Use method of centralized fixed support photovoltaic module installation work platform

By designing a centralized fixed bracket photovoltaic module installation operation platform, the problem of multi-person collaboration and low safety in photovoltaic module installation in mountainous areas and Gobi areas has been solved, and efficient and safe photovoltaic module installation has been achieved, reducing construction costs.

CN119266505APending Publication Date: 2025-01-07CCTEB INFRASTRUCTURE CONSTR CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411587374.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-11-07
Publication Date
2025-01-07

AI Technical Summary

Technical Problem

When installing photovoltaic modules in mountains, Gobi and other areas, the existing technology is difficult to meet the needs of collaborative installation by multiple people, and the use of low safety and high cost in uneven terrain or soft geology.

Method used

A centralized fixed bracket photovoltaic module installation operation platform is designed, including a three-stitch support frame, a working platform and a protective structure. It is composed of components such as stress hooks, main stress rods, trapezoidal rods, cross rods and protective rope hangings to achieve A lightweight support frame and a safe working platform allow both floors of personnel to work simultaneously and improve safety through protective rope hangings and seat belts.

Benefits of technology

It significantly improves installation safety and construction efficiency, reduces costs, is suitable for a wider range of photovoltaic construction scenarios, and effectively avoids damage to photovoltaic brackets.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119266505A_ABST
    Figure CN119266505A_ABST
Patent Text Reader

Abstract

The invention discloses a use method of a centralized fixed support photovoltaic module installation work platform, the photovoltaic module installation work platform is composed of a support frame, work platforms and a protective structure, the support frame can be carried, assembled and disassembled by a single person, each work platform is put into three trusses, and the work platform is a steel structure formed by splicing a plurality of strip-shaped steel materials. Limiting devices are arranged on the upper portion, the lower portion, the left portion and the right portion of the working platform, the working platform can transversely move in parallel, the protection structure is composed of a protection stress structure, protection rope hangers and protection ropes, safety buckles are arranged at the ends of the protection ropes, hanging and dismounting can be conducted on the protection rope hangers, and continuous translation operation of the supporting frame and the working platform is not affected. According to the invention, the technical problem that a conventional scaffold and a climbing operation machine cannot simply, efficiently and safely complete the installation of the photovoltaic module under the conditions that the flatness of sites such as mountainous regions, gobi deserts and deserts is poor and the photovoltaic module needs to be installed through climbing operation is solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of photovoltaic assembly construction, and in particular relates to a method for using a centralized fixed bracket photovoltaic assembly installation work platform. Background Art

[0002] In recent years, new energy projects such as photovoltaic power stations have developed explosively in China, and a large number of photovoltaic power station construction projects have been planned in non-agricultural land such as Gobi, mountainous areas, and water areas across the country. Photovoltaic module installation is one of the key processes in the construction of photovoltaic power stations, and the installation efficiency of photovoltaic modules determines the length of the construction period of photovoltaic power stations. Photovoltaic module installation brackets have been widely used in mountainous areas, Gobi and other areas. Previously, gantry scaffolding, ladders or climbing vehicles were mostly used.

[0003] In mountainous areas, Gobi Desert and other regions, due to the terrain, flood control, photovoltaic and animal husbandry complementarity, and dust burial prevention requirements, photovoltaic module supports are usually relatively high, with the highest end generally exceeding 3m. In this case, it is impossible to install the modules manually alone.

[0004] The existing portal scaffolding has the advantages of being structurally sound, not requiring reliance on existing fixed photovoltaic supports, and having large turnover space.

[0005] The shortcomings of the existing portal scaffolding are that the bracket is heavy and the adjustment of its position requires the cooperation of multiple people. After the installation of this part group is completed, it needs to be adjusted and translated as a whole before it can continue to be used. It cannot be used safely on uneven terrain or soft geology. The cost of use is high, and most of them are standardized, and it is impossible to find a size that is perfectly suitable for actual on-site construction.

[0006] The existing ladder has the advantages of simple structure, easy movement, low cost of use and large turnover space.

[0007] The existing ladders have the disadvantages of being unable to meet the requirements of multi-person collaborative installation, having low operational safety guarantees, and being unable to be safely used on uneven terrain or in areas with soft geology.

[0008] The existing aerial work vehicles have the advantages of being able to collaborate with multiple people in construction, having a high safety factor in construction work, not needing to rely on existing photovoltaic brackets, and not requiring manual movement.

[0009] The disadvantages of existing aerial work vehicles are that the photovoltaic power station construction area is wide, a large number of aerial work vehicles are needed, the construction cost is too high, and it cannot be used safely on uneven terrain or soft geology. Summary of the invention

[0010] In order to overcome the technical problems in the prior art, the present invention provides a method for using a centralized fixed bracket photovoltaic component installation work platform to solve the above-mentioned technical problems.

[0011] A centralized fixed bracket photovoltaic module installation work platform consists of 3 support frames + a work platform + a protective structure. The support frame consists of a load-bearing hook, a main load-bearing rod, a second diagonal rod, a first-layer diagonal rod, a second-layer cross bar, a diagonal support rod, a work platform limit structure, and a first-layer cross bar, and is divided into an upper and lower structure.

[0012] The working platform is made of long steel strips that are reliably connected. Its size is smaller than the working platform limit structure and its length is greater than the span of the photovoltaic module installation bracket.

[0013] The protective structure is composed of a protective force-bearing structure and a protective rope hanger effectively connected to the second-layer inclined rod. The protective structure is formed by hanging a protective rope on the protective rope hanger.

[0014] The load-bearing hook is made of a steel hook and is provided with a buffer pad to avoid direct contact between the steel hook and the support column. It is the connecting part between the upper part of the working platform and the photovoltaic support.

[0015] The main load-bearing rod is made of long steel strips and is the main load-bearing column of the support frame. It is connected to the other components by welding or bolts.

[0016] The protective load-bearing structure is welded from long steel strips and is part of the support frame protection structure. It is connected to other components by welding or bolts.

[0017] The protective rope hanger is made of arc-shaped flat steel, which is connected to the protective force-bearing structure by welding or bolts, and is the hanging part of the protective rope. The protective rope is made of steel strands or steel chains, etc., which are firmly fixed with safety buckles and hung on the protective chain hanger to form a protective structure.

[0018] The first layer of inclined braces is made of long steel strips, which is the tension-bearing structure of the first level of the support frame and is connected to the other components by welding or bolts. The second layer of inclined braces is made of long steel strips, which is the tension-bearing structure of the second level of the support frame and is connected to the other components by welding or bolts.

[0019] The first-layer cross bar is made of long steel strips and is the supporting part of the first-layer cross bar. It is connected to the other components by welding or bolts. The second-layer cross bar is made of long steel strips and is the placement part of the working platform. It is connected to the other components by welding or bolts.

[0020] The diagonal brace is made of long steel strips and is the supporting part of the second-layer crossbar. It is connected to the remaining components by welding or bolts.

[0021] The limit clamp is made of steel, which serves to fix the main load-bearing rod and is connected to the main load-bearing rod by bolts.

[0022] The limiting C-shaped steel is made of C-shaped steel and is connected to the first-layer crossbar with bolts to serve as a fixed support frame.

[0023] The working platform limiting structure is a rectangular structure formed by long steel strips, which is effectively connected to the cross bar or to limit the adverse displacement of the working platform. The working platform is made of long steel strips that are reliably connected to provide a working platform for personnel.

[0024] A method for using a centralized fixed bracket photovoltaic assembly installation work platform comprises the following steps:

[0025] S1: Each group of working platforms consists of three support frames and two working platforms;

[0026] S2: Because the support frame is very light, a worker hangs the support frame on the rear column of the photovoltaic bracket, tightens the lower clamp, and then uses hinges and the rear diagonal brace to fix it firmly;

[0027] S3: After the three supporting frames are hung, the working platform is placed and fixed. There are two layers of working platforms, and one working platform is placed on each layer;

[0028] S4: Workers climb up the support frame in two steps to hang the upper clamp and protective rope, and buckle the five-point safety belt on the upper photovoltaic support;

[0029] S5: The installation of the photovoltaic modules begins. Workers stand on the work platform in two layers, two on the first layer and one on the second layer.

[0030] S5: After the installation of the span component is completed, the worker climbs down the support frame, pushes the working platform toward the unused third auxiliary support frame, removes the vacant support frame, and installs it in the next span where the bracket is to be installed, thereby achieving continuous operation.

[0031] In general, the above technical solutions conceived by the present invention can achieve the following beneficial effects compared with the prior art:

[0032] 1. The centralized fixed bracket photovoltaic module installation work platform described in the present invention greatly increases the safety of use compared with ladders or other unconventional simple installation methods, and there is no need to consider the photovoltaic bracket when using it;

[0033] 2. The centralized fixed support photovoltaic module installation work platform described in the present invention increases construction efficiency and reduces construction costs compared to existing work supports and equipment such as gantry scaffolding and aerial work vehicles;

[0034] 3. The centralized fixed bracket photovoltaic module installation work platform described in the present invention simplifies the construction method of photovoltaic module installation, increases the construction efficiency of module installation, reduces the construction cost investment, and has a wider range of use in the photovoltaic construction industry;

[0035] 4. After the installation of the centralized fixed support photovoltaic module installation work platform described in the present invention is completed, the single-layer work platform can be pushed flatly to the next span support frame, without the need to move the entire scaffolding like a conventional scaffolding. Since the installation work platform has two layers of work platforms, the photovoltaic modules on the entire photovoltaic support plane can be installed and constructed at the same time, which greatly improves the construction efficiency;

[0036] 5. Compared with conventional brackets that rely on photovoltaic brackets for component installation, the force-bearing structure design of the present invention can effectively avoid adverse damage to the photovoltaic bracket. The core force point is at the top of the rear column of the bracket, and the force direction is vertical. The bearing capacity of the rear column of the bracket is greater than the deadweight and construction load of the present invention itself, and will not affect the accuracy of the installed photovoltaic bracket. BRIEF DESCRIPTION OF THE DRAWINGS

[0037] The specific embodiments of the present invention are further described in detail below with reference to the accompanying drawings, wherein:

[0038] Figure 1 This is a schematic diagram of the overall structure of a centralized fixed bracket photovoltaic assembly installation work platform of the present invention;

[0039] Figure 2 It is a front view of a centralized fixed support photovoltaic assembly installation work platform of the present invention;

[0040] In the figure: 1-load hook, 2-main load rod, 3-second layer inclined rod, 4-protective load structure, 5-protective rope hanging, 6-first layer inclined rod, 7-second layer cross bar, 8-diagonal brace, 9-limiting clamp, 10-limiting C-shaped steel, 11-working platform limiting structure, 12-first layer cross bar, 13-protective rope, 14-working platform. DETAILED DESCRIPTION

[0041] like Figure 1 and Figure 2 As shown, it is a schematic diagram and a front view of the overall structure of a centralized fixed bracket photovoltaic module installation work platform of the present invention, which is composed of 3 support frames + a work platform + a protective structure.

[0042] The support frame is composed of a load-bearing hook 1, a main load-bearing rod 2, a second-layer inclined rod 3, a first-layer inclined rod 6, a second-layer cross bar 7, an inclined support rod 8, a work platform limiting structure 11, and a first-layer cross bar 12, and is divided into an upper and lower structure.

[0043] The load-bearing hook 1 is made of a steel hook and is provided with a buffer pad to avoid direct contact between the steel hook and the support column. It is the connecting part between the upper part of the working platform and the photovoltaic support.

[0044] The main load-bearing rod 2 is made of long steel strips and is the main load-bearing column of the support frame. It is connected to other components by welding or bolts.

[0045] The first layer of inclined rods 6 are made of long strips of steel and are the first-level tension structure of the support frame. They are connected to the remaining components by welding or bolts.

[0046] The second layer crossbar 7 is made of long strip steel and is the location for placing the working platform 14. It is connected to other components by welding or bolts.

[0047] The second layer of inclined rods 3 are made of long steel strips and are the second-level tension members of the support frame. They are connected to the remaining members by welding or bolts.

[0048] The protective load-bearing structure 4 is welded from long strips of steel and is a component of the support frame protective structure. It is connected to other components by welding or bolts.

[0049] The protective rope hanger 5 is made of arc-shaped flat steel, which is connected to the protective force-bearing structure 4 by welding or bolts, and is the hanging part of the protective rope 13;

[0050] The diagonal brace 8 is made of long steel strips and is the supporting part of the second layer crossbar 7. It is connected to other components by welding or bolts.

[0051] The limit clamp 9 is made of a steel clamp, which plays a role of fixing the main load-bearing rod 2 and is connected to the main load-bearing rod 2 by bolts.

[0052] The limiting C-shaped steel 10 is made of C-shaped steel and is connected to the first-layer crossbar 12 by bolts to play the role of a fixed support frame.

[0053] The work platform limiting structure 11 is a rectangular structure formed by long steel strips, which is effectively connected to the second-layer crossbar 7 or the first-layer crossbar 12 to limit the adverse displacement of the work platform 14.

[0054] The first-layer crossbar 12 is made of long steel strips and is a supporting portion of the second-layer crossbar 7 . It is connected to other components by welding or bolts.

[0055] The protection rope 13 is made of steel strands or steel chains and is securely fixed with safety buckles, and is hung on the protection chain hanger 5 to form a protection structure.

[0056] The working platform 14 is made of long strips of steel and is reliably connected to form a working platform for personnel.

[0057] A method for using a centralized fixed bracket photovoltaic assembly installation work platform comprises the following steps:

[0058] S1: Each group of working platforms consists of three support frames and two working platforms;

[0059] S2: Because the support frame is very light, a worker hangs the support frame on the rear column of the photovoltaic bracket, tightens the lower clamp, and then uses hinges and the rear diagonal brace to fix it firmly;

[0060] S3: After the three supporting frames are hung, the working platform is placed and fixed. There are two layers of working platforms, and one working platform is placed on each layer;

[0061] S4: Workers climb up the support frame in two steps to hang the upper clamp and protective rope, and buckle the five-point safety belt on the upper photovoltaic support;

[0062] S5; Start the installation work of photovoltaic modules. Workers stand on the working platform in two layers, two people on the first layer and one person on the second layer.

[0063] S5: After the installation of the span component is completed, the worker climbs down the support frame, pushes the working platform toward the unused third auxiliary support frame, removes the vacant support frame, and installs it in the next span where the bracket is to be installed, thereby achieving continuous operation.

Claims

1. A method for using a centralized fixed bracket photovoltaic module installation work platform, characterized in that: The centralized fixed bracket photovoltaic module installation work platform includes a support frame, a work platform and a protective structure; The support frame is composed of a load-bearing hook (1), a main load-bearing rod (2), a second-layer inclined rod (3), a first-layer inclined rod (6), a second-layer cross rod (7), an inclined support rod (8), a work platform limiting structure (11), and a first-layer cross rod (12), and is divided into an upper and lower structure; The working platform (14) is made of long steel strips connected reliably, its size is smaller than the working platform limiting structure (11), and its length is greater than the span of the photovoltaic module installation bracket; The protective structure is composed of a protective force-bearing structure (4) and a protective rope hanger (5) effectively connected to the second layer of inclined rods (3), and a protective rope (13) is hung on the protective rope hanger (5) to form a protective structure; The method of use includes the following steps: S1: Each group of working platforms consists of three support frames and two working platforms; S2: Because the support frame is very light, a worker hangs the support frame on the rear column of the photovoltaic bracket, tightens the lower clamp, and then uses hinges and the rear diagonal brace to fix it firmly; S3: After the three supporting frames are hung, the working platform is placed and fixed. There are two layers of working platforms, and one working platform is placed on each layer; S4: Workers climb up the support frame in two steps to hang the upper clamp and protective rope, and buckle the five-point safety belt on the upper photovoltaic support; S5: During the installation of the photovoltaic modules, workers stand on the working platform in two layers, two people on the first layer and one person on the second layer; S5: After the installation of the span component is completed, the worker climbs down the support frame, pushes the working platform toward the unused third auxiliary support frame, removes the vacant support frame, and installs it in the next span where the bracket is to be installed, thereby achieving continuous operation.

2. The method for using a centralized fixed bracket photovoltaic module installation work platform according to claim 1, characterized in that: The upper and lower layers of the structure are composed of a first layer of cross bars (12), a second layer of cross bars (7), and corresponding diagonal rods and diagonal braces.

3. The method for using a centralized fixed bracket photovoltaic module installation work platform according to claim 1, characterized in that: The force-bearing hook (1) is an arc-shaped steel structure and can be hung on the photovoltaic support column. The main force-bearing rod (2), the first layer cross bar (12), and the second layer cross bar (7) are composed of square steel. The first layer inclined rod (6) and the second layer inclined rod (3) are composed of long strips of steel. The scaffolding limiting structure (11) is formed by welding rectangular steel, the second layer cross bar (7), and the first layer cross bar (12). The support limiting structure is composed of two limiting clamps (9) and limiting C-shaped steel (10), and the diagonal brace (8) is composed of long strips of steel.

4. The method for using a centralized fixed bracket photovoltaic module installation work platform according to claim 1, characterized in that: The protective rope (13) is composed of a steel strand or a steel chain etc. effectively connected with a safety buckle.