Engineering project purchase management system based on bim technology
Through the engineering project procurement management system based on BIM technology, the problem of supplier goods and evaluation in the existing technology is solved, and the procurement products are guaranteed to meet expectations and project progress, ensuring that the project is completed on schedule.
Patent Information
- Application Number
- CN202411138507.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-19
- Publication Date
- 2024-12-06
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
The existing technology integrates BIM with procurement business, without considering the supplier's goods and evaluation, resulting in the final purchased products that do not match expectations and affect the project progress.
A project procurement management system based on BIM technology was designed, including procurement management module, list generation module and terminal processing module. By building a BIM model, purchasing lists are generated, suppliers are screened, evaluation coefficients are calculated, and final suppliers are selected. And monitor the progress of the project in real time to determine whether a new round of procurement is needed.
Ensure that the purchased products meet expectations, ensure the quality of the project, avoid delays caused by untimely delivery of suppliers, and ensure that the project is completed within the preset period.
Smart Images

Figure CN119090584A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the field of engineering management, and relates to engineering project procurement management technology, in particular to an engineering project procurement management system based on BIM technology. Background Art
[0002] The BIM model is a three-dimensional digital model that integrates information such as the building's geometry, spatial relationships, material quantities, time plans and cost budgets; Project procurement management refers to the process and method of purchasing the required materials, equipment, engineering services, etc. according to project requirements and plans during the implementation of the project; Through meticulous procurement management, it can be ensured that procurement activities are carried out within the budget, including comparing the prices, quality and services of different suppliers, so as to select the most cost-effective option; Timely procurement and supply chain management can ensure that the funds required for the project are in place on time and avoid construction delays caused by material shortages; There are many risks in the procurement process, such as supplier default, price fluctuations, transportation delays, etc. Through procurement management, these potential risks can be identified, and corresponding response strategies and plans can be formulated to reduce the impact of risks on the project.
[0003] The prior art (invention patent application with publication number CN110097418A) discloses a project procurement platform and method based on BIM technology, the method comprising: BIM model modeling; uploading to the procurement platform through a lightweight plug-in tool; managing the BIM model in the procurement platform; adding the equipment to be purchased to the to-be-purchased library in the BIM model to achieve unified procurement; iterating the relevant contract information, supplier and price information to the BIM model to form a procurement list BIM model; dynamic visual management of project procurement under the BIM model to achieve deep integration of the BIM model and procurement business; however, the prior art integrates BIM with procurement business without considering the supplier's goods and evaluation, resulting in the final purchased products not meeting expectations, affecting the progress of the project.
[0004] The present invention provides a construction project procurement management system based on BIM technology to solve the above technical problems. Summary of the invention
[0005] The present invention aims to solve at least one of the technical problems existing in the prior art; to this end, the present invention proposes an engineering project procurement management system based on BIM technology, which is used to solve the technical problem that the prior art integrates BIM with procurement business, does not consider the goods and evaluation of suppliers, causes the final purchased products to be inconsistent with expectations, and affects the progress of the project.
[0006] To achieve the above-mentioned purpose, the first aspect of the present invention provides a project procurement management system based on BIM technology, comprising: a procurement management module, and a list generation module and a terminal processing module connected thereto;
[0007] List generation module: obtain the design drawings and parameters of the project, build the BIM model based on the design drawings and parameters; extract component information from the BIM model, and generate a purchase list based on the component information; the component information includes component name, quantity, specification and material
[0008] Procurement management module: screen several suppliers according to the procurement list, obtain supply information of several suppliers, calculate the evaluation coefficients of several suppliers; screen out the final supplier from the suppliers based on the evaluation coefficient; and,
[0009] Obtain product information of several components, divide the project into several project cycles, and match product information with several project cycles; obtain delivery information of final supplier products; monitor the progress of the project in real time to determine whether a new round of procurement is needed; if yes, generate a procurement processing signal; if no, continue to detect the progress of the project;
[0010] Terminal processing module: processes products based on procurement processing signals.
[0011] Preferably, constructing a BIM model according to the design drawings and parameters includes:
[0012] Retrieve the design drawings and parameters of the project; the design drawings include plan views, elevation views, and section views; the parameters include the size, material, and location of the components;
[0013] Select BIM modeling software, draw floor lines and grid lines according to the design drawings, draw several components in the BIM modeling software in sequence, set the parameters of the components according to the parameters, and obtain the BIM model.
[0014] The present invention constructs a BIM model according to engineering design drawings and parameters, lays a foundation for the subsequent generation of a purchase list, can link subsequent processing with the BIM model, and is conducive to monitoring the real-time situation of the engineering project.
[0015] Preferably, generating a purchase list according to component information includes:
[0016] Retrieve component information and determine whether the component information contains all types of information. If yes, retain the corresponding component information; if no, supplement the corresponding missing information.
[0017] The component information is numbered i according to the component name; the corresponding data types are arranged according to the component number to obtain a purchase list; wherein i = 1, 2, ..., n, and n is a positive integer.
[0018] The present invention generates component information according to the BIM model, analyzes the integrity of the component information according to the component information, and supplements the missing component information; and numbers the components according to the component names, which can facilitate the management of the component information and is conducive to the normal progress of subsequent procurement.
[0019] Preferably, the calculating of the evaluation coefficients of several suppliers includes:
[0020] Retrieve supply information of several suppliers; the supply information includes reputation score, product score and product type and quantity;
[0021] Divide several suppliers according to the purchase list and obtain supplier numbers ij; mark the reputation score, product score and number of product types as XFij, CFij and CSij respectively; where j represents the supplier number, j = 1, 2, ..., m, m is a positive integer;
[0022] The supplier's evaluation coefficient is calculated by the formula PXij=α×ln(CSij+1)+β×XFij+γ×CFij; wherein α, β and γ are proportional coefficients greater than 0.
[0023] The present invention evaluates the supply information of several suppliers, which can provide a basis for the subsequent selection of the final supplier, and is conducive to ensuring that the selected supplier meets expectations.
[0024] Preferably, the screening out the final supplier from the suppliers based on the evaluation coefficient includes:
[0025] Retrieving evaluation coefficients of several suppliers, dividing the several suppliers into a group according to the component names, and obtaining several groups of suppliers;
[0026] Suppliers in several groups are sorted from large to small according to the evaluation coefficients to obtain a supplier ranking table corresponding to each group; the supplier ranked first is selected from the supplier ranking table, and several suppliers are integrated to obtain the final supplier.
[0027] The present invention divides suppliers according to component names, selects the supplier with the highest evaluation coefficient from each group of components as the final supplier, and can select a different supplier for each component, which is conducive to providing products that meet expectations and ensure the quality of the project.
[0028] Preferably, the engineering project is divided into several project cycles, including:
[0029] Obtain the time of sub-projects in the engineering project from the database, calculate the average time of the same sub-projects, and use the average time as the basis for division;
[0030] The engineering sequence of the sub-projects is obtained, and the average values are sorted according to the engineering sequence to obtain several project cycles corresponding to the engineering projects.
[0031] The present invention obtains the time of several sub-projects in the engineering project, takes the average value of the same sub-project as the corresponding project cycle, and integrates several project cycles according to the engineering sequence of the sub-projects to obtain a complete project cycle, which can facilitate the subsequent monitoring of the progress of the engineering project and is conducive to the segmented management of the engineering project.
[0032] Preferably, matching the product information with a plurality of project cycles comprises:
[0033] Retrieve several project cycles and corresponding sub-projects, extract the delivered product information; match the product information with the sub-projects, and obtain the project product tables corresponding to several sub-projects;
[0034] According to the project cycle corresponding to the sub-project, the product information in the project product table is divided into the corresponding project cycle.
[0035] The present invention matches product information with several project cycles, can provide a basis for whether subsequent procurement is needed, and is conducive to monitoring the progress of the project.
[0036] Preferably, the determining whether a new round of procurement is needed includes:
[0037] Retrieve product information corresponding to several project cycles, extract delivery information, and match the delivery information with the product information to obtain a delivery matching table;
[0038] Before the subproject starts, determine whether all subproject components have been delivered based on the delivery matching table. If yes, analyze the next subproject; if not, determine that a new round of procurement is needed;
[0039] The progress of the sub-project is checked. When the sub-project progress reaches the preset progress, it is determined according to the delivery matching table whether all components of the next project cycle have been delivered. If yes, it is determined that a new round of procurement is not needed; if not, it is determined that a new round of procurement is needed.
[0040] The present invention analyzes whether the procurement of components in the engineering cycle has been completed, which can ensure the normal progress of the project. When the engineering process enters the preset process, it analyzes whether the components of the next project cycle have been delivered, which can ensure the normal progress of the next project, which is beneficial to ensure the progress rate of the engineering project and ensure that the engineering project is completed within the preset period.
[0041] Preferably, the processing of the product based on the purchase processing signal includes:
[0042] Retrieve the procurement processing signal, and negotiate with the final supplier to set the delivery deadline based on the procurement processing signal; test the delivery deadline, and re-screen the suppliers when the final supplier fails to deliver within the delivery deadline.
[0043] The present invention detects the delivery deadline of the supplier. When the supplier fails to deliver on time, a new supplier is selected, which can avoid the delay of the project due to the supplier's untimely delivery, and is conducive to ensuring the normal progress of the project.
[0044] Compared with the prior art, the present invention has the following beneficial effects:
[0045] 1. The present invention constructs a BIM model according to the engineering design drawings and parameters, which lays a foundation for the subsequent generation of a purchase list, can link subsequent processing with the BIM model, and is conducive to monitoring the real-time situation of the engineering project; generates component information according to the BIM model, analyzes the integrity of the component information according to the component information, and supplements the missing component information; numbers the components according to the component names, which can facilitate the management of the component information and is conducive to the normal progress of subsequent procurement; evaluates the supply information of several suppliers, divides the suppliers according to the component names, selects the supplier with the highest evaluation coefficient from each group of components as the final supplier, and can select different suppliers for each component, which is conducive to providing products that meet expectations and ensure the quality of the project.
[0046] 2. The present invention obtains the time of several sub-projects in the engineering project, takes the average value of the same sub-project as the corresponding project cycle, and integrates several project cycles according to the engineering sequence of the sub-projects to obtain a complete project cycle, which can facilitate the subsequent monitoring of the progress of the engineering project and is conducive to the segmented management of the engineering project; matching product information with several project cycles can provide a basis for whether subsequent procurement is needed, which is conducive to monitoring the progress of the project; analyzing whether the procurement of components in the engineering cycle is completed can ensure the normal progress of the project. When the engineering process enters the preset process, analyzing whether the components of the next project cycle are delivered can ensure the normal progress of the next project, which is conducive to ensuring the progress rate of the engineering project and ensuring that the engineering project is completed within the preset period; detecting the delivery deadline of the supplier. When the supplier fails to deliver on time, reselecting the supplier can avoid the delay of the engineering project due to the supplier's untimely delivery, which is conducive to ensuring the normal progress of the project. BRIEF DESCRIPTION OF THE DRAWINGS
[0047] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0048] Figure 1 It is a schematic diagram of the specific steps of the present invention;
[0049] Figure 2 A schematic diagram of the steps for selecting a supplier for the present invention;
[0050] Figure 3 It is a schematic diagram of the engineering component procurement monitoring steps of the present invention. DETAILED DESCRIPTION
[0051] The technical solution of the present invention will be clearly and completely described below in conjunction with the embodiments. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0052] See also Figure 1 The first aspect of the present invention provides a BIM-based engineering project procurement management system, including: a procurement management module, and a list generation module and a terminal processing module connected thereto;
[0053] List generation module: obtain the design drawings and parameters of the project, build the BIM model based on the design drawings and parameters; extract component information from the BIM model, and generate a purchase list based on the component information; the component information includes component name, quantity, specification and material
[0054] Procurement management module: screen several suppliers according to the procurement list, obtain supply information of several suppliers, calculate the evaluation coefficients of several suppliers; screen out the final supplier from the suppliers based on the evaluation coefficient; and,
[0055] Obtain product information of several components, divide the project into several project cycles, and match product information with several project cycles; obtain delivery information of final supplier products; monitor the progress of the project in real time to determine whether a new round of procurement is needed; if yes, generate a procurement processing signal; if no, continue to detect the progress of the project;
[0056] Terminal processing module: processes products based on procurement processing signals.
[0057] See also Figure 2 , obtain the design drawings and parameters of the engineering project, where the design drawings include plan views, elevation views, and section views; the parameters include the size, material, and position of the components; select BIM modeling software, draw floor lines and grid lines according to the design drawings, draw several components in the BIM modeling software in turn, set the parameters of the components according to the parameters, and obtain the BIM model.
[0058] For example: Assuming that there is a design drawing and parameters of an engineering project, select BIM software Revit / ArchiCAD to draw the project, set the parameters of the components according to the parameters, and finally get the BIM model.
[0059] Extract component information from the BIM model, and determine whether the component information contains all types of information. If yes, retain the corresponding component information; if not, supplement the corresponding missing information; number the component information i according to the component name; arrange the corresponding data types according to the component number to obtain a purchase list; where i = 1, 2, ..., n, and n is a positive integer.
[0060] For example, suppose three sets of component information are extracted from the BIM model, and the integrity of the component information is judged. It is found that the second set of data is missing the material of the component; then the component material of the second set of data is supplemented;
[0061] According to the collected results, the component information is sorted and numbered as 1, 2, and 3.
[0062] Filter several suppliers according to the purchase list, obtain the supply information of several suppliers, divide several suppliers according to the purchase list, and obtain the supplier number ij; mark the reputation score, product score and the number of product types as XFij, CFij and CSij respectively; where j represents the supplier number, j=1,2,…,m, m is a positive integer; calculate the supplier evaluation coefficient through the formula PXij=α×ln(CSij+1)+β×XFij+γ×CFij; where α, β and γ are proportional coefficients greater than 0.
[0063] For example: suppose that the suppliers of component 2 are screened and three suppliers are selected; α=10,β=0.5,γ=0.5; the supply information of the three suppliers is obtained as follows:
[0064] First supplier: reputation score XF21 = 94; product score CF21 = 89; number of product types CS21 = 5; then the evaluation coefficient PX21 = 109.42;
[0065] The second supplier: reputation score XF22 = 97; product score CF22 = 93; number of product types CS22 = 3; then the evaluation coefficient PX22 = 108.86;
[0066] The third supplier: reputation score XF23=96; product score CF23=92; number of product types CS23=6; then the evaluation coefficient PX23=113.46.
[0067] Divide several suppliers into a group according to the component name to obtain several groups of suppliers; sort the suppliers in the several groups from large to small according to the evaluation coefficients to obtain a supplier ranking table corresponding to each group; select the supplier ranked first from the supplier ranking table, and integrate several suppliers to obtain the final supplier.
[0068] For example: suppose the suppliers of component 2 are sorted from large to small according to the evaluation coefficient, and the supplier ranking table obtained is supplier 3, supplier 1, supplier 2; then supplier 3 is selected as the final supplier of component 2.
[0069] See also Figure 3 , obtain the time of sub-projects in the engineering project from the database, calculate the average time of the same sub-project, and use the average time as the basis for division; obtain the engineering sequence of the sub-projects, sort the average time according to the engineering sequence to obtain several project cycles corresponding to the engineering project.
[0070] For example: Assume that sub-projects A, B, and C are divided, and the average time of the sub-projects is calculated to be 2 months, 1 month, and 1.5 months;
[0071] The sub-projects are arranged in order: sub-project A takes 2 months to construct, sub-project B takes 1 month to construct, and sub-project C takes 1.5 months to construct.
[0072] Obtain product information of several components, retrieve several project cycles and corresponding sub-projects; match product information with sub-projects to obtain project product tables corresponding to several sub-projects; and divide product information in the project product table into corresponding project cycles according to the project cycles corresponding to the sub-projects.
[0073] For example: suppose that the products of sub-project A and sub-project B are matched, and the matching components of sub-project A are components 3, 7, 8, 9, 10 and 11; the matching components of sub-project B are components 2, 6, 14 and 17; fill in the quantity, material and final supplier of the corresponding components into the project product table.
[0074] Retrieve product information corresponding to several project cycles, extract delivery information, match the delivery information with the product information to obtain a delivery matching table; before the start of a sub-project, determine whether all components of the sub-project have been delivered based on the delivery matching table. If so, analyze the next sub-project; if not, generate a procurement processing signal; detect the progress of the sub-project, and when the sub-project progress reaches the preset progress, determine whether all components of the next project cycle have been delivered based on the delivery matching table. If so, continue to detect the engineering progress; if not, generate a procurement processing signal.
[0075] For example: Assuming that the delivery of the product is checked before the start of sub-project A, and all components of sub-project A are delivered, then construction of sub-project A begins; when the construction reaches 1.8 months, the delivery of sub-project B is checked, and it is found that component 6 has not been delivered, then a procurement processing signal is generated.
[0076] Retrieve the procurement processing signal, and negotiate with the final supplier to set the delivery deadline based on the procurement processing signal; test the delivery deadline, and re-screen the suppliers when the final supplier fails to deliver within the delivery deadline.
[0077] For example: Assume that according to the procurement processing information, the delivery period of component 6 is negotiated to be set at 10 days with the final supplier. The delivery is checked on 10 days and it is found that the final supplier of component 6 has delivered the component. Then the delivery information of the sub-project is continuously checked.
[0078] Part of the data in the above formula is calculated by removing the dimension and taking its numerical value. The formula is a formula closest to the actual situation obtained by software simulation of a large amount of collected data; the preset parameters and preset thresholds in the formula are set by technical personnel in this field according to actual conditions or obtained through simulation of a large amount of data.
[0079] Working principle of the present invention: The present invention obtains design drawings and parameters of the engineering project, and constructs a BIM model according to the design drawings and parameters; extracts component information from the BIM model, and generates a purchase list according to the component information; screens several suppliers according to the purchase list, obtains supply information of several suppliers, and calculates evaluation coefficients of several suppliers; screens out the final supplier from the suppliers based on the evaluation coefficient; obtains product information of several components, divides the engineering project into several project cycles, and matches product information with several project cycles; obtains delivery information of the final supplier's products; monitors the progress of the engineering project in real time to determine whether a new round of procurement is needed; if yes, generates a procurement processing signal; if not, continuously detects the progress of the engineering project; processes the product based on the procurement processing signal.
[0080] The above embodiments are only used to illustrate the technical method of the present invention rather than to limit it. Although the present invention has been described in detail with reference to the preferred embodiments, those skilled in the art should understand that the technical method of the present invention may be modified or replaced by equivalents without departing from the spirit and scope of the technical method of the present invention.
Claims
1. A project procurement management system based on BIM technology, characterized in that: include: Procurement management module, and its connected list generation module and terminal processing module; List generation module: obtains the design drawings and parameters of the engineering project, builds the BIM model based on the design drawings and parameters; extracts component information from the BIM model, and generates a purchase list based on the component information; the component information includes component name, quantity, specifications, and material Procurement management module: screen several suppliers according to the purchase list, obtain supply information of several suppliers, calculate the evaluation coefficients of several suppliers; screen out the final supplier from the suppliers based on the evaluation coefficients; and, Obtain product information for several components, divide the project into several project cycles, and match product information with the project cycles; obtain delivery information for final supplier products; monitor the progress of the project in real time to determine whether a new round of procurement is needed; if so, generate a procurement processing signal; if not, continue to monitor the progress of the project; Terminal processing module: processes products based on procurement processing signals.
2. The engineering project procurement management system based on BIM technology according to claim 1 is characterized in that: The construction of the BIM model according to the design drawings and parameters includes: Retrieve the design drawings and parameters of the engineering project; the design drawings include plan views, elevation views, and cross-section views; the parameters include the size, material, and location of components; Select BIM modeling software, draw floor lines and grid lines according to the design drawings, draw several components in sequence in the BIM modeling software, set the parameters of the components according to the parameters, and obtain the BIM model.
3. The engineering project procurement management system based on BIM technology according to claim 2 is characterized in that: Generating a purchase list according to component information includes: Retrieve component information and determine whether the component information contains all types of information. If yes, retain the corresponding component information; if not, supplement the corresponding missing information. The component information is numbered i according to the component name; the corresponding data types are arranged according to the component number to obtain a purchase list; wherein i = 1, 2, ..., n, and n is a positive integer.
4. The engineering project procurement management system based on BIM technology according to claim 1 is characterized in that: The calculation of evaluation coefficients of several suppliers includes: Retrieve supply information from several suppliers, including reputation scores, product ratings, and product types and quantities; Divide several suppliers according to the purchase list and obtain supplier numbers ij; mark the reputation score, product score and number of product types as XFij, CFij and CSij respectively; where j represents the supplier number, j = 1, 2, ..., m, m is a positive integer; The supplier's evaluation coefficient is calculated using the formula PXij = α × ln (CSij + 1) + β × XFij + γ × CFij; where α, β and γ are proportional coefficients greater than 0.
5. The engineering project procurement management system based on BIM technology according to claim 4 is characterized in that: The final supplier is selected from the suppliers based on the evaluation coefficient, including: Retrieving evaluation coefficients of several suppliers, dividing the suppliers into a group according to component names, and obtaining several groups of suppliers; The suppliers in several groups are sorted from large to small according to the evaluation coefficient to obtain a supplier ranking table corresponding to each group; the supplier ranked first is selected from the supplier ranking table, and several suppliers are integrated to obtain the final supplier.
6. The engineering project procurement management system based on BIM technology according to claim 1 is characterized in that: The engineering project is divided into several project cycles, including: Obtain the time of sub-projects in the engineering project from the database, calculate the average time of the same sub-projects, and use the average as the basis for division; Obtain the engineering sequence of the sub-projects, sort the average values according to the engineering sequence, and obtain several project cycles corresponding to the engineering projects.
7. The engineering project procurement management system based on BIM technology according to claim 1 is characterized in that: The product information is matched with several project cycles, including: Retrieve several project cycles and corresponding sub-projects, extract delivered product information; match product information with sub-projects to obtain project product tables corresponding to several sub-projects; According to the project cycle corresponding to the sub-project, the product information in the project product table is divided into the corresponding project cycle.
8. The engineering project procurement management system based on BIM technology according to claim 1 is characterized in that: The determination of whether a new round of procurement is necessary includes: Retrieve product information corresponding to several project cycles, extract delivery information, and match the delivery information with the product information to obtain a delivery matching table; Before a subproject begins, determine whether all subproject components have been delivered based on the delivery matching table. If so, analyze the next subproject; if not, determine that a new round of procurement is needed. Check the progress of the sub-project. When the sub-project progress reaches the preset progress, determine whether all components of the next project cycle have been delivered based on the delivery matching table. If so, it is determined that a new round of procurement is not needed; if not, it is determined that a new round of procurement is needed.
9. The engineering project procurement management system based on BIM technology according to claim 8 is characterized in that: The processing of the product based on the purchase processing signal includes: Retrieve the procurement processing signal and negotiate with the final supplier to set the delivery deadline based on the procurement processing signal; check the delivery deadline, and re-screen the suppliers when the final supplier fails to deliver within the delivery deadline.
Citation Information
Patent Citations
Engineering project purchase platform and method based on BIM technology
CN110097418A
Cited By
Engineering cycle management method and system based on BIM
CN122222210A
A bim-based engineering cycle management method and system
CN122222210B