Autoclaved aerated concrete batten and routing channel forming process thereof

By using paper molds and wire box models in the autoclaved aerated concrete strip process of partition wall panels, high temperature and high pressure are used to form trace channels, the high cost of wire hole forming and large carbon emissions in the existing technology of partition wall panels is solved. The problem of this paper has realized a low-cost, low-carbon emission partition panel forming process.

CN119141682APending Publication Date: 2024-12-17ZHEJIANG SANFENG CONSTR CO LTD
View PDF 9 Cites 0 Cited by

Patent Information

Application Number
CN202411427999.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-14
Publication Date
2024-12-17

AI Technical Summary

Technical Problem

The existing partition wall panel wire hole molding costs are high and the carbon emissions are large. Pre-embedded core tubes increase processing costs and increase carbon emissions.

Method used

The autoclaved aerated concrete strip process is adopted. By binding paper molds and wire box models on the steel bar mesh sheet, the concrete is poured and molded in the autoclave. The paper molds are automatically softened to form trace channels and wires. The box installation slot reduces disassembly and cleaning steps, reducing processing costs and carbon emissions.

Benefits of technology

The integrated wiring channel forming in partition panels is realized, processing costs and carbon emissions are reduced, the construction process is simplified, and the construction process is in line with the requirements of green and sustainable development.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119141682A_ABST
    Figure CN119141682A_ABST
Patent Text Reader

Abstract

The invention discloses an autoclaved aerated concrete batten and a wiring channel forming process thereof. The process sequentially comprises the steps of framework building, pouring, framework inserting, drawing, demolding, cutting, edge trimming, high-temperature steam curing, wiring channel cleaning and output placing. In the production process of the partition board, the paper rod and the paper wire box model are fixed to the steel bar support, and then the paper rod and the paper wire box model are inserted into the mold for pouring together with the steel bar support. In the steam curing process of the formed green body, the paper rod and the wire box model are automatically softened, and a required wire box mounting groove and a wire passing channel are formed in the partition wall board on the premise that the opening does not need to be disassembled for mounting, so that the integrity of the wall body is greatly ensured, and the construction is very simple. Meanwhile, the waste paper rod and the paper wire box model are used as supporting molds of the wire box mounting groove and the wiring channel, and compared with the mode that the wiring channel is formed by embedding a plastic pipe, the machining method greatly reduces the machining cost.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of assembled buildings, and in particular relates to an autoclaved aerated concrete slab and a wiring channel forming process thereof. Background Art

[0002] In the prior art, partition boards are mainly used as prefabricated wall panels in non-load-bearing parts of indoor areas. They are mainly used as indoor partition walls to separate indoor spaces and provide sound insulation. At the same time, when some partition boards are used, some partition boards are pre-buried with pipelines by cutting and grooving on site, which is time-consuming and labor-intensive.

[0003] The Chinese patent with the publication number "CN111711116A" discloses a process for pre-embedding electrical conduit boxes in concrete lightweight partition wall slats, including a mold trolley, a baffle, a wall, a core-penetrating tube, a wire box, an electrical conduit and a steel support. During the wall production process, the wire box and the core-penetrating tube are pre-embedded, and then the core-penetrating tube is fixed by the steel support, and then the position of the wire box is fixed by the steel structure, and then the electrical conduit is directly inserted into the wire box by the core-penetrating tube, and the pre-embedding of the electrical conduit box is completed.

[0004] In this patent, a through-core tube is pre-buried during the processing of the partition board to form a wiring channel for the layout of the electrical pipe. The layout of the through-core tube will greatly increase the processing cost. At the same time, the machine-driven through-core tube insertion operation will also increase the carbon emissions of the entire processing process. Summary of the invention

[0005] In order to make up for the deficiencies of the prior art, the present invention provides an autoclaved aerated concrete strip board and a wiring channel forming process thereof to solve the technical problem of high cost of forming wire holes in partition boards.

[0006] To achieve the above purpose, the specific technical solutions of the present invention are as follows: On the one hand, a wiring channel forming process of an autoclaved aerated concrete slab comprises the following steps: S1, skeleton construction, according to the size of each partition board to be constructed, the steel mesh sheets of corresponding size are manually tied. Multiple transverse insertion rods arranged along the transverse direction are detachably fixed to the corresponding longitudinal steel bars through clamps. Multiple paper molds are fixed to the corresponding transverse insertion rods.

[0007] S2, pouring, pouring the mixed concrete slurry into the constructed mold.

[0008] S3, inserting the skeleton, inserting a plurality of steel mesh sheets tied with paper molds into the mold after pouring through an inserting machine, and after insertion, transporting them together with the mold to a curing room for gasification and initial solidification to form a blank body.

[0009] S4, pulling out the horizontal insertion rod inserted in the blank body. The hole left by pulling out the horizontal insertion rod forms a horizontal wiring channel.

[0010] S5, demoulding, transfer the rested blank to the cutting area. The demoulding mechanism flips the blank 90° and places it on the trolley. The molds of the blank except the bottom surface are disassembled and separated.

[0011] S6, cutting, the blank body is driven by the trolley to pass through the vertical cutting device and the horizontal cutting device in sequence to perform vertical cutting and horizontal cutting processing.

[0012] S7, edge trimming, the finished split blank is driven by a trolley, passes through the top suction device and the air blowing device in turn, and the waste on the top and bottom edges of the partition board is removed in turn. At the same time, the edge cleaning machine is used to remove the waste on the side and bottom of the split blank to form a finely trimmed blank.

[0013] S8, high temperature steam curing, the refined green body is turned over by the turning table, returned to the trolley, and transported by the trolley to the autoclave for autoclave treatment.

[0014] S9, cleaning the wiring channel, removing the pulp residue attached to the refined blank body by a flexible drilling machine, and forming a finished product.

[0015] S10, output placement, the finished partition boards that have been cleaned are hoisted and stacked, and the separated molds are transported to the mold-closing area by a trolley for cleaning and mold-closing and wait for reuse.

[0016] Furthermore, in step S3, the temperature in the resting room is 40-45° C., and the resting time is 180-240 minutes.

[0017] Furthermore, the paper mold is divided into a paper stick and a wire box model. The length direction of the paper stick is perpendicular to the horizontal insertion rod.

[0018] Furthermore, the paper stick is a hollow paper stick with a cross-sectional diameter of 15 to 60 mm. The end of the paper stick is sealed by a plastic film.

[0019] Furthermore, in step S9, the pulp residue formed by the paper stick is removed by a flexible drilling machine, and the remaining space forms a longitudinal wiring channel.

[0020] Furthermore, the flexible drilling machine adopts Yongsheng 80 type pipeline dredging machine. The dredging end of the pipeline dredging machine is 3.5-6.5m long and 15-60mm in diameter.

[0021] Furthermore, the temperature in the autoclave in step S8 is 150-200° C., the pressure is about 8-13 standard atmospheres, and the entire autoclave lasts 8-12 hours.

[0022] Furthermore, in the step S5, grooves are cut on the side surfaces of the split blanks to form concave connecting grooves.

[0023] In a second aspect, an autoclaved aerated concrete strip board includes a wire box and a wall panel body. The wall panel body includes a plurality of partition boards. Each partition board is arranged in sequence along the transverse direction, and each partition board is provided with a longitudinal wiring channel in a cavity structure. A wire box installation groove connected to the longitudinal wiring channel is provided in the middle of the longitudinal wiring channel. The wire box is embedded and fixed in the wire box installation groove.

[0024] In a third aspect, an autoclaved aerated concrete strip board includes a wire box and a wall panel body. The wall panel body includes a plurality of partition boards. The partition boards are arranged in sequence along the vertical direction. A plurality of transverse wiring channels with a cavity structure are provided in each partition board. Each transverse wiring channel is divided into a first-section wiring channel and a last-section wiring channel. The first-section wiring channel and the last-section wiring channel are connected by a connecting groove. A wire box installation groove connected to the first-section wiring channel is provided at the top of the first-section wiring channel. The wire box is embedded in the wire box installation groove.

[0025] Compared with the prior art, the present invention has the following advantages: The present invention fixes the paper stick and the paper wire box model on the steel support or the plug during the production of the partition board, and then inserts the paper stick and the steel support into the mold for casting. When the formed blank is steamed, the paper stick and the wire box model are automatically softened, tapped, and softened, and the required wire box installation groove and wiring channel are formed in the partition board without disassembling the opening for installation, which greatly ensures the integrity of the wall and is very simple to construct.

[0026] The present invention utilizes waste paper sticks and paper wire box models as support molds for the wire box installation groove and the wiring channel. Compared with the pre-buried plastic pipe, the residue formed by melting when encountering a temperature of 90 degrees is difficult to clean and thus the wiring channel cannot be formed. The processing method greatly reduces the processing cost and the carbon emissions during the processing, achieving the goal of green and sustainable development. BRIEF DESCRIPTION OF THE DRAWINGS

[0027] Figure 1 It is a schematic diagram of the process flow of the present invention; Figure 2 This is a schematic diagram of the overall structure of Example 1 of the present invention; Figure 3 This is a schematic diagram of the overall structure of Example 2 of the present invention.

[0028] Figure numerals: 1. partition board; 2. junction box; 3. first section wiring channel; 4. last section wiring channel; 5. connecting groove; 6. longitudinal wiring channel. DETAILED DESCRIPTION

[0029] In the description of the present invention, it is necessary to understand that the terms "one end", "the other end", "outside", "upper", "inside", "horizontal", "coaxial", "center", "end", "length", "outer end" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present invention.

[0030] The present invention will be further described below in conjunction with the accompanying drawings.

[0031] Example 1

[0032] like Figure 2 As shown, a kind of autoclaved aerated concrete strip board includes a wire box 2 and a wall panel body. The wall panel body includes a plurality of partition boards 1. Each partition board 1 is arranged in sequence along the vertical direction. A plurality of transverse wiring channels with a cavity structure are provided in each partition board 1. Each transverse wiring channel is divided into a first-section wiring channel 3 and a last-section wiring channel 4. Among them, the top of the first-section wiring channel 3 is provided with a wire box installation groove connected thereto. The wire box 2 is embedded in the wire box installation groove. The first-section wiring channel 3 is connected to the outside world through the wire box 2. The bottom wire opening of the last-section wiring channel 4 is arranged on the bottom surface of the corresponding partition board 1 and is connected to the outside world. A connecting groove 5 is provided between the first-section wiring channel 3 and the last-section wiring channel 4, which is used to realize the connection between the first-section wiring channel 3 and the last-section wiring channel 4, so that the wires can be arranged and routed in the first-section wiring channel 3 and the last-section wiring channel 4.

[0033] In this embodiment, there are two partition boards 1, namely, an upper first partition board 1 and a lower second partition board 1. The first section wiring channel 3 and the last section wiring channel 4 are respectively arranged on the first partition board 1 and the second partition board 1.

[0034] In this embodiment, there are two first-section wiring channels 3 on the first partition board 1, and they are arranged at intervals along the horizontal direction.

[0035] The connection groove 5 is provided on the top of the second partition board 1 and is a notch structure with an open top. The connection groove 5 is connected to the first wiring channel 3 on the first partition board 1, so that the wires in the first wiring channel 3 can be gathered at the connection groove 5 and pass through the last wiring channel 4.

[0036] In this embodiment, the first section wiring channel 3 and the last section wiring channel 4 are both arranged in the center of the thickness direction of the corresponding partition board 1. The cross-sections of the first section wiring channel 3 and the last section wiring channel 4 have circular, elliptical, square, rectangular, diamond and other shapes, which can adapt to the wiring of wires of different shapes.

[0037] like Figure 1 As shown, the wiring channel forming process of the partition board in this embodiment has the following specific steps: S1, skeleton construction, according to the size of each partition board to be constructed, manually tie the steel mesh sheets of corresponding size. Multiple transverse plug rods arranged along the transverse direction are detachably fixed to the corresponding transverse steel bars through clamps. Tie the wire box model to the corresponding transverse plug rod. Among them, the wire box model is made of water-soluble material.

[0038] S2, pouring, pouring the concrete slurry automatically mixed by the autoclaved aerated concrete raw materials into the constructed mold.

[0039] S3, insert the skeleton, insert the multiple steel mesh sheets of the binding wire box model into the mold after casting through the inserter, and transport them together with the mold to the curing room for gasification and initial condensation to form a blank body. The temperature in the curing room is 40~45℃, and the static time is 180~240min. The wire box model made of water-soluble material softens during the static process.

[0040] S4, pulling out the horizontal plug rod inserted in the blank body. The hole left by pulling out the horizontal plug rod is a horizontal wiring channel for arranging the wires.

[0041] S5, demoulding, the blank body after resting is transferred to the cutting area. The flip demoulding mechanism flips the blank body 90 degrees and places it on the trolley. After it is placed stably, the flip demoulding mechanism grabs the mold of the blank body except the bottom surface and disassembles and separates it.

[0042] S6, segmentation, the blank body is driven by the trolley to pass through the vertical cutting device and the horizontal cutting device in turn, and vertical and horizontal cutting processes are performed. Through the vertical cutting process, the excess waste material of the blank body in the length direction is removed. Through the horizontal cutting process, the blank body will be sequentially segmented into multiple segmented blanks with the same thickness as the required partition board. During the horizontal cutting process, the wire box model part set between two adjacent segmented blanks will be split in half along the middle to form two wire box installation grooves set in the two segmented blanks. At the same time, the side of the segmented blank is grooved to form a concave connecting groove.

[0043] S7, edge trimming, the split blank that has been split is carried by a trolley and passes through the top suction device and air blowing device in turn to remove the waste on the top and bottom edges of the partition board. The split blank that has completed the bottom edge trimming is transferred to the turning table by a trolley and turned 90°. With the cooperation of the edge cleaning machine, the waste on the side and bottom of the split blank is removed to form a finely trimmed blank.

[0044] S8, high temperature steam curing, the refined green body is turned over by the turning table, returned to the trolley, and transported to the autoclave for autoclave treatment. During the autoclave process, the temperature in the autoclave is 150~200℃, and the pressure is 8~13 standard atmospheres. The entire autoclave lasts for 8~12 hours. The wire box model after the refined green body is softened forms pulp under high humidity and high temperature and is applied to the corresponding channel wall.

[0045] S9, clean the wiring channel, use a flexible drilling machine or steel chisel with a length of 3.5~6.5m and a diameter of 15~60mm to clean along the hole wall of the wiring channel, remove the pulp residue attached to the hole wall, and connect it with each wiring channel to form a finished partition board. Among them, the flexible drilling machine uses Yongsheng 80 type pipeline dredging machine.

[0046] S10, output placement, the finished partition boards that have been cleaned are hoisted and stacked, and the separated molds are transported to the mold-closing area by a trolley for cleaning and mold-closing and wait for reuse.

[0047] Example 2

[0048] like Figure 3 As shown, an autoclaved aerated concrete strip board includes a wire box 2 and a wall panel body. The wall panel body includes one or more partition boards 1. Each partition board 1 is arranged in sequence along the horizontal direction, and each has a wiring channel with a cavity structure. A wire box installation groove connected to the wiring channel is provided in the middle of the wiring channel. The wire box 2 is embedded and fixed in the wire box installation groove.

[0049] like Figure 1 As shown, the wiring channel forming process of the partition board in this embodiment has the following specific steps: S1, skeleton construction, according to the size of each partition board to be constructed, manually tie the steel mesh sheets of corresponding size. Multiple transverse plug rods arranged along the horizontal direction are detachably fixed to the corresponding transverse steel bars through clamps. Tie the paper stick and the wire box model to the corresponding transverse plug rod. Among them, the wire box model is made of water-soluble material. The length direction of the paper stick is perpendicular to the length direction of the transverse plug rod. The paper stick uses a hollow paper stick with a cross-sectional diameter of 15~60mm (the hole formed by the paper stick with a diameter of 15 can pass 2 wires, the hole formed by the paper stick with a diameter of 20 can pass 4 wires, and so on). The end of the paper stick is covered with a plastic film, which can effectively prevent the softening of the paper stick due to excessive external humidity under normal temperature environment, which affects the formation of the longitudinal wiring channel. The setting of the plastic film ensures that the paper stick can only be dissolved and softened in an environment of high temperature and high pressure (temperature of 150~200℃, pressure of 8~13 standard atmospheres), thus ensuring the smooth formation of the longitudinal wiring channel and the wire box installation groove.

[0050] S2, pouring, pouring the "slurry" automatically mixed by the autoclaved aerated concrete raw materials into the constructed mold.

[0051] S3, insert the skeleton, insert the multiple steel mesh sheets of the wire box model into the mold after casting through the inserter, and transport them together with the mold to the curing room for gasification and initial condensation to form a blank. The temperature in the curing room is 40~45℃, and the static time is 180~240min. The paper stick and wire box model soften during the static process.

[0052] S4, pulling out the horizontal insertion rod inserted on the blank body. The hole left by pulling out the horizontal insertion rod is the horizontal wiring channel.

[0053] S4, demoulding, transfer the blank body after resting to the cutting area. The flip demoulding mechanism flips the blank body 90° and places it on the trolley. After it is placed stably, the flip demoulding mechanism grabs the mold of the blank body except the bottom surface and disassembles and separates it.

[0054] S5, segmentation, the blank body is driven by the trolley to pass through the vertical cutting device and the horizontal cutting device in turn, and vertical and horizontal cutting processes are performed. Through the vertical cutting process, the excess waste material of the blank body in the length direction is cut off. Through the horizontal cutting process, the blank body will be sequentially segmented into multiple segmented blanks with the same thickness as the required partition board. During the horizontal cutting process, the wire box model part set between two adjacent segmented blanks will be split in half along the middle to form two wire box installation grooves set in the two segmented blanks.

[0055] S6, edge trimming, the finished split blank is carried by a trolley, passes through the top suction device and the air blowing device in turn, and the waste on the top and bottom edges of the partition board is removed in turn. The split blank that has completed the bottom edge trimming is transferred to the turning table by a trolley and turned 90°. With the cooperation of the edge cleaning machine, the waste on the side and bottom of the split blank is removed to form a finely trimmed blank.

[0056] S7, high temperature steam curing, the refined green body is turned over by the turning table and returned to the trolley, and then transported to the autoclave for autoclave treatment. During the autoclave process, the temperature in the autoclave is 150~200℃ and the pressure is 8~13 standard atmospheres. The entire autoclave takes 8~12 hours. After the refined green body is softened, the paper stick and wire box model are formed into pulp under high humidity and high temperature and applied to the corresponding channel wall.

[0057] S8, cleaning the wiring channel, using a flexible drilling machine with a length of 3.5~6.5m and a diameter of 15~60mm to clean along the hole wall of the wiring channel, remove the pulp residue attached to the hole wall, and form a finished partition board. Among them, after the pulp formed by the paper stick is removed, the remaining space forms a longitudinal wiring channel. After the pulp residue of the wire box model is removed, the remaining space forms a wire box installation groove connected to the horizontal wiring pipe and the longitudinal wiring channel.

[0058] S9, output and placement, the finished partition boards that have been cleaned are hoisted and stacked, and the separated molds are transported to the mold-closing area by a trolley for cleaning and mold-closing and wait for reuse.

[0059] With the same number of wiring channels and wiring box layout, the comparative data of the molding cost of the wiring channels and the wiring box installation cavity in the process of Example 2 and the existing pre-embedded technology, as well as the carbon emissions during the molding process are shown in Table 1: Table 1 Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit it. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or replace some or all of the technical features therein by equivalents. However, these modifications or replacements do not cause the essence of the corresponding technical solutions to deviate from the scope of the technical solutions of the embodiments of the present invention.

Claims

1. A wiring channel forming process for autoclaved aerated concrete slabs, characterized in that: The following steps are involved: S1, skeleton construction, according to the size of each partition board to be constructed, the steel mesh sheets of corresponding size are manually tied, multiple transverse inserted rods arranged along the transverse direction are detachably fixed to the corresponding longitudinal steel bars through clamps, and multiple paper molds are fixed to the corresponding transverse inserted rods or steel mesh sheets, S2, pouring, pouring the mixed concrete slurry into the constructed mold, S3, insert the skeleton, insert multiple steel mesh sheets tied with paper molds into the mold after pouring through the inserting machine, and transport them together with the mold to the curing room for gasification and initial solidification to form a blank body. S4, pull out the horizontal plug rod inserted in the blank body, and the hole left by the removal of the horizontal plug rod forms a horizontal wiring channel. S5, demoulding, the blank body after resting is transferred to the cutting area, the demoulding mechanism flips the blank body 90 degrees, and places it on the trolley, and the molds of the parts other than the bottom surface of the blank body are disassembled and separated. S6, cutting, the blank body is driven by the trolley and passes through the vertical cutting device and the horizontal cutting device in turn to perform vertical cutting and horizontal cutting processing. S7, edge trimming, the finished split blank is driven by a trolley, passes through the top suction device and the air blowing device in turn, and the waste on the top and bottom edges of the partition board is removed in turn. At the same time, the edge cleaning machine is used to remove the waste on the side and bottom of the split blank to form a finely trimmed blank. S8, high temperature steam curing, the finished green body is turned over by the turning table, returned to the trolley, and transported to the autoclave for autoclave treatment. S9, clean the wiring channel, remove the pulp residue attached to the refined blank body by a flexible drilling machine or a steel chisel to form a finished product. S10, output placement, the finished partition boards that have been cleaned are hoisted and stacked, and the separated molds are transported to the mold-closing area by a trolley for cleaning and mold-closing and wait for reuse.

2. The wiring channel forming process of the autoclaved aerated concrete slab according to claim 1 is characterized by: In step S3, the temperature in the resting room is 40-45° C., and the resting time is 180-240 minutes.

3. The wiring channel forming process of the autoclaved aerated concrete slab according to claim 1 is characterized by: The paper mold is divided into a paper stick and a wire box model, and the length direction of the paper stick is perpendicular to the horizontal insertion rod.

4. The wiring channel forming process of the autoclaved aerated concrete slab according to claim 3 is characterized by: The paper stick is a hollow paper stick with a cross-sectional diameter of 15 to 60 mm, and the end of the paper stick is sealed by a plastic film.

5. The wiring channel forming process of the autoclaved aerated concrete slab according to claim 4 is characterized by: In step S9, the residual pulp formed by the paper stick is removed by a flexible drilling machine or a steel chisel, and the remaining space forms a longitudinal wiring channel.

6. The wiring channel forming process of the autoclaved aerated concrete slab according to claim 1 is characterized by: The flexible drilling machine adopts Yongsheng 80 type pipe dredging machine, and the dredging end of the pipe dredging machine is 3.5~6.5m long and 15~60mm in diameter.

7. The wiring channel forming process of the autoclaved aerated concrete slab according to claim 1 is characterized by: The temperature in the autoclave in step S8 is 150-200° C., the pressure is about 8-13 standard atmospheres, and the entire autoclave lasts for 8-12 hours.

8. The wiring channel forming process of the autoclaved aerated concrete slab according to claim 1 is characterized by: In the step S5, grooves are cut on the side surfaces of the split blank to form an inwardly concave connecting groove (5).

9. The autoclaved aerated concrete slat manufactured by the wiring channel forming process of the autoclaved aerated concrete slat according to claim 3, characterized in that: The invention comprises a wire box (2) and a wall panel body, wherein the wall panel body comprises a plurality of partition panels (1), each of the partition panels (1) being arranged in sequence in a transverse direction and each of the partition panels (1) being provided with a longitudinal wiring channel in a cavity structure, wherein a wire box installation groove communicating with the longitudinal wiring channel is provided in the middle of the longitudinal wiring channel, and the wire box (2) is embedded and fixed in the wire box installation groove.

10. An autoclaved aerated concrete slat manufactured by the wiring channel forming process of an autoclaved aerated concrete slat according to claim 8, characterized in that: The invention comprises a wire box (2) and a wall panel body, wherein the wall panel body comprises a plurality of partition panels (1), each of the partition panels (1) being arranged in sequence along a vertical direction and each of the partition panels (1) being provided with a plurality of transverse wiring channels in a cavity structure. Each transverse wiring channel is divided into a first-section wiring channel (3) and a last-section wiring channel (4); the first-section wiring channel (3) and the last-section wiring channel (4) are connected via a connecting groove (5); a wire box installation groove communicating with the first-section wiring channel (3) is provided at the top; and the wire box (2) is embedded in the wire box installation groove.

Citation Information

Patent Citations

  • Concrete light partition wall batten electric wire box pre-burying process

    CN111711116A

  • Autoclaved aerated concrete plate production line and production method thereof

    CN106985270A

  • Fabricated autoclaved aerated concrete plate and preparation method thereof

    CN113105199A

  • Autoclaved aerated concrete slab

    CN206737258U

  • Embedded part, concrete prefabricated part and dry hanging system

    CN209194729U