Electrical inspection work package design method and system based on construction rules

Through the electrical inspection work package design method based on construction rules, the problems of inefficient expression of inspection processes, complicated design changes and dispersed information in electrical ship design and construction are solved, and the structured expression and data storage of inspection processes are realized, and the design is improved Efficiency and quality control.

CN119150455APending Publication Date: 2024-12-17JIANGNAN SHIPYARD (GRP) CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411209688.4
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-30
Publication Date
2024-12-17

AI Technical Summary

Technical Problem

The existing electrical ship design and construction model has problems such as insufficient expression of inspection processes, complicated design changes, prone to errors, and strong dispersion and abstraction of inspection information, which affects the design and construction progress, quality and risk control.

Method used

Using the electrical inspection work package design method based on construction rules, the structured expression and issuance of the inspection process is realized by generating the inspection work package, the inspection items and requirements are defined, the general electronic form is generated, and it is associated with the three-dimensional model to form a structure. Integrated inspection work packages ensure data storage and communication.

Benefits of technology

The inspection process design efficiency is improved, ensuring that on-site construction personnel accurately understand the design intention, improving inspection quality and efficiency, laying a data foundation for quality analysis, and reducing risks in the design and construction process.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119150455A_ABST
    Figure CN119150455A_ABST
Patent Text Reader

Abstract

The invention provides an electrical inspection work package design method and system based on construction rules, and the method achieves the structural expression and issuing of an inspection process through the generation of an inspection work package, improves the design efficiency of the process, and improves the design efficiency of the electrical inspection work package. It is ensured that on-site constructors can more accurately understand the intention of a designer, and the inspection quality and efficiency are improved; meanwhile, the inspection data and the structure are received and stored by utilizing the inspection work packet, and a data foundation is laid for further quality analysis.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of ship electrical inspection, and in particular to a construction rule-based electrical inspection work package design method and system. Background Art

[0002] Electrical ship design is a key link in ship design and construction, involving ship cable laying, electrical equipment installation and related support and penetration installation design. These designs are not only related to the safety and comfort of the cabin space, but also have an important impact on the operating efficiency and reliability of the entire ship. However, the existing electrical design and construction model has some limitations, which are mainly manifested in the following aspects: the expression of the inspection process. The current inspection process mainly adopts a file-type design model, which is compiled and expressed in the form of documents. This method is not conducive to the storage and circulation of inspection result information, nor is it conducive to information sharing between all parties; the handling of design changes. When the design changes, the process personnel need to manually find and modify the documents. This process is inefficient and prone to errors; the way of conveying inspection information. Various types of inspection information are scattered and conveyed in the form of two-dimensional drawings, resulting in scattered and abstract inspection information, which is not conducive to further analysis of inspection data.

[0003] These limitations of existing technologies lead to inefficient expression and circulation of inspection processes, affecting the progress and quality of the entire design and construction process; the design change process is cumbersome and error-prone, increasing the risks in the design and construction process; the dispersion and abstractness of inspection information limits the in-depth analysis and utilization of data, affecting the possibility of quality control and subsequent improvements.

[0004] Therefore, in order to achieve structured expression and distribution of inspection processes, improve process design efficiency, ensure that on-site construction personnel can accurately understand the designer's intentions, and improve inspection quality and efficiency, this application provides an electrical inspection work package design method and system based on construction rules. Summary of the invention

[0005] In view of the many drawbacks of the existing electrical technology, this application provides a construction rule-based electrical inspection work package design method and system. The construction rule-based electrical inspection work package design method generates an inspection work package to achieve structured expression and distribution of the inspection process, improve process design efficiency, ensure that on-site construction personnel understand the designer's intention more accurately, and improve inspection quality and efficiency; at the same time, the inspection work package is used to receive and store inspection data and structure, laying a data foundation for further quality analysis.

[0006] An embodiment of the present application provides a method for designing an electrical inspection work package based on construction rules, comprising the following steps:

[0007] Inspection standard determination: According to the construction rules, the inspection rules are formulated based on comprehensive consideration of the electrical construction links;

[0008] Inspection item definition: Based on the three-dimensional model, inspection items are formed according to the inspection rules. Each inspection item generates a unique serial code identifier, which is defined in the form of attributes in the electrical construction component, stored in the database, and associated with the inspection standard;

[0009] Inspection requirements definition: The inspection requirements include inspection elements, inspection levels and inspection methods;

[0010] Inspection form definition: extract the model information, inspection serial code, inspection item information, inspection requirement information, and inspection result information of electrical components to generate a general electronic form;

[0011] Generation of inspection work package: the generated inspection form is associated with the inspected three-dimensional model and packaged to generate the inspection work package.

[0012] As an implementation method, the construction rules used in determining the inspection standards include various standards, shipowner and ship inspection requirements, and construction requirements based on on-site safety factors and quality factors.

[0013] As an implementation method, the electrical construction process includes the production and installation of electrical support parts, the production and installation of penetration parts, the laying of cables, and the installation of electrical equipment.

[0014] As an implementation method, in addition to the electrical construction process, the inspection standards must also fully consider the factors of construction area, construction stage, and component type, and formulate the inspection items required in various situations. The inspection standards are finally summarized into an inspection standard table and stored in the database.

[0015] As an implementation method, the inspection elements in the inspection requirement definition include chemical composition, mechanical properties, weight center of gravity, external dimensions, surface quality, welding quality, and integrity.

[0016] As an implementation mode, the inspection level in the inspection requirement definition is determined by formulating the inspection execution unit with reference to the hull construction requirements and the actual situation of the shipyard.

[0017] As an implementation method, the determination of the inspection method in the inspection requirement definition includes environmental requirements, tool requirements, inspection procedures, and operation requirements, which must ensure safe operations and accurate data.

[0018] As an implementation method, the inspection form definition specifically includes:

[0019] The inspection form is bound to the inspection serial code in the inspection item definition. Based on the three-dimensional model of the electrical component, the inspection item list data is automatically generated from the model attribute information of the electrical component, the inspection item definition and the inspection requirement definition, and the relevant data is extracted and filled into the general inspection template. A special electronic inspection form for the corresponding inspection item of the corresponding electrical component is automatically generated. Each inspection form corresponds to an independent inspection serial code.

[0020] As an implementation method, after the inspection work package is generated, according to the inspection level and model making information in the inspection requirement definition, information technology is used to find the designated inspection site personnel and send the inspection work package to the site. The site personnel open the inspection work package on a fixed or mobile terminal and complete the inspection work with reference to the inspection work package.

[0021] An embodiment of the present application provides an electrical inspection work package design system based on construction rules, including:

[0022] The inspection standard determination module is used to specify the inspection rules according to the construction rules and comprehensive consideration of the electrical construction links;

[0023] An inspection item definition module is used to form inspection items based on the three-dimensional model and the inspection rules, each of which generates a unique serial code identifier, which is defined in the form of attributes in the electrical construction component, stored in the database, and associated with the inspection standard;

[0024] Inspection requirement definition module, used to determine inspection elements, inspection levels and inspection methods;

[0025] The inspection form definition module is used to extract the model information, inspection serial code, inspection item information, inspection requirement information, and inspection result information of electrical components to generate a general electronic form;

[0026] The inspection work package generation module is used to associate and package the generated inspection form with the inspected three-dimensional model to generate the inspection work package.

[0027] As described above, the construction rule-based electrical inspection work package design method and system of the present application have the following beneficial effects:

[0028] The electrical inspection work package design method based on construction rules of the present application realizes the structured expression and distribution of the inspection process by generating the inspection work package, thereby improving the efficiency of process design, ensuring that on-site construction personnel understand the designer's intention more accurately, and improving the inspection quality and efficiency; at the same time, the inspection work package is used to receive and store the inspection data and structure, laying a data foundation for further quality analysis. BRIEF DESCRIPTION OF THE DRAWINGS

[0029] Figure 1It shows a flowchart of the steps of the construction rule-based electrical inspection work package design method according to the first embodiment of the present invention.

[0030] Figure 2 Shown is a schematic diagram of an inspection standard table in a construction rule-based electrical inspection work package design method according to a first embodiment of the present invention.

[0031] Figure 3 It shows a schematic diagram of a three-dimensional model in the inspection item definition step in the construction rule-based electrical inspection work package design method of the first embodiment of the present invention.

[0032] Figure 4 A schematic diagram showing an inspection list generated by the inspection item definition step and the inspection requirement definition step in the construction rule-based electrical inspection work package design method according to the first embodiment of the present invention. DETAILED DESCRIPTION

[0033] The following describes the embodiments of the present invention through specific examples, and those skilled in the art can easily understand other advantages and effects of the present invention from the contents disclosed in this specification. The present invention can also be implemented or applied through other different specific embodiments, and the details in this specification can also be modified or changed in various ways based on different viewpoints and applications without departing from the spirit of the present invention.

[0034] It should be noted that the illustrations provided in this embodiment are only used to illustrate the basic concept of the present invention in a schematic manner, and therefore the illustrations only show components related to the present invention rather than being drawn according to the number, shape and size of components in actual implementation. In actual implementation, the type, quantity and proportion of each component may be changed arbitrarily, and the component layout may also be more complicated.

[0035] In the field of ship design and construction, electrical ship design is a key link that directly affects the navigation safety, operational efficiency and comfort of passengers or crew members. Electrical design covers many aspects, from cable laying, electrical equipment installation to the installation design of related supports and penetrations. These design details are not only complex but also highly dependent on precise space layout and coordination to ensure the reliable operation of the electrical system and the safety and comfort of the cabin environment.

[0036] However, there are several significant technical bottlenecks and deficiencies in the traditional electrical design, construction and inspection process, which are specifically reflected in the following aspects:

[0037] Limitations of the document-based design model: Currently, the design and expression of electrical inspection processes mainly rely on document forms, such as two-dimensional drawings and reports. This approach not only increases the complexity of information storage and circulation, but also limits the immediacy and dynamism of information, which is not conducive to effective communication and information sharing among multiple parties such as design, construction, and inspection;

[0038] Inefficiency in handling design changes: When a design changes, process personnel need to manually search and modify relevant documents one by one. This process is cumbersome and time-consuming, and is prone to errors due to human negligence, seriously affecting the efficiency of design iteration and construction progress;

[0039] Abstract and fragmented inspection information: Inspection information is usually presented in the form of two-dimensional drawings, which are abstract and scattered, and it is difficult to intuitively reflect the actual status and potential problems of the electrical system. This way of presenting information not only increases the difficulty of the inspectors' work, but also limits the possibility of in-depth analysis and mining of inspection data, thus affecting the improvement of the overall inspection quality and efficiency;

[0040] Lack of support for structured work packages: The traditional inspection process lacks a structured work package design based on construction rules, resulting in unclear inspection task allocation and inconsistent implementation standards, making it difficult to form an effective quality traceability and management system. At the same time, the storage and management of inspection data and results also lacks systematicity, making it difficult to provide comprehensive and accurate data support for subsequent quality analysis.

[0041] In view of the above defects, the present application provides a method for designing an electrical inspection work package based on construction rules, which is now described in detail through the following embodiments.

[0042] Embodiment 1

[0043] This embodiment provides a method for designing an electrical inspection work package based on construction rules, such as Figure 1 As shown, the design method includes the following steps:

[0044] S100. Determination of inspection standards: Based on the construction rules, inspection rules are formulated based on comprehensive consideration of the electrical construction links.

[0045] The construction rules include the "General Standards for Ship Construction" and other standards, as well as shipowner and ship inspection requirements. The electrical construction process includes but is not limited to the production and installation of electrical support parts, production and installation of penetration parts, cable laying, and electrical equipment installation.

[0046] The inspection should fully consider the requirements of all parties, including but not limited to shipowner inspections, various standards, and construction requirements based on on-site safety factors, quality factors, etc. In addition to the construction stage, the inspection standards should fully consider factors including but not limited to the construction area, construction stage, component type, etc., and formulate the inspection items required in various situations. The inspection standards are finally summarized into an inspection standard table and stored in the database for subsequent quick query. Figure 2 shown.

[0047] S200, inspection item definition: Based on the three-dimensional model, inspection items are formed according to inspection rules. Each inspection item generates a unique serial code identifier, which is defined in the form of attributes in the electrical construction component, stored in the database, and associated with the inspection standard.

[0048] For example, according to Figure 2 According to the inspection standard example, cable laying must include but is not limited to the following: laying in accordance with design requirements, verifying cable specifications and certificates, bending curvature meets regulations, avoiding moisture and condensation, and not damaging the cable insulation sheath.

[0049] Therefore, a certain section of cable-type components (cable01) needs to be inspected for compliance with regulations and avoidance of moisture and condensation in the "cable laying" link, "laying" stage, and "upper construction area". The inspection item codes are "cablecheck0003" and "cablecheck0004" respectively. Two inspection serial codes "cable01_cablecheck0003_001" and "cable01_cablecheck0004_001" are generated for the above inspection items of compliance with regulations and avoidance of moisture and condensation. The serial codes are stored in the electrical components and the database at the same time. The electrical component model information of the inspection item can be traced back by changing the code, and the corresponding inspection standards, inspection requirements, inspection results, etc. in the database can also be found. The three-dimensional model is shown as follows Figure 3 shown.

[0050] The checklist database storage table format is as follows Figure 4 .

[0051] S300, Inspection requirements definition: Inspection requirements include inspection elements, inspection levels and inspection methods.

[0052] Determine the inspection factors: including but not limited to chemical composition, mechanical properties, weight center of gravity, external dimensions, surface quality, welding quality, integrity, etc. For example, the cable curvature item needs to be inspected in step S200.

[0053] Determine the inspection level: refer to the hull construction requirements and the actual situation of the shipyard to specify the inspection execution unit. For example, there are the following types: Level I, which requires self-inspection by on-site operators and inspection by team leaders; Level II, which requires self-inspection by on-site operators and inspection by team leaders, and special inspection by the quality management department; Level III, which requires self-inspection by on-site operators and inspection by team leaders, special inspection by the quality management department, and inspection by the shipowner. Among them, according to the name of the electrical components and the defined inspection items and inspection elements, the inspection level can be automatically pushed for the process personnel to choose.

[0054] Determine the inspection method: If necessary, provide inspection guidance, including environmental requirements, tool requirements, inspection procedures, operating requirements, etc., to ensure safe operation and accurate data.

[0055] Steps S200 and S300 generate a list of inspection items and store them in a database. The list means Figure 4 shown.

[0056] S400, inspection form definition: extract model information, inspection serial number, inspection item information, inspection requirement information, and inspection result information of electrical components, and generate a general electronic form.

[0057] The inspection form is bound to the inspection serial code in step S200. Based on the three-dimensional model of the electrical component, the relevant data is automatically extracted from the model attribute information of the electrical component and the inspection item list data generated in steps S200 and S300, and filled into the general inspection template, and a special electronic inspection form corresponding to the inspection item of the corresponding electrical component is automatically generated. Each inspection form corresponds to a separate inspection serial code. The on-site personnel feedback the inspection data and results of the inspection in the electronic form. In this way, an inspection form covers all inspection information except the three-dimensional model itself. At the same time, the form format is fixed, making the inspection data structured.

[0058] S500, generating an inspection work package: associating and packaging the generated inspection form with the inspected three-dimensional model to generate an inspection work package.

[0059] The electrical inspection work package includes the inspection form in step S400, and the three-dimensional model to be inspected is added. After the work package is generated, according to the inspection level and model making information (including but not limited to segmentation, stage, etc.) in step S300, the designated inspection site personnel are found with the help of information technology and the inspection work package is sent to the site. The site personnel open the electrical inspection work package on a fixed or mobile terminal and complete the inspection work with reference to the inspection work package.

[0060] Embodiment 2

[0061] This embodiment provides an electrical inspection work package design system based on construction rules. The design system includes: an inspection standard determination module, an inspection item definition module, an inspection requirement definition module, an inspection form definition module and an inspection work package generation module.

[0062] The inspection standard determination module is used to specify inspection rules based on construction rules and comprehensive consideration of electrical construction links.

[0063] The inspection standard determination module is used to determine which regulations should be referred to for electrical inspection and which inspection items should be performed; the inspection standard determination module forms a database that matches the electrical components, and can quickly match the inspection items that should be done through the three-dimensional model stage, type and other features.

[0064] The inspection item definition module is used to form inspection items based on the three-dimensional model and inspection rules. Each inspection item generates a unique serial code identifier, which is defined in the form of attributes in the electrical construction components, stored in the database, and associated with the inspection standards.

[0065] The inspection item definition module is used to match the inspection items of the characteristic electrical components based on the model characteristics through the inspection standards, and identify the inspection items with unique serial codes and bind them to the electrical components; the inspection item information is stored in the database and identified with serial codes; the serial codes are also stored in the electrical component model attributes.

[0066] The inspection requirement definition module is used to determine the inspection elements, inspection levels and inspection methods.

[0067] The inspection requirement definition module is used to determine how the inspection items are specifically performed. The inspection elements determine which attributes need to be inspected. The inspection level determines the person responsible for the inspection. The inspection method provides environmental requirements, tool requirements, inspection procedures, operational requirements, etc. to ensure safe operations and accurate data. After the inspection requirements are determined, the inspection item is automatically pushed to the process personnel at the designated inspection level.

[0068] The inspection form definition module is used to extract the model information, inspection serial code, inspection item information, inspection requirement information, and inspection result information of electrical components to generate a general electronic form.

[0069] The inspection form definition module is used to form a general electronic form that is bound to specific inspection items. When electrical components need to be inspected, all the information of the inspection items and the three-dimensional model attribute information are automatically filled into the electronic form, and pushed to the designated inspection level process personnel along with the inspection items, waiting for the on-site personnel to feedback the inspection data and results in the electronic form.

[0070] The inspection work package generation module is used to associate and package the generated inspection form with the inspected three-dimensional model to generate the inspection work package.

[0071] The inspection work package generation module is used to bind the inspection form with the inspected 3D model to form a more intuitive and clear visual inspection work package; the inspection work package contains the 3D model and the inspection form, and the inspection item information and relevant standards and specifications can be checked through the inspection form; on-site personnel open the electrical inspection work package on a fixed or mobile terminal and complete the inspection work with reference to the inspection work package.

[0072] The above embodiments are merely illustrative of the principles and effects of the present invention, and are not intended to limit the present invention. Anyone familiar with the art may modify or alter the above embodiments without departing from the spirit and scope of the present invention. Therefore, all equivalent modifications or alterations made by a person of ordinary skill in the art without departing from the spirit and technical concept disclosed by the present invention shall still be covered by the claims of the present invention.

Claims

1. A construction rule-based electrical inspection work package design method, characterized in that: The following steps are involved: Inspection standard determination: According to the construction rules, the inspection rules are formulated based on comprehensive consideration of the electrical construction links; Inspection item definition: Based on the three-dimensional model, inspection items are formed according to the inspection rules. Each inspection item generates a unique serial code identifier, which is defined in the form of attributes in the electrical construction component, stored in the database, and associated with the inspection standard; Inspection requirements definition: The inspection requirements include inspection elements, inspection levels and inspection methods; Inspection form definition: extract the model information, inspection serial code, inspection item information, inspection requirement information, and inspection result information of electrical components to generate a general electronic form; Generation of inspection work package: the generated inspection form is associated with the inspected three-dimensional model and packaged to generate the inspection work package.

2. The design method according to claim 1, characterized in that: The construction rules used in determining the inspection standards include various standards, shipowner and ship inspection requirements, and construction requirements based on on-site safety and quality factors.

3. The design method according to claim 1 or 2, characterized in that: The electrical construction process includes the production and installation of electrical support parts, the production and installation of penetration parts, cable laying, and electrical equipment installation.

4. The design method according to claim 1, characterized in that: In addition to the electrical construction phase, the inspection standards must also fully consider the factors of construction area, construction stage, and component type, and formulate the inspection items required in various situations. The inspection standards are finally summarized into an inspection standard table and stored in the database.

5. The design method according to claim 1, characterized in that: The inspection elements in the inspection requirement definition include chemical composition, mechanical properties, weight center of gravity, external dimensions, surface quality, welding quality, and integrity.

6. The design method according to claim 1, characterized in that: The inspection level in the inspection requirement definition is determined by referring to the hull construction requirements and the actual situation of the shipyard to formulate the inspection execution unit.

7. The design method according to claim 1, characterized in that: The determination of the inspection method in the inspection requirement definition includes environmental requirements, tool requirements, inspection procedures, and operation requirements, which must ensure safe operations and accurate data.

8. The design method according to claim 1, characterized in that: The inspection form definition specifically includes: The inspection form is bound to the inspection serial code in the inspection item definition. Based on the three-dimensional model of the electrical component, the inspection item list data is automatically generated from the model attribute information of the electrical component, the inspection item definition and the inspection requirement definition, and the relevant data is extracted and filled into the general inspection template. A special electronic inspection form for the corresponding inspection item of the corresponding electrical component is automatically generated. Each inspection form corresponds to an independent inspection serial code.

9. The design method according to claim 1, characterized in that: After the inspection work package is generated, according to the inspection level and model making information in the inspection requirement definition, the designated inspection site personnel are found with the help of information technology and the inspection work package is sent to the site. The site personnel open the inspection work package on a fixed or mobile terminal and complete the inspection work with reference to the inspection work package.

10. An electrical inspection work package design system based on construction rules, characterized in that: include: The inspection standard determination module is used to specify the inspection rules according to the construction rules and comprehensive consideration of the electrical construction links; An inspection item definition module is used to form inspection items based on the three-dimensional model and the inspection rules, each of which generates a unique serial code identifier, which is defined in the form of attributes in the electrical construction component, stored in the database, and associated with the inspection standard; Inspection requirement definition module, used to determine inspection elements, inspection levels and inspection methods; The inspection form definition module is used to extract the model information, inspection serial code, inspection item information, inspection requirement information, and inspection result information of electrical components to generate a general electronic form; The inspection work package generation module is used to associate and package the generated inspection form with the inspected three-dimensional model to generate the inspection work package.