Method for constructing outer protective plate of coal transporting trestle by using lifting aerial work platform
By using a lifting and aerial working platform for the installation of the outer guard plate in the coal transport trench construction, the problems of traditional high construction costs and low efficiency are solved, and efficient and safe construction results are achieved.
Patent Information
- Application Number
- CN202411630444.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-11-15
- Publication Date
- 2025-01-10
AI Technical Summary
The construction of the outer guard plate of the traditional coal-transporting trest requires the cooperation of homemade cages and multiple cranes, resulting in high construction costs, large labor and material consumption, long time, and large site occupancy.
The lifting and aerial working platform is used for construction, and the outer guard plate is installed through the curved arm lifting and aerial working platform is used for material transportation and fixation, which reduces construction site occupation and material loss and improves construction efficiency and safety.
It realizes efficient external guard panel construction, reduces construction costs, improves construction efficiency and safety, and ensures high standards of construction quality.
Smart Images

Figure CN119287787A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of outer guard plate construction of a coal conveying trestle, and more specifically, to a method for constructing an outer guard plate of a coal conveying trestle by utilizing a lifting aerial work platform. Background Art
[0002] The coal conveyor trestle is one of the important structures in the fuel supply system of a thermal power plant. Through its internal coal conveyor belt, it connects the coal from outside the plant, the coal source inside the plant and the coal handling system between coal bunkers, ensuring a continuous supply of fuel required for the daily operation of the power plant.
[0003] The outer guard plate of the coal conveyor trestles is an important process in their construction. It has a series of functions such as decoration, waterproofing, fire prevention, heat preservation, and prevention of coal dust pollution. In traditional thermal power plant buildings, the coal conveyor trestles generally rise gradually with a certain slope. The installation of the outer guard plate requires a homemade hoist cage and the cooperation of multiple cranes to complete the construction. This requires a lot of manpower, material resources, time and space, which greatly increases the construction cost.
[0004] In view of this, we propose a method for constructing the outer guard plate of the coal conveyor trestle using a lifting aerial work platform. Summary of the invention
[0005] The purpose of the present invention is to provide a method for constructing outer guard plates of a coal conveyor trestle by utilizing a lifting aerial work platform, aiming to solve the problem that in traditional thermal power plants, the coal conveyor trestle generally gradually rises with a certain slope, and the installation of the outer guard plates requires a homemade hoist cage and the cooperation of multiple cranes to complete the construction, which requires a large amount of manpower, material resources, time and space, etc., greatly increasing the construction cost.
[0006] In order to solve the above technical problems, the present invention provides the following technical solutions: a method for constructing an outer guard plate of a coal conveying trestle using a lifting aerial work platform, the construction method comprising the following steps:
[0007] S1: Construction personnel enter the site, carry out personnel allocation and construction training, prepare and check safety equipment, and the boom lift aerial work platform enters the site for commissioning;
[0008] S2: Install the bracket in the working platform, wrap the bracket with ropes to prevent deformation caused by squeezing between the material and the bracket, and take anti-slip measures. Then adjust the position of the lifting aerial work platform. The position should be convenient for construction workers to plug and install the material with the trestle steel structure. After adjustment, move the material to the working platform of the articulated boom lifting aerial work platform, and take measures to prevent the material from falling during the ascent;
[0009] S3: Construction workers entering the operating platform must wear safety helmets, safety ropes and other safety equipment and take safety precautions for aerial work;
[0010] S4: The construction workers make fine adjustments to the position of the outer guard plate, and complete the alignment and plugging under the steel structure. After the plugging is completed, one person on the construction platform is responsible for supporting the plate, and two people use rivets to fix the outer guard plate. The rivet fixing position needs to be controlled with a line to ensure that the fixing points are on the same horizontal line;
[0011] S5: Workers lower the operating platform through the operating platform. Safety precautions are still required during the descent process until the operating platform is lowered to the ground for the next round of construction. Repeat the above steps until the installation of the outer guard plate is completed.
[0012] Preferably, the above step S1 also includes the following steps:
[0013] S1.1: First, the construction plan of the pier outer guard plate is submitted for review, and relevant personnel are notified to come to the site to conduct safety technical briefings and familiarize themselves with the construction process and precautions;
[0014] S1.2: Coordinate sufficient construction sites and take appropriate safety measures in the surrounding areas;
[0015] S1.3: Connect with the material supply department for construction, ensure the supply of materials with guaranteed quality and quantity, and ensure that the material quality is strictly controlled and the tracking information is complete;
[0016] S1.4: After the materials are transported to the site, they are piled at the bottom of both sides of the trestle to protect the finished products.
[0017] Preferably, the above step S1.2 also includes the following steps:
[0018] S1.2.1: Before the articulated boom lift enters the site, the site must be flat, the machine must be placed horizontally, the entire machine must be in the folded state, and the hydraulic oil level must be near the red dot. If it is insufficient, refill it immediately.
[0019] Preferably, the above step S2 also includes the following steps:
[0020] S2.1: When adjusting the position of the articulated boom lift, ensure that an appropriate safety distance is maintained between the platform and the steel structure of the trestle to prevent collision between the platform and the steel structure;
[0021] S2.2: When transporting materials to the work platform, special lifting tools should be used and the center of gravity of the materials should be ensured to be stable to prevent tilting or falling during transportation;
[0022] S2.3: When installing a bracket in a boom lift, ensure the stability of the bracket and use special tools to fix the bracket to prevent it from loosening or deforming during operation.
[0023] Preferably, the above step S3 also includes the following steps:
[0024] S3.1: Before entering the operating platform, construction workers need to check their safety equipment to ensure that they are not damaged and are worn correctly;
[0025] S3.2: During the construction process, construction workers must pay attention to changes in the surrounding environment at all times. If any abnormal situation is found, they must immediately stop the work and report it to relevant personnel.
[0026] Preferably, the above step S4 also includes the following steps:
[0027] S4.1: When fine-tuning the position of the outer guard plate, a dedicated measuring tool must be used for precise measurement to ensure that the position of the outer guard plate meets the design requirements;
[0028] S4.2: During the plugging process, a dedicated plugging tool must be used and the plugging must be secure and not loose;
[0029] S4.3: When fixing the outer guard plate, a special rivet gun must be used for riveting and ensure that the rivet fixing position is accurate.
[0030] Preferably, the above step S5 also includes the following steps:
[0031] S5.1: After the construction is completed, the construction results must be well protected, the surface of the completed pier outer guard plate must be cleaned, the construction personnel and machinery must leave the site, and surrounding construction operations must be reminded to avoid collisions that may cause deformation of the outer guard plate and contamination of the appearance.
[0032] Preferably, full-process monitoring and continuous improvement of construction quality, including immediate inspection, phased acceptance and quality feedback mechanism, ensure that construction quality always meets high standards.
[0033] Compared with the prior art, the present invention has the following beneficial effects:
[0034] 1. The present invention utilizes a lifting aerial work platform for construction. Compared with traditional construction, it reduces the occupation of the construction site, reduces the loss of materials, reduces the use of construction machinery, has strong flexibility, high fault tolerance, and greatly improves the construction efficiency. At the same time, it guarantees the safety of construction personnel to a greater extent, and the quality of the construction results of the outer guard plate is better, truly achieving the effect of efficient construction and reducing construction costs.
[0035] 2. The present invention utilizes a boom-type lifting aerial work platform that integrates operation, control platform, and vertical transportation. The transportation and installation of the outer guard plate are all completed on the operating platform, reducing the transmission of commands between various processes. A series of construction is completed by workers on the operating platform. The outer guard plate does not intersect with the steel structure during transportation and alignment, and the space for material movement becomes larger, which is more conducive to the construction personnel to complete the alignment and insertion of the base plate and the steel structure. BRIEF DESCRIPTION OF THE DRAWINGS
[0036] Figure 1 This is a schematic diagram of the process of this construction method. DETAILED DESCRIPTION
[0037] like Figure 1 As shown, the present invention relates to a method for constructing an outer guard plate of a coal conveying trestle using a lifting aerial work platform, and the construction method comprises the following steps:
[0038] S1: Construction personnel enter the site, carry out personnel allocation and construction training, prepare and check safety equipment, and the boom lift aerial work platform enters the site for commissioning;
[0039] S2: Install the bracket in the working platform, wrap the bracket with ropes to prevent deformation caused by squeezing between the material and the bracket, and take anti-slip measures. Then adjust the position of the lifting aerial work platform. The position should be convenient for construction workers to plug and install the material with the trestle steel structure. After adjustment, move the material to the working platform of the articulated boom lifting aerial work platform, and take measures to prevent the material from falling during the ascent;
[0040] S3: Construction workers entering the operating platform must wear safety helmets, safety ropes and other safety equipment and take safety precautions for aerial work;
[0041] S4: The construction workers make fine adjustments to the position of the outer guard plate, and complete the alignment and plugging under the steel structure. After the plugging is completed, one person on the construction platform is responsible for supporting the plate, and two people use rivets to fix the outer guard plate. The rivet fixing position needs to be controlled with a line to ensure that the fixing points are on the same horizontal line;
[0042] S5: The workers lower the operating platform through the operating platform. Safety precautions are still required during the descent process until the operating platform is lowered to the ground for the next round of construction. The above steps are repeated until the installation of the outer guard plate is completed;
[0043] The articulated boom lift aerial work platform integrates vertical transportation, operating platform and construction platform, and adopts a multi-stage folding arm combination. The maximum lifting height of the ordinary type can reach 26.5 meters, the rated load capacity is 454kg, and the whole vehicle can rotate 360° continuously and work at any angle.
[0044] The construction equipment configuration is as follows:
[0045]
[0046]
[0047] The main safety protection facilities and supplies are configured as follows:
[0048] Serial number name Specifications unit quantity 1 Gloves pay 20 2 Safety shoes pair 10 3 helmet top 10 4 seat belt Only 10 5 Horizontal safety rope rice 100
[0049] The use of a lifting aerial work platform for the construction of the outer guard plate ensures smooth material transportation, high precision, high efficiency, small site occupation, strong flexibility, a large construction platform area, high safety, better material protection, and easier control of construction quality. The lifting aerial work platform has a compact structure and flexible steering, which can ensure entry into narrow passages and crowded work areas. It occupies a small area. When constructing the outer guard plate of a coal transport trestle of general height, the entire outer guard plate can be fixed on the work platform. The lifting height and position are controlled by the construction personnel in the work platform. The platform's rising process is more stable, the material transportation precision is high, and the position is easy to adjust, which provides great convenience for the overlap installation of the outer guard plate and improves the construction efficiency. At the same time, it can carry three construction personnel to lift them to the work site at the same time for docking and assembly. After the single piece is assembled, it is lowered to the ground for re-loading, lifting, and assembly, and the process is repeated. The construction personnel are equipped as shown in the following table:
[0050] Position Number of people Position Number of people Construction responsible 1 electrician 1 Safety Officer 1 Installer 8 technician 1 Material clerk 1 Quality Inspector 1 Painter 1
[0051] The working platform has a large area and is equipped with anti-extrusion devices, which ensures the safety of construction workers. The bracket is installed in the platform and wrapped with ropes. On the one hand, anti-slip measures are taken to prevent materials from accidentally falling and causing damage and safety problems. On the other hand, the materials and brackets are prevented from being squeezed and deformed. The transportation, alignment, overlap and installation are completed under the steel structure. During the process, it will not be staggered with the trestle steel structure. The appearance quality of the outer guard plate construction is easy to control. After the construction is completed, the surface cleaning of the outer guard plate and other finished product protection measures also provide great convenience. Under the same conditions, the construction effects of this construction method and the traditional construction method are as follows:
[0052]
[0053] To sum up, compared with traditional construction, the use of lifting aerial work platforms for construction reduces the occupancy of construction sites, reduces material loss, reduces the use of construction machinery, has strong flexibility, high fault tolerance, and greatly improves construction efficiency. At the same time, it guarantees the safety of construction workers to a greater extent, and the quality of exterior guard plate construction results is better, truly achieving the effect of efficient construction.
[0054] The embodiments of the present invention disclose preferred embodiments, but are not limited thereto. A person skilled in the art can easily understand the spirit of the present invention based on the above embodiments and make different extensions and changes. However, as long as they do not deviate from the spirit of the present invention, they are all within the protection scope of the present invention.
Claims
1. A method for constructing an outer guard plate of a coal handling trestle using a lifting aerial work platform, characterized in that: The construction method comprises the following steps: S1: Construction personnel enter the site, carry out personnel allocation and construction training, prepare and check safety equipment, and the boom lift aerial work platform enters the site for commissioning; S2: Install the bracket in the working platform, wrap the bracket with ropes to prevent deformation caused by squeezing between the material and the bracket, and take anti-slip measures. Then adjust the position of the lifting aerial work platform. The position should be convenient for construction workers to plug and install the material with the trestle steel structure. After adjustment, move the material to the working platform of the articulated boom lifting aerial work platform, and take measures to prevent the material from falling during the ascent; S3: Construction workers entering the operating platform must wear safety helmets, safety ropes and other safety equipment and take safety precautions for aerial work; S4: The construction workers make fine adjustments to the position of the outer guard plate, and complete the alignment and plugging under the steel structure. After the plugging is completed, one person on the construction platform is responsible for supporting the plate, and two people use rivets to fix the outer guard plate. The rivet fixing position needs to be controlled with a line to ensure that the fixing points are on the same horizontal line; S5: Workers lower the operating platform through the operating platform. Safety precautions are still required during the descent process until the operating platform is lowered to the ground for the next round of construction. Repeat the above steps until the installation of the outer guard plate is completed.
2. The method for constructing the outer guard plate of a coal handling trestle using a lifting aerial work platform according to claim 1 is characterized in that: The above step S1 also includes the following steps: S1.1: First, the construction plan of the pier outer guard plate is submitted for review, and relevant personnel are notified to come to the site to conduct safety technical briefings and familiarize themselves with the construction process and precautions; S1.2: Coordinate sufficient construction sites and take appropriate safety measures in the surrounding areas; S1.3: Connect with the material supply department for construction, ensure the supply of materials with guaranteed quality and quantity, and ensure that the material quality is strictly controlled and the tracking information is complete; S1.4: After the materials are transported to the site, they are piled at the bottom of both sides of the trestle to protect the finished products.
3. The method for constructing the outer guard plate of a coal handling trestle using a lifting aerial work platform according to claim 1 is characterized in that: The above step S1.2 also includes the following steps: S1.2.1: Before the articulated boom lift enters the site, the site must be flat, the machine must be placed horizontally, the entire machine must be in the folded state, and the hydraulic oil level must be near the red dot. If it is insufficient, refill it immediately.
4. The method for constructing the outer guard plate of a coal handling trestle using a lifting aerial work platform according to claim 1 is characterized in that: The above step S2 also includes the following steps: S2.1: When adjusting the position of the articulated boom lift, ensure that an appropriate safety distance is maintained between the platform and the steel structure of the trestle to prevent collision between the platform and the steel structure; S2.2: When transporting materials to the work platform, special lifting tools should be used and the center of gravity of the materials should be ensured to be stable to prevent tilting or falling during transportation; S2.3: When installing a bracket in a boom lift, ensure the stability of the bracket and use special tools to fix the bracket to prevent it from loosening or deforming during operation.
5. The method for constructing the outer guard plate of a coal handling trestle using a lifting aerial work platform according to claim 1 is characterized in that: The above step S3 also includes the following steps: S3.1: Before entering the operating platform, construction workers need to check their safety equipment to ensure that they are not damaged and are worn correctly; S3.2: During the construction process, construction workers must pay attention to changes in the surrounding environment at all times. If any abnormal situation is found, they must immediately stop the work and report it to relevant personnel.
6. The method for constructing the outer guard plate of a coal handling trestle using a lifting aerial work platform according to claim 1 is characterized in that: The above step S4 also includes the following steps: S4.1: When fine-tuning the position of the outer guard plate, a dedicated measuring tool must be used for precise measurement to ensure that the position of the outer guard plate meets the design requirements; S4.2: During the plugging process, a dedicated plugging tool must be used and the plugging must be secure and not loose; S4.3: When fixing the outer guard plate, a special rivet gun must be used for riveting and ensure that the rivet fixing position is accurate.
7. The method for constructing the outer guard plate of a coal handling trestle using a lifting aerial work platform according to claim 1 is characterized in that: The above step S5 also includes the following steps: S5.1: After the construction is completed, the construction results must be well protected, the surface of the completed pier outer guard plate must be cleaned, the construction personnel and machinery must leave the site, and surrounding construction operations must be reminded to avoid collisions that may cause deformation of the outer guard plate and contamination of the appearance.
8. The method for constructing the outer guard plate of a coal handling trestle using a lifting aerial work platform according to claim 1 is characterized in that: The outer guard plate of the coal handling trestle is made of plastic-coated colored corrugated steel plate. The outer thickness of the bottom plate is ≥0.7mm, and the inner steel plate thickness is ≥0.6mm. The core of the bottom plate factory composite plate is 100 thick rock wool, and the rock wool bulk density is ≥100kg / m 3 The dimensions are 8460×1000×100mm. The mass of a corrugated steel plate is 200kg. The installation height gradually increases from 0 meters to 18 meters.