Ultra-shallow-buried tunnel construction method capable of achieving rapid covering

By adopting the ultra-shallow buried tunnel construction method with rapid overlay on urban main lines and important roads, and using steel cover plates and advanced support technology to carry out construction in steps, the construction difficulties of tight ground land use and large traffic flow are solved. The effect of rapid traffic recovery is achieved.

CN119061938APending Publication Date: 2024-12-03XIAMEN MUNICIPAL ENGINEERING DESIGN INSTITUTE CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411400681.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-09
Publication Date
2024-12-03

AI Technical Summary

Technical Problem

During the construction of urban main lines and important roads, the ground land is tight and cannot be temporarily displaced, resulting in construction difficulties and affecting traffic. It is difficult for the existing technology to achieve rapid and partially interrupted construction methods.

Method used

The ultra-shallow buried tunnel construction method is adopted with a fast upper cover. By digging foundation troughs on the current road partition and the roadway, prefabricated steel cover plates are laid, and pavement layer is applied above the steel cover plates, combining advanced support and short The step method is used to dig tunnels under the stairs and carry out construction in steps to avoid temporary major redirects on the current roads and complete traffic interruption.

Benefits of technology

It has achieved significant shortening of construction time and rapid recovery of traffic without interrupting or only partially interrupting traffic, and is suitable for environments with tight ground land and large traffic flow.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119061938A_ABST
    Figure CN119061938A_ABST
Patent Text Reader

Abstract

The invention discloses a rapid covering ultra-shallow-buried tunnel construction method which comprises the following steps: S1, open cutting a foundation trench to a steel cover plate design site at a separation zone, hoisting and laying a prefabricated steel cover plate into the foundation trench, and laying a pavement layer above the steel cover plate; s2, open-digging a foundation trench at a roadway on one side of the separation strip to a design site of a steel cover plate, hoisting the prefabricated steel cover plate, paving the prefabricated steel cover plate into the foundation trench, and paving a pavement layer above the prefabricated steel cover plate; s3, open excavation of a foundation trench is carried out on a roadway on the other side of the separation strip to a steel cover plate design site, the prefabricated steel cover plate is hoisted and laid in the foundation trench, and a pavement layer is laid on the steel cover plate; and S4, an advance support is constructed, and the tunnel is subsurface excavated step by step under the steel cover plate and the advance support. The method does not need extra foundation construction, does not need temporary large line change on the current road, is short in construction operation time, and is especially suitable for a construction environment in which land is insufficient and traffic is only allowed to be locally interrupted for several hours.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of tunnel construction, and in particular to a method for constructing an ultra-shallow buried tunnel with rapid covering. Background Art

[0002] With the continuous improvement of the transportation network and the continuous advancement of urbanization, more and more roads need to pass under the city's main roads and lifelines. These main roads usually connect the main areas and important nodes of the city, bear a large amount of traffic flow, are very important, and cannot be completely interrupted. However, in the case of land shortages adjacent to housing plots and important pipelines on both sides of the road, it is impossible to borrow land, and there is no possibility of temporary relocation and rerouting. Often, in-situ construction can only be used, which seriously affects traffic and causes construction difficulties. Summary of the invention

[0003] The purpose of the present invention is to provide a method for constructing an ultra-shallow tunnel with rapid cover, so as to adapt to the construction environment where land is scarce and only partial traffic interruption is allowed.

[0004] In order to achieve the above object, the technical solution adopted by the present invention is as follows:

[0005] A method for constructing an ultra-shallow tunnel with rapid cover, comprising the following steps:

[0006] S1. Open-cut the foundation trench at the dividing strip of the existing road to the designed position of the steel cover, hoist and lay the prefabricated steel cover into the foundation trench, and lay the pavement layer on top of the steel cover;

[0007] S2. Open-cut the foundation trench at the carriageway on one side of the median strip to the designed position of the steel cover, hoist and lay the prefabricated steel cover into the foundation trench, and lay the pavement layer on top of the steel cover;

[0008] S3. Open-cut the foundation trench at the carriageway on the other side of the median strip to the designed position of the steel cover, hoist and lay the prefabricated steel cover into the foundation trench, and lay the pavement layer on top of the steel cover;

[0009] S4. Carry out advance support and excavate the tunnel in steps under the steel cover and advance support.

[0010] Furthermore, the steel cover plates are welded to each other, and the road surface layer is an asphalt surface layer.

[0011] Furthermore, the steel cover plate includes a top plate, a bottom plate and a web plate. The top plate and the bottom plate are arranged in parallel up and down, and the web plate is vertically welded between the top plate and the bottom plate and arranged in a grid shape.

[0012] Furthermore, a shear nail group is vertically welded on the upper side of the top plate, and a steel fiber concrete layer is laid above the top plate, and the shear nail group is buried in the steel fiber concrete layer.

[0013] Furthermore, a plurality of stiffening ribs are vertically welded on the lower side of the top plate and the upper side of the bottom plate, and the stiffening ribs on the top plate and the stiffening ribs on the bottom plate are arranged opposite to each other up and down.

[0014] Furthermore, in step S4, the tunnel excavation section is divided into several parts and the pilot tunnels of each part are excavated accordingly using the short step method, and each pilot tunnel adopts a composite lining.

[0015] Furthermore, the pilot tunnel includes a first pilot tunnel, a second pilot tunnel, a third pilot tunnel and a fourth pilot tunnel arranged in sequence along the length direction of the road, each pilot tunnel is divided into an upper step and a lower step, and each pilot tunnel is excavated cyclically according to the following steps until it is connected:

[0016] S41. Excavate the first pilot tunnel and the third pilot tunnel, and apply initial support, first temporary horizontal support and temporary vertical support, so that the corresponding initial support, first temporary horizontal support and temporary vertical support are closed into a ring;

[0017] S42. Remove the first temporary cross brace and then carry out secondary lining construction of the first and third pilot tunnels;

[0018] S43. Excavate the second pilot tunnel, and apply the initial support and the second temporary horizontal support, so that the corresponding initial support, the second temporary horizontal support and the temporary vertical support are closed into a ring, and the initial supports in the first pilot tunnel, the second pilot tunnel and the third pilot tunnel are connected to form a ring;

[0019] S44. Remove the second temporary horizontal brace and the corresponding temporary vertical brace, and then carry out the construction of the secondary lining of the second pilot tunnel;

[0020] S45. excavate the fourth pilot tunnel, and apply the initial support and the third temporary horizontal support, so that the corresponding initial support, the third temporary horizontal support and the temporary vertical support are closed into a ring, and the initial supports in the third pilot tunnel and the fourth pilot tunnel are connected to form a ring;

[0021] S46. Remove the third temporary horizontal brace and the corresponding temporary vertical brace, and then carry out the secondary lining construction of the fourth pilot tunnel.

[0022] Furthermore, in step S4, the upper step and the lower step are staggered by 4m for construction, and the excavation progress of each pilot tunnel cycle is within 0.5m.

[0023] Furthermore, the advance support in step S4 includes an advance pipe shed, a pipe shed arch and an advance small guide tube, and the steel cover plate is partially supported by the pipe shed arch.

[0024] Furthermore, the advance small conduit and the advance conduit in the advance pipe rack are arranged along the excavation contour line on the side of the guide tunnel.

[0025] The present invention has the following beneficial effects:

[0026] The present invention does not require additional foundation construction, and before the step-by-step dark excavation of the tunnel, the steel cover plate and the road surface layer are laid in a side-by-side construction manner, and the cover plate is replaced with the upper cover on the entire section of the existing road in stages. During construction, there is no need to make a temporary major line change to the existing road, and there is no need to completely interrupt the traffic. Moreover, the construction time can be significantly shortened, and rapid construction can be achieved, which is conducive to the rapid restoration of traffic. It is particularly suitable for important roads such as those passing through urban trunk lines and lifelines, or construction environments where land is scarce and only partial traffic interruption for a few hours is allowed. BRIEF DESCRIPTION OF THE DRAWINGS

[0027] Figure 1 It is a construction flow chart of the present invention.

[0028] Figure 2 This is a plan view of the steel cover plate of the present invention.

[0029] Figure 3 This is a cross-sectional layout diagram of the steel cover plate of the present invention.

[0030] Figure 4 This is the elevation layout diagram of the steel cover plate of the present invention.

[0031] Figure 5 It is a schematic diagram of the laying steps of the steel cover plate of the present invention.

[0032] Figure 6 It is a schematic diagram of the cutaway structure of the steel cover plate of the present invention.

[0033] Figure 7 for Figure 6 Schematic diagram of the AA section structure.

[0034] Figure 8 Schematic diagram of the pilot tunnel excavation sequence of the present invention (I).

[0035] Fig. 9 Schematic diagram of the pilot tunnel excavation sequence of the present invention (II).

[0036] Fig.10 Schematic diagram of the pilot tunnel excavation sequence of the present invention (III).

[0037] Fig.11 Schematic diagram of the pilot tunnel excavation sequence of the present invention (IV).

[0038] Fig.12 Schematic diagram of the pilot tunnel excavation sequence of the present invention (V).

[0039] Fig.13 Schematic diagram of the pilot tunnel excavation sequence of the present invention (six).

[0040] Fig.14 Schematic diagram of the pilot tunnel excavation sequence of the present invention (VII).

[0041] Fig.15 It is a schematic elevation diagram of the pilot tunnel excavation of the present invention.

[0042] Explanation of the main component symbols: 1. Divider; 2. Carriageway; 3. Steel cover plate; 3a-3b, the first group of steel cover plates; 3c-3f, the second group of steel cover plates; 3g-3j, the third group of steel cover plates; 4. Weld; 5. Pavement layer; 6. Top plate; 7. Bottom plate; 8. Web plate; 9. Shear nail group; 10. Steel fiber concrete layer; 11. Stiffening ribs; 12. Guide hole; 13. Initial support; 14. Secondary lining; 15. First guide hole; 16. Second guide hole; 17. Third guide hole; 18. Fourth guide hole; 19. First temporary horizontal brace; 20. Temporary vertical brace; 20a-20b, the first group of temporary vertical braces; 20c, the second group of temporary vertical braces; 21. Second temporary horizontal brace; 22. Third temporary horizontal brace; 23. Advance duct; 24. Pipe shed arch; 25. Advance small duct. DETAILED DESCRIPTION

[0043] The present invention will be further described below in conjunction with the accompanying drawings and specific implementation methods.

[0044] like Figure 1-5 As shown, the present invention discloses a method for constructing an ultra-shallow buried tunnel with rapid cover, comprising the following steps:

[0045] S1. First remove the vegetation at the existing road dividing strip 1 to level the site, then dig the foundation trench at the existing road dividing strip 1 to the designed position of the steel cover plate 3, that is, dig to the position corresponding to the bottom of the steel cover plate 3. Hoist and lay the prefabricated steel cover plate 3 in the foundation trench. After the steel cover plate 3 is laid, lay the pavement layer 5 on top of the steel cover plate 3, and then complete the replacement of the cover plate in the dividing strip 1 area. In this embodiment, step S1 lays the first group of steel cover plates 3a-3b in sequence.

[0046] S2. Temporary traffic diversion: dig the foundation trench at the carriageway 2 on one side of the dividing strip 1 to the designed position of the steel cover plate 3, hoist and lay the prefabricated steel cover plate 3 in the foundation trench, and lay the road surface on the steel cover plate 3 to complete the replacement of the cover plate of the carriageway 2 on this side. In this embodiment, construction is first carried out on the left carriageway 2. Before construction, the left carriageway 2 of the existing road can be closed, and the traffic is temporarily diverted to the right carriageway 2 of the existing road without temporary major rerouting. In this embodiment, step S2 successively lays the second group of steel cover plates 3c-3f.

[0047] S3. Temporary traffic diversion, closing the right lane 2 of the existing road, temporarily diverting traffic to the left lane 2 of the existing road, excavating the foundation trench to the designed position of the steel cover plate 3 at the lane 2 on the other side of the dividing strip 1, that is, at the right lane 2, hoisting and laying the prefabricated steel cover plate 3 into the foundation trench, and laying the road surface layer 5 on the steel cover plate 3, thus completing the replacement of the cover plate of the entire section of the existing road. In this embodiment, step S3 successively lays the third group of steel cover plates 3g-3j.

[0048] The steel cover plates 3 laid in the above steps S1-S3 are welded to each other and are prefabricated before construction. The positions of the weld seams 4 are as follows: Figure 1 As shown in FIG. 1 , the road surface layer 5 correspondingly laid on the steel cover plate 3 is an asphalt surface layer, which is laid quickly, which is beneficial to greatly shorten the construction time and quickly restore traffic.

[0049] Since the existing road sections are covered with plates and replaced with covers in stages, there is no need to make temporary major changes to the existing roads, and there is no need to completely interrupt traffic. The construction time is short, and the work can be carried out during the early morning hours when there is less traffic. After the construction is completed quickly, the entire section can be restored to traffic, minimizing the impact on traffic. This is especially suitable for situations where land is scarce or there are important pipelines nearby and land cannot be borrowed, and traffic can only be partially interrupted for a few hours.

[0050] like Figure 6-7 As shown, the above-mentioned steel cover plates 3 all include structures such as a top plate 6, a bottom plate 7 and a web 8, wherein the top plate 6 and the bottom plate 7 are arranged in parallel up and down, and the web 8 is vertically welded between the top plate 6 and the bottom plate 7 and arranged in a grid shape. A shear nail group 9 is vertically welded on the upper side of the top plate 6, and a steel fiber concrete layer 10 is laid above the top plate 6, and the shear nail group 9 is buried in the steel fiber concrete layer 10. A plurality of stiffening ribs 11 are vertically welded on the lower side of the top plate 6 and the upper side of the bottom plate 7, and the stiffening ribs 11 on the top plate 6 and the stiffening ribs 11 on the bottom plate 7 are arranged opposite to each other up and down. Through the arrangement of the web 8, the shear nail group 9, the stiffening ribs 11, the steel fiber concrete layer 10, etc., the structural stability of the steel cover plate 3 can be effectively enhanced and its bearing capacity can be improved.

[0051] S4. Carry out advanced support, and excavate the tunnel step by step under the steel cover plate 3 and the advanced support. Among them, the advanced support includes an advanced pipe shed, a pipe shed arch 24 and an advanced small guide tube 25. The advanced pipe is a plurality of advanced guide tubes 23 extending along the longitudinal excavation contour line of the tunnel. The pipe shed arch 24 is located at the entrance and exit of the tunnel. The steel cover plate 3 is partially supported by the pipe shed arch 24, and the support is more stable. When excavating the tunnel, the tunnel excavation section is divided into several parts and the short step method is used to excavate the corresponding guide tunnels 12 of each part. Each guide tunnel 12 adopts a composite lining.

[0052] In this embodiment, the guide tunnel 12 includes a first guide tunnel 15, a second guide tunnel 16, a third guide tunnel 17 and a fourth guide tunnel 18 arranged in sequence along the length of the road, and each guide tunnel 12 is divided into an upper step and a lower step. The advance small guide tube 25 and the advance guide tube 23 in the advance pipe rack are arranged along the excavation contour line on the side of the guide tunnel 12. Figure 8-15 As shown, each guide tunnel 12 is excavated cyclically according to the following steps until it is penetrated. During excavation, the upper step and the lower step in each guide tunnel 12 are staggered by 4m for construction, and the cyclic excavation footage of each guide tunnel 12 is within 0.5m.

[0053] S41. Excavate the first pilot tunnel 15 and the third pilot tunnel 17, and apply the initial support 13, the first temporary horizontal support 19 and the temporary vertical support 20, so that the corresponding initial support 13, the first temporary horizontal support 19 and the temporary vertical support 20 are closed into a ring. In this embodiment, the applied temporary vertical support 4 includes a first group of temporary vertical supports 20a-20b and a second group of temporary vertical supports 20c.

[0054] S42. After the lower guide tunnel 12 is initially supported and closed to form a ring, the first temporary cross brace 19 in the first guide tunnel 15 and the third guide tunnel 17 can be removed, and then the secondary lining 14 of the first guide tunnel 15 and the third guide tunnel 17 can be constructed, and the invert, side wall and vault of the first guide tunnel 15 and the third guide tunnel 17 can be constructed.

[0055] S43. Excavate the second guide tunnel 16, and apply the initial support 13 and the second temporary horizontal support 21, so that the corresponding initial support 13, the second temporary horizontal support 21 and the first group of temporary vertical supports 20a-20b are closed into a ring, and the initial supports 13 in the first guide tunnel 15, the second guide tunnel 16 and the third guide tunnel 17 are connected to form a ring.

[0056] S44. After the lower guide tunnel 12 is initially supported and closed into a ring, the second temporary horizontal support 21 and the corresponding first set of temporary vertical supports 20a-20b can be removed, and then the secondary lining 14 of the second guide tunnel 16 can be constructed, and the invert and arch of the second guide tunnel 16 can be constructed.

[0057] S45. Excavate the fourth guide tunnel 18, and apply the initial support 13 and the third temporary horizontal support 22, so that the corresponding initial support 13, the third temporary horizontal support 22 and the second group of temporary vertical supports 20c are closed into a ring, and the initial supports 13 in the third guide tunnel 17 and the fourth guide tunnel 18 are connected to form a ring.

[0058] S46. After the lower guide tunnel 12 is initially supported and closed into a ring, the third temporary horizontal support 22 and the corresponding second set of temporary vertical supports 20c can be removed, and then the secondary lining 14 of the fourth guide tunnel 18 can be constructed, and the invert, side walls and vault of the fourth guide tunnel 18 can be constructed.

[0059] In summary, this method of ultra-shallow tunnel construction does not require additional foundation construction. Traffic control can be carried out on existing roads during periods of low traffic volume. The lanes can be compressed temporarily for rapid construction. The cover plates of the entire section of the existing road can be replaced with the upper cover without the need for major temporary changes to the existing road. It is especially suitable for places with limited land use and where the local traffic interruption time cannot exceed 6 hours.

[0060] Although the present invention has been specifically shown and described in conjunction with the preferred embodiments, it should be understood by those skilled in the art that various changes in form and details may be made to the present invention without departing from the spirit and scope of the invention as defined in the appended claims, all of which are within the scope of protection of the present invention.

Claims

1. A method for constructing an ultra-shallow tunnel with rapid cover, characterized in that: The following steps are involved: S1. Open-cut the foundation trench at the dividing strip of the existing road to the designed position of the steel cover, hoist and lay the prefabricated steel cover into the foundation trench, and lay the pavement layer on top of the steel cover; S2. Open-cut the foundation trench at the carriageway on one side of the median strip to the designed position of the steel cover, hoist and lay the prefabricated steel cover into the foundation trench, and lay the pavement layer on top of the steel cover; S3. Open-cut the foundation trench at the carriageway on the other side of the median strip to the designed position of the steel cover, hoist and lay the prefabricated steel cover into the foundation trench, and lay the pavement layer on top of the steel cover; S4. Carry out advance support and excavate the tunnel in steps under the steel cover and advance support.

2. A method for constructing a super shallow tunnel with rapid construction as claimed in claim 1, characterized in that: The steel cover plates are welded to each other, and the road surface layer is an asphalt surface layer.

3. A method for constructing a super shallow tunnel with rapid construction as claimed in claim 1, characterized in that: The steel cover plate includes a top plate, a bottom plate and a web plate. The top plate and the bottom plate are arranged in parallel up and down. The web plate is vertically welded between the top plate and the bottom plate and arranged in a grid shape.

4. A method for constructing a quick-covered ultra-shallow tunnel as claimed in claim 3, characterized in that: A shear nail group is vertically welded on the upper side of the top plate, and a steel fiber concrete layer is laid above the top plate, and the shear nail group is buried in the steel fiber concrete layer.

5. A method for constructing a super shallow tunnel with rapid construction as claimed in claim 3, characterized in that: A plurality of stiffening ribs are vertically welded to the lower side of the top plate and the upper side of the bottom plate, and the stiffening ribs on the top plate and the stiffening ribs on the bottom plate are arranged opposite to each other up and down.

6. A method for constructing a super shallow tunnel with rapid construction as claimed in claim 1, characterized in that: In step S4, the tunnel excavation section is divided into several parts and the pilot tunnels of each part are excavated accordingly using the short step method, and each pilot tunnel adopts a composite lining.

7. A method for constructing a super shallow tunnel with rapid construction as claimed in claim 6, characterized in that: The pilot tunnels include a first pilot tunnel, a second pilot tunnel, a third pilot tunnel and a fourth pilot tunnel arranged in sequence along the length direction of the road, each pilot tunnel is divided into an upper step and a lower step, and each pilot tunnel is excavated cyclically according to the following steps until it is connected: S41. Excavate the first pilot tunnel and the third pilot tunnel, and apply initial support, first temporary horizontal support and temporary vertical support, so that the corresponding initial support, first temporary horizontal support and temporary vertical support are closed into a ring; S42. Remove the first temporary cross brace and then carry out secondary lining construction of the first and third pilot tunnels; S43. Excavate the second pilot tunnel, and apply the initial support and the second temporary horizontal support, so that the corresponding initial support, the second temporary horizontal support and the temporary vertical support are closed into a ring, and the initial supports in the first pilot tunnel, the second pilot tunnel and the third pilot tunnel are connected to form a ring; S44. Remove the second temporary horizontal brace and the corresponding temporary vertical brace, and then carry out the construction of the secondary lining of the second pilot tunnel; S45. excavate the fourth pilot tunnel, and apply the initial support and the third temporary horizontal support, so that the corresponding initial support, the third temporary horizontal support and the temporary vertical support are closed into a ring, and the initial supports in the third pilot tunnel and the fourth pilot tunnel are connected to form a ring; S46. Remove the third temporary horizontal brace and the corresponding temporary vertical brace, and then carry out the secondary lining construction of the fourth pilot tunnel.

8. A method for constructing a super shallow tunnel with rapid construction as claimed in claim 7, characterized in that: In step S4, the upper step and the lower step are staggered by 4m for construction, and the excavation progress of each pilot tunnel cycle is within 0.5m.

9. A method for constructing a super shallow tunnel with rapid construction as claimed in claim 7, characterized in that: The advance support in step S4 includes an advance pipe shed, a pipe shed arch and an advance small guide tube, and the steel cover plate is partially supported by the pipe shed arch.

10. A method for constructing a super shallow tunnel with rapid construction as claimed in claim 8, characterized in that: The small advance guide tube and the advance guide tube in the advance pipe rack are arranged along the excavation contour line on the side of the guide tunnel.