Molding production task scheduling method

Through the scheduling method of molding production tasks, including project establishment, design review, preliminary preparation and production processing, the problem of mismatch in the production process of molding enterprises is solved, and efficient and high-quality mold product production is achieved.

CN119204528APending Publication Date: 2024-12-27NINGBO GUDE MOULD & PLASTIC CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411263913.2
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-10
Publication Date
2024-12-27

AI Technical Summary

Technical Problem

The molding companies lack standardized production task scheduling processes, resulting in mismatch in task progress during the production process and reducing production efficiency.

Method used

Adopt a scheduling method for molding production tasks, including project establishment, design review, preliminary preparation, production and processing, product inspection and other steps. Through the establishment of project management folders and multi-party collaborative tracking, ensure the reasonable arrangement and quality control of production plans. .

Benefits of technology

It achieves high efficiency and high quality completion of mold products needed by customers. Through reasonable production planning and timely quality feedback, production efficiency and product quality are improved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119204528A_ABST
    Figure CN119204528A_ABST
Patent Text Reader

Abstract

The invention discloses a scheduling method for molding production tasks. The scheduling method comprises the following steps of establishing a related project group according to a project notification of a client and formulating a development directory; selecting professionals to perform product analysis according to the development catalog, and feeding back to the customer based on an analysis result; after the customer puts forward a requirement, design adjustment is carried out according to the customer requirement, and product analysis is carried out again until the customer requirement is met; purchasing and warehousing the raw materials and making a processing plan based on a review result; machining nodes are implemented based on the machining plan, and workpiece machining is conducted; and the machined workpieces are subjected to quality inspection, and unqualified workpieces are required to be reworked. The beneficial effects of the invention are that compared with a traditional production process without determination of planning and scheduling, the invention provides a scheduling method based on actual production, the production plan can be reasonably arranged, and the feedback can be provided for the client at a specified time node. Therefore, mold products required by customers can be finished with high efficiency and high quality.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of molding production, and in particular to a method for scheduling molding production tasks. Background Art

[0002] For molding companies, the production of plastic products is a long process from receiving an order to the completion of the production of all products. For example, it needs to go through the processes of preliminary preparation, design, mold trial, production and transportation, and in these processes, it is also necessary to coordinate with multiple parties. However, at present, molding companies generally lack a more standardized scheduling process for molding production tasks, which often leads to mismatches in task progress between the various production processes of a plastic product, resulting in reduced product production efficiency. Based on this, there is an urgent need for a scheduling method that can effectively improve molding production efficiency. Summary of the invention

[0003] One of the objects of the present application is to provide a method for scheduling molding production tasks that can solve at least one of the defects in the above-mentioned background technology.

[0004] In order to achieve at least one of the above purposes, the technical solution adopted by the present application is: a method for scheduling molding production tasks, comprising the following steps:

[0005] Project establishment: The project department establishes relevant project teams and formulates development catalogues according to the customer's project notification;

[0006] Design review: The project department selects professionals to conduct product analysis based on the development catalog and provides feedback to customers based on the analysis results. After the customer makes a request, the design is adjusted according to the customer's requirements and the product is analyzed again until it meets the customer's requirements.

[0007] Preliminary preparation: The outsourcing department purchases and stores raw materials and formulates processing plans based on the review results;

[0008] Production and processing: The production department implements the processing nodes based on the processing plan and processes the workpieces; the project department, outsourcing department and production department simultaneously track the entire processing process in order to handle any quality accidents in a timely manner;

[0009] Product testing: The quality department conducts quality inspection on the finished workpieces and requires rework for the workpieces that do not meet the quality requirements until all the workpieces meet the quality requirements and then assemble the test molds; based on the results of the test molds, the workpieces are improved on site to meet the requirements and submitted to the customer for confirmation through the project department.

[0010] Preferably, project establishment includes a project initiation phase and a project planning phase; in the project initiation phase, the project initiation notification from the customer is received, and a project management folder is established within a specified time for project records after completing communication with the customer; in the project planning phase, a design plan, a manufacturing plan, and a customer plan are formulated in sequence, and data and mold-related information are locked according to the formulated plans to obtain a development catalog recorded in the project management folder.

[0011] Preferably, for the formulation of the design plan, select suitable designers to form a project design team, provide a design plan within the specified time, and complete the project technical confirmation and establish a development catalog through synchronization with the project department and the production department; for the manufacturing plan, select suitable production personnel to form a project production team, fill the personnel list into the development catalog to complete the production plan; for the customer plan, combine the design plan and the manufacturing plan to build a framework diagram of the project members and determine the responsibilities, and at the same time prepare the customer plan schedule within the specified time and submit it to the customer; when locking the data, the project design team will register the receipt of the project data, and when any node that affects the delivery date occurs, it must be reported to the customer and the project record sheet must be recorded in the development catalog.

[0012] Preferably, the design review includes an analysis phase, a review phase, and a data locking phase; in the analysis phase, the structure, function, process, and performance of the product are analyzed; in the review phase, the analysis results are modified through reviews by both the enterprise and the customer until they meet customer requirements; in the data locking phase, the product processing data is determined based on the final review results of the customer and the enterprise.

[0013] Preferably, the analysis phase includes product analysis and mold flow analysis; for product analysis, the following processes are included: preliminarily determine the injection position, number of points, structural direction, mold shape and machine model according to the function, appearance and matching requirements of the product; record the preliminary confirmed data, and propose unreasonable points based on the preliminary analysis to form a standard DFM report; send the obtained DFM report to the customer and reach an agreement with the customer within the specified time; for mold flow analysis, the following processes are included: according to the nodes determined in the project establishment stage, complete various analyses within the specified time according to the mold flow requirements to obtain the mold flow report; send the obtained mold flow report to the customer, and multiple mold flow reports need to be displayed to the customer in the form of a comparison table; among them, the mold flow report must be a terminal solution with terminal water channel mold manufacturing.

[0014] Preferably, the review stage includes internal review, customer review and re-review; the internal review includes the following process: organizing relevant technical personnel of the enterprise to conduct an internal preliminary review of the terminal solution of the mold flow report according to customer requirements and enterprise standards; recording and archiving the results of the preliminary review and completing the mold calculation book, customer review form and mold design inspection standards; the customer review includes the following process: making an appointment with the customer based on the task node and communicating with the customer with relevant materials of the internal review, and recording the customer's review requirements to facilitate subsequent design adjustments; the re-review includes the following process: organizing relevant technical personnel to conduct a final internal verification and review of the mold according to the customer's review requirements, and replying to the customer with the review results.

[0015] Preferably, product testing includes component testing stage, assembly and trial mold stage and adjustment and improvement stage; in the component testing stage, the quality department prepares a testing plan according to the processing plan, conducts quality inspection on the workpieces used to assemble the mold according to the formulated testing plan and issues an inspection report; qualified parts are put into storage, and a defective part handling report is required for unqualified parts; the quality department issues a quality accident handling unit to the production department and outsourcing department based on the defective part handling report and requires rework; in the assembly and trial mold stage, the production department provides the project department with a new product trial mold process sheet within the specified time after completing the preparations before the trial mold; the project department submits a mold construction application to the production department within the specified time according to customer needs and records it to obtain a trial mold plan statistical table; according to the trial mold plan statistics The scientific mold trial process sheet will be provided to the site simultaneously. After approval, the production department will prepare for the mold trial according to the mold trial regulations; after the mold trial is completed, the project department will pack the samples according to the customer's requirements and arrange for shipment. For samples that are identified as undesirable or have quality problems, written confirmation is required from the customer and packaging and shipment will be arranged after acceptance; in the adjustment and improvement stage, according to the problems encountered during the mold trial and the customer's design change requirements, the project department organizes the production department and the project design team to provide a mold design change analysis report within the specified time and send it to the customer for confirmation; after the customer confirms, the project department issues a change order to the production department and the project design team for design changes; before making design changes, keep evidence and submit to the customer for confirmation after the design changes are completed to complete product locking.

[0016] Preferably, during the assembly and mold trial stage, the mold trial must undergo a comprehensive test of short shot, sample delivery and destruction and record the results to obtain a mold trial tracking sheet; the project department uses the destructive samples as mold repair parts to confirm the problem and then fills out the mold trial problem sheet and hands it over to the production department; the production department completes the mold trial problem sheet within the specified time for subsequent adjustments and improvements.

[0017] Preferably, during the product locking stage, for plain panels or leather-grained parts, the project department will label the first and last pieces and seal them into storage based on the customer's confirmation; for non-appearance parts, the project department requires the customer to confirm the gradient sealing before labeling the first and last pieces and sealing them into storage.

[0018] Preferably, the product will be shipped out after completing product testing. During the product shipping stage, the project department will urge other relevant departments to improve the mold manual and conduct internal acceptance and customer acceptance of the mold within the specified time, and then transport the mold out of the warehouse to the customer's location for signature; when the customer conducts trial production on the signed mold, the project department needs to reach the enterprise site for trial production tracking.

[0019] Compared with the prior art, the beneficial effects of this application are:

[0020] Compared with the traditional production process without a certain planning and scheduling, this application provides a scheduling method based on actual production, which can reasonably arrange the production plan and provide feedback to customers at the specified time node, so as to complete the mold products required by customers with high efficiency and high quality. BRIEF DESCRIPTION OF THE DRAWINGS

[0021] Figure 1 The figure is a schematic diagram of the overall workflow of this application. DETAILED DESCRIPTION

[0022] Below, the present application is further described in conjunction with specific implementation methods. It should be noted that, under the premise of no conflict, the various embodiments or technical features described below can be arbitrarily combined to form new embodiments.

[0023] In the description of the present application, it should be noted that directional words, such as the terms "center", "lateral", "longitudinal", "length", "width", "thickness", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", "clockwise", "counterclockwise", etc., indicating directions and positional relationships are based on the directions or positional relationships shown in the accompanying drawings, which are only for the convenience of narrating the present application and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and cannot be understood as limiting the specific scope of protection of the present application.

[0024] It should be noted that the terms "first", "second", etc. in the description and claims of the present application are used to distinguish similar objects, and are not necessarily used to describe a specific order or sequence.

[0025] The terms "including" and "having" and any variations thereof in the specification and claims of the present application are intended to cover non-exclusive inclusions. For example, a process, method, system, product or apparatus comprising a series of steps or units is not necessarily limited to those steps or units explicitly listed, but may include other steps or units not explicitly listed or inherent to these processes, methods, products or apparatuses.

[0026] One of the preferred embodiments of the present application is as follows: Figure 1 As shown, a scheduling method for molding production tasks includes the following steps:

[0027] Project establishment: The project department will establish a relevant project team and formulate a development catalog based on the customer's project notification.

[0028] Design review: The project department selects professionals to conduct product analysis based on the development catalog and provides feedback to customers based on the results of the analysis. After the customer makes a request, the design is adjusted according to the customer's requirements and the product is analyzed again until it meets the customer's requirements.

[0029] Preliminary preparation: The outsourcing department purchases and stores raw materials and formulates processing plans based on the review results.

[0030] Production and processing: The production department implements the processing nodes based on the processing plan and performs workpiece processing; the project department, outsourcing department and production department track the entire processing process at the same time to facilitate timely handling of quality accidents.

[0031] Product testing: The quality department conducts quality inspection on the finished workpieces and requires rework for the workpieces that do not meet the quality requirements until all the workpieces meet the quality requirements and then assemble the test molds; based on the results of the test molds, the workpieces are improved on site to meet the requirements and submitted to the customer for confirmation through the project department.

[0032] It should be known that based on the above scheduling and planning process, this application provides a scheduling method based on actual production, which can reasonably arrange the production plan and provide feedback to customers at the specified time node. Compared with the traditional production process without definite planning and scheduling, the mold products required by customers can be completed with high efficiency and high quality. The specific content of the above workflow will be explained in detail below.

[0033] In this embodiment, Figure 1 As shown, the project establishment process includes the project initiation phase. In the project initiation phase, the project initiation notice is received from the customer, and a project management folder is established within the specified time after the communication with the customer is completed for project records. For ease of understanding, the specific process of the project initiation phase can be described in detail below.

[0034] Specifically, the project initiation phase mainly includes the written notification phase and the customer docking phase. In the written notification phase, the customer can connect with the project department through business methods such as email, phone or WeChat and issue a project initiation notice, and at the same time require the project department to provide an original quotation. The original quotation can refer to the price verification TSS table and the quotation summary table. For the customer docking phase, the project department replies to the customer's email and provides a project contact form. At the same time, the project department also simultaneously sets up a preliminary project team within the specified time based on the primary project information proposed by the customer, and then establishes a project management folder for storing and archiving project records.

[0035] It should be known that the cost time for the preliminary project team is generally established within 1 hour after the project starts, preferably within 0.5 hours. Since the establishment of the preliminary project team is relatively quick, and customer communication also takes time, the project department's communication with customers and the establishment of the preliminary project team can be carried out by different managers. One specific example is: Generally speaking, the management of the project department includes the project director and the project manager, so the project director can respond to the customer, and the project manager can set up the preliminary project team according to the customer's written notice. The project record can be in the form of word documents, pictures, PPT, etc.

[0036] In this embodiment, Figure 1 As shown in the figure, the project establishment stage also includes the project planning stage after the project initiation stage. In the project planning stage, the design plan, manufacturing plan and customer plan can be formulated in sequence, and the data and mold opening related materials can be locked according to the formulated plans to obtain the development directory recorded in the project management folder. For easy understanding, the specific process of the project planning stage can be described in detail below.

[0037] Specifically, for the formulation of the design plan, after the project department issues an order to establish a project design team, suitable designers will be selected to form the project design team within the specified time. At the same time, the project department and the production department can simultaneously complete the preparation of the project technical confirmation and development catalog to establish a mold manual.

[0038] It should be known that, based on the above example, the issuance of the instruction for the establishment of the project design team can be issued by the project manager, and the project design team needs to be established within 1-3 hours after the establishment of the preliminary project team, preferably within 2 hours. At the same time, the mold manual can be recorded and stored in the project management folder, and the establishment of the mold manual needs to be completed at least one day before the subsequent design review, so that the reviewers have enough time to complete the reading of the mold design manual.

[0039] Regarding the formulation of the manufacturing plan, after the project department issues an order to establish a project production team, appropriate production personnel are selected within the specified time to form the project production team and the personnel list is filled into the development directory to complete the production schedule.

[0040] It should be known that, based on the above example, the issuance of the order for the establishment of the project production team can be issued by the project manager, and the project production team needs to be established within 1-3 hours after the establishment of the preliminary project team, preferably within 2 hours. At the same time, the production schedule needs to be improved before the subsequent design review to ensure the integrity of the data.

[0041] For customer plans, the project department can combine the design schedule of the project design team and the production schedule of the project production team to prepare a plan schedule and report it to the customer within the specified time. At the same time, the internal members of each project team are improved and a project member framework is constructed to determine the rights and responsibilities during the project process.

[0042] It should be noted that, based on the above example, the formulation of the customer plan is completed by the project manager. The completion time of the planned schedule is generally completed within half a day, that is, within 12 hours, preferably within 2-8 hours.

[0043] For data locking, the project department can lock the data and related materials needed for mold opening according to the above-mentioned design schedule and production schedule. At the same time, the project design team needs to synchronously register the project data reception, and when any node that affects the delivery date occurs, it must be reported to the customer by email or other contact methods, and the node must be recorded in the project record sheet of the development catalog to complete the development catalog.

[0044] In this embodiment, Figure 1 As shown in the figure, the design review mainly includes the analysis stage, review stage and data locking stage. In the analysis stage, the structure, function, process and performance of the product are analyzed. In the review stage, the analysis results are modified through the review of both the enterprise and the customer until they meet the customer's requirements. In the data locking stage, the processing data of the product is determined according to the final review results of the customer and the enterprise. For easy understanding, the specific processes of the analysis stage, review stage and data locking stage can be described in detail below.

[0045] Specifically, Figure 1 As shown, the analysis phase includes product analysis and mold flow analysis.

[0046] Product analysis mainly includes the following processes: Preliminary determination of the injection position, number of points, structural direction, mold shape and machine model based on the product's function, appearance and matching requirements. Record the preliminary confirmed data, and propose unreasonable points based on the preliminary analysis to form a standard DFM report. The obtained DFM report is sent to the customer and reached an agreement with the customer within the specified time.

[0047] For ease of understanding, the product analysis process will be described in more detail below based on the aforementioned examples.

[0048] The project manager organizes the designers, process personnel and site managers to conduct product analysis and recognition meetings based on the nodes confirmed by the project manager. Through active communication among the participants, the mold's injection position, number of points, general structural direction, general mold shape, and several models are preliminarily determined based on the known conditions such as the product's function, appearance, and matching requirements. The members of the project design team need to conduct a preliminary analysis of the preliminarily determined parameters and propose unreasonable points to establish a standard DFM report. The project manager needs to report the DFM report to the customer via email or other communication methods and reach an agreement with the customer within the specified time. If there is a difference from the original quotation when the project manager communicates with the customer based on the DFM report and additional fees are required, a price verification data difference report needs to be submitted to the business department on the same day.

[0049] It is important to know that the record of the preliminary determined parameters is the prefix of the subsequent mold design book, so the record of the preliminary determined parameters needs to be clear and accurate. After obtaining the DFM report, the project manager needs to report to the customer within 1 day and reach an agreement based on the content of the report, preferably within 2-18 hours.

[0050] Mold flow analysis mainly includes the following processes: according to the nodes determined in the project establishment stage, various analyses are completed within the specified time according to the mold flow requirements to obtain a mold flow report; the obtained mold flow report is sent to the customer, and multiple mold flow reports need to be presented to the customer in the form of a comparison table; among them, the mold flow report must be a terminal solution with a terminal water channel that can be molded.

[0051] For ease of understanding, the mold flow analysis process will be described in more detail below based on the aforementioned examples.

[0052] The project manager issues mold flow analysis instructions based on the nodes determined by the project manager during the project establishment phase. The project design team will complete various analyses synchronously within the specified time according to the enterprise or industry mold flow requirements to obtain a mold flow report. The project manager then submits a mold flow node plan to the customer based on the mold flow report. The model node plan must be a terminal solution with water channels and mold manufacturing. At the same time, multiple reports must form a mold flow report comparison table, and the resulting mold flow report comparison table needs to be presented to the customer in the report and archived.

[0053] Specifically, Figure 1 As shown, the review stage includes internal review, customer review and re-evaluation.

[0054] Internal review mainly includes the following processes: organize relevant technical personnel of the enterprise to conduct an internal preliminary review of the terminal solution of the mold flow report according to customer requirements and enterprise standards; record and archive the results of the preliminary review and complete the mold calculation book, customer review form and mold design inspection standards.

[0055] For ease of understanding, the internal review process will be described in more detail below based on the aforementioned example.

[0056] According to the nodes determined by the project manager, the project manager organizes designers, on-site personnel and processing personnel (fitters) to conduct an internal preliminary review of the terminal solution of the mold flow report according to the customer's requirements and the company's own standards, and records the review results to obtain a mold review report and archive it in the review record folder. At the same time, complete the mold design book, customer review form and mold design inspection standards. It should be noted that if there is no special change in this review, the next review will be conducted within the specified time and will be mainly recorded in PPT. Generally speaking, the next review needs to be conducted within a week, preferably within 3-7 days.

[0057] For customer review, the main process includes the following: make an appointment with the customer based on the task node and communicate with the customer with relevant materials for internal review, and record the customer's review requirements to facilitate subsequent design adjustments.

[0058] For ease of understanding, the customer review process will be described in more detail below based on the aforementioned example.

[0059] The project manager will coordinate and communicate with the customer and make appointments with the customer according to the nodes determined by the project manager. At the same time, the project design team will work with the project department to improve the mold design inspection standards, DFM reports, design review reports, mold flow analysis reports, mold design books, review records and other data files. Then, the sorted and improved relevant materials will be taken to the designated location for design review with the customer. During the customer review process, the customer's review requirements, such as model and process requirements, will be recorded in detail on site. If there are any differences, they will be returned to the company and design adjustments will be made according to the customer's requirements.

[0060] The re-evaluation mainly includes the following process: organize relevant technical personnel to conduct a final internal review of the mold according to the customer's review requirements, and reply to the customer with the review results.

[0061] For ease of understanding, the review process will be described in more detail below based on the aforementioned examples.

[0062] According to the nodes determined by the project manager, the project manager organizes production personnel, designers, processing personnel and mold test personnel to conduct a final internal review of the mold according to the customer's review requirements and respond to the customer's final status. After completing the re-evaluation, the project manager can issue a cutting instruction to start product processing according to the customer and company's specifications, and the mold processing parameters will be locked at this time.

[0063] In this embodiment, Figure 1 As shown, before receiving the start-up instruction to start processing, preliminary preparations need to be made to purchase raw materials, etc. Specifically, it includes processing inquiry, material procurement, processing planning, material storage, and material outbound. For easy understanding, the following will combine the above examples to explain in detail the multiple stages of preliminary preparation.

[0064] Specifically, during the processing inquiry stage, the outsourcing department can verify the price, determine the location, and determine the period for various processing links based on the locked mold data, and obtain a processing price verification sheet.

[0065] In the material procurement stage, according to the mold material list submitted by the project design team, it is submitted to the procurement department for procurement implementation after approval by the production department and the company's general manager. The procurement staff submits the procurement plan to the warehouse, design department, production department and project department based on the mold material list, so that each department can track synchronously and collaboratively. The project manager organizes and handles changes in each link in a timely manner according to changes in the procurement process.

[0066] For the formulation of processing plans, the outsourcing department can prepare detailed processing schedules and production schedules based on the price verification results. At the same time, each department will work together to track the location, machine, machine time, estimated completion nodes, and actual nodes of the processing process. The project manager will organize and handle changes in each link in a timely manner according to changes in the process. Among them, the departments that need to be tracked in collaboration include the design department, project department, procurement department, production department, and quality department.

[0067] For material warehousing and delivery, the quality department and warehouse will inspect the size, appearance, hardness and other structures and delivery date of the raw materials purchased by the purchasing personnel according to the material list and fill out the inspection form before warehousing. After the completion of warehousing, it will be reported to the production department and project department. Raw materials that have passed the inspection of the quality department will be issued with material standard parts delivery orders and material collection orders, and can be claimed and shipped out after the signature and confirmation of the relevant person in charge.

[0068] In this embodiment, Figure 1 As shown, production and processing mainly include two stages: component processing and project control.

[0069] The component processing stage specifically includes two processes: processing and progress quality control. For the processing process, according to the previously specified processing plan, the project department, production department, outsourcing department and design department can synchronously monitor the data status of materials and processing in order to implement the various processing nodes specified in the early stage; the project manager promptly organizes and handles changes in each link according to changes in the process. For the progress quality control process, the project department, production department and outsourcing department synchronously monitor the processing progress; when there is a defective expedited process, each department will coordinate and fill out the quality accident handling form, and execute it with the ultimate goal of not affecting the final delivery date.

[0070] The project control phase specifically includes two processes: progress report communication and schedule update. The project manager reports to the client via email or other means on a weekly or agreed time basis; generally speaking, starting from the second week, the actual progress should be reported at least one week in advance; the progress status should be described in the body of the email report to the client, and the progress ratio of the updated schedule should be described.

[0071] In this embodiment, Figure 1As shown, product testing includes component testing, assembly and trial mold stage, and adjustment and improvement stage. In the component testing stage, the quality department prepares a test plan according to the processing plan, conducts quality inspection on the workpieces used to assemble the mold according to the formulated test plan, and issues an inspection report; qualified parts are put into storage, and a defective part handling report is required for unqualified parts; the quality department issues a quality accident handling unit to the production department and the outsourcing department according to the defective part handling report and requires rework. In the assembly and trial mold stage, after completing the preparation work before the trial mold, the production department provides the new product trial mold process sheet to the project department within the specified time; the project department submits a mold construction application to the production department within the specified time according to customer needs and records it, and obtains the trial mold plan statistics table; according to the trial mold plan statistics table, the scientific trial mold process sheet is simultaneously provided to the site, and after approval, the production department prepares for the trial mold according to the trial mold regulations; after completing the trial mold, the project department packs the samples according to the customer's requirements and arranges for shipment. For samples that are not requested or have quality problems, written confirmation with the customer is required to arrange packaging and shipment after acceptance. During the adjustment and improvement stage, according to the problems encountered during the mold trial and the customer's design change requirements, the project department organizes the production department and the project design team to provide a mold design change analysis report within the specified time and send it to the customer for confirmation; after the customer's confirmation, the project department issues a change order to the production department and the project design team to make the design change; before making the design change, evidence is retained and after the design change is completed, it is submitted to the customer for confirmation to complete the product lock.

[0072] For ease of understanding, the following will describe in detail each stage of product testing in conjunction with the aforementioned examples.

[0073] Specifically, Figure 1 As shown in the figure, the component inspection stage mainly includes the steps of formulation of inspection plan, workpiece inspection, rework of defective parts and warehousing of qualified parts.

[0074] Regarding the formulation of component inspection plans, the quality department can prepare inspection plans based on the previous processing plans, and report the prepared inspection plans to the production department, project department, and outsourcing department.

[0075] For the workpiece inspection process, the quality department inspects the finished workpiece according to various inspection standards and issues an inspection report; the inspection report is delivered to the production department, procurement department, design department and project department; for unqualified parts, a defective parts handling report needs to be filled out, and they are not allowed to flow into the next process without approval. For the inspection of the quality department, the slider, straight top, inclined top and electrode-related structures that make up the mold are mandatory inspection items, and the parting surface of the mold is also a mandatory inspection item. Standard parts can be sampled according to actual conditions.

[0076] For the defective product rework and qualified product storage process, the quality personnel will issue a quality accident handling form and hand it over to the person in charge of the production department, the outsourcing department and the quality department. Only after all parts have passed the inspection can they be stored in order to facilitate subsequent shipment.

[0077] Specifically, Figure 1 As shown in the figure, the assembly and trial mold stage mainly includes the steps of assembly and mold assembly, trial mold inspection, trial mold application and delivery and sample delivery.

[0078] For the assembly and mold making process, assembly case sharing and training, as well as identification of the assembly sequence and other learning processes are required before assembly; then the workpieces that have completed the inspection are assembled to obtain the mold products required for the test.

[0079] For the mold trial inspection process, before the mold trial, it is necessary to check the mold's circuit, gas circuit, water circuit and action path and fill in the initial inspection form for confirmation, and then complete the relevant preparations in accordance with the mold trial regulations.

[0080] In principle, the production department needs to submit a new product mold test process sheet to the project department one working day in advance during the mold test application process. Then, based on customer needs, the project manager should, in principle, submit a mold construction order application to the production department at least three working days in advance, and record the mold test plan and mold test statistics table in the archives, and the purpose of each mold test should be noted when recording. At the same time, the project department will provide a scientific mold test process sheet to the mold test site, and prepare mold test related matters according to the mold test regulations after approval by the relevant person in charge.

[0081] During the delivery and sample delivery process, the project department will isolate and package the products to ensure that the samples are not damaged during the shipment process. Then, according to the customer's requirements, the packaging boxes are labeled and packaged for shipment. According to the on-site conditions, the project manager will inform the customer of the shipping information through email, WeChat or other communication methods and register it in the file. If there are samples that are unclear or have quality problems, it is necessary to confirm the customer's acceptance in writing before packaging and shipment.

[0082] It should be noted that if Figure 1 As shown, during the assembly and mold trial stage, it is also necessary to confirm the problem points, that is, to confirm the problem points in the mold trial process. Specifically, the mold trial must undergo a comprehensive test of short shot, sample delivery and destruction and record it, and a mold trial tracking table can be obtained. Then the project department uses the destructive sample as the mold repair part to confirm the problem and fill out the mold trial problem sheet and hand it over to the production department; the production department completes the mold trial problem sheet within the specified time for subsequent adjustments and improvements.

[0083] It should be known that the production department generally completes the mold trial problem sheet within half a working day, that is, within 12 hours, preferably within 4-12 hours. When problems occur during the mold trial, the problem points are strictly handled in accordance with the event escalation regulations, and the contents of the event escalation regulations table are implemented; the project manager needs to sign for the delivery of samples and the final sealed samples on site, and post the first and last sealed sample labels. The samples with labels are sealed and stored in the warehouse, and the surface samples need to be compromised and the key points of qualified areas are indicated.

[0084] Specifically, Figure 1 As shown, the adjustment and improvement phase mainly includes the steps of problem point adjustment, change analysis, change confirmation and product locking.

[0085] Regarding the problem point adjustment process, the on-site adjustment of each problem point is implemented according to the mold trial problem list and the event escalation regulations table.

[0086] For the change analysis process, the project manager organizes the production department and the design department to provide a standard mold design change analysis report based on the customer's design change requirements; the mold design change analysis report is generally completed within 1 week, preferably completed and submitted within 1-8 working days. After the design change is confirmed and approved, the project manager issues a change order to the design department and the production department to initiate the design change.

[0087] For the change confirmation process, it is necessary to retain evidence before making design changes; after the change, the mold trial should be tested and confirmed before the mold trial, and after the mold trial is completed, it should be tested and confirmed, and the contents of the change order should be improved until it meets the customer's design change requirements and submitted to the customer.

[0088] It is important to know that the products produced by the mold can be divided into plain boards, leather-grained parts and non-appearance parts according to their appearance. During the product locking process, the project manager will label the first and last pieces of plain boards or leather-grained parts approved by the customer for storage and warehousing. The project manager can also label the first and last pieces of non-appearance parts that have been confirmed by the customer for gradient sealing and warehousing. Sealing and warehousing of products produced by the mold is generally carried out within six months to one year after the mold is shipped out of the warehouse.

[0089] In this embodiment, Figure 1As shown in the figure, after the product testing is completed, the product needs to be shipped out. The product shipping stage mainly includes two stages: shipping acceptance and service tracking. In the shipping acceptance stage, the project department urges other departments to improve the mold manual and conduct internal and customer acceptance of the mold within the specified time, and then ships the mold out of the warehouse to the customer's location for signing. In the service tracking stage, when the customer conducts trial production on the signed mold, the project department needs to go to the enterprise site for trial production tracking. For easy understanding, the following can be combined with the above examples to explain the two stages of shipping acceptance and service tracking in detail.

[0090] Specifically, in the acceptance and delivery stage, the main steps include data collation, internal acceptance, customer acceptance, mold delivery, and mold receipt. For the data collation process, the project manager supervises the relevant departments to improve the mold manual and archive it; the improvement of the mold manual is generally completed within one week before the mold is delivered. For the internal acceptance process, the project manager organizes relevant personnel to complete the various tasks of the mold pre-acceptance form within the company, and conducts action disassembly and inspection on site. For the customer acceptance process, the project manager cooperates with the customer according to the progress of the project, and conducts training according to the customer's requirements, supervises the completion of various acceptance tasks on site, implements and confirms the order with the customer in advance. For mold delivery, after the mold is accepted, the project department fills in the mold delivery application form and the mold shipping order, and delivers it after approval by the relevant person in charge; the shipment of the mold requires a shipping list, and a scientific mold trial report that conforms to the actual machine on the production site is submitted to the mass production customer at the same time. For the mold receipt process, after the mold arrives at the destination after delivery, it needs to be stamped and signed back on the mold shipping order, and then handed over to the general manager's office for storage and filing.

[0091] Specifically, the service tracking stage mainly includes trial production tracking, production tracking, and experience summary. For the trial production tracking process, the project department confirms and locks the customer's trial production node; if the customer is far away, it is necessary to fill out a travel application form in advance at a specified time, and coordinate with the production department to arrange related work after approval; among them, the on-site service personnel must have an after-sales service form signed by the customer on site to clarify the responsibility points and related results. For the production tracking process, synchronize the trial mold tracking, and increase the daily contact and concern of the project after the mold is shipped out. For the experience summary process, all project-related materials are sorted, archived, and summarized.

[0092] The above describes the basic principles, main features and advantages of the present application. Those skilled in the art should understand that the present application is not limited by the above embodiments, and the above embodiments and the specification only describe the principles of the present application. The present application may have various changes and improvements without departing from the spirit and scope of the present application, and these changes and improvements fall within the scope of the present application for which protection is sought. The scope of protection claimed by the present application is defined by the attached claims and their equivalents.

Claims

1. A method for scheduling molding production tasks, characterized in that: The steps include: Project establishment: The project department establishes relevant project teams and formulates development catalogues according to the customer's project notification; Design review: The project department selects professionals to conduct product analysis based on the development catalog and provides feedback to customers based on the analysis results. After the customer makes a request, the design is adjusted according to the customer's requirements and the product is analyzed again until it meets the customer's requirements. Preliminary preparation: The outsourcing department purchases and stores raw materials and formulates processing plans based on the review results; Production and processing: The production department implements the processing nodes based on the processing plan and processes the workpieces; the project department, outsourcing department and production department simultaneously track the entire processing process in order to handle any quality accidents in a timely manner; Product testing: The quality department conducts quality inspection on the finished workpieces and requires rework for the workpieces that do not meet the quality requirements until all the workpieces meet the quality requirements and then assemble the test molds; based on the results of the test molds, the workpieces are improved on site to meet the requirements and submitted to the customer for confirmation through the project department.

2. The method for scheduling molding production tasks according to claim 1, characterized in that: Project establishment includes: Project start-up phase: receiving the client's project start-up notice and creating a project management folder for project records within the specified time after completing communication with the client; and Project planning stage: formulate design plan, manufacturing plan and customer plan in sequence, and lock the data and mold-related information according to the formulated plan to obtain the development catalog recorded in the project management folder.

3. The method for scheduling molding production tasks according to claim 2, characterized in that: For the formulation of design plan, we select appropriate designers to form a project design team, provide a design schedule within the specified time, and complete the project technical confirmation and establish a development catalog by synchronizing the project department and the production department; For manufacturing planning, select appropriate production personnel to form a project production team and fill the personnel list into the development directory to complete the production schedule; For customer plans, we will build a framework diagram for project members and determine responsibilities in combination with design plans and manufacturing plans. At the same time, we will prepare a customer plan schedule within the specified time and submit it to the customer; When locking the data, the project design team will register the receipt of the project data, and if any node that affects the delivery date occurs, it must be reported to the customer and recorded in the project record sheet in the development catalog.

4. The method for scheduling molding production tasks according to claim 1, characterized in that: Design reviews include: Analysis stage: Analyze the structure, function, process and performance of the product; Review stage: the analysis results are modified through review by both the enterprise and the customer until they meet the customer's requirements; and Data locking stage: Determine the product processing data based on the final review results of the customer and the company.

5. The method for scheduling molding production tasks according to claim 4, characterized in that: The analysis phase includes product analysis and mold flow analysis; Product analysis includes the following processes: preliminarily determine the injection position, number of points, structural direction, mold shape and machine model according to the product's function, appearance and matching requirements; record the preliminary confirmed data, and propose unreasonable points based on the preliminary analysis to form a standard DFM report; send the obtained DFM report to the customer and reach an agreement with the customer within the specified time; Mold flow analysis includes the following processes: according to the nodes determined in the project establishment stage, complete various analyses within the specified time according to mold flow requirements to obtain a mold flow report; send the obtained mold flow report to the customer, and multiple mold flow reports need to be presented to the customer in the form of a comparison table; Among them, the mold flow report must be a terminal solution that can be molded with water channels.

6. The method for scheduling molding production tasks according to claim 5, characterized in that: The review stage includes internal review, customer review and re-review; Internal review includes the following process: organize relevant technical personnel of the enterprise to conduct internal preliminary review of the terminal solution of the mold flow report according to customer requirements and enterprise standards; record and archive the results of the preliminary review and complete the mold calculation book, customer review form and mold design inspection standards; Customer review includes the following process: Make an appointment with the customer based on the task node and communicate with the customer with relevant materials of internal review, and record the customer's review requirements to facilitate subsequent design adjustments; The re-evaluation includes the following process: organize relevant technical personnel to conduct a final internal review of the mold according to the customer's review requirements, and reply to the customer with the review results.

7. The method for scheduling molding production tasks according to any one of claims 3 to 6, characterized in that: Product testing includes component testing, assembly and trial mold testing, and adjustment and improvement stages; During the component inspection phase, the quality department prepares an inspection plan based on the processing plan, conducts quality inspection on the workpieces used to assemble the mold according to the prepared inspection plan, and issues an inspection report; Qualified parts will be put into storage, and unqualified parts need to fill in the defective parts handling report; The quality department issues a quality accident handling unit to the production department and outsourcing department based on the defective parts handling report and requires rework; During the mold assembly and trial stage, the production department will provide the project department with a new mold trial process sheet within the specified time after completing the preparatory work before the mold trial; the project department will submit a mold construction application to the production department within the specified time according to customer needs and record it, and obtain a mold trial plan statistical table; according to the mold trial plan statistical table, a scientific mold trial process sheet will be provided to the site simultaneously, and after approval, the production department will prepare for the mold trial according to the mold trial regulations; After the mold trial is completed, the project department will pack the samples according to the customer's requirements and arrange for shipment. For samples that are identified as unacceptable or have quality problems, written confirmation with the customer is required before packaging and shipment; During the adjustment and improvement phase, according to the problems encountered during the mold trial and the customer's design change requirements, the project department organizes the production department and the project design team to provide a mold design change analysis report within the specified time and send it to the customer for confirmation; After confirmation from the customer, the project department issues a change order to the production department and the project design team to make design changes; before making design changes, evidence is retained and after the design changes are completed, they are submitted to the customer for confirmation to complete product locking.

8. The method for scheduling molding production tasks according to claim 7, characterized in that: During the assembly and trial mold stage, the mold trial must be subjected to comprehensive tests such as short shot, sample delivery and destruction and recorded to obtain a trial mold tracking table; The project department uses destructive samples as mold repair parts to confirm the problems, fills out the mold trial problem sheet and hands it over to the production department; the production department completes the mold trial problem sheet within the specified time for subsequent adjustments and improvements.

9. The method for scheduling molding production tasks according to claim 7, characterized in that: During the product locking stage, for plain panels or leather-grained parts, the project department will label the first and last pieces and seal them into storage based on the customer's confirmation; for non-appearance parts, the project department needs the customer to confirm the gradient sealing before labeling the first and last pieces and sealing them into storage.

10. The method for scheduling molding production tasks according to claim 7, characterized in that: After completing product testing, the products will be shipped out. During the product shipping stage, the project department will urge other relevant departments to improve the mold manual and conduct internal acceptance and customer acceptance of the mold within the specified time, and then transport the mold out of the warehouse to the customer's location for signature. When the customer conducts trial production on the signed mold, the project department needs to reach the enterprise site for trial production tracking.