Control method for optimizing folding and unfolding of riprap elephant trunk device of ramming and flattening integrated ship

By using a symmetrical fixed pipe winch and universal cable guide on the tamping integrated ship rock-dumping device, combined with a small winch to control the wire rope, the problem of underwater unbuttoning and operation complexity of the lower position of the pipe is solved, and the pipe slip is realized Convenient collection and safety improvement.

CN119079824APending Publication Date: 2024-12-06NO 3 ENG COMPANY LTD OF CCCC FIRST HARBOR ENG COMPANY +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411261007.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-10
Publication Date
2024-12-06

AI Technical Summary

Technical Problem

The existing tamping flat-ship rock-drawing pipe device is underwater when the pipe is lowered, which leads to inconvenience in unbuttoning. The movement and lifting of the steel wire ropes are complicated and the safety is low.

Method used

The left and right symmetrical fixed pipe winch is adopted, and the wire rope is controlled through a universal cable guide and a small winch to realize the automatic retraction and expansion of the pipe, simplifying the operation, and avoiding the underwater wire rope unbuttoning.

Benefits of technology

It improves the convenience of sliding pipes and safety, reduces equipment costs, simplifies operating procedures, and enhances mobility flexibility.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119079824A_ABST
    Figure CN119079824A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of construction of ramming and leveling integrated ships, in particular to a control method for optimizing retraction and release of a riprap elephant trunk device of a ramming and leveling integrated ship. A hanging bracket is arranged on a main deck of a ship, a fixed pulley and an inclined hanging rod are arranged on the hanging bracket, a small winch is installed on a hanging bar, a steel wire rope of a chute winch on the right side of a chute trolley is led to a directional pulley on the hanging bracket, and then the telescopic sleeve can be put away and put down on a typhoon prevention shelf. The problem of unbuckling of the underwater steel wire rope is effectively solved, the cost of one traction winch device is saved, and convenience and applicability are achieved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of tamping integrated ship construction, and in particular to a control method for optimizing the retraction and deployment of a riprap chute device of a tamping integrated ship. Background Art

[0002] At present, the existing riprap chute device of the ramming ship is equipped with a riprap trolley, the upper part of the trolley is a collecting hopper, and the chute that can guide the material to be discharged is connected to the lower part of the hopper. The connection between the two is fixed by a rotatable hinge and three eye plate pins. The chute is generally composed of 1-3 telescopic sleeves. The sleeve connected to the hopper pin is the inner sleeve, and the outer telescopic sleeve is pulled by two winches set on the riprap platform. After the telescopic sleeve is retracted, the fixing pin on the tube body is inserted into the inner and outer sleeve pin holes for locking.

[0003] The existing method for collecting and releasing the slide pipe is to provide a rotatable shelf on the ship's side at the location of collecting and releasing the slide pipe on the ship's owner's deck, and to separately set a winch on the ship's owner's deck for lifting and releasing the slide pipe. The winch wire rope passes through the pulley on the collecting and releasing support and connects to the bottom ear of the outer tube of the slide pipe. The slide pipe is lifted and placed on the shelf on the ship's side by the winch action, so that the slide pipe is placed in a horizontal state; when lowering, the end of the slide pipe is pulled up by the winch wire rope, and after the shelf is rotated back to the side, the winch wire rope is used to release the dropped slide pipe, so that the slide pipe is in a vertical natural state.

[0004] The above existing methods have the following disadvantages: when the slide pipe is lowered to a vertical state, the end of the traction rope of the retracting winch is connected to the lifting ear at the bottom of the pipe. The connection position is more than 10 meters underwater, which is not convenient to disengage, and the unfastening requires the cooperation of a diver; if the stone-throwing slide pipe device is operated with a retracting wire rope, the moving distance of the stone-throwing slide pipe device on the track is limited, and the operation of synchronizing the movement of the stone-throwing device with the wire rope of the slide pipe winch is complicated and ineffective, and the wire rope is dragged underwater, which reduces safety. Summary of the invention

[0005] The object of the present invention is to provide a control method for optimizing the retraction and deployment of a ramming integrated ship riprap chute device, so as to solve the problems raised in the above-mentioned background technology.

[0006] To achieve the above object, the present invention provides the following technical solution: a control method for optimizing the retraction and deployment of a ramming integrated ship riprap chute device, characterized in that the control method comprises the following steps: S1. Control method for folding the riprap chute device: S11, the first and second winches are symmetrically fixed on the bottom surface of the trolley of the riprap device, and the steel wire ropes of the two winches are wound around the first and second universal cable guides corresponding to the winches, and then the steel wire ropes are respectively fixed on the bottom ears of the outer tube of the telescopic sleeve; S12, remove the three fixing pins on the outer side of the eye plate at the top of the telescopic sleeve, release the wire ropes of the slide pipe winch 1 and the slide pipe winch 2, and the telescopic sleeve is in a natural drooping state connected by a pin; S13, releasing the wire rope of the small winch fixed on the suspension rod, connecting the hook of the wire rope to the wire clamp, fixing the wire clamp to the wire rope of the second slide pipe winch and locking it, retrieving the wire rope of the small winch, pulling the wire rope of the second slide pipe winch and placing it on the single-cup pulley fixed on the lifting frame; S14, release the wire rope of the first slide winch, retract the wire rope of the second slide winch, lift the telescopic sleeve to the maximum height; pull out the two locking pins, and rotate the two anti-platform racks outward from the ship's side until they are limited by the limit blocks; S15, release the wire rope of the second slide winch, place the telescopic sleeve on the anti-platform shelf, insert the locking pin, and fix the pipe clamp; S2. Control method for lowering the riprap chute device: S21, reclaim the second steel wire rope of the slide winch, lift the telescopic sleeve through the lifting frame, pull out the lock pin, rotate the anti-platform shelf to make it rotate to the side of the ship along with the rotating shaft, and insert the lock pin; S22, releasing the steel wire rope of the second slide winch until the telescopic sleeve is in a naturally drooping state; S23, release the wire rope of the small winch fixed on the boom, fix the wire clamp connected to the hook head on the wire rope of the second slide pipe winch and lock it, use the wire rope of the small winch to recycle, pull the wire rope of the second slide pipe winch out of the wheel groove of the single-cup pulley, and lower the wire rope of the small winch until the wire rope of the second slide pipe winch is in a tension-free state; S24, dismantle the wire clamp and recover the wire rope of the small winch; S25, tighten the wire rope of the slide winch 1 until the eye plate on the top of the telescopic sleeve is fully aligned, insert the pin shaft, and tighten the wire rope of the slide winch 2; S3. Control method for the expansion and contraction of the riprap chute device: S31, tighten the wire ropes of the first and second winches, switch to the linkage synchronization control program of the two winches, and automatically fine-tune the tension of the two winches; S32. The inner sleeve of the telescopic sleeve is fixed to the discharge port through an eye plate, and the sleeve pins on both sides of the telescopic sleeve are pulled out, and the steel wire ropes of the slide pipe winch 1 and the slide pipe winch 2 are linked to be lowered or recovered, and the inner sleeve of the telescopic sleeve is lowered or recovered accordingly.

[0007] A control system for the retraction and deployment of a ramming and leveling integrated ship stone riprap chute device, characterized in that it comprises a chute winch 1 and a chute winch 2 which are symmetrically fixed to the bottom surface of a trolley of the stone riprap chute device, the chute winch 1 and the chute winch 2 are respectively connected to a universal fairlead 1 and a universal fairlead 2 through steel wire ropes, the steel wire ropes of the two fairleads are respectively fixed to the bottom lifting ears of a telescopic sleeve of the chute, and a steel wire clamp is fixedly connected to the steel wire rope of the chute winch 2; the two sides of the telescopic sleeve are connected to sleeve pins and the top is connected to an eye plate, and three fixed pins are connected to the outer side of the eye plate; it also comprises a lifting frame connected to the deck on the folding side of the chute, the lifting frame is connected to a boom, the upper end of the boom is connected to a small winch, the lifting frame is fixedly connected to a single-cake pulley, and an anti-platform shelf is provided between the lifting frame and the telescopic sleeve.

[0008] The typhoon-proof racks are a set of two, each having a groove for placing a telescopic sleeve, the groove being connected to a pipe clamp for fixing the telescopic sleeve, the typhoon-proof racks are connected to the side of the ship via a rotating shaft, and a limit block for positioning the typhoon-proof rack is provided on one side of the typhoon-proof rack.

[0009] The present invention is a control method for the retraction and release of a riprap tube device for an optimized tamping ship. A hanger is arranged on the side of the main deck of the ship, and a fixed pulley and an inclined hanger are arranged on the hanger. A small winch is installed on the hanger bar to lead the steel wire rope of the right side tube winch on the tube trolley to the directional pulley on the hanger, so that the telescopic sleeve can be retracted and lowered on the anti-trailer shelf. The problem of unbuckling the underwater steel wire rope is effectively solved, the cost of a traction winch equipment is saved, and it is convenient and applicable. BRIEF DESCRIPTION OF THE DRAWINGS

[0010] Figure 1 This is a layout diagram of the slide pipe winch of the present invention; Figure 2 It is a structural schematic diagram of the control system of the present invention (the slide pipe device is folded up and lowered); Figure 3 This is a schematic diagram of the structure of the platform-proof shelf of the present invention (in the state where the telescopic sleeve is stored); Figure 4 for Figure 3 Side view.

[0011] In the figure: 1. Slide pipe winch 1; 2. Slide pipe winch 2; 3. Universal cable guide 1; 4. Universal cable guide 2; 5. Telescopic sleeve; 6. Sleeve pin; 7. Anti-platform shelf; 8. Lifting frame; 9. Eye plate; 10. Lifting lug; 11. Single-plate pulley; 12. Hanging rod; 13. Small winch; 14. Wire clamp; 15. Rotating shaft; 16 Limit block; 17. Locking pin; 18. Fixed pipe clamp. DETAILED DESCRIPTION

[0012] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention. Example

[0013] A control system for the retraction and deployment of a ramming integrated ship riprap chute device, comprising a chute winch 1 and a chute winch 2 which are symmetrically fixed on the trolley base of the riprap chute device, the chute winch 1 and the chute winch 2 being connected to a universal fairlead 3 and a universal fairlead 4 respectively through steel wire ropes, the steel wire ropes of the two fairleads being respectively fixed to the bottom lifting ears 10 of a telescopic sleeve 5 of the chute, and a steel wire clamp 14 being fixedly connected to the steel wire rope of the chute winch 2; sleeve pins 6 are connected to the two sides of the telescopic sleeve 5, and an eye plate 9 is connected to the top, and three fixed pins are connected to the outer side of the eye plate 9; and also comprising a lifting frame 8 connected to the deck on the folding side of the chute, the lifting frame 8 being connected to a boom 12, the upper end of the boom 12 being connected to a small winch 13, the lifting frame 8 being fixedly connected to a single-cup pulley 11, and an anti-platform shelf 7 is provided between the lifting frame 8 and the telescopic sleeve 5.

[0014] There are two typhoon-proof racks 7, on which grooves for placing the telescopic sleeve 5 are provided, and the grooves are connected to pipe clamps 18 for fixing the telescopic sleeve 5. The typhoon-proof racks 7 are connected to the side of the ship through a rotating shaft 15, and a limit block 16 for positioning the typhoon-proof rack 7 is provided on one side. Example

[0015] A control method for optimizing the retraction and deployment of a ramming integrated ship riprap chute device, the control method comprising the following steps: S1. Control method for folding the riprap chute device: S11, the slide pipe winch 1 and the slide pipe winch 2 are fixed symmetrically on the bottom surface of the trolley of the riprap slide pipe device, and the steel wire ropes of the two winches are wound around the universal cable guide 1 3 and the universal cable guide 2 4 corresponding to the winches, and then the steel wire ropes are fixed on the bottom lifting ears 10 of the telescopic sleeve 5 respectively; S12, remove the three fixing pins on the outer side of the eye plate 9 at the top of the telescopic sleeve 5, release the wire ropes of the slide pipe winch 1 and the slide pipe winch 2, and the telescopic sleeve 5 is in a natural drooping state connected by a pin; S13, release the wire rope of the small hoist 13 fixed on the suspension rod 12, connect the hook of the wire rope to the wire clamp 14, fix the wire clamp 14 on the wire rope of the slide pipe winch 2 and lock it, use the wire rope of the small hoist 13 to recycle, and pull the wire rope of the slide pipe winch 2 to the single-cup pulley 11 fixed on the lifting frame 8; S14, release the steel wire rope of the slide winch 1, retract the steel wire rope of the slide winch 2, lift the telescopic sleeve 5 to the maximum height; pull out the two locking pins 17, rotate the two anti-platform racks 7 outward from the ship's side until they are limited by the limit blocks 16; S15, release the wire rope of the slide winch 2, place the telescopic sleeve 5 on the anti-platform shelf 7, insert the lock pin 17, and fix the pipe clamp 18; S2. Control method for lowering the riprap chute device: S21, reclaim the steel wire rope of the slide winch 2, lift the telescopic sleeve 5 through the lifting frame 8, pull out the lock pin 17, rotate the anti-platform shelf 7 to make it rotate to the side of the ship along with the rotating shaft 15, and insert the lock pin 17; S22, releasing the wire rope of the slide winch 2 until the telescopic sleeve 5 is in a naturally drooping state; S23, release the steel wire rope of the small winch 13 fixed on the suspension rod 12, fix the steel wire clamp 14 connected to the hook head on the steel wire rope of the slide pipe winch 2 and lock it, use the steel wire rope of the small winch 13 to recycle, pull the steel wire rope of the slide pipe winch 2 out of the wheel groove of the single-cup pulley 11, and lower the steel wire rope of the small winch 13 until the steel wire rope of the slide pipe winch 2 is in a tension-free state; S24, dismantle the wire clamp 14 and recover the wire rope of the small winch 13; S25, tighten the wire rope of the slide winch 1 until the eye plate 9 at the top of the telescopic sleeve 5 is fully aligned, insert the pin shaft, and tighten the wire rope of the slide winch 2; S3. Control method for the expansion and contraction of the riprap chute device: S31, tighten the wire ropes of the slide pipe winch 1 and the slide pipe winch 2, switch to the linkage synchronization control program of the two winches, and automatically fine-tune the tension of the two winches; S32, the inner sleeve of the telescopic sleeve 5 is fixed to the material discharge port through the eye plate 9, the sleeve latches 6 on both sides of the telescopic sleeve 5 are pulled out, and the steel wire ropes of the slide pipe winch 1 and the slide pipe winch 2 are linked to be lowered or recovered, and the outer sleeve of the telescopic sleeve 5 is lowered or recovered accordingly.

[0016] Contents not described in detail in this specification belong to the prior art known to professional and technical personnel in the field. Although the embodiments of the present invention have been shown and described, it is understood by those of ordinary skill in the art that various changes, modifications, substitutions and variations can be made to these embodiments without departing from the principles and spirit of the present invention, and the scope of the present invention is defined by the attached claims and their equivalents.

Claims

1. A control method for optimizing the retraction and deployment of a ramming integrated ship riprap chute device, characterized in that: The control method comprises the following steps: S1. Control method for folding the riprap chute device: S11, a first winch (1) and a second winch (2) are fixed symmetrically on the bottom surface of the trolley of the riprap device, and the steel wire ropes of the two winches are wound around a first universal cable guide (3) and a second universal cable guide (4) corresponding to the winches, and then the steel wire ropes are fixed to the bottom lifting ears (10) of the telescopic sleeve (5); S12, removing the three fixing pins on the outer side of the top eye plate (9) of the telescopic sleeve (5), releasing the steel wire ropes of the slide pipe winch 1 (1) and the slide pipe winch 2 (2), and the telescopic sleeve (5) is in a natural drooping state connected by a pin; S13, releasing the steel wire rope of the small winch (13) fixed on the suspension rod (12), connecting the hook of the steel wire rope to the steel wire clamp (14), fixing the steel wire clamp (14) on the steel wire rope of the second slide pipe winch (2) and locking it, retrieving the steel wire rope of the small winch (13), pulling the steel wire rope of the second slide pipe winch (2) and placing it on the single-plate pulley (11) fixed on the lifting frame (8); S14, releasing the steel wire rope of the first slide winch (1), retrieving the steel wire rope of the second slide winch (2), and lifting the telescopic sleeve (5) to the maximum height; pulling out the two locking pins (17), and rotating the two anti-platform racks (7) outward from the ship's side until they are stopped by the limit blocks (16); S15, releasing the steel wire rope of the second slide winch (2), placing the telescopic sleeve (5) on the anti-platform shelf (7), inserting the locking pin (17), and fixing the pipe clamp (18); S2. Control method for lowering the riprap chute device: S21, retrieving the steel wire rope of the second (2) slide winch, lifting the telescopic sleeve (5) through the lifting frame (8), pulling out the locking pin (17), rotating the anti-platform shelf (7) so that it rotates along the rotating shaft (15) to the side of the ship, and inserting the locking pin (17); S22, releasing the steel wire rope of the second slide winch (2) until the telescopic sleeve (5) is in a naturally drooping state; S23, releasing the steel wire rope of the small winch (13) fixed on the suspension rod (12), fixing the steel wire clamp (14) connected to the hook head on the steel wire rope of the second slide pipe winch (2) and locking it, using the steel wire rope of the small winch (13) to retract, pulling the steel wire rope of the second slide pipe winch (2) out of the wheel groove of the single-cup pulley (11), and lowering the steel wire rope of the small winch (13) until the steel wire rope of the second slide pipe winch (2) is in a tension-free state; S24, dismantling the wire clamp (14) and recovering the wire rope of the small winch (13); S25, tighten the steel wire rope of the slide winch 1 (1) until the eye plate (9) at the top of the telescopic sleeve (5) is completely aligned, insert the three pins, and tighten the steel wire rope of the slide winch 2 (2); S3. Control method for the expansion and contraction of the riprap chute device: S31, tighten the steel wire ropes of the first and second winches, switch to the linkage synchronization control program of the two winches, and automatically fine-tune the tension of the two winches; S32, the inner sleeve of the telescopic sleeve (5) is fixed to the discharge port through the eye plate (9), the sleeve pins (6) on both sides of the telescopic sleeve (5) are pulled out, and the outer sleeve of the telescopic sleeve (5) is lowered or recovered by linking the steel wire ropes of the slide pipe winch 1 (1) and the slide pipe winch 2 (2).

2. The control method for the retraction and deployment of the optimized tamping integrated ship riprap chute device according to claim 1 is characterized in that: There are two typhoon-proof racks (7), each having a groove for placing the telescopic sleeve (5), the groove being connected to a pipe clamp (18) for fixing the telescopic sleeve (5), the typhoon-proof rack (7) being connected to the side of the ship via a rotating shaft (15), and a limit block (16) for positioning the typhoon-proof rack (7) being provided on one side.