Concrete cylinder warehouse bottom plate construction method
The concrete silo floor construction method with a supporting structure of beams and ribs addresses the inefficiencies and safety issues of traditional methods by enabling quick assembly and disassembly, reducing costs and enhancing safety.
Patent Information
- Application Number
- CN202411473537.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-10-22
- Publication Date
- 2024-12-03
AI Technical Summary
Traditional concrete silo floor construction methods are costly, labor-intensive, time-consuming, and pose significant safety risks due to the use of steel pipe scaffolding, which requires extensive manual assembly and disassembly, and are prone to collapse on soft foundations.
A concrete silo floor construction method involving a first supporting structure with parallel support beams and ribs, allowing for the use of adjustable connections and fastening methods, eliminating the need for full-floor scaffolding, and enabling quick disassembly and reuse of materials.
This method improves construction efficiency, reduces costs, and enhances safety by avoiding the need for extensive scaffolding, allowing simultaneous construction of other projects and reducing material waste.
Smart Images

Figure CN119062112A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of concrete silo construction, and in particular to a concrete silo bottom plate construction method. Background Art
[0002] Concrete silos are a common storage structure, widely used in agriculture, industry, construction and other fields. They are mainly used to store bulk materials such as grain, coal, cement, etc. Due to its high strength, good durability, strong sealing and other advantages, it occupies an important position in modern storage systems. The concrete silo structure is generally composed of a foundation, a support structure under the silo, a silo bottom, a silo wall and a silo roof. As a structure that directly bears the material load, the silo bottom is generally thicker. For example, in the large-diameter circular storage tanks in the cement industry, the thickness of the bottom plate is mostly more than 1 meter, and the height from the ground is mostly more than 10 meters. This state makes the construction of the bottom plate template difficult and requires high safety.
[0003] The traditional silo floor formwork support solution usually uses a steel pipe scaffolding (or disc-type scaffolding) to build a full-floor load-bearing system. The height of this support system is generally more than 8 meters, which is an ultra-high formwork project with high technical risks. This method also needs to consider issues such as overall construction load verification, foundation sinking, and material turnover.
[0004] After years of on-site construction practice, it is found that traditional construction technology has the following disadvantages:
[0005] 1. High construction cost
[0006] 1. The material cost of leasing pipe fasteners is relatively high.
[0007] 2. The labor input for erecting scaffolding is large and the cost is high.
[0008] 2. The construction period is long, which affects other construction on site
[0009] 1. It takes a long time to erect and dismantle, especially to dismantle the pipe racks in confined spaces. Due to space limitations, the pipe racks can only be dismantled and erected one by one manually, which results in low construction efficiency and increased labor costs.
[0010] 2. During the construction of the warehouse bottom plate, the ±0.000 backfill, equipment foundation and warehouse bottom plate cannot be constructed at the same time.
[0011] 3. The safety risks in the construction process of ultra-high load-bearing formwork system are relatively large
[0012] 1. The distance between the vertical poles and the horizontal poles during the erection process is small, which makes the operation inconvenient and there is a risk of falling from a height;
[0013] 2. The dismantling of the rack pipe is usually carried out in a confined space, which may cause the fasteners and materials to fall and cannot be recovered, and the utilization rate of the materials is reduced;
[0014] 3. The load-bearing frame is at risk of collapse due to foundation settlement, for example, when the pipe support is on a soft foundation or a newly filled foundation.
[0015] It can be seen that there are urgent problems to be solved in the traditional concrete silo floor construction, and the efficiency and safety of the concrete silo floor construction should be optimized and improved to reduce the construction cost. Therefore, it is necessary to propose a more reasonable technical solution to solve the technical problems existing in the existing technology. Summary of the invention
[0016] In order to overcome at least one of the defects mentioned above, the present invention proposes a concrete silo floor construction method. By adjusting the construction plan, coordinating the storage design and construction, and setting a construction platform for the storage floor, the resource utilization rate and construction efficiency can be improved, and better comprehensive benefits can be achieved. The safety and economy of construction are guaranteed, and the construction cost can be saved and the construction period can be shortened.
[0017] In order to achieve the above-mentioned purpose, the concrete silo bottom plate construction method disclosed in the present invention can adopt the following technical scheme:
[0018] A concrete silo bottom plate construction method, comprising:
[0019] Carry out foundation construction and warehouse bottom support structure construction; the warehouse bottom support structure includes a plurality of support columns and a plurality of load-bearing walls;
[0020] A first support structure is arranged on the warehouse bottom support structure, wherein the first support structure comprises a plurality of support beams arranged in parallel and at intervals;
[0021] A plurality of parallel main ribs are connected and fixed in the plane above the support beam, and the main ribs are perpendicular to the support beam;
[0022] A plurality of parallel secondary ribs are connected and fixed in the plane above the main ribs, and the secondary ribs are perpendicular to the main ribs;
[0023] A plurality of casting templates are arranged in the plane above the secondary rib to form a casting and molding space for the bottom plate of the silo;
[0024] Pour concrete in the casting and forming space and wait for the silo bottom plate to be formed.
[0025] The above-disclosed silo floor construction method, by setting a first supporting structure on the supporting wall, continues to set main ribs and secondary ribs as encrypted supports to set the casting template of the silo floor, thereby realizing the setting of the casting template of the silo floor, and facilitating subsequent casting construction; in this process, there is no need to set up a full-floor scaffolding to support the casting template, which reduces the work intensity and ensures a clean and orderly construction environment. After the casting construction is completed, there is no need to dismantle a large number of scaffolding parts, but the first supporting structure, main ribs, secondary ribs and casting templates can be quickly disassembled, and the disassembled materials can be reused.
[0026] Furthermore, when setting the support beam, a variety of solutions can be used for connection and fixation, which are not limited to the only one. Here, optimization is made and one feasible option is proposed: the support column and the load-bearing wall are provided with a plurality of support brackets, and the two ends of the support beam are respectively matched with the support brackets and connected and fixed. When the above solution is adopted, the support bracket is fixedly connected to the load-bearing wall, and the support bracket includes a connection part attached to the load-bearing wall, and also includes a plurality of support parts integrally formed with the connection part, and the support part is used to connect and fix the support beam.
[0027] Furthermore, in order to facilitate the adjustment of the matching structure of the support corbel and the support beam, and to facilitate the adjustment of the support height of the support beam, the position of the support beam can be adjusted in a variety of ways, which are not limited to the only one. Here, an optimization is made and one of the feasible options is proposed: a pad assembly is provided between the support corbel and the support beam. When the above scheme is adopted, the pad assembly includes a pad plate and a pad tube, the pad plate fits the support corbel, and the pad tube fits the support beam. In the actual construction process, appropriate pad plates and pad tubes can be used according to the actual support requirements to meet the support requirements of the support beam.
[0028] Furthermore, the length of the support beam is generally smaller than the span of the silo, that is, a gap is formed between the two ends of the support beam and the load-bearing wall. In order to maintain the stability of the support beam, the two ends are kept relatively fixed with the load-bearing wall. It can be adjusted in a variety of ways, which are not limited to the only one. Here, it is optimized and one of the feasible options is proposed: a wedge block is set between the end of the support beam and the load-bearing wall. When the above scheme is adopted, the wedge block includes an inclined abutting surface. When the wedge block is set, the gap between the support beam and the load-bearing wall is filled from top to bottom, thereby maintaining the stability of the support beam. This fastening method also facilitates the removal of the support beam after casting.
[0029] Furthermore, when the support corbel is arranged on the load-bearing wall, it can be fixed by a variety of schemes, which are not limited to the only one. Here, an optimization is made and one of the feasible options is proposed: the load-bearing wall is provided with an embedded part, and the support corbel is connected and fixed to the embedded part. When the above scheme is adopted, the embedded part includes an embedded plate, which is arranged in the load-bearing wall and remains exposed on the surface of the load-bearing wall, so that it can be used to connect and fix the support corbel. Specifically, the support corbel can be fixed to the embedded plate by welding, or it can be connected and fixed to the embedded plate by fasteners.
[0030] Furthermore, in order to keep the relative position between the casting template and the secondary rib fixed, the casting template and the secondary rib can be fixed by iron nails, and a lifting ring structure can be reserved on the casting template to assist in the later removal of the secondary rib. The scheme of the lifting ring structure is not limited to the only one. Specifically, optimization is made here and one of the feasible options is proposed: the casting template is provided with a pre-embedded lifting ring, the upper part of the pre-embedded lifting ring is located above the casting template and enters the casting molding space, and the lower part of the pre-embedded lifting ring is located below the casting template and is wrapped around the secondary rib. When the above scheme is adopted, the lower part of the pre-embedded lifting ring is used to hang the secondary rib and form a lifting structure.
[0031] Furthermore, after the embedded lifting ring is set, it surrounds the secondary rib and realizes lifting, and a gap is formed between the embedded lifting ring and the secondary rib. In order to maintain the close fit between the embedded lifting ring and the secondary rib, the gap can be filled in a variety of ways, which are not limited to the only one. Here, optimization is made and one of the feasible options is proposed: the secondary rib and the embedded lifting ring are fixed by a wedge. When the above solution is adopted, the wedge is horizontally inserted into the gap between the embedded lifting ring and the secondary rib, so as to keep the embedded lifting ring and the secondary rib relatively fixed.
[0032] Furthermore, the setting of the first supporting structure can be achieved through a variety of solutions, which are not limited to a single one. Here, an optimization is performed and one feasible option is proposed: when setting the first supporting structure, the supporting beam is hoisted to the installation height and installed.
[0033] Furthermore, after the construction of the silo floor is completed, the tools set up in this method can be recycled, so an optimization is made here and one of the feasible options is proposed: when the silo floor is solidified, the support beams, main ribs, secondary ribs and casting templates are removed. When the above scheme is adopted, the tools can be quickly disassembled and recycled after the silo floor is cast.
[0034] Furthermore, before pouring, a first supporting structure is provided on the load-bearing wall, which affects the flatness of the surface of the load-bearing wall or causes damage to the surface of the load-bearing wall. Therefore, optimization is performed here and one of the feasible options is proposed: after removing the pouring formwork, the load-bearing wall is repaired. When the above scheme is adopted, the surface of the load-bearing wall can be repaired by grinding or coating.
[0035] Compared with the prior art, some beneficial effects of the technical solution disclosed in the present invention include:
[0036] By adjusting the silo floor construction method, the need to erect a full-floor scaffolding for construction was avoided, the construction efficiency was improved, and the overall construction period was shortened; at the same time, the recycling of construction tools and materials could be completed quickly, reducing the construction cost. BRIEF DESCRIPTION OF THE DRAWINGS
[0037] In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the drawings required for use in the embodiments are briefly introduced below. It should be understood that the following drawings only represent some embodiments of the present invention and therefore should not be regarded as limiting the scope. For ordinary technicians in this field, other related drawings can be obtained based on these drawings without creative work.
[0038] Figure 1 This is a schematic diagram of the composition of a concrete circular silo;
[0039] Figure 2 The schematic diagram of the support beam arrangement is shown below;
[0040] Figure 3 Schematic diagram of main beam layout;
[0041] Figure 4 This is a schematic diagram of the secondary ridge arrangement;
[0042] Figure 5 This is a detailed structural diagram;
[0043] Figure 6 This is a schematic diagram of the layout of the embedded lifting rings;
[0044] Figure 7 Schematic diagram of the position relationship between the scissor lift platform and the support beam 7 in the middle area;
[0045] Figure 8 It is a schematic diagram of the arrangement of the scissor lift and the flex boom lift 17 in the middle area;
[0046] Fig. 9 This is a schematic diagram of the main rib removal method in the middle area;
[0047] Fig.10 This is a schematic diagram of the removal of the support beams and main ribs in the middle area;
[0048] Fig.11 This is a schematic diagram of the dismantling and detailed construction of the supporting beams and main ribs;
[0049] Fig.12 It is a schematic diagram of the position relationship between the scissor lift platform and the support beam 7 in the two side areas;
[0050] Fig.13 It is a schematic diagram of the movement direction of the main ribs in the two side areas;
[0051] Fig.14 This is a schematic diagram of the final position of the main ribs in the two side areas;
[0052] Fig.15 It is a schematic diagram of the upper structural relationship of the scissor lift platform;
[0053] Fig.16 It is a schematic diagram of the coordination structure between the scissor lift platform and the support beam.
[0054] Fig.17 Schematic diagram of the structure of the supporting corbel.
[0055] In the above drawings, the meanings of the symbols are as follows:
[0056] 1. Pile foundation; 2. Silo bottom support structure; 3. Silo bottom plate; 4. Silo wall; 5. Silo roof plate; 6. Supporting corbel; 7. Support beam; 8. Main rib; 9. Secondary rib; 10. Casting formwork; 11. Embedded lifting ring; 12. Wedge block; 13. Embedded parts; 14. Spacer block; 15. Connection node between support beam and main rib; 16. Scissor lift; 17. Flex arm lift; 18. Connection node between lift and support beam; 19. Wooden box. DETAILED DESCRIPTION
[0057] The present embodiment is further explained below in conjunction with the accompanying drawings and specific embodiments.
[0058] In view of the many deficiencies in the existing concrete silo pouring construction, the following embodiments are optimized to overcome the deficiencies in the prior art.
[0059] Example
[0060] like Figure 1 to Figure 17 As shown, a method for constructing a concrete silo bottom plate 3 adopted in this embodiment includes:
[0061] like Figure 1 , Figure 2 As shown, the foundation construction and the warehouse bottom support structure construction are carried out, and the pile foundation 1 is formed after the foundation construction. The warehouse bottom support structure 2 is located on the upper part of the pile foundation 1; the warehouse bottom support structure includes a plurality of support columns and a plurality of load-bearing walls;
[0062] A first support structure is arranged on the warehouse bottom support structure 2, and the first support structure includes a plurality of support beams 7 arranged in parallel and at intervals;
[0063] like Figure 3 As shown, a plurality of parallel main ribs 8 are connected and fixed in the plane above the support beam 7, and the main ribs 8 are perpendicular to the support beam 7;
[0064] like Figure 4 As shown, a plurality of parallel secondary flutes 9 are connected and fixed in the plane above the main flutes 8, and the secondary flutes 9 are perpendicular to the main flutes;
[0065] like Figure 5 As shown, a plurality of casting templates 10 are arranged in the plane above the secondary rib 9 to form a casting and molding space for the silo bottom plate 3;
[0066] Concrete is poured in the pouring and molding space and the silo bottom plate 3 is formed.
[0067] The above-disclosed silo floor 3 construction method, by setting a first supporting structure on the supporting wall, continues to set the main ribs 8 and the secondary ribs 9 as encrypted supports to set the casting template 10 of the silo floor, thereby realizing the setting of the silo floor casting template 10, which is convenient for subsequent casting construction; in this process, there is no need to set up a full-floor scaffolding to support the casting template 10, which reduces the work intensity and ensures a clean and orderly construction environment. After the casting construction is completed, there is no need to dismantle a large number of scaffolding parts, and the first supporting structure, the main ribs 8, the secondary ribs 9 and the casting template 10 can be quickly disassembled, and the disassembled materials can be reused.
[0068] Preferably, a silo wall 4 is formed on the silo bottom plate support structure, and the top of the silo is closed by a silo roof plate 5 .
[0069] When the support beam 7 is provided, it can be connected and fixed by a variety of schemes, which are not limited to the only one. This embodiment is optimized and adopts one of the feasible options: a plurality of support brackets 6 are provided on the support column and the load-bearing wall, and the two ends of the support beam 7 are respectively matched with the support brackets 6 and connected and fixed. When the above scheme is adopted, the support bracket 6 is fixedly connected to the load-bearing wall, and the support bracket 6 includes a connecting portion attached to the load-bearing wall, and also includes a plurality of supporting portions integrally formed with the connecting portion, and the supporting portions are used to connect and fix the support beam 7.
[0070] In order to facilitate the adjustment of the matching structure of the supporting corbel 6 and the supporting beam 7, and to facilitate the adjustment of the supporting height of the supporting beam 7, the position of the supporting beam 7 can be adjusted in a variety of ways, which are not limited to the only one. This embodiment is optimized and adopts one of the feasible options: Figure 5 As shown, a pad 14 assembly is provided between the supporting corbel 6 and the supporting beam 7. When the above scheme is adopted, the pad 14 assembly includes a pad plate and a pad tube, the pad plate fits the supporting corbel 6, and the pad tube fits the supporting beam 7. In the actual construction process, appropriate pad plates and pad tubes can be used according to the actual support requirements to meet the support requirements of the supporting beam 7.
[0071] The length of the support beam 7 is generally smaller than the span of the silo, that is, a gap is formed between the two ends of the support beam 7 and the load-bearing wall. In order to maintain the stability of the support beam 7, the two ends are relatively fixed to the load-bearing wall, which can be adjusted in a variety of ways, which are not limited to the only one. This embodiment is optimized and adopts one of the feasible options: a wedge block 12 is set between the end of the support beam 7 and the load-bearing wall. When the above scheme is adopted, the wedge block 12 includes an inclined abutting surface. When the wedge block 12 is set, the gap between the support beam 7 and the load-bearing wall is filled from top to bottom, thereby maintaining the stability of the support beam 7. This fastening method is also convenient for removing the support beam 7 after casting.
[0072] When the support corbel 6 is arranged on the load-bearing wall, it can be fixed by a variety of schemes, which are not limited to the only one. This embodiment is optimized and adopts one of the feasible options: the load-bearing wall is provided with an embedded part 13, and the support corbel 6 is connected and fixed to the embedded part 13. When the above scheme is adopted, the embedded part 13 includes an embedded plate, which is arranged in the load-bearing wall and remains exposed on the surface of the load-bearing wall, so as to be used to connect and fix the support corbel 6. Specifically, the support corbel 6 can be fixed by welding with the embedded plate, or can be connected and fixed with the embedded plate by fasteners.
[0073] In order to keep the relative position between the casting template 10 and the secondary rib 9 fixed, the casting template 10 and the secondary rib 9 can be fixed by nails, and a lifting ring structure can be reserved on the casting template 10 to assist in the later removal of the secondary rib 9. The scheme of the lifting ring structure is not limited to the only one. Specifically, this embodiment is optimized and adopts one of the feasible options: the casting template 10 is provided with a pre-embedded lifting ring 11, the upper part of the pre-embedded lifting ring 11 is located above the casting template 10 and enters the casting molding space, and the lower part of the pre-embedded lifting ring 11 is located below the casting template 10 and is wound around the secondary rib 9. When the above scheme is adopted, the lower part of the pre-embedded lifting ring 11 is used to hang the secondary rib 9 and form a lifting structure.
[0074] After the embedded lifting ring 11 is set, it surrounds the secondary rib 9 and realizes lifting, and a gap is formed between the embedded lifting ring 11 and the secondary rib 9. In order to maintain the tight fit between the embedded lifting ring 11 and the secondary rib 9, the gap can be filled in a variety of ways, which are not limited to the only one. This embodiment is optimized and adopts one of the feasible options: the secondary rib 9 and the embedded lifting ring 11 are tightened by a wedge block 12. When the above solution is adopted, the wedge block 12 is horizontally inserted into the gap between the embedded lifting ring 11 and the secondary rib 9, so as to keep the embedded lifting ring 11 and the secondary rib 9 relatively tight.
[0075] The first supporting structure can be set up through a variety of solutions, which are not limited to the only one. This embodiment is optimized and adopts one of the feasible options: Figure 8 to Figure 15As shown, when setting the first supporting structure, the supporting beam 7 is hoisted to the installation height and installed.
[0076] After the construction of the silo floor 3 is completed, the tools set up in this method can be recycled, so this embodiment is optimized and adopts one of the feasible options: when the silo floor 3 is solidified, the support beam 7, the main rib 8, the secondary rib 9 and the casting template 10 are removed. When the above scheme is adopted, the tools can be quickly disassembled and recycled after the silo floor 3 is cast. When the above scheme is adopted, the structural parts are dismantled by the support trolley, and a lifting frame is provided on the support trolley, and a support plate is provided on the top of the lifting frame, and the node on the support plate cooperates with the support beam 7.
[0077] Before pouring, a first supporting structure is provided on the load-bearing wall, which affects the flatness of the surface of the load-bearing wall or causes damage to the surface of the load-bearing wall. Therefore, this embodiment is optimized and adopts one of the feasible options: after removing the pouring template 10, the load-bearing wall is repaired. When the above scheme is adopted, the surface of the load-bearing wall can be repaired by grinding or coating.
[0078] Here is an example to illustrate:
[0079] 1. Design calculation: According to the thickness of the warehouse floor 3 and the support span, design the specifications of the support beam 7; the specifications and layout spacing of the main ribs 8; and the specifications of the embedded parts. Among them, for the middle area, the layout spacing of the support beam 7 is half the length of the main ribs 8 plus 10mm, as shown in the attached Figure 7 As shown in the figure, for the two side areas, the spacing of the support beams 7 is equal to the length of the main rib plus 20mm. This requirement is not only to adjust the spacing error of the main rib, but also to facilitate the removal of the support beams 7 and the main rib 8 as a group, as shown in the figure. Fig. 9 Shown and attached Fig.13 shown.
[0080] 2. Making steel beams: When making steel beams 7 in the factory, the length of the steel beam is the net span minus 60mm. The 60mm gap is used to adjust the construction error and facilitate the installation of the steel beam.
[0081] 3. Install the steel corbel:
[0082] a) During the slipform construction process, embedded parts 13 are buried according to the designed elevation and spacing.
[0083] b) After the formwork is moved to the bottom plate of the warehouse, the embedded parts 13 are welded to the steel bracket 6 using the formwork hanging basket. Figure 5 As shown, 50mm is reserved at the bottom of the steel corbel 6 and the support beam 7, and the gap is filled with a pad. The rectangular tube in the pad is for easy knocking out; the steel plate in the pad is used to adjust the construction error of the steel corbel so that the support beam 7 is in the same plane.
[0084] 4. Install steel beams and primary and secondary beams:
[0085] a) Hoist the support beam 7 onto the pad 14 of the steel corbel 6, and make the gaps between the left and right ends of the steel beam 7 and the wall approximately equal, that is, the left and right gaps are about 30 mm.
[0086] b) Wedge blocks 12 are inserted into the gaps at both ends of the steel corbels to fix the steel beams.
[0087] c) Place the main ribs 8 from both sides to the middle. Connect the outermost and middle main ribs 8 to the support beam through the connection node 15 to form a whole and increase stability. The main ribs in the middle are placed and fixed according to the designed spacing. According to the design calculation, the main ribs can be ordinary channel steel 10 with a spacing of 100 to 250 mm.
[0088] d) Place the secondary ribs 9 on the main ribs 8, and fix the secondary ribs 9 and the main ribs 8 with steel wires. The secondary ribs 9 are made of 50*100mm wooden squares with a spacing of 200mm.
[0089] 5. Assemble the combined formwork: fully spread the casting formwork 10 on the secondary rib 9. The formwork 10 is fixed to the secondary rib 9 with iron nails.
[0090] 6. Install the embedded lifting ring: Install an embedded lifting ring 11 every 1500mm at the upper end along the secondary rib 9. At the same time, arrange the lifting ring every 1200mm in the direction perpendicular to the secondary rib 9. Figure 6 The embedded lifting ring 11 serves as a supporting point for the secondary rib 9 during the demolition stage.
[0091] 7. Pour the concrete of the reservoir floor.
[0092] 8. Remove the template in the middle area:
[0093] a) Place a lifting vehicle 16 in the middle of the support beam 7 as a fulcrum for dismantling the support beam, as shown in the attached figure. Figure 7 As shown;
[0094] b) fixing the support beam 7 using a lifting vehicle and the support beam connection node 15;
[0095] c) using the lifting vehicle 17 to transport the construction personnel to the demolition work plane;
[0096] d) knock out the pads 14 on both sides of the support beam 7;
[0097] e) removing the connection node 15 of the main rib associated with the supporting beam;
[0098] f) removing the steel brackets 6 on both sides so that the support beam 7 is supported by the lifting vehicle 16;
[0099] g) Two support beams 7 are grouped together. After removing the two ends of the inner steel beam 7, repeat steps a) to f) to remove the outer steel beams in the group. Figure 8 As shown;
[0100] h) Simultaneously operate the two lifting vehicles 16 to slowly move them downward by 50 mm to leave operating space for the main flute 8;
[0101] i) Remove the connection node between the innermost side of the main rib and the next set of support beams, and then move the main rib 8 outwards so that it is as shown in the attached figure. Fig. 9 As shown;
[0102] j) Use the support beam and the main rib connection node 15 to fix the middle main rib 8;
[0103] k) Move the main rib 8 toward the middle of the support beam 7 so that it Fig.10 As shown;
[0104] l) Use ropes to tie the main ribs 8 together to prevent the main ribs 8 from slipping during movement;
[0105] m) Synchronously operate the two lifting vehicles 18, first make them fall slowly and steadily at the same speed, as shown in the following figure. Fig.11 As shown;
[0106] n) After dismantling the group of steel beams, remove the wedge 12 on the pre-embedded lifting ring 11 of the section;
[0107] o) Separating the pouring formwork 10 together with the secondary ribs 9 from the bottom plate 3;
[0108] p) After removing the section, repeat steps a) to o) again.
[0109] 9. Remove the templates on both sides:
[0110] a) Arrange a lifting vehicle 16 in the middle of the inner support beam 7, and use the lifting vehicle to connect the support beam with the node 18 to fix the support beam 7, as shown in the attached figure. Fig.12 As shown;
[0111] b) knock out the pads 14 on both sides of the support beam 7;
[0112] c) removing the connection node 15 between the main rib and the supporting beam;
[0113] d) Remove the steel brackets 6 on both sides so that the support beam 7 is supported by the lifting vehicle 16;
[0114] e) Fix two wooden boxes with the same height as the support beam on the lifting platform to prevent the main beam from sliding down during the downward movement;
[0115] f) Operate the lifting vehicle 16 to slowly move it downward by 50 mm to leave operating space for the main rib 8; g) Remove the bolts of the support beam 7 connected to the other side of the main rib 8 and move the main rib 8 inwards so that it is as shown in the attached Fig.13 As shown;
[0116] h) Remove the main ribs 8 from both sides toward the middle, and repeat steps a) to g);.
[0117] i) Move the main rib 8 toward the middle of the support beam 7 so that it Fig.14 As shown;
[0118] j) Use ropes to tie the main ribs, support beams and wooden boxes together to prevent the main ribs 8 from slipping during movement;
[0119] k) operating the lifting vehicle 16, firstly making it fall steadily and slowly;
[0120] l) After dismantling the steel beam, remove the wedge 12 on the pre-embedded lifting ring 11 of the section;
[0121] m) Separate the pouring formwork together with the secondary ribs from the bottom plate of the warehouse;
[0122] n) After removing the section, repeat steps a) to m) again.
[0123] 10. After the casting formwork 10 is completely removed, the embedded parts 13 are polished and painted.
[0124] According to this case, the following effects can be achieved:
[0125] 1) Save construction costs; save scaffolding pipe rental fees, and 80% of the labor costs for erection and dismantling;
[0126] 2) Shorten the construction period. Compared with the traditional construction scheme, this scheme does not require the erection and removal of scaffolding, which can greatly shorten the above working time. In addition, since the combined steel beam formwork system does not occupy the ground space, the plane below the steel formwork can be constructed simultaneously, thereby shortening the overall construction period of the project;
[0127] 3) Ensure construction safety: effectively prevent risks such as scaffolding collapse and fastener falling;
[0128] 4) Improve material utilization: Composite steel beams can be used as templates for other warehouses and can also be used as components of other steel structures, saving project material costs.
[0129] The above are the implementation methods listed in this embodiment, but this embodiment is not limited to the above optional implementation methods. Those skilled in the art can arbitrarily combine the above methods to obtain other various implementation methods. Anyone can derive other various implementation methods under the inspiration of this embodiment. The above specific implementation methods should not be understood as limiting the protection scope of this embodiment. The protection scope of this embodiment should be based on the definition in the claims.
Claims
1. A method for constructing a concrete silo floor, characterized in that: include: Carry out foundation construction and warehouse bottom support structure construction; the warehouse bottom support structure (2) includes a plurality of support columns and a plurality of load-bearing walls; A first support structure is arranged on the warehouse bottom support structure (2), wherein the first support structure comprises a plurality of support beams (7) arranged in parallel and at intervals; A plurality of parallel main ribs (8) are connected and fixed in a plane above the support beam (7), wherein the main ribs (8) are perpendicular to the support beam; A plurality of parallel secondary flutes (9) are connected and fixed in the plane above the primary flutes (8), and the secondary flutes (9) are perpendicular to the primary flutes; A plurality of casting templates (10) are arranged in the plane above the secondary ribs (9) to form a casting and molding space for the silo bottom plate (3); Concrete is poured in the pouring and molding space and the silo bottom plate (3) is formed.
2. The concrete silo floor construction method according to claim 1 is characterized by: A plurality of supporting brackets are arranged on the supporting columns and the load-bearing walls, and the two ends of the supporting beam are respectively matched with the supporting brackets and connected and fixed.
3. The method for constructing a concrete silo floor according to claim 2, characterized in that: A cushion block (14) assembly is provided between the supporting corbel and the supporting beam.
4. The method for constructing a concrete silo floor according to any one of claims 1 to 3, characterized in that: A wedge block (12) is arranged between the end of the support beam and the load-bearing wall.
5. The concrete silo floor construction method according to claim 2 or 3, characterized in that: An embedded part (13) is arranged on the load-bearing wall, and the supporting corbel is connected and fixed to the embedded part (13).
6. The method for constructing a concrete silo floor according to claim 1, characterized in that: The casting template (10) is provided with a pre-embedded lifting ring (11), the upper part of the pre-embedded lifting ring (11) is located above the casting template (10) and enters the casting molding space, and the lower part of the pre-embedded lifting ring (11) is located below the casting template (10) and is arranged around the secondary rib (9).
7. The method for constructing a concrete silo floor according to claim 6, characterized in that: The secondary rib (9) and the embedded lifting ring (11) are fixed together by a wedge block (12).
8. The concrete silo floor construction method according to claim 1, characterized in that: When setting up the first supporting structure, the supporting beam is hoisted to the installation height and installed.
9. The method for constructing a concrete silo floor according to any one of claims 1 to 3 and 6 to 8, characterized in that: After the silo bottom plate (3) is solidified, the support beams, the main ribs (8), the secondary ribs (9) and the casting formwork (10) are removed. The construction is carried out in the following order: Remove the formwork in the middle area: a) Place the lifting vehicle in the middle of the support beam as a fulcrum when dismantling the support beam; b) Use a lifting vehicle to connect the support beam to the node to fix the support beam; c) Knock out the pads on both sides of the support beam; d) Remove the connection nodes of the main ribs related to the support beam e) Remove the steel brackets on both sides so that the support beam is supported by the lifting vehicle; f) Two support beams are grouped together. After removing the connections at both ends of the inner steel beam, repeat steps a) to e) to remove the outer steel beams in the group; g) Operate two lifting vehicles simultaneously and slowly move them downward 50mm to leave operating space for the main beam; h) Remove the connection node between the innermost side of the main rib and the next set of support beams, and then move the main rib outwards; i) Use the connection node between the support beam and the main rib to fix the middle main rib; j) Move the main rib towards the middle of the supporting beam; k) Use ropes to tie the main ribs together to prevent them from slipping during movement; l) Operate the two lifts synchronously, first making them fall slowly and steadily at the same speed; m) After dismantling the group of steel beams, remove the wedges on the embedded lifting rings in the section; n) Separate the pouring formwork from the base plate; o) After removing the section, repeat steps a) to n) again. Remove the templates on both sides: a) Arrange the lifting vehicle in the middle of the inner support beam and fix the support beam using the connection node between the lifting vehicle and the support beam; b) Knock out the pads on both sides of the support beam; c) Remove the connection node between the main rib and the supporting beam; d) Remove the steel brackets on both sides so that the support beam can be supported by the lifting vehicle; e) Fix two wooden boxes with the same height as the support beam on the lifting platform to prevent the main beam from sliding down during the downward movement; f) Operate the lifting vehicle to slowly move it downward 50mm to leave operating space for the main beam; g) Remove the bolts of the support beam connected to the other side of the main rib and move the main rib inwards; h) Remove the main ribs from both sides toward the middle, and repeat steps a) to g); i) Move the main rib towards the middle of the supporting beam; j) Use ropes to tie the main ribs to the support beams and wooden boxes to prevent the main ribs from slipping during movement; k) Operate the lift, first let it drop slowly and steadily; l) After dismantling the steel beam, remove the wedges on the embedded lifting rings in this section; m) Separate the pouring formwork together with the secondary ribs from the bottom plate of the warehouse; n) After removing the section, repeat steps a) to m) again.
10. The method for constructing a concrete silo floor according to claim 9, characterized in that: After the casting formwork (10) is removed, the load-bearing wall is repaired.