Path planning method of wind power plant current collection line and corresponding device
By analyzing the environmental and facility data of the wind farm, multiple candidate paths for the wind farm power collection lines are generated and planned, which solves the problems of low efficiency and insufficient accuracy of path planning in the existing technology, and achieves more efficient and accurate path planning. .
Patent Information
- Application Number
- CN202411222780.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-02
- Publication Date
- 2025-01-21
AI Technical Summary
The prior art wind farm collecting line path planning is inefficient and insufficient, and it depends on human experience and is difficult to reflect terrain changes in a timely manner.
By obtaining the power transmission demand and site survey data of the wind farm, analyzing the environmental and facility data, generating multiple candidate paths, and performing path planning based on the environmental and cost data to determine the target path.
It improves the efficiency and accuracy of path planning, reduces reliance on human experience, can better reflect terrain changes and environmental factors, and reduces construction difficulty and cost.
Smart Images

Figure CN119338085A_ABST
Abstract
Description
Technical Field
[0001] The present disclosure relates to the field of electric power technology, and in particular to a path planning method and corresponding device for a wind farm collector line. Background Art
[0002] The wind farm's collector line is mainly a power line connecting the wind turbine generator set and the wind farm booster station, and can transmit the electricity generated by the wind turbine generator set to the power grid. In related technologies, relevant personnel plan the path corresponding to the wind farm collector line based on the wind farm map information based on path planning experience, or use drones to plan the path corresponding to the wind farm collector line. However, when planning the path corresponding to the wind farm collector line by this method, the efficiency of the planned path may be low and the accuracy of the planned path may be low. Summary of the invention
[0003] The purpose of the present disclosure is to provide a path planning method and a corresponding device for a wind farm collector line to solve the technical problems existing in the related art.
[0004] In order to achieve the above objectives, in a first aspect, the present disclosure provides a path planning method for a wind farm collector line, comprising: Acquire the power transmission demand of the wind farm collection line and the site survey data around the wind farm, wherein the site survey data includes the environmental data around the wind farm and the site facility data of the wind farm; Analyzing the environmental data to obtain environmental analysis data, and analyzing the site facility data to obtain location data of various facilities in the wind farm; generating a plurality of candidate paths corresponding to the collector lines between the wind turbine generator sets in the wind farm and the substation according to the environmental analysis data, the location data and the power transmission demand; Determining environmental data and cost data for each candidate path among the plurality of candidate paths; Path planning is performed on the multiple candidate paths according to the environmental data and the cost data to obtain a target path.
[0005] Optionally, generating a plurality of candidate paths corresponding to the collector line between the wind turbine generator set in the wind farm and the substation according to the environmental analysis data, the location data and the power transmission demand includes: Obtaining a constraint condition of the wind farm, wherein the constraint condition is used to characterize the area data of the candidate path corresponding to the collector line in the wind farm where the candidate path cannot be set; Converting the constraint conditions and the environmental analysis data into spatial layers and / or attribute data in a geographic information system; The location data, the power transmission demand, and the spatial layer and / or attribute data are analyzed and processed through the grid analysis function in the geographic information system to generate multiple candidate paths corresponding to the collection line between the wind turbine generator set in the wind farm and the substation.
[0006] Optionally, performing path planning on the multiple candidate paths according to the environment data and the cost data to obtain a target path includes: Compare the cost data of each candidate path with a preset cost threshold, and determine a first number of candidate paths whose cost data is less than the preset cost threshold; The target path is determined according to the environmental data of each candidate path in the first number of candidate paths and a preset environmental assessment condition.
[0007] Optionally, performing path planning on the multiple candidate paths according to the environment data and the cost data to obtain a target path includes: Comparing the cost data of each candidate path with a preset cost threshold, and when the cost data of each candidate path is greater than the preset cost threshold, adjusting at least one of the path direction of each candidate path, the facilities connected by the path, and the surrounding environment of the path in response to the user, until a second number of candidate paths with the cost data less than the preset cost threshold exist among the plurality of candidate paths; The target path is determined according to the environmental data of each candidate path in the second number of candidate paths and a preset environmental assessment condition.
[0008] Optionally, the path planning method further includes: In response to an import operation on the target path in the simulation software, determining the target sub-candidate path model corresponding to the import operation; In response to a user's selection operation on a path direction, a tower type, and a conductor specification in the target sub-candidate path model, determining the target path model corresponding to the selection operation; In response to the user's evaluation operation on the target path model, when the evaluation operation shows that the power data corresponding to the target path meets the power transmission demand, the simulation is ended.
[0009] In a second aspect, the present disclosure provides a path planning device for a wind farm collector line, comprising a first data acquisition module, an analysis module, a path generation module, a determination module, and a planning module; The first data acquisition module is used to acquire the power transmission demand of the wind farm collector line and the site survey data around the wind farm, wherein the site survey data includes the environmental data around the wind farm and the site facility data of the wind farm; The analysis module is used to analyze the environmental data to obtain environmental analysis data, and to analyze the site facility data to obtain location data of various facilities in the wind farm; The path generation module is used to generate a plurality of candidate paths corresponding to the collector lines between the wind turbine generator sets in the wind farm and the substation according to the environmental analysis data, the location data and the power transmission demand; The determination module is used to determine the environmental data and cost data of each candidate path among the plurality of candidate paths; The planning module is used to perform path planning on the multiple candidate paths according to the environmental data and the cost data to obtain a target path.
[0010] Optionally, the path generation module includes: A second data acquisition module is used to acquire constraint conditions of the wind farm, where the constraint conditions are used to characterize the area data of the candidate path corresponding to the collector line in the wind farm where the candidate path cannot be set; A data conversion module, used for converting the constraint conditions and the environmental analysis data into spatial layers and / or attribute data in a geographic information system; The path generation submodule is used to analyze and process the location data, the power transmission demand and the spatial layer and / or attribute data through the grid analysis function in the geographic information system, and generate multiple candidate paths corresponding to the collection line between the wind turbine generator set in the wind farm and the substation.
[0011] Optionally, the planning module includes: A first determination submodule, configured to compare the cost data of each candidate path with a preset cost threshold, and determine a first number of candidate paths whose cost data is less than the preset cost threshold; The second determination submodule is used to determine the target path according to the environmental data of each candidate path in the first number of candidate paths and a preset environmental evaluation condition.
[0012] Optionally, the planning module includes: a comparison module, configured to compare the cost data of each candidate path with a preset cost threshold, and when the cost data of each candidate path is greater than the preset cost threshold, in response to a user adjusting at least one of the path direction of each candidate path, the facilities connected by the path, and the environment around the path, until a second number of candidate paths with the cost data less than the preset cost threshold exist among the plurality of candidate paths; The third determination submodule is used to determine the target path according to the environmental data of each candidate path in the second number of candidate paths and a preset environmental evaluation condition.
[0013] Optionally, the path planning device further includes: A fourth determination submodule, configured to, in response to an import operation for the target path in the simulation software, determine the target sub-candidate path model corresponding to the import operation; A fifth determination submodule, configured to determine the target path model corresponding to the selection operation by the user on the path direction, tower type and conductor specification in the target sub-candidate path model; The evaluation module is used to respond to the user's evaluation operation on the target path model, and end the simulation when the evaluation operation shows that the power data corresponding to the target path meets the power transmission demand.
[0014] In a third aspect, the present disclosure provides a path planning system for a wind farm collector line, including a data acquisition and processing module, a terrain analysis module, a path planning module, and a path selection module; The data acquisition and processing module is used to obtain the power transmission demand of the wind farm collection line and the site survey data around the wind farm, and input the power transmission demand into the path planning module, and input the site survey data into the site analysis module, wherein the site survey data includes the environmental data around the wind farm and the site facility data of the wind farm; The terrain analysis module is used to analyze the environmental data to obtain environmental analysis data, and to analyze the site facility data to obtain location data of various facilities in the wind farm, and to input the environmental analysis data and the location data into the path planning module; The path planning module is used to generate a plurality of candidate paths corresponding to the collector lines between the wind turbine generator sets in the wind farm and the substation according to the environmental analysis data, the location data and the power transmission demand, and input the plurality of candidate paths into the path selection module; The path selection module is used to determine the environmental data and cost data of each candidate path among the multiple candidate paths; and perform path planning on the multiple candidate paths according to the environmental data and the cost data to obtain a target path.
[0015] In a fourth aspect, the present disclosure provides a non-temporary computer-readable storage medium having a computer program stored thereon, which, when executed by a processor, implements the steps of any one of the methods provided in the first aspect of the present disclosure.
[0016] In a fifth aspect, the present disclosure provides an electronic device, including: a memory having a computer program stored thereon; A processor is used to execute the computer program in the memory to implement the steps of any one of the methods provided in the first aspect of the present disclosure.
[0017] In a sixth aspect, the present disclosure provides a computer program product, comprising a computer program, which, when executed by a processor, implements the steps of any one of the methods provided in the first aspect of the present disclosure.
[0018] Through the above technical solution, according to the environmental analysis data, location data and power transmission requirements of the wind farm, multiple candidate paths corresponding to the wind farm collection line are generated between the wind turbine generator set and the substation, and the multiple candidate paths are planned according to the cost data and environmental data corresponding to each candidate path to obtain the target path. Among them, the environmental analysis data and the location data are obtained by analyzing the site survey data around the wind farm. By using the environmental analysis data and location data obtained by analyzing the site survey data to determine the multiple candidate paths corresponding to the wind farm collection line, it is possible to reduce reliance on human experience to determine multiple paths, thereby improving the efficiency of candidate path planning and the accuracy of candidate path planning. According to the cost data and environmental data corresponding to the candidate paths, multiple candidate paths are planned to obtain the target path, which can improve the accuracy of the target path.
[0019] Other features and advantages of the present disclosure will be described in detail in the following detailed description. BRIEF DESCRIPTION OF THE DRAWINGS
[0020] The accompanying drawings are used to provide a further understanding of the present disclosure and constitute a part of the specification. Together with the following specific embodiments, they are used to explain the present disclosure but do not constitute a limitation of the present disclosure. In the accompanying drawings: Figure 1 The diagram is a schematic diagram showing a method for planning a path of electric lines in a wind farm according to an exemplary embodiment of the present disclosure.
[0021] Figure 2The diagram is a schematic diagram showing a path planning device for electric lines in a wind farm according to an exemplary embodiment of the present disclosure.
[0022] Figure 3 The diagram is a schematic diagram showing a path planning system for electric lines in a wind farm according to an exemplary embodiment of the present disclosure.
[0023] Figure 4 It is a block diagram of an electronic device according to an exemplary embodiment. DETAILED DESCRIPTION
[0024] The specific implementation of the present disclosure is described in detail below in conjunction with the accompanying drawings. It should be understood that the specific implementation described herein is only used to illustrate and explain the present disclosure, and is not used to limit the present disclosure.
[0025] It should be noted that all actions of acquiring signals, information or data in the present disclosure are carried out in compliance with the relevant data protection laws and policies of the country where the device is located and with the authorization given by the owner of the corresponding device.
[0026] Wind farm collection lines directly affect the power generation efficiency of wind farms and the stability of power grids, and are an important part of wind farm infrastructure. Reasonable planning of collection lines can reduce power loss, improve power generation efficiency, reduce the failure rate of power grids, and improve the reliability of power grids.
[0027] In the first related technology, when the location of the wind turbine generator set and the location of the booster station in the wind farm are determined, the path corresponding to the wind farm collector line is planned according to the topographic map or electronic map. For example, CAD (Computer-Aided Design) software can be used as the main planning tool, and relevant personnel manually judge the available paths based on the map information and select all feasible path plans. After completing the preliminary selection, the relevant personnel will review the selected path plan on the spot through surveying and mapping instruments. Then, based on the information of the field survey and combined with factors such as path length, construction difficulty, cost, and convenience of operation and maintenance, the optimal path corresponding to the collector line in the wind farm is determined. For example, by establishing a collection of tower groups, the enumeration method is used to meet the preset conditions to plan the line path, or the wind turbines are grouped according to the location of the wind turbine generator set, the location of the substation and the direction of the transmission line, and the path selection is performed manually.
[0028] In the second related technology, the path corresponding to the collector line in the wind farm is planned by using drone technology. Compared with the path plan based on topographic maps, electronic maps and surveying instruments, it can efficiently and accurately obtain high-resolution image data of the wind farm area, providing more detailed and reliable terrain information for path planning. For example, wind turbines can be intelligently grouped by setting constraints, and the line path can be planned using the Dijkstra algorithm.
[0029] However, the inventors found that when planning the path corresponding to the collector line in the wind farm through the first related technology, there is a lack of systematic and scientific planning methods, which is highly dependent on human experience, increasing a lot of manpower and time, while reducing the efficiency of path planning. The data update speed in the map or electronic map is slow, and it is unable to reflect the changes in terrain, new buildings or facilities in a timely manner, which leads to deviations between the planned path and the actual terrain, reducing the accuracy of path planning. The lack of multi-faceted consideration of local environmental factors leads to the planned path not meeting the actual environmental requirements, increasing the difficulty and cost of construction, and may cause damage to the environment.
[0030] When planning the path corresponding to the wind farm collection line through the second related technology, the flight distance, height and load capacity of the drone are subject to certain restrictions, which leads to the fact that the drone may not be able to cover all necessary areas or meet all requirements when planning large or complex wind farm collection lines. When subjected to adverse environments such as strong winds, heavy rains, high temperatures or cold weather, the operation of the drone may be seriously affected and unable to perform normal work.
[0031] In view of this, the present disclosure provides a path planning method and corresponding device for a wind farm collector line to solve the technical problems existing in the above-mentioned related technologies.
[0032] like Figure 1 As shown, Figure 1 is a schematic diagram showing a method for planning a path of a wind farm electric line according to an exemplary embodiment of the present disclosure, with reference to Figure 1 ,include: S101: Acquire power transmission requirements of a wind farm collection line and site survey data around the wind farm, wherein the site survey data includes environmental data around the wind farm and site facility data of the wind farm; S102: Analyze the environmental data to obtain environmental analysis data, and analyze the site facility data to obtain location data of various facilities in the wind farm; S103: generating a plurality of candidate paths corresponding to the collector lines between the wind turbine generator sets in the wind farm and the substation according to the environmental analysis data, the location data and the power transmission demand; S104: Determine the environment data and cost data of each candidate path among the plurality of candidate paths; S105: Perform path planning on the multiple candidate paths according to the environment data and the cost data to obtain a target path.
[0033] Through the above technical solution, according to the environmental analysis data, location data and power transmission requirements of the wind farm, multiple candidate paths corresponding to the wind farm collection line are generated between the wind turbine generator set and the substation, and the multiple candidate paths are planned according to the cost data and environmental data corresponding to each candidate path to obtain the target path. Among them, the environmental analysis data and the location data are obtained by analyzing the site survey data around the wind farm. By using the environmental analysis data and location data obtained by analyzing the site survey data to determine the multiple candidate paths corresponding to the wind farm collection line, it is possible to reduce reliance on human experience to determine multiple paths, thereby improving the efficiency of candidate path planning and the accuracy of candidate path planning. According to the cost data and environmental data corresponding to the candidate paths, multiple candidate paths are planned to obtain the target path, which can improve the accuracy of the target path.
[0034] In order to enable those skilled in the art to better understand the path planning method for wind farm collector lines provided by the present disclosure, the above steps are described in detail with examples below.
[0035] For example, the environmental data may be natural environmental data and cultural element data of the wind farm, wherein the natural environmental data may include natural data of the site, construction data of the site, and public restriction data of the site, and the cultural element data may be architectural art element data of the site.
[0036] In the natural environment data, the natural data of the site may include topographic conditions, climatic conditions and geological conditions. Among them, the topographic conditions can be described through topographic maps, contour maps and corresponding topographic data and through a set of strict and clear expression languages. The climatic conditions can be the site wind conditions (wind direction, wind speed, air flow map, etc.), sunshine (sunshine hours, sunshine percentage, solar azimuth, etc.), temperature and precipitation. The geological conditions may include topography, geological structure, hydrogeology and earthquake conditions.
[0037] The construction data of the site may include regional location conditions, surrounding site conditions, internal construction conditions, and municipal facilities conditions. Among them, the regional location conditions may be the macro-environmental conditions in the area where the wind farm is located, and the surrounding site conditions may be the construction conditions of adjacent sites, special landscapes near the base, and cultural elements. Internal construction conditions may be the current conditions of buildings / structures, the conditions of site facilities (electricity, water facilities, etc.), and the current greening and vegetation. Municipal facilities conditions may be traffic conditions, water supply and drainage, and access points for electrical and telecommunication circuits.
[0038] The public restriction data of the site may include land use restrictions, land use nature, traffic control, density control, height control and population status. Among them, land use restrictions can be site boundaries (road red lines, land use red lines, building red lines, various lines), lengths of each side of the site and area data. The land use nature can be the positioning of the site use in urban planning. Traffic control can be the direction, size and parking conditions of the site's pedestrian and vehicle traffic. Density control can include building density and floor area ratio, and density control mainly represents the spatial distribution of blocks. Height control can include height restrictions and building floor control. Population status can be the number of existing residents in the site, the number of households and the population structure.
[0039] The data of architectural art elements may include site context analysis, cultural facade, site base analysis, site section, important buildings and landscape analysis in the site, sight line analysis in the site, volume analysis and local resident survey. Among them, site context analysis can be the overview of the surrounding and site buildings and cultural history, important historical events and historical elements. The cultural facade can be the more distinctive culture in the site. Site base analysis can be the plane base conversion analysis of buildings, vegetation, roads, and important water bodies. Site section can be the relationship between the existing buildings and landscape elements and terrain in the site. The analysis method in the analysis of important buildings and landscapes in the site can be a general architectural analysis method, such as block, light and shadow, material, space, function, traffic, etc. The sight line analysis in the site can be through the analysis of the best viewing angle of each building, and then a spatial model of a good sight corridor can be established. Volume analysis can study the volume relationship of buildings or important retained elements in the site, and find suitable building volume forms and insertion points. Local resident surveys can be for residents who usually live in the site.
[0040] The facility data of the site may be location data and layout data of each facility in the wind farm, wherein the facility may include a wind turbine generator set, a booster station, and a transformer substation, which is not specifically limited in the present disclosure.
[0041] The power transmission demand may be the required capacity that the user expects the path corresponding to the wind farm collection line to transmit in the wind farm to reach.
[0042] For example, environmental data can be analyzed to obtain environmental analysis data. Among them, when analyzing environmental data, the site analysis method can be used to analyze environmental data. Site analysis can be used to study the conditions of wind farms that need to be built and utilized, determine the essential attributes of wind farms and the relationships and contradictions between the various parts of the site, analyze the natural conditions, construction conditions and planning requirements of the wind farm where the building is located, and clarify the various factors affecting the site design. And after performing site analysis on environmental data, the wind farm can be evaluated from multiple factors such as topography, hydrogeology, climatic conditions and ecological sensitive areas. So that when the environmental analysis data is used for subsequent planning of candidate paths, it can be guaranteed that the candidate paths are environmentally friendly and sustainable paths for users. At the same time, it can also ensure that the collector lines operate in coordination with these facilities, thereby improving the overall operating efficiency of the wind farm.
[0043] The facility data of the site may be analyzed to obtain the location data of facilities in various directions in the wind farm, wherein the location data of facilities in various directions may include the location data of wind turbines and the location data of substations, which is not specifically limited in the embodiments of the present disclosure.
[0044] For example, multiple candidate paths corresponding to the collection line can be generated between the wind turbine and the substation based on the environmental analysis data, location data and power transmission requirements, and each candidate path can include parameters such as the number of wind turbines, the cross-section and length of the wire corresponding to the candidate path.
[0045] In a possible manner, generating a plurality of candidate paths corresponding to the collector line between the wind turbine generator set in the wind farm and the substation according to the environmental analysis data, the location data and the power transmission demand includes: Obtaining a constraint condition of the wind farm, wherein the constraint condition is used to characterize the area data of the candidate path corresponding to the collector line in the wind farm where the candidate path cannot be set; Converting the constraint conditions and the environmental analysis data into spatial layers and / or attribute data in a geographic information system; The location data, the power transmission demand, and the spatial layer and / or attribute data are analyzed and processed through the grid analysis function in the geographic information system to generate multiple candidate paths corresponding to the collection line between the wind turbine generator set in the wind farm and the substation.
[0046] It should be understood that the constraint condition may be regional data where candidate paths cannot be set in the wind farm. For example, the constraint condition may be restricted areas such as cultivated land, forest land, and protected areas; areas with unfavorable construction conditions such as caves, rivers, and earthquake zones; areas with sensitive factors such as cultural relics and minerals; and unfavorable meteorological conditions such as low temperature, repeated ice areas, and high altitudes.
[0047] A geographic information system (GIS) can be used to capture, store, analyze and manage geographic spatial data. In this embodiment, the constraints and environmental analysis data can be imported into the GIS together, and the constraints and environmental analysis data can be converted into spatial layers and / or attribute data through the GIS. For example, the prohibited construction area in the constraint condition can be set as an inaccessible area. The spatial layer can be used to represent a two-dimensional or three-dimensional model of a wind farm, and the attribute data can be non-spatial information associated with the geographic elements in the spatial layer.
[0048] Then, the location data, power transmission requirements, and spatial layers and / or attribute data can be analyzed and processed through the network analysis function in the geographic information system, and multiple candidate paths corresponding to the collector line can be generated between the wind turbine and the substation. The starting point of each candidate path is the wind turbine and the end point is the substation.
[0049] Based on the location data, power transmission requirements and constraints, the geographic information system generates multiple candidate paths between the wind turbine generator set and the substation, thereby increasing the speed of data update in the geographic information system. Compared with the planning of candidate paths corresponding to the collector line by relevant personnel based on the topographic map and the planning of paths by drones, the planning efficiency can be improved, and the accuracy of the candidate paths can be improved. At the same time, when multiple candidate paths are used to determine the target path in the future, the optimal line direction and tower position of the target path can be improved, thereby improving the safety and reliability of the path.
[0050] For example, in each candidate path, the candidate path has corresponding environmental data and cost data, and the environmental data of the candidate path can be electromagnetic environment data, noise environment data, ecological environment data, land resource data, water environment data, etc. Among them, the electromagnetic environment data can be the power frequency electric field and power frequency magnetic field generated by the candidate path during operation. The noise environment data can be the audible noise that may be generated by the candidate path during operation, such as the vibration of the wire in the wind, corona discharge, etc., and the noise generated by construction machinery and transportation vehicles during the construction of the candidate path. The ecological environment data can be the data such as vegetation destruction, topography changes, and wildlife habitats affected by construction activities during the construction of the candidate path. The land resource data can be the line corridor, substation construction land, etc. when constructing the candidate path. The water environment data can be the construction wastewater that may be generated when constructing the candidate path, such as foundation pit drainage, equipment cleaning water, etc.
[0051] The cost data can be determined based on the construction cost data, maintenance cost data and wind farm operation efficiency. Then, multiple candidate paths can be planned based on the environmental data and cost data to obtain the target path.
[0052] By planning multiple candidate paths through the environmental data and cost data and obtaining the target path, the negative impact of wind farm construction on the environment can be reduced, thereby improving the sustainable development capacity of the wind farm. At the same time, it can also provide comprehensive data support and scientific analysis methods, thereby improving the determination of the target path.
[0053] In a possible manner, performing path planning on the multiple candidate paths according to the environment data and the cost data to obtain a target path includes: Compare the cost data of each candidate path with a preset cost threshold, and determine a first number of candidate paths whose cost data is less than the preset cost threshold; The target path is determined according to the environmental data of each candidate path in the first number of candidate paths and a preset environmental assessment condition.
[0054] It should be understood that the preset cost threshold may be the minimum cost value that the user expects to achieve. When the cost data of a candidate path is less than the preset cost threshold, it may represent that the candidate path at this time is the candidate path expected by the user, and all candidate paths with cost data less than the preset cost threshold may be determined as the first number of candidate paths.
[0055] In the first number of candidate paths, the target path can be determined according to the golden data of each candidate path and the preset environmental evaluation condition, wherein the preset environmental evaluation condition can be the environmental benefit that the user expects to achieve in the process of constructing the candidate path.
[0056] Determining the target path from multiple candidate paths based on cost data and environmental data can comprehensively consider various constraints of the wind farm, thereby avoiding the target path crossing rugged terrain or areas prone to natural disasters, and achieving a balance between economy and feasibility when building a wind farm. At the same time, it can also improve the safety of wind power and avoid geological disasters in wind farms. At the same time, it can also reduce the length of the candidate path and reduce the loss of the candidate path, thereby improving the transmission efficiency of the candidate path.
[0057] In a possible manner, performing path planning on the multiple candidate paths according to the environment data and the cost data to obtain a target path includes: Comparing the cost data of each candidate path with a preset cost threshold, and when the cost data of each candidate path is greater than the preset cost threshold, adjusting at least one of the path direction of each candidate path, the facilities connected by the path, and the surrounding environment of the path in response to the user, until a second number of candidate paths with the cost data less than the preset cost threshold exist among the plurality of candidate paths; The target path is determined according to the environmental data of each candidate path in the second number of candidate paths and a preset environmental assessment condition.
[0058] It should be understood that when the cost data corresponding to each candidate path is less than the preset cost threshold, it may mean that there is no candidate path to continue the environmental assessment at this time. At this time, the user can adjust the path direction on the candidate path, the facilities connected by the path, and the environment around the path, so that there are a second number of candidate paths less than the preset cost threshold among the multiple candidate paths. The facilities connected by the path can be equipment such as poles, wind turbines, etc. The path direction can be the direction in which the path is laid. Then, among the second number of candidate paths, the target path is determined based on the environmental data of each candidate path and the preset environmental assessment conditions.
[0059] Determining the target path from multiple candidate paths based on cost data and environmental data can comprehensively consider various constraints of the wind farm, thereby avoiding the target path crossing rugged terrain or areas prone to natural disasters, and achieving a balance between economy and feasibility when building a wind farm. At the same time, it can also improve the safety of wind power and avoid geological disasters in wind farms. At the same time, it can also reduce the length of the candidate path and reduce the loss of the candidate path, thereby improving the transmission efficiency of the candidate path.
[0060] In a possible manner, the path planning method further includes: In response to an import operation on the target path in the simulation software, determining the target sub-candidate path model corresponding to the import operation; In response to a user's selection operation on a path direction, a tower type, and a conductor specification in the target sub-candidate path model, determining the target path model corresponding to the selection operation; In response to the user's evaluation operation on the target path model, when the evaluation operation shows that the power data corresponding to the target path meets the power transmission demand, the simulation is ended.
[0061] It should be understood that after determining the target path, in order to enable the target path to meet the power transmission requirements during the actual construction process, the path direction, tower type and conductor specifications required for the target path can be set in the simulation software platform.
[0062] Then, the target path can be simulated in the simulation software. First, the target can be imported into the simulation software, and the target sub-candidate path model can be obtained in the simulation software. Then, based on the target sub-candidate path model, the path direction, tower type and conductor specification can be selected to obtain the target path model, and then the target path model can be evaluated. When the evaluation result shows that the power data corresponding to the target path does not meet the power transmission demand, the path direction, tower type and conductor specification are adjusted until the power data corresponding to the target path meets the power transmission demand.
[0063] The simulation software may be any one of the overhead transmission line software, the transmission line digital platform and Daoheng software, and this embodiment does not make any specific limitation on this.
[0064] Based on the same concept, this embodiment also discloses a path planning device 200 for a wind farm collector line, referring to Figure 2 , Figure 2 is a schematic diagram showing a path planning device 200 for a wind farm electric line according to an exemplary embodiment of the present disclosure, such as Figure 2 As shown, it includes a first data acquisition module 201, an analysis module 202, a path generation module 203, a determination module 204 and a planning module 205; The first data acquisition module 201 is used to acquire the power transmission demand of the wind farm collection line and the site survey data around the wind farm, wherein the site survey data includes the environmental data around the wind farm and the site facility data of the wind farm; The analysis module 202 is used to analyze the environmental data to obtain environmental analysis data, and to analyze the site facility data to obtain location data of various facilities in the wind farm; The path generation module 203 is used to generate a plurality of candidate paths corresponding to the collector lines between the wind turbine generator sets in the wind farm and the substation according to the environmental analysis data, the location data and the power transmission demand; The determination module 204 is used to determine the environment data and cost data of each candidate path among the plurality of candidate paths; The planning module 205 is used to perform path planning on the multiple candidate paths according to the environmental data and the cost data to obtain a target path.
[0065] Optionally, the path generation module 203 includes: A second data acquisition module is used to acquire constraint conditions of the wind farm, where the constraint conditions are used to characterize the area data of the candidate path corresponding to the collector line in the wind farm where the candidate path cannot be set; A data conversion module, used for converting the constraint conditions and the environmental analysis data into spatial layers and / or attribute data in a geographic information system; The path generation submodule is used to analyze and process the location data, the power transmission demand and the spatial layer and / or attribute data through the grid analysis function in the geographic information system, and generate multiple candidate paths corresponding to the collection line between the wind turbine generator set in the wind farm and the substation.
[0066] Optionally, the planning module 205 includes: A first determination submodule, configured to compare the cost data of each candidate path with a preset cost threshold, and determine a first number of candidate paths whose cost data is less than the preset cost threshold; The second determination submodule is used to determine the target path according to the environmental data of each candidate path in the first number of candidate paths and a preset environmental evaluation condition.
[0067] Optionally, the planning module 205 includes: a comparison module, configured to compare the cost data of each candidate path with a preset cost threshold, and when the cost data of each candidate path is greater than the preset cost threshold, in response to a user adjusting at least one of the path direction of each candidate path, the facilities connected by the path, and the environment around the path, until a second number of candidate paths with the cost data less than the preset cost threshold exist among the plurality of candidate paths; The third determination submodule is used to determine the target path according to the environmental data of each candidate path in the second number of candidate paths and a preset environmental evaluation condition.
[0068] Optionally, the path planning device further includes: A fourth determination submodule, configured to, in response to an import operation for the target path in the simulation software, determine the target sub-candidate path model corresponding to the import operation; A fifth determination submodule, configured to determine the target path model corresponding to the selection operation by the user on the path direction, tower type and conductor specification in the target sub-candidate path model; The evaluation module is used to respond to the user's evaluation operation on the target path model, and end the simulation when the evaluation operation shows that the power data corresponding to the target path meets the power transmission demand.
[0069] Regarding the device in the above embodiment, the specific manner in which each module performs operations has been described in detail in the embodiment of the method, and will not be elaborated here.
[0070] Based on the same concept, this embodiment also discloses a path planning system for wind farm collector lines, referring to Figure 3 , Figure 3 It is a schematic diagram showing a path planning system for electric lines in a wind farm according to an exemplary embodiment of the present disclosure, as shown in the figure, including a data acquisition and processing module 301, a terrain analysis module 302, a path planning module 303 and a path selection module 304; The data acquisition and processing module 301 is used to obtain the power transmission demand of the wind farm collection line and the site survey data around the wind farm, and input the power transmission demand into the path planning module, and input the site survey data into the site analysis module, wherein the site survey data includes the environmental data around the wind farm and the site facility data of the wind farm; The terrain analysis module 302 is used to analyze the environmental data to obtain environmental analysis data, and to analyze the site facility data to obtain location data of various facilities in the wind farm, and to input the environmental analysis data and the location data into the path planning module; The path planning module 303 is used to generate a plurality of candidate paths corresponding to the collector lines between the wind turbines in the wind farm and the substation according to the environmental analysis data, the location data and the power transmission demand, and input the plurality of candidate paths into the path selection module; The path selection module 304 is used to determine the environment data and cost data of each candidate path among the multiple candidate paths; and perform path planning on the multiple candidate paths according to the environment data and the cost data to obtain a target path.
[0071] Through the above technical scheme, according to the site survey data and facility data of the wind farm obtained, and the site survey data and facility data are analyzed and processed, the risk factors of each part of the wind farm can be more comprehensively understood, which provides strong data support for subsequent path planning, makes the target path selection more in line with the actual situation, and reduces blindness and uncertainty. By performing cost-benefit analysis and environmental analysis on the candidate paths, selecting a target path that is both economical and efficient can reduce construction costs and maintenance costs, and can improve the economic benefits of the wind farm. Through spatial analysis and simulation of wind farms by geographic information system technology, the optimal line direction and tower location can be determined; using simulation software to conduct risk assessment and prediction of the target path, the operating status and safety performance of the target path under different conditions can be predicted. In this way, it can be ensured that the target path meets the power transmission needs and safety requirements, and at the same time, the safety and reliability of the path can be improved. It can provide comprehensive data support and scientific analysis methods, thereby improving the efficiency and accuracy of decision-making.
[0072] Based on the same concept, the present embodiment further discloses a non-temporary computer-readable storage medium on which a computer program is stored. When the computer program is executed by a processor, the steps of the path planning method for the wind farm collector line disclosed in the present embodiment are implemented.
[0073] Based on the same concept, this embodiment also discloses an electronic device, including: a memory having a computer program stored thereon; The processor is used to execute the computer program in the memory to implement the steps of the path planning method for the wind farm collector line disclosed in this embodiment.
[0074] Based on the same concept, this embodiment further discloses a computer program product, including a computer program, which, when executed by a processor, implements the steps of the path planning method for the wind farm collector line disclosed in this embodiment.
[0075] Figure 4 FIG. 4 is a block diagram of an electronic device 400 according to an exemplary embodiment. Figure 4 As shown, the electronic device 400 may include: a processor 401 , a memory 402 . The electronic device 400 may also include one or more of a multimedia component 403 , an input / output (I / O) interface 404 , and a communication component 405 .
[0076] The processor 401 is used to control the overall operation of the electronic device 400 to complete all or part of the steps in the path planning method for the wind farm collector line. The memory 402 is used to store various types of data to support the operation of the electronic device 400, and these data may include, for example, instructions for any application or method used to operate on the electronic device 400, and application-related data, such as contact data, sent and received messages, pictures, audio, video, etc. The memory 402 can be implemented by any type of volatile or non-volatile storage device or a combination thereof, such as static random access memory (Static Random Access Memory, referred to as SRAM), electrically erasable programmable read-only memory (Electrically Erasable Programmable Read-Only Memory, referred to as EEPROM), erasable programmable read-only memory (Erasable Programmable Read-Only Memory, referred to as EPROM), programmable read-only memory (Programmable Read-Only Memory, referred to as PROM), read-only memory (Read-Only Memory, referred to as ROM), magnetic memory, flash memory, disk or optical disk. The multimedia component 403 may include a screen and an audio component. The screen may be, for example, a touch screen, and the audio component is used to output and / or input audio signals. For example, the audio component may include a microphone, which is used to receive external audio signals. The received audio signal may be further stored in the memory 402 or sent through the communication component 405. The audio component also includes at least one speaker for outputting audio signals. The I / O interface 404 provides an interface between the processor 401 and other interface modules, and the above-mentioned other interface modules may be keyboards, mice, buttons, etc. These buttons may be virtual buttons or physical buttons. The communication component 405 is used for wired or wireless communication between the electronic device 400 and other devices. Wireless communication, such as Wi-Fi, Bluetooth, Near Field Communication (NFC), 2G, 3G, 4G, NB-IOT, eMTC, or other 5G, etc., or a combination of one or more of them, is not limited here. Therefore, the corresponding communication component 405 may include: Wi-Fi module, Bluetooth module, NFC module, etc.
[0077] In an exemplary embodiment, the electronic device 400 can be implemented by one or more application specific integrated circuits (ASIC), digital signal processors (DSP), digital signal processing devices (DSPD), programmable logic devices (PLD), field programmable gate arrays (FPGA), controllers, microcontrollers, microprocessors or other electronic components to execute the above-mentioned path planning method for wind farm collection lines.
[0078] In another exemplary embodiment, a computer-readable storage medium including program instructions is also provided, and when the program instructions are executed by a processor, the steps of the above-mentioned path planning method for the wind farm collector line are implemented. For example, the computer-readable storage medium can be the above-mentioned memory 402 including program instructions, and the above-mentioned program instructions can be executed by the processor 401 of the electronic device 400 to complete the above-mentioned path planning method for the wind farm collector line.
[0079] The preferred embodiments of the present disclosure are described in detail above in conjunction with the accompanying drawings; however, the present disclosure is not limited to the specific details in the above embodiments. Within the technical concept of the present disclosure, a variety of simple modifications can be made to the technical solution of the present disclosure, and these simple modifications all fall within the protection scope of the present disclosure.
[0080] It should also be noted that the various specific technical features described in the above specific embodiments can be combined in any suitable manner without contradiction. In order to avoid unnecessary repetition, the present disclosure will not further describe various possible combinations.
[0081] In addition, various embodiments of the present disclosure may be arbitrarily combined, and as long as they do not violate the concept of the present disclosure, they should also be regarded as the contents disclosed by the present disclosure.
Claims
1. A path planning method for a wind farm collector line, characterized in that: include: Acquire the power transmission demand of the wind farm collection line and the site survey data around the wind farm, wherein the site survey data includes the environmental data around the wind farm and the site facility data of the wind farm; Analyzing the environmental data to obtain environmental analysis data, and analyzing the site facility data to obtain location data of various facilities in the wind farm; generating a plurality of candidate paths corresponding to the collector lines between the wind turbine generator sets in the wind farm and the substation according to the environmental analysis data, the location data and the power transmission demand; Determining environmental data and cost data for each candidate path among the plurality of candidate paths; Path planning is performed on the multiple candidate paths according to the environmental data and the cost data to obtain a target path.
2. The path planning method for wind farm collector lines according to claim 1, characterized in that: The step of generating a plurality of candidate paths corresponding to the collector line between the wind turbine generator set in the wind farm and the substation according to the environmental analysis data, the location data and the power transmission demand comprises: Obtaining a constraint condition of the wind farm, wherein the constraint condition is used to characterize the area data of the candidate path corresponding to the collector line in the wind farm where the candidate path cannot be set; Converting the constraint conditions and the environmental analysis data into spatial layers and / or attribute data in a geographic information system; The location data, the power transmission demand, and the spatial layer and / or attribute data are analyzed and processed through the grid analysis function in the geographic information system to generate multiple candidate paths corresponding to the collection line between the wind turbine generator set in the wind farm and the substation.
3. The path planning method for wind farm collector lines according to claim 1, characterized in that: The performing path planning on the multiple candidate paths according to the environment data and the cost data to obtain a target path includes: Compare the cost data of each candidate path with a preset cost threshold, and determine a first number of candidate paths whose cost data is less than the preset cost threshold; The target path is determined according to the environmental data of each candidate path in the first number of candidate paths and a preset environmental assessment condition.
4. The path planning method for wind farm collector lines according to claim 1, characterized in that: The performing path planning on the multiple candidate paths according to the environment data and the cost data to obtain a target path includes: Comparing the cost data of each candidate path with a preset cost threshold, and when the cost data of each candidate path is greater than the preset cost threshold, adjusting at least one of the path direction of each candidate path, the facilities connected by the path, and the surrounding environment of the path in response to the user, until a second number of candidate paths with the cost data less than the preset cost threshold exist among the plurality of candidate paths; The target path is determined according to the environmental data of each candidate path in the second number of candidate paths and a preset environmental assessment condition.
5. The path planning method for wind farm collector lines according to claim 1, characterized in that: The path planning method further includes: In response to an import operation on the target path in the simulation software, determining the target sub-candidate path model corresponding to the import operation; In response to a user's selection operation on a path direction, a tower type, and a conductor specification in the target sub-candidate path model, determining the target path model corresponding to the selection operation; In response to the user's evaluation operation on the target path model, when the evaluation operation shows that the power corresponding to the target path meets the power transmission demand, the simulation is ended.
6. A path planning device for a wind farm collector line, characterized in that: It includes a first data acquisition module, an analysis module, a path generation module, a determination module and a planning module; The first data acquisition module is used to acquire the power transmission demand of the wind farm collector line and the site survey data around the wind farm, wherein the site survey data includes the environmental data around the wind farm and the site facility data of the wind farm; The analysis module is used to analyze the environmental data to obtain environmental analysis data, and to analyze the site facility data to obtain location data of various facilities in the wind farm; The path generation module is used to generate a plurality of candidate paths corresponding to the collector lines between the wind turbine generator sets in the wind farm and the substation according to the environmental analysis data, the location data and the power transmission demand; The determination module is used to determine the environmental data and cost data of each candidate path among the plurality of candidate paths; The planning module is used to perform path planning on the multiple candidate paths according to the environmental data and the cost data to obtain a target path.
7. The path planning device for wind farm collector lines according to claim 6, characterized in that: The path generation module comprises: A second data acquisition module is used to acquire constraint conditions of the wind farm, where the constraint conditions are used to characterize the area data of the candidate path corresponding to the collector line in the wind farm where the candidate path cannot be set; A data conversion module, used for converting the constraint conditions and the environmental analysis data into spatial layers and / or attribute data in a geographic information system; The path generation submodule is used to analyze and process the location data, the power transmission demand and the spatial layer and / or attribute data through the grid analysis function in the geographic information system, and generate multiple candidate paths corresponding to the collection line between the wind turbine generator set in the wind farm and the substation.
8. The path planning device for wind farm collector lines according to claim 6, characterized in that: The planning module includes: A first determination submodule, configured to compare the cost data of each candidate path with a preset cost threshold, and determine a first number of candidate paths whose cost data is less than the preset cost threshold; The second determination submodule is used to determine the target path according to the environmental data of each candidate path in the first number of candidate paths and a preset environmental evaluation condition.
9. The path planning device for wind farm collector lines according to claim 6, characterized in that: The planning module includes: a comparison module, configured to compare the cost data of each candidate path with a preset cost threshold, and when the cost data of each candidate path is greater than the preset cost threshold, in response to a user adjusting at least one of the path direction of each candidate path, the facilities connected by the path, and the environment around the path, until a second number of candidate paths with the cost data less than the preset cost threshold exist among the plurality of candidate paths; The third determination submodule is used to determine the target path according to the environmental data of each candidate path in the second number of candidate paths and a preset environmental evaluation condition.
10. The path planning device for wind farm collector lines according to claim 6, characterized in that: The path planning device also includes: A fourth determination submodule, configured to, in response to an import operation for the target path in the simulation software, determine the target sub-candidate path model corresponding to the import operation; A fifth determination submodule, configured to determine the target path model corresponding to the selection operation by the user on the path direction, tower type and conductor specification in the target sub-candidate path model; The evaluation module is used to respond to the user's evaluation operation on the target path model, and end the simulation when the evaluation operation shows that the power corresponding to the target path meets the power transmission demand.
11. A path planning system for a wind farm collector line, characterized in that: It includes data acquisition and processing module, terrain analysis module, path planning module and path selection module; The data acquisition and processing module is used to obtain the power transmission demand of the wind farm collection line and the site survey data around the wind farm, and input the power transmission demand into the path planning module, and input the site survey data into the site analysis module, wherein the site survey data includes the environmental data around the wind farm and the site facility data of the wind farm; The terrain analysis module is used to analyze the environmental data to obtain environmental analysis data, and to analyze the site facility data to obtain location data of various facilities in the wind farm, and to input the environmental analysis data and the location data into the path planning module; The path planning module is used to generate a plurality of candidate paths corresponding to the collector lines between the wind turbine generator sets in the wind farm and the substation according to the environmental analysis data, the location data and the power transmission demand, and input the plurality of candidate paths into the path selection module; The path selection module is used to determine the environmental data and cost data of each candidate path among the plurality of candidate paths; And path planning is performed on the multiple candidate paths according to the environmental data and the cost data to obtain a target path.
12. A non-transitory computer-readable storage medium having a computer program stored thereon, characterized in that: When the computer program is executed by a processor, the steps of the method according to any one of claims 1 to 5 are implemented.
13. An electronic device, characterized in that: include: a memory having a computer program stored thereon; A processor, configured to execute the computer program in the memory to implement the steps of the method according to any one of claims 1 to 5.
14. A computer program product comprising a computer program, characterized in that When the computer program is executed by a processor, the steps of the method according to any one of claims 1 to 5 are implemented.
Citation Information
Cited By
Power transmission method and device based on offshore energy island of deep sea, terminal equipment and storage medium