Manufacturing method of combined cable bent tower section steel pipe unit
By setting up saddle-shaped grooves and horizontal pallets on the steel pipe, combining stiffener limit sample and angle ruler, high-precision assembly of steel pipe and web joints is achieved, and the problem of insufficient manufacturing accuracy of steel pipe units in the existing technology is solved. Improve product quality and work efficiency.
Patent Information
- Application Number
- CN202411568488.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-11-05
- Publication Date
- 2024-12-06
AI Technical Summary
The existing steel cable tower manufacturing technology cannot meet the assembly accuracy requirements of steel pipes and web joints, which affects the manufacturing accuracy of steel pipe units and the overall quality of the structure.
A combined cable tower segment steel pipe unit manufacturing method is adopted. By setting saddle-shaped grooves and horizontal pallets on the steel pipe, combining stiffener limit sample and angle ruler, the precise positioning and spot welding fixing of web joints is achieved to ensure that High-precision assembly of steel pipe and web joints.
It improves the manufacturing accuracy of steel pipe units, reduces labor intensity, improves work efficiency, ensures product quality, and is suitable for the manufacturing of different types of steel pipe-steel shell combination cable tower segments.
Smart Images

Figure CN119077204A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of combined cable tower segment manufacturing, and in particular to a method for manufacturing a combined cable tower segment steel pipe unit. Background Art
[0002] The steel tube-steel shell composite cable tower is composed of several segments. The four corners of each segment are composed of steel tube units. The steel tube units are connected by steel structure web plates (see Figure 8 ), which reduces the cross-sectional size of the tower column and enhances the structural ductility and earthquake resistance. How to ensure the manufacturing accuracy of the segment and the manufacturing accuracy of the steel pipe unit become key factors.
[0003] The steel tube unit is composed of a steel tube and two web joints axially fixed on the outer circle of the steel tube. The assembly accuracy of the steel tube and the web joint becomes the key to ensuring the manufacturing accuracy of the steel tube unit, while the existing steel cable tower manufacturing technology cannot meet the assembly accuracy requirements of the steel tube and the web joint. Summary of the invention
[0004] The invention provides a method for manufacturing a combined cable tower segment steel pipe unit to overcome the shortcomings of the prior art.
[0005] The technical solution adopted by the present invention is: a method for manufacturing a combined cable tower segment steel pipe unit, the steel pipe unit comprises a steel pipe and two web joints axially fixed on the outer circle of the steel pipe, the web joint comprises two mutually parallel webs and a stiffening plate vertically welded and fixed between the two webs, the inner end of the stiffening plate has an arc opening that matches the outer circle of the steel pipe, the arc opening is evenly distributed with notches, and a middle notch is located in the middle position of the arc opening, the method comprises the following steps: Step 1: a longitudinal baseline and a transverse baseline are arranged on the surface of the platform, and then a plurality of support seats are arranged side by side on the surface of the platform, wherein a saddle-shaped groove is arranged on the top of the left side of the support seat, and a horizontal support plate is arranged on the top of the right side, and the center of the saddle-shaped groove coincides with the longitudinal baseline; Step 2: four axial baselines and one annular baseline are equally set on the outer surface of the steel pipe, and then the steel pipe is placed on the saddle-shaped groove, and an axial baseline at the bottom of the steel pipe is overlapped with the longitudinal baseline, and the annular baseline is parallel to the transverse baseline; Step 3: Weld two middle stiffeners along the axial baselines at the top and right of the steel pipe, and then position and weld the stiffeners on both sides based on the middle stiffener; Step 4: Place the first web joint on the horizontal support plate, and make the inner arc opening of the stiffening plate in the web joint fit with the outer circle of the steel pipe, and make the evenly distributed notches on the arc opening correspondingly snap into the middle stiffening rib and the stiffening ribs on both sides of the right side of the steel pipe, and then adjust the position of the web joint to the designed position based on the annular baseline to complete the positioning of the web joint, and then temporarily fix the web joint to the horizontal support plate with a buckle; Step 5: hoist the second web joint to the top of the steel pipe, and make the inner arc opening of the stiffener in the web joint fit with the outer circle of the steel pipe, and make the evenly distributed notches on the arc opening correspondingly snap into the middle stiffener and the stiffeners on both sides of the top of the steel pipe, and then adjust the position of the web joint to the designed position based on the annular baseline to complete the positioning of the web joint, and then confirm that the web joint is perpendicular to the first web joint by measuring instruments and then fix them by spot welding; Step 6: After the first web joint is welded and fixed to the steel pipe, the second web joint is welded and fixed to the steel pipe, and then the buckle is removed. At this point, the steel pipe unit is manufactured.
[0006] In step 3, the positioning welding of the stiffeners on both sides is completed through the stiffener limiting template, and the inner end of the stiffener limiting template has an arc opening and a notch that are exactly the same as the inner end of the stiffening plate; the specific positioning method is to fit the arc opening of the inner end of the stiffener limiting template with the outer circle of the steel pipe, and make the middle notch on the arc opening fit into the middle stiffener, and then insert the stiffeners on both sides from the notches on both sides of the arc opening to complete the positioning of the stiffeners on both sides of the point and spot weld them to fix them. In this way, after the stiffener limiting template is moved parallel to complete the spot welding positioning of the stiffeners on both sides, the stiffeners on both sides are welded and fixed to the steel pipe.
[0007] The measuring instrument in step 5 is a protractor, which is modified from a right-angled triangle. Specifically, the right angle of the right-angled triangle is modified into an arc opening that fits the outer circle of the steel pipe.
[0008] The saddle-shaped groove is an arc-shaped groove.
[0009] The saddle-shaped groove is a V-shaped groove.
[0010] Compared with the prior art, the present invention has the following beneficial effects: 1. The positioning tooling used in the present invention is simple and easy to manufacture, and the positioning operation is simple, the positioning speed is fast, the precision is high, and the damage to the material and appearance of the steel pipe is avoided, thus ensuring the product quality; 2. The present invention can realize the horizontal positioning of the web joint by setting a horizontal support plate on one side of the steel pipe support, and can complete the vertical positioning of the web joint based on this, without rotating the steel pipe, to ensure the verticality of the two web joints, thereby reducing labor intensity and improving work efficiency.
[0011] 3. The present invention uses a stiffening rib limiting template to realize convenient positioning of the stiffening ribs on both sides of the reference line, thereby ensuring the manufacturing accuracy of the stiffening ribs and further ensuring the assembly accuracy of the steel pipe and web joint.
[0012] 4. The present invention can be applied to the manufacture of different types of steel tube-steel shell combined cable tower segment steel tube units after appropriate adjustment, and also provides a new idea for the future development of steel cable towers. BRIEF DESCRIPTION OF THE DRAWINGS
[0013] Figure 1 is a schematic diagram of step 1 of the present invention; Figure 2 It is a schematic diagram of step 2 of the present invention; Figure 3 It is a schematic diagram of step 3 of the present invention; Figure 4 It is a schematic diagram of step 4 of the present invention; Figure 5 is a schematic diagram of step 5 of the present invention; Figure 6 It is a schematic diagram of the stiffening rib limiting template and the use method of the present invention; Figure 7 It is a schematic diagram of the angle ruler of the present invention and its use method; Figure 8 It is a schematic diagram of the combined cable tower segment structure. DETAILED DESCRIPTION
[0014] The present invention is described in detail below with reference to the accompanying drawings and specific embodiments.
[0015] See also Figure 8 The combined cable tower segment steel pipe unit includes a steel pipe 6 and two web joints 9 axially fixed on the outer circle of the steel pipe 6. The web joint 9 includes two webs 10 parallel to each other and a stiffening plate 11 vertically welded and fixed between the two webs 10. The inner end of the stiffening plate 11 has an arc opening that matches the outer circle of the steel pipe 6. Three notches are evenly distributed on the arc opening, and the middle notch is located in the middle position of the arc opening. See also Figure 1-5 , the manufacturing method of the steel pipe unit comprises the following steps: Step 1: a longitudinal baseline 1-1 and a transverse baseline 1-2 are arranged on the surface of the platform 1, and then a plurality of support seats 2 are arranged side by side on the surface of the platform 1, wherein a saddle-shaped groove 3 is arranged on the top of the left side of the support seat 2, and a horizontal support plate 4 is arranged on the top of the right side, and the center of the saddle-shaped groove 3 coincides with the longitudinal baseline 1-1; The saddle-shaped groove 3 is an arc-shaped groove or a V-shaped groove, preferably a V-shaped groove.
[0016] Step 2: four axial baselines 6-1 and one annular baseline 6-2 are equally divided on the outer surface of the steel pipe 6, and then the steel pipe 6 is placed on the saddle-shaped groove 3, and the axial baseline 6-1 at the bottom of the steel pipe 6 is overlapped with the longitudinal baseline 1-1, and the annular baseline 6-2 is parallel to the transverse baseline 1-2; Step 3: Weld two middle stiffeners 7 along the axial baseline 6-1 at the top and right side of the steel pipe 6, and then position and weld the stiffeners 8 on both sides based on the middle stiffener 7; Step 4: Place the first web joint 9 on the horizontal support plate 4, and make the inner arc opening of the stiffening plate 11 in the web joint fit with the outer circle of the steel pipe 6, and make the three evenly distributed notches on the arc opening correspondingly snap into the middle stiffening rib 7 and the two side stiffening ribs 8 on the right side of the steel pipe 6, and then adjust the position of the web joint to the designed position based on the annular baseline 6-2 to complete the positioning of the web joint, and then use the buckle 12 to temporarily fix the web joint to the horizontal support plate 4; Step 5: hoist the second web joint 9 to the top of the steel pipe 6, and make the inner arc opening of the stiffening plate 11 in the web joint fit with the outer circle of the steel pipe 6, and make the three evenly distributed notches on the arc opening correspondingly snap into the middle stiffening rib 7 and the two side stiffening ribs 8 at the top of the steel pipe 6, and then adjust the position of the web joint to the designed position based on the annular baseline 6-2 to complete the positioning of the web joint, and then confirm that the web joint is perpendicular to the first web joint by measuring instruments and then fix them by spot welding; Step 6: After the first web joint 9 is welded and fixed to the steel pipe 6, the second web joint 9 is welded and fixed to the steel pipe 6, and then the buckle 12 is removed. At this point, the steel pipe unit is manufactured; After the steel pipe unit is manufactured, the finished product will be hoisted to the cable tower construction site for the construction of the steel pipe-steel shell combined cable tower segment.
[0017] See also Figure 6 In the step 3, the positioning welding of the stiffening ribs 8 on both sides is completed by the stiffening rib limiting template 5, and the inner end of the stiffening rib limiting template 5 has an arc opening and a notch that are exactly the same as the inner end of the stiffening plate 11; the specific positioning method is to fit the arc opening of the inner end of the stiffening rib limiting template 5 with the outer circle of the steel pipe 6, and make the middle notch 5-1 on the arc opening be inserted into the middle stiffening rib 7, and then insert the stiffening ribs 8 on both sides from the remaining two notches 5-2 on the arc opening to complete the positioning of the stiffening ribs 8 on both sides of the point and spot weld them to fix them. In this way, after the stiffening rib limiting template 5 is moved parallel to complete the spot welding positioning of the stiffening ribs 8 on both sides, the stiffening ribs 8 on both sides are welded to the steel pipe 6 to fix them.
[0018] See also Figure 7The measuring instrument in step 5 is a protractor 13, which is modified from a right-angled triangle. Specifically, the right angle of the right-angled triangle is modified into a circular arc opening 13-1 that fits the outer circle of the steel pipe 6. The measuring method is to insert the protractor 13 between the two mutually perpendicular webs 10 of the second web joint and the first web, and make the circular arc opening 13-1 fit the outer circle of the steel pipe 6 to confirm whether the second web joint is perpendicular to the first web joint. If not, the circumferential position of the second web joint can be adjusted until it is perpendicular to the first web joint.
[0019] The above embodiments are only preferred embodiments of the present invention and are not intended to limit the scope of implementation of the present invention. Therefore, all equivalent changes made to the contents described in the claims of the present invention should be included in the scope of the claims of the present invention.
Claims
1. A method for manufacturing a combined cable tower segment steel pipe unit, the steel pipe unit comprising a steel pipe (6) and two web joints (9) axially fixed on the outer circle of the steel pipe (6), the web joint (9) comprising two webs (10) parallel to each other and a stiffening plate (11) vertically welded and fixed between the two webs (10), the inner end of the stiffening plate (11) having an arc opening that matches the outer circle of the steel pipe (6), the arc opening having notches evenly distributed thereon, and a middle notch located in the middle of the arc opening, characterized in that The method comprises the following steps: Step 1: a longitudinal baseline (1-1) and a transverse baseline (1-2) are arranged on the surface of the platform (1), and then a plurality of support seats (2) are arranged side by side on the surface of the platform (1), wherein a saddle-shaped groove (3) is provided at the top of the left side of the support seat (2), and a horizontal support plate (4) is provided at the top of the right side, and the center of the saddle-shaped groove (3) coincides with the longitudinal baseline (1-1); Step 2: four axial baselines (6-1) and one annular baseline (6-2) are equally spaced on the outer surface of the steel tube (6), and then the steel tube (6) is placed on the saddle-shaped groove (3), and an axial baseline (6-1) at the bottom of the steel tube (6) is made to coincide with the longitudinal baseline (1-1), and the annular baseline (6-2) is made parallel to the transverse baseline (1-2); Step 3: Weld two middle stiffeners (7) along the axial baseline (6-1) at the top and right side of the steel pipe (6), and then position and weld the stiffeners (8) on both sides with the middle stiffener (7) as the reference; Step 4: Place the first web joint (9) on the horizontal support plate (4), and make the inner arc opening of the stiffening plate (11) in the web joint fit with the outer circle of the steel pipe (6), and make the evenly distributed notches on the arc opening correspondingly snap into the middle stiffening rib (7) and the stiffening ribs (8) on the right side of the steel pipe (6), and then adjust the position of the web joint to the designed position based on the annular baseline (6-2), complete the positioning of the web joint, and then use the buckle (12) to temporarily fix the web joint to the horizontal support plate (4); Step 5: hoist the second web joint (9) to the top of the steel pipe (6), and make the inner arc opening of the stiffening plate (11) in the web joint fit with the outer circle of the steel pipe (6), and make the evenly distributed notches on the arc opening correspondingly fit into the middle stiffening rib (7) and the two side stiffening ribs (8) at the top of the steel pipe (6), and then adjust the position of the web joint to the designed position based on the annular baseline (6-2), complete the positioning of the web joint, and then confirm through a measuring instrument that the web joint is perpendicular to the first web joint, and then fix them by spot welding; Step 6: After the first web joint (9) and the steel pipe (6) are welded and fixed, the second web joint (9) and the steel pipe (6) are welded and fixed, and then the buckle (12) is removed. At this point, the steel pipe unit is manufactured.
2. The method for manufacturing a combined cable tower segment steel pipe unit according to claim 1, characterized in that: In step 3, the positioning welding of the stiffening ribs (8) on both sides is completed by the stiffening rib limiting template (5), and the inner end of the stiffening rib limiting template (5) has a circular arc opening and a notch that are completely identical to the inner end of the stiffening plate (11); the specific positioning method is to fit the circular arc opening of the inner end of the stiffening rib limiting template (5) with the outer circle of the steel pipe (6), and to make the middle notch (5-1) on the circular arc opening snap into the middle stiffening rib (7), and then insert the stiffening ribs (8) on both sides from the notches (5-2) on both sides of the circular arc opening to complete the positioning of the stiffening ribs (8) on both sides of the point and fix them by spot welding. In this way, after the stiffening rib limiting template (5) is moved parallel to complete the spot welding positioning of the stiffening ribs (8) on both sides, the stiffening ribs (8) on both sides are welded and fixed to the steel pipe (6).
3. The method for manufacturing a combined cable tower segment steel pipe unit according to claim 1, characterized in that: The measuring instrument in step 5 is a square ruler (13), which is modified from a right-angled triangle. Specifically, the right angle of the right-angled triangle is modified into a circular arc opening (13-1) that fits the outer circle of the steel pipe (6).
4. The method for manufacturing a combined cable tower segment steel pipe unit according to claim 1, characterized in that: The saddle-shaped groove (3) is an arc-shaped groove.
5. The method for manufacturing a combined cable tower segment steel pipe unit according to claim 1, characterized in that: The saddle-shaped groove (3) is a V-shaped groove.