Method for building basement-containing building on existing tunnel by adopting bundled plate ground structure

By adopting a bundled slab structure on the subway tunnel, the impact of upper cover development on the lower tunnel and construction risks are solved, and the stable construction and investment optimization of the basement are achieved.

CN119061882APending Publication Date: 2024-12-03SHANGHAI URBAN CONSTRUCTION DESIGN & RESEARCH INSTITUTE (GROUP) CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411339777.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-25
Publication Date
2024-12-03

AI Technical Summary

Technical Problem

When the overhead cover of subway tunnels is developed, the existing technology is difficult to effectively reduce the impact on the operating tunnels below, and there are problems of construction risks and high investment waste.

Method used

Adopt a bundled slab floor structure, by constructing various pipe sections on existing tunnels, tensing prestress and anchoring, it forms anti-floating control, reducing up-floating deformation, and using bundled slab floor as the foundation pit excavation site to realize basement construction .

Benefits of technology

It effectively reduces the impact of upper cover development on the lower tunnel, reduces construction risks and investment, and achieves efficient construction and structural stability of the basement.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119061882A_ABST
    Figure CN119061882A_ABST
Patent Text Reader

Abstract

The invention discloses a method for building a building containing a basement on an existing tunnel by adopting a bundled plate ground structure, which comprises the following steps of: 1, finishing the jacking construction of each pipe joint of the bundled plate ground in a soil body on the existing tunnel; 2, a worker enters each B-type pile working pipe where the pile foundation needs to be arranged, and the corresponding pile foundation is constructed; 3, construction of the bundled plate is completed, and anti-floating control over an existing tunnel and isolation of construction disturbance of a building containing a basement on the upper portion are achieved; 4, the foundation pit is excavated to the bundled plate ground; 5, the bunched plate ground serves as a construction operation site, the upper cover of the basement-containing building with the structural style capable of being freely selected is developed, and meanwhile the bunched plate ground serves as a raft foundation of the basement-containing building; and 6, soil is backfilled to the ground, and construction of the building containing the basement is completed. The method can reduce the influence of the development of the upper cover on the operation subway tunnel below, controls the construction risk, reduces the project investment, and has better economic and social benefits compared with the prior art.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of underground space construction, and in particular to a method for constructing a building containing a basement on an existing tunnel by using a bundled slab-ground structure. Background Art

[0002] Metro construction has made rapid progress since the 21st century, with a significant increase in operating mileage, prompting the development intensity of urban underground space to become increasingly higher.

[0003] But because of Figure 1 The construction and operation of the subway shown in the figure comes first, and the land is crossed by the built shield tunnel, and then the upper cover development is carried out. The construction of the upper cover development will have a great impact on the running subway. In particular, the shield tunnel is a flexible structure assembled by block and ring segments. When the upper cover development is carried out for foundation pit excavation, it will cause the tunnel structure below to float up.

[0004] The conventional practice in the engineering community is, first, to reinforce the soil layer from the ground down to improve the stiffness and integrity of the soil; second, to pre-reinforce the tunnel structure; then, to set up anti-floating slabs on the ground or at a shallow excavation depth, combined with anti-pullout piles, zoning construction, automated monitoring and other measures to control the floating deformation of the tunnel. The core problem of this approach is that, due to the need to ensure a thicker cover for the existing tunnel, the upper cover development cannot have a basement or can only have a shallow basement, which limits the building function of the upper cover development;

[0005] At the same time, when setting up a basement, the foundation pit excavation, even if the corresponding measures are taken, the problem of unloading soil first and then controlling it cannot be avoided, which poses a major safety hazard. In addition, soil reinforcement and zoning construction are temporary projects. In addition to the cumbersome construction, the upper cover development cannot be utilized during the use stage, resulting in a waste of investment.

[0006] Therefore, how to reduce the impact of superstructure development on the operating subway tunnels below, control construction risks, and reduce project investment have become technical problems that technical personnel in this field urgently need to solve. Summary of the invention

[0007] In view of the above-mentioned defects of the prior art, the present invention provides a method for constructing a building including a basement on an existing tunnel by using a bundled slab-ground structure, so as to reduce the impact of the upper cover development on the operating subway tunnel below, control construction risks and reduce project investment.

[0008] To achieve the above object, the present invention discloses a method for constructing a building including a basement by using a bundled slab-ground structure on an existing tunnel, comprising the following steps:

[0009] Step 1: In the soil above the existing tunnel, according to the design requirements of the basement building, complete the jacking construction of each pipe segment of the bundled slab ground;

[0010] Step 2: Workers enter each B-type pile working pipe where pile foundations need to be set, and use small equipment to construct the corresponding pile foundations;

[0011] Step 3: pouring concrete in each pipe segment and between the pipe segments, tensioning prestress and anchoring at the ends, completing the bundled slab-ground construction, achieving anti-floating control of the existing tunnel and isolation of the disturbance caused by the construction of the upper part including the basement;

[0012] Step 4, excavating a foundation pit to the bundled slab ground;

[0013] Step 5, using the bundled slab as a construction site, developing the upper cover of the building with basement, the structural type of which can be freely selected, and serving as the raft foundation of the building with basement;

[0014] Step 6: Backfill the soil to the ground to complete the basement construction of the building with basement, and continue to construct the part of the building with basement located on the ground.

[0015] Preferably, step 1 is as follows:

[0016] Step 1.1, according to the basement range of the basement building, two working pits are constructed at the positions corresponding to the bundled slab on both sides of the existing tunnel;

[0017] Step 1.2, in the soil above the existing tunnel, according to the bottom elevation of the basement, push each pipe segment of the bundled slab from one working shaft to another working shaft;

[0018] Every two adjacent pipe sections are connected by a lock;

[0019] All the pipe sections include a plurality of A-type standard pipes and a plurality of B-type pile working pipes;

[0020] A plurality of the A-type standard pipes may be spaced between each two of the B-type pile working pipes or between each of the B-type pile working pipes and the side of the bundled slab;

[0021] Under each of the B-type pile working pipes, a plurality of pile foundations are arranged along the length direction at positions corresponding to both sides of each of the existing tunnels.

[0022] More preferably, the net distance between each pipe segment and the existing tunnel is not less than 0.2 m.

[0023] More preferably, the outer dimensions and wall thickness of each pipe section of the A-type standard pipe, and the number of the A-type standard pipes between each two B-type pile working pipes or between each B-type pile working pipe and the side of the bundled slab are determined based on the anti-floating of the subsequent excavation construction after the formation of the bundled slab, and the force calculation of the raft slab containing the basement building during the use stage;

[0024] The size of each B-type pile working pipe is determined according to the size of the construction equipment used to construct the corresponding pile foundation, and is not less than 2.8m.

[0025] More preferably, the depth of each of the working wells is more than 1.5 m deeper than the lower edge of the pipe section of the bundled plate floor.

[0026] Preferably, in step 2, each of the pile foundations is a cast-in-place pile; when each of the B-type pile working pipes is prefabricated in the factory, a pile opening and a sealing plate are reserved at the location where each of the pile foundations is set;

[0027] Each of the sealing plates is fixed to the corresponding B-type pile working pipe by a fillet weld formed by welding;

[0028] The specific construction steps are as follows:

[0029] Step 2A.1, removing the sealing plate at the position where the pile foundation needs to be set in each B-type pile working tube to expose the corresponding pile position opening;

[0030] Step 2A.2, drilling holes at each exposed pile position and setting up small construction equipment to perform cast-in-place pile rapid construction;

[0031] The small construction equipment is a vertical pipe jacking machine;

[0032] The quick pile construction of the cast-in-place pile is as follows: after vertical hole formation, cement slurry is injected to maintain the stability of the hole wall, and after the corresponding pile reinforcement of the pile foundation is sunk, concrete is poured underwater to form the cast-in-place pile made of reinforced concrete;

[0033] Step 2A.3, installing and restoring the removed cover plate through the reserved steel bar opening corresponding to the pile steel bar of the completed pile foundation;

[0034] The pile reinforcement of each pile foundation is connected to the corresponding sealing plate by plug welding, and is fixed to the corresponding B-type pile working pipe by a fillet weld formed by welding.

[0035] Preferably, in step 2, each of the pile foundations is a steel pipe pile; when each of the B-type pile working pipes is prefabricated in the factory, a pile opening and a sealing plate are reserved at the location where each of the pile foundations is set;

[0036] Each of the sealing plates is fixed to the corresponding B-type pile working pipe by a fillet weld formed by welding;

[0037] The specific construction steps are as follows:

[0038] Step 2B.1, remove the sealing plate at the position where the pile foundation needs to be set in each B-type pile working tube to expose the corresponding pile position opening;

[0039] Step 2B.2, drilling holes at each exposed pile position and setting up static pressure equipment to press each pile foundation into a pile;

[0040] Step 2B.3, restore the removed sealing plate by welding it to the pile foundation.

[0041] More preferably, the length of each of the pile foundations is determined based on anti-floating calculations of subsequent excavation construction after the bundled slab is formed.

[0042] Preferably, step 3 is as follows:

[0043] Step 3.1, using the reserved openings on the web of each pipe segment to penetrate a plurality of corrugated pipes perpendicular to the length direction of each pipe segment, and using the corrugated pipes to pull and penetrate the prestressed steel strands;

[0044] Step 3.2, pouring concrete on all the pipe sections except the two outermost pipe sections and between all the pipe sections;

[0045] Step 3.3, tensioning the prestressed steel strands in the two outermost pipe sections, and anchoring both ends of the tensioned prestressed steel strands in the two outermost pipe sections;

[0046] Step 3.4: pour concrete in the two outermost pipe sections to form the integrally stressed bundled slab floor.

[0047] Beneficial effects of the present invention:

[0048] The present invention can reduce the impact of the upper cover development on the operating subway tunnel below, control the construction risk, and reduce the project investment, and has better economic and social benefits compared with the prior art.

[0049] On the one hand, the present invention, by tensioning prestressed tendons, bundles discrete, small-section rectangular steel pipe groups into an integral structure that can bear lateral forces, breaks the whole into parts, and realizes the development of the upper cover of a basement building in an ultra-close distance above an existing tunnel without sensible disturbance.

[0050] On the other hand, after constructing the pull-out piles in the bundled slab, the foundation pit above is excavated, which can realize the construction of the basement at an ultra-close distance to the existing tunnel, and fundamentally solve the problem of unloading the soil first and then controlling the foundation pit excavation for basement construction in the conventional practice. At the same time, the structure has high rigidity and small controlled deformation, which can better control the floating of the existing tunnel.

[0051] The present invention can optimize a large number of temporary projects such as soil reinforcement, anti-floating slabs, etc. The bundled slab can also be used as the upper cover to develop the basement floor, realizing the combination of permanent and temporary projects, which is green and environmentally friendly.

[0052] The concept, specific structure and technical effects of the present invention will be further described below in conjunction with the accompanying drawings to fully understand the purpose, characteristics and effects of the present invention. BRIEF DESCRIPTION OF THE DRAWINGS

[0053] Figure 1 A schematic diagram showing the situation in the prior art where the construction and operation of the subway comes first, the land is traversed by the built shield tunnel, and then the upper cover development is carried out.

[0054] Figure 2 A schematic plan view of a bundled slab ground on an existing tunnel according to an embodiment of the present invention is shown.

[0055] Figure 3 A schematic diagram showing the execution of step 1 in an embodiment of the present invention is shown.

[0056] Figure 4 A schematic diagram showing the execution of step 2 in an embodiment of the present invention is shown.

[0057] Figure 5 A schematic diagram of a partially enlarged structure of a pile foundation connected to a B-type pile working pipe in one embodiment of the present invention is shown.

[0058] Figure 6 A schematic diagram of a partially enlarged structure of a pile foundation in one embodiment of the present invention when the pile foundation is a steel pipe pile connected to a B-type pile working pipe is shown.

[0059] Figure 7 A schematic diagram showing the execution of step 3 in an embodiment of the present invention is shown.

[0060] Figure 8 A schematic diagram showing the state of a pipe segment tensioning a prestressed steel strand in one embodiment of the present invention is shown.

[0061] Fig. 9 A schematic diagram showing the execution of step 4 in an embodiment of the present invention is shown.

[0062] Fig.10 A schematic diagram showing the execution of step 5 in an embodiment of the present invention is shown.

[0063] Fig.11A schematic diagram showing the execution of step 6 in an embodiment of the present invention is shown. DETAILED DESCRIPTION

[0064] Example

[0065] like Figures 2 to 11 As shown, a method for constructing a building including a basement by using a bundled slab-ground structure on an existing tunnel comprises the following steps:

[0066] Step 1: In the soil above the existing tunnel 1, according to the design requirements of the basement building 20, the jacking construction of each pipe segment of the bundled slab 5 is completed;

[0067] Step 2: Workers enter each B-type pile working pipe 7 where pile foundation 9 needs to be set, and use small equipment to construct the corresponding pile foundation 9;

[0068] Step 3: pour concrete in and between each pipe segment, tension the prestress and anchor it at the end, complete the construction of the bundled slab 5, realize the anti-floating control of the existing tunnel 1 and the isolation of the disturbance caused by the construction of the upper part including the basement;

[0069] Step 4, excavating the foundation pit 19 to the bundled slab ground 5;

[0070] Step 5, using the bundled slab 5 as a construction site, developing the upper cover of the basement building 20 with a freely selectable structural type, and serving as the raft foundation of the basement building 20;

[0071] Step 6: Backfill the soil to the ground 2 to complete the basement construction including the basement building 20, and continue to construct the part of the basement building 20 located on the ground 2.

[0072] In some embodiments, step 1 is as follows:

[0073] Step 1.1, according to the basement range 3 including the basement building 20, two working shafts 4 are constructed at positions corresponding to the bundled slab 5 on both sides of the existing tunnel 1;

[0074] Step 1.2, in the soil above the existing tunnel 1, according to the bottom elevation of the basement including the basement building 20, each pipe section of the bundled slab 5 is pushed from one working shaft 4 to another working shaft 4;

[0075] Every two adjacent pipe sections are connected by a lock buckle 8;

[0076] All pipe sections include multiple A-type standard pipes 6 and multiple B-type pile working pipes 7;

[0077] Multiple A-type standard pipes 6 may be spaced between every two B-type pile working pipes 7 or between each B-type pile working pipe 7 and the side of the bundled slab 5;

[0078] Under each B-type pile working tube 7 , a plurality of pile foundations 9 are arranged along the length direction at positions corresponding to both sides of the existing tunnel 1 .

[0079] The net distance between each pipe segment and the existing tunnel 1 is not less than 0.2m.

[0080] The outer dimensions and wall thickness of each A-type standard pipe 6, and the number of A-type standard pipes 6 between each two B-type pile working pipes 7 or between each B-type pile working pipe 7 and the side of the bundled slab 5 are determined based on the anti-floating of the subsequent excavation construction after the formation of the bundled slab 5, and the force calculation of the raft slab containing the basement building 20 during the use stage;

[0081] The size of each B-type pile working pipe 7 is determined according to the size of the construction equipment used to construct the corresponding pile foundation 9, and is not less than 2.8 m.

[0082] The depth of each working well 4 is more than 1.5m deeper than the lower edge of the pipe section of the bundled plate floor 5.

[0083] like Figure 5 As shown, in some embodiments, in step 2, each pile foundation 9 is a cast-in-place pile; when each B-type pile working pipe 7 is prefabricated in the factory, a pile opening 10 and a sealing plate 11 are reserved at the location where each pile foundation 9 is set;

[0084] Each closure plate 11 is fixed to the corresponding B-type pile working pipe 7 by a fillet weld 12 formed by welding;

[0085] The specific construction steps are as follows:

[0086] Step 2A.1, remove the sealing plate 11 at the position where the pile foundation 9 is to be set in each B-type pile working tube 7 to expose the corresponding pile position opening 10;

[0087] Step 2A.2, setting up small construction equipment at each exposed pile opening 10 to carry out cast-in-place pile rapid construction;

[0088] Small construction equipment is a vertical pipe jacking machine;

[0089] The construction of cast-in-place pile rapid construction is as follows: after vertical hole formation, cement slurry is injected to maintain the stability of the hole wall, and after the pile reinforcement 13 of the corresponding pile foundation 9 is sunk, concrete is poured underwater to form a cast-in-place pile made of reinforced concrete;

[0090] Step 2A.3, install and restore the removed cover plate 11 through the reserved steel bar opening corresponding to the pile steel bar 13 of the completed pile foundation 9;

[0091] The pile reinforcement 13 of each pile foundation 9 is connected to the corresponding sealing plate 11 by plug welding, and is fixed to the corresponding B-type pile working pipe 7 by the fillet weld 12 formed by welding to ensure water-stopping performance.

[0092] like Figure 6 As shown, in some embodiments, in step 2, each pile foundation 9 is a steel pipe pile; when each B-type pile working pipe 7 is prefabricated in the factory, a pile opening 10 and a sealing plate 11 are reserved at the location where each pile foundation 9 is set;

[0093] Each closure plate 11 is fixed to the corresponding B-type pile working pipe 7 by a fillet weld 12 formed by welding;

[0094] The specific construction steps are as follows:

[0095] Step 2B.1, remove the sealing plate 11 at the position where the pile foundation 9 is to be set in each B-type pile working tube 7 to expose the corresponding pile position opening 10;

[0096] Step 2B.2, set up static pressure equipment in each exposed pile opening 10, and press each pile foundation 9 into a pile;

[0097] Step 2B.3, restore the removed sealing plate 11 by welding it to the completed pile foundation 9.

[0098] In practical applications, the pile foundation 9 of the steel pipe pile is directly connected to the cover plate 11 by welding, without reserving steel bar openings and punching and plug welding the pile steel bars 13 .

[0099] The length of each pile foundation 9 is determined based on the anti-floating calculation of the subsequent excavation construction after the bundled slab 5 is formed.

[0100] In some embodiments, step 3 is as follows:

[0101] Step 3.1, using the reserved openings 17 on the web of each pipe segment 6 to penetrate a plurality of corrugated tubes 18 perpendicular to the length direction of each pipe segment 6, and using the corrugated tubes 18 to pull and penetrate the prestressed steel strands 15;

[0102] Step 3.2, pouring concrete on all pipe segments 6 except the two outermost pipe segments 6 and between all pipe segments 6;

[0103] Step 3.3, tensioning the prestressed steel strand 15 in the two outermost A-type standard tubes 6, and anchoring both ends of the tensioned prestressed steel strand 15 in the two outermost A-type standard tubes 6;

[0104] Step 3.4: pour concrete into the two outermost A-type standard pipes 6 to form an integrally stressed bonded slab floor 5.

[0105] Prestressing, grouting inside the corrugated pipe and anchoring are all routine operations in post-tensioning prestressing construction and will not be elaborated here.

[0106] The preferred specific embodiments of the present invention are described in detail above. It should be understood that a person skilled in the art can make many modifications and changes based on the concept of the present invention without creative work. Therefore, any technical solution that can be obtained by a person skilled in the art through logical analysis, reasoning or limited experiments based on the concept of the present invention on the basis of the prior art should be within the scope of protection determined by the claims.

Claims

1. A method for constructing a building including a basement by using a bundled slab-ground structure on an existing tunnel; characterized in that: The steps include: Step 1: In the soil above the existing tunnel (1), according to the design requirements of the basement building (20), the jacking construction of each pipe segment of the bundled slab (5) is completed; Step 2: Workers enter each B-type pile working pipe (7) where a pile foundation (9) is to be set, and use small equipment to construct the corresponding pile foundation (9); Step 3, pouring concrete in each pipe segment and between the pipe segments, tensioning prestress and anchoring at the ends, completing the construction of the bundled slab (5), achieving anti-floating control of the existing tunnel (1) and isolation of construction disturbance of the upper basement building (20); Step 4, excavating a foundation pit (19) to the bundled slab floor (5); Step 6: Backfill the soil to the ground (2), complete the basement construction of the basement-containing building (20), and continue to construct the part of the basement-containing building (20) located on the ground (2).

2. The method for constructing a building including a basement by using a bundled slab-ground structure on an existing tunnel according to claim 1, characterized in that: Step 1 is as follows: Step 1.1, according to the basement range (3) of the basement building (20), two working shafts (4) are constructed at positions corresponding to the bundled slab ground (5) on both sides of the existing tunnel (1); Step 1.2, in the soil above the existing tunnel (1), according to the bottom elevation of the basement of the basement building (20), each pipe segment of the bundled slab ground (5) is pushed from one working shaft (4) to another working shaft (4); Every two adjacent pipe sections are connected via a lock buckle (8); All the pipe sections (6) include a plurality of A-type standard pipes (6) and a plurality of B-type pile working pipes (7); A plurality of the A-type standard tubes (6) may be spaced between each two of the B-type pile working tubes (7) or between each of the B-type pile working tubes (7) and the side edge of the bundled floor plate (5); Under each of the B-type pile working pipes (7), a plurality of pile foundations (9) are arranged along the length direction at positions corresponding to both sides of the existing tunnel (1).

3. The method for constructing a building including a basement by using a bundled slab-ground structure on an existing tunnel according to claim 2, characterized in that: The net distance between each pipe segment and the existing tunnel (1) is not less than 0.2 m.

4. The method for constructing a building including a basement by using a bundled slab-ground structure on an existing tunnel according to claim 2, characterized in that: The outer dimensions and wall thickness of each pipe section of the A-type standard pipe (6), and the number of the A-type standard pipes (6) between each two B-type pile working pipes (7) or between each B-type pile working pipe (7) and the side of the bundled slab (5) are all determined based on the subsequent anti-floating construction after the formation of the bundled slab (5) and the force calculation of the raft slab as the basement building (20) during the use stage; The size of each B-type pile working pipe (7) is determined according to the size of the construction equipment used to construct the corresponding pile foundation (9), and is not less than 2.8 m.

5. The method for constructing a building including a basement by using a bundled slab-ground structure on an existing tunnel according to claim 2, characterized in that: The depth of each working well (4) is more than 1.5 m deeper than the lower edge of the pipe section of the bundled plate floor (5).

6. The method for constructing a building including a basement by using a bundled slab-ground structure on an existing tunnel according to claim 1, characterized in that: In step 2, each of the pile foundations (9) is a cast-in-place pile; when each of the B-type pile working pipes (7) is prefabricated in the factory, a pile opening (10) and a sealing plate (11) are reserved at the location where each of the pile foundations (9) is set; Each of the sealing plates (11) is fixed to the corresponding B-type pile working pipe (7) by a fillet weld (12) formed by welding; The specific construction steps are as follows: Step 2A.1, removing the sealing plate (11) at the position where the pile foundation (9) is to be set in each B-type pile working tube (7) to expose the corresponding pile position opening (10); Step 2A.2, setting up small construction equipment at each exposed pile opening (10) to carry out cast-in-place pile rapid construction; The small construction equipment is a vertical pipe jacking machine; The quick pile construction of the cast-in-place pile is as follows: after vertical hole formation, cement slurry is injected to maintain the stability of the hole wall, and after the pile reinforcement (13) of the corresponding pile foundation (9) is sunk, concrete is poured underwater to form the cast-in-place pile made of reinforced concrete; Step 2A.3, installing and restoring the removed cover plate (11) through the reserved steel bar opening corresponding to the pile steel bar (13) of the completed pile foundation (9); The pile reinforcement (13) of each pile foundation (9) is connected to the corresponding sealing plate (11) by plug welding, and is fixed to the corresponding B-type pile working pipe (7) by a fillet weld (12) formed by welding.

7. The method for constructing a building with a basement using a bundled slab-ground structure on an existing tunnel according to claim 1, characterized in that: In step 2, each of the pile foundations (9) is a steel pipe pile; when each of the B-type pile working pipes (7) is prefabricated in the factory, a pile opening (10) and a sealing plate (11) are reserved at the location where each of the pile foundations (9) is set; Each of the sealing plates (11) is fixed to the corresponding B-type pile working pipe (7) by a fillet weld (12) formed by welding; The specific construction steps are as follows: Step 2B.1, remove the sealing plate (11) at the position where the pile foundation (9) is to be set in each B-type pile working tube (7) to expose the corresponding pile position opening (10); Step 2B.2, installing static pressure equipment in each exposed pile opening (10) to press each pile foundation (9) into a pile; Step 2B.3, restore the removed sealing plate (11) by welding it to the completed pile foundation (9).

8. The method for constructing a building including a basement on an existing tunnel using a bundled slab-ground structure according to claim 6 or 7, characterized in that: The length of each pile foundation (9) is determined based on the anti-floating calculation of the subsequent excavation construction after the bundled slab ground (5) is formed.

9. The method for constructing a building with a basement on an existing tunnel using a bundled slab-ground structure according to claim 1, characterized in that: Step 3 is as follows: Step 3.1, using the reserved openings (17) on the web of each pipe segment (6) to penetrate a plurality of corrugated tubes (18) perpendicular to the length direction of each pipe segment (6), and using the corrugated tubes (18) to pull and penetrate the prestressed steel strands (15); Step 3.2, pouring concrete on all the pipe sections (6) except the two pipe sections (6) located on the outermost sides, and between all the pipe sections (6); Step 3.3, tensioning the prestressed steel strand (15) in the two outermost A-type standard tubes (6), and anchoring the two ends of the tensioned prestressed steel strand (15) in the two outermost A-type standard tubes (6); Step 3.4: pour concrete into the two outermost A-type standard pipes (6) to form the integrally stressed bundled slab floor (5).