Integral lifting installation construction method for steel structure inclined strut ceiling joist
Through the overall lifting and installation construction method of steel structure keel, BIM technology and electric slide rail lifting device are used to solve the problem of time, labor and low efficiency of transportation during the installation of steel structure ceiling keel, and efficient and safe construction is achieved. Suitable for space-constrained scenarios.
Patent Information
- Application Number
- CN202411277893.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-12
- Publication Date
- 2024-12-13
- Estimated Expiration
- 2044-09-12
AI Technical Summary
During the installation process of existing steel structure ceiling keels, there are problems such as time-consuming and laborious transportation of raw materials, low installation efficiency and many safety hazards, and the lack of economicality for setting up large vertical transportation equipment separately.
A steel structure oblique support ceiling keel is adopted to carry out the overall lifting and installation construction method. The steel structure is deepened by measuring and laying out lines, establishing a control network, using BIM technology, and designing an electric slide rail lifting device for lifting to realize the steel structure ceiling keel. Overall improvement.
It improves the convenience and installation efficiency of raw material transfer, reduces construction costs, ensures construction safety, avoids material pollution, and is suitable for construction environments with space limitations.
Smart Images

Figure CN119122277A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of building decoration and renovation construction, and in particular to a method for integrally lifting and installing a steel structure oblique bracing ceiling keel. Background Art
[0002] With the rapid development of modern architecture in my country, steel structure ceiling keels have become a construction content that is widely used in the decoration and renovation process. Due to the increasingly high requirements of various projects for the construction environment, there is a risk of pollution when the steel structure ceiling keel decoration and renovation materials are transported together with other materials, and the separate vertical transportation equipment is limited by the site. In addition, the installation of steel structure ceiling keels is basically in the middle and late stages of the project, the site space restrictions are more severe, and the materials required for steel structure ceiling keels are trivial and sporadic, and the separate large-scale vertical transportation equipment is not economical. At present, the installation generally involves manual transportation of raw materials to the room, which has the disadvantages of time-consuming and labor-intensive transportation of raw materials, low installation efficiency, and many safety hazards, resulting in high transportation costs and uncontrollable construction period. Summary of the invention
[0003] 1. Technical issues to be resolved In view of the shortcomings of the prior art, the present invention provides a method for overall lifting and installation of a steel structure diagonal brace ceiling keel, which has the advantages of convenient raw material transportation and high installation efficiency, and solves the problems of time-consuming and labor-intensive raw material transportation and low installation efficiency.
[0004] (II) Technical solution In order to achieve the above-mentioned purpose of convenient raw material transportation and high installation efficiency, the present invention provides the following technical solution: a method for overall lifting and installation of a steel structure inclined brace ceiling keel, the specific steps are as follows: S1. Survey and lay out the lines, combine the existing control points, arrange the corner wire network, and establish the control network for the construction of the steel structure diagonal brace ceiling keel; S2. Deepening of steel structure ceiling keel structure, using BIM technology in conjunction with steel structure ceiling keel design to carry out the deepening of steel structure ceiling keel structure; S3. Design and manufacture a lifting device based on computer theoretical data; S4, installation of the lifting device; S5. Assemble the steel structure ceiling keels on the ground according to the construction drawings; S6. Lift the steel structure ceiling keel as a whole through the lifting device.
[0005] Preferably, the lifting device is an electric slide rail lifting device; the electric slide rail lifting device comprises a slide rail and a steel structure ceiling keel, a fixing component is provided on the top of the slide rail, the fixing component is fixedly installed on the ceiling, the bottom of the slide rail is slidably connected with a power trolley, a lifting drive component is fixedly installed on the bottom of the power trolley, a suspension component is fixedly installed on the bottom of the lifting drive component, two groups of hooks are provided at the bottom of the suspension component, the four ends of the steel structure ceiling keel are fixedly installed with diagonal braces, two diagonal braces distributed front and back are fixedly installed with steel cables, the middle parts of the two groups of steel cables are respectively hung on the two groups of hooks, four groups of pre-embedded brackets one and four groups of pre-embedded brackets two are fixedly installed on the wall, the four groups of pre-embedded brackets one are used to lift on the lower side of the four ends of the steel structure ceiling keel, and the four groups of pre-embedded brackets two are used to lift on the lower side of the four diagonal braces.
[0006] Preferably, the slide rail is an I-beam, the fixing assembly includes a sleeve, the slide rail is slidably connected inside the sleeve, a plurality of hangers are equidistantly fixed on the top of the sleeve, threaded holes are penetrated on both sides of the sleeve, the sleeve is connected with limiting bolts through the threaded holes, and the limiting bolts are fitted on the surface of the slide rail.
[0007] Preferably, the power trolley comprises a U-shaped plate 1, wherein the U-shaped plate 1 is composed of two side plates and a bottom plate, and the U-shaped plate 1 is in a U-shape; mounting covers are fixedly installed on both sides of the U-shaped plate 1, and a accommodating cavity is formed between the mounting cover and the side plates of the U-shaped plate 1; each of the mounting covers is rotatably connected with two rotating shafts 1, and the rotating shaft 1 penetrates the side plates of the U-shaped plate 1 and extends into the interior of the U-shaped plate 1, and a wheel is fixedly installed on one end of the rotating shaft 1 located inside the U-shaped plate 1, and the wheel rolls on the upper surface of the bottom end of the slide rail; a sprocket 1 is fixedly installed on the circumferential surface of the rotating shaft 1 located inside the accommodating cavity, and a motor 1 is fixedly installed on the surface of the mounting cover on the front side, and a driving shaft is fixedly installed on the output end of the motor 1, and the driving shaft penetrates and is rotatably connected to the U-shaped plate 1 and the two groups of mounting covers, and two groups of sprocket wheels 2 are fixedly installed on the surface of the driving shaft, and the two groups of sprocket wheels 2 are respectively located in the two accommodating cavities; in the accommodating cavity, the two groups of sprocket wheels 1 and sprocket wheels 2 are connected by chain belts.
[0008] Preferably, the lifting drive component includes a U-shaped plate 2 fixedly mounted on the bottom of the U-shaped plate 1, a motor 2 is fixedly mounted on the right side of the U-shaped plate 2, a winding roller is fixedly mounted on the output end of the motor 2, the winding roller is rotatably connected to the inside of the U-shaped plate 2, a steel wire rope is wound on the winding roller, a through hole is formed through the bottom of the U-shaped plate 2, the steel wire rope passes through the through hole, and arc chamfers are arranged on the edges at both ends of the through hole.
[0009] Preferably, the suspension assembly includes an arch plate 1, which is arched, and has L-shaped plates fixedly installed on the front and rear sides of the arch plate 1, and a motor 3 is fixedly installed on the back of the L-shaped plate on the rear side, and a rotating shaft 2 is fixedly installed on the output end of the motor 3, and the rotating shaft 2 penetrates and is rotatably connected to the two groups of L-shaped plates and the arch plate 1; a turntable is fixedly installed on the circumferential surface of the rotating shaft 2 located inside the arch plate 1, and spherical grooves are arranged in an array on the circumferential surface of the turntable; the rotating shaft 2 is rotatably connected to the arch plate 2 on the circumferential surface between the L-shaped plate and the arch plate 1, and the top of the arch plate 2 is fixedly installed on the bottom end of the steel wire rope; a suspension rope is attached to the surface of the upper half of the turntable, and a plurality of steel balls are equidistantly fixed on the surface of the suspension rope, and the steel balls are embedded in the spherical grooves, and the two groups of the hooks are respectively fixedly installed on the two ends of the suspension rope.
[0010] Preferably, in S2, the deepening work of the steel structure ceiling keel structure is to realize the deepening of the steel structure ceiling keel structure through three-dimensional visualization, material parameter extraction, simulation arrangement, virtual sample, drawing, and three-dimensional briefing; the main deepening contents include: deepening of the steel structure ceiling keel structure, collision detection, deepening of installation methods, etc.; through BIM modeling, the steel structure ceiling keel is integrated and analyzed with the building main body and electromechanical pipeline model to check whether there are collision situations or conflicting parts, and to carry out in-depth design optimization in advance.
[0011] Preferably, in S3, the design strength and stability of the lifting device are analyzed by using integrated finite element modeling; three-dimensional solid unit modeling is performed on the structural beams and slabs, the lifting device components and the lifting load, and the model is defined by assigning different real constants, assigning section types and sizes, etc. The material model adopts a multilinear isotropic hardening model (MISO), the lifting weight takes the most unfavorable weight, and the design shear stress of the load nodes of the lifting device and the deformation and displacement of the slide rail are simulated and verified.
[0012] Preferably, in S6, a trial lift is performed before the steel structure ceiling keel is lifted as a whole using a lifting device, and the lifting can be carried out only after confirming that the lifting equipment is stable and firm, and the trial lifting height does not exceed 0.5m; the steel structure ceiling keel is lifted to the installation positioning point, and the diagonal brace and the embedded bracket two are fixed with expansion bolts, and finally the installation of the steel structure ceiling keel and the embedded bracket one is completed.
[0013] Preferably, the steel structure ceiling keel is lifted as a whole. After the construction is completed, measuring instruments such as total stations and levels are required to detect the distance from the ground of each hanging point, calculate the relative height difference of each hanging point, and adjust the height of each hanging point to make the steel structure ceiling keel reach the designed posture; while ensuring that all design parameters are correct, use the lifting device to lift the steel structure ceiling keel as a whole.
[0014] (III) Beneficial effects Compared with the prior art, the present invention provides a method for overall lifting and installation of a steel structure diagonal ceiling keel, which has the following beneficial effects: 1. The overall lifting and installation construction method of the steel structure diagonal brace ceiling keel applies the advanced BIM technology to analyze the early stage of construction, deepen and pre-assemble the steel structure ceiling keel, check the collision and structural stability, eliminate safety hazards, solve theoretical difficulties, control various risks in advance, and save trial and error costs.
[0015] 2. The overall lifting and installation construction method of the steel structure diagonal ceiling keel innovatively designs an electric slide rail lifting device through S3 and S4, and uses integrated finite element modeling to analyze the design strength and stability of the lifting device to ensure construction quality and safety. At the same time, the lifting device is highly flexible, which solves the problem of transporting decoration materials in restricted spaces and avoids material pollution during lifting.
[0016] 3. The overall lifting and installation construction method of the steel structure inclined ceiling keel is elaborated in detail through S5 and S6. The lifting technology occupies a small space, the scheme is flexible, simple and efficient, and it is highly scalable.
[0017] In summary, the overall lifting and installation construction method of the steel structure inclined ceiling keel is suitable for the construction of steel structure ceiling keels. The overall lifting hoisting technology can not only effectively ensure the construction safety and construction period, save construction costs, but also effectively ensure the construction safety. The construction design level is first-class, the scheme is flexible and simple, the application scenario range is wide, and the promotion is high, providing an operational implementation case for peers. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] Figure 1 A schematic diagram of the process of the overall lifting and installation construction method of the steel structure inclined bracing ceiling keel proposed by the present invention; Figure 2 This is a schematic diagram of the three-dimensional structure of the electric slide rail lifting device proposed by the present invention; Figure 3 The electric slide rail lifting device proposed by the present invention Figure 2 A is a schematic diagram of the enlarged structure of the details; Figure 4 A schematic diagram of the three-dimensional structure of the power trolley, lifting drive component and suspension assembly of the electric slide rail lifting device proposed by the present invention; Figure 5 A schematic diagram of the three-dimensional structure of the power trolley of the electric slide rail lifting device proposed by the present invention; Figure 6 A schematic diagram of the three-dimensional structure of the lifting and lowering driving component of the electric slide rail lifting device proposed by the present invention; Figure 7A schematic diagram of the three-dimensional structure of the suspension assembly of the electric slide rail lifting device proposed by the present invention; Figure 8 It is a schematic diagram of the collision between the steel structure diagonal ceiling keel and the BIM model of the electromechanical pipeline in S2 of the present invention; Fig. 9 A schematic diagram of simulated stress for the in-depth design of the electric slide rail lifting device proposed in the present invention; Fig.10 This is a schematic diagram of simulated displacement for the in-depth design of the electric slide rail lifting device proposed in the present invention.
[0019] In the figure: 1. Slide rail; 2. Fixing assembly; 3. Power trolley; 4. Lifting drive component; 5. Suspension assembly; 6. Steel structure ceiling keel; 7. Diagonal brace; 8. Steel cable; 9. Pre-buried bracket 1; 10. Pre-buried bracket 2; 101, baffle; 201, sliding sleeve; 202, suspension rod; 203, stop bolt; 301, U-shaped plate 1; 302, mounting cover; 303, rotating shaft 1; 304, wheel; 305, sprocket 1; 306, motor 1; 307, driving shaft; 308, sprocket 2; 309, chain belt; 401, U-shaped plate 2; 402, motor 2; 403, winding roller; 404, wire rope; 501. Arch plate one; 502. L-shaped plate; 503. Motor three; 504. Rotating shaft two; 505. Turntable; 506. Spherical groove; 507. Arch plate two; 508. Lifting rope; 509. Steel ball; 510. Lifting hook. DETAILED DESCRIPTION
[0020] In the description of the present application, it should be understood that the terms "length", "width", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", etc., indicating the orientation or position relationship, are based on the orientation or position relationship shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present application.
[0021] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0022] See also Figure 1-Figure 10, a method for overall lifting and installation of steel structure diagonal ceiling keels, using overall lifting hoisting technology, suitable for most steel keel decoration projects, ensuring construction safety and construction period, saving construction costs, and ensuring construction safety. The specific construction steps are as follows: S1. Survey and lay out the lines, combine the existing control points, arrange the corner wire network, and establish the control network for the construction of the steel structure diagonal brace ceiling keel; S2. Deepening of the structure of steel structure ceiling keel 6. Use BIM technology to cooperate with the design of steel structure ceiling keel 6 to carry out the deepening of the structure of steel structure ceiling keel 6; The structural deepening of the steel structure ceiling keel 6 is to deepen the structure of the steel structure ceiling keel 6 through 3D visualization, material parameter extraction, simulated arrangement, virtual sample, drawing, and 3D explanation. The main deepening contents include: structural deepening of the steel structure ceiling keel 6, collision detection, and installation method deepening. Through BIM modeling, the steel structure ceiling keel 6 is integrated and analyzed with the main building and electromechanical pipeline model to check whether there are collisions or conflicting parts, and to carry out in-depth design optimization in advance; S3. Design and manufacture a lifting device based on computer theoretical data as an important transportation device for the steel structure ceiling keel 6 material; The lifting device is an electric slide rail lifting device. The design strength and stability of the lifting device are analyzed by using integrated finite element modeling to ensure construction quality and safety. Three-dimensional solid unit modeling is performed on the structural beams and slabs, the lifting device components and the lifting load. The model is defined by assigning different real constants, section types and sizes, etc. The material model uses the multi-linear isotropic hardening model (MISO). The lifting weight takes the most unfavorable weight, and the design shear stress of the lifting device force node and the deformation displacement of the slide rail 1 are simulated and verified; S4, installation of electric slide rail lifting device; S5. According to the construction drawings, assemble the steel structure ceiling keel 6 on the ground; S6, the steel structure ceiling keel 6 is lifted as a whole, and the diagonal braces 7 are welded at the four corners of the ceiling for preliminary lifting and fixing. Four diagonal braces 7 are set above the steel structure ceiling keel 6. Before using the lifting device to lift the whole, a trial lift must be carried out to confirm that the lifting device is stable and firm before lifting. The trial lifting height shall not exceed 0.5m. Control the power trolley 3 to lift to the installation positioning point, use expansion bolts to fix the diagonal brace 7 and the embedded bracket 2 10, and finally complete the installation of the steel structure ceiling keel 6 and the embedded bracket 1 9.
[0023] The steel structure ceiling keel 6 is lifted as a whole. After the construction is completed, measuring instruments such as total stations and levels are required to detect the distance from the ground of each hanging point, calculate the relative height difference of each hanging point, and adjust the height of each hanging point to make the steel structure ceiling keel 6 reach the designed posture; after ensuring that all design parameters are correct, the steel structure ceiling keel 6 is lifted as a whole using a lifting device.
[0024] See also Figure 2-Figure 7 The electric slide rail lifting device comprises a slide rail 1 and a steel structure ceiling keel 6. A fixing assembly 2 is arranged on the top of the slide rail 1, and the fixing assembly 2 is fixedly installed on the ceiling by screws or the like. A power trolley 3 is slidably connected to the bottom of the slide rail 1, a lifting drive member 4 is installed at the bottom of the power trolley 3, a suspension assembly 5 is fixedly installed at the bottom of the lifting drive member 4, two groups of hooks 510 are arranged at the bottom of the suspension assembly 5, four ends of the steel structure ceiling keel 6 are fixedly installed with diagonal braces 7, four hanging points are arranged on the top of the steel structure ceiling keel 6, steel cables 8 are fixedly installed on two hanging points distributed in front and back, and the middle parts of the two groups of steel cables 8 are respectively hung on the two groups of hooks 510, and four groups of pre-buried brackets 1 9 and four groups of pre-buried brackets 2 10 are fixedly installed on the wall, and the four groups of pre-buried brackets 1 9 are used to lift on the lower sides of the four ends of the steel structure ceiling keel 6, and the four groups of pre-buried brackets 2 10 are used to lift on the lower sides of the four diagonal braces 7. The end of the steel structure ceiling keel 6 is fixed to the embedded bracket 1 9 by bolts, and the diagonal brace 7 is fixed to the embedded bracket 2 10.
[0025] The slide rail 1 is an I-beam, and the fixing assembly 2 includes a sleeve 201. The slide rail 1 is slidably connected to the inside of the sleeve 201. A plurality of suspension rods 202 are fixed at equal intervals on the top of the sleeve 201. Threaded holes are provided on both sides of the sleeve 201. The sleeve 201 is connected to limit bolts 203 through the threaded holes. The limit bolts 203 are attached to the surface of the slide rail 1. The slide rail 1 slides relative to the sleeve 201, so that part of the slide rail 1 extends to the outside of the building. Then, the building materials are lifted upward, and the slide rail 1 is slid toward the inside of the building, so that the building materials can be transferred from the outside to the inside of the building. Then, the relative position of the slide rail 1 and the sleeve 201 can be fixed by screwing the limit bolts 203. In addition, baffles 101 are welded at both ends of the slide rail 1 to prevent the slide rail 1 from detaching from the sleeve 201 when sliding relative to the sleeve 201; and also to prevent the power trolley 3 from detaching from the slide rail 1 when moving along the slide rail 1.
[0026] The power trolley 3 includes a U-shaped plate 301, which is composed of two side plates and a bottom plate, and is U-shaped. Both sides of the U-shaped plate 301 are fixedly installed with mounting covers 302, and a receiving cavity is formed between the mounting covers 302 and the side plates of the U-shaped plate 301. Each mounting cover 302 is rotatably connected with two rotating shafts 303, which penetrate the side plates of the U-shaped plate 301 and extend to the inside of the U-shaped plate 301. One end of the rotating shaft 303 located inside the U-shaped plate 301 is fixedly installed with a wheel 304, and the wheel 304 rolls on the upper surface of the bottom end of the slide rail 1 in contact with the mounting covers 302.
[0027] The rotating shaft 1 303 is fixedly mounted with a sprocket 1 305 on the circumferential surface inside the accommodating cavity, the front side mounting cover 302 is fixedly mounted with a motor 1 306, the output end of the motor 1 306 is fixedly mounted with a drive shaft 307, the drive shaft 307 penetrates and is rotatably connected to the U-shaped plate 1 301 and the two sets of mounting covers 302, and the surface of the drive shaft 307 is fixedly mounted with two sets of sprocket 2 308, and the two sets of sprocket 2 308 are respectively located in the two accommodating cavities; in the accommodating cavity, the two sets of sprocket 1 305 and the sprocket 2 308 are connected by a chain belt 309. The motor 1 306 drives the drive shaft 307 to rotate, which can drive the two sets of sprocket 2 308 to rotate synchronously; with the transmission effect of the sprocket 2 308, the chain belt 309 and the sprocket 1 305, the four sets of wheels 304 are driven to rotate synchronously. Therefore, the four sets of wheels 304 roll on the slide rail 1, and the power trolley 3 can move on the slide rail 1.
[0028] The lifting drive member 4 includes a U-shaped plate 2 401 fixedly mounted at the bottom of the U-shaped plate 1 301, a motor 2 402 fixedly mounted on the right side of the U-shaped plate 2 401, a winding roller 403 fixedly mounted at the output end of the motor 2 402, the winding roller 403 rotatably connected to the inside of the U-shaped plate 2 401, a steel wire rope 404 wound on the winding roller 403, a through hole 405 is formed through the bottom of the U-shaped plate 2 401, the steel wire rope 404 passes through the through hole 405, and arc chamfers are arranged at the edges of both ends of the through hole 405. The winding roller 403 is driven to rotate by the motor 2 402 to wind up or release the steel wire rope 404, thereby driving the suspension assembly 5, the steel cable 8 and the steel structure ceiling keel 6 to rise and fall.
[0029] The suspension assembly 5 includes an arch plate 501, which is arch-shaped. L-shaped plates 502 are fixedly installed on the front and rear sides of the arch plate 501. A motor 3 503 is fixedly installed on the back of the rear L-shaped plate 502. A rotating shaft 2 504 is fixedly installed on the output end of the motor 3 503. The rotating shaft 2 504 penetrates and is rotatably connected to the two groups of L-shaped plates 502 and the arch plate 501; a turntable 505 is fixedly installed on the circumferential surface of the rotating shaft 2 504 located inside the arch plate 501, and an array of spherical grooves 506 are arranged on the circumferential surface of the turntable 505.
[0030] The rotating shaft 2 504 is rotatably connected with the arch plate 2 507 on the circumferential surface between the L-shaped plate 502 and the arch plate 1 501, and the top of the arch plate 2 507 is fixedly installed at the bottom of the wire rope 404; the upper surface of the turntable 505 is attached with a suspension rope 508, and a plurality of steel balls 509 are fixedly installed on the surface of the suspension rope 508 at equal intervals, and the steel balls 509 are embedded in the spherical groove 506, and two groups of hooks 510 are respectively fixedly installed on both ends of the suspension rope 508. Because it is difficult to ensure that the lengths of the two steel cables 8 are equal during the specific operation, the steel structure ceiling keel 6 is prone to tilt during the hoisting. The rotating shaft 2 504 and the turntable 505 are driven to rotate by the motor 3 503, and the suspension rope 508 is driven to move, so as to adjust the height difference of the two groups of hooks 510, so that the steel structure ceiling keel 6 is kept horizontal.
[0031] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. A method for overall lifting and installation of a steel structure diagonal ceiling keel, characterized in that: The specific steps are as follows: S1. Survey and lay out the lines, combine the existing control points, arrange the corner wire network, and establish the control network for the construction of the steel structure diagonal brace ceiling keel; S2. Deepening of the steel structure ceiling keel structure. Use BIM technology to coordinate the design of the steel structure ceiling keel (6) and carry out the deepening of the steel structure ceiling keel (6) structure; S3. Design and manufacture a lifting device based on computer theoretical data; S4, installation of the lifting device; S5. According to the construction drawings, assemble the steel structure ceiling keel (6) on the ground; S6. The steel structure ceiling keel (6) is lifted as a whole by means of a lifting device.
2. The overall lifting and installation construction method of the steel structure diagonal brace ceiling keel according to claim 1 is characterized by: The lifting device is an electric slide rail lifting device; The electric slide rail lifting device comprises a slide rail (1) and a steel structure ceiling keel (6); a fixing component (2) is arranged on the top of the slide rail (1); the fixing component (2) is fixedly mounted on the ceiling; a power trolley (3) is slidably connected to the bottom of the slide rail (1); a lifting drive component (4) is fixedly mounted on the bottom of the power trolley (3); a suspension component (5) is fixedly mounted on the bottom end of the lifting drive component (4); two groups of hooks (510) are arranged on the bottom of the suspension component (5); and the steel structure ceiling The four ends of the keel (6) are fixedly installed with diagonal braces (7), and two diagonal braces (7) distributed front and back are fixedly installed with steel cables (8). The middle parts of the two groups of steel cables (8) are respectively hung on two groups of hooks (510). Four groups of pre-buried brackets (9) and four groups of pre-buried brackets (10) are fixedly installed on the wall. The four groups of pre-buried brackets (9) are used to support the lower sides of the four ends of the steel structure ceiling keel (6), and the four groups of pre-buried brackets (10) are used to support the lower sides of the four diagonal braces (7).
3. The overall lifting and installation construction method of the steel structure diagonal brace ceiling keel according to claim 2 is characterized by: The slide rail (1) is an I-beam, and the fixing assembly (2) comprises a slide sleeve (201). The slide rail (1) is slidably connected inside the slide sleeve (201). A plurality of suspension rods (202) are equidistantly fixed to the top of the slide sleeve (201). Threaded holes are provided on both sides of the slide sleeve (201). The slide sleeve (201) is connected to a limiting bolt (203) via the threaded hole, and the limiting bolt (203) is attached to the surface of the slide rail (1).
4. The overall lifting and installation construction method of the steel structure diagonal brace ceiling keel according to claim 2 is characterized by: The power vehicle (3) comprises a U-shaped plate (301), wherein the U-shaped plate (301) is composed of two side plates and a bottom plate, and the U-shaped plate (301) is U-shaped; Both sides of the U-shaped plate 1 (301) are fixedly mounted with mounting covers (302), a receiving cavity is formed between the mounting covers (302) and the side plates of the U-shaped plate 1 (301), each of the mounting covers (302) is rotatably connected to two rotating shafts (303), the rotating shafts (303) penetrate the side plates of the U-shaped plate 1 (301) and extend into the interior of the U-shaped plate 1 (301), a wheel (304) is fixedly mounted on one end of the rotating shaft (303) located inside the U-shaped plate 1 (301), and the wheel (304) rolls in contact with the upper surface of the bottom end of the slide rail (1); A sprocket wheel 1 (305) is fixedly mounted on the circumferential surface of the rotating shaft 1 (303) located inside the accommodating cavity, a motor 1 (306) is fixedly mounted on the surface of the mounting cover (302) on the front side, a driving shaft (307) is fixedly mounted on the output end of the motor 1 (306), the driving shaft (307) penetrates and is rotatably connected to the U-shaped plate 1 (301) and the two sets of mounting covers (302), two sets of sprocket wheels 2 (308) are fixedly mounted on the surface of the driving shaft (307), and the two sets of sprocket wheels 2 (308) are respectively located in the two accommodating cavities; In the accommodating cavity, the two groups of sprocket wheel one (305) and sprocket wheel two (308) are connected via a chain belt (309).
5. The overall lifting and installation construction method of the steel structure diagonal brace ceiling keel according to claim 2 is characterized by: The lifting drive member (4) comprises a U-shaped plate 2 (401) fixedly mounted at the bottom of the U-shaped plate 1 (301); a motor 2 (402) is fixedly mounted on the right side of the U-shaped plate 2 (401); a winding roller (403) is fixedly mounted at the output end of the motor 2 (402); the winding roller (403) is rotatably connected to the inside of the U-shaped plate 2 (401); a steel wire rope (404) is wound around the winding roller (403); a through hole (405) is formed through the bottom of the U-shaped plate 2 (401); the steel wire rope (404) passes through the through hole (405); and arc chamfers are arranged at both ends of the through hole (405).
6. The overall lifting and installation construction method of the steel structure diagonal brace ceiling keel according to claim 2 is characterized by: The suspension assembly (5) comprises an arched plate 1 (501), the arched plate 1 (501) is arched, L-shaped plates (502) are fixedly mounted on the front and rear sides of the arched plate 1 (501), a motor 3 (503) is fixedly mounted on the back of the L-shaped plate (502) on the rear side, a rotating shaft 2 (504) is fixedly mounted on the output end of the motor 3 (503), and the rotating shaft 2 (504) is rotatably connected to the two groups of L-shaped plates (502) and the arched plate 1 (501); A rotating disk (505) is fixedly mounted on the circumferential surface of the rotating shaft (504) located inside the arch plate (501), and an array of spherical grooves (506) are arranged on the circumferential surface of the rotating disk (505); The second rotating shaft (504) is located on the circumferential surface between the L-shaped plate (502) and the first arch plate (501) and is rotatably connected to the second arch plate (507), and the top of the second arch plate (507) is fixedly mounted on the bottom end of the steel wire rope (404); A suspension rope (508) is attached to the upper surface of the rotating disk (505), a plurality of steel balls (509) are fixed at equal intervals on the surface of the suspension rope (508), the steel balls (509) are embedded in the spherical grooves (506), and two groups of suspension hooks (510) are respectively fixedly mounted on the two ends of the suspension rope (508).
7. The overall lifting and installation construction method of the steel structure diagonal brace ceiling keel according to claim 1 is characterized by: In S2, the structural deepening work of the steel structure ceiling keel (6) is to realize the structural deepening of the steel structure ceiling keel (6) through three-dimensional visualization, material parameter extraction, simulated arrangement, virtual sample, drawing, and three-dimensional explanation; The main contents of the in-depth study include: steel structure ceiling keel (6) structural in-depth study, collision detection, installation method in-depth study, etc.; Through BIM modeling, the steel structure ceiling keel (6) is integrated and analyzed with the building main body and electromechanical pipeline model to check whether there are any collisions or conflicting parts, so as to carry out in-depth design optimization in advance.
8. The method for overall lifting and installation of the steel structure diagonal ceiling keel according to claim 1 is characterized in that: In S3, the design strength and stability of the lifting device were analyzed by using integrated finite element modeling; The structural beams, lifting device components and lifting loads are modeled by three-dimensional solid elements. The model is defined by assigning different real constants, section types and sizes, etc. The material model adopts the multi-linear isotropic hardening model (MISO). The lifting load takes the most unfavorable weight, and the design shear stress of the lifting device load node and the deformation and displacement of the slide rail (1) are simulated and verified.
9. The method for overall lifting and installation of the steel structure diagonal ceiling keel according to claim 1 is characterized in that: In S6, a trial lifting is performed before the steel structure ceiling keel (6) is lifted as a whole using a lifting device, and the lifting can be performed only after confirming that the lifting device is stable and firm, and the trial lifting height does not exceed 0.5m; The steel structure ceiling keel (6) is lifted to the installation positioning point, and the diagonal brace (7) and the embedded bracket 2 (10) are fixed using expansion bolts, and finally the steel structure ceiling keel (6) and the embedded bracket 1 (9) are installed.
10. The method for integrally lifting and installing the steel structure diagonal ceiling keel according to claim 9 is characterized in that: The steel structure ceiling keel (6) is hoisted as a whole. After the construction is completed, a measuring instrument such as a total station, a level, etc. is used to detect the distance from the ground of each hanging point, calculate the relative height difference of each hanging point, and adjust the height of each hanging point to make the steel structure ceiling keel (6) reach the designed posture; when ensuring that all design parameters are correct, the steel structure ceiling keel (6) is hoisted as a whole using a hoisting device.
Citation Information
Patent Citations
Fabricated inverted ceiling keel installation method
CN110439171A
Excavator accessory hoisting device
CN118479375A
Equipment for hoisting prefabricated arched tunnel top structure
CN214653150U
Anti-shaking hoisting device for building external wall thermal insulation material construction
CN216764113U
Hoisting structure for grouping and integrally lifting high-altitude suspended ceiling aluminum plates
CN218403389U
Cited By
Large-span space suspended ceiling unit module dividing construction method and device
CN119843818A
A method and device for constructing a large-span space ceiling unit module
CN119843818B