Prefabricated part for cable pipe gallery construction, formwork sliding system and construction method

By designing the base plate and side plate connectors and formwork slip system, the problems of long construction cycles and difficult to detect gaps in traditional cable pipeline construction have been solved, and the continuous construction of cable pipeline corridors and the improvement of geological disaster resistance has been achieved.

CN119061935AActive Publication Date: 2024-12-03CHINA MCC17 GRP CO LTD
View PDF 3 Cites 0 Cited by

Patent Information

Application Number
CN202411186961.6
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-28
Publication Date
2024-12-03
Estimated Expiration
2044-08-28

AI Technical Summary

Technical Problem

The traditional cable pipeline construction methods have problems such as long construction cycles, difficult to detect gaps and weak resistance to geological disasters. The prefabricated assembly method is easy to miss relying on manual experience, so it is impossible to achieve continuous construction.

Method used

A cable and pipe gallery construction method including bottom plate, side plate prefabricated parts and formwork slip system was designed. Continuous construction is achieved through the design of bottom plate and side plate connectors, and the formwork slip system is used to reduce the frequency of formwork disassembly and assembly, and increase concrete Contact area and steel bar arrangement to enhance structural stability.

Benefits of technology

The continuous construction of cable and pipe corridors has been achieved, the construction cycle has been reduced, the risk of gaps and geological disasters has been avoided, and the construction efficiency and the disaster resistance of the structure have been improved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119061935A_ABST
    Figure CN119061935A_ABST
Patent Text Reader

Abstract

The invention discloses a prefabricated part for cable pipe gallery construction, a formwork sliding system and a construction method, and belongs to the technical field of cable pipe gallery structures. The prefabricated parts comprise side plate prefabricated parts, side plate connecting parts, bottom plate connecting parts and top plate prefabricated parts, the side plate prefabricated parts are matched with the bottom plate, the top ends of the side plate prefabricated parts are matched with the top plate prefabricated parts, and the side plate connecting parts are matched with the two ends of the side plate prefabricated parts; the side plate prefabricated part and the side plate formwork are installed on the formwork sliding system to move. The method comprises the following steps: S1, excavating earthwork; s2, constructing a cushion layer; s3, the steel bars are bundled for the first time; s4, pouring a bottom plate; s5, the steel bars are bundled for the second time; s6, side plate pouring; s7, moving a template sliding system; s8, mounting a top plate prefabricated part; the problems that gaps are caused by traditional interval construction and splicing, only one working procedure can be conducted in the same period through a traditional open excavation cast-in-place method, and the resistance of a traditional pipe gallery to geological disasters is poor are solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention belongs to the technical field of cable corridor structures, and specifically relates to a prefabricated component for cable corridor construction, a template sliding system and a construction method. Background Art

[0002] At present, with the rapid development of urbanization, the demand for infrastructure construction is increasing, but the traditional cable gallery construction method can no longer meet the growing construction needs.

[0003] Prefabrication technology is increasingly being used in the construction industry. Its maturity and reliability have been proven, providing more possibilities for new cable gallery construction methods.

[0004] At present, the construction of cable corridors is mainly based on open-cut cast-in-place method and prefabricated assembly method. However, the entire corridor is constructed by pouring concrete. Although the structure is relatively strong, the construction period is long. Only a single process can be carried out in the same period. The installation formwork needs to be frequently removed. At the same time, the concrete needs time to solidify and form. This leads to the need for interval construction during construction. Gaps are prone to appear between adjacent corridors. The gaps are not easy to be found during the construction process, which leads to risks such as water seepage in the later stage.

[0005] Prefabrication and assembly method: prefabricate corresponding shaped templates or concrete prefabricated parts in the factory and assemble them on the construction site. The construction is convenient and less polluting. However, due to the tolerances between prefabricated parts and the gaps between panels, additional layers need to be added manually. This method completely relies on manual experience and is prone to omissions. In addition, the panels are not a whole and have weak resistance to geological disasters.

[0006] After searching, the publication number CN106759478B provides a method for constructing a prefabricated pipe gallery, which includes the following steps: 1. Construction of prefabricated components: prefabricate the outer wall, the top plate and the bottom plate, and respectively set connectors at the upper and lower ends of the outer wall, the left and right ends of the top plate, and the left and right ends of the bottom plate; 2. Assembling prefabricated components: first hoist the bottom plate, then hoist the outer wall, and fix the connector at the lower end of the outer wall to the corresponding connector on the bottom plate, then install the formwork equipment, and finally hoist the top plate, and fix the connector at the upper end of the outer wall to the corresponding connector on the top plate; 3. Cast-in-place molding: pour concrete on the inner surface of the outer wall and the outer surface of the top plate;

[0007] However, the problem of gaps between two adjacent pipeline corridors still depends on the construction situation of the staff. The traditional on-site pouring of pipeline corridor construction has the problem that only a single process can be carried out in the same cycle, which slows down the progress of work. At the same time, it cannot resist geological disasters well. Summary of the invention

[0008] The technical problem to be solved by the present invention is to provide a prefabricated component, a template sliding system and a construction method for cable duct construction to solve the problems mentioned in the background technology or achieve better technical effects;

[0009] It includes a prefabricated component, a template sliding system and a construction method for cable duct construction;

[0010] A prefabricated component for cable duct construction, characterized in that it includes the bottom plate at the bottom of the duct, side plate prefabricated components, side plate connectors, bottom plate connectors, and top plate prefabricated components;

[0011] Concrete grooves are provided on the upper surface of the bottom plate. The bottom plate includes multiple bottom plates, and bottom plate connectors are connected between adjacent bottom plates;

[0012] The lower end of the side plate prefabricated component fits into the concrete groove. The left and right ends of the side plate prefabricated component fit into the side plate connectors to form a cavity. The side plate prefabricated component is provided with protrusions and connectors;

[0013] The side plate connector is provided with a first through hole, and the first through hole is located at the part where the side plate connector extends into the cavity; the side plate connector includes a part connecting adjacent left and right side plate prefabricated components, and the lower end of the side plate connector fits into the concrete groove;

[0014] The side plate prefabricated component is provided with prefabricated steel bars on the surface facing the cavity. Concrete is poured inside the cavity. The cross-sectional shape of the side plate connector is "zhong" (Chinese character for middle). The upper and lower ends of the "zhong" shape are the parts extending into the side plate cavity, and the left and right ends fit into the grooves at both ends of the adjacent side plate prefabricated components perpendicular to the construction direction. The left and right ends of the "zhong" shape are the parts extending into the grooves.

[0015] The concrete grooves are arranged on the left and right sides in the construction direction of the bottom plate. The bottom plate includes multiple bottom plates, and bottom plate connectors are connected between adjacent bottom plates. The bottom plate connectors are arranged parallel to the bottom plate. The bottom plate connectors are provided with second through holes. The cross-sectional shape of the bottom plate connectors is "cross" (Chinese character for cross). The second through holes are located at the part where the bottom plate connectors extend into the concrete, increasing the contact area with the concrete. It is convenient to move by connecting the template sliding device through the connectors. The top plate prefabricated component is positioned by the protrusions, facilitating construction. The side plate steel bars enable the side plate prefabricated component to be closely combined with the concrete. The connectors are provided with through holes, reducing the weight while increasing the contact area with the concrete and making the connection more firm. The side plate connector with a "zhong" - shaped cross-section can extend into the cavity, strengthening the connection between adjacent side plates, and at the same time, can be embedded in the side plate prefabricated component to play a fixing function.

[0016] Concrete grooves are arranged on both sides of the bottom plate, and the concrete grooves are matched with the lower ends of the side plate prefabricated parts. Bottom plate connectors are connected between multiple bottom plates, and the bottom plate connectors are arranged parallel to the bottom plates. The bottom plate connectors are provided with second through holes, and the cross-sectional shape of the bottom plate connectors is a "cross" shape; the positions of the side plate prefabricated parts are positioned by the bottom plate concrete grooves, and the construction is more convenient. Through holes are provided on the bottom plate connectors, which reduce the weight while increasing the contact area with the concrete, and firmly connect the adjacent bottom plates; the concrete grooves are constructed when the bottom plate is poured, and the parallelly arranged bottom plate connectors connect the adjacent bottom plates, so that the bottom plate forms a whole, thereby increasing the resistance to geological disasters.

[0017] A template sliding system for cable corridor construction. The template sliding system of the present invention is adapted to the prefabricated parts of the present invention and is not completely the same as a conventional template sliding system. The template sliding system comprises a main frame, an aisle is arranged on the upper surface of the frame, a moving device is installed at the lower end of the main frame base, a hook and cable device is arranged on the upper part of the main frame, and the hook and lock device cooperates to connect the side panel prefabricated parts (2) and connect the prefabricated parts and the side panel templates (7). Through the cooperation between the moving device and the hook and cable device on the template sliding system, workers do not need to repeatedly disassemble and assemble the side wall templates, but only need to replenish the prefabricated parts. At the same time, the moving device drives the overall movement of the equipment, thereby improving work efficiency.

[0018] The present invention also discloses a cable corridor construction method, which comprises the following steps:

[0019] S1. Excavation of earthwork: According to the measurement control points and construction drawings, the construction trenching line is accurately laid out and confirmed by both parties. During the excavation process, the thickness of the reserved earthwork is strictly controlled. A grid is placed at the bottom of the trench before manual trench cleaning. Construction is carried out according to the elevation points to ensure the construction quality;

[0020] S2. Pad construction: According to the design requirements, the edge line of the concrete pad is accurately laid out, and square wood is used to fix the side formwork. After passing the inspection, the concrete pouring operation can be carried out. The concrete pad uses commercial concrete and is transported by a mixer truck. According to the actual situation on site, a suitable method is selected for pouring, such as a chute or a concrete delivery pump. A flat vibrator is used to ensure that the concrete is dense, and then a wooden trowel is used for detailed leveling work to achieve the expected flatness and quality standards.

[0021] S3. First steel bar bundling: bundling bottom plate steel bars and side plate wall vertical bars;

[0022] S4. Floor casting: Floor templates are installed around the floor. The floor templates include floor connectors. Adjacent floor plates are connected with floor connectors. After the floor templates are installed and fixed, casting begins.

[0023] S5. Second reinforcement bundling: bundling the transverse reinforcement of the side panel wall;

[0024] S6. Side panel casting: The hook device on the template sliding system connects the corresponding side panel template and the side panel connector. After confirming that the connection is firm, the construction begins on site. The side panel template and the side panel connector are installed at the side panel reinforcement. The side panel template is a double-layer structure. The side panel template is a conventional template with a hollowed-out middle portion of the outer layer, and the inner layer is a prefabricated side panel. After the side panel template and the side panel connector are installed, a support device is installed at the corresponding position of the outer wall inside the side panel to support the inner layer prefabricated side panel. At the same time, it is manually confirmed that the outer side of the side panel template is fixed to the hook device of the template sliding system, and the inner prefabricated panel is not fixed to the hook device on the template sliding system. After confirmation, casting begins;

[0025] S7. Move the template sliding system: After completing the subsequent work of pouring, loosen the fastening device, leaving the inner side panel prefabricated parts and the corresponding supporting devices, move the template sliding system to the next side panel pouring position, and reinstall the corresponding prefabricated parts; after confirming that it is fixed in place, repeat S6 until the construction is completed;

[0026] S8. Install the top plate prefabricated parts: After the side plates are solidified, install the top plate prefabricated parts. After they are fixed, remove the side plate fixing devices, and carry out external waterproofing, internal decoration and other operations;

[0027] When pouring the bottom plate, the bottom plate connector is used as the template for the connection. After the bottom plate solidifies, it becomes an integral part, which solves the gap caused by the interval construction and realizes the continuous construction of the bottom plate. On the basis of the continuous construction of the bottom plate, through the template sliding system, during the construction of the side plate, through the cooperation of the side plate template and the side plate prefabricated parts and connectors, the frequent disassembly and assembly of the template is avoided. At the same time, the side plate connector connects the two adjacent side plates, and after solidification, the adjacent side plates are connected as a whole to avoid the appearance of gaps. At the same time, the template prefabricated parts undertake part of the side plate template tasks. After the initial solidification, the external template can be removed, and the side plate prefabricated parts are reinforced and moved to the next construction position for uninterrupted construction.

[0028] Furthermore, the base plate connector is included in the base plate formwork, and the base plate connector becomes one with the base plate after pouring is completed. The base plate connector connects two adjacent base plates; the adjacent components are connected as one, the connection is more stable, and the gaps in traditional pouring and splicing are avoided.

[0029] Furthermore, sand wells and drainage pipes are arranged at intervals before pouring the base plate. When the base plate template is installed on the base plate, the surface of the base plate template is coated with a motor oil release agent to enhance drainage and ventilation capabilities. The release agent is a conventional choice.

[0030] Furthermore, the bottom plate formwork is fixed by tension bolts, and a PVC pipe is provided outside the tension rod between the formworks.

[0031] Furthermore, the casting surface of the side panel precast part is provided with precast steel bars, the top view cross section of the side panel precast part is a parallelogram, the side panel precast part, the side panel connector and the poured concrete together form the side panel, the steel bars and the concrete are more closely connected, and at the same time the on-site pouring amount of concrete is reduced.

[0032] Furthermore, a connecting piece is provided above the side panel prefabricated part, and the connecting piece is a lifting ring. A protrusion is provided on the top of the side panel prefabricated part, and the protrusion cooperates with the positioning groove on the bottom surface of the top panel prefabricated part; the connecting piece cooperates with the template sliding system to facilitate disassembly, and the cooperation between the protrusion and the positioning groove facilitates the positioning of the top panel prefabricated part.

[0033] Furthermore, connecting prefabricated parts are installed between the side panels, and the connecting prefabricated parts; the side panel connecting parts are part of the side panel formwork, taking on part of the support, and the connecting parts are matched with the side panel connecting parts.

[0034] Compared with the prior art, the present invention can achieve the following technical effects:

[0035] During the bottom plate construction, the bottom plate connector is used as a part of the bottom plate formwork. At the same time, when the concrete solidifies, the bottom plate is integrated into one to achieve continuous construction of adjacent bottom plates, avoiding the problem of uneven docking caused by interval construction. On the basis of the completion of the bottom plate construction, the side plate wall steel bars are tied. At the same time, the bottom plate is continuously constructed without waiting for the remaining steps. After the steel bars are tied, the formwork sliding system enters the site to install the inner side plate prefabricated parts and the outer side plate formwork. The side plate connectors are installed at the side plate joints. The side plate connectors are fixed with the side plate prefabricated parts. At the same time, the prefabricated steel bars are set on the concrete pouring surface of the side plate prefabricated parts, which can be tightly combined with the concrete. After the pouring is completed, the side plate prefabricated part support device is installed, and the outer side plate can be removed at this time. The template is used to move the template sliding system to the next side panel casting location. The side panel prefabricated parts are moved by the template sliding system to avoid the need for a large number of templates in traditional casting. Only side panel prefabricated parts and side panel connectors need to be added, which greatly reduces work pressure and realizes continuous construction, avoiding the problem of only being able to complete one process within a cycle. At the same time, the side panel connectors connect adjacent side panels and serve as part of the template, so that the side panel construction can be carried out continuously, improving work efficiency and avoiding the problem of misalignment of traditional prefabricated parts and cracks at the end of casting. At the same time, the bottom plate connectors cooperate with the side panel connectors and the bottom plate and side panels to make the structure a whole, and the metal prefabricated parts and connectors have a certain toughness, which greatly improves the resistance to geological disasters.

[0036] The top uses prefabricated top plates, which improves work efficiency. The prefabricated top plates can also be customized in the factory according to different functions, shortening the subsequent decoration time. BRIEF DESCRIPTION OF THE DRAWINGS

[0037] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, for ordinary technicians in this field, other drawings can be obtained based on these drawings without paying any creative work.

[0038] Figure 1 It is the installation drawing of the side panel prefabricated parts and the side panel formwork;

[0039] Figure 2 It is a cross-sectional structural diagram of the pipe gallery;

[0040] Figure 3 It is a cross-sectional view of the side panel connection;

[0041] Figure 4 It is the cross-sectional view of the base plate connection;

[0042] Figure 5 It is the structural diagram of the bottom plate connection;

[0043] Figure 6 This is the structural diagram of the side panel connector.

[0044] In the figure: 1. bottom plate, 2. side plate precast parts, 3. concrete, 4. lifting rings, 5. top plate precast parts, 6. protrusions, 7. side plate formwork, 8. precast steel bars, 9. side plate wall vertical bars, 10. side plate wall transverse bars, 11. formwork sliding system, 12. bottom plate connector, 13. side plate connector, 14. first through hole, 15. second through hole. DETAILED DESCRIPTION

[0045] In order to make the purpose, technical solution and advantages of the present invention more clearly understood, the present invention is further described in detail below in conjunction with the embodiments. It should be understood that the specific embodiments described herein are only used to explain the present invention and are not used to limit the present invention.

[0046] The application principle of the present invention is further described below in conjunction with the accompanying drawings and specific embodiments.

[0047] Example 1

[0048] A prefabricated component for cable corridor construction, comprising a bottom plate 1 at the bottom of the corridor, a side plate prefabricated component 2, a side plate connecting component 13, a bottom plate connecting component 12, and a top plate prefabricated component 5;

[0049] A concrete groove is provided on the upper surface of the bottom plate 1, and the bottom plate 1 includes a plurality of bottom plates 1, and bottom plate connectors 12 are connected between adjacent bottom plates 1;

[0050] The lower end of the side plate precast member 2 is fitted into the concrete trough, and the left and right ends of the side plate precast member 2 are fitted with the side plate connecting member 13 to form a cavity. A protrusion 6 and a connecting member are provided at the top end of the side plate precast member 2; the concrete trough is formed during the pouring of the bottom plate 1.

[0051] The side plate connecting member 13 is provided with a first through hole 14, and the first through hole 14 is located at the part where the side plate connecting member 13 extends into the cavity; the side plate connecting member 13 includes a part connecting adjacent side plate precast members 2, and the lower end of the side plate connecting member 13 is fitted into the concrete trough.

[0052] The cross-sectional shape of the side plate connecting member 13 is "zhong" (Chinese character for middle). The upper and lower ends of the "zhong" character are the parts extending into the side plate cavity, and the first through hole 14 is provided on the parts extending into the side plate cavity. The left and right ends of the "zhong" character are fitted with the grooves at the two ends perpendicular to the construction direction of the adjacent side plate precast members 2. The left and right ends of the "zhong" character are the parts extending into the grooves. The side plate precast member 2 is provided with precast member steel bars 8 on the surface facing the cavity, and concrete is poured inside the cavity.

[0053] The concrete trough is arranged on the left and right sides in the construction direction of the bottom plate 1. The bottom plate 1 includes a plurality of continuous bottom plates 1, and a bottom plate connecting member 12 is connected between adjacent bottom plates 1. The bottom plate connecting member 12 is arranged parallel to the bottom plate 1. The bottom plate connecting member 12 is provided with a second through hole 14, and the cross-sectional shape of the bottom plate connecting member 12 is "cross" shape, and the second through hole 14 is located on the part where the bottom plate connecting member 12 extends into the concrete.

[0054] A formwork sliding system for cable pipe gallery construction includes a side plate precast member 2, a side plate connecting member 13, a bottom plate connecting member 12, and a top plate precast member 5, any kind of precast member for cable pipe gallery construction. It is characterized in that: the formwork sliding system includes a main frame, a passage is arranged on the upper surface of the frame, a moving device is installed at the lower end of the base of the main frame, a hook and cable device is arranged at the upper part of the main frame, the hook and lock device is connected and fitted with the side plate precast member 2, and connects the precast member and the side plate formwork 7.

[0055] A cable pipe gallery construction method, a precast member for cable pipe gallery construction, and a formwork sliding system include the following steps:

[0056] S1. Earthwork excavation: According to the measurement control points and construction drawings, accurately set out the construction trench line, and after double-check and confirmation by both parties, strictly control the reserved soil thickness during the excavation process. Before manual trench cleaning, a grid is placed at the bottom of the trench, and construction is carried out according to the elevation points to ensure construction quality.

[0057] S2. Pad construction: According to the design requirements, the edge line of the concrete pad is accurately laid out, and square wood is used to fix the side formwork. After passing the inspection, pouring can be carried out. The concrete pad uses commercial concrete and is transported by a mixer truck. According to the actual situation on site, a suitable method is selected for pouring, such as a chute or concrete delivery pump. A flat vibrator is used to ensure that the concrete is dense, and then a wooden trowel is used for detailed leveling work to achieve the expected flatness and quality standards.

[0058] S3, first steel bar bundling: bundling the bottom plate 1 steel bar and the side plate wall vertical bar 9;

[0059] S4, bottom plate pouring: bottom plate templates are installed around the bottom plate 1, and the bottom plate templates include bottom plate connectors 12. Bottom plate connectors 12 are set at the connection between adjacent bottom plates 1. After the bottom plate templates are installed and fixed, pouring begins;

[0060] S5. Second steel bar bundling: bundling 10 transverse bars of the side panel wall;

[0061] S6, side panel casting: the hook cable device on the template sliding system 11 is connected to the corresponding side panel template 7 and the side panel connector 13. After confirming that the connection is firm, the construction is started, and the side panel template 7 and the side panel connector 13 are installed at the casting position. The side panel template 7 is a double-layer structure, and the outer layer of the side panel template 7 is a conventional template with a hollowed-out middle portion, and the inner layer is the side panel prefabricated part 2. After the side panel template 7 and the side panel connector 13 are installed, a support device is installed at the corresponding position of the outer wall inside the side panel to support the inner layer side panel prefabricated part 2. At the same time, the outer side of the side panel template 7 is manually fixed to the hook cable device on the template sliding system 11. After confirmation, casting begins;

[0062] S7, moving the template sliding system 11: after completing the subsequent work of pouring, loosen the fastening device, leaving the inner side panel prefabricated part 2 and the corresponding supporting device, and move the template sliding system 11 to the next side panel pouring position, and reinstall the corresponding prefabricated part; after confirming that it is fixed in place, repeat S6 until the construction is completed;

[0063] S8. Install the top plate prefabricated parts 5: After the concrete 3 in the side plate is completely solidified, start installing the top plate prefabricated parts 5. After the installation and fixation, remove the side plate fixing devices, and carry out external waterproofing, internal decoration and other operations. The top plate prefabricated parts 5 can be poured and decorated in the factory according to the functions of the different corridor sections below.

[0064] The bottom plate connector 12 is integrated with the bottom plate 1 after pouring the bottom plate concrete, and the adjacent bottom plates 1 are connected as a whole, thereby enhancing the resistance to geological disasters.

[0065] The base plate formwork is fixed with tension bolts, and the tie rods between the formworks are wrapped with PVC pipes.

[0066] The side panel prefabricated member 2 has a parallelogram cross section when viewed from above. The side panel prefabricated member 2 , the side panel connecting member 13 and the concrete 3 together form the side panel.

[0067] A connecting piece is arranged above the side panel prefabricated part 2, and the connecting piece is a lifting ring 4. A protrusion 6 is arranged on the top of the side panel prefabricated part 2, and the protrusion 6 cooperates with the positioning groove on the bottom surface of the top panel prefabricated part 5. When installing the top panel prefabricated part 5, an angle grinder is used to remove the lifting ring to avoid the formation of gaps at the connection.

[0068] Before pouring the base plate, sand wells and drainage pipes are set at intervals. When installing the base plate formwork on the base plate 1, the formwork surface is coated with engine oil release agent.

[0069] It will be apparent to those skilled in the art that the present invention is not limited to the details of the exemplary embodiments described above and that the present invention can be implemented in other specific forms without departing from the spirit or essential features of the present invention. Therefore, the embodiments should be considered exemplary and non-restrictive in all respects, and the scope of the present invention is defined by the appended claims rather than the above description, and it is intended that all changes falling within the meaning and scope of the equivalent elements of the claims be included in the present invention.

[0070] In addition, it should be understood that although the present specification is described according to implementation modes, not every implementation mode contains only one independent technical solution. This description of the specification is only for the sake of clarity. Those skilled in the art should regard the specification as a whole. The technical solutions in each embodiment may also be appropriately combined to form other implementation modes that can be understood by those skilled in the art.

Claims

1. A prefabricated component for cable gallery construction, characterized in that: It includes the bottom plate (1) of the pipe gallery, The upper surface of the bottom plate (1) is provided with a concrete groove, the bottom plate (1) comprises a plurality of bottom plates, adjacent bottom plates (1) are connected with bottom plate connectors (12), and the concrete grooves are matched with side plate prefabricated parts (2); The left and right ends of the side panel prefabricated member (2) are matched with side panel connecting members (13) to form a cavity, and the top of the side panel prefabricated member (2) is provided with a protrusion (6) and a connecting member; The side panel connecting member (13) is provided with a first through hole (14), and the first through hole (14) is located at the portion where the side panel connecting member (13) extends into the cavity; the side panel connecting member (13) includes a portion for connecting adjacent side panel prefabricated members (2), and the lower end of the side panel connecting member (13) is matched with the concrete groove.

2. A prefabricated component for cable gallery construction according to claim 1, characterized in that: The cross-sectional shape of the side panel connecting member (13) is a "Z" shape; the upper and lower ends of the "Z" shape are portions extending into the side panel cavity, the left and right ends of the "Z" shape cooperate with the grooves at both ends of the adjacent side panel prefabricated member (2) perpendicular to the construction direction, the left and right ends of the "Z" shape are portions extending into the grooves, the side panel prefabricated member (2) is provided with prefabricated steel bars (8) facing the cavity surface, and concrete (3) is poured inside the cavity.

3. The prefabricated component for cable gallery construction according to claim 1, characterized in that: The concrete trough is arranged on the left and right sides of the bottom plate (1) in the construction direction. The bottom plate (1) comprises a plurality of continuous bottom plates (1). A bottom plate connecting piece (12) is connected between adjacent bottom plates (1). The bottom plate connecting piece (12) is arranged parallel to the bottom plate (1). The bottom plate connecting piece (12) is provided with a second through hole (14). The cross-sectional shape of the bottom plate connecting piece (12) is a "cross" shape.

4. A template sliding system for cable corridor construction, comprising a prefabricated component for cable corridor construction according to any one of claims 1 to 3, characterized in that: The template sliding system comprises a main frame, an aisle is arranged on the upper surface of the frame, a moving device is installed at the lower end of the main frame base, a hook and rope device is arranged on the upper part of the main frame, and the hook and lock device connects the prefabricated part and the side plate template (7).

5. A cable corridor construction method, comprising a prefabricated component for cable corridor construction according to claims 1-4, and a template sliding system, characterized in that: The following steps are involved: S1. Excavation of earthwork: According to the measurement control points and construction drawings, the construction trenching line is accurately laid out and confirmed by both parties. During the excavation process, the thickness of the reserved earthwork is strictly controlled. A grid is placed at the bottom of the trench before manual trench cleaning. Construction is carried out according to the elevation points to ensure the construction quality; S2. Pad construction: according to the design requirements, the edge line of the concrete pad is accurately laid out, and the side form is fixed with square wood. After passing the inspection, the pouring operation can be carried out. The concrete pad is made of commercial concrete and transported by a mixer truck. According to the actual situation on site, a suitable method is selected for pouring, such as a chute or a concrete delivery pump. A flat vibrator is used to ensure that the concrete is dense, and then a wooden trowel is used for detailed leveling work to achieve the expected flatness and quality standards; S3, first steel bar bundling: bundling the bottom plate (1) steel bars and the side plate wall vertical bars (9); S4, bottom plate pouring: a bottom plate template is installed around the bottom plate (1), the bottom plate template includes a bottom plate connecting piece (12), adjacent bottom plates (1) are connected with the bottom plate connecting piece (12), and after the bottom plate template is installed and fixed, pouring begins; S5. Second reinforcement bundling: bundling the transverse reinforcement of the side panel wall (10); S6, side panel casting: the hook cable device on the template sliding system (11) connects the corresponding side panel template (7) and the side panel connecting piece (13). After confirming that the connection is firm, the construction is started on site. The side panel template (7) and the side panel connecting piece (13) are installed at the casting position. The side panel template (7) is a double-layer structure. The outer layer of the side panel template (7) is a conventional template with a hollow middle portion, and the inner layer is a side panel prefabricated part (2). After the side panel template (7) and the side panel connecting piece (13) are installed, a support device is installed at a corresponding position of the outer wall inside the side panel to support the inner layer side panel prefabricated part (2). At the same time, the outer side of the side panel template (7) is manually fixed to the hook cable device on the template sliding system (11). After confirmation, casting begins; S7, moving the template sliding system (11): after completing the subsequent work of pouring, loosen the fastening device, leaving the inner side panel prefabricated part (2) and the corresponding supporting device, and move the template sliding system (11) to the next side panel pouring position, and reinstall the corresponding prefabricated part; after confirming that it is fixed in place, repeat S6 until the construction is completed; S8, installing the top plate prefabricated component (5): after the concrete (3) in the side plate is completely solidified, the top plate prefabricated component (5) is installed. After the installation is completed and fixed, the side plate fixing device is removed, and the outer layer waterproofing and internal decoration operations are carried out.

6. A cable corridor construction method according to claim 5, characterized in that: The base plate connecting piece (12) becomes one with the base plate (1) after casting is completed.

7. A cable corridor construction method according to claim 5, characterized in that: The bottom plate formwork is fixed by tension bolts, and the tie rods between the formworks are provided with PVC pipes for sealing.

8. A cable corridor construction method according to claim 5, characterized in that: The side panel prefabricated component (2) has a parallelogram cross-section when viewed from above. The side panel prefabricated component (2), the side panel connecting component (13) and the concrete (3) together form the side panel.

9. A cable corridor construction method according to claim 5, characterized in that: A connecting piece is arranged above the side plate prefabricated piece (2), and the connecting piece is a lifting ring (4). A protrusion (6) is arranged at the top of the side plate prefabricated piece (2), and the protrusion (6) is matched with a positioning groove on the bottom surface of the top plate prefabricated piece (5).

10. A cable corridor construction method according to claim 6, characterized in that: Before the base plate (1) is cast, sand wells and drainage pipes are arranged at intervals.

Citation Information

Patent Citations

  • A prefabricated pipe gallery construction method

    CN106759478B

  • Assembly type comprehensive pipe rack and assembly process thereof

    CN115807445A

  • Superimposed assembly-type underground pipe gallery system and construction and manufacturing process

    WO2017206412A1