Air energy water heater control method, system, device and medium

By predicting and optimizing the heating time and startup time of the air-energy water heater, the energy consumption increase caused by long-term heating and excess heat is solved, and energy consumption reduction and heat utilization are improved.

CN119245217APending Publication Date: 2025-01-03GUANGDONG PHNIX TECH CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411378615.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-30
Publication Date
2025-01-03

AI Technical Summary

Technical Problem

The integrated air energy water heater has increased energy consumption due to long-term heating and excess heat, which has the problem of heat waste.

Method used

By obtaining the temperature of the hot water outlet, the temperature of the cold water inlet, the flow rate of the hot water flow and the use time, predicting and determining the heating time and startup time of the air energy water heater, optimizing the working status of the compressor, and avoiding frequent start-stop and electric heating modes Use of

Benefits of technology

It reduces the energy consumption of air-energy water heaters, reduces heat waste, and improves user satisfaction and equipment efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119245217A_ABST
    Figure CN119245217A_ABST
Patent Text Reader

Abstract

The invention discloses an air energy water heater control method, system and device and a storage medium. The method comprises the steps that the first water temperature, the second water temperature, the first hot water flow speed, the first starting moment, the first ending moment, the second starting moment and the second ending moment are obtained; according to the first water temperature, the second water temperature, the first hot water flow speed, the first starting moment and the first ending moment, the first heating time of the air energy water heater needing to be started for meeting the predicted hot water requirement of the nth section of the (n + 1) th day is determined; according to the first water temperature, the second water temperature, the first hot water flow speed, the second starting moment and the second ending moment, the second heating time of the air energy water heater needing to be started for meeting the predicted hot water requirement of the (n + 1) th section of the (n + 1) th day is determined; and determining first preset time according to the first starting moment and the second starting moment. The water heater can be widely applied to the technical field of water heaters.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of water heaters, and in particular to a control method, system, device and storage medium for an air-energy water heater. Background Art

[0002] Nowadays, the technology of integrated air-energy water heaters continues to mature, and its application scenarios are increasing, and it has become a common household appliance in people's daily life.

[0003] Compared with traditional electric water heaters and gas water heaters that obtain heat energy by consuming gas and electricity, the integrated air-energy water heater uses appropriate electricity to drive the compressor to work. After the high-pressure liquid refrigerant passes through the throttling device such as the electronic expansion valve, it absorbs heat energy from the air in the evaporator and evaporates into gas. The gaseous refrigerant is compressed by the compressor into a high-temperature and high-pressure liquid, which circulates to the water tank for heat exchange. This cycle is repeated to heat the cold water to the temperature we want. While consuming the same amount of electricity, the air-energy water heater can absorb heat energy equivalent to about three times the electricity, that is, to heat the same amount of hot water, the air-energy water heater saves two-thirds of electricity compared to traditional water heaters.

[0004] In the related art, integrated air-energy water heaters are used in multiple scenarios. Generally, integrated air-energy water heaters have larger water tanks than traditional water heaters, and because they continuously use the heat in the air for conversion, the heating time of the air-energy water heater is relatively long. When users use hot water, they need to wait or turn on the water heater in advance for heating. This leads to the common situation of excess heat in integrated air-energy water heaters, which leads to increased energy consumption of integrated air-energy water heaters. Therefore, it is recognized that there are technical problems that need to be solved in the related art. Summary of the invention

[0005] The purpose of this application is to solve one of the technical problems existing in the prior art to at least a certain extent.

[0006] To this end, an object of an embodiment of the present application is to provide an air-energy water heater control method, system, device and storage medium, which can reduce the energy consumption of the air-energy water heater.

[0007] In order to achieve the above technical objectives, the technical solutions adopted by the embodiments of the present application include: a method for controlling an air-energy water heater, including: obtaining a first water temperature of a hot water outlet, a second water temperature of a cold water inlet, a first hot water flow rate of a hot water outlet, a first start time of an n-th segment of hot water use time on an n-th day, a first end time of an n-th segment of hot water use time on an n-th day, a second start time of an n+1-th segment of hot water use time on an n-th day, and a second end time of an n+1-th segment of hot water use time on an n-th day; Determine, according to the first water temperature, the second water temperature, the first hot water flow rate, the first start time, and the first end time, a first heating time of the air-energy water heater required to be turned on to meet the predicted hot water demand for the nth period on the n+1th day; Determine, according to the first water temperature, the second water temperature, the first hot water flow rate, the second start time, and the second end time, a second heating time of the air-energy water heater required to be turned on to meet the predicted hot water demand for the n+1th period on the n+1th day; Determining a first preset time according to the first start time and the second start time; When the second heating time is greater than or equal to the first preset time, or when the second heating time is less than the first preset time, and the difference between the second start time and the first end time is less than the second preset time, the start time of the nth section of the air-energy water heater on the n+1th day is determined according to the second start time, the first heating time and the second heating time; When the second heating time is less than the first preset time or the difference between the second start time and the first end time is greater than or equal to the second preset time, the start time of the air-energy water heater in the nth section on the n+1th day is determined according to the second start time and the first heating time.

[0008] In addition, the method for controlling an air energy water heater according to the above embodiment of the present invention may also have the following additional technical features: Further, in the embodiment of the present application, determining the first heating time of the air-energy water heater required to be turned on to meet the predicted hot water demand of the nth segment on the n+1th day according to the first water temperature, the second water temperature, the first hot water flow rate, the first start time, and the first end time specifically includes: The first water temperature, the second water temperature, the first hot water flow rate, the first start time, and the first end time are input into a first heating time calculation formula to obtain a first heating time of the air-energy water heater required to be turned on to meet the predicted hot water demand of the nth segment on the n+1th day, wherein the first heating time calculation formula is: , Where T o is the first water temperature, T i is the second water temperature, c is the specific heat capacity of water, ρ is the density of water, T n B n is the first starting time, T n E n is the first end time, V(t) is the first hot water flow rate, P 常Indicates the actual heating power of the air energy water heater when only the compressor is turned on for heating; T n H (n+1) The first heating time of the air-energy water heater required to be turned on to meet the hot water demand predicted in the nth period on the n+1th day.

[0009] Further, in the embodiment of the present application, determining the first preset time according to the first start time and the second start time specifically includes: Subtract the first starting time from the second starting time to obtain a first difference; The first difference is used as the first preset time.

[0010] Further, in the embodiment of the present application, determining the start time of the nth segment of the air-energy water heater on the n+1th day according to the second start time, the first heating time and the second heating time specifically includes: determining a first set time according to the second start time, the first heating time, and the second heating time; The start time of the air-energy water heater in the nth section on the n+1th day is determined to be a time that is less than or equal to the first set time.

[0011] Further, in the embodiment of the present application, determining the first set time according to the second start time, the first heating time and the second heating time specifically includes: determining a first time difference according to the first heating time and the second heating time; The second start time and the first time difference are subtracted to obtain a first set time.

[0012] Further, in the embodiment of the present application, determining the start time of the nth section of the air-energy water heater on the n+1th day according to the second start time and the first heating time specifically includes: Determining a second set time according to the second start time and the first heating time; The start time of the air-energy water heater in the nth section on the n+1th day is determined to be a time that is less than or equal to the second set time.

[0013] Further, in the embodiment of the present application, determining the second set time according to the second start time and the first heating time specifically includes: Subtract the second starting time from the first heating time to obtain a second difference; The second difference is used as the second set time.

[0014] On the other hand, the embodiment of the present application also provides an air energy water heater control system, including: The first processing unit is used to obtain a first water temperature of the hot water outlet, a second water temperature of the cold water inlet, a first hot water flow rate of the hot water outlet, a first start time of the nth segment of hot water use time on the nth day, a first end time of the nth segment of hot water use time on the nth day, a second start time of the n+1th segment of hot water use time on the nth day, and a second end time of the n+1th segment of hot water use time on the nth day; a second processing unit, for determining a first heating time of the air-energy water heater required to be turned on to meet the predicted hot water demand for the nth period on the n+1th day according to the first water temperature, the second water temperature, the first hot water flow rate, the first start time, and the first end time; a third processing unit, for determining, according to the first water temperature, the second water temperature, the first hot water flow rate, the second start time, and the second end time, a second heating time of the air-energy water heater required to be turned on to meet the hot water demand predicted for the n+1th period on the n+1th day; a fourth processing unit, configured to determine a first preset time according to the first start time and the second start time; a fifth processing unit, configured to determine, when the second heating time is greater than or equal to the first preset time, or when the second heating time is less than the first preset time and the difference between the second start time and the first end time is less than the second preset time, a start time of the air-energy water heater for the nth section on the n+1th day according to the second start time, the first heating time and the second heating time; The sixth processing unit is used to determine the start time of the nth section of the air-energy water heater on the n+1th day according to the second start time and the first heating time when the second heating time is less than the first preset time or the difference between the second start time and the first end time is greater than or equal to the second preset time.

[0015] On the other hand, the present application also provides an air energy water heater control device, comprising: at least one processor; at least one memory for storing at least one program; When the at least one program is executed by the at least one processor, the at least one processor implements an air-energy water heater control method as described in any one of the invention contents.

[0016] In addition, the present application also provides a computer-readable storage medium, which stores instructions executable by a processor. When the instructions executable by the processor are executed by the processor, they are used to execute an air-energy water heater control method as described in any of the above items.

[0017] The advantages and benefits of the present application will be partially given in the following description, and partially become apparent from the following description, or be understood through the practice of the present application: The present application can obtain a first water temperature of the hot water outlet, a second water temperature of the cold water inlet, a first hot water flow rate of the hot water outlet, a first start time of the nth segment of hot water use time on the nth day, a first end time of the nth segment of hot water use time on the nth day, a second start time of the n+1th segment of hot water use time on the nth day, and a second end time of the n+1th segment of hot water use time on the nth day; determine a first heating time of the air-energy water heater required to be turned on to meet the predicted hot water demand of the nth segment on the n+1th day according to the first water temperature, the second water temperature, the first hot water flow rate, the first start time and the first end time; determine a first heating time of the air-energy water heater required to be turned on to meet the predicted hot water demand of the nth segment on the n+1th day according to the first water temperature, the second water temperature, the first hot water flow rate, the second start time and the second end time The second heating time of the air-energy water heater that needs to be turned on to meet the hot water demand is measured; the first preset time is determined according to the first start time and the second start time; when the second heating time is greater than or equal to the first preset time, or when the second heating time is less than the first preset time, and the difference between the second start time and the first end time is less than the second preset time, the start time of the nth section of the air-energy water heater on the n+1th day is determined according to the second start time, the first heating time and the second heating time; when the second heating time is less than the first preset time or the difference between the second start time and the first end time is greater than or equal to the second preset time, the start time of the nth section of the air-energy water heater on the n+1th day is determined according to the second start time and the first heating time. The present application controls the air-energy water heater through a new method, which can reduce the energy consumption of the air-energy water heater. BRIEF DESCRIPTION OF THE DRAWINGS

[0018] Figure 1 A schematic diagram of the steps of a method for controlling an air-energy water heater in a specific embodiment of the present invention; Figure 2 It is a structural schematic diagram of an air energy water heater in a specific embodiment of the present invention; Figure 3 A schematic diagram of a user's water use habits of a water heater in another specific embodiment of the present invention; Figure 4 A schematic diagram of a user's water use habits of a water heater in another specific embodiment of the present invention; Figure 5 A schematic diagram of a user's water use habits of a water heater in another specific embodiment of the present invention; Figure 6 A schematic diagram of a user's water use habits of a water heater in another specific embodiment of the present invention; Figure 7A schematic diagram of the structure of an air energy water heater control system in a specific embodiment of the present invention Figure 8 It is a structural schematic diagram of an air energy water heater control device in a specific embodiment of the present invention. DETAILED DESCRIPTION

[0019] The principles and processes of the air energy water heater control method, system, device and storage medium in the embodiments of the present invention are described below in conjunction with the accompanying drawings.

[0020] Reference Figure 1 The present application provides an air energy water heater control method. The method may include but is not limited to steps S101 to S105, or steps S101 to 104 and step 106.

[0021] S101. Obtain the first water temperature of the hot water outlet, the second water temperature of the cold water inlet, the first hot water flow rate of the hot water outlet, the first start time of the nth section of hot water usage time on the nth day, the first end time of the nth section of hot water usage time on the nth day, the second start time of the n+1th section of hot water usage time on the nth day, and the second end time of the n+1th section of hot water usage time on the nth day.

[0022] S102. Determine a first heating time of the air-energy water heater required to be turned on to meet the predicted hot water demand for the nth period on the n+1th day according to the first water temperature, the second water temperature, the first hot water flow rate, the first start time, and the first end time.

[0023] S103, determining a second heating time of the air-energy water heater required to be turned on to meet the predicted hot water demand of the n+1th period on the n+1th day according to the first water temperature, the second water temperature, the first hot water flow rate, the second start time and the second end time.

[0024] S104: Determine a first preset time according to the first start time and the second start time.

[0025] S105. When the second heating time is greater than or equal to the first preset time, or when the second heating time is less than the first preset time, and the difference between the second start time and the first end time is less than the second preset time, determine the start time of the nth section of the air-energy water heater on the n+1th day according to the second start time, the first heating time and the second heating time.

[0026] S106. When the second heating time is less than the first preset time or the difference between the second start time and the first end time is greater than or equal to the second preset time, determine the start time of the nth section of the air-energy water heater on the n+1th day according to the second start time and the first heating time.

[0027] Further, in the embodiment of the present application, according to the first water temperature, the second water temperature, the first hot water flow rate, the first start time and the first end time, the step of determining the first heating time of the air energy water heater required to be turned on to meet the predicted hot water demand of the nth segment on the n+1th day may specifically include: The first water temperature, the second water temperature, the first hot water flow rate, the first start time and the first end time are input into the first heating time calculation formula to obtain the first heating time of the air energy water heater required to be turned on to meet the hot water demand predicted in the nth period of the n+1th day, wherein the first heating time calculation formula is: , Where T o is the first water temperature, T i is the second water temperature, c is the specific heat capacity of water, ρ is the density of water, T n B n is the first starting time, T n E n is the first end time, V(t) is the first hot water flow rate, P 常 Indicates the actual heating power of the air energy water heater when only the compressor is turned on for heating. n H (n+1) The first heating time of the air-energy water heater required to be turned on to meet the hot water demand predicted in the nth period on the n+1th day.

[0028] Further, in the embodiment of the present application, the step of determining the first preset time according to the first start time and the second start time may specifically include steps S201 and S202.

[0029] S201. Subtract the first start time from the second start time to obtain a first difference.

[0030] S202: Using the first difference as a first preset time.

[0031] Further, in an embodiment of the present application, the start time of the nth section of the air-energy water heater on the n+1th day is determined according to the second start time, the first heating time and the second heating time, which may specifically include steps S301 and S302.

[0032] S301, determining a first set time according to a second start time, a first heating time, and a second heating time.

[0033] S302: Determine the start time of the nth section of the air-energy water heater on the n+1th day to be a time that is less than or equal to the first set time.

[0034] Further, in the embodiment of the present application, the step of determining the first set time according to the second start time, the first heating time and the second heating time may specifically include steps S401 and S402. S401, determining a first time difference according to the first heating time and the second heating time.

[0035] S402: Subtract the second start time from the first time difference to obtain a first set time.

[0036] Further, in the embodiment of the present application, determining the start time of the nth section of the air-energy water heater on the n+1th day according to the second start time and the first heating time may specifically include steps S501 and S502.

[0037] S501. Determine a second set time according to a second start time and a first heating time.

[0038] S501, determining the start time of the nth section of the air-energy water heater on the n+1th day to be a time that is less than or equal to the second set time.

[0039] Further, in the embodiment of the present application, the step of determining the second set time according to the second start time and the first heating time may specifically include steps S601 and S602.

[0040] S601, subtract the second starting time from the first heating time to obtain a second difference.

[0041] S602: Use the second difference as the second set time.

[0042] The specific calculation principle of this application is explained below with reference to the accompanying drawings: See also Figure 2 This is the basic working principle of the air-energy water heater. Cold water enters the water tank of the water heater from the cold water inlet at the bottom. After being heated internally, the hot water is in the upper layer and flows out from the upper hot water outlet. It is then diverted to different hot water terminals and applied to different scenarios. By adding sensors at the outlet of the water heater, the time period when the customer uses hot water, the flow rate and temperature of the hot water are collected, and the customer's water demand habits are recorded.

[0043] See also Figure 3 On the first day when the customer starts the air-energy water heater, the continuous heating state is turned on by default to ensure that the user has hot water available 24 hours a day, greatly reducing the need for users to wait for hot water, and then start recording the 24-hour usage status of the air-energy water heater. Figure 4 According to the user's hot water demand in the last 24 hours, the different time periods for opening the air energy water heater in the next 24 hours can be calculated. Human life activities are cyclical, and the demand for hot water is also cyclical.

[0044] In the first 7 days, when the demand for hot water is less than the maximum volume of the water tank, the heating time to meet the hot water demand in the nth period in the last 24 hours is:

[0045] T o Indicates the water temperature at the hot water outlet detected by the sensor on that day.

[0046] T i Indicates the water temperature at the cold water inlet detected by the sensor on that day.

[0047] c represents the specific heat capacity of water, which is 4.2×10 3 J / (kg*℃).

[0048] ρ represents the density of water.

[0049] T n B n Indicates the start time of the nth hot water usage period on the nth day. For example, T2B3 indicates the start time of the second hot water usage period on the third day.

[0050] T n E n Indicates the end time of the nth segment of hot water usage time on the nth day. For example, T3E5 indicates the end time of the 3rd segment of hot water usage time on the 5th day.

[0051] V(t) represents the hot water flow rate collected at the hot water outlet.

[0052] P 常 It indicates the actual heating power of the air-energy water heater when only the compressor is turned on for heating.

[0053] T n H (n+1) It indicates the time required to start the air-energy water heater for normal heating to meet the hot water demand predicted in the nth period of the (n+1)th day.

[0054] T (n+1) H (n+1) It can also be obtained by the above formula, if T (n+1) H (n+1) ≥T (n+1) B n -T n B n , indicating that the demand for hot water during the (n+1)th water usage period on the nth day is much greater than the demand for hot water during the nth water usage period on the nth day, so we do not need to shut down the air-energy water heater during the interval between the two hot water usage periods, and we need to keep the compressor working continuously. At this time, the start time of the air-energy water heater during the nth period on the (n+1)th day is set to:

[0055] In this way, the air-energy water heater can meet the needs of multiple stages of hot water use while avoiding excessive heat waste.

[0056] If T (n+1) H (n+1) <T (n+1) B n -T n B n , and T (n+1) B n -T n E n <30min, in order to avoid frequent start and stop of the compressor, the start time of the air energy water heater in the nth section of the (n+1)th day is set as:

[0057] In other cases, the start time of the air energy water heater in the nth section on the (n+1)th day is:

[0058] If the hot water storage is lower than the customer's demand during use, the user needs to manually turn on the electric heating mode to participate in heating to ensure that the hot water demand is met. This hot water demand will also be recorded.

[0059] See also Figure 5 When n>7, we have completed the record of users' hot water demand habits in the first small cycle and established the water use model for the first week. In the following time period, we can use the water demand collected in the previous small cycle to predict the water demand in the next cycle.

[0060]

[0061] T (n+1) H (n+1) It can also be obtained by the above formula, if T (n+1) H n ≥T (n+1) B (n-7) -T n B (n-7) , indicating that the predicted hot water demand for the (n+1)th water usage time on the nth day is much greater than the predicted hot water demand for the nth water usage time on the nth day, so we do not need to shut down the air-energy water heater during the interval between the two hot water usage times, and we need to keep the compressor working continuously. At this time, the start time of the air-energy water heater on the nth day and the nth period is set to:

[0062] In this way, the air-energy water heater can meet the needs of multiple stages of hot water use while avoiding excessive heat waste.

[0063] If T n H n <T (n+1) B (n-7) -T n B (n-7) , and T (n+1) B (n-7) -T n E (n-7) <30min, in order to avoid frequent start and stop of the compressor, the start time of the nth section of the nth day of the air energy water heater is set as:

[0064] The start time of the air energy water heater in the nth period of the nth day under other circumstances

[0065] If the hot water storage is lower than the customer's demand during use, the user needs to manually turn on the electric heating mode to participate in heating to ensure that the hot water demand is met. This hot water demand will also be recorded.

[0066] See also Figure 6 After recording 4 small cycles, that is, n>28, we obtained the user's water usage model within 4 weeks. For the sudden large demand for water on Monday of the second week, and the large demand for heating in advance on Monday of the third week, if the number of occurrences in 4 consecutive weeks is less than or equal to 2 times, the second largest demand for water is identified as a temporary demand, and the advance heating of the predicted demand will not be performed in the next cycle to avoid a large amount of heat waste.

[0067] If the user really needs a large amount of hot water, he can remotely control the air-energy water heater to heat the water in advance.

[0068] Through this intelligent control system, a user's water use model is established and the model is continuously revised. It can predict the user's water use time and water demand during regular periods, thereby achieving advance heating, reducing the frequent start and stop of the compressor and the use of the more power-consuming electric heating mode, reducing the user's waiting time for hot water, and avoiding the heat waste of a large amount of hot water remaining in the water tank after the user uses the hot water, thereby further improving user satisfaction.

[0069] In addition, Figure 1 Corresponding to the method, refer to Figure 7In an embodiment of the present application, an air energy water heater control system is also provided. The system may include a first processing unit 1001, a second processing unit 1002, a third processing unit 1003, a fourth processing unit 1004, a fifth processing unit 1005 and a sixth processing unit 1006.

[0070] The first processing unit 1001 is used to obtain the first water temperature of the hot water outlet, the second water temperature of the cold water inlet, the first hot water flow rate of the hot water outlet, the first start time of the nth section of hot water usage time on the nth day, the first end time of the nth section of hot water usage time on the nth day, the second start time of the n+1th section of hot water usage time on the nth day, and the second end time of the n+1th section of hot water usage time on the nth day.

[0071] The second processing unit 1002 is used to determine the first heating time of the air-energy water heater required to be turned on to meet the hot water demand predicted in the nth period of the n+1th day based on the first water temperature, the second water temperature, the first hot water flow rate, the first start time and the first end time.

[0072] The third processing unit 1003 is used to determine the second heating time of the air-energy water heater required to be turned on to meet the hot water demand predicted in the n+1th period of the n+1th day based on the first water temperature, the second water temperature, the first hot water flow rate, the second start time and the second end time.

[0073] The fourth processing unit 1004 is configured to determine a first preset time according to the first start time and the second start time.

[0074] The fifth processing unit 1005 is used to determine the start time of the nth section of the air-energy water heater on the n+1th day according to the second start time, the first heating time and the second heating time when the second heating time is greater than or equal to the first preset time, or when the second heating time is less than the first preset time and the difference between the second start time and the first end time is less than the second preset time.

[0075] The sixth processing unit 1006 is used to determine the start time of the nth section of the air-energy water heater on the n+1th day according to the second start time and the first heating time when the second heating time is less than the first preset time or the difference between the second start time and the first end time is greater than or equal to the second preset time.

[0076] It should be noted that the acquisition unit can be any integrated circuit unit or microprocessor unit obtained by integrating a chip with processing functions and its peripheral circuits through existing integration technology. The first processing unit and the second processing unit can also be any integrated circuit module or microprocessor module obtained by integrating a chip with processing functions and its peripheral circuits through existing integration technology. The first processing unit and the second processing unit can also include one or more memories. One or more memories can be used to store the specific algorithm in this application.

[0077] In some embodiments of the present application, the first processing unit 1001 can be set in the same gateway or device with a processor as the second processing unit 1002. The specific device connection mode and device setting of the first processing unit 1001 and the second processing unit 1002 and the second processing unit 1002 and the third processing unit 1003 are not limited.

[0078] It should be noted that the contents of the above-mentioned air-energy water heater control method embodiment are all applicable to the present air-energy water heater control system embodiment. The functions specifically implemented by the present air-energy water heater control system embodiment are the same as those of the above-mentioned air-energy water heater control method embodiment, and the beneficial effects achieved are also the same as those achieved by the above-mentioned air-energy water heater control method embodiment.

[0079] Corresponding to the method, the embodiment of the present application also provides an air energy water heater control device, the specific structure of which can be referred to Figure 8 ,include: At least one processor 1011.

[0080] At least one memory 1012 is used to store at least one program.

[0081] When at least one program is executed by at least one processor, the at least one processor implements the air-energy water heater control method.

[0082] The contents of the above method embodiments are all applicable to the present device embodiments. The functions specifically implemented by the present device embodiments are the same as those of the above method embodiments, and the beneficial effects achieved are also the same as those achieved by the above method embodiments.

[0083] and Figure 1 Corresponding to the method, an embodiment of the present application further provides a computer-readable storage medium, which stores instructions executable by a processor, and the instructions executable by the processor are used to execute the air-energy water heater control method when executed by the processor.

[0084] The contents of the above-mentioned air-energy water heater control method embodiment are all applicable to the present storage medium embodiment. The functions specifically implemented by the present storage medium embodiment are the same as those of the above-mentioned air-energy water heater control method embodiment, and the beneficial effects achieved are also the same as those achieved by the above-mentioned air-energy water heater control method embodiment.

[0085] In some optional embodiments, the function / operation mentioned in the block diagram may not occur in the order mentioned in the operation diagram. For example, depending on the function / operation involved, the two boxes shown in succession can actually be executed substantially simultaneously or the boxes can sometimes be executed in reverse order. In addition, the embodiment presented and described in the flow chart of the present application is provided by way of example, for the purpose of providing a more comprehensive understanding of technology. The disclosed method is not limited to the operation and logic flow presented herein. The optional embodiment is expected, wherein the order of various operations can be changed and the sub-operation described as a part of a larger operation can be performed independently.

[0086] In addition, although the present application is described in the context of functional modules, it should be understood that, unless otherwise specified, one or more of the functions and / or features can be integrated into a single physical device and / or software module, or one or more functions and / or features can be implemented in a separate physical device or software module. It is also understood that a detailed discussion of the actual implementation of each module is unnecessary for understanding the present application. More specifically, in view of the properties, functions, and internal relationships of the various functional modules in the device disclosed herein, the actual implementation of the module will be understood within the conventional techniques of the engineer. Therefore, those skilled in the art can implement the present application set forth in the claims without excessive experimentation using ordinary techniques. It is also understood that the specific concepts disclosed are merely illustrative and are not intended to limit the scope of the present application, which is determined by the full scope of the attached claims and their equivalents.

[0087] If the function is implemented in the form of a software functional unit and sold or used as an independent product, it can be stored in a computer-readable storage medium. Based on this understanding, the technical solution of the present application can essentially or in other words, the part that contributes to the prior art or the part of the technical solution can be embodied in the form of a software product. The computer software product is stored in a storage medium, including several programs to enable a computer device (which can be a personal computer, server, or network device, etc.) to perform all or part of the steps of the various embodiments of the present application. The aforementioned storage medium includes: U disk, mobile hard disk, read-only memory (ROM, Read-Only Memory), random access memory (RAM, Random Access Memory), disk or optical disk and other media that can store program codes.

[0088] The logic and / or steps represented in the flowchart or otherwise described herein, for example, may be considered as an ordered list of executable programs for implementing logical functions, and may be embodied in any computer-readable medium for use by a program execution system, device or apparatus (such as a computer-based system, a system including a processor, or other system that can fetch and execute a program from a program execution system, device or apparatus), or in conjunction with such program execution system, device or apparatus. For purposes of this specification, a "computer-readable medium" may be any device that can contain, store, communicate, propagate or transmit a program for use by a program execution system, device or apparatus, or in conjunction with such program execution system, device or apparatus.

[0089] More specific examples of computer-readable media (a non-exhaustive list) include the following: an electrical connection with one or more wires (electronic device), a portable computer disk case (magnetic device), a random access memory (RAM), a read-only memory (ROM), an erasable and programmable read-only memory (EPROM or flash memory), an optical fiber device, and a portable compact disk read-only memory (CDROM). In addition, the computer-readable medium may even be a paper or other suitable medium on which the program is printed, since the program may be obtained electronically, for example, by optically scanning the paper or other medium, followed by editing, deciphering or processing in another suitable manner as necessary, and then stored in a computer memory.

[0090] It should be understood that the various parts of the present application can be implemented by hardware, software, firmware or a combination thereof. In the above-mentioned embodiments, multiple steps or methods can be implemented by software or firmware stored in a memory and executed by a suitable program execution system. For example, if implemented by hardware, as in another embodiment, it can be implemented by any one of the following technologies known in the art or their combination: a discrete logic circuit having a logic gate circuit for implementing a logic function for a data signal, a dedicated integrated circuit having a suitable combination of logic gate circuits, a programmable gate array (PGA), a field programmable gate array (FPGA), etc.

[0091] In the above description of this specification, the description with reference to the terms "one embodiment / example", "another embodiment / example" or "certain embodiments / examples" etc. means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present application. In this specification, the schematic representation of the above terms does not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described may be combined in any one or more embodiments or examples in a suitable manner.

[0092] Although the embodiments of the present application have been shown and described, those skilled in the art will appreciate that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present application, and that the scope of the present application is defined by the claims and their equivalents.

[0093] The above is a specific description of the preferred implementation of the present application, but the present application is not limited to the described embodiments. Technical personnel familiar with the field may make various equivalent modifications or substitutions without violating the spirit of the present application. These equivalent modifications or substitutions are all included in the scope defined by the claims of the present application.

Claims

1. A method for controlling an air energy water heater, characterized in that: The following steps are involved: Obtain a first water temperature of the hot water outlet, a second water temperature of the cold water inlet, a first hot water flow rate of the hot water outlet, a first start time of the nth segment of hot water use time on the nth day, a first end time of the nth segment of hot water use time on the nth day, a second start time of the n+1th segment of hot water use time on the nth day, and a second end time of the n+1th segment of hot water use time on the nth day; Determine, according to the first water temperature, the second water temperature, the first hot water flow rate, the first start time, and the first end time, a first heating time of the air-energy water heater required to be turned on to meet the predicted hot water demand for the nth period on the n+1th day; Determine, according to the first water temperature, the second water temperature, the first hot water flow rate, the second start time, and the second end time, a second heating time of the air-energy water heater required to be turned on to meet the predicted hot water demand for the n+1th period on the n+1th day; Determining a first preset time according to the first start time and the second start time; When the second heating time is greater than or equal to the first preset time, or when the second heating time is less than the first preset time, and the difference between the second start time and the first end time is less than the second preset time, the start time of the nth section of the air-energy water heater on the n+1th day is determined according to the second start time, the first heating time and the second heating time; When the second heating time is less than the first preset time or the difference between the second start time and the first end time is greater than or equal to the second preset time, the start time of the air-energy water heater in the nth section on the n+1th day is determined according to the second start time and the first heating time.

2. The air energy water heater control method according to claim 1, characterized in that: The determining, according to the first water temperature, the second water temperature, the first hot water flow rate, the first start time, and the first end time, of a first heating time of the air-energy water heater required to be turned on to meet the predicted hot water demand for the nth segment on the n+1th day specifically includes: The first water temperature, the second water temperature, the first hot water flow rate, the first start time, and the first end time are input into a first heating time calculation formula to obtain a first heating time of the air-energy water heater required to be turned on to meet the predicted hot water demand of the nth segment on the n+1th day, wherein the first heating time calculation formula is: Where T o is the first water temperature, T i is the second water temperature, c is the specific heat capacity of water, ρ is the density of water, T n B n is the first starting time, T n E n is the first end time, V(t) is the first hot water flow rate, P 常 Indicates the actual heating power of the air energy water heater when only the compressor is turned on for heating; T n H (n+1) The first heating time of the air-energy water heater required to be turned on to meet the hot water demand predicted in the nth period on the n+1th day.

3. The air energy water heater control method according to claim 1, characterized in that: The determining the first preset time according to the first start time and the second start time specifically includes: Subtract the first starting time from the second starting time to obtain a first difference; The first difference is used as the first preset time.

4. The air energy water heater control method according to claim 1, characterized in that: The step of determining the start time of the nth section of the air-energy water heater on the n+1th day according to the second start time, the first heating time, and the second heating time specifically includes: determining a first set time according to the second start time, the first heating time, and the second heating time; The start time of the air-energy water heater in the nth section on the n+1th day is determined to be a time that is less than or equal to the first set time.

5. The air energy water heater control method according to claim 4, characterized in that: The determining the first set time according to the second start time, the first heating time and the second heating time specifically includes: determining a first time difference according to the first heating time and the second heating time; The second start time and the first time difference are subtracted to obtain a first set time.

6. The air energy water heater control method according to claim 1, characterized in that: The step of determining the start time of the air-energy water heater in the nth section on the n+1th day according to the second start time and the first heating time specifically includes: Determining a second set time according to the second start time and the first heating time; The start time of the air-energy water heater in the nth section on the n+1th day is determined to be a time that is less than or equal to the second set time.

7. The air energy water heater control method according to claim 6, characterized in that: The determining the second set time according to the second start time and the first heating time specifically includes: Subtract the second starting time from the first heating time to obtain a second difference; The second difference is used as the second set time.

8. An air energy water heater control system, characterized in that: include: The first processing unit is used to obtain a first water temperature of the hot water outlet, a second water temperature of the cold water inlet, a first hot water flow rate of the hot water outlet, a first start time of the nth segment of hot water use time on the nth day, a first end time of the nth segment of hot water use time on the nth day, a second start time of the n+1th segment of hot water use time on the nth day, and a second end time of the n+1th segment of hot water use time on the nth day; a second processing unit, for determining a first heating time of the air-energy water heater required to be turned on to meet the predicted hot water demand for the nth period on the n+1th day according to the first water temperature, the second water temperature, the first hot water flow rate, the first start time, and the first end time; a third processing unit, for determining, according to the first water temperature, the second water temperature, the first hot water flow rate, the second start time, and the second end time, a second heating time of the air-energy water heater required to be turned on to meet the hot water demand predicted for the n+1th period on the n+1th day; a fourth processing unit, configured to determine a first preset time according to the first start time and the second start time; a fifth processing unit, configured to determine, when the second heating time is greater than or equal to the first preset time, or when the second heating time is less than the first preset time and the difference between the second start time and the first end time is less than the second preset time, a start time of the air-energy water heater for the nth section on the n+1th day according to the second start time, the first heating time and the second heating time; The sixth processing unit is used to determine the start time of the nth section of the air-energy water heater on the n+1th day according to the second start time and the first heating time when the second heating time is less than the first preset time or the difference between the second start time and the first end time is greater than or equal to the second preset time.

9. An air energy water heater control device, characterized in that include: at least one processor; at least one memory for storing at least one program; When the at least one program is executed by the at least one processor, the at least one processor implements the air-energy water heater control method as described in any one of claims 1 to 7.

10. A computer-readable storage medium storing instructions executable by a processor, characterized in that: The processor executable instructions are used to execute the air energy water heater control method as described in any one of claims 1-7 when executed by the processor.