Composite bridge abutment and construction method thereof

By adopting a composite abutment structure in the highway renovation and expansion project, including abutment pile foundation, bearing and tree-shaped pile, the safety hazards and construction difficulty of ribbed abutment are solved, and the foundation pit opening is reduced The effect of digging and reducing construction costs.

CN119061778AInactive Publication Date: 2024-12-03山西晋阳高速改扩建项目管理有限公司 +1
View PDF 8 Cites 0 Cited by

Patent Information

Application Number
CN202411540170.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-31
Publication Date
2024-12-03
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

In the highway renovation and expansion project, the construction of ribbed abutments requires large-area foundation pit excavation on the original fill subgrade slope, resulting in increased construction difficulty and threatening the safe operation of existing expressways.

Method used

A composite abutment structure is adopted, including abutment pile foundation, support platform, cover beam and tree-shaped pile. The abutment pile foundation is vertically arranged on the junction slope of the new and old roadbeds, and tree-shaped piles are arranged in two rows, one row is vertically and the other is inclined. , the inclined tree-shaped piles are connected to the support platform, and the mortar is poured into the internal structure to reduce the damage to the stratigraphic structure and form a stable stone body.

Benefits of technology

Eliminate safety hazards caused by the construction of traditional ribbed abutments of fill roadbed wide-submarine bridges, reduce the impact of high-slope soil landslides on the punching and cutting of bridge pile foundations, save costs and construction cycles, and improve the economicality of construction. and security.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119061778A_ABST
    Figure CN119061778A_ABST
Patent Text Reader

Abstract

The invention discloses a combined type bridge abutment and a construction method thereof.The combined type bridge abutment is applied to highway reconstruction and expansion bridge widening engineering and comprises a bridge abutment pile foundation, a bearing platform, a bent cap and tree-shaped piles, the bridge abutment pile foundation is vertically arranged on the junction slope face of an old roadbed and a newly-built roadbed, and the bearing platform is arranged on the bearing platform; one end of the abutment pile foundation extends into a soil layer at the bottom of the old roadbed, a bearing platform is arranged at the other end of the abutment pile foundation, and a cover beam is arranged at the top of the bearing platform and located below the top of the newly-built roadbed; a tree-shaped pile is arranged on one side of the bridge abutment pile foundation, one end of the tree-shaped pile extends into the old roadbed, and the other end of the tree-shaped pile extends into the bearing platform and is fixedly connected with the bearing platform. The method can solve the problem that in a traditional reorganization and extension highway widening project, large-area excavation is conducted on the side slope of an original fill roadbed during construction of the rib plate type bridge abutment, and potential safety hazards are brought to traffic protection and safe operation of an existing highway, so that safe operation of the existing highway is guaranteed, and the construction period of the existing highway is shortened. And the punching influence of the high slope soil body landslide on the bridge pile foundation is also reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of roads and bridges, and in particular to a composite abutment and a construction method thereof. Background Art

[0002] In current highway reconstruction and expansion projects, especially in the construction of fill roadbed widening bridges, when the roadbed fill height exceeds 6 meters, ribbed abutment structures are usually used. This structure not only helps to shorten the overall length of the bridge, but also enhances the ability of the abutment to resist lateral soil pressure, and to a certain extent can reduce the overall cost of the project. However, in actual operation, especially when widening and reconstructing existing highways, if the new and old roadbeds are closely adjacent, the construction of ribbed abutments will face a series of complex problems.

[0003] Specifically, during the construction process, large-scale foundation pit excavation operations need to be carried out at the slope position of the original fill roadbed. In addition, in order to ensure the stability between the new and old roadbeds, it is necessary to implement anti-slip piles and other reinforcement measures on the outside of the hard shoulder of the existing roadbed. Although these technical means are necessary, they will significantly increase the difficulty of construction in mountainous highways or when the road width itself is limited, and will also pose a potential threat to the safety and smooth flow of existing highways. Summary of the invention

[0004] In order to overcome the problems existing in the related art to at least a certain extent, the present invention provides a composite abutment and a construction method thereof, so as to solve the problem that in the traditional highway widening and reconstruction project, large-scale excavation is required at the slope of the original fill roadbed during the construction of the rib-type abutment, which brings safety hazards to the maintenance and safe operation of the existing highway.

[0005] The present invention provides a composite abutment, which is used in the widening project of highway reconstruction and expansion bridges, and comprises an abutment pile foundation, a capping platform, a cap beam and a tree-like pile, wherein the abutment pile foundation is vertically arranged at the intersection slope of an old roadbed and a newly built roadbed, one end of the abutment pile foundation extends into the soil layer at the bottom of the old roadbed, and the capping platform is arranged at the other end, and the capping platform is arranged on the top of the capping platform, and the capping beam is located below the top of the newly built roadbed; the tree-like pile is arranged on one side of the abutment pile foundation, one end of the tree-like pile extends into the old roadbed, and the other end of the tree-like pile extends into the capping platform, and is fixedly connected to the capping platform.

[0006] According to the composite abutment provided by the present invention, the interior of the tree-like piles is poured with mortar.

[0007] According to the composite abutment provided by the present invention, two rows of tree-like piles are arranged on one side of the abutment pile foundation, wherein one row of the tree-like piles are vertically arranged at the intersection slope of the old roadbed and the newly built roadbed; and the opposite end of the other row of the tree-like piles connected to one end of the abutment is inclined in a direction away from the abutment pile foundation.

[0008] Furthermore, the angle between another row of the tree-like piles and the abutment pile foundation is 10°~15°.

[0009] Furthermore, the diameter of the tree-like pile is 10 cm to 15 cm, and the length of the tree-like pile extending into the foundation is 60 cm to 80 cm.

[0010] The present invention also provides a construction method for a composite abutment, which comprises the following steps: Construct a retaining wall at the foot of the new roadbed slope, and construct reinforced concrete piles in the surface soil layer below the retaining wall; Fill the newly built roadbed in two stages: fill to the bottom of the cap beam in the first stage, and fill to the top of the roadbed after the cap beam is completed in the second stage. The soil is compacted layer by layer during the filling process. Construct abutment pile foundations in the soil of the newly built roadbed, and the abutment pile foundations include steel cages and concrete; On one side of the abutment pile foundation, tree piles are constructed near the intersection slope of the old roadbed and the new roadbed, and mortar is poured inside the tree piles; A cap is constructed above the abutment pile foundation and the tree-like piles, and the top of the tree-like pile is extended into the cap to be connected with the cap as a whole; Construct a cap beam above the pedestal to complete the construction of the pile-connected cap beam abutment.

[0011] The construction method of the composite abutment provided by the present invention further comprises cleaning the surface of the newly built roadbed slope before construction.

[0012] The construction method of the composite abutment provided by the present invention also includes constructing a T-beam on the top of the cap beam, and constructing a bridge deck system and an anti-collision guardrail on the top of the T-beam.

[0013] According to the construction method of the composite abutment provided by the present invention, during the filling process, a layer of geogrid is laid every 2m to 3m according to the filling height.

[0014] According to the construction method of the composite abutment provided by the present invention, the tree-shaped piles are constructed on one side of the abutment pile foundation, near the intersection slope of the old roadbed and the newly built roadbed, including: Two rows of tree-like piles are constructed for each abutment pile foundation, wherein one row of tree-like piles is arranged vertically, and the other row of tree-like piles is arranged obliquely; one end of the inclined tree-like piles extending into the old roadbed is inclined in a direction away from the abutment pile foundation, and the opposite end of the tree-like piles extending into the old roadbed is inclined in a direction close to the abutment pile foundation.

[0015] According to the above specific embodiments of the present invention, it can be known that at least the following beneficial effects are achieved: the composite abutment provided by the present invention, by arranging abutment pile foundations and tree-like piles at the intersection slope of the new and old roadbeds, and arranging a pedestal and a cap beam above the abutment pile foundations, can eliminate the safety hazards caused by the need to carry out large-scale foundation pit excavation on the slope of the original fill roadbed during the construction of traditional rib-type abutments for widening bridges on fill roadbeds, thereby ensuring the safe operation of existing highways and reducing the shearing effect of high slope soil landslides on bridge pile foundations.

[0016] The construction method of the composite abutment provided by the present invention eliminates the anti-slide piles and anti-collision walls set at the junction of the new and old roadbeds, can save costs, shorten the construction period, is simple to construct, and has good economy. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] In order to more clearly illustrate the technical solutions in the present invention or the prior art, the following briefly introduces the drawings required for use in the embodiments or the description of the prior art. Obviously, the drawings described below are some embodiments of the present invention. For ordinary technical workers in this field, other drawings can be obtained based on these drawings without paying creative work.

[0018] Figure 1 It is a cross-sectional view of a composite abutment provided by an embodiment of the present invention in application in a highway reconstruction and expansion project; Figure 2 It is a side view of a composite abutment provided by an embodiment of the present invention.

[0019] Description of reference numerals: 1. Abutment pile foundation; 2. Capping platform; 3. Cap beam; 4. Tree pile; 10. Old roadbed; 20. New roadbed; 30. Retaining wall; 40. Reinforced concrete piles; 50. Geogrid; 60. T-beam; 70. Bridge deck system and anti-collision guardrail. Add cone slope protection DETAILED DESCRIPTION

[0020] In order to make the purpose, technical solution and advantages of the present invention clearer, the technical solution of the present invention will be clearly and completely described below in conjunction with the drawings of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0021] In order to solve the shortcomings of traditional rib-plate abutments in highway reconstruction and expansion projects, thereby improving construction efficiency and safety and ensuring the normal operation of existing highways, the present invention provides a composite abutment and a construction method thereof.

[0022] Combine the following Figure 1-Figure 2 The composite abutment provided by the present invention is described.

[0023] like Figure 1 As shown, the composite abutment provided by the present invention can be used in the widening project of the bridge expansion and reconstruction of the highway, and includes an abutment pile foundation 1, a cap 2, a cap beam 3 and a tree-like pile 4, wherein the abutment pile foundation 1 is vertically arranged at the intersection slope of the old roadbed 10 and the newly built roadbed 20, one end of the abutment pile foundation 1 extends to the soil layer at the bottom of the old roadbed 10, and the other end thereof is provided with a cap 2, and the top of the cap 2 is provided with a cap beam 3, and the cap beam 3 is located below the top of the newly built roadbed 20 to cover the cap 2. A tree-like pile 4 is arranged on one side of the abutment pile foundation 1, one end of the tree-like pile 4 extends into the old roadbed 10, and the other end thereof extends into the cap 2, and can be fixedly connected with the cap 2.

[0024] The present invention sets abutment pile foundation 1 and tree piles 4 at the intersection slope of the new and old roadbeds 10. When it rains or the like, the artificial fill in the newly built roadbed 20 tends to slide along the original slope surface. The stone bodies in the tree piles 4 and the adjacent areas bear the horizontal component of the sliding soil. After being greatly weakened by the tree piles 4, the horizontal displacement component of the soil will basically not affect the abutment pile foundation 1 when it acts on the abutment pile foundation 1. The construction process of the composite abutment provided by the present invention has no effect on the operation of the existing highway and can also meet the requirements for maintaining the traffic of the existing highway.

[0025] In the above embodiment, the interior of the tree-like piles 4 is poured with mortar. Under the grouting pressure, the slurry penetrates into the rock and soil gaps without disturbing or destroying the stratum structure, cementing the soil particles together, changing the mechanical properties of the foundation soil, and forming a stone body with a new structure, high strength and good stability.

[0026] In a specific embodiment, two rows of tree-like piles 4 are arranged on one side of the abutment pile foundation 1, wherein one row of tree-like piles 4 is arranged parallel to the abutment pile foundation 1, and is vertically arranged at the intersection slope of the old roadbed 10 and the newly built roadbed 20; the other row of tree-like piles 4 is arranged at an angle away from the abutment pile foundation 1 at an end opposite to the end connected to the cap 2, and the angle between the tree-like piles 4 and the abutment pile foundation 1 is 10° to 15°. Specifically, each row of tree-like piles 4 may include three tree-like piles.

[0027] It should be noted that, in a specific embodiment, two abutment pile foundations 1 can be provided, and the two abutment pile foundations 1 are arranged side by side. Two rows of tree-like piles 4 are provided on one side of each abutment pile foundation 1, and the two rows of tree-like piles 4 form a more stable support structure. The diameter of the tree-like pile 4 can be 10 cm to 15 cm, and the length of the tree-like pile 4 can be determined according to the fill height, which is usually approximately equal to the fill height. The length of the tree-like pile 4 extending into the cap 2 is 60 to 80 cm, which is approximately half of the thickness of the cap 2.

[0028] Based on the composite abutment provided by the present invention, the present invention also provides a construction method of the composite abutment, which comprises the following steps: S1. Construct a retaining wall 30 at the foot of the newly built roadbed 20, and construct reinforced concrete piles 40 in the surface soil layer below the retaining wall 30. The retaining wall 30 and the reinforced concrete piles 40 can prevent the roadbed slope soil from undergoing large horizontal displacement or sliding.

[0029] S2. Fill the newly built roadbed 20 in two stages until it is flush with the top surface of the old roadbed 10. During the filling process, the soil is rolled layer by layer, and the thickness of each layer of soil after compaction is ensured to be 25cm~35cm. During the filling process, a geogrid 50 is laid every 2m~3m according to the filling height. The geogrid 50 can effectively reduce the uneven settlement of the soil.

[0030] S3, constructing a bridge abutment pile foundation 1 in the soil of the newly built roadbed 20, wherein the bridge abutment pile foundation 1 includes a steel cage and concrete, and the process is as follows: Holes are drilled in the soil of the newly constructed roadbed 20, and steel cages are installed in the holes and concrete is poured.

[0031] S4, located on one side of the abutment pile foundation 1, a tree-like pile 4 is constructed at the intersection slope near the old roadbed 10 and the newly built roadbed 20, and mortar is poured into the tree-like pile 4. Under the grouting pressure, the slurry penetrates into the rock and soil gaps without disturbing or destroying the stratum structure, cementing the soil particles, changing the mechanical properties of the foundation soil, and forming a stone body with a new structure, high strength and good stability.

[0032] Specifically, two rows of tree-like piles 4 can be constructed for each abutment pile foundation 1, one of which is arranged vertically and the other is arranged obliquely. One end of the obliquely arranged tree-like piles 4 extending into the old roadbed 10 is inclined in a direction away from the abutment pile foundation 1, and the opposite end of the tree-like piles 4 extending into the old roadbed 10 is inclined in a direction close to the abutment pile foundation 1. The angle between the obliquely arranged tree-like piles 4 and the abutment pile foundation 1 is 10° to 15°.

[0033] S5. Construct the cap 2 above the abutment pile foundation 1 and the tree-like pile 4, and extend the top of the tree-like pile 4 into the cap 2 to connect with the cap 2 as a whole.

[0034] S6. Construct the cap beam 3 above the cap 2 to complete the construction of the pile-connected cap beam abutment. Subsequent construction of the superstructure and erection of prefabricated beams can be carried out according to conventional steps. Specifically, a T beam 60 can be constructed on the top of the cap beam 3, and a bridge deck system and an anti-collision guardrail 70 can be constructed on the top of the T beam 60.

[0035] In the construction method of the composite abutment provided by the present invention, after the construction of the abutment pile foundation 1 and the tree-like pile 4 is completed, the abutment 2 and the cap beam 3 are directly connected, and there is no need to construct a traditional ribbed abutment. In addition, the surface of the slope of the newly built roadbed 20 needs to be cleaned before construction.

[0036] The composite abutment and construction method provided by the present invention can eliminate the potential safety hazard caused by the need to carry out large-scale foundation pit excavation at the slope of the original fill roadbed during the construction of traditional rib-plate abutments for widening bridges on fill roadbeds, thereby ensuring the safe operation of existing highways and reducing the shearing effect of high slope soil landslides on bridge pile foundations.

[0037] The composite abutment provided by the present invention eliminates the anti-slip piles and anti-collision walls provided at the junction of the new and old roadbeds 10, which can save costs, shorten the construction period, simplify the construction, and have good economy.

[0038] The device embodiments described above are merely illustrative, wherein the units described as separate components may or may not be physically separated, and the components shown as units may or may not be physical units, that is, they may be located in one place, or they may be distributed on multiple network units. Some or all of the modules may be selected according to actual needs to achieve the purpose of the scheme of this embodiment. Ordinary technical workers in this field can understand and implement it without paying creative labor.

[0039] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit it. Although the present invention has been described in detail with reference to the aforementioned embodiments, ordinary technical workers in the field should understand that they can still modify the technical solutions recorded in the aforementioned embodiments, or make equivalent replacements for some of the technical features therein. However, these modifications or replacements do not deviate the essence of the corresponding technical solutions from the spirit and scope of the technical solutions of the embodiments of the present invention.

Claims

1. A composite abutment, characterized in that: It is used in the widening project of highway reconstruction and expansion bridges, and includes abutment pile foundations, pedestals, cap beams and tree-like piles, wherein the abutment pile foundations are vertically arranged at the intersection slope of the old roadbed and the newly built roadbed, one end of the abutment pile foundation extends to the soil layer at the bottom of the old roadbed, and the pedestal is arranged at the other end, and the cap beam is arranged on the top of the pedestal, and the cap beam is located below the top of the newly built roadbed; the tree-like piles are arranged on one side of the abutment pile foundation, one end of the tree-like pile extends into the old roadbed, and the other end extends into the pedestal, and is fixedly connected to the pedestal.

2. The composite abutment according to claim 1, characterized in that: The interior of the tree-like pile is poured with mortar.

3. The composite abutment according to claim 1, characterized in that: Two rows of tree-like piles are arranged on one side of the abutment pile foundation, wherein one row of the tree-like piles is vertically arranged at the intersection slope of the old roadbed and the newly built roadbed; and the other row of the tree-like piles is inclined at the opposite end connected to the abutment in a direction away from the abutment pile foundation.

4. The composite abutment according to claim 3, characterized in that: The angle between another row of tree-like piles and the abutment pile foundation is 10°~15°.

5. The composite abutment according to claim 3, characterized in that: The diameter of the tree-like pile is 10 cm to 15 cm, and the length of the tree-like pile extending into the foundation is 60 cm to 80 cm.

6. A construction method for a composite abutment according to any one of claims 1 to 5, characterized in that: The following steps are involved: Construct a retaining wall at the foot of the new roadbed slope, and construct reinforced concrete piles in the surface soil layer below the retaining wall; Fill the newly built roadbed in two stages: fill to the bottom of the cap beam in the first stage, and fill to the top of the roadbed after the cap beam is completed in the second stage. The soil is compacted layer by layer during the filling process. Construct abutment pile foundations in the soil of the newly built roadbed, and the abutment pile foundations include steel cages and concrete; On one side of the abutment pile foundation, tree piles are constructed near the intersection slope of the old roadbed and the new roadbed, and mortar is poured inside the tree piles; A cap is constructed above the abutment pile foundation and the tree-like piles, and the top of the tree-like pile is extended into the cap to be connected with the cap as a whole; Construct a cap beam above the pedestal to complete the construction of the pile-connected cap beam abutment.

7. The construction method of the composite abutment according to claim 6, characterized in that: It also includes surface cleaning of the new roadbed slopes before construction.

8. The construction method of the composite abutment according to claim 6, characterized in that: It also includes the construction of a T-beam on top of the cap beam, and the construction of the bridge deck system and anti-collision guardrail on top of the T-beam.

9. The construction method of the composite abutment according to claim 6, characterized in that: During the filling process, a layer of geogrid is laid every 2m~3m according to the filling height.

10. The construction method of the composite abutment according to claim 6, characterized in that: The tree piles located on one side of the abutment pile foundation and at the intersection slope near the old roadbed and the newly built roadbed include: Two rows of tree-like piles are constructed for each abutment pile foundation, wherein one row of tree-like piles is arranged vertically, and the other row of tree-like piles is arranged obliquely; one end of the inclined tree-like piles extending into the old roadbed is inclined in a direction away from the abutment pile foundation, and the opposite end of the tree-like piles extending into the old roadbed is inclined in a direction close to the abutment pile foundation.

Citation Information

Patent Citations

  • Stability and deformation control structure of mountainside high-filled embankment and construction method

    CN107503257A

  • Transverse grouting roadbed reinforcing structure and roadbed repairing method

    CN112048959A

  • On-slope bridge construction method for side slope easy to slip and bridge

    CN113863145A

  • Construction method for widening and reinforcing bridge through front-mounted light combination column type platform

    CN115094787A

  • Slope bridge deformation control reinforcing structure and construction method

    CN117364666A