9. The control method of the energy storage distribution cabinet according to claim 8, characterized in that: The adjusting the first unit change value based on the difference between the to-be-determined capacity and the capacity of the energy storage distribution cabinet includes: Adjust the area of ​​the target closed figure to adjust the pending capacity; Obtain the difference between the adjusted pending capacity and the capacity of the energy storage distribution cabinet; obtain two power consumption time nodes corresponding to the second power consumption before fine-tuning; Arrange the two power consumption time nodes corresponding to the second power consumption before fine-tuning in chronological order, and use the time period between the two power consumption time nodes corresponding to the second power consumption before fine-tuning as the time period to be fine-tuned; Calculate the ratio of the difference between the to-be-determined capacity and the capacity of the energy storage distribution cabinet to the time span of the time period to be fine-tuned, and record the ratio as the first unit change value.

10. The control method of the energy storage distribution cabinet according to claim 9, characterized in that: When the electricity consumption type of the sample data to be tested is a capacity pricing type, obtaining the electricity price table of the capacity to be tested, the electricity consumption time table of the capacity to be tested, and the capacity of the energy storage distribution cabinet in the sample data to be tested, obtaining at least one capacity electricity consumption peak period based on each capacity electricity consumption time table and the preset electricity consumption, and fine-tuning the preset electricity consumption so that the energy storage distribution cabinet discharges with the optimal strategy during each capacity electricity consumption peak period, further comprising: Obtain a curve of power consumption per unit time-time in the power consumption time table of the capacity to be measured; Based on the target second power consumption, obtaining at least one discharge time period of a curve of power consumption per unit time-time of the power consumption schedule of the capacity to be measured; After the energy storage distribution cabinet is powered on, a discharge operation is performed on the energy storage distribution cabinet in each discharge time period.

Citation Information

Patent Citations

  • Energy storage device peak return time forecasting method and energy storage device peak return time forecasting model creating method

    CN107565585A

  • Charging and discharging control method and device for user-side energy storage equipment, and storage medium

    CN111525601A

  • Charging and discharging control method and device of energy storage equipment, electronic equipment and storage medium

    CN116865454A

  • Method and device for planning output of gravity energy storage power station

    CN117613961A