Structure of expansion joint of elevated bridge and construction method thereof
By employing anchoring and fastening components in bridge expansion joints, the problem of poor structural stability of bridge expansion joints has been solved, resulting in bridge expansion joints with high stability and durability, thus ensuring traffic safety.
Patent Information
- Application Number
- CN202411387085.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-30
- Publication Date
- 2024-11-29
AI Technical Summary
Existing bridge expansion joint structures have poor stability and are prone to cracking after vehicles pass over them, affecting driving speed, comfort and safety, and may even lead to safety accidents.
The structure employs anchoring and fastening components, including anchor plates, connecting plates, reinforcing ribs, sleeves, and prestressed steel bars. These components are fixedly connected to the toothed plate via embedded steel bars to form an integral structure, which is then filled with concrete to enhance stability.
It improves the stability and durability of bridge expansion joints, reduces crack formation, ensures driving safety, and avoids safety hazards caused by expansion joint damage.
Smart Images

Figure CN119041290A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of bridge expansion joints, and in particular relates to a structure of an elevated bridge expansion joint and a construction method thereof. Background Art
[0002] Bridges are open-air permanent structures that cross obstacles such as rivers, deep valleys and built roads. Due to factors such as temperature changes, concrete shrinkage and creep, and changing loads, the beam ends of the bridge will creep. To adapt to this characteristic of the bridge structure, it is necessary to set expansion joints that can deform freely in the bridge structure and between the beam ends and the back wall of the abutment to ensure a smooth bridge deck and protect the structure.
[0003] At present, the existing expansion joint structure has poor stability. After years of use and the passage of vehicles, cracks will appear, which will cause the expansion joint to be damaged. Once the position of the bridge expansion joint is damaged, it will seriously affect the speed, comfort and safety of driving, and may even cause driving safety accidents in severe cases. Therefore, a structure of an elevated bridge expansion joint and its construction method are needed to solve this problem. Summary of the invention
[0004] To achieve the above-mentioned purpose, the present invention provides a structure of an expansion joint of an elevated bridge, which is arranged in a gap between two adjacent main beams, and a pavement layer is laid on the upper surfaces of the two main beams. The spacing between the two pavement layers is greater than the spacing between the two main beams. A row of first embedded steel bars is embedded in the two main beams, including a tooth plate arranged in the gap, the tooth plate is horizontally arranged from front to back along the length direction of the gap, and anchoring components are provided on the left and right sides of the tooth plate. The tooth plate is fixedly connected to the first embedded steel bar through the anchoring component, and a fastening component is provided on the anchoring component.
[0005] Furthermore, the anchor assembly is composed of a number of anchor plates with rectangular vertical cross-sections spliced in sequence from front to back, the anchor plates are horizontally arranged along the length direction of the tooth plate, the anchor plates are hollow and have openings at both ends, the fastening assembly is located in the anchor plate, the anchor plate is fixedly mounted on the first embedded steel bar, the rear end of the anchor plate is fixedly connected to a connecting plate, the connecting plate is fixedly connected to the tooth plate, and two adjacent anchor plates are fixedly connected via the connecting plate.
[0006] Furthermore, the upper and lower sides of the front end of the anchor assembly are fixedly connected with reinforcement ribs, and the two reinforcement ribs on the anchor plate are respectively horizontally arranged along the width direction of the anchor plate.
[0007] Further, the fastening assembly includes a horizontally arranged sleeve which sequentially passes through a plurality of the anchoring plates along the length direction of the toothed plate. A vertical backing plate is provided at the front end of the sleeve, and a fixing plate is fixedly connected to the rear end of the sleeve. A vertical baffle is provided at the rear side of the fixing plate, and the baffle is fixed at the rear end of the last anchoring plate. Two prestressed steel bars are horizontally arranged in the sleeve. The front ends of the prestressed steel bars horizontally slide through the backing plate, and the rear ends of the prestressed steel bars sequentially pass through the fixing plate and the baffle and are fixedly connected by bolts and nuts.
[0008] Further, spiral steel bars are provided at the rear end of the sleeve, and the spiral steel bars are sleeved on the two prestressed steel bars.
[0009] Further, a waterstop is provided directly below the toothed plate.
[0010] Further, a slag retaining slide plate is provided at the bottom of the toothed plate.
[0011] Further, the first embedded steel bar is in a "冂" shape, and a second embedded steel bar is provided at the lower end of the vertical part of the first embedded steel bar. The second embedded steel bar is horizontally arranged along the width direction of the main beam.
[0012] Further, it further includes two groups of transverse steel bars. The two groups of transverse steel bars are respectively located on the left and right sides of the toothed plate. The number of each group of transverse steel bars is set to three. The three transverse steel bars are horizontally arranged along the width direction of the main beam, and two of the three transverse steel bars are located within the anchoring plates.
[0013] A construction method for an expansion joint of an elevated bridge includes the following steps:
[0014] S1: First, the first embedded steel bar and the second embedded steel bar are pre-embedded in the main beam, and then the main beam and the paving layer are constructed to form a gap of the expansion joint.
[0015] S2: Install the toothed plate, the anchoring assembly, the waterstop and the slag retaining slide plate in the expansion joint. Among them, a plurality of anchoring plates in the anchoring assembly are sequentially arranged along the width of the main beam and erected on the first embedded steel bar, and then the plurality of anchoring plates are sequentially connected by connecting plates and reinforcing rib plates to form a whole. The frontmost anchoring plate abuts against the side wall in the width direction of the main beam, and the anchoring plate is fixedly connected to the toothed plate through the connecting plate.
[0016] S3: Install the sleeve, the prestressed steel bars, the backing plate, the fixing plate and the baffle in the fastening assembly on the anchoring plates respectively. Among them, the front ends of the prestressed steel bars are reserved forward to the side guardrail for setting the tensioning end, and the baffle fixes and seals the rear end of the last anchoring plate.
[0017] S4: Two groups of cross-bars are installed on the left and right sides of the tooth plate respectively, and each group of cross-bars has three bars, two of which are located in the anchor plate and do not interfere with the fastening components;
[0018] S5: After the installation is completed, fill the outside of the anchor plate located in the expansion joint with concrete. After filling, apply stress to the prestressed steel bars from the tensioning end. After the stress is applied, open a grouting port above the frontmost anchor plate, and then fill the inside with concrete through the grouting port by pressure pouring to complete the construction.
[0019] The advantages of the present invention are as follows: the present invention provides a structure of an expansion joint of an elevated bridge and a construction method thereof, and by arranging an anchoring assembly, the construction structure of the existing expansion joint is changed, and the stability is greatly improved; and by splicing a plurality of anchoring plates into an integral structure, the road load borne by the tooth plate can be better dispersed, thereby extending the service life of the expansion joint, reducing the vertical vibration force on the expansion joint caused by the passing of vehicles, and preventing the expansion joint from cracking in the later stage through the fastening assembly, thereby preventing the expansion joint from being damaged, so as to improve driving safety, solve the problem that the expansion joint will crack after years of use and the passing of vehicles, thereby causing the expansion joint to be damaged, and avoid the problem that once the position of the bridge expansion joint is damaged, it will seriously affect the driving speed, comfort and safety, and may cause driving safety accidents in serious cases, thereby achieving the increase of high stress and high stability of the bridge structure through the new expansion joint structure, and improving durability at the same time.
[0020] The present invention is described in detail below with reference to the accompanying drawings and embodiments. BRIEF DESCRIPTION OF THE DRAWINGS
[0021] Figure 1 It is a schematic diagram of the structure of the present invention.
[0022] Figure 2 It is a schematic diagram of the structure of the parts of the anchoring assembly of the present invention.
[0023] Figure 3 It is a schematic diagram of the structure of the fastening assembly parts of the present invention.
[0024] Figure 4 It is an enlarged view of the structure at location A of the present invention.
[0025] Figure 5 It is an enlarged view of the structure at B of the present invention.
[0026] Explanation of the accompanying reference numerals: 1. Main beam; 2. Gap; 3. Pavement layer; 4. First embedded steel bar; 5. Tooth plate; 6. Anchor assembly; 61. Anchor plate; 62. Connecting plate; 63. Reinforcement rib; 7. Fastening assembly; 71. Casing; 72. Pad; 73. Fixing plate; 74. Baffle; 75. Prestressed steel bar; 76. Spiral steel bar; 8. Waterstop; 9. Slag retaining plate; 10. Second embedded steel bar; 11. Cross steel bar. DETAILED DESCRIPTION
[0027] In order to further explain the technical means and effects adopted by the present invention to achieve the predetermined purpose, the specific implementation methods, structural features and effects of the present invention are described in detail below in conjunction with the accompanying drawings and embodiments.
[0028] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0029] In the description of the present invention, it is necessary to understand that the terms "center", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "aligned", "overlap", "bottom", "inside", "outside" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the referred device or element must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present invention.
[0030] The terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Therefore, the features defined as "first" and "second" may explicitly or implicitly include one or more of the features; in the description of the present invention, unless otherwise specified, "plurality" means two or more.
[0031] Example 1
[0032] This embodiment provides Figure 1 to Figure 5The structure of an expansion joint for an elevated bridge is shown, which is arranged in the gap 2 between two adjacent main girders 1. The upper surfaces of the two main girders 1 are both paved with a paving layer 3. The distance between the two paving layers 3 is greater than the distance between the two main girders 1. A row of first embedded steel bars 4 is embedded in each of the two main girders 1, including a toothed plate 5 arranged in the gap 2. The toothed plate 5 is horizontally arranged from front to back along the length direction of the gap 2. Anchor components 6 are provided on both the left and right sides of the toothed plate 5. The toothed plate 5 is fixedly connected to the first embedded steel bar 4 through the anchor components 6. A fastening component 7 is provided on the anchor component 6. The part of the main girder 1 between the paving layer 3 and the gap 2 is filled with concrete, and among them, the concrete is C50 steel fiber concrete.
[0033] Further, the anchor component 6 is composed of a number of anchor plates 61 with a rectangular vertical cross-section spliced in sequence from front to back. The anchor plates 61 are horizontally arranged along the length direction of the toothed plate 5. The anchor plates 61 are hollow and open at both the front and rear ends. The fastening component 7 is located inside the anchor plates 61. The anchor plates 61 are fixedly placed on the first embedded steel bar 4. A connecting plate 62 is fixedly connected to the rear end of the anchor plate 61. The connecting plate 62 is fixedly connected to the toothed plate 5, and two adjacent anchor plates 61 are fixedly connected through the connecting plate 62.
[0034] Further, reinforcing rib plates 63 are fixedly connected to both the upper and lower sides of the front end of the anchor component 6. The two reinforcing rib plates 63 on the anchor plate 61 are horizontally arranged along the width direction of the anchor plate 61 respectively.
[0035] Further, the fastening component 7 includes a horizontally arranged sleeve 71. The sleeve 71 sequentially passes through a number of anchor plates 61 along the length direction of the toothed plate 5. A vertical backing plate 72 is provided at the front end of the sleeve 71. A fixing plate 73 is fixedly connected to the rear end of the sleeve 71. A vertical baffle 74 is provided at the rear side of the fixing plate 73. The baffle 74 is fixed at the rear end of the last anchor plate 61. Two prestressed steel bars 75 are horizontally arranged inside the sleeve 71. The front ends of the prestressed steel bars 75 horizontally slide through the backing plate 72. The rear ends of the prestressed steel bars 75 sequentially pass through the fixing plate 73 and the baffle 74 and are fixedly connected through bolts and nuts.
[0036] Further, a spiral steel bar 76 is provided at the rear end of the sleeve 71. The spiral steel bar 76 is sleeved on the two prestressed steel bars 75.
[0037] Further, a water stop 8 is provided directly below the toothed plate 5.
[0038] Further, a slag retaining slide plate 9 is provided at the bottom of the toothed plate 5.
[0039] Further, the first embedded steel bar 4 is in a "冂" shape, and a second embedded steel bar 10 is provided at the lower end of the vertical part of the first embedded steel bar 4. The second embedded steel bar 10 is horizontally arranged along the width direction of the main girder 1.
[0040] Further, it further includes two groups of transverse steel bars 11, which are respectively located on the left and right sides of the tooth plate 5. The number of each group of transverse steel bars 11 is set to three, and the three transverse steel bars 11 are horizontally arranged along the width direction of the main beam 1, and two of the three transverse steel bars 11 are located within the anchoring plate 61.
[0041] A construction method for an expansion joint of an elevated bridge includes the following steps:
[0042] S1: First, embed the first embedded steel bar 4 and the second embedded steel bar 10 in the main beam 1, and then construct and build the main beam 1 and the paving layer 3 to form the gap 2 of the expansion joint;
[0043] S2: Install the tooth plate 5, the anchoring assembly 6, the water stop belt 8 and the slag retaining slide plate 9 in the expansion joint. Among them, several anchoring plates 61 in the anchoring assembly 6 are arranged in sequence along the width of the main beam 1 and are erected on the first embedded steel bar 4, and then connect several anchoring plates 61 in sequence through the connecting plate 62 and the reinforcing rib plate 63 to form a whole. The frontmost anchoring plate 61 abuts against the side wall in the width direction of the main beam 1, and the anchoring plate 61 is fixedly connected to the tooth plate 5 through the connecting plate 62;
[0044] S3: Install the sleeve 71, the prestressed steel bar 75, the backing plate 72, the fixing plate 73 and the baffle plate 74 in the fastening assembly 7 on the anchoring plate 61 respectively. Among them, the front end of the prestressed steel bar 75 is reserved forward to the side guardrail for setting the tensioning end, and the baffle plate 74 fixes and seals the rear end of the rearmost anchoring plate 61;
[0045] S4: Install the two groups of transverse steel bars 11 on the left and right sides of the tooth plate 5 respectively, and each group of transverse steel bars 11 has three. Two of each group are located within the anchoring plate 61 and do not interfere with the fastening assembly 7;
[0046] S5: After the installation is completed, fill the outside of the anchoring plate 61 located in the expansion joint with concrete. After filling, apply stress to the prestressed steel bar 75 from the tensioning end. After the application is completed, open a grouting port above the frontmost anchoring plate 61, and then fill the inside of it with concrete by means of pressure grouting from the grouting port to complete the construction.
[0047] During use, first, embed the first embedded steel bar 4 and the second embedded steel bar 10 in the main beam 1. The first embedded steel bar 4 is in a "冂" shape, and the second embedded steel bar 10 is provided at the lower end of the vertical part of the first embedded steel bar 4. The second embedded steel bar 10 is horizontally arranged along the width direction of the main beam 1. Then, construct and build the main beam 1 and the paving layer 3 to form the gap 2 of the expansion joint. Among them, the paving layer 3 is laid on the upper surfaces of the two main beams 1, and the distance between the two paving layers 3 is greater than the distance between the two main beams 1;
[0048] Then, the tooth plate 5, the anchor assembly 6, the water stop strip 8 and the slag retaining plate 9 are installed in the expansion joint, the slag retaining plate 9 is arranged at the bottom of the tooth plate 5, and the water stop strip 8 is arranged in the gap 2 between two adjacent main beams 1, wherein a plurality of anchor plates 61 in the anchor assembly 6 are sequentially arranged along the width of the main beam 1 and laid on the first embedded steel bar 4, and then a plurality of anchor plates 61 are sequentially connected to form a whole through the connecting plate 62 and the reinforcing rib plate 63, the frontmost anchor plate 61 abuts against the side wall of the main beam 1 in the width direction, and the anchor plate 61 is fixedly connected to the tooth plate 5 through the connecting plate 62, so that the main beam 1, the first embedded steel bar 4, the anchor assembly 6 and the tooth plate 5 are fixed together to form a whole, thereby improving the stability of the bridge;
[0049] Secondly, the sleeve 71, prestressed steel bar 75, pad 72, fixing plate 73 and baffle 74 in the fastening assembly 7 are respectively installed on the anchor plate 61, and the front end of the prestressed steel bar 75 is reserved forward to the side guardrail for setting the tensioning end, and the baffle 74 fixes and seals the rear end of the last anchor plate 61, wherein the sleeve 71 can not only prevent the concrete from fixing the prestressed steel bar 75 during the first pouring of concrete, so that the prestressed steel bar 75 cannot be stressed after the first filling of cement, but the sleeve 71 can also cooperate with the fixing plate 73 to prevent the prestressed steel bar 75 from damaging the sleeve 71 when the prestressed steel bar 75 is passed through the fixing plate 73 and fixed by bolts and nuts, and a spiral steel bar 76 is provided at the rear end of the sleeve 71, and the spiral steel bar 76 is sleeved on the two prestressed steel bars 75, and is used to limit and fix the fixed end of the prestressed steel bar 75 when stress is applied to the prestressed steel bar 75;
[0050] In addition, two groups of transverse steel bars 11 are included, and the two groups of transverse steel bars 11 are respectively located on the left and right sides of the tooth plate 5. The two groups of transverse steel bars 11 are respectively installed on the left and right sides of the tooth plate 5, and each group of transverse steel bars 11 has three steel bars, and two of them in each group are located in the anchor plate 61 and do not interfere with the fastening assembly 7.
[0051] Finally, after the installation is completed, the outside of the anchor plate 61 located in the expansion joint is filled with concrete. After filling, stress is applied to the prestressed steel bars 75 from the tensioning end. After the application is completed, a grouting port is opened above the front end anchor plate 61, and then the concrete is filled inside through pressure pouring from the grouting port to complete the construction.
[0052] In summary, the present invention provides a structure of an expansion joint of an elevated bridge and a construction method thereof. By arranging an anchoring assembly 6, the construction structure of the existing expansion joint is changed, and the stability is greatly improved. Moreover, by splicing a plurality of anchoring plates 61 into an integral structure, the road load on the tooth plate 5 can be better dispersed, thereby extending the service life of the expansion joint and reducing the vertical vibration force on the expansion joint caused by the passing of vehicles. Furthermore, by means of the fastening assembly 7, cracks are prevented from being generated in the expansion joint in the later stage, thereby preventing the expansion joint from being damaged, so as to improve driving safety, solve the problem that cracks will be generated in the expansion joint after long-term use, which will eventually lead to the damage of the expansion joint, and avoid the problem that once the expansion joint position of the bridge is damaged, the driving speed, comfort and safety will be seriously affected, and in serious cases, driving safety accidents may be caused, thereby achieving the high stress and high stability of the bridge structure through the new expansion joint structure, while improving the durability.
[0053] The above contents are further detailed descriptions of the present invention in combination with specific preferred embodiments, and it cannot be determined that the specific implementation of the present invention is limited to these descriptions. For ordinary technicians in the technical field to which the present invention belongs, several simple deductions or substitutions can be made without departing from the concept of the present invention, which should be regarded as falling within the protection scope of the present invention.
Claims
1. A structure of an expansion joint of an elevated bridge, which is arranged in a gap (2) between two adjacent main beams (1), wherein a paving layer (3) is laid on the upper surface of the two main beams (1), the spacing between the two paving layers (3) is greater than the spacing between the two main beams (1), and a row of first pre-embedded steel bars (4) is pre-embedded in the two main beams (1), characterized in that: It includes a toothed plate (5) arranged in the gap (2). The toothed plate (5) is horizontally arranged from front to back along the length direction of the gap (2). Anchor components (6) are provided on both the left and right sides of the toothed plate (5). The toothed plate (5) is fixedly connected to the first embedded steel bar (4) through the anchor components (6), and a fastening component (7) is provided on the anchor components (6).
2. The structure of an expansion joint of an elevated bridge according to claim 1, characterized in that: The anchor component (6) is composed of a number of anchor plates (61) with a rectangular vertical cross-section spliced in sequence from front to back. The anchor plates (61) are horizontally arranged along the length direction of the toothed plate (5). The anchor plates (61) are hollow and open at both the front and rear ends. The fastening component (7) is located inside the anchor plates (61). The anchor plates (61) are fixedly laid on the first embedded steel bar (4). A connecting plate (62) is fixedly connected to the rear end of the anchor plate (61). The connecting plate (62) is fixedly connected to the toothed plate (5), and two adjacent anchor plates (61) are fixedly connected through the connecting plate (62).
3. The structure of an expansion joint of an elevated bridge as claimed in claim 2, characterized in that: Reinforcing rib plates (63) are fixedly connected to both the upper and lower sides of the front end of the anchor component (6). The two reinforcing rib plates (63) on the anchor plate (61) are horizontally arranged along the width direction of the anchor plate (61) respectively.
4. The structure of an expansion joint of an elevated bridge as claimed in claim 2, characterized in that: The fastening component (7) includes a horizontally arranged sleeve (71). The sleeve (71) sequentially passes through a number of the anchor plates (61) along the length direction of the toothed plate (5). A vertical backing plate (72) is provided at the front end of the sleeve (71). A fixing plate (73) is fixedly connected to the rear end of the sleeve (71). A vertical baffle (74) is provided at the rear side of the fixing plate (73). The baffle (74) is fixed at the rear end of the last anchor plate (61). Two prestressed steel bars (75) are horizontally arranged inside the sleeve (71). The front ends of the prestressed steel bars (75) horizontally slide through the backing plate (72). The rear ends of the prestressed steel bars (75) sequentially pass through the fixing plate (73) and the baffle (74) and are fixedly connected through bolts and nuts.
5. The structure of an expansion joint of an elevated bridge as claimed in claim 4, characterized in that: A spiral steel bar (76) is provided at the rear end of the sleeve (71). The spiral steel bar (76) is sleeved on the two prestressed steel bars (75).
6. The structure of an expansion joint of an elevated bridge according to claim 1, characterized in that: A water stop belt (8) is provided directly below the toothed plate (5).
7. The structure of an expansion joint of an elevated bridge according to claim 1, characterized in that: A slag blocking slide plate (9) is provided at the bottom of the toothed plate (5).
8. The structure of an expansion joint of an elevated bridge as claimed in claim 1, characterized in that: The first embedded steel bar (4) is in a "冂" shape. A second embedded steel bar (10) is provided at the lower end of the vertical part of the first embedded steel bar (4). The second embedded steel bar (10) is horizontally arranged along the width direction of the main beam (1).
9. The structure of an expansion joint of an elevated bridge as claimed in claim 2, characterized in that: It also includes two groups of transverse steel bars (11). The two groups of transverse steel bars (11) are respectively located on the left and right sides of the toothed plate (5). The number of each group of transverse steel bars (11) is set to three. The three transverse steel bars (11) are horizontally arranged along the width direction of the main beam (1), and two of the transverse steel bars (11) are located inside the anchor plate (61).
10. A construction method for an expansion joint of an elevated bridge, characterized in that: It includes the following steps: S1: first, pre-embed a first pre-embedded steel bar (4) and a second pre-embedded steel bar (10) in the main beam (1), and then construct a gap (2) between the main beam (1) and the pavement layer (3) to form an expansion joint; S2: Install the tooth plate (5), the anchor assembly (6), the water stop strip (8) and the slag retaining plate (9) in the expansion joint, wherein a plurality of anchor plates (61) in the anchor assembly (6) are sequentially arranged along the width of the main beam (1) and laid on the first embedded steel bar (4), and then the plurality of anchor plates (61) are sequentially connected through the connecting plate (62) and the reinforcing rib plate (63) to form a whole, the frontmost anchor plate (61) abuts against the side wall of the main beam (1) in the width direction, and the anchor plate (61) is fixedly connected to the tooth plate (5) through the connecting plate (62); S3: The sleeve (71), the prestressed steel bar (75), the pad (72), the fixing plate (73) and the baffle (74) in the fastening assembly (7) are respectively installed on the anchor plate (61), wherein the front end of the prestressed steel bar (75) is reserved forward to the side guardrail for setting the tensioning end, and the baffle (74) fixes and seals the rear end of the rearmost anchor plate (61); S4: installing two groups of transverse steel bars (11) on the left and right sides of the tooth plate (5), respectively, and each group of transverse steel bars (11) has three steel bars, two of which are located in the anchor plate (61) and do not interfere with the fastening assembly (7); S5: After the installation is completed, the outside of the anchor plate (61) located in the expansion joint is filled with concrete. After the filling is completed, stress is applied to the prestressed steel bar (75) from the tensioning end. After the stress is applied, a grouting port is opened above the frontmost anchor plate (61), and then concrete is poured from the grouting port to fill the inside by pressure pouring to complete the construction.
Citation Information
Patent Citations
Post-tensioned prestressing underground diaphragm wall and construction method
CN103835311A
Telescopic device
CN105803935A
Simply-supported welding low-noise / dustproof / waterproof comb-tooth-shaped telescopic device and construction method thereof
CN117144789A
Bridge expansion joint device
CN209211262U
Cold-resistant expansion joint device
CN213836283U
Cited By
Expansion joint structure for bridge construction and construction method thereof