Cable trench support structure and cable laying method

By designing the cable trench bracket structure and using the combination of slide rod and clamping components, the problem of easy slippage of cables in the cable trench is solved, improving the efficiency and convenience of cable laying, reducing labor intensity, and providing greater flexibility Sex and stability.

CN119070206AInactive Publication Date: 2024-12-03WUHAN BAITAI ELECTRIC POWER ENG CO LTD
View PDF 0 Cites 2 Cited by

Patent Information

Application Number
CN202411101555.5
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-12
Publication Date
2024-12-03
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

During construction, the existing cable trench is easy to slip and fall off, resulting in many fixing devices and inconvenient operation, which consumes time and effort, affects the efficiency of cable laying, and is especially prominent in small cable trenches.

Method used

A cable trench bracket structure is designed, including a fixing frame, a slide rod, a snap-on assembly and an unlocking assembly. The slide rod can slide on the fixing frame and can be stopped and unlocked through the snap-on assembly and unlocking assembly. The support rod can be detached. , The cross bar is used for the rapid lifting and lowering of multiple slide bars, simplifying the cable laying process.

Benefits of technology

It improves the convenience and efficiency of cable laying, reduces labor intensity, provides greater flexibility, facilitates cable layout and length adjustment, and ensures normal laying.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119070206A_ABST
    Figure CN119070206A_ABST
Patent Text Reader

Abstract

The invention discloses a cable trench support structure and a cable laying method, the cable trench support structure comprises a fixing frame fixedly connected with the side wall of a cable trench, and the inner wall of the fixing frame is provided with a plurality of clamping grooves along the height direction; the sliding rod is in sliding connection with the fixing frame in the height direction, and a supporting rod used for supporting a cable is fixed to the side wall of the sliding rod; the clamping assembly is arranged in the sliding rod, the clamping end of the clamping assembly can be clamped in the clamping groove so that the sliding rod and the fixing frame can be relatively fixed, and the clamping assembly can stop movement of the sliding rod from top to bottom; and the unlocking assembly is arranged in the sliding rod and used for unlocking the clamping assembly, and the operation end of the unlocking assembly is located on the outer side of the sliding rod. Second operation holes are formed in the multiple sliding rods, and the same transverse rod can penetrate through the second operation holes. According to the invention, the convenience of cable laying can be improved, the labor intensity of cable laying is reduced, and the cable laying efficiency is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of cable laying, and in particular to a cable trench support structure and a cable laying method. Background Art

[0002] A cable trench is an underground pipeline used for laying and replacing power or telecommunication cable facilities. It is an important enclosure structure for the laid cable facilities. During the construction of existing cable trenches, pre-buried cable brackets are generally used or expansion bolts are used to evenly set the cable brackets on the cable trench wall, and then the cables are placed on the cable brackets. Since cables are prone to slipping when placed horizontally on cable brackets, most cable brackets are also equipped with clamps, tie ties, clamps and other fixing devices. After the cables are straightened using cable traction devices, the above fixing devices are used to fix the cables.

[0003] After the cable is placed on the cable bracket, it is necessary to use a fixing device to fix the cable and the cable bracket. For a small cable trench, due to its small space, it is not convenient to operate. At the same time, the cable and the cable bracket need to be fixed in multiple places, which is time-consuming and labor-intensive, affecting the overall cable laying efficiency. Summary of the invention

[0004] In order to improve the efficiency of cable laying, the present application provides a cable trench support structure and a cable laying method.

[0005] The present application provides a cable trench support structure that adopts the following technical solution: First aspect A cable trench support structure, comprising: A fixing frame, used for fixed connection with the side wall of the cable trench, wherein the inner wall of the fixing frame is provided with a plurality of snap-in grooves along the height direction; A sliding rod is slidably connected to the fixing frame along a height direction, and a supporting rod for supporting the cable is fixed on a side wall of the sliding rod; A clamping assembly is arranged in the slide bar, and the clamping end of the clamping assembly can be clamped in the clamping groove to fix the slide bar relative to the fixing frame, and the clamping assembly can stop the slide bar from moving from top to bottom; An unlocking component is arranged inside the slide bar and is used to unlock the clamping component. The operating end of the unlocking component is located outside the slide bar.

[0006] Wherein, a plurality of the sliding rods are provided with second operating holes for the same cross rod to pass through.

[0007] By adopting the above technical solution, the sliding rod is lifted up so that the support rod is located outside the cable trench, and then the cable is laid on the support rod, and the cable and the support rod are tied; due to the effect of the clamping assembly, the sliding rod can be maintained in a certain position, and this position is convenient for personnel to lay the cable on the support rod, saving time and effort; after laying the cable of one layer of support rods, the unlocking assembly is used to unlock, and the sliding rod moves down a distance to continue laying the next layer of cables. At the same time, multiple sliding rods can be operated together through the same crossbar, and the operation is more convenient. Therefore, the present application can improve the convenience of laying cables, reduce the labor intensity of laying cables, and improve the efficiency of cable laying.

[0008] Optionally, the clamping assembly includes: A first wedge block, wherein the first wedge block has a first wedge surface and a first supporting surface, wherein the first wedge surface is located above the first supporting surface and is slidably connected to the inner wall of the clamping groove, the first supporting surface abuts against the plane of the clamping groove, and a portion of the first wedge surface structure extends out of the range of the clamping groove wall; The elastic member has elastic potential energy for pushing the first wedge block toward the clamping groove.

[0009] By adopting the above technical solution, the upward movement of the slide bar is not affected, and the downward movement of the slide bar is stopped, so that the slide bar can remain stable under the gravity of the cable.

[0010] Optionally, the unlocking component includes: An adjusting rod, slidably connected to the sliding rod along a height direction; A pull rope, one end of which is connected to the first wedge-shaped block, and the other end of which is connected to the adjusting rod. When the adjusting rod moves from bottom to top along the height direction, the pull rope can pull the first wedge-shaped block away from the clamping groove.

[0011] By adopting the above technical solution, when the slide bar needs to be moved downward, the slide bar can be quickly loosened by operating the adjustment rod, so that the slide bar moves downward under the gravity of the cable, thereby completing the adaptive position adjustment.

[0012] Optionally, a first operating hole is formed at one end of the adjusting rod outside the sliding rod, and the first operating holes of a plurality of adjusting rods can allow the same cross bar to pass through.

[0013] By adopting the above technical solution, multiple adjustment rods can be operated synchronously to improve the operating efficiency.

[0014] Optionally, a second wedge-shaped surface is provided on the uppermost side of the fixing frame, and the second wedge-shaped surface is in sliding contact with the first wedge-shaped block so that the first wedge-shaped block can be retracted into the sliding rod.

[0015] By adopting the above technical solution, it is ensured that the slide bar can move downward smoothly.

[0016] Optionally, the support rod is detachably connected to the sliding rod.

[0017] By adopting the above technical solution, when laying cables, there is another way, which is to dismantle the support rods at the upper layer and first lay the cables on the lowest support rods. At this time, since there is no influence of the upper support rods, the cable laying efficiency is further improved; after laying the lower support rods, the upper support rods are connected to the sliding rods, and the cable laying on the upper support rods is continued. This solution can reduce the influence of the support rods on the cable laying and improve the cable laying efficiency.

[0018] Optionally, multiple layers of support rods are arranged on the sliding rod, and the number of the clamping components corresponds to the number of layers of the support rods.

[0019] By adopting the above technical solution, when the sliding rod moves to the uppermost end, only a few snap-in components realize the connection between the sliding rod and the fixed frame. After the cables are laid layer by layer, the sliding rod moves downward. At this time, the gravity of the sliding rod increases, and the number of snap-in components increases, which can improve the supporting effect of the sliding rod and ensure the stability of temporary support.

[0020] Optionally, a rough surface is provided between the sliding rod and the fixing frame, and the roughness of the rough surface increases along the height direction.

[0021] By adopting the above technical solution, when the slide bar moves to the uppermost side, the risk of the slide bar and the support rod tipping over can be reduced.

[0022] Second aspect A cable laying method comprises the following steps: S1. Install the cable trench support structure in the cable trench; S2. Lift the slide bar upwards so that the support rod is located outside the cable trench; S3, moving the plurality of slide bars to a predetermined position, wherein the predetermined position enables the snap-in end of the snap-in assembly to snap-in into the snap-in groove to achieve relative fixation of the slide bars and the fixing frame; S4. Lay the cables on the support poles and tie the cables and the support poles together; S5. After the laying of cables on one layer of support poles is completed, the locking of the clamping assembly is released by using the unlocking assembly, and the sliding rod is moved down to a certain height to lay cables on the next layer of support poles.

[0023] S6. After laying the cables on each layer of support poles, move the slide bar into the cable trench.

[0024] By adopting the above technical solution, the cables are laid outside the cable trench, which reduces the problem of narrow cable trenches being inconvenient for cable laying and improves the cable laying efficiency. Furthermore, laying the cables outside the cable trench can provide greater flexibility and facilitate adjustment of the cable layout and length to ensure normal and correct laying.

[0025] Optionally, step S2 includes: using the same cross bar to penetrate the second operating holes of multiple sliding rods, and lifting the multiple sliding rods upward through the same cross bar so that the support rods are located outside the cable trench.

[0026] By adopting the above technical solution, multiple slide bars can be quickly lifted and lowered by using the cross bar, thereby improving efficiency. At the same time, after laying cables on the support rods, the slide bars can be lowered by operating the cross bar, thereby improving the stability of cable lowering and ensuring the cable laying effect.

[0027] In summary, the present application includes at least one of the following beneficial technical effects: 1. The cable of the present application can be laid outside the cable trench, which can improve the convenience of cable laying, reduce the labor intensity of cable laying, and improve the efficiency of cable laying.

[0028] 2. When laying cables, remove the upper support rods and lay the cables on the lowest support rods first. At this time, the cable laying efficiency is further improved because there is no influence of the upper support rods. After laying the lower support rods, connect the upper support rods with the sliding rods and continue laying the cables on the upper support rods. This solution can reduce the influence of the support rods on cable laying and improve the cable laying efficiency.

[0029] 3. Reduce the problem of narrow cable trenches being inconvenient for cable laying, improve cable laying efficiency, and the cable laying is located outside the cable trench, which can provide greater flexibility and facilitate adjustment of the cable layout and length to ensure normal and correct laying. BRIEF DESCRIPTION OF THE DRAWINGS

[0030] Figure 1 It is a front cross-sectional view of the cable trench and cable trench support structure of the present application.

[0031] Figure 2 It is a front cross-sectional view of the cable trench support structure of the present application when it is moved to the outside of the cable trench.

[0032] Figure 3 yes Figure 2 A magnified schematic diagram of the structure of part A.

[0033] Figure 4 yes Figure 3 A magnified schematic diagram of the structure of part B.

[0034] Figure 5 It is a top view of the cable trench and cable trench support structure of the present application.

[0035] Description of reference numerals: 10. Cable trench; 20. Fixing frame; 21. Sliding hole; 22. Snap-in groove; 23. Second wedge-shaped surface; 30. Sliding rod; 31. Support rod; 32. Mounting hole; 33. Connecting piece; 331. Second operating hole; 40. Snap-in assembly; 41. First wedge block; 411. First wedge-shaped surface; 412. First supporting surface; 42. Elastic member; 50. Unlocking assembly; 51. Adjusting rod; 511. First operating hole; 52. Pull rope; 53. Guide wheel; 60. Cross bar. DETAILED DESCRIPTION

[0036] The following is combined with Figure 1-5 This application is described in further detail.

[0037] The present application embodiment discloses a cable trench support structure. Figure 1 and Figure 2 The support structure includes a fixing frame 20, a slide bar 30, a clamping assembly 40 and an unlocking assembly 50. The fixing frame 20 is fixed to the side wall of the cable trench 10. The slide bar 30 is slidably connected to the fixing frame 20 along the height direction. The side wall of the slide bar 30 is horizontally connected with a support rod 31 for supporting the cable. The clamping assembly 40 can stop the movement of the slide bar 30 from top to bottom. The unlocking assembly 50 is used to unlock the clamping assembly 40. The present application can make the support rod 31 located outside the cable trench 10, so as to lay the cable outside the cable trench 10 and reduce the labor intensity.

[0038] Reference Figure 2 The fixing frame 20 can be fixedly connected to the side wall of the cable trench 10 by bolt connection or pre-buried anchor connection. The fixing frame 20 is provided with a sliding hole 21 along the height direction, and the sliding rod 30 is slidably connected in the sliding hole 21. In this embodiment, the sliding hole 21 is arranged in a T-shape so that the sliding rod 30 has a stronger anti-overturning performance. In other embodiments, the sliding hole 21 can also be arranged in a dovetail shape, a polygon, etc.

[0039] Reference Figure 2 and Figure 3 The inner wall of the fixing frame 20 is provided with a plurality of engaging grooves 22 along the height direction, and the engaging assembly 40 includes a first wedge block 41 and an elastic member 42. The first wedge block 41 is slidably connected to the inner wall of the sliding rod 30 along the radial direction of the sliding rod 30, and the first wedge block 41 has a first wedge surface 411 and a first supporting surface 412. The first wedge surface 411 is located above the first supporting surface 412 and the first wedge surface 411 is slidably connected to the inner wall of the engaging groove 22, and the first supporting surface 412 abuts against the plane of the engaging groove 22, and a partial structure of the first wedge surface 411 extends out of the groove wall range of the engaging groove 22, so that when the sliding rod 30 moves upward, the first wedge block 41 can be retracted into the sliding rod 30, and the sliding rod 30 can move up smoothly. When the sliding rod 30 has a tendency to move downward, the first wedge block 41 is engaged in the engaging groove 22 to realize the limited fixation of the sliding rod 30.

[0040] In this embodiment, the elastic member 42 is a telescopic spring, one end of which is connected to the first wedge block 41, and the other end is connected to the inner wall of the slide bar 30. The telescopic spring has elastic potential energy to push the first wedge block 41 toward the clamping groove 22, so that the first wedge block 41 can lock the position of the slide bar 30. The elastic member 42 can also be a reset function member.

[0041] In this embodiment, a mounting hole 32 is provided in the slide bar 30, the first wedge block 41 and the elastic member 42 are both located in the mounting hole 32, and the unlocking assembly 50 includes an adjustment rod 51 and a pull rope 52, the adjustment rod 51 is located in the mounting hole 32 and is slidably connected to the inner wall of the slide bar 30, the adjustment rod 51 slides in the height direction, and one end of the adjustment rod 51 extends to the outside of the slide bar 30 for easy operation. One end of the pull rope 52 is connected to the first wedge block 41, and the other end is connected to the adjustment rod 51, and a guide wheel 53 may be provided in the mounting hole 32, and the guide wheel 53 is used to transmit the pull rope 52 to ensure that the pull rope 52 can pull the first wedge block 41 to move.

[0042] When the locking of the first wedge block 41 needs to be released, the adjusting rod 51 is pulled upwards, and the first wedge block 41 retracts toward the inside of the slide bar 30 under the action of the pull rope 52, and the slide bar 30 can move downwards.

[0043] Reference Figure 2 In this embodiment, multiple groups of snap-in assemblies 40 are provided, and multiple groups of snap-in assemblies 40 are arranged at intervals along the height direction. Multiple layers of support rods 31 are arranged on the slide bar 30, and the number of snap-in assemblies 40 corresponds to the number of layers of support rods 31. When the slide bar 30 moves to the uppermost end, only a few snap-in assemblies 40 realize the connection between the slide bar 30 and the fixed frame 20. After laying the cables layer by layer, the slide bar 30 moves downward. At this time, the gravity of the slide bar 30 increases, and the number of snap-in assemblies 40 increases, which can improve the supporting effect of the slide bar 30 and ensure the stability of temporary support. There are multiple first wedge blocks 41, and multiple first wedge blocks 41 are connected to the same adjustment rod 51 through a pull rope 52. When the adjustment rod 51 is lifted upward, multiple first wedge blocks 41 can be pulled to move at the same time to achieve unlocking.

[0044] In order to further improve the stability of the temporary support of the support rod 31, a rough surface is provided between the slide rod 30 and the fixing frame 20, and the roughness of the rough surface increases along the height direction. That is, when only a few clamping components 40 realize the connection between the slide rod 30 and the fixing frame 20, the rough surface can further reduce the risk of the slide rod 30 and the support rod 31 tipping over.

[0045] Reference Figure 4 and Figure 5In the actual construction process, multiple support structures are installed in the cable trench 10. In order to improve the operation efficiency, the adjustment rods 51 of the multiple support structures are provided with a first operation hole 511 at one end outside the slide rod 30. The first operation holes 511 of the multiple adjustment rods 51 can be passed through by the same cross bar 60. The cross bar 60 is either pre-fixed on the adjustment rod 51 or installed on the adjustment rod 51 by disassembly. The cross bar 60 can be used to operate multiple adjustment rods 51 at the same time, so as to unlock multiple slide rods 30 at the same time, thereby improving the convenience of operation.

[0046] At the same time, a connecting piece 33 is provided on the top side of the slide bar 30, and the connecting pieces 33 on the multiple slide bars 30 are provided with a second operating hole 331 for the same cross bar 60 to pass through. When it is necessary to lift and lower the slide bars 30 of multiple support structures, the slide bars 30 of multiple support structures can be lifted and lowered at the same time by operating the cross bar 60. In addition, when laying the cables of the bottom support rods 31, due to the existence of the cross bar 60, if it is for heavier cables, the cross bar 60 can provide a hoisting position, and hoisting is performed at the cross bar 60, further improving the stability of the slide bar 30 temporarily supporting the cable.

[0047] In order to facilitate the disassembly and assembly of the crossbar 60 on the connecting piece 33, the connecting pieces 33 of different bracket structures are arranged in a staggered manner, such as Figure 5 As shown, different cross bars 60 can be assembled and disassembled with the connecting piece 33 in the horizontal direction.

[0048] Reference Figure 3 A second wedge surface 23 is provided on the uppermost side of the fixed frame 20, and the second wedge surface 23 slides and abuts against the first wedge block 41 so that the first wedge block 41 can be retracted into the sliding rod 30. When the sliding rod 30 moves to the uppermost side, this design scheme can make the first wedge block 41 retract smoothly into the sliding rod 30, thereby improving the smoothness of the downward movement of the sliding rod 30.

[0049] In addition, after laying one layer of cables, the slide bar 30 is moved down to continue laying the next layer of cables until the cable laying is completed. The bottom end of the slide bar 30 abuts against the bottom end of the mounting hole 32, and the fixing frame 20 is used to support the slide bar 30 as a whole, thereby improving the stability of subsequent cable placement.

[0050] In one embodiment, the support rod 31 and the slide rod 30 are detachably connected, and the specific detachable connection method can be a threaded connection, or a snap connection method. The purpose of setting the support rod 31 and the slide rod 30 to be detachably connected is that when laying cables, the support rod 31 located at the upper layer is removed, and the cables of the lowest support rod 31 are laid first. At this time, since there is no shielding effect of the upper support rod 31, the laying efficiency of the cables is further improved; after laying the lower support rod 31, the upper support rod 31 is connected to the slide rod 30, and the laying of the cables on the upper support rod 31 is continued. This solution can reduce the influence of the support rod 31 on the laying of cables and improve the efficiency of cable laying.

[0051] At the same time, due to the special design of the clamping assembly 40 of the present application, the slide rod 30, the support rod 31 and the cable can have a certain upward movement space. When vibration occurs, the slide rod 30 has a certain upward movement buffer relative to the fixed frame 20. Therefore, in actual use, the cable laid on this bracket structure has a certain seismic buffering performance, further enhancing the stability of subsequent cable operation.

[0052] The implementation principle of a cable trench support structure of the embodiment of the present application is as follows: after the slide bar 30 is lifted up so that the support bar 31 is located outside the cable trench 10, the cable is laid on the support bar 31 and the cable and the support bar 31 are bundled; due to the action of the clamping assembly 40, the slide bar 30 can be maintained in a certain position, and this position is convenient for personnel to lay the cable on the support bar 31, saving time and effort; after laying the cable of one layer of support bar 31, the unlocking assembly 50 is used to unlock, the slide bar 30 moves down a distance, and the laying of the next layer of cables continues. At the same time, multiple slide bars 30 can be operated together through the same cross bar 60, and the operation is more convenient. Therefore, the present application can improve the convenience of laying cables, reduce the labor intensity of laying cables, and improve the efficiency of cable laying.

[0053] The present application also discloses a cable laying method, comprising the following steps: S1. Install a cable trench support structure in the cable trench 10.

[0054] Specifically, determine the size and position of the cable trench 10 to ensure that it can accommodate the number and type of cables to be laid; select appropriate bracket materials, such as steel or aluminum alloy brackets, according to the weight of the cables and the laying method; when installing the brackets, ensure the stability and durability of the bracket structure, and the brackets should be evenly distributed in the cable trench 10 to support the weight of the cables and keep the cables neatly arranged; the installation of the brackets should comply with relevant safety regulations and engineering standards to ensure the safety of construction workers.

[0055] S2. Lift the slide bar 30 upwards so that the support rod 31 is located outside the cable trench 10.

[0056] Preferably, the second operating holes 331 of the plurality of slide bars 30 are penetrated by the same cross bar 60 , and the plurality of slide bars 30 are lifted upward by the same cross bar 60 , so that the support rods 31 are located outside the cable trench 10 .

[0057] Specifically, the design of the slide bar 30 should allow it to move freely between the inside and outside of the cable trench 10 to facilitate laying and adjusting the cables; use appropriate tools or mechanical devices to lift the slide bar 30 to ensure the safety and efficiency of the operation; when lifting the slide bar 30, care should be taken to maintain the balance of the slide bar 30 to avoid damage or safety accidents caused by imbalance.

[0058] S3, moving the plurality of slide bars 30 to a predetermined position, wherein the predetermined position enables the snap-in end of the snap-in assembly 40 to snap-in into the snap-in groove 22 to achieve relative fixation of the slide bars 30 and the fixing frame 20.

[0059] Specifically, the predetermined position of the slide bar 30 is determined to ensure that the snap-in end of the snap-in assembly 40 can be accurately snap-into the snap-in groove 22. The snap-in assembly 40 should be designed to be easy to operate and provide sufficient locking force to ensure relative fixation between the slide bar 30 and the fixing frame 20.

[0060] S4, laying the cable on the support rod 31, and binding the cable and the support rod 31.

[0061] Specifically, before laying the cable, the surface of the support rod 31 should be cleaned to ensure that there is no oil or dust to facilitate the fixing of the cable. Use appropriate bundling materials, such as nylon tie or metal clamps, to firmly fix the cable on the support rod 31. Ensure that the bending radius of the cable during laying complies with the regulations of the cable manufacturer to avoid damage to the cable. When laying the cable, pay attention to the arrangement order of the cables to avoid crossing and overlapping, and ensure heat dissipation and maintenance space for the cables.

[0062] S5. After the cables on one layer of support rods 31 are laid, the unlocking assembly 50 is used to release the lock of the clamping assembly 40, and the slide bar 30 is moved down to a certain height to lay the cables on the next layer of support rods 31.

[0063] Specifically, when the slide bar 30 is moved down to a certain height, the stability of the slide bar 30 should be ensured to prevent accidents during the movement. When laying cables on the next layer of support rods 31, steps S3 to S5 are repeated until all cables are laid.

[0064] The present application can alleviate the problem that the narrow cable trench 10 is inconvenient for cable laying, improve the cable laying efficiency, and the cable laying is located outside the cable trench 10, which can provide greater flexibility and facilitate adjustment of the cable layout and length to ensure normal and correct laying.

[0065] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, any equivalent changes made according to the structure, shape, and principle of the present application should be included in the protection scope of the present application.

Claims

1. A cable trench support structure, characterized in that: include: A fixing frame (20) is used for fixedly connecting to the side wall of the cable trench (10), wherein the inner wall of the fixing frame (20) is provided with a plurality of snap-in grooves (22) along the height direction; A sliding rod (30) is slidably connected to the fixing frame (20) along a height direction, and a supporting rod (31) for supporting a cable is fixed to a side wall of the sliding rod (30); A clamping assembly (40) is disposed in the slide bar (30), wherein the clamping end of the clamping assembly (40) can be clamped in the clamping groove (22) so that the slide bar (30) and the fixing frame (20) are relatively fixed, and the clamping assembly (40) can stop the slide bar (30) from moving from top to bottom; An unlocking component (50) is arranged in the slide bar (30) and is used to unlock the clamping component (40), and an operating end of the unlocking component (50) is located outside the slide bar (30); Wherein, a plurality of the sliding rods (30) are provided with second operating holes (331) for the same cross rod (60) to pass through.

2. The cable trench support structure according to claim 1, characterized in that: The clamping assembly (40) comprises: A first wedge block (41), the first wedge block (41) having a first wedge surface (411) and a first supporting surface (412), the first wedge surface (411) being located above the first supporting surface (412) and the first wedge surface (411) being slidably connected to an inner wall of the clamping groove (22), the first supporting surface (412) being in contact with a plane of the clamping groove (22), and a portion of the first wedge surface (411) extending beyond the range of the wall of the clamping groove (22); The elastic member (42) has elastic potential energy for pushing the first wedge block (41) toward the clamping groove (22).

3. The cable trench support structure according to claim 2, characterized in that: The unlocking component (50) comprises: An adjusting rod (51) slidably connected to the sliding rod (30) along a height direction; A pull rope (52) has one end connected to the first wedge block (41) and the other end connected to the adjustment rod (51). When the adjustment rod (51) moves from bottom to top in the height direction, the pull rope (52) can pull the first wedge block (41) away from the clamping groove (22).

4. The cable trench support structure according to claim 3 is characterized in that: A first operating hole (511) is formed at one end of the adjusting rod (51) located outside the sliding rod (30), and the first operating holes (511) of a plurality of adjusting rods (51) can allow the same cross bar (60) to pass through them.

5. The cable trench support structure according to claim 2, characterized in that: A second wedge-shaped surface (23) is provided on the uppermost side of the fixing frame (20), and the second wedge-shaped surface (23) is in sliding contact with the first wedge-shaped block (41) so that the first wedge-shaped block (41) can be retracted into the sliding rod (30).

6. The cable trench support structure according to claim 1, characterized in that: The support rod (31) is detachably connected to the sliding rod (30).

7. The cable trench support structure according to claim 1, characterized in that: Multiple layers of support rods (31) are arranged on the sliding rod (30), and the number of the clamping assemblies (40) corresponds to the number of layers of the support rods (31).

8. The cable trench support structure according to claim 1, characterized in that: A rough surface is provided between the sliding rod (30) and the fixing frame (20), and the roughness of the rough surface increases along the height direction.

9. A cable laying method, based on the cable trench support structure according to any one of claims 1 to 8, characterized in that: The following steps are involved: S1. Installing a cable trench support structure in the cable trench (10); S2, lift the slide bar (30) upward so that the support rod (31) is located outside the cable trench (10); S3, moving the plurality of slide bars (30) to a predetermined position, wherein the predetermined position enables the snap-fitting end of the snap-fitting assembly (40) to snap-fit ​​into the snap-fitting groove (22) to achieve relative fixation of the slide bars (30) and the fixing frame (20); S4, laying the cable on the support rod (31), and tying the cable and the support rod (31); S5, after the laying of cables on one layer of support rods (31) is completed, the locking of the clamping assembly (40) is released by using the unlocking assembly (50), the sliding rod (30) is moved downward to a certain height, and the laying of cables on the next layer of support rods (31) is carried out; S6, after the cables are laid on the supporting rods (31) of each layer in sequence, the sliding rod (30) is moved into the cable trench (10).

10. The cable laying method according to claim 9, characterized in that: Step S2 comprises: using the same cross bar (60) to penetrate the second operating holes (331) of the plurality of sliding bars (30), and lifting the plurality of sliding bars (30) upwards through the same cross bar (60) so that the support rods (31) are located outside the cable trench (10).

Citation Information

Cited By

  • Auxiliary tool for cable laying

    CN119921226A

  • An auxiliary tooling for cable laying

    CN119921226B