A dock anti-seepage wall construction method adaptable to various geological conditions

Through the combination of prefabricated L-shaped concrete guide wall blocks and concrete strength detection devices, the problems of large guide wall length and difficulty in pulling out joint pipes are solved, and the efficiency and flexibility of anti-seepage wall construction is achieved, and the construction cost and time are reduced.

CN119145399BActive Publication Date: 2025-02-18SEPCO ELECTRIC POWER CONSTR CORP
View PDF 3 Cites 0 Cited by

Patent Information

Application Number
CN202411666856.2
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-11-21
Publication Date
2025-02-18
Estimated Expiration
2044-11-21

AI Technical Summary

Technical Problem

In the existing anti-seepage wall construction technology, the guide wall is large in length and difficult to convert, and it takes several days to be maintained after pouring the guide wall, which affects the construction efficiency; at the same time, it is difficult to pull out the joint pipe, which leads to the failure of the anti-seepage wall and needs to be re-established. Construction is high cost.

Method used

Prefabricated L-shaped concrete guide wall blocks are connected by straight steel pipes or straight steel rods to form a "┘└"-shaped guide wall foundation groove; after concrete is poured, concrete strength detection device is used to detect concrete strength, and after reaching the set value, Use a hydraulic pipe puller to gradually pull out the joint pipe.

Benefits of technology

The flexible conversion and efficient construction of guide wall blocks are achieved, reducing construction time and cost; by accurately detecting the strength of concrete, the problem of insufficient strength of concrete caused by the inability to pull out the joint pipe or the premature ejaculation of the concrete is avoided.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119145399B_ABST
    Figure CN119145399B_ABST
Patent Text Reader

Abstract

The invention belongs to the technical field of anti-seepage wall construction, and specifically relates to a dock anti-seepage wall construction method that can adapt to various geological conditions, including measurement and positioning, prefabrication of concrete guide wall blocks, installation of concrete guide wall blocks, digging of groove holes by grooving equipment, cleaning of groove holes, and concrete pouring. Compared with the prior art, the advantages and positive effects of the invention are as follows: after the foundation groove of the anti-seepage wall guide wall in the invention is dug, a plurality of concrete guide wall blocks are tightly connected by sequentially inserting straight steel pipes or straight steel rods into the connection holes of a plurality of concrete guide wall blocks, and the longitudinal cross-sections of the two rows of concrete guide wall blocks are in a "┘└" shape; after the pouring is completed and the anti-seepage wall concrete reaches 75% of the design strength, the rows of concrete guide wall blocks are removed for circulation; through a concrete strength detection device at the bottom of a joint pipe, the strength of the concrete can be accurately detected, and when the concrete strength reaches a set value, the joint pipe is started to be pulled out to avoid the joint pipe being unable to be pulled out.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of anti-seepage wall construction, and in particular relates to a dock anti-seepage wall construction method which can adapt to various geologies. Background Art

[0002] In the prior art, the guide wall in the construction of the anti-seepage wall is cast on site, and the guide wall construction procedure is: leveling the site → measuring and determining the plane position of the guide wall → digging the guide ditch → erecting the formwork → re-measurement → pouring concrete → removing the formwork → backfilling the outer side of the guide wall and compacting it. Since the cast-in-place guide wall is long (generally tens of meters), it is very difficult to repurpose it. In addition, the guide wall needs to be cured for several days after casting before it can be put into use, which affects the efficiency of the anti-seepage wall construction.

[0003] The anti-seepage wall is usually cast with concrete, and the purpose of building a large-span anti-seepage wall is achieved through segmented construction. The adjacent anti-seepage wall sections are connected by the joint pipe method, and a joint pipe is set in advance at the end of the length of the slot hole of the anti-seepage wall. After the initial setting of the concrete, the joint pipe needs to be pulled out upward to avoid the problem that the joint pipe cannot be pulled out after the concrete is completely solidified. In the prior art, a pipe pulling machine is used to fix the upper end of the joint pipe on the surface for direct pipe pulling. The pipe pulling force is usually 350T-450T. This method of pipe pulling requires a very accurate grasp of the initial setting time of the concrete. If you are not careful, the joint pipe may not be pulled out, which will cause the entire joint pipe to be stranded in the stratum, making this section of the anti-seepage wall ineffective, and it is necessary to rebuild the anti-seepage wall next to it, which will invest huge costs. Summary of the invention

[0004] The invention aims at the technical problems existing in the construction of the anti-seepage wall in the prior art and provides a construction method of the dock anti-seepage wall which can adapt to various geological conditions.

[0005] In order to achieve the above object, the technical solution adopted by the present invention is: a method for constructing a dock cut-off wall that can adapt to various geological conditions, comprising the following steps:

[0006] S1: Measurement and positioning: measure and mark the construction ground according to the design drawings of the anti-seepage wall;

[0007] S2: The concrete guide wall block is prefabricated, and the longitudinal section of the concrete guide wall block is L-shaped; the upper and lower parts of the concrete guide wall block are both reserved with connection holes, and the concrete guide wall block is pre-embedded with a lifting ring;

[0008] S3: After the foundation trench of the cut-off wall guide wall is dug, a straight steel pipe or a straight steel rod is sequentially inserted into the connection holes of a plurality of concrete guide wall blocks to tightly connect the plurality of concrete guide wall blocks, and a row of connected concrete guide wall blocks is respectively arranged on both sides of the width of the foundation trench of the cut-off wall guide wall;

[0009] S4: using a trenching device to dig the ground, opening a trench hole for an anti-seepage wall on the ground, and filling the trench hole with mud when digging the trench hole for the anti-seepage wall;

[0010] S5: Cleaning the slot holes of the anti-seepage wall, lowering the slag discharge pipe into the slot holes of the anti-seepage wall, sucking the slurry residue at the bottom of the slot holes of the anti-seepage wall out of the slot holes of the anti-seepage wall, and replenishing fresh mud into the slot holes of the anti-seepage wall;

[0011] S6: pouring concrete in the slots of the cut-off wall; after the pouring is completed and the cut-off wall concrete reaches 75% of the design strength, the rows of concrete guide wall blocks are removed for circulation;

[0012] S7: Move the groove grabbing device and repeat steps S3-S6.

[0013] Preferably, in step S3, the longitudinal cross-sections of the two rows of concrete guide wall blocks are in a "┘└" shape; pin holes are provided at the ends of the straight steel pipes or straight steel rods, and pin shafts are inserted into the pin holes.

[0014] Preferably, the adjacent anti-seepage wall sections are connected by a joint pipe method, a joint pipe is provided in advance at the end of the length of the anti-seepage wall slot, and a concrete strength detection device is installed in the lower part of the joint pipe; the concrete strength detection device is used to detect the strength of the concrete in the lower part of the anti-seepage wall slot, and when the strength of the concrete in the lower part of the anti-seepage wall slot reaches a set value, a hydraulic pipe pulling machine is used to start pulling the joint pipe.

[0015] Preferably, the concrete strength detection device comprises a pressure detector, a ball screw, a laser displacement sensor and a controller;

[0016] The pressure detector is provided with a slider at the lower end, and the slider cooperates with the ball screw; the pressure detector includes a pressure sensor, and a probe is horizontally installed at the front end of the detection part of the pressure sensor, and the longitudinal section of the probe is circular; the ball screw is installed on the horizontal plate; the laser displacement sensor is also installed on the horizontal plate and can detect the moving distance of the pressure detector; the lower part of the joint pipe is provided with a detection hole for the probe to pass through;

[0017] The laser displacement sensor and the pressure sensor are respectively connected to the controller for communication; the ball screw is driven by a servo motor installed at the end of the horizontal plate, and the servo motor is connected to the controller for communication; the servo motor is electrically connected to an external power supply.

[0018] Preferably, there are multiple detection holes; the multiple detection holes are distributed along the height direction of the joint pipe and are in a straight line.

[0019] Preferably, an arc-shaped baffle is slidably connected to the inner wall of the joint pipe at positions corresponding to the multiple detection holes, and an electric telescopic rod is installed on the upper end of the arc-shaped baffle, and the electric telescopic rod can drive the arc-shaped baffle to rise and fall; the upper part of the electric telescopic rod is fixedly connected to the inner wall of the joint pipe through a mounting plate; the electric telescopic rod is communicatively connected to the controller.

[0020] Preferably, the concrete strength detection device also includes two electric telescopic rods 2; a connecting plate is fixedly connected in the middle of the length of the horizontal plate, and the lower ends of the piston rods of the two electric telescopic rods 2 are respectively fixedly connected to the two ends of the connecting plate; the upper part of the electric telescopic rod 2 is fixedly connected to the inner wall of the joint pipe through the mounting plate 2; the electric telescopic rod 2 is communicatively connected to the controller.

[0021] Preferably, arc blocks are fixedly connected to both ends of the horizontal plate in the length direction, and the arc blocks are slidably connected to the inner wall of the joint pipe; the concrete strength detection device also includes an infrared camera.

[0022] The infrared camera is connected to the controller for communication, and the infrared camera is mounted on the connecting plate.

[0023] Preferably, when removing the rows of concrete guide wall blocks in step S6, first pull out the straight steel pipe or straight steel rod, tie a sling to the lifting ring, lift and remove the concrete guide wall blocks one by one, and then install them on the subsequent construction surface to continue construction.

[0024] Preferably, when using a hydraulic pipe pulling machine to pull the joint pipe, the joint pipe is first pulled five to ten centimeters by the hydraulic pipe pulling machine, and then the joint pipe is moved every 15 to 20 minutes; 6 to 8 hours after the concrete is poured, the joint pipe is pulled out.

[0025] Compared with the prior art, the advantages and positive effects of the present invention are:

[0026] (1) After the foundation trench of the anti-seepage wall guide wall is dug, a plurality of concrete guide wall blocks are tightly connected by inserting straight steel pipes or straight steel rods into the connection holes of the plurality of concrete guide wall blocks in sequence, and the longitudinal cross-sections of the two rows of concrete guide wall blocks are in the shape of "┘└"; after the pouring is completed and the anti-seepage wall concrete reaches 75% of the design strength, the rows of concrete guide wall blocks are removed for turnover;

[0027] (2) Connection holes are reserved at the upper and lower parts of the concrete guide wall blocks. A straight steel pipe or a straight steel rod is inserted into the connection holes of multiple concrete guide wall blocks in sequence to achieve alignment of the concrete guide wall blocks; a pin hole is opened at the end of the straight steel pipe or the straight steel rod, and a pin shaft is inserted into the pin hole to ensure that multiple concrete guide wall blocks are tightly connected through the pin shaft;

[0028] (3) The concrete strength detection device at the bottom of the joint pipe can accurately detect the strength of the concrete. When the concrete strength reaches the set value, the joint pipe is pulled out to avoid the joint pipe being unable to be pulled out. At the same time, it also avoids the situation where the concrete has not formed enough strength to support the wall structure and the wall collapses or leaks due to premature pulling out of the pipe.

[0029] (4) When pouring concrete, the arc-shaped baffle blocks multiple detection holes;

[0030] (5) The controller above the slot displays the concrete strength detected by the pressure sensor, which helps the operator to accurately determine the timing of pipe removal;

[0031] (6) If the concrete strength value of the first test does not reach the set value, then after an interval of 10-15 minutes, use the electric telescopic rod 2 to move the horizontal plate up or down so that the probe is aligned with other test holes for retesting;

[0032] (7) The pipe section where the concrete strength testing device is located is modularized, which facilitates the application of the concrete strength testing device to the lower ends of different joint pipes. BRIEF DESCRIPTION OF THE DRAWINGS

[0033] In order to more clearly illustrate the technical solution of the embodiment of the present invention, the following is a brief introduction to the drawings required for describing the embodiment:

[0034] Figure 1 It is a flowchart of the construction method of dock cut-off wall that can adapt to various geological conditions;

[0035] Figure 2 It is a longitudinal cross-sectional schematic diagram of two rows of concrete guide wall blocks;

[0036] Figure 3 It is a diagram of the joint pipe used in the construction method of dock cut-off wall that can adapt to various geological conditions;

[0037] Figure 4 It is a perspective view of a device for testing the concrete strength of the lower part of the joint pipe;

[0038] Figure 5 It is a top view of the concrete strength detection device at the lower part of the joint pipe;

[0039] Figure 6 It is a three-dimensional diagram of the concrete strength detection device at the lower part of the joint pipe;

[0040] Figure 7 It is a schematic diagram of the arc-shaped baffle plate at the lower part of the joint pipe and the electric telescopic rod.

[0041] Description of reference numerals:

[0042] 1. Concrete guide wall block, 2. Connection hole;

[0043] 3. Connector pipe, 31. Inspection hole;

[0044] 4. Pressure detector, 5. Ball screw, 6. Electric telescopic rod 2, 7. Laser displacement sensor, 8. Horizontal plate, 9. Arc block, 10. Probe, 11. Arc baffle, 12. Electric telescopic rod 1, 13. Controller, 14. Infrared camera. DETAILED DESCRIPTION

[0045] In order to more clearly understand the above-mentioned objects, features and advantages of the present invention, the present invention is further described below with reference to the accompanying drawings and embodiments.

[0046] In the following description, many specific details are set forth to facilitate a full understanding of the present invention. However, the present invention may also be implemented in other ways than those described herein. Therefore, the present invention is not limited to the specific embodiments of the following disclosure.

[0047] Example 1

[0048] Combine the following Figure 1-Figure 7 The construction method of a dock cut-off wall that can adapt to various geological conditions in Example 1 is further described as follows: Figure 1 As shown, the construction method in this embodiment is applied to the dock anti-seepage wall project (the overall strata are divided into three strata from top to bottom: the surface to a depth of 5m is a blown fill layer, which is mainly composed of river sand, coral reefs and rock debris, with a loose structure and strong permeability; the depth range of 5m to 20m is a sand layer and a fine sand layer; the depth below 20m is a clastic rock layer), including the following steps:

[0049] S1: Measurement and positioning: measure and mark the construction ground according to the design drawings of the anti-seepage wall;

[0050] S2: The concrete guide wall block 1 is prefabricated, and the longitudinal section of the concrete guide wall block 1 is L-shaped (length 2m); the upper and lower parts of the concrete guide wall block 1 are both reserved with connection holes 2, and the concrete guide wall block 1 is pre-embedded with lifting rings;

[0051] S3: After the foundation trench of the cut-off wall guide wall is dug, a straight steel pipe or a straight steel rod is sequentially inserted into the connection holes 2 of a plurality of concrete guide wall blocks 1 to tightly connect the plurality of concrete guide wall blocks 1, and a row of connected concrete guide wall blocks 1 (50 blocks in each row) is respectively arranged on both sides of the width of the foundation trench of the cut-off wall guide wall;

[0052] S4: using a trough grabbing device (hydraulic grab bucket) to dig the ground (digging along two rows of concrete guide wall blocks 1), opening a cut-off wall slot on the ground, and filling the cut-off wall slot with mud (bentonite wall protection mud) when digging the cut-off wall slot;

[0053] S5: Cleaning the slot holes of the anti-seepage wall, lowering the slag discharge pipe into the slot holes of the anti-seepage wall, sucking the slurry residue at the bottom of the slot holes of the anti-seepage wall out of the slot holes of the anti-seepage wall, and replenishing fresh mud into the slot holes of the anti-seepage wall;

[0054] S6: pouring concrete in the slot of the anti-seepage wall; after the pouring is completed and the anti-seepage wall concrete reaches 75% of the design strength, the rows of concrete guide wall blocks 1 are removed for turnover; when removing the rows of concrete guide wall blocks 1 in step S6, first pull out the straight steel pipe or straight steel rod, tie a sling to the lifting ring, lift and remove the concrete guide wall blocks 1 one by one, and then install them on the subsequent construction surface to continue construction;

[0055] S7: Move the above-mentioned groove grabbing device and repeat steps S3-S6.

[0056] like Figure 2 As shown, in step S3, the longitudinal cross-sections of the two rows of concrete guide wall blocks 1 are in a "┘└" shape; pin holes are provided at the ends of the straight steel pipes or straight steel rods, and pin shafts are inserted into the pin holes.

[0057] like Figure 3 As shown, the joint pipe method is used to connect adjacent anti-seepage wall sections, and a joint pipe 3 (diameter 1.2m) is set in advance at the end of the length of the anti-seepage wall slot, and a concrete strength detection device is installed in the lower part of the joint pipe 3; the concrete strength detection device is used to detect the strength of the concrete at the lower part of the anti-seepage wall slot, and when the strength of the concrete at the lower part of the anti-seepage wall slot reaches a set value (the set value in this embodiment is 0.2MPa), the hydraulic pipe pulling machine is used to start pulling the joint pipe 3. In the process of pulling the joint pipe 3 by the hydraulic pipe pulling machine, the joint pipe 3 is first pulled by the hydraulic pipe pulling machine for five to ten centimeters, and then the joint pipe 3 is moved every 15 to 20 minutes; 6 to 8 hours after the concrete is poured, the joint pipe 3 is pulled out.

[0058] like Figure 4-Figure 6 As shown, the concrete strength detection device includes a pressure detector 4, a ball screw 5, a laser displacement sensor 7 and a controller 13. A slider is installed at the lower end of the pressure detector 4, and the slider cooperates with the ball screw 5; the pressure detector 4 includes a pressure sensor, and a probe 10 is horizontally installed at the front end of the detection part of the pressure sensor, and the longitudinal section of the probe 10 is circular (longitudinal section area 1 square millimeter); the ball screw 5 is installed on the horizontal plate 8; the laser displacement sensor 7 is also installed on the horizontal plate 8 and can detect the moving distance of the pressure detector 4; the lower part of the joint pipe 3 is provided with a detection hole 31 for the probe 10 to pass through.

[0059] like Figure 6 As shown, the laser displacement sensor 7 and the pressure sensor are respectively connected to the controller 13 for communication; the ball screw 5 is driven by a servo motor installed at the end of the horizontal plate 8, and the servo motor is connected to the controller 13 for communication; the servo motor is electrically connected to an external power supply.

[0060] like Figure 3 and Figure 4 As shown, there are multiple detection holes 31; the multiple detection holes 31 are distributed along the height direction of the joint pipe 3 and are located in a straight line.

[0061] like Figure 7 As shown, an arc-shaped baffle 11 is slidably connected to the inner wall of the joint pipe 3 and the corresponding positions of the multiple detection holes 31, and an electric telescopic rod 12 is installed on the upper end of the arc-shaped baffle 11. The electric telescopic rod 12 can drive the arc-shaped baffle 11 to rise and fall; the upper part of the electric telescopic rod 12 is fixedly connected to the inner wall of the joint pipe 3 through a mounting plate 1; the electric telescopic rod 12 is communicatively connected to the controller 13.

[0062] like Figure 6 As shown, the concrete strength detection device also includes two electric telescopic rods 26; a connecting plate is fixedly connected in the middle of the length of the horizontal plate 8, and the lower ends of the piston rods of the two electric telescopic rods 26 are respectively fixedly connected to the two ends of the connecting plate; the upper part of the electric telescopic rod 26 is fixedly connected to the inner wall of the joint pipe 3 through the mounting plate 2; the electric telescopic rod 26 is connected to the controller 13 for communication. The two ends of the horizontal plate 8 in the length direction are respectively fixedly connected to the arc block 9, and the arc block 9 is connected to the inner wall of the joint pipe 3 for sliding; the concrete strength detection device also includes an infrared camera 14, which is connected to the controller 13 for communication, and the infrared camera 14 is mounted on the connecting plate.

[0063] The working principle of the concrete strength detection device of the present invention is as follows: when pouring concrete, the arc baffle 11 blocks multiple detection holes 31; after 2-3 hours of concrete pouring (this time is adjusted according to the concrete composition, temperature, etc., and can be obtained through experiments), the arc baffle 11 moves up; the servo motor drives the ball screw 5 to rotate, and the pressure detector 4 and the probe 10 move toward the detection hole 31 until the probe 10 penetrates the concrete for a certain distance, and the controller 13 displays the concrete strength detected by the pressure sensor (the pressure value detected by the pressure sensor / the longitudinal cross-sectional area of ​​the probe 10). If the concrete strength value detected for the first time does not reach the set value, the horizontal plate 8 is moved up or down by the electric telescopic rod 26 at an interval of 10-15 minutes so that the probe 10 is aligned with other detection holes 31 for detection again. The distance between adjacent detection holes 31 is about 10mm, and the concrete strength corresponding to the detection holes 31 can be regarded as the same. During the detection process, the infrared camera 14 transmits the real-time image of the concrete strength detection device to the controller 13, which is convenient for the operator to control.

[0064] Example 2

[0065] The difference between this embodiment and embodiment 1 is that the concrete strength detection device is in a pipe section, and the length of the pipe section does not exceed 1m. The upper end of the pipe section is provided with an external thread, and the lower end of the joint pipe 3 is provided with an internal thread. The pipe section and the joint pipe 3 are threadedly connected, thereby realizing the modularization of the concrete strength detection device.

[0066] Example 3

[0067] The difference between this embodiment and embodiment 2 is that when the strength of the concrete at the lower part of the anti-seepage wall slot reaches 0.15 MPa, the joint pipe 3 is pulled out by a hydraulic pipe pulling machine.

[0068] The above description is only a preferred embodiment of the present invention and does not limit the present invention in other forms. Any technician familiar with the profession may use the technical content disclosed above to change or modify it into an equivalent embodiment with equivalent changes for application in other fields. However, any simple modification or equivalent change made to the above embodiment based on the technical essence of the present invention without departing from the content of the technical solution of the present invention still falls within the protection scope of the technical solution of the present invention.

Claims

1. A method for constructing a dock cut-off wall that can adapt to various geological conditions, characterized in that: The following steps are involved: S1: Measurement and positioning: measure and mark the construction ground according to the design drawings of the anti-seepage wall; S2: A concrete guide wall block (1) is prefabricated, and the longitudinal section of the concrete guide wall block (1) is L-shaped; connection holes (2) are reserved at the upper and lower parts of the concrete guide wall block (1), and a lifting ring is pre-embedded in the concrete guide wall block (1); S3: After the foundation trench of the anti-seepage wall guide wall is dug, a straight steel pipe or a straight steel rod is sequentially inserted into the connection holes (2) of a plurality of concrete guide wall blocks (1) to tightly connect the plurality of concrete guide wall blocks (1), and a row of connected concrete guide wall blocks (1) is respectively arranged on both sides of the width of the foundation trench of the anti-seepage wall guide wall; S4: using a trenching device to dig the ground, opening a trench hole for an anti-seepage wall on the ground, and filling the trench hole with mud when digging the trench hole for the anti-seepage wall; S5: Cleaning the slot holes of the anti-seepage wall, lowering the slag discharge pipe into the slot holes of the anti-seepage wall, sucking the slurry residue at the bottom of the slot holes of the anti-seepage wall out of the slot holes of the anti-seepage wall, and replenishing fresh mud into the slot holes of the anti-seepage wall; S6: pouring concrete in the slots of the anti-seepage wall; after the pouring is completed and the anti-seepage wall concrete reaches 75% of the design strength, the rows of concrete guide wall blocks (1) are removed for circulation; S7: Move the trough grabbing device and repeat steps S3-S6; Adjacent anti-seepage wall sections are connected by a joint pipe method, a joint pipe (3) is provided in advance at the end of the length of the anti-seepage wall slot, and a concrete strength detection device is installed in the lower part of the joint pipe (3); the strength of the concrete at the lower part of the anti-seepage wall slot is detected by the concrete strength detection device, and when the strength of the concrete at the lower part of the anti-seepage wall slot reaches a set value, the joint pipe (3) is pulled out by a hydraulic pipe pulling machine; The concrete strength detection device comprises a pressure detector (4), a ball screw (5), a laser displacement sensor (7) and a controller (13); A slider is installed at the lower end of the pressure detector (4), and the slider cooperates with the ball screw (5); the pressure detector (4) includes a pressure sensor, and a probe (10) is horizontally installed at the front end of the detection part of the pressure sensor, and the longitudinal section of the probe (10) is circular; the ball screw (5) is installed on the horizontal plate (8); the laser displacement sensor (7) is also installed on the horizontal plate (8) and can detect the moving distance of the pressure detector (4); the lower part of the joint pipe (3) is provided with a detection hole (31) for the probe (10) to pass through; The laser displacement sensor (7) and the pressure sensor are respectively connected to the controller (13) for communication; the ball screw (5) is driven by a servo motor installed at the end of the horizontal plate (8), and the servo motor is connected to the controller (13) for communication; the servo motor is electrically connected to an external power supply.

2. The method for constructing a dock cut-off wall that can adapt to various geological conditions according to claim 1 is characterized in that: In step S3, the longitudinal cross-sections of the two rows of concrete guide wall blocks (1) are in the shape of "┘└"; the ends of the straight steel pipes or straight steel rods are provided with pin holes, and the pin shafts are inserted into the pin holes.

3. The method for constructing a dock cut-off wall that can adapt to various geological conditions according to claim 1 is characterized in that: The number of the detection holes (31) is multiple; the multiple detection holes (31) are distributed along the height direction of the joint pipe (3) and are located in a straight line.

4. The method for constructing a dock cut-off wall that can adapt to various geological conditions according to claim 3 is characterized in that: An arc-shaped baffle (11) is slidably connected to the inner wall of the joint pipe (3) and the corresponding positions of the plurality of detection holes (31); an electric telescopic rod (12) is mounted on the upper end of the arc-shaped baffle (11); the electric telescopic rod (12) can drive the arc-shaped baffle (11) to rise and fall; the upper part of the electric telescopic rod (12) is fixedly connected to the inner wall of the joint pipe (3) via a mounting plate (1); and the electric telescopic rod (12) is communicatively connected to a controller (13).

5. The method for constructing a dock cut-off wall that can adapt to various geological conditions according to claim 4 is characterized in that: The concrete strength detection device also includes two electric telescopic rods (6); a connecting plate is fixedly connected in the middle of the length of the horizontal plate (8), and the lower ends of the piston rods of the two electric telescopic rods (6) are respectively fixedly connected to the two ends of the connecting plate; the upper part of the electric telescopic rod (6) is fixedly connected to the inner wall of the joint pipe (3) through the mounting plate (2); and the electric telescopic rod (6) is in communication connection with the controller (13).

6. The method for constructing a dock cut-off wall that can adapt to various geological conditions according to claim 5 is characterized in that: The two ends of the horizontal plate (8) in the length direction are respectively fixedly connected with arc blocks (9), and the arc blocks (9) are slidably connected to the inner wall of the joint pipe (3); the concrete strength detection device also includes an infrared camera (14), the infrared camera (14) is communicatively connected to the controller (13), and the infrared camera (14) is mounted on the connection plate.

7. The method for constructing a dock cut-off wall that can adapt to various geological conditions according to claim 2, characterized in that: When removing the rows of concrete guide wall blocks (1) in step S6, first pull out the straight steel pipe or straight steel rod, tie a sling to the lifting ring, lift and remove the concrete guide wall blocks (1) one by one, and then install them on the subsequent construction surface to continue construction.

8. The method for constructing a dock cut-off wall that can adapt to various geological conditions according to claim 1, characterized in that: When the joint pipe (3) is pulled out by the hydraulic pipe pulling machine, the joint pipe (3) is first pulled out by five to ten centimeters, and then the joint pipe (3) is moved once every 15 to 20 minutes; 6 to 8 hours after the concrete is poured, the joint pipe (3) is pulled out.

Citation Information

Patent Citations

  • Construction method of deep foundation pit enclosure structure of subway station

    CN110747862A

  • Construction method for pulling joint pipe in underground diaphragm wall section connection construction

    CN111794230A

  • Foundation pile concrete strength detection method and device

    CN118641362A