Desert brine sampling device and method

By designing a desert brine sampling device including auger and a sampling cylinder, the problem of low brine sampling efficiency in the prior art is solved, efficient sampling without manual excavation is achieved, and sampling efficiency is significantly improved.

CN119394713APending Publication Date: 2025-02-07CHINA GEOLOGICAL SURVEY URUMQI NATURAL RESOURCES COMPREHENSIVE SURVEY CENT
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411605478.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-11-11
Publication Date
2025-02-07

AI Technical Summary

Technical Problem

In desert environments, the prior art is inefficient in brine sampling, requires a lot of manpower and material resources, and has extremely low sampling efficiency.

Method used

Design a desert brine sampling device, including auger and a sampling barrel, the auger has a hollow cavity, and the drill rod drives the auger to drill. When brine is observed in the drill hole, the sampling barrel is placed in the hollow cavity of the auger. Extend into the drill hole to take samples.

Benefits of technology

There is no need for manual excavation and sampling of underground samples, which improves the efficiency of brine sampling in desert areas, has low labor intensity and significantly improves efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119394713A_ABST
    Figure CN119394713A_ABST
Patent Text Reader

Abstract

The invention discloses a desert brine sampling device and method, and relates to the technical field of sampling devices.The desert brine sampling device comprises a twist drill which is provided with a hollow cavity, the top of the twist drill is connected with a drill rod, and the bottom of the twist drill is provided with drilling teeth; the sampling barrel can be placed in the hollow cavity of the twist drill, a sampling opening is formed in the side wall of the sampling barrel, and brine can enter the sampling barrel through the sampling opening. According to the sampling method based on the desert brine sampling device, the brine sampling efficiency of the desert area can be improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of sampling devices, and in particular to a desert brine sampling device and method. Background Art

[0002] Brine refers to liquid minerals with a salt content greater than 5%. Brine that accumulates on the surface is called surface brine or lake brine. Brine that accumulates below the ground is called underground brine. In order to study underground brine, it is necessary to use a sampler to sample the brine underground, collect it and then conduct testing and analysis. In the past, when sampling brine in a desert environment, manual excavation was often used to dig 3 to 4 meters underground, and 3 to 5 brine samples could be taken every day. This not only consumed a lot of manpower and material resources, but also had extremely low sampling efficiency. Therefore, it is urgent to design an efficient sampling tool and sampling method to improve the efficiency of brine sampling in desert areas. Summary of the invention

[0003] The purpose of the present invention is to provide a desert brine sampling device and method to solve the problems existing in the above-mentioned prior art and to improve the brine sampling efficiency in desert areas.

[0004] To achieve the above object, the present invention provides the following solutions:

[0005] The present invention provides a desert brine sampling device, comprising:

[0006] An auger having a hollow cavity with a drill rod connected to the top and drilling teeth at the bottom;

[0007] The sampling barrel can be placed in the hollow cavity of the auger, and a sampling port is provided on the side wall of the sampling barrel, through which brine can enter the sampling barrel.

[0008] Preferably, the drill rod comprises a plurality of extension rods, the plurality of extension rods are fixedly connected end to end in sequence via threads, and the extension rod located at the bottom is fixedly connected to the top of the auger.

[0009] Preferably, a cross handle is threadedly connected to the top of the drill rod.

[0010] Preferably, the auger comprises a cylinder with openings at both ends, the hollow cavity is opened in the cylinder, the drilling teeth are integrally formed at the bottom of the cylinder, an inverted U-shaped connecting frame is provided at the top of the cylinder, and the top of the inverted U-shaped connecting frame is connected to the drill rod.

[0011] Preferably, a slot is provided on the inner side of the top of the cylinder body, and a hook is provided on the top of the sampling cylinder, and the hook can be engaged in the slot.

[0012] Preferably, the side wall of the cylinder is provided with two symmetrical elliptical openings.

[0013] Preferably, the bottom of the sampling tube is closed, a sealing cover is connected to the top, and the side wall of the sampling tube is a double-layer structure; the sampling port runs through the side wall in the middle of the sampling tube, and absorbent sponge is provided between the inner side wall and the outer side wall of the sampling tube, and the absorbent sponge is located at the sampling port.

[0014] Preferably, a water inlet is provided on the upper side wall of the sampling tube.

[0015] Preferably, it also includes a funnel and a sampling bottle, and gauze is laid in the funnel.

[0016] The present invention also provides a method for sampling desert brine, comprising the following steps:

[0017] Step 1: Use a shovel to scrape away the soft fine sand on the surface at the sampling location;

[0018] Step 2: Place the auger at the sampling position, press and turn the cross handle to drive the auger downward, and after the hollow cavity of the auger is filled with sand, lift it up from the borehole, remove the sand inside, and then re-insert it into the borehole for drilling;

[0019] Step 3, repeating step 3 until the sand layer is penetrated and brine is observed in the borehole;

[0020] Step 4: Install the sampling tube into the hollow cavity of the auger and insert it into the borehole to take out the brine.

[0021] Compared with the prior art, the present invention has achieved the following technical effects:

[0022] The present invention uses an auger with a hollow cavity to drill a hole at a location to be sampled. After brine is observed in the hole, a sampling tube is placed in the hollow cavity of the auger and inserted into the hole to sample the brine. There is no need for manual underground digging for sampling, thereby improving the brine sampling efficiency in desert areas. BRIEF DESCRIPTION OF THE DRAWINGS

[0023] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0024] Figure 1 This is a schematic diagram of the structure of the desert brine sampling device of the present invention;

[0025] Figure 2 It is a schematic diagram of the installation of the sampling tube and the auger of the present invention;

[0026] Figure 3 It is a schematic diagram of a drill rod of the present invention;

[0027] Figure 4 It is a schematic diagram of the funnel and sampling bottle of the present invention.

[0028] In the figure: 1-auger, 101-drilling teeth, 102-inverted U-shaped connecting frame, 103-cylinder body, 104-slot, 2-sampling cylinder, 201-sampling port, 202-water intake port, 203-hook, 3-drill rod, 301-extension rod, 4-cross handle, 5-funnel, 6-sampling bottle. DETAILED DESCRIPTION

[0029] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0030] The purpose of the present invention is to provide a desert brine sampling device and method to solve the problems existing in the above-mentioned prior art and to improve the brine sampling efficiency in desert areas.

[0031] In order to make the above-mentioned objects, features and advantages of the present invention more obvious and easy to understand, the present invention is further described in detail below with reference to the accompanying drawings and specific embodiments.

[0032] In view of the known brine sampling in desert areas, it is necessary to manually dig downward until brine appears to realize sampling. In order to improve the sampling efficiency, the present invention provides a desert brine sampling device, such as Figure 1 , Figure 2 , Figure 3 and Figure 4 As shown, it includes an auger 1, which has a hollow cavity, and a drill rod 3 is connected to the top of the auger, and a drilling tooth 101 is provided at the bottom. The drilling tooth 101 is a spiral blade structure. A plurality of spiral blade structures are arranged on the side of the bottom of the auger 1. The use of the spiral blade structure makes it convenient and labor-saving to drill through the sand layer, and the labor intensity is low. The drill rod 3 can drive the auger 1 to drill downward, and when brine can be observed in the borehole; the sampling tube 2 is placed in the hollow cavity of the auger 1 and extended into the bottom of the borehole. A sampling port 201 is opened on the side wall of the sampling tube 2, and brine can enter the sampling tube 2 through the sampling port 201. There is no need for manual excavation and sampling, which improves the sampling efficiency.

[0033] In order to facilitate installation and storage, the drill rod 3 of this embodiment includes multiple extension rods 301, each of which is 1.5 meters long. The multiple extension rods 301 are fixedly connected end to end in sequence through threads, and the extension rod 301 located at the bottom is fixedly connected to the top of the auger 1, which is convenient for installation and disassembly. In a specific embodiment, different augers 1 can be replaced according to different sampling layers; in order to facilitate drilling and sampling, a cross handle 4 is threadedly connected to the top of the drill rod, so that the operator can hold the cross handle 4, rotate and press down the drill rod, and realize the drilling of the auger 1.

[0034] In order to facilitate drilling and sampling, the auger 1 of this embodiment includes a barrel 103 with openings at both ends, a hollow cavity is provided in the barrel 103, a plurality of drilling teeth 101 are integrally formed on the side of the bottom of the barrel 103, and an inverted U-shaped connecting frame 102 is provided at the top of the barrel 103. The top of the inverted U-shaped connecting frame 102 is connected to the drill rod 3, so that when drilling, sand can fill the hollow cavity, and then the auger 1 is lifted upward, and the drilling can be repeated after the sand is removed, and the hole can be drilled quickly until brine can be observed. In this embodiment, a slot 104 is provided on the inner side of the top of the barrel 103, and a hook 203 is provided on the top of the sampling barrel 2. The hook 203 can be snapped into the slot 104, so that the sampling barrel 2 can be fixed in the hollow cavity, which is convenient for the sampling barrel 2 to follow the auger 1 into the bottom of the borehole to sample brine.

[0035] In a preferred embodiment, two symmetrical elliptical openings are opened on the side wall of the barrel 103 of the auger 1, and the sampling port 201 of the sampling tube 2 is located at the elliptical opening, so that the side wall of the auger 1 will not hinder the brine from entering the sampling tube 2 from the sampling port 201.

[0036] The sampling tube 2 of the present embodiment is closed at the bottom, connected to a sealing cover at the top, and the side wall of the sampling tube 2 is a double-layer structure; the sampling port 201 passes through the side wall in the middle of the sampling tube 2, and absorbent sponges are provided between the inner side wall and the outer side wall of the sampling tube 2, and the absorbent sponges are located at the sampling port 201. A water intake port 202 is provided on the upper side wall of the sampling tube 2. When the underground brine content is low, the brine is absorbed by the absorbent sponge to enter the sampling tube 2 and is taken to the surface. When the brine content is high, the water intake port 202 can be directly used to fill the sampling tube 2 with brine and lift it to the surface.

[0037] The present invention also provides a method for sampling desert brine, comprising the following steps:

[0038] Step 1: Use a shovel to scrape away the soft fine sand on the surface at the sampling location; use a wrench to assemble the auger 1, the cross handle 4 and the extension rod 301;

[0039] Step 2: Place the auger 1 at the sampling position, press and turn the cross handle 4 to drive the auger 1 to drill downward, and after the hollow cavity of the auger 1 is filled with sand, lift it up from the borehole, remove the sand inside, and then re-insert it into the borehole for drilling;

[0040] Step 3, repeating step 3 until the sand layer is penetrated and brine is observed in the borehole;

[0041] Step 4: Install the sampling tube 2 into the hollow cavity of the auger 1, and insert it into the borehole to take out the brine.

[0042] When the brine content in the desert is relatively low, and no observable brine appears after drilling a hole to a set depth at the sampling position using the auger 1, the sampling tube 2 may not be used, and the auger 1 may be used instead to take the sand containing brine at the bottom of the hole to the surface. At this time, the funnel 5 and the sampling bottle 6 are introduced, gauze is laid in the funnel 5, and then the bottom of the funnel 5 is set at the opening of the sampling bottle 6, the sand containing brine is poured onto the gauze in the funnel 5, and the sand containing brine is filtered, so that the brine in the sand is filtered into the sampling bottle 6, and the sampling bottle 6 is repeatedly cleaned with the taken out brine to ensure that the sample is contaminated and the sampling is completed.

[0043] The present invention uses specific examples to illustrate the principles and implementation methods of the present invention. The above examples are only used to help understand the method and core ideas of the present invention. At the same time, for those skilled in the art, according to the ideas of the present invention, there will be changes in the specific implementation methods and application scope. In summary, the content of this specification should not be understood as limiting the present invention.

Claims

1. A desert brine sampling device, characterized in that: include: An auger having a hollow cavity with a drill rod connected to the top and drilling teeth at the bottom; The sampling barrel can be placed in the hollow cavity of the auger, and a sampling port is provided on the side wall of the sampling barrel, through which brine can enter the sampling barrel.

2. The desert brine sampling device according to claim 1, characterized in that: The drill rod comprises a plurality of extension rods, which are fixedly connected end to end in sequence through threads, and the extension rod located at the bottom is fixedly connected to the top of the auger.

3. The desert brine sampling device according to claim 1, characterized in that: The top of the drill rod is threadedly connected with a cross handle.

4. The desert brine sampling device according to claim 1, characterized in that: The auger comprises a cylinder with openings at both ends, the hollow cavity is arranged in the cylinder, the drilling teeth are integrally formed at the bottom of the cylinder, an inverted U-shaped connecting frame is arranged at the top of the cylinder, and the top of the inverted U-shaped connecting frame is connected to the drill rod.

5. The desert brine sampling device according to claim 4, characterized in that: A slot is provided inside the top of the cylinder body, and a hook is provided on the top of the sampling cylinder. The hook can be engaged in the slot.

6. The desert brine sampling device according to claim 4, characterized in that: The side wall of the cylinder is provided with two symmetrical elliptical openings.

7. The desert brine sampling device according to claim 1, characterized in that: The bottom of the sampling tube is closed, the top is connected with a sealing cover, and the side wall of the sampling tube is a double-layer structure; the sampling port runs through the side wall in the middle of the sampling tube, and absorbent sponges are provided between the inner side wall and the outer side wall of the sampling tube, and the absorbent sponges are located at the sampling port.

8. The desert brine sampling device according to claim 1, characterized in that: A water inlet is provided on the upper side wall of the sampling tube.

9. The desert brine sampling device according to claim 1, characterized in that: The invention also comprises a funnel and a sampling bottle, wherein gauze is laid in the funnel.

10. A method for sampling desert brine, characterized in that: The steps include: Step 1: Use a shovel to scrape away the soft fine sand on the surface at the sampling location; Step 2: Place the auger at the sampling position, press and turn the cross handle to drive the auger downward, and after the hollow cavity of the auger is filled with sand, lift it up from the borehole, remove the sand inside, and then re-insert it into the borehole for drilling; Step 3, repeating step 3 until the sand layer is penetrated and brine is observed in the borehole; Step 4: Install the sampling tube into the hollow cavity of the auger and insert it into the borehole to take out the brine.