Intelligent guidance system and method for shallow solidification construction
Through real-time monitoring and feedback of digital site and equipment models of the intelligent guidance system, the problems of low construction depth deviation and reliability in shallow soft foundation reinforcement construction are solved, precise control of construction depth and coverage area is achieved, and construction efficiency is improved and quality.
Patent Information
- Application Number
- CN202411047517.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-01
- Publication Date
- 2024-11-29
AI Technical Summary
During shallow soft foundation reinforcement construction, operators cannot intuitively monitor the progress and quality of underground construction, resulting in construction depth deviation, material waste and reduced construction reliability.
The intelligent guidance system is adopted to establish digital site models and digital equipment models, and real-time collection and feedback of construction data is provided, accurate construction guidance and quality evaluation are provided, ensuring accurate control of construction depth and coverage area.
It reduces construction depth deviation and repeated construction phenomena, improves construction efficiency, avoids material waste, and improves construction reliability and quality.
Smart Images

Figure CN119041391A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of shallow soft foundation reinforcement treatment, and in particular to an intelligent guiding system and method for shallow layer solidification construction. Background Art
[0002] Shallow solidification construction equipment uses a mixing head to treat soft foundations at a depth of 0-7 meters, and uses a mechanical structure to mix the solidification material and soft clay evenly to reinforce the foundation. Usually, due to the huge volume of project reinforcement treatment in the project, omissions or repeated construction are prone to occur on the construction surface during construction, and reasonable planning of the construction scope on site takes a lot of time and cannot be accurately controlled. Because the mixing head is mixing underground, the operator cannot intuitively see the completion of the reinforcement construction, especially for the mixing depth of the mixing head, the number of mixing times and the coverage rate of the overall coverage area are difficult to accurately control;
[0003] The existing shallow soft foundation reinforcement construction equipment and construction methods have the following defects:
[0004] 1) Construction depth deviation, missing reinforcement volume or repeated construction often occur during construction. Excessive construction depth will cause material waste and reduced work efficiency. Too shallow construction depth will lead to poor reinforcement treatment effect, resulting in excessive and uneven settlement of the treated foundation.
[0005] 2) Operators are prone to make operational errors due to long-term repetitive operations. Since the construction work is carried out below the ground, it is difficult to detect construction quality problems, resulting in reduced construction reliability. Summary of the invention
[0006] The technical problem to be solved by the present invention is how to overcome the problem that operators are unable to detect the quality of underground construction and cannot accurately know the progress and status of underground construction. In order to overcome the defects of the above-mentioned prior art, the present invention provides an intelligent guidance system and method for shallow solidification construction.
[0007] The present invention provides an intelligent guidance system for shallow layer solidification construction, which is used to guide an operator to interact with shallow layer solidification construction equipment to complete a shallow layer solidification construction project. The intelligent guidance system includes a human-machine interaction display module, a controller, a data acquisition module, a site grid generation module, a construction quality evaluation module, a central operation module and a local database;
[0008] The human-machine interactive display module interacts with the operator, and the operator operates the shallow curing construction equipment through the controller to control the movement of the shallow curing construction equipment on the construction site and the shallow curing construction; the human-machine interactive display module is mainly used to display and feedback the data information of the operator controlling the shallow curing construction equipment to operate on the construction site;
[0009] The shallow layer solidification construction equipment is provided with a data acquisition module for collecting construction data information of the shallow layer solidification construction equipment, wherein the construction data information includes the center coordinates of the mixing equipment, the center coordinates of the mixing head of the mixing equipment, the rotation speed of the mixing head, the working temperature of the mixing head, the torque of the mixing head, the pressure of the feed pipe on the feeding equipment, and the flow rate of the solidified material in the feed pipe;
[0010] The site grid generation module is used to establish a digital site model that maps the construction site, and divide the digital site model into m×n×l three-dimensional construction grid bodies according to the construction requirement parameter information, and calculate the vertex coordinates and center coordinates of each three-dimensional construction grid body; the site grid generation module is connected to the human-computer interaction screen display module to display the digital site model after grid division; the site grid generation module is connected to the local database to store the digital site module;
[0011] The central operation module is connected to the data acquisition module to establish a digital equipment model that maps the shallow solidification construction equipment. The central operation module is connected to the local database to obtain the digital site model, and establishes an association between the digital equipment model and the digital site model according to the data acquisition module; the central operation module includes a model mapping unit for establishing the digital equipment model, a projection calculation unit for calculating the effective construction area of the shallow solidification construction equipment according to the digital equipment model, a construction trajectory calculation unit for dividing the three-dimensional construction grid in the digital site model into columnar construction units according to the effective construction area and generating a construction trajectory, and a working condition mapping unit for calculating and recording the construction condition of the digital equipment model on the digital site model according to the data acquisition module and the construction trajectory. The central operation module is connected to the human-computer interaction screen display module to display the construction condition of the digital equipment model on the construction site model.
[0012] Compared with the prior art, the intelligent guidance system for shallow solidification construction in the present application has the following advantages: a digital site model mapping the construction site and a digital equipment model mapping the shallow solidification construction equipment are established, and the relative positions of the digital site model and the digital equipment model are matched and associated. Then, the operator controls the operation data of the shallow solidification construction equipment through a controller and feeds it back to the operator through a data acquisition module, thereby providing the operator with guidance services for entering and exiting the shallow solidification construction, thereby reducing the depth deviation and repeated construction phenomena that often occur during construction, and avoiding material waste caused by excessive construction depth, while improving work efficiency.
[0013] In a possible implementation, the shallow layer solidification construction equipment includes a mechanical arm on a mixing device, a mixing head on the mechanical arm, a walking mechanism on the mixing device, a feeding device, and a feeding pipe for conveying the solidified material on the feeding device to the mixing device.
[0014] In a possible implementation, the construction requirement parameter information includes: construction site coordinates, construction depth, three-dimensional construction grid plane side length, three-dimensional construction grid depth, set curing material dosage of the three-dimensional construction grid, and set stirring times of the three-dimensional construction grid.
[0015] In one possible embodiment, the data acquisition module includes a satellite positioning sensor provided on the mixing equipment, multiple inclination sensors provided on the robotic arm, a satellite positioning sensor provided on the mixing head, a rotary encoder, a hydraulic oil flow sensor, a hydraulic oil pressure sensor, a hydraulic oil temperature sensor, a mixing head speed sensor, a feed pipe pressure sensor provided on the feed pipe, a feed pipe flow sensor and a background weighing sensor provided on the feeding equipment.
[0016] In one possible implementation, the intelligent guidance system also includes a construction quality evaluation module, which is connected to a local database and is used to calculate the construction progress and construction quality indicators of each three-dimensional construction grid body. The construction quality evaluation module is connected to a human-computer interaction screen display module to synchronously display the construction progress and construction quality indicators of the corresponding three-dimensional construction grid body.
[0017] An intelligent guidance method of an intelligent guidance system for shallow layer solidification construction based on any one of the above items, comprising:
[0018] S1. Establishing a digital site model based on the characteristic information of the construction site, and establishing a digital equipment model based on the shallow solidification construction equipment; the characteristic information of the construction site includes boundary characteristics, coordinate characteristics and geological characteristics;
[0019] S2. The operator inputs construction requirement parameter information according to the geological information of the construction site, and the construction requirement parameter information includes: construction site coordinates, construction depth, plane side length of the three-dimensional construction grid body, depth of the three-dimensional construction grid body, set curing material dosage of the three-dimensional construction grid body and set stirring times of the three-dimensional construction grid body; the site grid generation module establishes a three-dimensional coordinate system according to the digital site model, and divides the digital site model into m×n×l three-dimensional construction grid bodies according to the construction requirement parameter information, and numbers each construction unit in the form of (i, p, o), i represents the number of rows on the construction surface, p represents the number of columns on the construction surface, and o represents the sequence number in the construction depth direction; calculates the vertex coordinates and center coordinates of each three-dimensional construction grid body; saves and displays it through the human-computer interaction screen display module;
[0020] S3. Establishing the correlation matching between the digital equipment model and the digital site model in the coordinate position according to the coordinate position of the shallow curing construction equipment collected by the data acquisition module and the coordinate features on the digital site model; enabling the operator to accurately understand the current shallow curing construction equipment position on the construction site through the human-computer interaction screen display module;
[0021] S4. Obtain the three-dimensional construction grid body to be constructed, and use all the three-dimensional construction grid bodies (i,p,1), (i,p,2)…(i,p,o)…(i,p,l) in the depth direction as the construction grid group; the operator controls the shallow solidification construction equipment to move to the three-dimensional construction grid body (i,p,1) through the controller;
[0022] S5. Calculate the effective construction area S1 of the mixing head at a time, and divide it twice on the horizontal plane of the three-dimensional construction grid group according to the effective construction area S1, and divide it into s×t columnar construction units. The depth of each columnar construction unit is consistent with the construction depth, and the s×t columnar construction units are numbered and sorted 1, 2, 3...s×t; and calculate the center coordinates of each columnar construction unit and set the amount of solidifying material; and perform solidifying material injection and stirring on each columnar construction unit according to the construction sequence; preset the number U of columnar construction units that have completed stirring and injection, and initialize U=0;
[0023] S6. Calculate the displacement of the mixing head according to the change of the center coordinate of the mixing head and display the horizontal direction guidance information on the human-machine interactive screen display module. The operator controls and adjusts the robotic arm through the controller so that the mixing head moves to the center coordinate of the kth columnar construction unit.
[0024] S7. The mixing equipment performs solidification material injection and mixing work on the kth columnar construction unit according to the construction requirement parameter information; the displacement of the mixing head is calculated according to the change of the center coordinate of the mixing head and the vertical direction guidance information is displayed on the human-computer interaction screen display module. The operator controls and adjusts the mechanical arm through the controller to move the mixing head to the bottom of the kth columnar construction unit; it is determined whether the mixing head reaches the bottom of the kth columnar construction unit according to the displacement, if so, enter S8; if not, return to S7;
[0025] S8. Mark the current columnar construction unit as completed, add the number of columnar construction units U=U+1, and judge whether U≥s×t is satisfied. If so, mark the current construction grid group as completed, and evaluate the construction quality of each three-dimensional construction grid body of the construction grid group according to the set curing material dosage and the cumulative curing material injection volume of the three-dimensional construction grid body, as well as the set stirring times and the cumulative stirring times, and enter S9; if not satisfied, k=k+1, and return to S6;
[0026] S9. Perform Manhattan distance calculation based on the plane position (i, p) of the completed construction grid group and the plane position of the adjacent unconstructed construction grid group to obtain all selected paths, and select the path with the shortest distance as the optimal path, and sort the construction grid groups in the path; and perform S4-S8 operations on the construction grid groups in the path in turn to complete the construction of the current construction site.
[0027] Compared with the prior art, the intelligent guidance method for shallow solidification construction of the present invention has the following advantages: by establishing a digital site model that maps the construction site and a digital equipment model that maps the shallow solidification construction equipment, and by matching the relative positions of the associated digital site model and the digital equipment model, when the operator controls the mobile shallow solidification construction equipment, the position of the digital equipment on the digital site model is updated in real time through the data acquisition module, thereby realizing two-way control of the operator, the digital equipment model and the digital scene model, providing the operator with precise regulation and feedback when controlling the shallow solidification construction equipment to perform shallow solidification construction, so that the operator can grasp the construction progress of the entire construction site and the construction quality.
[0028] In a possible implementation manner, step 4 specifically includes:
[0029] S401. The operator controls the movement of the shallow curing construction equipment through the controller, and the data acquisition module collects the coordinate information of the shallow curing construction equipment in real time;
[0030] S402. Update the position of the digital equipment model on the digital site model according to the coordinate information of the shallow solidification construction equipment collected in S401 and the coordinate features on the digital site model, save it and display it through the human-computer interaction interface;
[0031] S403. By comparing the coordinate information of the shallow solidification construction equipment with the coordinates of each vertex of the three-dimensional construction grid (i, p, 1), it is determined whether the shallow solidification construction equipment has reached the three-dimensional construction grid (i, p, 1). If so, proceed to S404; if not, return to S401;
[0032] S404. Use a reminder to remind the operator that the shallow layer curing construction equipment is in place.
[0033] In a possible implementation, the calculation of the effective construction area S1 of the mixing head in a single time in S5 specifically includes: calculating the coordinates (X0, Y0) of the reference point of the center of the mixing head, which can further deduce the coordinates of the four corners of the mixing head on the horizontal plane X1 (X+a, Y+b), X2 (Xa, Yb), X3 (X+a, Yb) and X4 (Xa, Y+b), and determine their projected shape area, thereby determining the effective construction area S1 of the mixing head in a single time; wherein a represents the horizontal projection width of the mixing head, and b represents the horizontal projection length of the mixing head.
[0034] In a possible implementation manner, the S6 specifically includes:
[0035] S601. The operator controls and adjusts the robotic arm through the controller;
[0036] S602. The data acquisition module collects the horizontal inclination angle of each segment of the robot arm, the pitch and roll angles of the shallow solidification construction equipment, and the center coordinates of the mixing head in real time, and calculates the relative elevation relationship between each reference point of the robot arm and the construction equipment, the absolute elevation coordinates, and the coordinates of the mixing head
[0037] S603. Update the posture of the robot arm in the digital equipment model according to the relative elevation relationship and absolute elevation coordinates of each reference point of the robot arm and the construction equipment;
[0038] S604. Determine whether the mixing head has moved to the kth columnar construction unit by comparing the center coordinates of the mixing head with the center coordinates of the kth columnar construction unit. If so, remind the operator through a prompter that the mixing head is in place and enter S7; if not, return to S601.
[0039] In one possible implementation,
[0040] The step S8 of evaluating the construction quality of each three-dimensional construction grid body of the construction grid group according to the set curing material dosage and the cumulative injection amount of the curing material of the three-dimensional construction grid body specifically includes:
[0041] The quality score coefficient R of the three-dimensional construction grid is:
[0042] R=R1 0.7 ×R2 2.3
[0043] R1 is the cumulative stirring times of the stirring head. When N>350, R1=1; when 300<N<350, 0.8<R1<1; when 250<N<300, 0.6<R1<0.8; when 200<N<250, 0.5<R1<0.6;
[0044] R2 is the achieved value of the actual ash content PV and the target design value SV:
[0045] R2=PV / SV
[0046] The scoring table generated by the formula is used to mark the three-dimensional construction grid body. R below 0.6 is unqualified, R above 0.6 is qualified, R above 0.8 is good, and R above 0.9 is excellent. BRIEF DESCRIPTION OF THE DRAWINGS
[0047] Figure 1is a system structure diagram of a specific embodiment 1 of the present invention;
[0048] Figure 2A / Figure 2B A hardware implementation scheme for the human-machine interactive guidance system in the specific embodiment 1 of the present invention to interact with the operator in the cab;
[0049] Figure 3 It is a structural diagram of shallow layer solidification construction equipment in specific embodiment 1 of the present invention;
[0050] Figure 4 It is a schematic diagram of gridding a construction site in specific embodiment 2 of the present invention;
[0051] Figure 5 The construction path display of the columnar construction unit on the three-dimensional construction grid body in the specific embodiment 2 of the present invention;
[0052] Figure 6 It is a schematic diagram of the movement path guidance of shallow layer solidification construction equipment by the human-machine interactive guidance system in the specific embodiment 2 of the present invention;
[0053] Figure 7 The scoring table of the quality qualification scoring coefficient R in the specific embodiment 2 of the present invention.
[0054] Description of reference numerals:
[0055] 100. Central controller; 101. Satellite positioning unit; 102. Posture sensing unit; 103. Mixing head power monitoring unit; 104. Human-machine interaction guidance system; 105. Operator; 106. Robotic arm; 107. Walking mechanism; 108. Mixing head; 109. Driver's cab; 110. Construction site; 201. Short-focus projection equipment; 202. Human-machine interaction guidance display interface; 203. Operating handle; 204. Optical polarization refractive film; 301. Digital grid of the construction site; 302. Limited construction scope of the construction site; 400. Digital grid facing the operator; 401. Speed guidance information; 402. Curing agent guidance information; 403. Current position of the mixing head; 404. Position of the mixing head at the next moment; 405. Direction guidance information. DETAILED DESCRIPTION
[0056] First, those skilled in the art should understand that these implementations are only used to explain the technical principles of the embodiments of the present application, and are not intended to limit the protection scope of the embodiments of the present application. Those skilled in the art can make adjustments to them as needed to adapt to specific application scenarios.
[0057] In the description of the embodiments of the present application, it should be noted that, unless otherwise clearly specified and limited, the terms "connected" and "connection" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be directly connected or indirectly connected through an intermediate medium. For ordinary technicians in this field, the specific meanings of the above terms in the embodiments of the present application can be understood according to specific circumstances.
[0058] In the embodiments of the present application, unless otherwise clearly specified and limited, a first feature being "above" or "below" a second feature may mean that the first and second features are in direct contact, or the first and second features are in indirect contact through an intermediate medium. Moreover, a first feature being "above", "above" or "above" a second feature may mean that the first feature is directly above or obliquely above the second feature, or simply means that the first feature is higher in level than the second feature. A first feature being "below", "below" or "below" a second feature may mean that the first feature is directly below or obliquely below the second feature, or simply means that the first feature is lower in level than the second feature.
[0059] The present application is further described in detail below with reference to the accompanying drawings and specific embodiments. Specific embodiment 1
[0061] See also Figure 1 As shown in Figure 2, the embodiment of the present application discloses an intelligent guidance system for shallow solidification construction, which is used to guide the operator to interact with the shallow solidification construction equipment to complete the shallow solidification construction project. The intelligent guidance system includes a human-computer interaction display module, a controller, a data acquisition module, a site grid generation module, a central operation module and a local database;
[0062] The human-machine interactive screen display module interacts with the operator, and the operator operates the shallow solidification construction equipment through the controller to control the shallow solidification construction equipment to move and construct on the construction site; the human-machine interactive screen display module is mainly used to display and feedback the data information of the operator controlling the shallow solidification construction equipment to operate on the construction site; in this specific embodiment, the shallow solidification construction equipment includes a mechanical arm on the mixing equipment, a mixing head on the mechanical arm, a walking mechanism on the mixing equipment, a feeding device, and a feeding pipe for conveying the solidified material on the feeding device to the mixing equipment; the construction requirement parameter information includes: construction site coordinates, construction depth, plane side length of the three-dimensional construction grid body, depth of the three-dimensional construction grid body, set curing material dosage of the three-dimensional construction grid body, and set stirring times of the three-dimensional construction grid body;
[0063] The shallow solidification construction equipment is provided with a data acquisition module for collecting construction data information of the shallow solidification construction equipment, and the data acquisition module includes a satellite positioning sensor provided on the mixing equipment, a plurality of inclination sensors provided on the mechanical arm, a satellite positioning sensor provided on the mixing head, a rotary encoder, a hydraulic oil flow sensor, a hydraulic oil pressure sensor, a hydraulic oil temperature sensor, a mixing head speed sensor, an ash conveying pipe pressure sensor provided on the ash conveying pipe, an ash conveying pipe flow sensor and a background weighing sensor provided on the feeding equipment; the construction data information includes the center coordinates of the mixing equipment, the center coordinates of the mixing head on the mixing equipment, the mixing head speed, the mixing head working temperature, the mixing head torque, the pressure of the feeding pipe on the feeding equipment and the flow rate of the solidified material in the feeding pipe;
[0064] The site grid generation module is used to establish a digital site model that maps the construction site, and divide the digital site model into m×n×l three-dimensional construction grid bodies according to the construction requirement parameter information, and calculate the vertex coordinates and center coordinates of each three-dimensional construction grid body; the site grid generation module is connected to the human-computer interaction screen display module to display the digital site model after grid division; the site grid generation module is connected to the local database to store the digital site module;
[0065] The central operation module is connected to the data acquisition module to establish a digital equipment model that maps the shallow solidification construction equipment. The central operation module is connected to the local database to obtain the digital site model, and the association between the digital equipment model and the digital site model is established according to the data acquisition module; the central operation module includes a model mapping unit for establishing the digital equipment model, a projection calculation unit for calculating the effective construction area of the shallow solidification construction equipment according to the digital equipment model, a construction trajectory calculation unit for dividing the three-dimensional construction grid in the digital site model into columnar construction units according to the effective construction area and generating a construction trajectory, and a working condition mapping unit for calculating and recording the construction working condition of the digital equipment model on the digital site model according to the data acquisition module and the construction trajectory. The central operation module is connected to the human-computer interaction screen display module to display the construction working condition of the digital equipment model on the construction site model;
[0066] It also includes a construction quality evaluation module, which is connected to a local database and is used to calculate the construction progress and construction quality indicators of each three-dimensional construction grid body. The construction quality evaluation module is connected to a human-computer interaction screen display module to synchronously display the construction progress and construction quality indicators of the corresponding three-dimensional construction grid body.
[0067] Combined with actual construction cases, Figure 3As shown, this specific embodiment uses a 20-30 ton excavator as the main construction bearing equipment, equipped with a mechanical arm 106 and a crawler-type walking mechanism 107; an operator 105 in the cockpit 109 uses the buttons and operating levers integrated on the central controller 100 to control the mechanical arm and walking mechanism of the shallow solidification construction equipment, thereby adjusting the construction process of the soft foundation treatment. The central operation module generates a digital equipment model mapping the shallow solidification construction equipment based on the data acquisition module including the satellite positioning unit 101, the posture perception unit 102, and the mixing head power monitoring unit 103, and feeds back the working status of the shallow reinforcement construction equipment in the physical world to the operator through the human-computer interaction guidance system 104 through the data acquisition module; and gives the construction direction and mixing power of the mixing head 108 at the next moment in the human-computer interaction guidance display interface, and guides the operator to operate the central controller to complete the solidification treatment construction of the construction site 110.
[0068] The presentation and interaction forms of the system of the present invention are not limited to the use of this hardware architecture. The human-computer interaction display module can realize various types of interactive projection technologies, which may include VR glasses or helmets, liquid crystal displays, and optical projections, and can also be connected and used with other portable electronic devices. Figure 2A / Figure 2B The figure shows an implementation scheme of a human-machine interactive guidance display interface, which uses a short-focus projection device located in the cockpit to project an optical image onto the polarization refraction film of the front windshield of the cockpit, and forms a visual interactive interface on the front windshield through the polarization film. The short-focus projection device is also equipped with a speaker for transmitting acoustic guidance instructions to the operator. The operating handle in the cockpit in this implementation scheme has a vibration function for transmitting tactile guidance instructions to the operator.
[0069] In addition, the image generated by the collaborative work of the central operation module and the site grid generation module includes the digital equipment model of the shallow curing construction equipment and the digital site module of the construction site. The digital model of the mixing head is generated by the posture module of the shallow curing construction equipment. The center point of the mixing head of the shallow curing construction equipment is located by the data acquisition module, and the horizontal projection 403 is calculated, and interacts with the digital construction grid 400. The central black block seen by the operator in the display interface is the current position of the mixing head. The horizontal movement guidance instruction of the mixing head given in step S5 guides the operator to move the mixing head through the vector arrow 405 in this embodiment. When the mixing head reaches the target grid, the border 404 of the target grid is displayed as highlighted, and the operator is informed of the mixing and curing operation performed by the vibration feedback of the operator handle on the central controller. In this embodiment, other guidance information is included, and the guidance instruction of the construction depth includes a construction depth progress bar in the display interface, which shows the current depth of the mixing head. When the construction depth guidance control reaches the design depth threshold, that is, when the actual construction depth is less than 10cm from the target construction depth, the construction depth progress bar starts to flash, and the vibration device on the operating handle is turned on at the same time and vibrates at a frequency of 20Hz to remind the operator to slow down and perform shallow reinforcement bottom hardening treatment within the corresponding time of 10s-20s. Figure 5 The guidance instruction 401 uses the mixing head power monitoring unit to display the real-time rotation speed PV of the mixing head and compares it with the set rotation speed SV, thereby guiding the operator to control the rotation speed of the mixing head. Figure 5 The guidance instruction 402 displays the actual usage PV and the designed usage SV of the curing agent in the current construction grid. The two sets of data displayed can guide the operator to control the flow of the curing agent supplied in the background. Specific embodiment 2
[0071] An intelligent guidance method of an intelligent guidance system based on shallow layer solidification construction, comprising:
[0072] S1. Establishing a digital site model based on the characteristic information of the construction site, and establishing a digital equipment model based on the shallow solidification construction equipment; the characteristic information of the construction site includes boundary characteristics, coordinate characteristics and geological characteristics;
[0073] S2. The operator inputs construction requirement parameter information according to the geology of the construction site, and the construction requirement parameter information includes: construction site coordinates, construction depth, plane side length of three-dimensional construction grid body, depth of three-dimensional construction grid body, set curing material dosage of three-dimensional construction grid body, and set stirring times of three-dimensional construction grid body; the site grid generation module establishes a three-dimensional coordinate system according to the digital site model, and divides the digital site model into m×n×l three-dimensional construction grid bodies according to the construction requirement parameter information, and numbers each construction unit in the form of (i, p, o), i represents the number of rows on the construction surface, p represents the number of columns on the construction surface, and o represents the sequence number in the construction depth direction; calculates the vertex coordinates and center coordinates of each three-dimensional construction grid body; saves and displays it through the human-computer interaction screen display module;
[0074] S3. Establishing the correlation matching between the digital equipment model and the digital site model in the coordinate position according to the coordinate position of the shallow curing construction equipment collected by the data acquisition module and the coordinate features on the digital site model; so that the operator can accurately understand the current shallow curing construction equipment position on the construction site through the human-computer interaction screen display module;
[0075] S4. Obtain all three-dimensional construction grid bodies (i,p,1), (i,p,2)…(i,p,o)…(i,p,l) of the three-dimensional construction grid body to be constructed in the depth direction as a construction grid group; the operator controls the shallow solidification construction equipment to move to the three-dimensional construction grid body (i,p,1) through the controller; specifically includes:
[0076] S401. The operator controls the movement of the shallow curing construction equipment through the controller, and the data acquisition module collects the coordinate information of the shallow curing construction equipment in real time;
[0077] S402. Update the position of the digital equipment model on the digital site model according to the coordinate information of the shallow solidification construction equipment collected in S401 and the coordinate features on the digital site model, save it and display it through the human-computer interaction interface;
[0078] S403. By comparing the coordinate information of the shallow solidification construction equipment with the coordinates of each vertex of the three-dimensional construction grid (i, p, 1), it is determined whether the shallow solidification construction equipment has reached the three-dimensional construction grid (i, p, 1). If so, proceed to S404; if not, return to S401;
[0079] S404. Remind the operator through the reminder that the shallow curing construction equipment is in place;
[0080] S5. Calculate the effective construction area S1 of the mixing head at one time, and divide it twice on the horizontal plane of the three-dimensional construction grid group according to the effective construction area S1, and divide it into s×t columnar construction units, the depth of each columnar construction unit is consistent with the construction depth, and the s×t columnar construction units are numbered and sorted 1, 2, 3...s×t; and calculate the center coordinates of each columnar construction unit and set the amount of solidifying material; and perform solidifying material injection and stirring on each columnar construction unit according to the construction sequence; preset the number U of columnar construction units that complete the stirring and injection, and initialize U=0; Calculate the effective construction area S1 of the mixing head at one time specifically including: calculate the coordinates (X0, Y0) of the reference point of the center of the mixing head, and the coordinates of the four corners of the mixing head on the horizontal plane can be further calculated X1 (X+a, Y+b), X2 (Xa, Yb), X3 (X+a, Yb) and X4 (Xa, Y+b), and determine their projection shape area, so as to determine the effective construction area S1 of the mixing head at one time;
[0081] S6. The operator controls and adjusts the robot arm through the controller so that the mixing head moves to the position directly above the center coordinate of the k-th columnar construction unit;
[0082] Specifically include:
[0083] S601. The operator controls and adjusts the robotic arm through the controller;
[0084] S602. The data acquisition module collects the horizontal inclination angle of each segment of the robot arm, the pitch and roll angles of the shallow solidification construction equipment, and the center coordinates of the mixing head in real time, and calculates the relative elevation relationship between each reference point of the robot arm and the construction equipment, the absolute elevation coordinates, and the coordinates of the mixing head
[0085] S603. Update the posture of the robot arm in the digital equipment model according to the relative elevation relationship and absolute elevation coordinates of each reference point of the robot arm and the construction equipment;
[0086] S604. By comparing the center coordinates of the mixing head with the center coordinates of the k-th columnar construction unit, determine whether the mixing head has moved to the k-th columnar construction unit. If so, remind the operator through a reminder that the mixing head is in place, and enter S7; if not, return to S601;
[0087] S7. The mixing equipment performs solidification material injection and mixing work on the k-th columnar construction unit according to the construction requirement parameter information; calculates the displacement of the mixing head according to the change of the center coordinate of the mixing head, and determines whether the mixing head reaches the bottom of the k-th columnar construction unit according to the displacement. If so, enter S8; if not, return to S7;
[0088] S8. Mark the current columnar construction unit as completed, accumulate U=U+1 for the columnar construction unit, and determine whether U≥s×t is satisfied. If so, the construction grid group is completed. According to the set curing material dosage and the cumulative injection amount of the curing material of the three-dimensional construction grid body, as well as the set stirring times and the cumulative stirring times, the construction quality of each three-dimensional construction grid body of the construction grid group is evaluated, and the process goes to S9; if not satisfied, k=k+1, and returns to S6;
[0089] S9. Perform Manhattan distance calculation based on the plane position (i, p) of the completed construction grid group and the plane position of the adjacent unconstructed construction grid group to obtain all selected paths, and select the path with the shortest distance as the optimal path, and sort the construction grid groups in the path; and perform S4-S8 operations on the construction grid groups in the path in turn to complete the construction of the current construction site.
[0090] Furthermore, the calculation formula for the cumulative number of stirring times in S8 is:
[0091]
[0092] The stirring times are N, ΣM is the number of blades on the stirring head, V d 、V u are the descending and ascending speeds of the mixing head respectively, and n is the number of mixing times. The flow data of the same coordinates are integrated to obtain the cumulative injection amount of the solidified material of the three-dimensional construction grid.
[0093] The construction quality evaluation of the three-dimensional construction grid in S9 specifically includes:
[0094] The quality score coefficient R of the three-dimensional construction grid is:
[0095] R=R1 0.7 ×R2 2.3
[0096] R1 is the cumulative number of stirring times, when N>350, R1=1; when 300<N<350, 0.8<R1<1; when 250<N<300, 0.6<R1<0.8; when 200<N<250, 0.<R1<0.6;
[0097] R2 is the achieved value of the cumulative injection volume PV of the solidifying material and the set solidifying material dosage SV:
[0098] R2=PV / SV
[0099] The scoring table generated by this formula is as follows Figure 7 As shown in the figure, the scoring table is used to mark the three-dimensional construction grid. Figure 4As shown, R below 0.6 is unqualified, R exceeding 0.6 is qualified, exceeding 0.8 is good, and exceeding 0.9 is excellent.
[0100] In combination with actual construction cases, a site is a coastal tidal flat landform, with a thick silt layer that has high water content, low strength, high compressibility, etc. The plant foundation is planned to use prefabricated pile foundation. In order to meet the bearing capacity requirements of large-scale construction equipment such as piling construction equipment in the plant site, it is necessary to perform shallow solidification treatment on the soft soil layer of the site. The site covers an area of about 1 million square meters. The large walking equipment weighs 216 tons, and the average ground pressure when fully loaded is 78kPa.
[0101] The basic situation in this implementation plan: the silt soil layer is 5-22 meters thick and has a water content of 70%. The design requires that the temporary site solidification bearing capacity must reach 80kPa in 7 days. The moving path passed by large construction equipment is constructed according to 8% ash content and 2.5m depth, which is a heavy reinforcement area. The remaining areas are constructed with 6% ash content and 1.5m depth, which are light reinforcement areas. The shallow solidification construction equipment uses a crawler excavator with a shallow solidification mixing head. For the path passed by large construction equipment, the lifting speed of the mixing head is 3m / min, each three-dimensional construction grid is stirred twice, the slurry flow rate is 150L / min, and the stirring number is set to 560r / m. In the remaining areas, the lifting speed of the mixing head is 2-3m / min, the number of stirring times is 1, the slurry flow rate is 100L / min, and the stirring number is set to 280r / m. Before the shallow layer solidification construction, the three-dimensional construction grid generator in step S1 marks the construction site grid and divides it into a strong reinforcement area and a weak reinforcement area. Figure 6 The image of the three-dimensional construction grid in the strong reinforcement area is constructed by the No. 1 shallow solidification construction equipment, and the three-dimensional construction grid in the weak reinforcement area is constructed by the No. 2 shallow solidification construction equipment. The human-computer interaction center plans the plane path of the light and heavy reinforcement area according to the coordinate position of the shallow solidification construction equipment and the length limit of the slurry supply pipeline. The No. 1 construction equipment path is shown by the dotted arrow, and the No. 2 construction equipment path is shown by the solid arrow. By using the present invention, the plane error of the construction surface can be controlled within 5 cm, and the construction depth error can be controlled within 10 cm.
[0102] In the description of the embodiments of the present application, it should be noted that in the description of the present application, terms such as "inside" and "outside" indicating directions or positional relationships are based on the directions or positional relationships shown in the drawings. This is only for the convenience of description, and does not indicate or imply that the device or component must have a specific orientation, be constructed and operated in a specific orientation. Therefore, it cannot be understood as a limitation on the present application.
[0103] In the description of the present application, the description with reference to the terms "one embodiment", "some embodiments", "in the present embodiment", "specific example", or "some examples" etc. means that the specific features, mechanisms, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present application. In this specification, the schematic representations of the above terms do not necessarily refer to the same embodiment or example. Moreover, the specific features, mechanisms, materials or characteristics described may be combined in a suitable manner in any one or more embodiments or examples. In addition, those skilled in the art may combine and combine the different embodiments or examples described in this specification and the features of the different embodiments or examples, without contradiction.
[0104] The above is only a specific implementation of the present application, but the protection scope of the present application is not limited thereto. Any changes or substitutions that can be easily thought of by a person skilled in the art within the technical scope disclosed in the present application should be included in the protection scope of the present application. Therefore, the protection scope of the present application shall be based on the protection scope of the claims.
Claims
1. An intelligent guidance system for shallow layer solidification construction, used to guide operators to interact with shallow layer solidification construction equipment to complete shallow layer solidification construction projects, characterized in that: The intelligent guidance system includes a human-computer interaction screen display module, a controller, a data acquisition module, a site grid generation module, a construction quality evaluation module, a central operation module and a local database; The human-machine interactive display module interacts with the operator, and the operator operates the shallow curing construction equipment through the controller to control the shallow curing construction equipment to walk on the construction site and perform shallow curing construction; the human-machine interactive display module is mainly used to display and guide the operator to control the construction data information of the shallow curing construction equipment running on the site; The shallow layer solidification construction equipment is provided with a data acquisition module for collecting construction data information of the shallow layer solidification construction equipment, wherein the construction data information includes the center coordinates of the mixing equipment, the center coordinates of the mixing head of the mixing equipment, the rotation speed of the mixing head, the working temperature of the mixing head, the torque of the mixing head, the pressure of the feed pipe on the feeding equipment, and the flow rate of the solidified material in the feed pipe; The site grid generation module is used to establish a digital site model that maps the construction site, and divide the digital site model into m×n×l three-dimensional construction grid bodies according to the construction requirement parameter information, and calculate the vertex coordinates and center coordinates of each three-dimensional construction grid body; the site grid generation module is connected to the human-computer interaction screen display module to display the digital site model after grid division; the site grid generation module is connected to the local database to store the digital site module; The central operation module is connected to the data acquisition module to establish a digital equipment model that maps the shallow solidification construction equipment. The central operation module is connected to the local database to obtain the digital site model, and establishes an association between the digital equipment model and the digital site model according to the data acquisition module; the central operation module includes a model mapping unit for establishing the digital equipment model, a projection calculation unit for calculating the effective construction area of the shallow solidification construction equipment according to the digital equipment model, a construction trajectory calculation unit for dividing the three-dimensional construction grid in the digital site model into columnar construction units according to the effective construction area and generating a construction trajectory, and a working condition mapping unit for calculating and recording the construction condition of the digital equipment model on the digital site model according to the data acquisition module and the construction trajectory. The central operation module is connected to the human-computer interaction screen display module to display the construction condition of the digital equipment model on the construction site model.
2. The intelligent guidance system for shallow layer solidification construction according to claim 1 is characterized in that: The shallow layer solidification construction equipment includes a mechanical arm of a mixing device, a mixing head on the mechanical arm, a walking mechanism of the mixing device, a feeding device, and a feeding pipe for conveying the solidified material of the feeding device to the mixing head.
3. The intelligent guidance system for shallow layer solidification construction according to claim 1 is characterized in that: The construction requirement parameter information includes: construction site coordinates, construction depth, plane side length of the three-dimensional construction grid body, depth of the three-dimensional construction grid body, set curing material dosage of the three-dimensional construction grid body, and set stirring times of the three-dimensional construction grid body.
4. The intelligent guidance system for shallow layer solidification construction according to claim 1 is characterized in that: The data acquisition module includes a satellite positioning sensor arranged on the mixing equipment, multiple inclination sensors arranged on the robotic arm, a satellite positioning sensor arranged on the mixing head, a rotary encoder, a hydraulic oil flow sensor, a hydraulic oil pressure sensor, a hydraulic oil temperature sensor, a mixing head speed sensor, a feed pipe pressure sensor arranged on the feed pipe, a feed pipe flow sensor and a background weighing sensor arranged on the feeding equipment.
5. The intelligent guidance system for shallow layer solidification construction according to claim 1 is characterized in that: The intelligent guidance system also includes a construction quality evaluation module, which is connected to a local database and is used to calculate the construction progress and construction quality indicators of each three-dimensional construction grid body. The construction quality evaluation module is connected to a human-computer interaction screen display module to synchronously display the construction progress and construction quality indicators of the corresponding three-dimensional construction grid body.
6. An intelligent guidance method for the intelligent guidance system of shallow layer solidification construction based on any one of claims 1 to 5, characterized in that: include: S1. Establishing a digital site model based on the characteristic information of the construction site, and establishing a digital equipment model based on the shallow solidification construction equipment; the characteristic information of the construction site includes boundary characteristics, coordinate characteristics and geological characteristics; S2. The operator inputs construction requirement parameter information according to the geology of the construction site, and the construction requirement parameter information includes: construction site coordinates, construction depth, plane side length of three-dimensional construction grid body, depth of three-dimensional construction grid body, dosage of curing material required for three-dimensional construction grid body, and set stirring times of three-dimensional construction grid body; the site grid generation module establishes a three-dimensional coordinate system according to the digital site model, and divides the digital site model into m×n×l three-dimensional construction grid bodies according to the construction requirement parameter information, and numbers each construction unit in the form of (i, p, o), i represents the number of rows on the construction surface, p represents the number of columns on the construction surface, and o represents the sequence number in the construction depth direction; calculates the vertex coordinates and center coordinates of each three-dimensional construction grid body; saves and displays it through the human-computer interaction screen display module; S3. Establishing the correlation matching between the digital equipment model and the digital site model in the coordinate position according to the coordinate position of the shallow curing construction equipment collected by the data acquisition module and the coordinate features on the digital site model; enabling the operator to accurately understand the current shallow curing construction equipment position on the construction site through the human-computer interaction screen display module; S4. Obtain the three-dimensional construction grid body to be constructed, and use all the three-dimensional construction grid bodies (i,p,1), (i,p,2)…(i,p,o)…(i,p,l) in the depth direction as the construction grid group; the operator controls the shallow solidification construction equipment to move to the three-dimensional construction grid body (i,p,1) through the controller; S5. Calculate the effective construction area S1 of the mixing head at a time, and divide it twice on the horizontal plane of the three-dimensional construction grid group according to the effective construction area S1, and divide it into s×t columnar construction units. The depth of each columnar construction unit is consistent with the construction depth, and the s×t columnar construction units are numbered and sorted 1, 2, 3...s×t; and calculate the center coordinates of each columnar construction unit and set the amount of solidifying material; and perform solidifying material injection and stirring on each columnar construction unit according to the construction sequence; preset the number U of columnar construction units that have completed stirring and injection, and initialize U=0; S6. Calculate the displacement of the mixing head according to the change of the center coordinate of the mixing head and display the horizontal direction guidance information on the human-machine interactive screen display module. The operator controls and adjusts the robotic arm through the controller so that the mixing head moves to the center coordinate of the kth columnar construction unit. S7. The mixing equipment performs solidification material injection and mixing work on the kth columnar construction unit according to the construction requirement parameter information; the displacement of the mixing head is calculated according to the change of the center coordinate of the mixing head and the vertical direction guidance information is displayed on the human-computer interaction screen display module. The operator controls and adjusts the mechanical arm through the controller to move the mixing head to the bottom of the kth columnar construction unit; it is determined whether the mixing head reaches the bottom of the kth columnar construction unit according to the displacement, if so, enter S8; if not, return to S7; S8. Mark the current columnar construction unit as completed, add the number of columnar construction units U=U+1, and judge whether U≥s×t is satisfied. If so, mark the current construction grid group as completed, and evaluate the construction quality of each three-dimensional construction grid body of the construction grid group according to the set curing material dosage and the cumulative injection amount of the curing material, as well as the set stirring times and the cumulative stirring times of the three-dimensional construction grid body, and enter S9; if not satisfied, k=k+1, and return to S6; S9. Perform Manhattan distance calculation based on the plane position (i, p) of the completed construction grid group and the plane position of the adjacent unconstructed construction grid group to obtain all selected paths, and select the path with the shortest distance as the optimal path, and sort the construction grid groups in the path; and perform S4-S8 operations on the construction grid groups in the path in turn to complete the construction of the current construction site.
7. The intelligent guidance method according to claim 6, characterized in that: The step 4 of obtaining the three-dimensional construction grid body to be constructed specifically includes: S401. The operator controls the movement of the shallow curing construction equipment through the controller, and the data acquisition module collects the coordinate information of the shallow curing construction equipment in real time; S402. Update the position of the digital equipment model on the digital site model according to the coordinate information of the shallow solidification construction equipment collected in S401 and the coordinate features on the digital site model, save it and display it through the human-computer interaction interface;. S403. By comparing the coordinate information of the shallow solidification construction equipment with the coordinates of each vertex of the three-dimensional construction grid (i, p, 1), it is determined whether the shallow solidification construction equipment has reached the three-dimensional construction grid (i, p, 1). If so, proceed to S404; if not, return to S401; S404. Remind the operator to put shallow curing construction equipment in place through the human-machine interactive screen module.
8. The intelligent guidance method according to claim 6, characterized in that: The calculation of the effective construction area S1 of the mixing head in a single time in S5 specifically includes: calculating the coordinates (X0, Y0) of the central reference point of the mixing head, the coordinates can continue to calculate the coordinates of the four corners of the mixing head on the horizontal plane X1 (X+a, Y+b), X2 (Xa, Yb), X3 (X+a, Yb) and X4 (Xa, Y+b), and determine their projected shape area, thereby determining the effective construction area S1 of the mixing head in a single time; wherein a represents the width of the mixing head, and b represents the length of the mixing head.
9. The intelligent guidance method according to claim 6, characterized in that: The S6 specifically includes: S601. The operator controls and adjusts the robotic arm through the controller; S602. The data acquisition module collects the horizontal inclination angle of each segment of the robot arm, the pitch and roll angles of the shallow solidification construction equipment, and the center coordinates of the mixing head in real time, and calculates the relative elevation relationship between each reference point of the robot arm and the construction equipment, the absolute elevation coordinates, and the coordinates of the mixing head S603. Update the posture of the robot arm in the digital equipment model according to the relative elevation relationship and absolute elevation coordinates of each reference point of the robot arm and the construction equipment; S604. Determine whether the mixing head has moved to the kth columnar construction unit by comparing the center coordinates of the mixing head with the center coordinates of the kth columnar construction unit. If so, remind the operator through a prompter that the mixing head is in place and enter S7; if not, return to S601.
10. The intelligent guidance method according to claim 6, characterized in that: The step S8 evaluates the construction quality of each three-dimensional construction grid body of the construction grid group according to the set curing material dosage and the cumulative injection amount of the curing material of the three-dimensional construction grid body, specifically including: The quality score coefficient R of the three-dimensional construction grid is: R=R1 0.7 ×R2 2.3 R1 is the cumulative stirring times of the stirring head, when N ≥ 350, R1 = 1; when 350 > N ≥ 300, R1 = 0.8; when 300 > N ≥ 250, R1 = 0.6; when 250 > N ≥ 200, R1 = 0.5; R2 is the achieved value of the cumulative injection volume PV of the solidifying material and the set solidifying material dosage SV: R2=PV / SV The scoring table generated by the formula is used to mark the three-dimensional construction grid body. R below 0.6 is unqualified, R above 0.6 is qualified, R above 0.8 is good, and R above 0.9 is excellent.
Citation Information
Patent Citations
Autonomous 3D excavation construction robot
CN108797669A
Intelligent construction method and system suitable for in-situ reinforcement of large-area soft foundation
CN114036625A
Auxiliary control system of in-situ sludge solidification stirring equipment
CN116282782A
Intelligent mixing pile construction method based on combination of automatic intelligent control module and Beidou positioning system