Method and device for analyzing and planning low-voltage problem of low-voltage distribution network
Through the technical means of combining GPS satellite timing and the Internet of Things, the precise location and line information of low-voltage distribution network users can be obtained, the analysis model is constructed, and the low voltage problem is identified and managed, which solves the problem of strong subjectivity of low voltage judgment in the existing technology. , improves the accuracy and efficiency of governance.
Patent Information
- Application Number
- CN202411232166.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-04
- Publication Date
- 2024-12-06
AI Technical Summary
In low-voltage distribution networks, the judgment and management of low-voltage problems lack scientific analysis and are easily affected by subjective factors, resulting in insufficient grid planning and design levels and ineffective improvement of user power consumption quality.
Use GPS satellite timing technology and Internet of Things communication to obtain user preliminary position information, combine Bluetooth phase setting device to obtain preliminary line phase sequence information, further obtain field line topology measurement structure and equipment positioning data, build user edge layout and topology diagrams, and accurately identify them. Low voltage users have formulated governance measures, including adjusting the three-phase imbalance of the line, replacing the wire diameter, handling leakage areas and building a new voltage regulator.
It realizes accurate identification and governance of low-voltage users, improves identification efficiency and accuracy, can solve low-voltage problems more targetedly, and improves user power quality.
Smart Images

Figure CN119089007A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of intelligent distribution network, and in particular to a method and device for analyzing and planning low voltage problems in a low voltage distribution network. Background Art
[0002] In the field of low-voltage distribution networks, with the continuous growth of power load, the low voltage problems of users in the substation area are gradually increasing, affecting the quality of power consumption of users. In order to improve the quality of power consumption of users, at present, planners and operation and maintenance personnel need to rely on experience to judge the low voltage problems of users in the substation area and formulate corresponding measures to improve user satisfaction. However, this method lacks scientific analysis and evaluation of low voltage problems, is easily affected by subjective factors, and cannot guarantee the level of power grid planning and design. Summary of the invention
[0003] The present invention provides a method and device for analyzing and planning low voltage problems in a low voltage distribution network, so as to timely discover low voltage users in the distribution network and quickly formulate treatment measures.
[0004] According to one aspect of the present invention, a method for analyzing and planning low voltage problems in a low voltage distribution network is provided, which includes:
[0005] Obtaining basic information of users in the area, including: obtaining preliminary location information of users in the area through GPS satellite timing technology combined with Internet of Things communication, and obtaining preliminary phase sequence information of user lines in the area through Bluetooth phase-fixing devices of the lines;
[0006] Acquire on-site information of users in the substation area, the on-site information of users is a further improvement of the basic information of the users, and the on-site information of users in the substation area includes: acquiring on-site line topology measurement structure, and obtaining connection relationship information of user lines in the substation area according to the on-site line topology measurement structure; acquiring on-site equipment positioning data, and combining the preliminary position information, determining the precise position information of users in the substation area; acquiring on-site line phase information, and combining the preliminary phase sequence information, determining the precise phase sequence information of user lines in the substation area; creating a navigation route for users in the substation area based on the precise position information and the connection relationship information;
[0007] Based on the basic information of the user and the on-site information of the user, draw a user layout map and a user topology map in the area, and build an analysis model;
[0008] According to the analysis model, the user layout of the substation area and the user topology map of the substation area, low-voltage users whose voltage in the substation area is lower than the normal power supply voltage are obtained, and treatment measures are formulated.
[0009] Optionally, the governance measures include at least one of the following measures:
[0010] Adjusting the three-phase imbalance of the line and marking the area where the three-phase imbalance of the line is adjusted;
[0011] For areas with insufficient flow on the line path, replace the wire with a larger wire diameter, and mark the area with insufficient flow and the wire diameter;
[0012] Process the leakage areas of lines and equipment and mark the leakage areas of the lines and equipment;
[0013] For areas where the three-phase imbalance of the line has been adjusted, where the line cannot be replaced with a larger wire diameter, and where the number of low-voltage users is less than or equal to the set number of users, a new voltage regulator is built and the location of the new voltage regulator is marked.
[0014] Optionally, before obtaining low-voltage users whose voltage in the area is lower than the normal power supply voltage according to the area user layout and the area user topology map and formulating treatment measures, the method further includes:
[0015] Get data information for establishing a new area.
[0016] Optionally, the governance measures include:
[0017] For areas where the three-phase imbalance of the line has been adjusted and cannot be replaced with a larger wire diameter and the number of low-voltage users is greater than the set number, a new substation is created and the location of the new substation is marked.
[0018] Optionally, after creating the new station area and marking the location of the new station area, the method further includes:
[0019] The newly built substation location and the line path information from the newly built substation location to the user's electricity consumption point are loaded in the substation user layout, the voltage drop from the newly built substation location to the user's electricity consumption point is calculated, and the voltage drop is marked in the substation user layout.
[0020] According to another aspect of the present invention, a device for analyzing and planning low voltage problems in a low voltage distribution network is provided, the device comprising:
[0021] The user basic information acquisition module is used to obtain the basic information of users in the area, specifically including: obtaining the preliminary location information of users in the area through GPS satellite timing technology combined with Internet of Things communication, and obtaining the preliminary phase sequence information of user lines in the area through the Bluetooth phase-fixing device of the line;
[0022] The user on-site information acquisition module is used to acquire the on-site information of users in the substation area. The user on-site information is a further improvement of the basic information of the user. The acquisition of the on-site information of users in the substation area includes: acquiring the on-site line topology measurement structure, and obtaining the connection relationship information of the user lines in the substation area according to the on-site line topology measurement structure; acquiring the on-site equipment positioning data, and combining the preliminary location information, determining the precise location information of the users in the substation area; acquiring the on-site line phase information, and combining the preliminary phase sequence information, determining the precise phase sequence information of the user lines in the substation area; creating a navigation route for users in the substation area based on the precise location information and the connection relationship information;
[0023] An analysis model building module, used to draw a user layout map and a user topology map in the area based on the basic information of the user and the on-site information of the user, and to build an analysis model;
[0024] The analysis and measures formulation module is used to obtain low-voltage users in the substation whose voltage is lower than the normal power supply voltage based on the analysis model, the user layout of the substation area and the user topology map of the substation area, and formulate treatment measures.
[0025] The technical solution of the embodiment of the present invention uses GPS satellite timing technology combined with Internet of Things communication to obtain the preliminary location information of users in the substation area, and obtains the preliminary phase sequence information of the user lines in the substation area through the Bluetooth phasing device of the line; then obtains the user's on-site information; draws the substation user layout and the substation user topology map based on the preliminary location information, preliminary phase sequence information and user on-site information, and then constructs an analysis model to obtain low-voltage users in the substation area whose voltage is lower than the normal power supply voltage, and formulates governance measures. Compared with the traditional identification of low-voltage users relying on manual experience, the technical solution of the embodiment of the present invention adopts GPS positioning, Internet of Things communication, line Bluetooth phasing and other technical means to achieve more accurate and automated acquisition and analysis of substation user information, improve the efficiency and accuracy of identifying low-voltage users, and thus can solve the power supply problem of low-voltage users in a more targeted manner.
[0026] It should be understood that the contents described in this section are not intended to identify the key or important features of the embodiments of the present invention, nor are they intended to limit the scope of the present invention. Other features of the present invention will become easily understood through the following description. BRIEF DESCRIPTION OF THE DRAWINGS
[0027] In order to more clearly illustrate the technical solutions in the embodiments of the present invention, the following briefly introduces the drawings required for use in the description of the embodiments. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.
[0028] Figure 1 It is a flow chart of a method for analyzing and planning low voltage problems in a low voltage distribution network provided by an embodiment of the present invention;
[0029] Figure 2 It is a schematic diagram of a user layout provided by an embodiment of the present invention;
[0030] Figure 3 It is a partial structural schematic diagram of a user topology diagram provided by an embodiment of the present invention;
[0031] Figure 4 is a flow chart of another method for analyzing and planning low voltage problems in a low voltage distribution network provided by an embodiment of the present invention;
[0032] Figure 5 is a flow chart of another method for analyzing and planning low voltage problems in a low voltage distribution network provided by an embodiment of the present invention;
[0033] Figure 6 is a schematic diagram of the connection relationship of a low voltage monitoring device provided by an embodiment of the present invention;
[0034] Figure 7 is a flow chart of another method for analyzing and planning low voltage problems in a low voltage distribution network provided by an embodiment of the present invention;
[0035] Figure 8 is a flow chart of another method for analyzing and planning low voltage problems in a low voltage distribution network provided by an embodiment of the present invention;
[0036] Fig. 9 It is a schematic diagram of a device for analyzing and planning low voltage problems in a low voltage distribution network provided by an embodiment of the present invention. DETAILED DESCRIPTION
[0037] In order to enable those skilled in the art to better understand the scheme of the present invention, the technical scheme in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work should fall within the scope of protection of the present invention.
[0038] It should be noted that the terms "first", "second", etc. in the specification and claims of the present invention and the above-mentioned drawings are used to distinguish similar objects, and are not necessarily used to describe a specific order or sequence. It should be understood that the data used in this way can be interchanged where appropriate, so that the embodiments of the present invention described herein can be implemented in an order other than those illustrated or described herein. In addition, the terms "including" and "having" and any variations thereof are intended to cover non-exclusive inclusions, for example, a process, method, system, product or device that includes a series of steps or units is not necessarily limited to those steps or units that are clearly listed, but may include other steps or units that are not clearly listed or inherent to these processes, methods, products or devices.
[0039] Figure 1 This is a flow chart of a method for analyzing and planning low voltage problems in a low voltage distribution network provided by an embodiment of the present invention. The embodiment of the present invention is applicable to the case where the voltage at the user of the low voltage distribution network is lower than the normal power supply voltage. The method can be executed by an analysis and planning device for low voltage problems in a low voltage distribution network. The analysis and planning device can be implemented in the form of hardware and / or software, and the analysis and planning device can be configured in a computing device. Figure 1 As shown, the method includes:
[0040] S110, obtaining basic information of users in the substation area, specifically including: obtaining preliminary location information of users in the substation area through GPS satellite timing technology combined with Internet of Things communication, and obtaining preliminary phase sequence information of user lines in the substation area through Bluetooth phasing devices of the lines.
[0041] In the embodiment of the present invention, the substation area can be interpreted as an area powered by one substation, which usually includes multiple users.
[0042] GPS satellite timing technology is a technology that uses GPS satellite signals for time synchronization, which mainly includes multiple GPS satellites and GPS receivers; GPS satellites continuously transmit signals containing precise time information, and GPS receivers receive these signals and calculate the signal propagation time to obtain precise time information.
[0043] IoT communication can be explained as the technology of connecting various devices through the network to achieve information exchange and data sharing; the network connecting the IoT can be various types of networks, for example, cellular networks, Wi-Fi networks, low-power wide area networks and satellite networks.
[0044] The preliminary location information may be interpreted as the location information of the user in the station area. For example, the preliminary location information may be location information such as the street, community, or building where the user is located.
[0045] The Bluetooth phase-determining device can be interpreted as a device that uses Bluetooth communication technology to monitor and analyze the specific conditions of the three-phase line losses of each branch unit and determine the phase sequence of the power system; it usually includes a Bluetooth communication module, a power parameter acquisition module, a phase sequence calculation module and a data processing module.
[0046] Among them, GPS satellite timing technology, Internet of Things communication function, and Bluetooth phasing device are all part of the substation line loss management device. The substation line loss management device identifies the phase sequence of users in the substation, implements and manages the quantification of substation line losses, and combines power information technology and data analysis methods to provide the functions of monitoring, analyzing and managing substation line losses, user power consumption, voltage, and current.
[0047] The preliminary phase sequence information can be interpreted as the phase sequence relationship of the line obtained by performing a preliminary judgment on the phase sequence of the line using a Bluetooth phase determination device.
[0048] Exemplarily, the steps for obtaining basic information of users in the substation in the embodiment of the present invention are: receiving signals from multiple GPS satellites through a GPS receiver and calculating the propagation time of the signals to obtain accurate time information, and then uploading the time information to the cloud platform through the Internet of Things communication, and then calculating the preliminary location information of the street, community, building, etc. where the user is located. Connecting with sensors or other devices on the power line through the Bluetooth communication module, collecting power parameter data such as voltage and current of the line, and then transmitting the collected data to the phase sequence calculation module for calculation, and sending the calculation results to the host computer or other devices through the Bluetooth communication module to determine the preliminary phase sequence of the user lines in the substation.
[0049] S120. Obtaining on-site information of users in the substation area. The on-site information of users is a further improvement of the basic information of users. Obtaining on-site information of users in the substation area includes: obtaining the on-site line topology measurement structure, and obtaining the connection relationship information of the user lines in the substation area according to the on-site line topology measurement structure; obtaining on-site equipment positioning data, and combining it with the preliminary location information, determining the precise location information of users in the substation area; obtaining on-site line phase verification information, and combining it with the preliminary phase sequence information, determining the precise phase sequence information of the user lines in the substation area; and creating a navigation route for users in the substation area based on the precise location information and the connection relationship information.
[0050] In an embodiment of the present invention, the field line topology measurement structure can be interpreted as the connection relationship between various lines in the power system obtained by measuring in the actual substation area. The field equipment positioning data can be interpreted as the data for positioning the user equipment in the actual substation area and recording its location information. The connection relationship information is the connection relationship between the user's meter and the transformer and the line in the substation area, and the connection relationship between the user's meter and the meter of other users. The precise location information refers to the specific positioning information of the user that is more accurate than the preliminary location information, which can effectively avoid the positioning error caused by the environmental influence of the GPS satellite positioning technology; for example, the precise location information can be accurate to the specific line information where the user's meter is located. The field line phase information refers to the data for measuring and recording the phase of the line in the power system to determine the phase relationship between the phases of the line. The precise phase sequence information is the phase sequence information that is more accurate than the preliminary phase sequence information, which can effectively avoid the error caused by the Bluetooth phasing device due to signal interference, distance limitation and environmental influence. The navigation route can be interpreted as a route planned from the user's meter to the transformer or other target location based on the user's precise location information and the connection relationship between the user's meter and the transformer and the line.
[0051] Exemplarily, in the embodiment of the present invention, the on-site information of users in the substation area is obtained by using a total station, theodolite and other measuring equipment to measure the lines in the substation area to obtain information such as the direction, branches, and connection points of the lines; or using a drone or other aerial platform to take aerial photos of the substation area, and combining image processing technology to identify information such as the direction, branches, and connection points of the lines. This information can be input into the analysis and planning device for low voltage problems in the low-voltage distribution network through an input device.
[0052] Use measuring equipment to measure the distance, angle and other information between the user's electricity meter and the reference point, and match it with the preliminary phase sequence information to determine the line, branch, connection method, etc. where the user's electricity meter is located, and obtain the user's precise location information.
[0053] More accurate line phase sequence information is obtained through the phase checker, and compared and verified with the preliminary phase sequence information obtained previously to confirm whether the preliminary phase sequence information is accurate, and finally obtain the precise phase sequence information of the user line.
[0054] Use precise location information and connection relationship information to create user navigation routes within the station area, ensuring that the navigation routes can provide clear route guidance.
[0055] S130. Based on the basic information of the users and the on-site information of the users, a user layout map of the substation area and a user topology map of the substation area are drawn to construct an analysis model.
[0056] In the embodiment of the present invention, the user layout can be interpreted as the specific location and connection mode of the user's electric meter in the station area, as well as the connection relationship between the user's electric meter and the transformer and line. Figure 2 It is a schematic diagram of a user layout provided by an embodiment of the present invention. Figure 2 In the diagram, thick black lines represent low-voltage equipment and line distribution, and thick white lines connected to thick black lines represent medium-voltage equipment and line distribution. The user topology diagram can be interpreted as a graphical display of the connection relationship between the user's meter and the transformer, line, and the connection relationship between the user's meter and the meter of other users in the substation area. Figure 3 FIG. 1 is a schematic diagram of a partial structure of a user topology diagram provided by an embodiment of the present invention. Figure 3 As shown in the figure, the user layout focuses on the connection relationship and location information of a single user, usually displayed in the form of a schematic diagram; the user topology diagram focuses on the connection relationship information of users and devices in the entire area, among which, the user layout focuses on the connection relationship and location information of a single user, usually displayed in the form of a schematic diagram; the user topology diagram focuses on the connection relationship information of users in the entire area, which is convenient and intuitive to grasp the connection status of users in the entire area. The analysis model can be interpreted as an abstract structure or framework, which is used to analyze the characteristics of user lines in the area and obtain low-voltage users in the area whose voltage is lower than the normal power supply.
[0057] By converting basic user information and user on-site information into a graphic model and building an analysis model based on the graphic model, the connection information of user lines in the substation area can be obtained more intuitively and a more in-depth analysis can be performed.
[0058] S140. According to the analysis model, the user layout map and the user topology map of the substation area, low-voltage users in the substation area whose voltage is lower than the normal power supply voltage are obtained, and treatment measures are formulated.
[0059] In an embodiment of the present invention, low-voltage users can be interpreted as users whose actual received voltage is lower than the low-voltage standard. The main reasons for this include line loss, excessive load and equipment failure, which will affect the normal operation of electrical equipment and reduce power supply reliability.
[0060] The analysis model, user layout map and user topology map provide detailed information about the user route connections, power consumption and voltage levels within the substation. This information is used to analyze and judge the voltage conditions of users in the substation. Based on the analysis results, different control measures are formulated for low voltage problems caused by different reasons.
[0061] The technical solution of the embodiment of the present invention uses GPS satellite timing technology combined with Internet of Things communication to obtain the preliminary location information of users in the substation area, and obtains the preliminary phase sequence information of the user lines in the substation area through the Bluetooth phasing device of the line; then obtains the user's on-site information; draws the substation user layout and the substation user topology map based on the preliminary location information, preliminary phase sequence information and user on-site information, and then constructs an analysis model to obtain low-voltage users in the substation area whose voltage is lower than the normal power supply voltage, and formulates governance measures. Compared with the traditional identification of low-voltage users relying on manual experience, the technical solution of the embodiment of the present invention adopts GPS positioning, Internet of Things communication, line Bluetooth phasing and other technical means to achieve more accurate and automated acquisition and analysis of substation user information, improve the efficiency and accuracy of identifying low-voltage users, and thus can solve the power supply problem of low-voltage users in a more targeted manner.
[0062] Figure 4 is a flow chart of another method for analyzing and planning low voltage problems in a low voltage distribution network provided by an embodiment of the present invention. Based on the above embodiment, optionally, as Figure 4 As shown, governance measures include:
[0063] S190. According to the analysis model, the user layout diagram of the substation area and the user topology diagram of the substation area, low-voltage users whose voltage in the substation area is lower than the normal power supply voltage are obtained.
[0064] S150, adjusting the three-phase imbalance of the line, and marking the area where the three-phase imbalance of the line is adjusted.
[0065] In the embodiment of the present invention, the three-phase imbalance can be interpreted as the degree of deviation of the three-phase current or voltage, which is expressed by the difference between the maximum value and the minimum value of the three-phase current or voltage divided by the average value of the three-phase current or voltage. The line three-phase imbalance area refers to the area in the line where the three-phase imbalance exceeds the set threshold.
[0066] When the three phases of the line are unbalanced, the current will tend to flow through the phase line with smaller impedance, resulting in uneven current distribution between the phase lines, causing an increase in the current flowing through the neutral line, which in turn causes an increase in line losses and a decrease in the voltage reaching the user end. Therefore, adjusting the three-phase imbalance can reduce line losses, thereby increasing the voltage level and improving the low voltage problem at the user end.
[0067] S160. For areas on the line path where the flow is insufficient, replace the wire with a larger wire diameter and mark the area with insufficient flow and the wire diameter model.
[0068] In the embodiment of the present invention, the through-current can be interpreted as the ability of current to pass through a wire or line, also known as the current carrying capacity. Insufficient through-current can be interpreted as the cross-sectional area of the wire or line is insufficient to carry the current, which will cause the line voltage to decrease.
[0069] Replacing the wire with a larger diameter will reduce the resistance of the line, reduce the loss when current flows through the wire, and thus reduce the voltage drop and improve the low voltage problem at the user's site.
[0070] The wire diameter selection criteria are shown in Table 1-2.
[0071] Table 1 Design standards for power distribution lines in power infrastructure projects
[0072]
[0073] Table 2 Low voltage line safe operation current table
[0074]
[0075]
[0076] Among them, BLVV is a round wire with aluminum conductor as the material, and its outer layer is wrapped with a layer of insulating material. This is an aluminum core PVC insulated sheath round wire. The second letter L in BLVV indicates that the wire is aluminum wire; the V in the model number indicates that the outer insulating layer is made of polyvinyl chloride, which can prevent the conductor from contacting the outside world and causing leakage and electric shock.
[0077] S170. Process the leakage areas of the lines and equipment, and mark the leakage areas of the lines and equipment.
[0078] In the embodiment of the present invention, the leakage area can be interpreted as an area where insulation defects exist in a line or device, causing current to leak to the ground or other conductors.
[0079] Treating the leakage area can reduce the leakage current, thereby reducing line losses, reducing voltage drops, and improving low voltage problems at the user's site.
[0080] S180. For areas where the three-phase imbalance of the line has been adjusted and cannot be replaced with a larger wire diameter, and the number of low-voltage users is less than or equal to the set number of users, a new voltage regulator is built and the location of the new voltage regulator is marked.
[0081] In the embodiment of the present invention, the set number can be interpreted as a pre-set threshold value, which is used to determine whether the number of low-voltage users reaches the standard that requires a new voltage regulator; for example, the set number can be 3 households, 4 households and 5 households. The voltage regulator is an autotransformer, and its working principle is: the input voltage remains unchanged, and then a part of the voltage is taken from the input coil as the output. When the number of turns of this coil changes due to the movement of the sliding arm on the input coil, the output voltage also changes accordingly, thereby achieving the purpose of adjusting the output voltage.
[0082] The newly built voltage regulator can directly increase the line voltage at low-voltage users to the normal power supply voltage level, avoid large-scale transformation of the entire line, and reduce management costs.
[0083] Figure 5 is a flow chart of another method for analyzing and planning low voltage problems in a low voltage distribution network provided by an embodiment of the present invention. Based on the above embodiments, optionally, as Figure 5 As shown, the method comprises the following steps:
[0084] S210, obtaining basic information of users in the substation area, specifically including: obtaining preliminary location information of users in the substation area through GPS satellite timing technology combined with Internet of Things communication, and obtaining preliminary phase sequence information of user lines in the substation area through the Bluetooth phase-fixing device of the line.
[0085] S220. Obtaining on-site information of users in the substation area. The on-site information of users is a further improvement of the basic information of users. Obtaining on-site information of users in the substation area includes: obtaining the on-site line topology measurement structure, and obtaining the connection relationship information of the user lines in the substation area according to the on-site line topology measurement structure; obtaining on-site equipment positioning data, and combining it with the preliminary location information, determining the precise location information of users in the substation area; obtaining on-site line phase verification information, and combining it with the preliminary phase sequence information, determining the precise phase sequence information of the user lines in the substation area; and creating a navigation route for users in the substation area based on the precise location information and the connection relationship information.
[0086] S230. Based on the basic information of the users and the on-site information of the users, a user layout map of the substation area and a user topology map of the substation area are drawn to construct an analysis model.
[0087] S240, obtaining data information for establishing a new area.
[0088] In the embodiment of the present invention, the data information may be information such as the number of users, power load and voltage level in the new substation area, or information such as the cost budget and construction information of building the new substation area.
[0089] Based on the collected data and information, the feasibility of establishing a new area is evaluated to provide a basis for the next decision.
[0090] Optionally, data information for establishing a new substation is obtained, including: locating medium-voltage equipment and lines around the substation, and loading the positioning data into a user layout map of the substation.
[0091] In an embodiment of the present invention, medium-voltage equipment and lines can be interpreted as power equipment and lines with voltage levels between 10kV and 35kV; establishing a new substation requires connection to the existing medium-voltage power grid, and it is necessary to determine the best way to connect the new substation based on information such as the location, capacity and operating status of the medium-voltage equipment and lines around the substation, as well as to evaluate whether connecting the new substation will affect the power supply reliability of the existing power grid.
[0092] Figure 6 Schematic diagram of the connection relationship of a low voltage monitoring device provided by an embodiment of the present invention. Figure 6 As shown, for example, the voltage of the medium-voltage power line is 10kV, and the transformer directly connected to the 10kV power line belongs to the medium-voltage power equipment. The transformer converts the medium voltage into a 400V low voltage for users, and is connected to the 400V low-voltage line through the incoming switch. The low-voltage line contains several branches, and each branch is connected to multiple users through the outgoing switch. In addition, each branch is equipped with a low-voltage loop measurement and control terminal, which is responsible for real-time monitoring of the operation of the branch and transmitting the monitored data to the intelligent gateway through a broadband power carrier; the status signals of the incoming switch and the outgoing switch are transmitted to the intelligent gateway through the RS485 serial communication interface; the intelligent gateway is configured with the SOOC protocol for data exchange and control command transmission with the terminal device; the intelligent gateway transmits the signal to the upper-level global Internet of Things platform / energy interconnection sharing platform through 4G or optical fiber.
[0093] For example, drone RTK equipment or GPS positioning equipment is used to mark the location information of medium-voltage equipment and lines in the form of icons on the user layout of the substation area, and different colors or symbols are used to distinguish between medium-voltage equipment and lines.
[0094] Optionally, data information for establishing a new substation is obtained, including: establishing a substation user voltage measurement table based on standardized substation construction and parameter configuration.
[0095] In an embodiment of the present invention, standardized substation construction and parameter configuration can be interpreted as formulating unified standards and specifications in the construction of substations in the low-voltage distribution network, and designing, constructing and configuring parameters of the substations according to these standards and specifications; illustratively, standardized substation construction and parameter configuration can include: infrastructure project construction standards, low-voltage line safe operating current, low-voltage line reactance parameters and low-voltage line resistance parameters; by formulating unified standards and specifications, the efficiency of substation construction can be improved and the quality and safety of substation construction can be guaranteed. Substation user voltage calculation table can be interpreted as a table used to calculate and evaluate the voltage level of users in the substation; illustratively, the substation user voltage calculation table can include: user account number, line length, line diameter, line resistance and other parameters.
[0096] By establishing a voltage calculation table for users in the substation, we can calculate the voltage level of each user after the new substation is built based on standardized substation construction and parameter configuration, combined with actual user power load, line length and other information, providing a basis for the next decision.
[0097] S250. According to the analysis model, the user layout map and the user topology map of the substation area, low-voltage users whose voltage in the substation area is lower than the normal power supply voltage are obtained, and treatment measures are formulated.
[0098] The embodiment of the present invention obtains data information for establishing a new area through S240, provides data support for the subsequent establishment of the new area, ensures that the construction of the new area complies with the specifications, and improves the quality and safety of the construction.
[0099] Figure 7 is a flow chart of another method for analyzing and planning low voltage problems in a low voltage distribution network provided by an embodiment of the present invention. Based on the above embodiments, optionally, as Figure 7 As shown, governance measures include:
[0100] S260. For areas where the three-phase imbalance of the line has been adjusted and cannot be replaced with a larger wire diameter, and the number of low-voltage users is greater than the set number, a new substation is created and the location of the new substation is marked.
[0101] In the embodiment of the present invention, building a new substation can be interpreted as building a new distribution transformer and distribution line to solve the low voltage problem at the low voltage users in the substation.
[0102] Adjusting the three-phase imbalance of the line usually only requires adjusting the line connection method or replacing some line components; replacing with a larger wire diameter only requires replacing some lines, and no new transformers and distribution lines need to be built; building a new voltage regulator, which is small in size and simple to install, and does not require the construction of new transformers and distribution lines. The above three measures have low costs and short construction periods, and can solve the problem of low user voltage caused by unbalanced line load, excessive line resistance and circuit fluctuations; however, if the power load of users in the substation is too large and the existing substation cannot meet the power demand of users, the above three measures cannot increase the capacity of the line, and measures to build a new substation are needed to solve the low voltage problem at the users in the substation.
[0103] Building a new substation means adding a transformer, which directly increases the power supply capacity; and the location of the new substation will be closer to low-voltage users, shortening the distance between users and the transformer, thereby reducing voltage losses on the line. Therefore, building a new substation can improve low voltage problems at users.
[0104] The reference standards for selecting new transformers are shown in Table 3.
[0105] Table 3 Transformer selection criteria
[0106] Voltage level Rated capacity of distribution transformer (kVA) 10(20) kV 50、100、200、315、400、500、630、800、1250
[0107] Figure 8 is a flow chart of another method for analyzing and planning low voltage problems in a low voltage distribution network provided by an embodiment of the present invention. Based on the above embodiments, optionally, as Figure 8 As shown, after creating a new area and marking the location of the new area, it also includes:
[0108] S270, loading the newly built substation location and the line path information from the newly built substation location to the user's power consumption point in the substation user layout, calculating the voltage drop from the newly built substation location to the user's power consumption point, and marking the voltage drop in the substation user layout.
[0109] In the embodiment of the present invention, the voltage drop can be interpreted as the difference in voltage drop from the newly built substation to each user, that is, the voltage loss. By calculating the voltage drop, the voltage level of each user after the new substation is built can be understood, and it is evaluated whether the new substation can effectively improve the user voltage, and a basis is provided for subsequent optimization design.
[0110] The reference standard for line voltage drop from the location of a new substation to the user's power consumption point is shown in Table 4-13.
[0111] Table 4 Single 240mm 2 Voltage drop of aluminum core overhead line (power factor 0.85, ambient temperature 30℃)
[0112]
[0113] Table 5 Single 185mm 2 Voltage drop of aluminum core overhead line (power factor 0.85, ambient temperature 30℃)
[0114]
[0115]
[0116] Table 6 Single 150mm 2 Voltage drop of aluminum core overhead line (power factor 0.85, ambient temperature 30℃)
[0117]
[0118] Table 7 Single 120mm 2 Voltage drop of aluminum core overhead line (power factor 0.85, ambient temperature 30℃)
[0119]
[0120]
[0121] Table 8 Single 95mm 2 Voltage drop of aluminum core overhead line (power factor 0.85, ambient temperature 30℃)
[0122]
[0123] Table 9 Single 70mm 2 Voltage drop of aluminum core overhead line (power factor 0.85, ambient temperature 30℃)
[0124]
[0125] Table 10 Voltage drop of a single 50mm2 aluminum core overhead line (power factor 0.85, ambient temperature 30°C)
[0126]
[0127]
[0128] Table 11 Voltage drop of a single 35mm2 aluminum core overhead line (power factor 0.85, ambient temperature 30℃)
[0129]
[0130] Table 12 Voltage drop of a single 25mm2 aluminum core overhead line (power factor 0.85, ambient temperature 30°C)
[0131]
[0132]
[0133] Table 13 Single 16mm 2 Voltage drop of aluminum core overhead line (power factor 0.85, ambient temperature 30℃)
[0134]
[0135] Fig. 9 Schematic diagram of a low voltage distribution network low voltage problem analysis and planning device provided by an embodiment of the present invention. Fig. 9 As shown, the device comprises:
[0136] The user basic information acquisition module 310 is used to obtain the basic information of users in the area, specifically including: obtaining the preliminary location information of users in the area through GPS satellite timing technology combined with Internet of Things communication, and obtaining the preliminary phase sequence information of user lines in the area through the Bluetooth phase determination device of the line
[0137] The user on-site information acquisition module 320 is used to obtain the on-site information of users in the substation area. The user on-site information is a further improvement of the basic information of the user. The acquisition of the on-site information of users in the substation area includes: obtaining the on-site line topology measurement structure, and obtaining the connection relationship information of the user lines in the substation area according to the on-site line topology measurement structure; obtaining the on-site equipment positioning data, and combining it with the preliminary location information, determining the precise location information of the users in the substation area; obtaining the on-site line phase information, and combining it with the preliminary phase sequence information, determining the precise phase sequence information of the user lines in the substation area; creating a navigation route for users in the substation area based on the precise location information and connection relationship information
[0138] The analysis model building module 330 is used to draw a user layout map and a user topology map in the area based on the basic information of the user and the user's on-site information, and build an analysis model;
[0139] The analysis and measures formulation module 340 is used to obtain low-voltage users in the substation whose voltage is lower than the normal power supply voltage based on the analysis model, the substation user layout and the substation user topology map, and formulate treatment measures.
[0140] The low-voltage distribution network low-voltage problem analysis and planning device provided in the embodiment of the present invention can execute the low-voltage distribution network low-voltage problem analysis and planning method provided in any embodiment of the present invention, and has the corresponding functional modules and beneficial effects of the execution method.
[0141] It should be understood that the various forms of processes shown above can be used to reorder, add or delete steps. For example, the steps described in the present invention can be executed in parallel, sequentially or in different orders, as long as the desired results of the technical solution of the present invention can be achieved, and this document does not limit this.
[0142] The above specific implementations do not constitute a limitation on the protection scope of the present invention. It should be understood by those skilled in the art that various modifications, combinations, sub-combinations and substitutions can be made according to design requirements and other factors. Any modification, equivalent substitution and improvement made within the spirit and principle of the present invention should be included in the protection scope of the present invention.
Claims
1. A method for analyzing and planning low voltage problems in a low voltage distribution network, characterized in that: include: Obtaining basic information of users in the area, including: obtaining preliminary location information of users in the area through GPS satellite timing technology combined with Internet of Things communication, and obtaining preliminary phase sequence information of user lines in the area through Bluetooth phase-fixing devices of the lines; Acquire on-site information of users in the substation area, the on-site information of users is a further improvement of the basic information of the users, and the on-site information of users in the substation area includes: acquiring on-site line topology measurement structure, and obtaining connection relationship information of user lines in the substation area according to the on-site line topology measurement structure; acquiring on-site equipment positioning data, and combining the preliminary position information, determining the precise position information of users in the substation area; acquiring on-site line phase information, and combining the preliminary phase sequence information, determining the precise phase sequence information of user lines in the substation area; creating a navigation route for users in the substation area based on the precise position information and the connection relationship information; Based on the basic information of the user and the on-site information of the user, draw a user layout map and a user topology map in the area, and build an analysis model; According to the analysis model, the user layout of the substation area and the user topology map of the substation area, low-voltage users whose voltage in the substation area is lower than the normal power supply voltage are obtained, and treatment measures are formulated.
2. The method for analyzing and planning low voltage problems in a low voltage distribution network according to claim 1, characterized in that: The governance measures include at least one of the following measures: Adjusting the three-phase imbalance of the line and marking the area where the three-phase imbalance of the line is adjusted; For areas with insufficient flow on the line path, replace the wire with a larger wire diameter, and mark the area with insufficient flow and the wire diameter; Process the leakage areas of lines and equipment and mark the leakage areas of the lines and equipment; For areas where the three-phase imbalance of the line has been adjusted, where the line diameter cannot be replaced with a larger one, and where the number of low-voltage users is less than or equal to the set number of users, a new voltage regulator is built and the location of the new voltage regulator is marked.
3. The method for analyzing and planning low voltage problems in a low voltage distribution network according to claim 1, characterized in that: Before obtaining low-voltage users whose voltage is lower than the normal power supply voltage in the substation area according to the substation area user layout and the substation area user topology map and formulating treatment measures, the method further includes: Obtain data information for establishing a new area.
4. The method for analyzing and planning low voltage problems in a low voltage distribution network according to claim 3, characterized in that: The step of obtaining data information for establishing a new zone includes: The medium voltage equipment and lines around the substation area are located, and the location data is loaded into the user layout map of the substation area.
5. The method for analyzing and planning low voltage problems in a low voltage distribution network according to claim 3, characterized in that: The step of obtaining data information for establishing a new zone includes: According to the standardized substation construction and parameter configuration, establish the substation user voltage calculation table.
6. The method for analyzing and planning low voltage problems in a low voltage distribution network according to any one of claims 3 to 5, characterized in that: The governance measures include: For areas where the three-phase imbalance of the line has been adjusted and cannot be replaced with a larger wire diameter and the number of low-voltage users is greater than the set number, a new substation is created and the location of the new substation is marked.
7. The method for analyzing and planning low voltage problems in a low voltage distribution network according to claim 6, characterized in that: After creating the new station area and marking the location of the new station area, the method further includes: The newly built substation location and the line path information from the newly built substation location to the user's electricity consumption point are loaded in the substation user layout, the voltage drop from the newly built substation location to the user's electricity consumption point is calculated, and the voltage drop is marked in the substation user layout.
8. The method for analyzing and planning low voltage problems in a low voltage distribution network according to claim 1, characterized in that: The information of the user layout in the station area includes: At least one of the location information of users in the substation area, the location information of low-voltage users in the substation area, the location information of medium-voltage equipment around the substation area, and the location information of medium-voltage lines around the substation area.
9. The method for analyzing and planning low voltage problems in a low voltage distribution network according to claim 1, characterized in that: The information of the user layout in the station area includes: At least one of line connection relationship, line branching condition, line phase sequence, line current condition, line voltage value and line current value.
10. A device for analyzing and planning low voltage problems in a low voltage distribution network, characterized in that: include: The user basic information acquisition module is used to obtain the basic information of users in the area, specifically including: obtaining the preliminary location information of users in the area through GPS satellite timing technology combined with Internet of Things communication, and obtaining the preliminary phase sequence information of user lines in the area through the Bluetooth phase-fixing device of the line; The user on-site information acquisition module is used to acquire the on-site information of users in the substation area. The user on-site information is a further improvement of the basic information of the user. The acquisition of the on-site information of users in the substation area includes: acquiring the on-site line topology measurement structure, and obtaining the connection relationship information of the user lines in the substation area according to the on-site line topology measurement structure; acquiring the on-site equipment positioning data, and combining the preliminary location information, determining the precise location information of the users in the substation area; acquiring the on-site line phase information, and combining the preliminary phase sequence information, determining the precise phase sequence information of the user lines in the substation area; creating a navigation route for users in the substation area based on the precise location information and the connection relationship information; An analysis model building module, used to draw a user layout map and a user topology map in the area based on the basic information of the user and the on-site information of the user, and to build an analysis model; The analysis and measures formulation module is used to obtain low-voltage users in the substation whose voltage is lower than the normal power supply voltage based on the analysis model, the user layout of the substation area and the user topology map of the substation area, and formulate treatment measures.