Construction method of bridge closure section
Through the swing lifting method of cable-loading crane and hoist, combined with the traction system and three-way adjustment device, the longitudinal displacement problem in the long-span bridge is solved, the construction efficiency and quality are improved, the bracket construction is reduced, and construction safety is ensured.
Patent Information
- Application Number
- CN202411125385.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-15
- Publication Date
- 2024-12-06
AI Technical Summary
In bridge construction, especially during the process of multi-span continuous bridges, the larger bridge span leads to a large longitudinal displacement of the concrete of the anchor section and anchor span section, and conventional brackets cannot adapt, which affects the construction quality and poses safety risks.
Using the method of lifting and moving the cable-loading crane and hoist, two joint points are set up in the bridge, and the joint section is lifted through the cable-loading crane, and precise adjustment is made using the traction system and three-way adjustment device to ensure the lifting and lifting of the joint section. The connection process is safe and efficient.
It improves the construction efficiency of bridge merging, reduces the construction site support construction risks, ensures construction quality and safety, and is suitable for suspension bridges with larger bridge spans.
Smart Images

Figure CN119083307A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of bridge construction, and in particular to a construction method for a bridge closure section. Background Art
[0002] The closure method of multi-span continuous bridges has a great impact on the construction period and quality of the bridge. At present, the closure method of multi-span continuous bridges is usually to close the side spans first and then the middle spans. The construction characteristics of this are: the bridge span is usually small, and during the closure, the longitudinal displacement of the beam body of the cast-in-place section of the support is very small or even negligible.
[0003] However, when the span of the bridge is large, the longitudinal displacement of the concrete in the anchor section and the anchor span section is large, and conventional brackets cannot adapt to it, which seriously affects the quality of concrete construction and poses serious safety risks. Therefore, a closure method suitable for suspension bridges with large spans is needed. Summary of the invention
[0004] The purpose of the present application is to provide a method for constructing a bridge joint section, which sets two joint points in the middle span of the bridge close to the side span beam section, and uses a cable-mounted crane and a winch to lift and swing to complete the lifting construction of the joint section. The operation is convenient and the linear control is good.
[0005] In order to achieve the above objectives, this application provides the following technical solutions: A construction method for a bridge closure section comprises the following steps: The cable-mounted crane moves unloaded to the lifting position on the main cable near the middle span of the cable tower for lifting the joint segment, and the transport ship transports the beam segment to be installed to the bottom of the lifting position; The secondary closure section is first lifted to a position higher than the design elevation by a cable-mounted crane, and the traction system provided on the side span is used to tug the secondary closure section toward the side span to swing closer to the side span beam section, and the secondary closure section is connected to the sling and temporarily connected to the adjacent beam section; After the installation of other secondary closure sections is completed according to the above steps, the cable-mounted crane lifts the main closure section from the transport ship to a position flush with the installed beam section, the main closure section is connected to the permanent sling, and the two ends of the main closure section are connected to the middle span beam section and the secondary closure section connected to the side span beam section on site; A three-way adjustment device is installed on the top of the transition pier, and the position of the side span beam section adjusted by the three-way adjustment device is then connected to the closure section on site to complete the closure of the bridge.
[0006] Further setting: Before the cable-mounted crane lifts the main closure section, it is necessary to measure the width of the closure mouth and cut the main closure section on the transport ship according to the width of the closure mouth.
[0007] Further setting: When the cable-mounted crane lifts the beam section, the beam section is first suspended below the design elevation to confirm that the plane position of the beam section does not conflict with the installed beam section, and then continues to lift the beam section to the set height position.
[0008] Further configuration: the traction system includes a winch arranged on the tower top gantry, the tower top gantry is provided with a steering pulley, the steel wire rope of the winch passes around the steering pulley and is lowered along the cable tower, a shoulder pole beam is installed at the door hole at the bottom of the cable tower, the fixed pulley group is fixed to the shoulder pole beam by the steel wire rope, and the steel wire rope lowered by the winch to the bottom of the cable tower is turned by the fixed pulley group on the shoulder pole beam to connect with the beam section that needs to be pulled offset.
[0009] Further configuration: the three-way adjustment device includes an upper support plate, a lower support plate, a vertical jack and a thin lateral jack. The upper support plate is arranged on the lower support plate, so the lower support plate is fixed to the transition pier, and the upper support plate and the lower support plate are independent of each other. A polyfluoro slide plate is provided between the upper support plate and the lower support plate as a relative sliding device between the upper support plate and the lower support plate. The vertical jack is arranged on the upper support plate, and the protruding end of its piston rod is connected to the beam section to adjust the vertical direction of the beam section. The thin lateral jack is arranged horizontally and its two ends are respectively connected to the upper support plate and the lower support plate to adjust the relative position of the upper support plate and the lower support plate through the thin lateral jack.
[0010] It is further configured that a limiting plate is provided on the side of the lower supporting plate to limit the upper supporting plate from sliding off the lower supporting plate.
[0011] Further arrangement: after linear adjustment using the three-way adjustment device, the matching parts between the temporary beam sections are connected in the order of first the side web, then the inclined bottom plate, then the bottom plate, and the top plate to adjust the beam section interface.
[0012] Further configuration: by arranging an auxiliary trolley and a construction shed on the beam segment to assist in the construction site connection between the beam segments, the auxiliary trolley and the construction shed form a closed working place at the joints of adjacent beam segments.
[0013] Further setting: The on-site connection is carried out in the order of vertical welding first and then flat welding, and internal welding first and then external welding.
[0014] Further settings: When performing simple on-site connections of beam sections, the butt joints of the bottom plate of the beam section and the corner welds of the plate ribs are welded by intelligent welding robots; the on-site butt joints of the top plate, bottom plate and inclined bottom plate of the beam section are constructed using a welding process that uses a ceramic liner on the back, CO2 gas shielded automatic welding for primer, and submerged arc automatic welding for single-sided welding and double-sided forming.
[0015] Compared with the prior art, the solution of this application has the following advantages: 1. In the construction method of the bridge joint section involved in the present application, the main cable of the suspension bridge is used in conjunction with a cable-mounted crane and a winch to complete the construction of the joint section, so that the swinging construction of the beam section is rapid and efficient, which can significantly improve the construction efficiency of the joint. In addition, during the construction of the beam section, there is no need to rely on temporary supports, which reduces the construction of scaffolding on the construction site, reduces the construction content, and is conducive to shortening the construction period.
[0016] 2. In the construction method of the bridge joint section involved in the present application, the traction equipment adopts a winch installed on the tower top gantry and equipped with a guide wheel group to realize the offset of the traction plate of the hoisting beam section. The guide wheel group can change the direction of the force and increase the length of the wire rope to improve the lifting capacity of the winch or its ability to adapt to complex terrain.
[0017] 3. In the construction method of the bridge joint section involved in the present application, each time the cable-mounted crane lifts a beam section, the beam section is first suspended in the air to determine whether the horizontal plane of the beam section conflicts with the installed beam section, so as to ensure the safety of the construction and avoid the situation where the lifted beam section collides with the installed beam section and causes damage to the beam body.
[0018] 4. In the construction method of the bridge joint section involved in the present application, a three-way adjustment device is set on the top of the transition pier to adjust the gap and linearity between the side span beam section and the beam section of the joint section to meet the subsequent site connection requirements and ensure the construction quality.
[0019] Additional aspects and advantages of the present application will be partially given in the following description, which will become apparent from the following description, or will be understood through the practice of the present application. BRIEF DESCRIPTION OF THE DRAWINGS
[0020] The above and / or additional aspects and advantages of the present application will become apparent and easily understood from the following description of the embodiments in conjunction with the accompanying drawings, in which: Figure 1 A process flow chart of an embodiment of a construction method for a bridge closure section of the present application; Figure 2 A schematic diagram of hoisting a secondary closure section in one embodiment of a construction method for a bridge closure section of the present application; Figure 3 A schematic diagram of hoisting the main closure section in one embodiment of the construction method of the bridge closure section of the present application; Figure 4 A schematic diagram of the structure of a tower top gantry in one embodiment of a construction method for a bridge closure section of the present application; Figure 5 A schematic diagram of a shoulder beam at the bottom of a cable tower in one embodiment of a construction method for a bridge closure section of the present application; Figure 6A schematic structural diagram of a three-way adjustment device in one embodiment of a construction method for a bridge closure section of the present application; Figure 7 This is a schematic elevational structural diagram of a three-way adjustment device in an embodiment of a construction method for a bridge closure section of the present application. DETAILED DESCRIPTION
[0021] The embodiments of the present application are described in detail below, and examples of the embodiments are shown in the accompanying drawings, wherein the same or similar reference numerals throughout represent the same or similar elements or elements having the same or similar functions. The embodiments described below with reference to the accompanying drawings are exemplary and are only used to explain the present application, and cannot be interpreted as limiting the present application.
[0022] Those skilled in the art will appreciate that, unless specifically stated, the "said" and "the" used herein may also include plural forms. It should be further understood that the term "including" used in the specification of the present application refers to the presence of the features, parts and / or components, but does not exclude the implementation of other features, parts, components and / or their combinations supported by the technical field. The term "and / or" used herein refers to at least one of the items defined by the term, for example, "A and / or B" can be implemented as "A", or as "B", or as "A and B".
[0023] In the description of the present application, the directions or positional relationships indicated by words such as "center", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside" and "outside" are based on the exemplary directions or positional relationships shown in the accompanying drawings. They are for the convenience of describing or simplifying the description of the embodiments of the present application, and do not indicate or imply that the referred device or component must have a specific orientation, or be constructed and operated in a specific orientation. Therefore, they should not be understood as limitations on the present application.
[0024] The terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Thus, a feature defined as "first" or "second" may explicitly or implicitly include one or more of the features. In the description of this application, unless otherwise specified, "plurality" means two or more.
[0025] In the description of this application, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a direct connection, or an indirect connection through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in this application can be understood according to specific circumstances.
[0026] In order to make the objectives, technical solutions and advantages of the present application clearer, the implementation methods of the present application will be further described in detail below with reference to the accompanying drawings.
[0027] Please combine Figures 1 to 7 The present application provides a construction method for a bridge joint section, which mainly utilizes a cable-mounted crane 2 and a winch 31 to first perform the lifting and swinging construction of a secondary joint section 200, and after completing the connection of the slings and the temporary connection of adjacent beam sections, the cable-mounted crane 2 is then used to continue to complete the lifting construction of the main joint section to complete the jointing of the main beam.
[0028] In this embodiment, the entire bridge is provided with 2 main joint sections 100 and 4 secondary joint sections 200. The secondary joint section 200 is the G beam section on the east and west banks near the tower side of the main bridge, and the main joint section 100 is the B beam section located on the east and west banks near the tower side of the main bridge. After completing the construction of the beam section near the middle span side of the main joint section 100, the lifting and swinging construction of the secondary joint section 200 is carried out.
[0029] Please combine Figures 1 to 3 The construction method of the bridge closure section of the present application comprises the following steps: Before lifting the beam section, it is necessary to install a cable-mounted crane 2 on the main cable. The cable-mounted crane 2 includes a traveling mechanism, a main beam truss and a lifting system. The traveling mechanism is connected to the main cable and can move along the axial direction of the traveling mechanism. The main beam truss is mounted on two sets of traveling mechanisms respectively arranged on two main cables. The lifting system is arranged in the main beam truss for lifting the beam section. A tower top gantry 3 is arranged on the top of the cable tower 500. The tower top gantry 3 extends to the outside of the cable tower 500 along the bridge direction, and a winch 31 is arranged on the tower top gantry 3. At the same time, a guide wheel group is arranged on the main beam at the cable tower 500 for pulling the beam section for construction.
[0030] During construction, the cable-mounted crane is first moved empty to the lifting position on the main cable located on the side of the tower near the middle span for lifting the joint section. The lifting position is located above the joint mouth. The transport ship 1 transports the beam section to be installed to the bottom of the lifting position, and the cable-mounted crane 2 lowers its lifting device onto the transport ship 1 to connect with the beam section to be lifted.
[0031] Start the cable-mounted crane 2, and first lift the secondary joint section 200 to a position higher than the designed elevation by the cable-mounted crane 2, and then use the traction system arranged on the side span side to pull the secondary joint section 200 toward the side span side to swing closer to the side span beam section 300. After the secondary joint section 200 and the side span beam section 300 are close to each other, the secondary joint section 200 is connected to the sling and temporarily connected to the adjacent beam section to complete the connection of the secondary joint section 200.
[0032] When the cable-mounted crane 2 is lifting the secondary joint section 200, it first lifts the secondary joint section 200 and suspends it for 20 cm to confirm that the plane position of the beam section does not conflict with the side span beam section 300, and then continues to lift. During the lifting process, attention should be paid to the longitudinal position of the beam section. If there is any displacement, it needs to be adjusted in time. In addition, the entire lifting process needs to ensure that the lifting wire rope is subjected to vertical force to prevent the beam section from swinging after being vacated and increasing the load force of the cable-mounted crane 2, so as to ensure the stability of the beam section lifting. In this embodiment, the secondary joint section 200 is lifted to about 1 m above the design elevation and then the lifting is stopped, and then the secondary joint section 200 is towed by the traction system provided on the side span side.
[0033] Please combine Figure 4 and Figure 5 The traction system of this embodiment includes a winch 31 provided on the tower top gantry 3, and a steering pulley 32 is provided on the tower top gantry 3. The steel wire rope of the winch 31 passes over the steering pulley 32 and is lowered along the cable tower 500. A shoulder beam 4 is installed at the door hole at the bottom of the cable tower 500. The fixed pulley block 41 is fixed to the shoulder beam 4 through the steel wire rope. The steel wire rope lowered by the winch 31 to the bottom of the cable tower 500 is turned through the fixed pulley block 41 on the shoulder beam 4 to connect with the beam section that needs to be pulled and offset, and then the winch 31 provided on the tower top gantry 3 is used to pull and offset the hoisted beam section. In this embodiment, the maximum swing angle of the hoisting offset of the cable-mounted crane 2 is 16.66°, which does not exceed the maximum offset angle of 20° of the cable-mounted crane 2, and can ensure the stability of the hoisting offset of the secondary joint section 200.
[0034] After completing the installation of other secondary closure sections 200 according to the above steps, the cable-mounted crane 2 lifts the main closure section 100 from the transport ship 1 to a position flush with the installed beam section, stops lifting the main closure section 100, and installs a permanent sling on the closure section.
[0035] Before lifting the main closure section 100, the cable-mounted crane 2 needs to continuously and accurately measure the width of the closure mouth within a specified period of time. The measurement points include: the intersection point between the top plate and the side web plate, the intersection point between the side web plate and the inclined bottom plate, the intersection point between the inclined bottom plate and the bottom plate, etc. At the same time, it is also necessary to measure the atmospheric temperature, the temperature inside the beam section, etc. After the first measurement, it is necessary to re-measure immediately. The measured length dimension of the same point shall not be greater than 3mm, otherwise it is necessary to measure again, eliminate the excess value, and take the average value of the two sets of data at each point as the measurement result at the temperature. Then, based on the elimination of the excess value, take the average value of the two sets of data at each point as the measurement result at the temperature. In addition, according to the measured closure mouth width value, the steel beam of the main closure section 100 on the transport ship 1 is cut to make the hoisted main closure section 100 fit the closure mouth. During the lifting process, the main joint section 100 needs to be suspended 20 cm first, and after confirming that the plane position of the steel box girder does not conflict with the installed beam section, the top plane of the main joint section 100 is lifted to be flush with the top plane of the installed adjacent beam section, and then the permanent cable clamp is connected, and the secondary joint section 200 is connected on site.
[0036] A three-way adjustment device 5 is installed on the top of the transition pier 400, and the position of the side span beam section 300 is adjusted by the three-way adjustment device 5 to connect it with the joint section on site.
[0037] Please combine Figure 6 and Figure 7 The three-way adjustment device 5 includes an upper support plate 51, a lower support plate 52, two vertical jacks 53 and a thin lateral jack 54. The upper support plate 51 is arranged on the lower support plate 52, and the lower support plate 52 is fixed to the transition pier 400. The upper support plate 51 and the lower support plate 52 are independent of each other. A polytetrafluoroethylene slide plate 55 is arranged between the upper support plate 51 and the lower support plate 52 as a relative sliding device between the upper support plate 51 and the lower support plate 52. A limit plate 56 is also arranged on the side of the lower support plate 52 to limit the upper support plate 51 from sliding off the lower support plate 52. The vertical jack 53 is arranged on the upper support plate 51, and the extended end of its piston rod is connected to the beam section to adjust the vertical direction of the beam section. The two ends of the thin lateral jack 54 are respectively connected to the upper support plate 51 and the lower support plate 52, so as to adjust the relative position of the upper support plate 51 and the lower support plate 52 through the thin lateral jack 54. Specifically in this embodiment, the vertical jack 53 has a minimum height of 310 mm, an extended height of 435 mm, and a stroke of 125 mm; the thin lateral jack 54 has a minimum height of 160 mm, an extended height of 260 mm, and a stroke of 100 mm.
[0038] After the installation of the joint section is completed, the side span beam section 300 is returned to the top of the side span section using the three-way adjustment device 5 to accurately adjust the linearity of the steel beam, accurately adjust the gap between the two beam sections, make the upper stop top plates of the adjacent beam sections contact each other, and use the vertical jack 53 to fine-tune the elevation of the side span beam section 300 so that the top plate of the side span beam section 300 and the top plate of the joint section beam section are at the same elevation, and then perform precise matching of the interface.
[0039] The precise matching connection of the beam section interface follows the principle of completing it from the place with strong vertical rigidity to the place with weak rigidity at both ends of the cross section, that is, the matching parts between the temporary beam sections are connected in the order of the side web, then the inclined bottom plate, then the bottom plate, and the top plate. First align the web and tighten the tension rod bolts at the web, then align the inclined bottom plate and the bottom plate, and tighten the angle matching bolts and tension rod bolts on the inclined bottom plate and the bottom plate. A small amount of misalignment can be adjusted with a jack. During the precise matching adjustment process, check the misalignment of the interface and the welding gap. Because the stress state after the beam section is hoisted is inconsistent with the stress state during pre-assembly, the plate surface of the non-matching part connection part is misaligned. After the matching parts are connected, local misalignment adjustment is performed, that is, the horse plate is used with the jack for local adjustment to ensure that the plate surface misalignment is not greater than 1.0mm. In addition, the horse plate of this embodiment adopts the form of reverse hook, the back of the horse plate is a steel plate to fit the lower surface of the parent material, and the front hook position is tightened with a wedge. After the weld primer between the spans is completed, the horse plate is removed and a secondary welding is performed on the weld position occupied by the original horse plate. This can reduce the welding work with the bridge deck during assembly while ensuring the assembly accuracy of the beam section and controlling deformation, so as to reduce the damage to the beam section parent body after removing the horse plate.
[0040] After the side span beam section 300 is accurately aligned with the joint section, the connection between the frame beam section and the joint section is carried out on site. The welding conditions of the connection on site are more complicated and difficult than those in the factory. For example, the components cannot be turned over after they are in place, which affects the welding. The climate changes greatly and high-altitude operation is required. Therefore, the process evaluation conditions of the connection on site are more complicated, and more considerations should be made for high-altitude wind speed, low-temperature welding and other aspects. Flux-cored wire shielded welding is often used for high-altitude welding on site.
[0041] Before the construction site connection, it is necessary to configure a welding power supply with a capacity of not less than 200KVA on each hoisting and welding operation surface according to the total amount of welding projects on the bridge and the construction progress requirements. At the same time, a temporary auxiliary trolley is designed and manufactured. The auxiliary trolley has the function of moving longitudinally along the beam section. The lower walkway of the auxiliary trolley can be retracted horizontally so that the operator can reach any position of the annular joint. Before the beam section to be closed is hoisted, the auxiliary trolley can be pre-installed on the installed beam section. A construction shed is also installed on the auxiliary trolley. The construction shed and the auxiliary trolley can form a closed workplace in the wind. The outer cover of the construction shed is equipped with a protective tarpaulin. The protective tarpaulin can seal the joints between the construction shed and the auxiliary trolley and the outer plate of the box beam on rainy days. The protective tarpaulin and the top plate of the steel box beam are pressed tightly with heavy objects or magnetic seats to prevent rainwater from flowing along the surface of the box beam to the weld area, so as to prevent rainwater from flowing along the top plate to the annular joint.
[0042] Before welding between beam sections, the weld and 50mm on both sides must be derusted, and no water, oil, scale or other contaminants are allowed; the surface of the parent material with ceramic pads pasted 120mm must not have dust, water, oil or other contaminants. The longitudinal weld excess height should be scraped and ground to at least 60mm from the port on the ceramic pad surface, and the welding surface should be at least 90mm wide to facilitate pasting of ceramic pads and flaw detection to ensure the quality of the weld. Welding must be carried out within 24 hours after the weld is derusted. If it exceeds 24 hours, it should be derusted again before welding. In addition, before welding, it is necessary to check the weld condition of the butt joint of the steel structure segment, including whether the joint groove angle gap, size, welding height difference, etc. meet the requirements. If not, it must be repaired and corrected.
[0043] Due to the complex construction environment and poor welding conditions at the bridge site, the welding quality is the key to the welding quality of the entire bridge. In order to reduce the impact of human factors on the welding quality at the bridge site and improve the appearance quality of the weld, this embodiment adopts an intelligent welding mode to improve the first-time welding pass rate and avoid delays in rework. The bottom (inclined bottom) plate butt joints and plate rib fillet welds are welded using an intelligent welding robot (portable robot) to improve the first-time welding pass rate and avoid delays in rework. The on-site butt joints of the top plate, bottom plate and inclined bottom plate adopt the welding process of single-sided welding and double-sided forming with ceramic lining on the back, CO2 gas shielded automatic welding for base laying and submerged arc automatic welding. At the same time, the following requirements should be followed: ① The annular seam between the beam sections is a transverse butt weld, which is the main force transmission weld and requires 100% penetration and 100% non-destructive testing; ② Positioning welding can be done by manual welding or CO2 gas shielded welding. During positioning welding, the relevant regulations on the bridge connection welding process shall be implemented. When cracks or other serious defects appear in the positioning weld, the cause should be found out before the defects are removed and the positioning weld is supplemented; ③ When CO2 gas shielded welding is used in the box, the welder must wear a protective mask and must be equipped with ventilation and protection safety facilities to prevent the CO generated during welding from affecting the welder's safety.
[0044] That is, the welding sequence between the beam sections of this embodiment is: vertical welding first and then flat welding, internal welding first and then external welding, that is, after the on-site beam adjustment is completed, the web vertical welding is first welded, then the bottom plate horizontal internal welding is welded, and finally the top plate horizontal external welding is welded, thereby completing the welding between the beam sections and completing the main beam joint.
[0045] The above description is only a partial implementation method of the present application. It should be pointed out that for ordinary technicians in this technical field, several improvements and modifications can be made without departing from the principles of the present application. These improvements and modifications should also be regarded as the scope of protection of the present application.
Claims
1. A construction method for a bridge closure section, characterized in that: The following steps are involved: The cable-mounted crane moves unloaded to the lifting position on the main cable near the middle span of the cable tower for lifting the joint segment, and the transport ship transports the beam segment to be installed to the bottom of the lifting position; The secondary closure section is first lifted to a position higher than the design elevation by a cable-mounted crane, and the traction system provided on the side span is used to traction the secondary closure section to swing toward the side span to get closer to the side span beam section, and the secondary closure section is connected to the sling and temporarily connected to the adjacent beam section; After the installation of other secondary closure sections is completed according to the above steps, the cable-mounted crane lifts the main closure section from the transport ship to a position flush with the installed beam section, the main closure section is connected to the permanent sling, and the two ends of the main closure section are connected to the middle span beam section and the secondary closure section connected to the side span beam section on site; A three-way adjustment device is installed on the top of the transition pier, and the position of the side span beam section adjusted by the three-way adjustment device is then connected to the closure section on site to complete the closure of the bridge.
2. The construction method of the bridge closure section according to claim 1, characterized in that: Before lifting the main closure section, the cable-mounted crane needs to measure the width of the closure mouth and cut the main closure section on the transport ship according to the width of the closure mouth.
3. The construction method of the bridge closure section according to claim 1, characterized in that: When the cable-mounted crane is lifting a beam section, it first suspends the beam section below the design elevation to confirm that the plane position of the beam section does not conflict with the installed beam section, and then continues to lift the beam section to the set height position.
4. The construction method of the bridge closure section according to claim 1, characterized in that: The traction system includes a winch installed on the tower top gantry, and a steering pulley is provided on the tower top gantry. The steel wire rope of the winch passes around the steering pulley and is lowered along the cable tower. A shoulder pole beam is installed at the door hole at the bottom of the cable tower, and a fixed pulley block is fixed to the shoulder pole beam through a steel wire rope. The steel wire rope lowered by the winch to the bottom of the cable tower is turned through the fixed pulley block on the shoulder pole beam to connect with the beam section that needs to be pulled offset.
5. The construction method of the bridge closure section according to claim 1, characterized in that: The three-way adjustment device includes an upper support plate, a lower support plate, a vertical jack and a thin lateral jack. The upper support plate is arranged on the lower support plate, so the lower support plate is fixed to the transition pier, and the upper support plate and the lower support plate are independent of each other. A polyfluoro slide plate is provided between the upper support plate and the lower support plate as a relative sliding device between the upper support plate and the lower support plate. The vertical jack is arranged on the upper support plate, and the protruding end of its piston rod is connected to the beam section to adjust the vertical direction of the beam section. The thin lateral jack is arranged horizontally and its two ends are respectively connected to the upper support plate and the lower support plate to adjust the relative position of the upper support plate and the lower support plate through the thin lateral jack.
6. The construction method of the bridge closure section according to claim 5, characterized in that: A limiting plate for limiting the upper supporting plate from sliding off the lower supporting plate is also provided on the side of the lower supporting plate.
7. The construction method of the bridge closure section according to claim 1, characterized in that: After linear adjustment using the three-way adjustment device, the matching parts between temporary beam sections are connected in the order of first the side web, then the inclined bottom plate, then the bottom plate, and the top plate to adjust the beam section interface.
8. The construction method of the bridge closure section according to claim 1, characterized in that: The connection between the beam sections is assisted by arranging an auxiliary trolley and a construction shed on the beam sections, wherein the auxiliary trolley and the construction shed form a closed working place at the joints of adjacent beam sections.
9. The construction method of the bridge closure section according to claim 1, characterized in that: The on-site connection is carried out in the order of vertical welding first and then flat welding, and internal welding first and then external welding.
10. The construction method of the bridge closure section according to claim 9, characterized in that: When making simple on-site connections of beam sections, intelligent welding robots are used to weld the butt joints of the bottom plate of the beam section and the corner welds of the plate ribs; the on-site butt joints of the top plate, bottom plate and inclined bottom plate of the beam section are constructed using a welding process that uses a ceramic liner on the back, CO2 gas shielded automatic welding for primer laying, and submerged arc automatic welding for single-sided welding and double-sided forming.
Citation Information
Patent Citations
Construction method for erecting stiffening girder through movable cable clamp
CN110878526A
Mid-span closure method for steel box girders of cable-stayed bridge
CN113106872A
Cantilever type steel box girder high-precision cable hoisting construction method
CN115162182A
Double-section hoisting equipment and method for steel box girder of large suspension bridge in deepwater sea area
CN118207797A
Asymmetric erection construction method for cable-stayed and suspension cable cooperative system bridge
CN118360871A