Power distribution network optimization planning method, system and equipment based on multi-objective cooperation and medium
Through the multi-objective collaborative optimization planning method and NSGA-II algorithm, the shortcomings of multi-element collaborative optimization in the distribution network are solved, and the comprehensive evaluation of economy, low carbonity and reliability is achieved, and an optimized distribution network planning scheme is provided. .
Patent Information
- Application Number
- CN202410957402.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-17
- Publication Date
- 2024-12-06
AI Technical Summary
The existing technology lacks a coordinated optimization planning method for distribution networks covering multiple elements such as hydropower, photovoltaics, charging piles, and energy storage, and fails to fully consider factors such as economic costs, low carbonity and grid stability.
Using a distribution network optimization planning method based on multi-objective collaboration, the overall objective function is solved through the NSGA-II algorithm, including economic cost, charging distance and carbon emissions, and a scenario model is established and optimized planning is carried out, considering economic, low-carbon and reliability.
The optimal planning scheme of the distribution network in different scenarios has been achieved, and the economic, low-carbon, social and reliability of the system has been comprehensively evaluated, which has reduced decision-making variables and improved the economic and low-carbon operation capabilities of the distribution network.
Smart Images

Figure CN119090165A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of distribution network optimization planning, and more specifically, to a distribution network optimization planning method, system, equipment and medium based on multi-objective collaboration. Background Art
[0002] With the construction of new power systems and the rapid development of the electric vehicle industry, a large number of distributed photovoltaic and charging loads will be connected to the distribution network in the future, which will have a significant impact on the source-load characteristics and reliable operation of the distribution network. The distribution network in hydropower-rich areas often has multiple local small hydropower sources, which have a certain potential for flexible adjustment; on the other hand, as the cost of new energy storage gradually decreases, it will usher in its large-scale application on the distribution network side. Giving full play to the flexible adjustment capabilities of small hydropower and new energy storage, coping with the random fluctuation characteristics of distributed photovoltaic and charging loads, and building an integrated "water-light-charging-storage" system has become one of the typical forms of the new distribution network. The "water-light-charging-storage" system can not only improve the clean energy absorption capacity and user power guarantee capacity, but also reduce peak load demand, thereby reducing the investment cost of distribution network planning. Obviously, the installation location and capacity selection of photovoltaic, energy storage and charging stations have an important impact on the economic and low-carbon operation of the distribution network; therefore, it is necessary to reasonably plan the distribution network with coordinated operation of hydropower, light and storage.
[0003] At present, many scholars at home and abroad have conducted relevant research on distribution network systems including hydropower, photovoltaics, charging piles, and energy storage. Some take system economics as the objective function to optimize the capacity of photovoltaics and energy storage. Some take the comprehensive cost minimization and distribution network operator profit maximization as the comprehensive optimality as the economic goal, and optimize the optimal configuration of different distributed power sources under different scenarios; others take the various costs of microgrid operation as the objective function, and propose an optimal configuration method for electric vehicle charging stations with multiple types of charging piles; in the actual operation of the distribution network, the factors that need to be considered include not only economic factors, but also other factors such as low carbon and grid stability. Moreover, the above schemes only select the capacity and site for distributed power sources and energy storage, and do not consider the impact of charging stations on the distribution network. There is a lack of coordinated optimization planning methods for distribution networks covering multiple elements such as hydropower, photovoltaics, charging piles, and energy storage. Summary of the invention
[0004] The purpose of the present invention is to provide a distribution network optimization planning method, system, equipment and medium based on multi-objective collaboration, taking into account economic costs, charging distances and system carbon emissions, and using algorithms to solve multi-objective functions, thereby obtaining the optimal planning scheme under different scenarios.
[0005] The above technical objectives of the present invention are achieved through the following technical solutions:
[0006] In a first aspect, the present application provides a distribution network optimization planning method based on multi-objective collaboration, comprising the following specific steps:
[0007] Establishing a total objective function based on multiple collaborative objectives and constraints corresponding to the multiple collaborative objectives, where the multiple collaborative objectives include economic cost, charging distance, and carbon emissions;
[0008] Obtaining grid data of the distribution network to be planned, and using the grid data and the overall objective function to establish a scenario model corresponding to the distribution network to be planned;
[0009] The NSGA-II algorithm is used to solve the scenario model to obtain the optimal solution of the scenario model of the distribution network to be planned, and the optimal solution is used to optimize the planning of the distribution network to be planned.
[0010] Based on the above technical solution, the present invention can also be improved as follows.
[0011] Furthermore, the above overall objective function is specifically:
[0012] F = min[f1 f2 f3];
[0013] Where F represents the total objective function, f1 represents the objective function of economic cost, f2 represents the objective function of charging distance, and f3 represents the objective function of carbon emissions.
[0014] Furthermore, the objective function of the above economic cost is specifically:
[0015] f1=C inv +C grid +C po ;
[0016] Where f1 represents the objective function of economic cost, C inv represents the investment and operation cost of the planned distribution network components, C grid represents the electricity purchase cost of the planned distribution network, C po Represents the power outage loss cost of the planned distribution network, where:
[0017] The investment and operation and maintenance costs of the planned distribution network components are as follows:
[0018]
[0019] In the formula, C inv represents the investment and operation cost of the planned distribution network components, k O&M The coefficient representing the operation and maintenance cost, c tran represents the cost of the unit capacity transformer, k tran Represents the safety factor of expanding transformer capacity, p grid,t represents the purchased power at time t, Ptran represents the rated power of the existing transformer in the distribution network to be planned, c cs represents the cost of a charging station per unit capacity, E cs represents the total capacity of the charging station, c bat Represents the cost of energy storage per unit capacity, E bat represents the energy storage capacity, c PV Represents the cost of photovoltaic power per unit capacity, E PV represents photovoltaic capacity;
[0020] The specific electricity purchase cost of the planned distribution network is:
[0021]
[0022] In the formula, C grid represents the electricity purchase cost of the planned distribution network, c grid,t represents the purchased power at time t, p grid,t represents the electricity purchase price at time t, and T represents the electricity purchase cycle;
[0023] The power outage loss cost of the planned distribution network is as follows:
[0024]
[0025] In the formula, C po represents the power outage loss cost of the planned distribution network, c po represents the power outage power at time t, p po,t It represents the power outage loss cost per unit power, and T represents the power outage period.
[0026] Furthermore, the objective function of the above economic cost is specifically:
[0027]
[0028] In the formula, i, j both represent the nodes of the distribution network to be planned, N represents the set of nodes of the distribution network to be planned, T represents the set of time, and I cs Indicates the node where the charging station is installed in the planned distribution network, n i,j,t represents the number of vehicles that node j chooses to go to node i to charge at time t, d i,j, represents the distance between node j and node i, and f2 represents the objective function of the charging distance.
[0029] Furthermore, the objective function of the above carbon emissions is specifically:
[0030]
[0031] In the formula, k CO2 Indicates the amount of carbon dioxide emitted per unit power generated by the grid, p grid,trepresents the purchased electricity power at time t, and f3 represents the objective function of carbon emissions.
[0032] Furthermore, the above constraints include power balance constraints, charging station discharge constraints, renewable energy output constraints, energy storage constraints and power flow constraints.
[0033] Furthermore, the above power balance constraint is specifically:
[0034]
[0035] In the formula, p grid,t represents the purchased power at time t, p hyd,t represents the power of hydroelectric power generation at time t, p po,t represents the power of power outage at time t, p pv,t represents the photovoltaic power generation at time t, p bat,t represents the power of energy storage generation at time t, p load,t represents the traditional load at time t, p cs,t represents the total load of the charging station at time t, p loss,t represents the power loss at time t, and T represents the power consumption cycle;
[0036] The specific discharge constraints of the charging station are:
[0037]
[0038] In the formula, p cs,t is the total load of the charging station at time t, p cs,i,t is the charging station load of node i at time t, P cs,i is the capacity of the charging station at node i, P cs,i is the capacity of the charging station at node i, E cs is the total capacity of the charging station;
[0039] The specific constraints on renewable energy output are:
[0040]
[0041] E PV,min ≤E PV,i ≤E PV,max ;
[0042] In the formula, p Hyd,i,t represents the hydropower power of node i at time t, P Hyd,t It represents the unit hydropower output power at time t, E Hyd,i represents the hydropower capacity of node i, p Hyd,t represents the total hydropower power at time t, I Hyd Indicates the set of hydropower nodes, p PV,i,t represents the photovoltaic power of node i at time t, PPV,t Represents the unit photovoltaic output power at time t, E PV,i represents the photovoltaic capacity of node i, p PV,t represents the total photovoltaic power at time t, I PV Indicates the set of photovoltaic nodes, E PV Represents photovoltaic capacity, E PV,i represents the photovoltaic capacity of node i, E PV,min represents the lower limit of the node photovoltaic capacity, E PV,max Indicates the upper limit of the node's photovoltaic capacity;
[0043] The energy storage constraints are as follows:
[0044] E bat,min ≤E bat,i ≤E bat,max ,
[0045]
[0046] In the formula, E bat,i represents the energy storage capacity of node i, E bat,min Represents the lower limit of energy storage photovoltaic capacity, E bat,max represents the upper limit of energy storage photovoltaic capacity, p bat,i,t represents the discharge power of energy storage at node i at time t, p bat,t It represents the total energy storage discharge power at time t, I bat represents the set of energy storage nodes, E bat represents the energy storage capacity, p grid,i,t represents the purchased power of node i at time t, represents the average power purchased by node i at time t;
[0047] The power flow constraint is specifically expressed as:
[0048]
[0049] S ij ≤S max,ij , U min,i ≤U i ≤U max,i ;
[0050] Where P i represents the active power of node i, U i represents the voltage amplitude of node i, G ij represents the conductance between nodes i and j, B ij represents the susceptance between nodes i and j, θ i represents the phase of node i, Q i represents the reactive power of node i, S ij represents the capacity between nodes i and j, Smax,ij represents the upper limit of the capacity between nodes i and j, U max,i represents the voltage upper limit of node i, U min,i Indicates the lower voltage limit of node i.
[0051] In a second aspect, the present application provides a distribution network optimization planning system based on multi-objective collaboration, which is applied to any one of the distribution network optimization planning methods based on multi-objective collaboration in the first aspect, including:
[0052] The first module is used to establish a total objective function based on multiple collaborative objectives and constraints corresponding to the multiple collaborative objectives, and the multiple collaborative objectives include economic cost, charging distance and carbon emissions;
[0053] The second module is used to obtain the grid data of the distribution network to be planned, and use the grid data and the overall objective function to establish a scenario model corresponding to the distribution network to be planned;
[0054] The third module is used to solve the scenario model using the NSGA-II algorithm to obtain the optimal solution of the scenario model of the distribution network to be planned, and use the optimal solution to optimize the planning of the distribution network to be planned.
[0055] In a third aspect, the present application provides an electronic device comprising a memory, a processor, and a computer program stored in the memory and executable on the processor, wherein the processor implements any one of the methods in the first aspect when executing the computer program.
[0056] In a fourth aspect, the present application provides a non-transitory computer-readable storage medium, which stores computer instructions, and the computer instructions enable a computer to execute any one of the methods in the first aspect.
[0057] Compared with the prior art, the present invention has at least the following beneficial effects:
[0058] In this application, the economic cost, charging distance and system carbon emissions are comprehensively analyzed as collaborative objectives, and a multi-objective optimization planning method for multi-factor site selection and sizing of the "hydro-solar-charging-storage" distribution network system is proposed. The NSGA-II algorithm is used to solve the multi-objective function, and the optimal planning scheme for the distribution network under different scenarios is obtained, thereby achieving a comprehensive evaluation of the system's economy, low carbon, sociality, safety and reliability.
[0059] In this application, the planning of the "hydro-solar-charging-storage" distribution network needs to take into account economy, society, low carbon and reliability. The power outage electricity corresponding to reliability can be converted into power outage losses and included in the economic cost to reduce decision variables. Therefore, it is necessary to establish an objective function that quantifies the system's economic cost, low carbon and sociality, clarify boundary conditions such as power balance, charging and discharging station operation, renewable energy output, energy storage operation status and flow constraints, construct different types of planning scenarios based on local power grid and transportation network data, solve planning schemes for planning models of different scenarios respectively, and obtain the optimal solution under different scenarios by approximating the ideal solution. Finally, a comprehensive evaluation can be conducted on the configuration results of the "hydro-solar-charging-storage" distribution network under each scenario to verify the rationality of the configuration scheme under different target scenarios. BRIEF DESCRIPTION OF THE DRAWINGS
[0060] The drawings described herein are used to provide a further understanding of the embodiments of the present invention, constitute a part of this application, and do not constitute a limitation of the embodiments of the present invention. In the drawings:
[0061] Figure 1 A method flow chart of a planning method in an embodiment of the present invention;
[0062] Figure 2 Schematic diagram of a hydro-solar charging and storage distribution network in an embodiment of the present invention;
[0063] Figure 3 A flow chart of power distribution network system planning in an embodiment of the present invention;
[0064] Figure 4 A connection diagram of a planning system in an embodiment of the present invention;
[0065] Figure 5 Schematic diagram of the connection of electronic equipment in an embodiment of the present invention. DETAILED DESCRIPTION
[0066] In order to make the purpose, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Generally, the components of the embodiments of the present invention described and shown in the drawings here can be arranged and designed in various different configurations.
[0067] Therefore, the following detailed description of the embodiments of the present invention provided in the accompanying drawings is not intended to limit the scope of the invention claimed for protection, but merely represents selected embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0068] It should be noted that similar reference numerals and letters denote similar items in the following drawings, and therefore, once an item is defined in one drawing, further definition and explanation thereof is not required in subsequent drawings.
[0069] The "hydro-solar-charging-storage" distribution network is a new type of high-proportion renewable energy distribution network that covers multiple clean elements such as hydropower, photovoltaics, charging stations, and energy storage. The distribution network mainly supplies local loads with distributed small hydropower and distributed photovoltaics. The part where the local power supply is insufficient meets the user's electricity demand through substations connected to the large power grid. In order to make full use of the distributed photovoltaic output and adjust the power fluctuations and voltage fluctuations of each node, energy storage is further introduced to achieve the regulation of system power and the storage and release of clean electricity. The structure of the "hydro-solar-charging-storage" distribution network is as follows: Figure 2 shown.
[0070] Embodiment 1:
[0071] The planning of the "hydro-photovoltaic-charging-storage" distribution network system needs to consider the carbon emission characteristics of hydropower, photovoltaics and other energy sources, the supply and demand coupling characteristics of hydropower-photovoltaic-energy storage-charging stations, and the distribution and flow constraints of the distribution network that meet the needs of low-carbon development. The planning of the "hydro-photovoltaic-charging-storage" system is based on electricity demand, hydropower and photovoltaic installed capacity and site selection. It mainly coordinates the location and capacity of charging stations and energy storage in the system. It is necessary to take into account the economy, low carbon and sociality of the system at the same time, establish a multi-objective collaborative optimization planning model for the "hydro-photovoltaic-charging-storage" distribution network, propose a joint planning method for the "hydro-photovoltaic-charging-storage" distribution network that meets the requirements of low-carbon development under different structural forms, and derive the optimized planning scheme for charging facilities, distributed clean energy and energy storage. Finally, a comprehensive evaluation of the planning results is carried out through multiple dimensions such as economy, low carbon, sociality, safety and reliability. The economic efficiency of the system includes the construction and operation costs of charging stations and energy storage and the system's electricity purchase costs; low carbon is mainly characterized by the utilization rate of the system's clean energy; social indicators are mainly used to quantify the charging satisfaction of electric vehicle users in the "water-solar-charging-storage" system, which is characterized by the charging distance; safety indicators mainly quantify the impact of different planning schemes on the safe and stable operation of the power grid, which is characterized by voltage stability and load stability; reliability is mainly used to quantify the user's power outage and load loss, and the system planning process is as follows: Figure 2 shown.
[0072] Among them, the planning of the "hydro-solar-charging-storage" distribution network needs to take into account economy, society, low carbon and reliability. The power outage power corresponding to reliability can be converted into power outage losses and included in the economic cost to reduce decision variables. Therefore, it is necessary to establish an objective function that quantifies the economic cost, low carbon and sociality of the system, clarify boundary conditions such as power balance, charging and discharging station operation, renewable energy output, energy storage operation status and flow constraints, and construct different types of planning scenarios based on local power grid and transportation network data. The planning models of different scenarios are solved respectively, and the optimal solutions under different scenarios are obtained by approximating the ideal solution, such as Figure 3 As shown in the figure, finally, a comprehensive evaluation is conducted on the configuration results of the “hydro-solar-charging-storage” distribution network under each scenario to verify the rationality of the configuration scheme under different target scenarios.
[0073] This embodiment provides a distribution network optimization planning method based on multi-objective coordination. The economic, social and low-carbon characteristics of the "hydro-solar-charging-storage" distribution network system are characterized by economic cost, charging distance and system carbon emissions respectively. The overall objective function is shown in the following formula:
[0074] F = min[f1 f2 f3];
[0075] Where F represents the total objective function, f1 represents the objective function of economic cost, f2 represents the objective function of charging distance, and f3 represents the objective function of carbon emissions.
[0076] Furthermore, the economic cost includes the investment and operation and maintenance costs of system components, the power purchase cost, and the power outage loss cost, as shown in the following formula:
[0077] f1=C inv +C grid +C po ;
[0078] Where f1 represents the objective function of economic cost, C inv represents the investment and maintenance cost of system components, C grid represents the system's electricity purchase cost, C po Represents the power outage loss cost of the system.
[0079] Optional, investment and maintenance costs of system components C inv It is composed of the investment and operation and maintenance costs of the newly added transformers, charging stations, energy storage and photovoltaics in the system. The operation and maintenance cost is the investment cost multiplied by the corresponding coefficient, as shown in the following formula:
[0080]
[0081] In the formula, C inv represents the investment and maintenance cost of system components, k O&M The coefficient representing the operation and maintenance cost, c tranrepresents the cost of the transformer per unit capacity, k tran represents the safety factor of expanding the transformer capacity, which can be 1.8; p grid,t represents the purchased power at time t, P tran represents the rated power of the existing transformer in the distribution network to be planned, c cs represents the cost of a charging station per unit capacity, E cs represents the total capacity of the charging station, c bat Represents the cost of energy storage per unit capacity, E bat represents the energy storage capacity, c PV Represents the cost of photovoltaic power per unit capacity, E PV Represents photovoltaic capacity.
[0082] Optionally, the system's electricity purchase cost is as follows:
[0083]
[0084] In the formula, C grid represents the system's electricity purchase cost, c grid,t represents the purchased power at time t, p grid,t It represents the electricity purchase price at time t, and T represents the electricity purchase cycle.
[0085] Optionally, the power outage loss cost of the system is as follows:
[0086]
[0087] In the formula, C po represents the power outage loss cost of the system, c po represents the power outage power at time t, p po,t It represents the power outage loss cost per unit power, and T represents the power outage period.
[0088] Furthermore, in this embodiment, the total charging distance of the car owner in the system is calculated to represent the charging route loss of the car owner as shown in the following formula:
[0089]
[0090] In the formula, i and j represent system nodes, N represents the set of system nodes, T represents the set of time, and I cs Indicates the node where the charging station is installed in the system, n i,j,t represents the number of vehicles that node j chooses to go to node i to charge at time t, d i,j, represents the distance between node j and node i, and f2 represents the objective function of the charging distance.
[0091] Furthermore, the carbon emissions of the system are determined by the amount of electricity purchased by the system, as shown in the following formula:
[0092]
[0093] In the formula, k CO2 Indicates the amount of carbon dioxide emitted per unit power generated by the grid, p grid,t represents the purchased electricity power at time t, and f3 represents the objective function of carbon emissions.
[0094] Furthermore, in order to ensure the power balance of the system, this embodiment adds power balance constraints for the "water-solar-storage" system:
[0095]
[0096] In the formula, p grid,t represents the purchased power at time t, p hyd,t represents the power of hydroelectric power generation at time t, p po,t represents the power of power outage at time t, p pv,t represents the photovoltaic power generation at time t, p bat,t represents the power of energy storage generation at time t, p load,t represents the traditional load at time t, p cs,t represents the total load of the charging station at time t, p loss,t It represents the power loss at time t, and T represents the power consumption cycle.
[0097] Optionally, the present embodiment sets the following constraints for the charging and discharging power and capacity of the charging station. First, the total load provided by the charging station at each moment of the system is the sum of the loads of each charging station, as shown in the following formula:
[0098]
[0099] In the formula, p cs,t is the total load of the charging station at time t, p cs,i,t is the charging station load at node i at time t.
[0100] Among them, the load of each charging station cannot exceed its rated power, and its constraints are as follows:
[0101]
[0102] In the formula, p cs,i,t is the charging station load of node i at time t, P cs,i is the charging station capacity of the i-node.
[0103] Among them, the constraints between the total capacity of the charging station and the capacity of each node charging station are as follows:
[0104]
[0105] Where P cs,i is the capacity of the charging station at node i, Ecs is the total capacity of the charging station.
[0106] Furthermore, the present embodiment sets the following constraints for the charging and discharging power and capacity of renewable energy. First, the hydropower generation power is set to the generation curve obtained by clustering multiplied by its capacity, as shown in the following formula:
[0107]
[0108] In the formula, p Hyd,i,t is the hydropower power of node i at time t, P Hyd,t is the unit hydropower output at time t, E Hyd,i is the water and electricity capacity of node i.
[0109] Among them, the power of hydropower at each moment in the system is the sum of the power of each hydropower, as shown in the following formula:
[0110]
[0111] In the formula, p Hyd,i,t is the hydropower power of node i at time t, p Hyd,t is the total hydropower power at time t, I Hyd A collection of hydropower nodes is set.
[0112] The photovoltaic power generation is the power generation curve obtained by clustering multiplied by its capacity, as shown in the following formula:
[0113]
[0114] In the formula, p PV,i,t is the photovoltaic power of node i at time t, P PV,t is the unit photovoltaic output power at time t, E PV,i is the photovoltaic capacity of node i.
[0115] Among them, the photovoltaic power of the system at each moment is the sum of the power of each photovoltaic, as shown in the following formula:
[0116]
[0117] In the formula, p PV,i,t is the photovoltaic power of node i at time t, p PV,t is the total photovoltaic power at time t, I PV To set the collection of photovoltaic nodes.
[0118] The total capacity of the photovoltaic system in this embodiment is the sum of the capacities of each photovoltaic, and its calculation method is as follows:
[0119]
[0120] In the formula, E PVis the photovoltaic capacity, E PV,i is the photovoltaic capacity of node i, I PV To set the collection of photovoltaic nodes.
[0121] Among them, according to the actual situation, the upper and lower limits of photovoltaic power that can be installed at each node are set, as shown in the following formula:
[0122] E PV,min ≤E PV,i ≤E PV,max ;
[0123] In the formula, E PV,i is the photovoltaic capacity of node i, E PV,min is the lower limit of the node photovoltaic capacity, E PV,max is the upper limit of the node’s photovoltaic capacity.
[0124] Furthermore, in view of the charging and discharging power and capacity of the energy storage, this embodiment formulates the following constraints and charging and discharging strategies for the energy storage. To ensure the stable operation of the energy storage and the regulation capability of the next cycle, the charge state at the beginning and end of a scheduling cycle should be equal.
[0125] Optionally, according to the actual situation, set the upper and lower limits of the energy storage that can be installed at each node, as shown in the following formula:
[0126] E bat,min ≤E bat,i ≤E bat,max ;
[0127] In the formula, E bat,i is the energy storage capacity of node i, E bat,min is the lower limit of energy storage photovoltaic capacity, E bat,max It is the upper limit of energy storage photovoltaic capacity.
[0128] Among them, the charging and discharging power of the energy storage at each moment of the system is the sum of the charging and discharging of each energy storage, as shown in the following formula:
[0129]
[0130] In the formula, p bat,i,t is the discharge power of energy storage at node i at time t, p bat,t is the total energy storage discharge power at time t, I bat is a collection of energy storage nodes.
[0131] The total charging and discharging power of each node energy storage during the scheduling period is set to 0, and the constraints are as follows:
[0132]
[0133] In the formula, p bat,i,tis the discharge power of the energy storage at node i at time t, and the constraint ensures that the energy storage state is the same at the beginning and end of the scheduling period.
[0134] Among them, the total capacity of energy storage in the system is the sum of the capacities of each energy storage, and its constraints are as follows:
[0135]
[0136] In the formula, E bat is the energy storage capacity, E bat,i is the energy storage capacity of node i, I bat A collection of energy storage nodes.
[0137] The energy storage capacity of node i is the maximum charge / discharge energy of the energy storage system as its rated capacity, as shown in the following formula:
[0138]
[0139] In the formula, E bat,i is the energy storage capacity of node i, p bat,i,t is the discharge power of the energy storage at node i at time t, and the node energy storage capacity is the maximum charge / discharge energy of the energy storage system as its rated capacity.
[0140] Among them, in order to ensure the stability of the node load and minimize the node load fluctuation, the charging and discharging strategy of the energy storage installation node is formulated as shown in the following formula:
[0141]
[0142] In the formula, I bat is the node where energy storage is placed, p grid,i,t is the power purchased by node i from the grid at time t, is the average power purchased by node i from the grid at time t.
[0143] Furthermore, in order to ensure that the optimization results meet the constraints of the distribution network topology, the system power flow active constraints are set as follows:
[0144]
[0145] Where P i is the active power of node i, U i is the voltage amplitude of node i, G ij is the conductance between nodes i and j, B ij is the susceptance between nodes i and j, θ i is the phase of node i.
[0146] Among them, the system power flow reactive constraints are as follows:
[0147]
[0148] In the formula, Q i is the reactive power of node i, U i is the voltage amplitude of node i, G ij is the conductance between nodes i and j, B ij is the susceptance between nodes i and j, θ i is the phase of node i.
[0149] The line transmission capacity constraint is as follows:
[0150] S ij ≤S max,ij ;
[0151] In the formula, S ij is the capacity between nodes i and j, S max,ij is the upper limit of the capacity between nodes i and j.
[0152] The node voltage amplitude constraint is as follows:
[0153] U min,i ≤U i ≤U max,i ;
[0154] Where U i is the voltage amplitude of node i, U max,i is the voltage upper limit of node i, U min,i is the lower limit of the voltage of node i.
[0155] Embodiment 2:
[0156] This embodiment provides a distribution network optimization planning method based on multi-objective coordination, such as Figure 1 As shown, the specific steps include:
[0157] S1, establishes a total objective function based on multiple collaborative objectives and constraints corresponding to the multiple collaborative objectives, and the multiple collaborative objectives include economic cost, charging distance and carbon emissions.
[0158] Optionally, the above overall objective function is specifically:
[0159] F = min[f1 f2 f3];
[0160] Where F represents the total objective function, f1 represents the objective function of economic cost, f2 represents the objective function of charging distance, and f3 represents the objective function of carbon emissions.
[0161] Optionally, the objective function of the above economic cost is specifically:
[0162] f1=C inv +Cgrid +C po ;
[0163] Where f1 represents the objective function of economic cost, C inv represents the investment and maintenance cost of system components, C grid represents the system's electricity purchase cost, C po Represents the power outage loss cost of the system.
[0164] The investment and operation costs of system components are as follows:
[0165]
[0166] In the formula, C inv represents the investment and maintenance cost of system components, k O&M The coefficient representing the operation and maintenance cost, c tran represents the cost of the unit capacity transformer, k tran Represents the safety factor of expanding transformer capacity, p grid,t represents the purchased power at time t, P tran represents the rated power of the existing transformer in the distribution network to be planned, c cs represents the cost of a charging station per unit capacity, E cs represents the total capacity of the charging station, c bat Represents the cost of energy storage per unit capacity, E bat represents the energy storage capacity, c PV Represents the cost of photovoltaic power per unit capacity, E PV Represents photovoltaic capacity.
[0167] Among them, the power purchase cost of the system is specifically:
[0168]
[0169] In the formula, C grid represents the system's electricity purchase cost, c grid,t represents the purchased power at time t, p grid,t It represents the electricity purchase price at time t, and T represents the electricity purchase cycle.
[0170] Among them, the power outage loss cost of the system is specifically:
[0171]
[0172] In the formula, C po represents the power outage loss cost of the system, c po represents the power outage power at time t, p po,t It represents the power outage loss cost per unit power, and T represents the power outage period.
[0173] Optionally, the objective function of the above economic cost is specifically:
[0174]
[0175] In the formula, i and j represent system nodes, N represents the set of system nodes, T represents the set of time, and I cs Indicates the node where the charging station is installed in the system, n i,j,t represents the number of vehicles that node j chooses to go to node i to charge at time t, d i,j, represents the distance between node j and node i, and f2 represents the objective function of the charging distance.
[0176] Optionally, the objective function of the above carbon emissions is specifically:
[0177]
[0178] In the formula, k CO2 Indicates the amount of carbon dioxide emitted per unit power generated by the grid, p grid,t represents the purchased electricity power at time t, and f3 represents the objective function of carbon emissions.
[0179] Optionally, the above constraints include power balance constraints, charging station discharge constraints, renewable energy output constraints, energy storage constraints and power flow constraints.
[0180] Specifically, the above power balance constraints are:
[0181]
[0182] In the formula, p grid,t represents the purchased power at time t, p hyd,t represents the power of hydroelectric power generation at time t, p po,t represents the power of power outage at time t, p pv,t represents the photovoltaic power generation at time t, p bat,t represents the power of energy storage generation at time t, p load,t represents the traditional load at time t, p cs,t represents the total load of the charging station at time t, p loss,t It represents the power loss at time t, and T represents the power consumption cycle.
[0183] Among them, the specific discharge constraints of the charging station are:
[0184]
[0185] In the formula, p cs,t is the total load of the charging station at time t, p cs,i,t is the charging station load of node i at time t, P cs,i is the capacity of the charging station at node i, Pcs,i is the capacity of the charging station at node i, E cs is the total capacity of the charging station.
[0186] Among them, the renewable energy output constraints are specifically as follows:
[0187]
[0188] E PV,min ≤E PV,i ≤E PV,max ;
[0189] In the formula, p Hyd,i,t represents the hydropower power of node i at time t, P Hyd,t represents the unit hydropower output at time t, E Hyd,i represents the hydropower capacity of node i, p Hyd,t represents the total hydropower power at time t, I Hyd Indicates the set of hydropower nodes, p PV,i,t represents the photovoltaic power of node i at time t, P PV,t Represents the unit photovoltaic output power at time t, E PV,i represents the photovoltaic capacity of node i, p PV,t represents the total photovoltaic power at time t, I PV Indicates the set of photovoltaic nodes, E PV Represents photovoltaic capacity, E PV,i represents the photovoltaic capacity of node i, E PV,min represents the lower limit of the node photovoltaic capacity, E PV,max Indicates the upper limit of the node’s PV capacity.
[0190] The energy storage constraints are as follows:
[0191] E bat,min ≤E bat,i ≤E bat,max ,
[0192]
[0193] In the formula, E bat,i represents the energy storage capacity of node i, E bat,min Represents the lower limit of energy storage photovoltaic capacity, E bat,max represents the upper limit of energy storage photovoltaic capacity, p bat,i,t represents the discharge power of energy storage at node i at time t, p bat,t It represents the total energy storage discharge power at time t, I bat represents the set of energy storage nodes, E bat represents the energy storage capacity, p grid,i,t represents the purchased power of node i at time t, Represents the average power purchased by node i at time t.
[0194] The power flow constraint is specifically expressed as:
[0195]
[0196] S ij ≤S max,ij , U min,i ≤U i ≤U max,i ;
[0197] Where P i represents the active power of node i, U i represents the voltage amplitude of node i, G ij represents the conductance between nodes i and j, B ij represents the susceptance between nodes i and j, θ i represents the phase of node i, Q i represents the reactive power of node i, S ij represents the capacity between nodes i and j, S max,ij represents the upper limit of the capacity between nodes i and j, U max,i represents the voltage upper limit of node i, U min,i Indicates the lower voltage limit of node i.
[0198] S2, obtaining the grid data of the distribution network to be planned, and using the grid data and the overall objective function to establish a scenario model corresponding to the distribution network to be planned.
[0199] Among them, the overall objective function aims at economy, low carbon and sociality, and carries out power constraints, capacity constraints and flow constraints, such as Figure 3 Specifically, the acquired power grid data may include processing data, load data and travel data, and the scenario model may include a power output prediction probability model, a load prediction model and a charging demand prediction model based on the formation chain corresponding to each data, see Figure 3 .
[0200] S3, using the NSGA-II algorithm to solve the scenario model, obtain the optimal solution of the scenario model of the distribution network to be planned, and use the optimal solution to optimize the planning of the distribution network to be planned.
[0201] Among them, the NSGA-II algorithm can use the non-dominated classification procedure to transform multiple objectives into a fitness function form and obtain the optimal solution set of the multi-objective problem. The specific steps of the algorithm are as follows:
[0202] Step 1: Chromosome encoding. The chromosome contains all decision variables, which are divided into four sections, including the power outage within time T, the location and capacity of the charging station and the decision variables for electric vehicles to choose the charging station for charging, the location and capacity of the energy storage and its charging and discharging power, and the location and capacity of photovoltaics. One chromosome represents a solution. The generation of chromosomes must meet the corresponding constraints, otherwise it will be discarded. Set the population size N, generate the initial population Po, and calculate its fitness function according to the weighted corresponding objective function.
[0203] Step 2: Fast non-dominated sorting. According to the individual fitness function and crowding information, select high-quality parents for genetic operations to obtain the offspring population. The calculation formula for individual crowding is as follows:
[0204]
[0205] In the formula, f i+1,j 、f i-1,j They are the function values of the i+1 point and i-1 objective functions, namely the three objective function values of economic cost, charging distance and system carbon emissions; J is the number of objective functions.
[0206] Step 3: Selection, crossover and mutation. The selection step adopts the roulette wheel selection method. The probability of individual selection is determined by the size of its fitness, and the probability of individual selection is proportional to its fitness. The crossover operation performs a single-point crossover on the selected individuals, that is, a gene point is selected on a pair of chromosomes to divide the chromosome into two parts, and then interchange and reorganize into two new chromosomes, that is, a point is randomly selected in the variable for crossover operation, and a part of the values of different variable combinations are exchanged. After completion, other decision variables are randomly generated according to the values of this part, and individuals that do not meet the constraints are eliminated. The mutation operation refers to any individual in the population mutating one or several gene positions in its chromosome with a certain probability, changing the values of these decision variables to obtain new chromosomes.
[0207] Step 4: Elite selection. The elite strategy is to combine the parent population N1 and the next generation new population N2 generated by the parent into a population N3 of size 2N, and perform a fast non-dominated sorting calculation on the new population, and select the best N individuals as the parent population of the new generation. This retains the optimal solution before and after the operation and optimizes the accuracy of the result.
[0208] Furthermore, the NSGA-II algorithm will continuously update the Pareto solution set during the iteration process. However, when the distribution of Pareto optimal solutions is too dense, the algorithm will eliminate some optimal solutions through the following formula:
[0209]
[0210] In the formula, f m,iis the objective function value of the ith solution, D m is the Pareto frontier distance threshold of the mth objective function value; f max,m 、f min,m Respectively represent the maximum and minimum values found by the current storage pool in the mth objective function; N r The upper limit of the number of Pareto optimal solutions in the storage pool.
[0211] Furthermore, the optimal ideal solution can be used to evaluate the target, and the solution set can be evaluated using the value of the objective function to find the optimal solution that comprehensively considers economy, carbon emissions and charging distance under different scenarios. After calculating the value of the evaluation index, it is normalized, and the formula is as follows:
[0212]
[0213] Among them, the normalized target ideal point is O. In order to find the optimal solution that takes into account multiple objectives at the same time, the ideal point proximity calculation is carried out for all optimization solutions. The square of the Euclidean distance from all Pareto optimal solutions to the target ideal point is:
[0214]
[0215] In the formula, f m '(x i ) is the value of the mth evaluation index after normalization of the ith solution in the Pareto solution set, f m ' ,ideal is the value of the ideal solution for this evaluation index.
[0216] Furthermore, the best decision plan is objectively determined based on the principle that the sum of the squares of the Euclidean distances between all Pareto optimal solutions and the ideal points on each target is minimized, as shown in the following formula:
[0217]
[0218] In the formula, x best This is the optimal solution selected in this scenario.
[0219] S4, based on the optimal solution of the scenario model of the distribution network to be planned, comprehensively evaluate the planning results of the “hydro-solar-charging-storage” distribution network, such as Figure 3 As shown, it can be evaluated from the perspectives of economy, low carbon, society, reliability and safety.
[0220] Embodiment 3:
[0221] The embodiment of the present application provides a distribution network optimization planning system based on multi-objective collaboration, which is applied to the distribution network optimization planning method based on multi-objective collaboration in any one of Embodiment 1 or Embodiment 2, such as Figure 4 As shown, including:
[0222] The first module is used to establish an overall objective function based on multiple collaborative objectives and constraints corresponding to the multiple collaborative objectives. The multiple collaborative objectives include economic cost, charging distance and carbon emissions.
[0223] The second module is used to obtain the grid data of the distribution network to be planned, and use the grid data and the overall objective function to establish a scenario model corresponding to the distribution network to be planned.
[0224] The third module is used to solve the scenario model using the NSGA-II algorithm to obtain the optimal solution of the scenario model of the distribution network to be planned, and use the optimal solution to optimize the planning of the distribution network to be planned.
[0225] The present application embodiment provides an electronic device, such as Figure 5 As shown, it includes a memory, a processor, and a computer program stored in the memory and executable on the processor. When the processor executes the computer program, the method of any one of Embodiment 1 or Embodiment 2 is implemented.
[0226] An embodiment of the present application also provides a non-transitory computer-readable storage medium, which stores computer instructions, and the computer instructions enable a computer to execute any method in Example 1 or Example 2.
[0227] The specific implementation methods described above further illustrate the objectives, technical solutions and beneficial effects of the present invention in detail. It should be understood that the above description is only a specific implementation method of the present invention and is not intended to limit the scope of protection of the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the scope of protection of the present invention.
Claims
1. A distribution network optimization planning method based on multi-objective collaboration, characterized in that: The specific steps include: Establishing a total objective function based on multiple collaborative objectives and constraints corresponding to the multiple collaborative objectives, wherein the multiple collaborative objectives include economic cost, charging distance, and carbon emissions; Acquire grid data of the distribution network to be planned, and use the grid data and the overall objective function to establish a scenario model corresponding to the distribution network to be planned; The scenario model is solved using the NSGA-II algorithm to obtain an optimal solution to the scenario model of the distribution network to be planned, and the optimal solution is used to optimize the planning of the distribution network to be planned.
2. The distribution network optimization planning method based on multi-objective collaboration according to claim 1 is characterized in that: The overall objective function is specifically: F = min[f1 f2 f3]; Where F represents the total objective function, f1 represents the objective function of economic cost, f2 represents the objective function of charging distance, and f3 represents the objective function of carbon emissions.
3. The distribution network optimization planning method based on multi-objective collaboration according to claim 2 is characterized in that: The objective function of the economic cost is specifically: f1=C inv +C grid +C po ; Where f1 represents the objective function of economic cost, C inv represents the investment and operation cost of the planned distribution network components, C grid represents the electricity purchase cost of the planned distribution network, C po Represents the power outage loss cost of the planned distribution network, where: The investment and operation and maintenance costs of the distribution network components to be planned are specifically: In the formula, C inv represents the investment and operation cost of the planned distribution network components, k O&M The coefficient representing the operation and maintenance cost, c tran represents the cost of the unit capacity transformer, k tran Represents the safety factor of expanding transformer capacity, p grid,t represents the purchased power at time t, P tran represents the rated power of the existing transformer in the distribution network to be planned, c cs represents the cost of a charging station per unit capacity, E cs represents the total capacity of the charging station, c bat Represents the cost of energy storage per unit capacity, E bat represents the energy storage capacity, c PV Represents the cost of photovoltaic power per unit capacity, E PV represents photovoltaic capacity; The power purchase cost of the distribution network to be planned is specifically: In the formula, C grid represents the electricity purchase cost of the planned distribution network, c grid,t represents the purchased power at time t, p grid,t represents the electricity purchase price at time t, and T represents the electricity purchase cycle; The power outage loss cost of the distribution network to be planned is specifically: In the formula, C po represents the power outage loss cost of the planned distribution network, c po represents the power outage power at time t, p po,t It represents the power outage loss cost per unit power, and T represents the power outage period.
4. The distribution network optimization planning method based on multi-objective collaboration according to claim 2 is characterized in that: The objective function of the economic cost is specifically: In the formula, i, j both represent the nodes of the distribution network to be planned, N represents the set of nodes of the distribution network to be planned, T represents the set of time, and I cs Indicates the node where the charging station is installed in the planned distribution network, n i,j,t represents the number of vehicles that node j chooses to go to node i to charge at time t, d i,j, represents the distance between node j and node i, and f2 represents the objective function of the charging distance.
5. The distribution network optimization planning method based on multi-objective collaboration according to claim 2 is characterized in that: The objective function of carbon emissions is specifically: In the formula, k CO2 Indicates the amount of carbon dioxide emitted per unit power generated by the grid, p grid,t represents the purchased electricity power at time t, and f3 represents the objective function of carbon emissions.
6. The distribution network optimization planning method based on multi-objective collaboration according to claim 1 is characterized in that: The constraints include power balance constraints, charging station discharge constraints, renewable energy output constraints, energy storage constraints and power flow constraints.
7. The distribution network optimization planning method based on multi-objective coordination according to claim 6 is characterized in that: The power balance constraint is specifically: In the formula, p grid,t represents the purchased power at time t, p hyd,t represents the power of hydroelectric power generation at time t, p po,t represents the power outage at time t, p pv,t represents the photovoltaic power generation at time t, p bat,t represents the power of energy storage generation at time t, p load,t represents the traditional load at time t, p cs,t represents the total load of the charging station at time t, p loss,t represents the power loss at time t, and T represents the power consumption cycle; The charging station discharge constraints are specifically: In the formula, p cs,t is the total load of the charging station at time t, p cs,i,t is the charging station load of node i at time t, P cs,i is the capacity of the charging station at node i, P cs,i is the capacity of the charging station at node i, E cs is the total capacity of the charging station; The renewable energy output constraints are specifically: In the formula, p Hyd,i,t represents the hydropower power of node i at time t, P Hyd,t represents the unit hydropower output at time t, E Hyd,i represents the hydropower capacity of node i, p Hyd,t represents the total hydropower power at time t, I Hyd Indicates the set of hydropower nodes, p PV,i,t represents the photovoltaic power of node i at time t, P PV,t Represents the unit photovoltaic output power at time t, E PV,i represents the photovoltaic capacity of node i, p PV,t represents the total photovoltaic power at time t, I PV Indicates the set of photovoltaic nodes, E PV Represents photovoltaic capacity, E PV,i represents the photovoltaic capacity of node i, E PV,min represents the lower limit of the node photovoltaic capacity, E PV,max Indicates the upper limit of the node's photovoltaic capacity; The energy storage constraints are specifically: In the formula, E bat,i represents the energy storage capacity of node i, E bat,min Represents the lower limit of energy storage photovoltaic capacity, E bat,max represents the upper limit of energy storage photovoltaic capacity, p bat,i,t represents the discharge power of energy storage at node i at time t, p bat,t It represents the total energy storage discharge power at time t, I bat represents the set of energy storage nodes, E bat represents the energy storage capacity, p grid,i,t represents the purchased power of node i at time t, represents the average power purchased by node i at time t; The power flow constraint specifically represents: WITH ij ≤S max,ij ,IN min,i ≤U i ≤U max,i ; Where P i represents the active power of node i, U i represents the voltage amplitude of node i, G ij represents the conductance between nodes i and j, B ij represents the susceptance between nodes i and j, θ i represents the phase of node i, Q i represents the reactive power of node i, S ij represents the capacity between nodes i and j, S max,ij represents the upper limit of the capacity between nodes i and j, U max,i Indicates the voltage upper limit of node i, U min,i Indicates the lower voltage limit of node i.
8. A distribution network optimization planning system based on multi-objective collaboration, applied to a distribution network optimization planning method based on multi-objective collaboration according to any one of claims 1 to 7, characterized in that: include: A first module is used to establish a total objective function based on multiple collaborative objectives and constraints corresponding to the multiple collaborative objectives, wherein the multiple collaborative objectives include economic cost, charging distance and carbon emissions; The second module is used to obtain the power grid data of the distribution network to be planned, and use the power grid data and the overall objective function to establish a scenario model corresponding to the distribution network to be planned; The third module is used to solve the scenario model by using the NSGA-II algorithm to obtain the optimal solution of the scenario model of the distribution network to be planned, and use the optimal solution to optimize the planning of the distribution network to be planned.
9. An electronic device, characterized in that: The method comprises a memory, a processor and a computer program stored in the memory and executable on the processor, wherein the method according to any one of claims 1 to 7 is implemented when the processor executes the computer program.
10. A non-transitory computer-readable storage medium, characterized in that: The non-transitory computer-readable storage medium stores computer instructions, which enable a computer to execute the method of any one of claims 1-7.
Citation Information
Patent Citations
Charging network and power distribution network collaborative planning method considering guiding type charging control
CN110880755A
Site selection and optimal configuration method for microgrid comprising electric vehicle charging station
CN111310966A
Micro-grid multi-objective optimization method based on Tent chaotic mapping NSGA-II algorithm
CN116090325A
Wind, light, diesel, hydrogen and storage micro-grid multi-target double-layer optimization method and system
CN117650580A
Charging station recommendation system based on electric vehicle driving information and method therefor
KR102386343B1
Cited By
Urban heat supply system boundary condition optimization method and device based on multi-energy complementation
CN120278048A
Comprehensive optimization method of power supply power grid
CN121303450A