5G multi-carrier frequency power amplifier base station amplification system optimization method
By obtaining the operator's estimated cost and geographical information, using personnel distribution maps and building distribution information to divide the area, determine the number and location of remote units, and generate an optimized 5G multi-carrier amplifier base station amplification system construction plan, solving the existing technology The problems of slow planning speed and high cost achieve efficient solution generation and appropriate communication quality.
Patent Information
- Application Number
- CN202410894244.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-04
- Publication Date
- 2024-12-06
- Estimated Expiration
- 2044-07-04
AI Technical Summary
During the construction process, the existing 5G multi-carrier amplifier base station amplification system has problems such as slow planning speed, high labor consumption, and the inability to formulate suitable construction plans based on operators and users' needs. The communication quality may decline when the number of remote units is large, and the cost is Higher.
By obtaining the operator's estimated cost and geographical information, using personnel distribution maps and building distribution information to divide the areas to be built, determining the number and location of remote units, generating an optimized construction plan, and automatically calculating the appropriate construction plan to reduce labor costs. And improve planning efficiency.
The construction plan for the amplification system of the 5G multi-carrier frequency amplifier base station has been realized, which reduces labor costs, improves planning efficiency, and generates suitable construction plans based on actual conditions to meet the needs of operators and users.
Smart Images

Figure CN119095066A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of wireless communications, and in particular to a 5G multi-carrier frequency power amplifier base station system optimization method. Background Art
[0002] With the rapid development of mobile communication networks, we have quietly entered the 5G network era. Although mobile communication networks have been covered relatively comprehensively in many areas and the signals of mobile communication networks can also support local users, it is limited to 4G networks. For users who need 5G networks, the current coverage of 5G networks obviously cannot meet the needs of current users. The cost of re-establishing a new base station in areas where 5G networks are not covered will be relatively high. To solve this problem, the 5G multi-frequency power amplifier base station amplification system came into being.
[0003] The 5G multi-frequency power amplifier base station amplification system is a network coverage system that uses wired coupling of base station signals and digital transmission for wireless network coverage. It consists of a remote unit and a near-end unit. The near-end unit forwards the signal sent by the base station to the remote unit, and then the remote unit forwards the signal to users near the remote unit. Similarly, the remote unit can receive the signal sent by the user and send it to the near-end unit, which is then sent to the base station by the near-end unit, thereby achieving the effect of expanding the base station 5G network coverage area without building a new base station.
[0004] However, at present, there are the following problems in achieving 5G network coverage by building a 5G multi-carrier frequency power amplifier base station amplification system: 1. When constructing a 5G multi-carrier frequency power amplifier base station amplification system, since the system consists of two parts, the remote unit and the near-end unit, and the number of near-end units can be adjusted according to actual needs, and the number of near-end units, the location information of each near-end unit, and the connection information of each near-end unit are different, the construction plan of the multi-carrier frequency power amplifier base station amplification system will be different, and the effects produced after construction according to the construction plan will also be different (including cost and communication quality, etc.), and currently, since the construction plan is manually planned by engineers and the construction plan involves more content, the planning speed of the construction plan is relatively slow and consumes a lot of manpower.
[0005] 2. The more remote units there are, the larger the coverage area of the 5G network will be. At the same time, the communication quality may decline (for example, the delay will be longer) and the cost will be higher. That is, it is currently impossible to develop a 5G multi-carrier frequency power amplifier base station amplification system suitable for local actual conditions based on the needs of operators and users. Summary of the invention
[0006] In order to solve the above problems, the present invention provides a 5G multi-carrier frequency power amplifier base station amplification system optimization method, which adopts the following technical solutions: A 5G multi-carrier frequency power amplifier base station amplification system optimization method, comprising: Step S101, obtaining the estimated cost of the current operator and the geographical information of the area to be constructed, the personnel distribution map of the area to be constructed, and the location information of the base station corresponding to the area to be constructed, wherein the area to be constructed is the area where the 5G multi-carrier frequency power amplifier base station amplification system is currently required to be constructed; Step S102, determining the location information of the base station corresponding to the area to be constructed as the proximal location information of the proximal unit of the 5G multi-carrier frequency power amplifier base station amplification system, and dividing the area to be constructed based on the personnel distribution map to obtain a plurality of sub-areas to be constructed, and each sub-area to be constructed has a corresponding importance level; Step S103, sorting the multiple sub-areas to be constructed based on the importance levels to obtain a first sorting result; Step S104, obtaining the construction cost of a single remote unit; Step S105, determining a target sub-region according to the first sorting result, wherein the target sub-region is a sub-region to be constructed that has not been subjected to step S106; Step S106, determining the number of remote units corresponding to the target sub-area, the remote position information corresponding to each remote unit, and the connection information based on the geographic information of the target sub-area and the proximal position information, generating and storing a sub-construction plan for the target sub-area; Step S107, determining the regional construction cost corresponding to the target sub-region based on the number of the remote units, the construction cost and the connection information; Step S108, determining the total regional construction cost of all target sub-regions that have currently executed step S107 based on the regional construction cost, and judging whether the total regional construction cost reaches the estimated cost; Step S109: if not reached, re-execute step S105 until the target sub-area does not exist in the first sorting result, and generate a construction plan based on the sub-construction plan stored in step S106; Step S110: if reached, a construction plan is generated based on the sub-construction plan stored in step S106.
[0007] In another possible implementation manner, obtaining a personnel distribution map of the area to be constructed includes: Obtaining usage of the mobile network in the area to be constructed within a preset time period; A personnel distribution map of the area to be constructed is generated based on the usage situation.
[0008] In another possible implementation, the personnel distribution map is displayed in a single color, and the darker the color, the larger the population. The area to be constructed is divided based on the personnel distribution map to obtain multiple sub-areas to be constructed, and each sub-area to be constructed has a corresponding importance level, including: grayscale the personnel distribution map to obtain an initial grayscale image; Performing Gaussian filtering on the grayscale image to remove noise and obtain a final grayscale image; Using the Sobel algorithm to perform edge processing on the ultimate grayscale image, dividing the area to be constructed into a plurality of sub-areas to be constructed; Calculate the average grayscale value corresponding to each sub-area to be constructed; The importance level of each sub-area to be constructed is determined based on the average gray value.
[0009] In another possible implementation, the geographic information includes building distribution information and signal influencing source information, and determining the number of remote units corresponding to the target sub-area, remote location information corresponding to each remote unit, and connection information based on the geographic information of the target sub-area and the proximal location information includes: Determine a plurality of candidate locations from the target sub-area based on the building distribution information, the candidate locations being locations where the remote unit can be established; Calculate the coverage area of the remote unit at each candidate location based on the signal influencing source information; determining remote location information for establishing a remote unit from the plurality of candidate locations based on the coverage area; The number of remote units and connection information are determined based on the remote location information and the near-end location information.
[0010] In another possible implementation, the signal influencing source information includes a signal influencing source type and an influencing factor corresponding to the signal source type, and calculating the coverage area of the remote unit at any candidate position based on the signal influencing source information includes: Determine the type of signal influencing source corresponding to any candidate position; Obtaining the ideal coverage area of the remote unit in an ideal state; The coverage area of the remote unit at any of the candidate positions is calculated based on the impact factor corresponding to the signal impact source type and the ideal coverage area.
[0011] In another possible implementation manner, determining the remote location information for establishing the remote unit from the multiple candidate locations based on the coverage area includes: Step Sa, calculating the overlapping area and the exclusive area corresponding to each current candidate position based on the coverage area, and calculating the overlapping rate corresponding to each candidate position based on the overlapping area and the coverage area corresponding to each candidate position, wherein the overlapping area represents the area when the coverage areas corresponding to at least two candidate positions overlap; Step Sb, based on the exclusive area, the overlap rate, the preset overlap rate threshold and the preset area threshold, determining whether there is a position to be eliminated among the multiple candidate positions, if not, determining the current multiple candidate positions as the remote unit position information, if yes, continuing to execute steps Sc to step Sd, the position to be eliminated is a candidate position whose exclusive area does not reach the preset area threshold and whose overlap rate reaches the preset overlap rate threshold; Step Sc, determining the number of the positions to be eliminated. If the number is 1, directly eliminating the positions to be eliminated from the multiple candidate positions, and determining that other candidate positions in the multiple candidate positions are remote position information. If the number is not 1, continuing to execute step Sd; Step Sd: determine the position to be eliminated with the smallest exclusive area from at least two positions to be eliminated, eliminate the position to be eliminated, and continue to execute step Sa.
[0012] In another possible implementation manner, determining the number and connection information of remote units based on the remote location information and the near-end location information includes: Step Sf, determining the number of the remote units according to the number of remote location information determined; Step Sg, determining whether the number is greater than 1, if not, directly determining that the connection information of the remote unit is connected to the near-end unit, if yes, continuing to execute step Sh; Step Sh, determining a first distance value corresponding to each remote unit based on the remote position information and the near-end position information, wherein the first distance value is a distance value between the remote unit and the near-end unit; Step S1, sorting the remote units based on the first distance values to obtain a third sorting result, wherein the remote unit at the first position in the third sorting result has the smallest first distance value; Step Sj, based on the third sorting result, calculating the difference between the first distance values corresponding to every two adjacent remote units; Step Sk, determining whether there is a difference reaching a preset difference among the differences corresponding to each two adjacent remote units, if not, directly determining the connection information of the plurality of remote units as being connected to the near-end unit, if yes, continuing to execute step S1; Step S1, classifying the remote units in the third sorting result based on the difference value to obtain the level number corresponding to each remote unit and the total level number corresponding to the current target sub-region, wherein the smaller the level number, the smaller the corresponding first distance value; Step Sm, determining the connection information of the first-level remote unit to be connected to the proximal unit, and determining the first-level remote unit as the upper-level unit, the first-level remote unit being a remote unit with a level number of one; Step Sn, increasing the level number corresponding to the upper level unit by 1 to obtain the current level number, and determining the remote unit corresponding to the current level number as the unit to be determined; Step So, determining the number of the upper level units; Step Sp, determining whether the number of the upper-level unit is 1, and if so, determining that the connection information of the current unit to be determined is connected to the upper-level unit; Step Sq: if not, then calculate the distance between each unit to be determined and each upper-level unit to obtain a second distance value, wherein each unit to be determined corresponds to at least two second distance values; Step Sr, determining the connection information of each to-be-determined unit based on the second distance value; Step St, determining whether the current level number reaches the total level number; Step Su, if yes, then the loop ends; Step Sv: If not, the unit to be determined is re-determined as the upper-level unit, and step Sn is continued.
[0013] In summary, the present application includes at least one of the following beneficial technical effects: 1. Engineers only need to input relevant information (estimated cost, geographical information of the area to be built, construction cost and other parameter information, which are not listed here one by one), and the computer can automatically calculate the construction plan for the area where the 5G multi-carrier frequency power amplifier base station amplification system is currently required, reducing labor costs and improving the planning efficiency of the construction plan; 2. Based on the estimated cost input by the operator and the actual situation of the area to be built, a construction plan for a 5G multi-carrier frequency power amplifier base station amplification system suitable for the current actual situation was calculated. BRIEF DESCRIPTION OF THE DRAWINGS
[0014] Figure 1 It is a flow chart of a 5G multi-carrier frequency power amplifier base station amplification system optimization method in an embodiment of the present application.
[0015] Figure 2 This is an example diagram of possible distribution of remote units in a target sub-area in an embodiment of the present application.
[0016] Figure 3 This is another example diagram of possible distribution of remote units in a target sub-area in an embodiment of the present application. DETAILED DESCRIPTION
[0017] The present application is further described in detail below in conjunction with the accompanying drawings.
[0018] After reading this specification, those skilled in the art may make non-creative modifications to this embodiment as needed, but such modifications are protected by patent law as long as they are within the scope of the claims of this application.
[0019] In order to make the purpose, technical solution and advantages of the embodiments of the present application clearer, the technical solution in the embodiments of the present application will be clearly and completely described below in conjunction with the drawings in the embodiments of the present application. Obviously, the described embodiments are part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of this application.
[0020] In addition, the term "and / or" in this article is only a description of the association relationship of associated objects, indicating that there can be three relationships. For example, A and / or B can represent: A exists alone, A and B exist at the same time, and B exists alone. In addition, the character " / " in this article, unless otherwise specified, generally means that the associated objects before and after are in an "or" relationship.
[0021] The embodiments of the present application are further described in detail below in conjunction with the drawings in the specification.
[0022] like Figure 1 As shown, the embodiment of the present application provides a 5G multi-carrier frequency power amplifier base station amplification system optimization method, the method comprising: Step S101, obtaining the estimated cost of the current operator, the geographical information of the area to be built, the personnel distribution map of the area to be built, and the location information of the base stations corresponding to the area to be built.
[0023] Among them, the area to be constructed is the area where 5G multi-carrier frequency power amplifier base station amplification system needs to be built.
[0024] For the embodiment of the present application, the estimated cost is a budget acceptable to the operator, the area to be constructed is an area where the base station can provide 4G network but cannot be covered by 5G network, and the personnel distribution map represents the personnel distribution situation in the current area to be constructed. Since the 4G network coverage has been achieved in the area to be constructed, it is possible to obtain the usage of the mobile network, i.e., the 4G network, in the area to be constructed within a preset time period, and generate a personnel distribution map of the area to be constructed based on the usage. The greater the usage of the mobile network in a certain area in the area to be constructed, the larger the number of users in the area and the greater the demand for network use. Among them, the preset time period is a time period determined in advance by engineers according to needs, which can be one week or half a month, and is not limited here.
[0025] In step S102, the location information of the base station corresponding to the area to be constructed is determined as the proximal location information of the proximal unit of the 5G multi-carrier power amplifier base station amplification system, and the area to be constructed is divided based on the personnel distribution map to obtain multiple sub-areas to be constructed and each sub-area to be constructed has a corresponding importance level.
[0026] For the embodiments of the present application, in the 5G multi-carrier frequency power amplifier base station amplification system, the proximal unit is installed on the base station, so the location information of the base station corresponding to the area to be constructed can be directly determined as the location information of the proximal unit, that is, the proximal location information.
[0027] Furthermore, when covering the area to be built with 5G network, it may not be possible to fully cover it due to budget issues. Therefore, by dividing the area to be built into sub-areas and determining different importance levels, more people in the area to be built can use the 5G network within a limited budget. Specifically, when generating a personnel distribution map based on the use of the mobile network, a monochrome display can be used. The darker the color, the larger the population and the greater the demand for 5G network. Therefore, when dividing the area to be built based on the personnel distribution map, obtaining multiple sub-areas to be built and each sub-area to be built has a corresponding importance level, it can be specifically achieved in the following ways: The personnel distribution map is grayed to obtain an initial gray image. The gray image is Gaussian filtered to remove noise and obtain an ultimate gray image. The ultimate gray image is edge processed using the Sobel algorithm. The area to be constructed is divided into multiple sub-areas to be constructed. The average gray value corresponding to each sub-area to be constructed is calculated. The higher the average gray value, the fewer people are distributed. The importance level of each sub-area to be constructed is determined based on the average gray value, thereby achieving the effect of determining the importance level of each sub-area to be constructed.
[0028] Step S103, sorting the multiple sub-areas to be constructed based on the importance level to obtain a first sorting result, wherein the greater the importance level, the more personnel are distributed, and the first sub-area to be constructed in the first sorting result has the highest importance level.
[0029] Step S104, obtaining the construction cost of a single remote unit.
[0030] Step S105 , determining a target sub-region according to the first sorting result, where the target sub-region is a sub-region to be constructed that has not been subjected to step S106 .
[0031] Step S106, based on the geographic information and proximal location information of the target sub-area, determine the number of remote units corresponding to the target sub-area, the remote location information and connection information corresponding to each remote unit, generate and store a sub-construction plan for the target sub-area.
[0032] For the embodiments of the present application, geographic information includes building distribution information and signal influencing source information. Signal influencing source information refers to factors that may affect signal transmission, specifically including signal influencing source types and influencing factors corresponding to signal influencing source types. Signal influencing source types refer to the types of objects that affect mobile network signals. Influencing factors characterize the degree of influence of objects of the signal influencing source type on mobile network signals. Signal influencing source types and influencing factors can be set by engineers based on experience. For example, signal influencing source types can be residential buildings, construction areas, railways, etc., and the influencing factors corresponding to each type are formulated by engineers.
[0033] Specifically, the specific implementation process of determining the number of remote units corresponding to the target sub-area, the remote location information corresponding to each remote unit, and the connection information based on the geographic information of the target sub-area and the proximal location information includes: Step S1061: determine multiple candidate locations from the target sub-area based on the building distribution information.
[0034] For the embodiments of the present application, the building distribution information characterizes the distribution of buildings. The buildings in the present application are buildings (including residential buildings, office buildings, shopping malls, etc.), and do not include ornamental buildings such as rockery. The candidate location is a location where a remote unit can be established. There is a building near the candidate location and the candidate location can accommodate the remote unit. Therefore, multiple candidate locations are determined from the target sub-area based on the building distribution information, so that the specific location for installing the remote unit can be determined from the candidate locations later, thereby achieving the effect of narrowing the scope of determining the remote location information.
[0035] Step S1062: Calculate the coverage area of the remote unit at each candidate position based on the signal influencing source information.
[0036] For the sake of clarity in the description of the embodiment of the present application, the calculation process of the coverage area of a single candidate position is described in the embodiment of the present application (the calculation method of the coverage area of other candidate positions also adopts the following method, which will not be described in detail here), specifically including: Step S10621, determining the type of signal influencing source corresponding to any candidate position.
[0037] For the embodiment of the present application, the signal influencing source type represents the type of object that exists around the current candidate location and affects the propagation of the mobile network signal. Different types have different corresponding impacts, that is, different influencing factors.
[0038] Step S10622, obtaining the ideal coverage area of the remote unit in an ideal state.
[0039] For the embodiments of the present application, the ideal state refers to the state when the remote unit is not affected by any external factors, and the ideal coverage area refers to the area that the signal of the remote unit can cover in the ideal state.
[0040] Step S10623, based on the impact factor corresponding to the signal impact source type and the ideal coverage area, calculate the coverage area of the remote unit at any candidate position.
[0041] For the embodiments of the present application, specifically, the ideal coverage area and the influencing factor may be multiplied to obtain the actual corresponding coverage area when the remote unit is installed at the candidate position, thereby determining the coverage area.
[0042] Step S1063: Determine remote location information for establishing a remote unit from a plurality of candidate locations based on the coverage area.
[0043] For the embodiment of the present application, the specific implementation process of determining the remote location information for establishing the remote unit from multiple candidate locations based on the coverage area includes: Step Sa, calculating the overlapping area and exclusive area corresponding to each current candidate position based on the coverage area, and calculating the overlapping rate corresponding to each candidate position based on the overlapping area and the coverage area corresponding to each candidate position.
[0044] For the embodiments of the present application, the overlapping area represents the area when the coverage areas corresponding to at least two candidate positions overlap, and the exclusive area is the area of the coverage area corresponding to the candidate position excluding the overlapping area. There may be overlapping areas in the coverage area corresponding to each candidate position. When the overlapping area does not exist, the corresponding overlapping area is 0, and when the overlapping area exists, the corresponding overlapping area is the area corresponding to the overlapping area. Therefore, the overlapping area corresponding to each candidate position can be calculated according to the coverage area, and the exclusive area corresponding to each candidate position can be calculated based on the coverage area and the overlapping area. The coverage area corresponding to any candidate position is determined according to the coverage area corresponding to the candidate position, and then the overlapping area is divided by the coverage area to obtain the overlap rate corresponding to the candidate position.
[0045] Step Sb, based on the exclusive area, the overlap rate, the preset overlap rate threshold and the preset area threshold, determine whether there is a position to be eliminated among the multiple candidate positions. If not, determine the current multiple candidate positions as the remote unit position information. If so, continue to execute steps Sc to step Sd.
[0046] For the embodiments of the present application, the preset overlap rate threshold and the preset area threshold are thresholds set in advance and can be manually set by engineers. The preset overlap rate threshold is a standard indicating a larger overlap rate, and the preset area threshold is a standard indicating a smaller exclusive area. The position to be eliminated is a candidate position whose exclusive area does not reach the preset area threshold and whose overlap rate reaches the preset overlap rate threshold, indicating that the candidate position has a smaller exclusive area and more overlapping areas with other candidate positions, that is, the area covered by the position to be eliminated can be covered by other candidate positions. Therefore, when there is a position to be eliminated among multiple candidate positions, it means that there is a position that can be eliminated among the current multiple candidate positions, and when there is no position to be eliminated among the multiple candidate positions, it means that there is no position that can be eliminated among the current multiple candidate positions, that is, each candidate position needs to be retained, so the current multiple candidate positions can all be determined as remote position information.
[0047] Step Sc, determine the number of the positions to be eliminated. If the number is 1, directly eliminate the positions to be eliminated from multiple candidate positions, and determine that other candidate positions in the multiple candidate positions are remote position information. If the number is not 1, continue to execute step Sd.
[0048] Step Sd: determine the position to be eliminated with the smallest exclusive area from at least two positions to be eliminated, eliminate the position to be eliminated, and continue to execute step Sa.
[0049] For the embodiment of the present application, when the number of positions to be eliminated is 1, it means that there is only one region with a small exclusive area and a high overlap rate. Therefore, the position to be eliminated can be directly eliminated from multiple candidate positions, and other candidate positions in the multiple candidate positions are determined as remote position information; When the number of positions to be eliminated is not 1, that is, it is at least two, it means that the at least two positions to be eliminated can be eliminated. However, each time a position to be eliminated is eliminated, the coverage rate and exclusive area of other candidate areas around the position to be eliminated may change. Therefore, when there are at least two positions to be eliminated, only one of them can be eliminated. Specifically, the smaller the exclusive area of the position to be eliminated, the smaller the impact on the coverage range of the signal when the position to be eliminated is eliminated. Therefore, the position to be eliminated with the smallest exclusive area can be eliminated, and steps Sa to Sd are continued until there is no position to be eliminated in the candidate positions, thereby achieving the effect of determining the remote position information.
[0050] Step S1064, determining the number and connection information of the remote units based on the remote location information and the near-end location information.
[0051] For the embodiment of the present application, the connection information of the remote unit indicates which remote unit or proximal unit the remote unit is connected to, and the specific implementation process of determining the number of remote units and the connection information based on the remote location information and the proximal location information includes: Step Sf, determining the number of remote units according to the number of remote location information determined.
[0052] For the embodiment of the present application, since the remote location information is the location where the remote unit is installed, the number corresponding to the determined remote location information can be directly determined as the number of remote units.
[0053] Step Sg, determining whether the number is greater than 1, if not, directly determining that the connection information of the remote unit is connected to the near-end unit, if yes, continuing to execute step Sh; Step Sh: determining a first distance value corresponding to each remote unit based on the remote position information and the near-end position information, wherein the first distance value is a distance value between the remote unit and the near-end unit.
[0054] For the embodiment of the present application, when the number of remote units is 1, it means that only one remote unit is needed to cover the current target sub-area, that is, the connection information corresponding to the remote unit can be directly determined as: connected to the proximal unit. When the number of remote units is greater than 1, it means that at least two remote units need to be established to cover the current target sub-area, that is, it is necessary to continue to determine which of the at least two remote units is connected to the proximal unit and which two remote units are connected. Specifically, the distance value of each remote unit from the proximal unit, that is, the first distance value, can be calculated based on the position information of the proximal unit and the remote position information corresponding to each remote unit, so as to facilitate the subsequent classification of the at least two remote units based on the first distance value.
[0055] Step Si, sorting the remote units based on the first distance values to obtain a third sorting result, in which the remote unit at the first position in the third sorting result has the smallest first distance value.
[0056] For the embodiment of the present application, the smaller the first distance value corresponding to the remote unit is, the shorter the distance between the remote unit and the near-end unit is, and when the remote unit is connected to the near-end unit, the signal effect of the coverage area corresponding to the remote unit is better.
[0057] Step Sj, based on the third sorting result, calculating the difference between the first distance values corresponding to every two adjacent remote units; Step Sk, determining whether there is a difference reaching a preset difference among the differences corresponding to every two adjacent remote units, if not, directly determining the connection information of the multiple remote units as being connected to the near-end unit, if so, continuing to execute step Sl.
[0058] For the embodiments of this application, Figure 2As shown, the solid circle containing the base station is the coverage area of the base station 4G network (Note: this is an example diagram, the actual coverage area is not a regular circle), the dotted circle is the coverage area of the base station 5G network, and the area where the solid circle containing the base station and the dotted circle do not intersect is the area to be built. With the position information of the proximal unit as the center of the circle, multiple circles can be drawn, and multiple rings can be formed between the multiple circles. The difference in the first distance value represents the distance of the positions of the rings in which the multiple remote devices fall respectively, that is, the difference in the first distance value between each two adjacent remote units in the third sorting result is calculated, so as to facilitate the clarification of whether the effect of at least two remote units being directly connected to the proximal unit is better, or whether there is a remote unit in at least two remote units that is connected to the remote unit. Specifically, the preset difference is a difference set in advance, which is a standard for indicating whether the first distance values of two adjacent remote units are greatly different. When there is no difference reaching the preset difference in the difference corresponding to each two adjacent remote units in the third sorting result, it means that at least two remote units in the current target sub-area can be directly connected to the proximal unit (such as Figure 3 As shown, the first distance values corresponding to the four remote units A, B, C, and D are slightly different), and when there is a difference (such as Figure 2 As shown in the figure, the distribution of four remote units A, B, C, and D) indicates that the effect of connecting one of the at least two remote units in the target sub-area with another remote unit is better than the effect of directly connecting with the near-end unit. The effect here includes the comprehensive effect reflected by the cost and signal quality. For example, the first distance value of the remote unit D is 400m, the first distance value of the remote unit B is 800m, and the distance value of the remote unit B to the remote unit D is only 200m. If the remote unit B and the remote unit D are directly connected to the near-end unit at this time, the connection cost of the remote unit B will be larger, and The signal quality of the remote unit B is also related to the signal transmission distance. The longer the distance, the greater the delay, that is, the worse the signal effect. If the remote unit B is connected to the remote unit D, the connection cost of the remote unit B is greatly reduced, and the signal transmission distance of the remote unit B is only 600m. The delay of the remote unit B will be related to the distance of 600m and the process of forwarding the signal by the remote unit D. That is, from a comprehensive perspective, the effect of the remote unit B connecting to the remote unit D is better than that of connecting to the near-end unit. Therefore, when there is a difference that reaches the preset difference, it is necessary to continue to execute the following steps S1 to Sv to determine the connection information of each remote unit.
[0059] Step S1, classifying the remote units in the third sorting result based on the difference, obtaining the level number corresponding to each remote unit and the total level number corresponding to the current target sub-region, the smaller the level number, the smaller the corresponding first distance value.
[0060] For the embodiment of the present application, when performing level division, specifically, the difference that reaches the preset difference is determined as the target difference, the number of target difference is at least one, and then the remote unit with the smallest first distance value among the two remote units corresponding to each target difference and the last remote unit in the third sorting result are marked as hierarchical units, and at least one hierarchical unit is sorted based on the first distance value of the hierarchical unit, and the sequence number of each hierarchical unit is determined as the level number of each hierarchical unit and the sequence number of the last hierarchical unit is determined as the total level number, and it is determined whether there are other hierarchical units before the hierarchical unit in the third sorting result. If not, the level number of the hierarchical unit is determined as the level number of other remote units before the hierarchical unit. If so, the level number of the hierarchical unit is determined as the level number of other remote units between the hierarchical unit and the previous hierarchical unit.
[0061] For ease of understanding, an example is given for explanation. Assume that the current third sorting result is: remote unit A, remote unit C, remote unit D and remote unit B, wherein the first distance value of remote unit A is 329m, the first distance value of remote unit C is 400m, the first distance value of remote unit D is 800m, the first distance value of remote unit B is 1120m, the difference AC is 71m, the difference CD is 400m, and the difference DB is 320m. Assume that the preset difference is 200m, that is, the difference that reaches the preset difference at this time is the difference CD and the difference DB. Therefore, remote unit C, remote unit D and remote unit B can be determined as hierarchical units, and the hierarchical units are sorted to obtain remote unit C, remote unit D and remote unit B. Element B, and then because the sequence number of remote unit C is one, it can be determined that the level number of remote unit C is one, and so on, the levels of remote unit D and remote unit B are two and three respectively, and three levels are determined as the total level number, and then it is determined that there are no other remote units belonging to the hierarchical unit before remote unit B in the third sorting result, so the level number of remote unit A before remote unit C can be directly determined as one, and then there is a remote unit belonging to the hierarchical unit before remote unit D, that is, remote unit C, so the level number of other remote units between remote unit C and remote unit D in the third sorting result is determined as two, and so on to determine the level number of each remote unit and the total level number of the target sub-area.
[0062] Specifically, as in the above example, when there is no other remote unit between two hierarchical units, it means that the level to which the hierarchical unit with the larger first distance value belongs in the two hierarchical units has only one remote unit.
[0063] Step Sm, determining the connection information of the first-level remote unit as being connected to the proximal unit, and determining the first-level remote unit as the upper unit, the first-level remote unit being a remote unit with the first level.
[0064] For the embodiment of the present application, continuing with the above example, the connection information of the remote unit A and the remote unit C is determined to be connected to the proximal unit. At this time, the upper-level unit includes the remote unit A and the remote unit C.
[0065] Step Sn, increasing the level number corresponding to the upper level unit by 1 to obtain the current level number, and determining the remote unit corresponding to the current level number as the unit to be determined.
[0066] For the embodiment of the present application, continuing with the above example, the current level number is level 2, and the level 2 remote unit, ie, remote unit D, is determined as the unit to be determined.
[0067] Step So, determine the number of upper level units; Step Sp, determining whether the number of upper-level units is 1, and if so, determining that the connection information of the current unit to be determined is connected to the upper-level unit; Step Sq: if not, then calculate the distance between each unit to be determined and each upper-level unit to obtain a second distance value, wherein each unit to be determined corresponds to at least two second distance values.
[0068] For the embodiment of the present application, when the number of upper-level units is 1, it means that the connection relationship of the unit to be determined can be directly determined to be connected to the upper-level unit, and when the number of upper-level units is not 1, it means that it is necessary to determine which upper-level unit the unit to be determined is specifically connected to, so it is necessary to judge whether the current number of upper-level units is 1, so that the connection relationship of the unit to be determined can be determined according to the judgment result. Continuing with the above example, the upper-level units include remote units A and remote units C, that is, the number of upper-level units is 2, so it is necessary to continue to determine whether the unit to be determined, that is, remote unit D, needs to be connected to remote unit A or remote unit C. Specifically, the distance value between remote unit D and remote unit A and the distance value between remote unit D and remote unit C can be calculated, that is, the second distance value corresponding to remote unit D is calculated and the connection information of remote unit D is determined according to the second distance value. Assume that the distance value between remote unit D and remote unit A is 300m, and the distance value between remote unit D and remote unit C is 200m, that is, the second distance values corresponding to remote unit D are 300m and 200m.
[0069] Step Sr: determining the connection information of each to-be-determined unit based on the second distance value.
[0070] For the embodiment of the present application, continuing with the above example, the primary unit corresponding to the minimum value in the second distance value is determined as the remote unit connected to the remote unit D, that is, the connection information of the remote unit D is connected to the remote unit C.
[0071] Step St, determine whether the current level number reaches the total level number.
[0072] Step Su, if yes, then the loop ends; Step Sv: If not, the unit to be determined is re-determined as the upper-level unit, and step Sn is continued.
[0073] For the embodiment of the present application, the current level number indicates the level number of the remote unit for which the connection information has been determined, and the total level number indicates the highest level number corresponding to the remote units in the target sub-area. When the current level number reaches the total level number, it means that there are no remote units for which the connection information has not been determined in the current target sub-area, and the loop can be ended; and when the current level number does not reach the total level number, it means that there are still remote units for which the connection information has not been determined in the current target sub-area, and it is necessary to continue to determine the connection information for the remote units for which the connection information has not been determined. Specifically, the unit to be determined can be re-determined as the upper-level unit. Continuing with the above example, the upper-level unit is the remote unit D at this time, and then the process from step Sn to step Sv is continued until there are no remote units for which the connection information has not been determined in the target sub-area.
[0074] Step S107, determining the regional construction cost corresponding to the target sub-region based on the number of remote units, the construction cost and the connection information.
[0075] For the embodiments of the present application, it specifically includes: determining the connection cost of the target sub-area based on the connection information. Specifically, the engineer can obtain the connection cost corresponding to the unit connection distance, that is, the unit connection cost, and then determine the connection distance of the target sub-area based on the connection information, so as to multiply the connection distance by the unit connection cost to obtain the connection cost of the target sub-area, and at the same time multiply the number of remote units and the construction cost to obtain the cost of establishing the remote units, and sum the obtained cost of establishing the remote units and the connection cost to obtain the regional construction cost of the target sub-area.
[0076] Step S108, determining the total regional construction cost of all target sub-regions that have currently executed step S107 based on the regional construction cost, and judging whether the total regional construction cost reaches the expected cost; Step S109, if not reached, re-execute step S105 until the target sub-area does not exist in the first sorting result, and generate a construction plan based on the sub-construction plan stored in step S106; Step S110: if reached, a construction plan is generated based on the sub-construction plan stored in step S106.
[0077] For the embodiment of the present application, the total regional construction cost is the cost of all the target sub-regions that have been calculated at present. When the total regional construction cost does not reach the expected cost, it means that the remote unit can still be established at present, and the process from step S105 to step S110 is re-executed until the target sub-region cannot be determined from the first sorting result, and then a construction plan is generated according to the sub-construction plan stored in step S106; and when the total regional construction cost reaches the expected cost, it means that the cost of the target sub-region that has been constructed has reached the budget, that is, it is not possible to continue to build the remote unit for the area to be constructed. Therefore, a construction plan can be directly generated according to the sub-construction plan stored in step S106, thereby achieving the effect of efficiently planning the construction plan.
[0078] Furthermore, in addition to the parameters involved in step S106, the construction plan may also include the total regional construction cost, that is, the actual required cost corresponding to the construction plan.
[0079] The above are only some implementation methods of the present application. It should be pointed out that for ordinary technicians in this technical field, several improvements and modifications can be made without departing from the principles of the present application. These improvements and modifications should also be regarded as the scope of protection of the present application.
Claims
1. A 5G multi-carrier frequency power amplifier base station amplification system optimization method, characterized in that: include: Step S101, obtaining the estimated cost of the current operator and the geographical information of the area to be constructed, the personnel distribution map of the area to be constructed, and the location information of the base station corresponding to the area to be constructed, wherein the area to be constructed is the area where the 5G multi-carrier frequency power amplifier base station amplification system is currently required to be constructed; Step S102, determining the location information of the base station corresponding to the area to be constructed as the proximal location information of the proximal unit of the 5G multi-carrier frequency power amplifier base station amplification system, and dividing the area to be constructed based on the personnel distribution map to obtain a plurality of sub-areas to be constructed, and each sub-area to be constructed has a corresponding importance level; Step S103, sorting the multiple sub-areas to be constructed based on the importance levels to obtain a first sorting result; Step S104, obtaining the construction cost of a single remote unit; Step S105, determining a target sub-region according to the first sorting result, wherein the target sub-region is a sub-region to be constructed that has not been subjected to step S106; Step S106, determining the number of remote units corresponding to the target sub-area, the remote position information corresponding to each remote unit, and the connection information based on the geographic information of the target sub-area and the proximal position information, generating and storing a sub-construction plan for the target sub-area; Step S107, determining the regional construction cost corresponding to the target sub-region based on the number of the remote units, the construction cost and the connection information; Step S108, determining the total regional construction cost of all target sub-regions that have currently executed step S107 based on the regional construction cost, and judging whether the total regional construction cost reaches the estimated cost; Step S109: if not reached, re-execute step S105 until the target sub-area does not exist in the first sorting result, and generate a construction plan based on the sub-construction plan stored in step S106; Step S110: if reached, a construction plan is generated based on the sub-construction plan stored in step S106.
2. According to claim 1, a 5G multi-carrier frequency power amplifier base station amplification system optimization method is characterized in that: Obtaining a personnel distribution map of the area to be constructed, including: Obtaining usage of the mobile network in the area to be constructed within a preset time period; A personnel distribution map of the area to be constructed is generated based on the usage situation.
3. A 5G multi-carrier frequency power amplifier base station amplification system optimization method according to claim 1, characterized in that: The personnel distribution map is displayed in monochrome, and the darker the color, the larger the population. Based on the personnel distribution map, the area to be constructed is divided to obtain multiple sub-areas to be constructed, and each sub-area to be constructed has a corresponding importance level, including: grayscale the personnel distribution map to obtain an initial grayscale image; Performing Gaussian filtering on the grayscale image to remove noise and obtain a final grayscale image; Using the Sobel algorithm to perform edge processing on the ultimate grayscale image, dividing the area to be constructed into a plurality of sub-areas to be constructed; Calculate the average grayscale value corresponding to each sub-area to be constructed; The importance level of each sub-area to be constructed is determined based on the average gray value.
4. A 5G multi-carrier frequency power amplifier base station amplification system optimization method according to claim 1, characterized in that: The geographic information includes building distribution information and signal influencing source information. The number of remote units corresponding to the target sub-area, the remote location information corresponding to each remote unit, and the connection information are determined based on the geographic information of the target sub-area and the proximal location information, including: Determine a plurality of candidate locations from the target sub-area based on the building distribution information, the candidate locations being locations where the remote unit can be established; Calculate the coverage area of the remote unit at each candidate location based on the signal influencing source information; determining remote location information for establishing a remote unit from the plurality of candidate locations based on the coverage area; The number of remote units and connection information are determined based on the remote location information and the near-end location information.
5. A 5G multi-carrier frequency power amplifier base station amplification system optimization method according to claim 4, characterized in that: The signal influencing source information includes a signal influencing source type and an influencing factor corresponding to the signal source type. Calculating the coverage area of the remote unit at any candidate position based on the signal influencing source information includes: Determine the type of signal influencing source corresponding to any candidate position; Obtaining the ideal coverage area of the remote unit in an ideal state; The coverage area of the remote unit at any of the candidate positions is calculated based on the impact factor corresponding to the signal impact source type and the ideal coverage area.
6. A 5G multi-carrier frequency power amplifier base station amplification system optimization method according to claim 4, characterized in that: The step of determining remote location information for establishing a remote unit from the plurality of candidate locations based on the coverage area comprises: Step Sa, calculating the overlapping area and the exclusive area corresponding to each current candidate position based on the coverage area, and calculating the overlapping rate corresponding to each candidate position based on the overlapping area and the coverage area corresponding to each candidate position, wherein the overlapping area represents the area when the coverage areas corresponding to at least two candidate positions overlap; Step Sb, based on the exclusive area, the overlap rate, the preset overlap rate threshold and the preset area threshold, determining whether there is a position to be eliminated among the multiple candidate positions, if not, determining the current multiple candidate positions as the remote unit position information, if yes, continuing to execute steps Sc to step Sd, the position to be eliminated is a candidate position whose exclusive area does not reach the preset area threshold and whose overlap rate reaches the preset overlap rate threshold; Step Sc, determining the number of the positions to be eliminated. If the number is 1, directly eliminating the positions to be eliminated from the multiple candidate positions, and determining that other candidate positions in the multiple candidate positions are remote position information. If the number is not 1, continuing to execute step Sd; Step Sd: determine the position to be eliminated with the smallest exclusive area from at least two positions to be eliminated, eliminate the position to be eliminated, and continue to execute step Sa.
7. A 5G multi-carrier frequency power amplifier base station amplification system optimization method according to claim 4, characterized in that: Determining the number and connection information of remote units based on the remote location information and the near-end location information includes: Step Sf, determining the number of the remote units according to the number of remote location information determined; Step Sg, determining whether the number is greater than 1, if not, directly determining that the connection information of the remote unit is connected to the near-end unit, if yes, continuing to execute step Sh; Step Sh, determining a first distance value corresponding to each remote unit based on the remote position information and the near-end position information, wherein the first distance value is a distance value between the remote unit and the near-end unit; Step S1, sorting the remote units based on the first distance values to obtain a third sorting result, wherein the remote unit at the first position in the third sorting result has the smallest first distance value; Step Sj, based on the third sorting result, calculating the difference between the first distance values corresponding to every two adjacent remote units; Step Sk, determining whether there is a difference reaching a preset difference among the differences corresponding to each two adjacent remote units, if not, directly determining the connection information of the plurality of remote units as being connected to the near-end unit, if yes, continuing to execute step S1; Step S1, classifying the remote units in the third sorting result based on the difference value to obtain the level number corresponding to each remote unit and the total level number corresponding to the current target sub-region, wherein the smaller the level number, the smaller the corresponding first distance value; Step Sm, determining the connection information of the first-level remote unit to be connected to the proximal unit, and determining the first-level remote unit as the upper-level unit, the first-level remote unit being a remote unit with a level number of one; Step Sn, increasing the level number corresponding to the upper level unit by 1 to obtain the current level number, and determining the remote unit corresponding to the current level number as the unit to be determined; Step So, determining the number of the upper level units; Step Sp, determining whether the number of the upper-level unit is 1, and if so, determining that the connection information of the current unit to be determined is connected to the upper-level unit; Step Sq: if not, then calculate the distance between each unit to be determined and each upper-level unit to obtain a second distance value, wherein each unit to be determined corresponds to at least two second distance values; Step Sr, determining the connection information of each to-be-determined unit based on the second distance value; Step St, determining whether the current level number reaches the total level number; Step Su, if yes, then the loop ends; Step Sv: If not, the unit to be determined is re-determined as the upper-level unit, and step Sn is continued.
Citation Information
Patent Citations
LTE230 power system special network construction layout method
CN107231640A
Mobile communication network stereo layered laying method based on 4 / 5G high frequency band
CN107666670A
Base station far-end unit dynamic classification method and device and cell networking method and system
CN112235804A
5G site planning method and device, electronic equipment and storage medium
CN112950243A
5g distributed community network coverage system
CN113115334A