Foundation pit dewatering construction method

The foundation pit dewatering method through drainage ditch construction with a water collection well pipe and gravel backfilling addresses the interference between underground and above-ground construction, optimizing the construction process and reducing costs and time.

CN119083471AInactive Publication Date: 2024-12-06CHINA MCC22 GROUP CORP LTD
View PDF 7 Cites 0 Cited by

Patent Information

Application Number
CN202411485081.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-23
Publication Date
2024-12-06
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

Existing drainage ditch construction methods in large public buildings interfere with above-ground construction, increasing costs and affecting the construction period due to the need for wider foundation pits and simultaneous work with groundwater management.

Method used

A foundation pit dewatering method involving a drainage ditch construction with a water collection well pipe, gravel backfill, and concrete pouring to minimize excavation width and facilitate scaffolding, utilizing a sandless cement filter well pipe and precise gravel layering to ensure efficient groundwater collection.

Benefits of technology

Saves construction time and cost, simplifies the construction process, and addresses the issue of tight scaffolding space, enhancing project efficiency and reducing mutual interference between underground and above-ground construction.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119083471A_ABST
    Figure CN119083471A_ABST
Patent Text Reader

Abstract

The invention relates to construction dewatering, in particular to a foundation pit dewatering construction method. Comprising the following steps: S1, constructing a collecting ditch at the bottom of a foundation trench; s2, a water collecting well pipe is installed, specifically, the well pipe is installed in the water collecting ditch, and the well pipe is installed to the designated depth; s3, backfilling the collecting gutter, namely backfilling the collecting gutter by adopting sand and gravel materials; s4, concrete is poured, specifically, concrete is poured on the tops of the collecting gutters; and S5, a scaffold is erected on the concrete. The construction period is shortened, and the working procedure distribution problem of a construction site can be solved to a great extent; the structure is simple, and the foundation pit excavation width is reduced; construction is convenient, construction period cost is saved, and project benefits are improved; the problem that the construction period is affected due to the fact that a scaffold erecting working face is tense due to the site is effectively solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to construction dewatering, in particular to a foundation pit dewatering construction method. Background Art

[0002] In large public buildings, due to the influence of groundwater level, a circular drainage ditch is usually set up around the main body of the underground structure, and a water collection well is arranged in the drainage ditch to lower the groundwater level to meet construction needs. Usually, the setting of the drainage ditch will affect the erection of external protective scaffolding during the construction of the underground structure, and it is necessary to increase the width of the foundation pit excavation. At the same time, in order to meet the requirements of the construction period, the construction of the above-ground structure needs to be carried out simultaneously with the precipitation. The existing drainage ditch construction method increases the construction cost, and crosses the construction with the above-ground main structure and affects each other. Summary of the invention

[0003] The present invention aims to solve the above technical problems, thereby providing a foundation pit dewatering construction method to solve the problem of cross-construction and mutual influence between continuous dewatering and the main structure on the ground in the limited space outside the underground structure.

[0004] The present invention solves the technical problem and adopts the following technical solution: A foundation pit dewatering construction method comprises the following steps: S1. Construction of drainage ditch at the bottom of foundation trench According to the outer dimensions of the underground structure, the width is set outward as the inner edge of the drainage ditch, and the drainage ditch is dug; S2. Installation of water collection well pipe Install the well pipe in the drainage ditch to the specified depth; S3. Backfilling of drainage ditch Backfill the drainage ditch with gravel; S4. Pouring concrete Concrete is poured on the top of the ditch; S5. Set up scaffolding on concrete.

[0005] Compared with the prior art, the present invention using the above technical solution has the following beneficial effects: 1) Save construction time and solve the process distribution problem of the construction site to a great extent; 2) Simple structure, reducing the width of foundation pit excavation; 3) Convenient construction, saving construction time and cost, thus improving project benefits; 4) Effectively solve the problem of tight scaffolding work surface caused by site reasons, thus affecting the construction period.

[0006] Further, the optimization scheme of the present invention is: In step 2, the bottom height of the well pipe is higher than the backfill height of the backfill gravel material.

[0007] In step 3, the depth inside and outside the well pipe is measured before backfilling, and the difference between the two is greater than the height of the water suction pump.

[0008] In step 3, the input amount of sand and gravel is greater than or equal to 95% of the calculated amount.

[0009] The thickness of the concrete is greater than 100 mm.

[0010] The well pipe is a sandless cement water filter well pipe. BRIEF DESCRIPTION OF THE DRAWINGS

[0011] Figure 1 A three-dimensional diagram of an embodiment of the present invention; Figure 2 It is a cross-sectional view of an embodiment of the present invention.

[0012] In the figure: basement outer wall 1; scaffolding 2; concrete 3; gravel 4; well pipe 5; foundation pit slope protection 6. DETAILED DESCRIPTION

[0013] The technical solutions in the embodiments of the present invention will be described clearly and completely below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all the embodiments.

[0014] In the description of the present invention, it is necessary to understand that the terms "upper", "lower", "front", "back", "left", "right", "top", "bottom", "inside", "outside", etc., indicating the orientation or position relationship are based on the orientation or position relationship shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present invention.

[0015] See also Figure 1 , Figure 2 This embodiment provides a foundation pit dewatering construction method, comprising the following steps: S1. Construction of drainage ditch at the bottom of foundation trench According to the outer dimensions of the underground structure, the inner edge of the drainage ditch is expanded 1 meter outward. After verifying that the outer edge dimensions are correct, a drainage ditch with a width of 1 meter and a depth of 1.2 meters is dug according to the laid-out position. The construction of the drainage ditch is completed.

[0016] S2. Installation of water collection well pipe Install the well pipe 5 in the water collection ditch. Use a 600mm diameter sandless cement filter well pipe. After the well pipe 5 arrives at the site, check whether the product meets the design requirements. After the well pipe 5 is hoisted to the specified depth using a lifting belt, the wellhead of the well pipe 5 is fixed in the center. The installation process of the well pipe 5 should be carried out continuously without stopping halfway. The bottom height of the well pipe 5 is higher than the backfill height of the backfill gravel material 4 to prevent mud and sand from flowing in and prevent the well pipe 5 from being blocked.

[0017] S3. Backfilling of drainage ditch The backfill material of the water collection ditch is 40-60mm gravel 4, which is backfilled and compacted in layers. Before backfilling, the depth inside and outside the well pipe 5 is measured. The difference between the two is greater than the height of the water suction pump to ensure the normal operation of the water pump. The height of the gravel 4 should be measured as it is backfilled. The backfilling process should be carried out continuously and should not be stopped midway until the gravel 4 is filled to the predetermined position. The final input amount of gravel 4 should not be less than 95% of the calculated amount.

[0018] S4. Pouring concrete After the backfill reaches the specified height and is compacted, 100mm thick C20 concrete is poured on the top layer to ensure that the erection of scaffolding 2 meets the design strength requirements.

[0019] S5. Set up scaffolding 2 on the concrete.

[0020] The present invention utilizes the water permeability of gravel and collects groundwater into a water collection well by calculating the water level difference. The gravel is backfilled and compacted in layers, and after compaction, the upper integral cast concrete is used to evenly transfer the force downward to bear the bearing capacity of the foundation to solve the on-site problem. The present invention saves construction time and can greatly solve the process distribution problem of the construction site. It has a simple structure, reduces the width of the foundation pit excavation, and is convenient for construction, thereby improving the project efficiency. The present invention meets the on-site operation requirements and is suitable for large public buildings with high water levels.

[0021] The above shows and describes the basic principles and main features of the present invention and the advantages of the present invention. It should be understood by those skilled in the art that the present invention is not limited by the above embodiments, and the above embodiments and descriptions are only for explaining the principles of the present invention. Without departing from the spirit and scope of the present invention, the present invention may have various changes and improvements, and these changes and improvements all fall within the scope of the present invention to be protected.

Claims

1. A foundation pit dewatering construction method, comprising the following steps: S1. Construction of drainage ditch at the bottom of foundation trench According to the outer dimensions of the underground structure, the width is set outward as the inner edge of the drainage ditch, and the drainage ditch is dug; S2. Installation of water collection well pipe Install the well pipe in the drainage ditch to the specified depth; S3. Backfilling of drainage ditch Backfill the drainage ditch with gravel; S4. Pouring concrete Concrete is poured on the top of the ditch; S5. Set up scaffolding on concrete.

2. The foundation pit dewatering construction method according to claim 1, characterized in that: In step 2, the bottom height of the well pipe is higher than the backfill height of the backfill gravel material.

3. The foundation pit dewatering construction method according to claim 1, characterized in that: In step 3, the depth inside and outside the well pipe is measured before backfilling, and the difference between the two is greater than the height of the water suction pump.

4. The foundation pit dewatering construction method according to claim 1, characterized in that: In step 3, the input amount of sand and gravel is greater than or equal to 95% of the calculated amount.

5. The foundation pit dewatering construction method according to claim 1, characterized in that: The thickness of the concrete is greater than 100 mm.

6. The foundation pit dewatering construction method according to claim 1, characterized in that: The well pipe is a sandless cement water filter well pipe.

Citation Information

Patent Citations

  • Method and device for dewatering and draining water collecting well of blind drain of deep foundation pit

    CN102116033A

  • Waterproof flow diversion seepage-proofing construction method under the condition that water seepage occurs at base plate guide wall position

    CN103938639A

  • Foundation pit blind ditch drainage construction structure and method

    CN110241835A

  • Foundation pit side wall water seepage position processing structure and construction method

    CN116335157A

  • Method for rapidly constructing water collecting pit in foundation pit of subway entrance and exit of water-rich sand layer

    CN116591205A