Building construction progress monitoring method and system
By collecting multiple data indicators and calculating multiple deviation indicators, comprehensively evaluating the progress of the building construction, the problem of single data types and neglecting factors in the existing technology is solved, and more accurate progress evaluation and resource allocation decisions are achieved.
Patent Information
- Application Number
- CN202510031038.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2025-01-09
- Publication Date
- 2025-02-11
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
The existing construction progress monitoring method has a single data type, lacks diversity, and ignores the connection between various factors, resulting in the inability to reflect the real progress deviation, thereby reducing the effectiveness of resource allocation decisions.
By collecting multiple data indicators, such as time data, cost data, workload data, resource data, construction quality data, safety data, design data, complaint data and information transmission data, multiple deviation indicators, such as progress and engineering volume balance, Deviation, comprehensive deviation of quality and resources, safety and design deviation and comprehensive operation deviation, comprehensive evaluation of construction progress deviation, and determine the progress adjustment method based on the deviation level.
It has achieved multi-dimensional evaluation of the construction progress of the building, improved the accuracy of the assessment, accurately identified potential problems in the project, rationally allocated resources, and improved the effectiveness of resource allocation decisions.
Smart Images

Figure CN119417200A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of data analysis, and in particular to a method and system for monitoring the progress of a building construction. Background Art
[0002] In the field of construction, by monitoring the construction progress, it is possible to accurately manage material and equipment resources, rationally allocate labor resources, and improve project management efficiency and safety.
[0003] The traditional construction progress monitoring method mainly collects the actual completion time data and the actual completed project volume data of the construction tasks and compares them with the planned completion time and the planned completed project volume. Based on the comparison results, the deviation between the actual progress and the planned progress is judged, and the corresponding progress adjustment strategy is formulated according to the size of the progress deviation.
[0004] The existing technology still has the following shortcomings: the data type for evaluating construction progress deviation is single and lacks diversity, and the relationship between various factors is ignored, resulting in the inability to reflect the actual progress deviation, thereby reducing the effectiveness of resource allocation decisions. Summary of the invention
[0005] 1. Technical issues to be resolved In view of the shortcomings of the prior art, the present invention provides a construction progress monitoring method, which can monitor the progress of a building according to the progress and engineering quantity balance deviation index. , quality and resource comprehensive deviation indicators , safety and design deviation indicators and comprehensive operational deviation indicators Calculating Schedule Variance Indicator , based on the deviation level threshold set and progress deviation indicator Judging the construction progress deviation level and determining the construction progress adjustment method based on the construction progress deviation level solves the problem that the data type for evaluating construction progress deviation is single and lacks diversity, while ignoring the relationship between various factors, resulting in the inability to reflect the actual progress deviation situation, thereby reducing the effectiveness of resource allocation decisions.
[0006] (II) Technical solution To achieve the above objectives, the present invention is implemented through the following technical solutions: A construction progress monitoring method, comprising the following steps: Collect time data, cost data, workload data, resource data, construction quality data, safety data, design data, complaint data and information transmission data; Calculate time deviation indicators based on time data and cost data , calculate the engineering quantity deviation index based on workload data and cost data , according to the time deviation indicator and quantity deviation index Calculate progress and engineering quantity balance deviation indicators ; Calculate the comprehensive deviation index of quality and resources based on resource data, construction quality data and workload data ; Calculate safety and design deviation indicators based on safety data, design data and time data ; Calculate the cost-complaint impact index based on cost data, complaint data and time data , calculate supply chain stability indicators based on resource data , calculate the information communication efficiency index based on information transmission data ; Based on the cost-complaint impact indicator , Supply Chain Stability Indicators and information communication efficiency indicators Calculate the comprehensive operational deviation index ; According to the progress and engineering quantity balance deviation index , quality and resource comprehensive deviation indicators , safety and design deviation indicators and comprehensive operational deviation indicators Calculating Schedule Variance Indicator ; Preset deviation level threshold set; according to the deviation level threshold set and progress deviation indicator Determine the construction progress deviation level and determine the construction progress adjustment method based on the construction progress deviation level.
[0007] In the preferred embodiment of the above-mentioned construction progress monitoring method: calculating the time deviation index The method is: Time data includes employees’ actual working time Plan working hours with employees ; Cost data including earned value and planned value ; Calculate time deviation indicators based on time data and cost data , the formula based on is: in, For the The actual working time of each employee, It is the serial number corresponding to different employees, and its value is ; is the total number of employees, which must be a positive integer; For the The planned working hours of each employee.
[0008] In the preferred embodiment of the above-mentioned construction progress monitoring method: calculating the progress and engineering quantity balance deviation index The method is: Workload data includes the actual completion of construction tasks and the planned completion of construction tasks ; Cost data also includes the planned unit price of construction tasks ; Plan unit price based on workload data and construction tasks Calculate the engineering quantity deviation index , the formula based on is: in, No. The actual completion amount of each construction task, is the sequence number corresponding to different construction tasks, and its value is ; is the total amount of construction tasks, which is a positive integer; For the The planned unit price of each construction task; No. The planned completion amount of each construction task; According to the time deviation indicator and quantity deviation index Calculate progress and engineering quantity balance deviation indicators , the formula based on is: .
[0009] In the preferred embodiment of the above-mentioned construction progress monitoring method: calculating the comprehensive deviation index of quality and resources The method is: Resource data includes actual material supply , Planned material supply , Actual equipment utilization and planned equipment utilization ; Construction quality data including rework ; Workload data also includes total engineering work ; Based on resource data, construction quality data and total project volume Calculation quality and resource comprehensive deviation index , the formula based on is: .
[0010] In the preferred embodiment of the above-mentioned construction progress monitoring method: calculating the safety and design deviation index The method is: Safety data includes the number of days of downtime caused by safety incidents and the number of safety hazards ; Design data including design task change delay time score and the number of design task changes ; Time data also includes the total number of days planned for construction ; Based on safety data, design data and planned total construction days Calculate safety and design deviation indicators , the formula based on is: in, is the weight coefficient of potential safety hazard deviation, ranging from 0.3 to 0.7; is the weight coefficient of the design change deviation, ranging from 0.3 to 0.7; and .
[0011] In the preferred embodiment of the above-mentioned construction progress monitoring method: calculating the cost-complaint impact index and information communication efficiency indicators The method is: Cost data also includes actual costs and planned costs ; Complaints data including complaint handling difficulty rating ; According to actual cost , Planned cost , complaint data and total planned construction days Calculate Cost-Complaint Impact Indicator , the formula based on is: in, For the The difficulty rating of complaints is the serial number corresponding to different complaints, and its value is ; is the total number of complaints, which is a positive integer; Resource data also includes the number of times suppliers deliver on time , Planned delivery times and the number of qualified materials ; According to the actual material supply , Suppliers deliver on time , Planned delivery times and the number of qualified materials Calculating the Supply Chain Stability Index , the formula based on is: Information delivery data includes the number of people who actually received the information , the number of people who are expected to receive the information , Actual information feedback cycle and plan information feedback cycle ; Calculate information communication efficiency index based on information transmission data , the formula based on is: in, The actual received The number of people who have received the information, It is the serial number corresponding to different information, and its value is ; is the total amount of information, which is a positive integer; Is the plan to receive the The number of people who received the information; It is The actual information feedback cycle of the information; It is Planned information feedback cycle of information; is the weight coefficient of the information dissemination breadth index, ranging from 0.4 to 0.6; is the weight coefficient of the information dissemination efficiency index, ranging from 0.4 to 0.6; and .
[0012] In the preferred embodiment of the above-mentioned construction progress monitoring method: calculating the comprehensive operation deviation index The method is: Based on cost-complaint impact indicator , Supply Chain Stability Indicators and information communication efficiency indicators Calculate the comprehensive operational deviation index , the formula based on is: .
[0013] In the preferred embodiment of the above-mentioned construction progress monitoring method: calculating the progress deviation index The method is: According to the progress and engineering quantity balance deviation index , quality and resource comprehensive deviation indicators , safety and design deviation indicators and comprehensive operational deviation indicators Calculating Schedule Variance Indicator , the formula based on is: in, The deviation index of progress and engineering quantity balance The weight coefficient is between 0.2 and 0.4; Comprehensive deviation index of quality and resources The weight coefficient is 0.2 to 0.3; Safety and design deviation indicators The weight coefficient is 0.2 to 0.3; Comprehensive operational deviation index The weight coefficient is 0.3 to 0.4; and .
[0014] In the preferred embodiment of the above-mentioned construction progress monitoring method, the method for determining the construction progress deviation level is: Deviation level threshold set includes high deviation level threshold and low deviation level threshold ; Deviation indicators based on deviation level thresholds and progress The standards for judging the construction progress deviation level are: .
[0015] The present invention also discloses a construction progress monitoring method and system, including: Data collection module, which can collect time data, cost data, workload data, resource data, construction quality data, safety data, design data, complaint data and information transmission data; Indicator calculation module, which can calculate time deviation indicators based on time data and cost data , calculate the engineering quantity deviation index based on workload data and cost data , according to the time deviation indicator and quantity deviation index Calculate progress and engineering quantity balance deviation indicators ; Calculate the comprehensive deviation index of quality and resources based on resource data, construction quality data and workload data ; Calculate safety and design deviation indicators based on safety data, design data and time data ; Calculate the cost-complaint impact index based on cost data, complaint data and time data , calculate supply chain stability indicators based on resource data , calculate the information communication efficiency index based on information transmission data , based on the cost-complaint impact indicator , Supply Chain Stability Indicators and information communication efficiency indicators Calculate the comprehensive operational deviation index ; According to the progress and engineering quantity balance deviation index , quality and resource comprehensive deviation indicators , safety and design deviation indicators and comprehensive operational deviation indicators Calculating Schedule Variance Indicator ; The judgment module is used to preset a set of deviation level thresholds; according to the deviation level threshold set and the progress deviation index Determine the construction progress deviation level and determine the construction progress adjustment method based on the construction progress deviation level.
[0016] (III) Beneficial effects The present invention provides a construction progress monitoring method and system, which have the following beneficial effects: (1) By collecting time data, cost data, workload data, resource data, construction quality data, safety data, design data, complaint data and information transmission data, the construction progress can be evaluated from multiple dimensions, which is conducive to improving the accuracy of the evaluation.
[0017] (2) Calculate the progress and engineering quantity balance deviation index based on time data, cost data and workload data , can accurately grasp the matching degree between project progress and engineering quantity, help identify potential problems that may arise in engineering quantity, and calculate the comprehensive deviation index of quality and resources based on resource data, construction quality data and workload data , can measure project quality from multiple perspectives, understand whether resources are used effectively, and calculate safety and design deviation indicators based on safety data, design data and time data , which helps to identify potential risks in safety and design in advance, and calculates comprehensive operational deviation indicators based on cost data, complaint data, time data, resource data and information transmission data , can understand the overall benefits of the project, so as to make dynamic adjustments, according to the progress and engineering quantity balance deviation indicators , quality and resource comprehensive deviation indicators , safety and design deviation indicators and comprehensive operational deviation indicators Calculating Schedule Variance Indicator It can evaluate progress deviation from multiple dimensions, solving the problem that the data type for evaluating construction progress deviation is single and lacks diversity, while ignoring the relationship between various factors, resulting in failure to reflect the actual progress deviation, thereby reducing the effectiveness of resource allocation decisions.
[0018] (3) Based on the deviation level threshold set and progress deviation indicator Judging the deviation level of construction progress is conducive to accurately determining the degree of deviation. Determining the construction progress adjustment method based on the deviation level of construction progress will help to reasonably allocate resources and make the adjustment measures more in line with the actual situation. BRIEF DESCRIPTION OF THE DRAWINGS
[0019] Figure 1 A schematic diagram of the working steps of a construction progress monitoring method of the present invention; Figure 2 The invention provides a method for calculating the comprehensive operation deviation index in a construction progress monitoring method. Schematic diagram of the steps; Figure 3 The present invention is a structural schematic diagram of a construction progress monitoring system. DETAILED DESCRIPTION
[0020] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0021] See also Figure 1-2 The present invention provides a construction progress monitoring method, comprising the following steps: Step 1: Collect time data, cost data, workload data, resource data, construction quality data, safety data, design data, complaint data and information transmission data.
[0022] Combined with the content of step 1: By collecting time data, cost data, workload data, resource data, construction quality data, safety data, design data, complaint data and information transmission data, the progress of construction can be evaluated from multiple dimensions, which is conducive to improving the accuracy of the evaluation.
[0023] Step 2: Calculate the time deviation index based on time data and cost data , calculate the engineering quantity deviation index based on workload data and cost data , according to the time deviation indicator and quantity deviation index Calculate progress and engineering quantity balance deviation indicators ; Calculate the comprehensive deviation index of quality and resources based on resource data, construction quality data and workload data ; Calculate safety and design deviation indicators based on safety data, design data and time data ; Calculate the cost-complaint impact index based on cost data, complaint data and time data , calculate supply chain stability indicators based on resource data , calculate the information communication efficiency index based on information transmission data ; Based on the cost-complaint impact indicator , Supply Chain Stability Indicators and information communication efficiency indicators Calculate the comprehensive operational deviation index ; According to the progress and engineering quantity balance deviation index , quality and resource comprehensive deviation indicators , safety and design deviation indicators and comprehensive operational deviation indicators Calculating Schedule Variance Indicator .
[0024] Step 2 includes the following steps: Step 201: Calculate the time deviation index The method is: Time data includes employees’ actual working time Plan working hours with employees .
[0025] It should be noted that the actual working hours of employees Refers to the actual working time of employees in the construction project. The method of obtaining it is: querying the employees' working time through the attendance system, calculating the difference between the off-duty time and the working time as the daily working time, and calculating the sum of the daily working time of all employees up to the current time as the actual working time of the employees. Employees' planned working hours It is the predetermined working hours of employees. The method of obtaining it is: by checking the labor contract to determine the daily working hours and the number of working days of the employee, and then multiplying the daily working hours of the employee by the number of working days to determine the employee's planned working time. .
[0026] Cost data including earned value and planned value .
[0027] It should be noted that earned value It refers to the budget value of the work completed during the project implementation. The method of obtaining it is: identify the milestone events in the project, determine whether each milestone event has been completed, if completed, include the budget value of the milestone event in the earned value, if not completed, do not include it, add the budget value of the completed milestone events to get the earned value Milestone events refer to key nodes in the project, marking the completion of an important stage or the delivery of important results. They are determined by consulting the project construction contract, and the budget value corresponding to each milestone event is determined by consulting the bidding documents. Planned value It refers to the budget value of the work that should be completed at the current time point according to the planned schedule of the project. It is obtained by breaking down the project into multiple tasks or activities with clear start and end times, assigning a budget cost to each task, and then determining the tasks that should be completed before the current time and the sum of their budget costs according to the schedule, which is the planned value. .
[0028] Calculate time deviation indicators based on time data and cost data , the formula based on is: in, For the The actual working time of each employee, It is the serial number corresponding to different employees, and its value is ; is the total number of employees, which must be a positive integer; For the The planned working hours of each employee.
[0029] It should be noted that this formula takes into account the degree of deviation between the actual working time and the planned working time of employees and the earned value. and planned value The degree of deviation between them is used to obtain the time deviation index .
[0030] Step 202: Calculate the progress and engineering quantity balance deviation index The method is: Workload data includes the actual completion of construction tasks and the planned completion of construction tasks .
[0031] It should be noted that the actual completion of the construction task Refers to the amount of construction work that has actually been completed during the construction process. The method of obtaining it is as follows: the construction team will submit progress reports regularly, which record the completion status of each construction task in detail. By querying the progress report, the actual completion amount of the construction task can be determined Different construction tasks correspond to different units. For example, when the construction task is to lay pipes, the unit is meter; when the construction task is to install steel bars, the unit is ton; when the construction task is to pour concrete, the unit is cubic meter. It refers to the amount of construction work that should be completed according to the project's construction schedule. The method of obtaining it is as follows: according to the overall project schedule, the construction tasks are decomposed into specific and actionable work packages according to the work breakdown structure, and the planned start time, planned completion time and expected workload for each work package are determined. The workload of all work packages that should be completed for each construction task before the current time point is summarized as the planned completion amount of the construction task. .
[0032] Cost data also includes the planned unit price of construction tasks .
[0033] It should be noted that the planned unit price of the construction task It refers to the cost required to complete a unit construction task, which is predetermined during the planning stage of a construction project. It is determined by consulting the price clauses in the construction contract. The unit is determined according to the construction task. For example, when the construction task is to lay the length of the pipeline, the unit is yuan / meter; when the construction task is to install steel bars, the unit is yuan / ton; when the construction task is to pour concrete, the unit is yuan / cubic meter.
[0034] Plan unit price based on workload data and construction tasks Calculate the engineering quantity deviation index , the formula based on is: in, No. The actual completion amount of each construction task, is the sequence number corresponding to different construction tasks, and its value is ; is the total amount of construction tasks, which is a positive integer; For the The planned unit price of each construction task; No. The planned completion amount of each construction task.
[0035] It should be noted that this formula calculates the deviation between the value of the actual completed workload and the value of the planned completed workload to obtain the engineering quantity deviation index. , engineering quantity deviation index The higher it is, the greater the deviation between the completed workload and the planned workload.
[0036] According to the time deviation indicator and quantity deviation index Calculate progress and engineering quantity balance deviation indicators , the formula based on is: It should be noted that this formula calculates the time deviation index and quantity deviation index The sum of the squares gives the progress and engineering quantity balance deviation index , time deviation indicator and quantity deviation index The higher the value, the greater the deviation from the planned construction progress. The higher.
[0037] Step 203: Calculate the quality and resource comprehensive deviation index The method is: Resource data includes actual material supply , Planned material supply , Actual equipment utilization and planned equipment utilization .
[0038] It should be noted that the actual material supply It refers to the amount of materials that are actually delivered to the construction site and can be used for construction during the construction project, including cement, steel, sand, gravel, bricks, etc. The method of obtaining it is as follows: there are special material management personnel at the construction site who are responsible for recording the arrival of materials. When the materials arrive at the construction site, the material management personnel will record the name, quantity, supplier, arrival date and other information of the materials, and summarize the number of incoming materials as the actual material supply. Planned material supply Refers to the quantity of materials that need to be supplied to the construction site, which is predetermined based on the project's construction schedule and engineering volume. In the material demand plan, the construction company will list the quantity of materials required by stage and type based on the overall design and construction arrangement of the project. By consulting the material demand plan, the total quantity of materials required at the current stage is summarized as the planned material supply. . Actual equipment utilization It refers to the ratio of the actual use time of construction equipment to the available time of the equipment during the construction project. It reflects the actual use efficiency of the construction equipment in the project. The method of obtaining it is: by checking the timer, operation recorder and other operation record systems on the equipment, obtaining the actual use time of the equipment, calculating the ratio of the actual use time of the equipment to the total time of the equipment on the construction site, and taking it as the actual equipment utilization rate. . Planned equipment utilization It refers to the ratio of the estimated use time of construction equipment to the available time of the equipment, which is determined in advance according to the construction schedule and equipment use arrangement of the project. It is an important indicator of project equipment resource planning. The method of obtaining it is as follows: the construction company will prepare a detailed equipment use plan in the early stage of the project, which clearly stipulates the use arrangement of each equipment. The estimated use time and available time of the equipment are obtained by querying the equipment use plan, and the ratio of the estimated use time to the available time is calculated as the planned equipment utilization rate. .
[0039] Construction quality data including rework .
[0040] It should be noted that the amount of rework It refers to the amount of work that needs to be dismantled and reconstructed due to quality failure, design changes, construction errors, etc. during the construction process. The method of obtaining it is as follows: when the quality management personnel or supervisors find that rework is required due to quality problems, they will issue a rework notice, which will describe in detail the rework area, rework reasons and estimated rework amount. The rework amount is obtained by summarizing the estimated rework amount recorded in the rework notice. The unit of engineering quantity is determined according to the type of construction project. For example, when the construction project is a linear project such as road construction, the unit is meter or kilometer. When the construction project is a three-dimensional solid volume project for earthwork, concrete engineering, etc., the unit is cubic meter.
[0041] Workload data also includes total engineering work .
[0042] It should be noted that the total project volume Refers to the quantitative measurement of all construction work involved in a construction project from the beginning to the end of the project. The method of obtaining it is: importing the construction drawings into existing engineering software such as Glodon Engineering Cost Software, and the software automatically calculates the total engineering quantity according to the built-in calculation rules .
[0043] Based on resource data, construction quality data and total project volume Calculation quality and resource comprehensive deviation index , the formula based on is: It should be noted that this formula takes into account the material supply deviation and equipment utilization deviation, and combines the proportion of rework volume to the total volume to derive the comprehensive deviation index of quality and resources. . Quality and resource comprehensive deviation index The larger the value, the greater the comprehensive deviation from the plan in terms of material supply, equipment utilization and construction quality. The smaller the value, the closer the actual situation is to the plan.
[0044] Step 204: Calculate safety and design deviation indicators The method is: Safety data includes the number of days of downtime caused by safety incidents and the number of safety hazards .
[0045] It should be noted that the number of days of downtime caused by safety accidents It refers to the number of days that the construction site has to stop normal construction activities in order to investigate, handle, rectify and ensure the safety of subsequent construction due to a safety accident during the construction process. It reflects the impact of the safety accident on the construction progress. The method of obtaining it is as follows: When a safety accident occurs, the construction company must submit an accident report to the relevant department in accordance with relevant regulations. The accident report usually records the time, cause, and handling process of the accident, including the time interval from the occurrence of the accident to the approval of the relevant department to resume construction, that is, the number of days of suspension of work. The number of days of suspension of work in all accident reports is summarized as the number of days of suspension of work caused by the safety accident. . Number of safety hazards It refers to the number of potential risk factors that may lead to safety accidents at the construction site. The number of potential risk factors is obtained as follows: construction companies will conduct safety inspections regularly, and inspectors will record the safety hazards found during the inspection process. These records include information such as the type, number, location, and severity of the hazards. The inspection record with the shortest interval between the inspection date and the current date is checked, and the number of hazards in the inspection record is used as the number of safety hazards. .
[0046] Design data including design task change delay time score and the number of design task changes .
[0047] It should be noted that the design task change delay time score It is a quantitative evaluation of the delay caused by the change of design tasks. The method of obtaining it is as follows: check the design task completion time agreed in the project design contract. When a design change occurs, determine the re-determined design completion time after the change, and calculate the difference between the re-determined design completion time and the agreed design task completion time. When the difference is less than 2 days, the delay score is 1 point, when the difference is between 3 and 5 days, the delay score is 3 points, and when the difference is 6 days or more, the delay score is 5 points. The delay scores of all design changes are counted and their average value is calculated as the design task change delay time score. . Design task change number score It is a quantitative assessment of the frequency of changes in design tasks during the project process. The method of obtaining it is: by querying the design change notice, change application letter, change meeting minutes, etc., to determine the number of design changes. When the number of design changes is less than 3 times, the number of design task changes is scored. 1 point. When the number of design changes is between 3 and 6, the number of design task changes is scored as 3 points. When the number of changes exceeds 6, the number of design task changes is scored is 5 points.
[0048] Time data also includes the total number of days planned for construction .
[0049] It should be noted that the total number of days planned for construction It refers to the total number of days required from the start to the end of construction, which is planned and determined in advance before the construction of a construction project begins, based on factors such as the project's scale, complexity, construction technology, and resource allocation. It is determined by referring to the project construction period specified in the construction contract.
[0050] Based on safety data, design data and planned total construction days Calculate safety and design deviation indicators , the formula based on is: in, is the weight coefficient of potential safety hazard deviation, ranging from 0.3 to 0.7. The degree of impact is determined. is the weight coefficient of design change deviation, ranging from 0.3 to 0.7, and is calculated based on the impact of design change deviation on safety and design deviation indicators. The degree of impact is determined, and .
[0051] It should be noted that the operating principle of this formula is: Used to measure the impact of safety accidents and hidden dangers on project progress. It is used to measure the impact of design changes on project progress. The formula comprehensively considers the impact of safety hazard deviation and design change deviation through a weighted formula to obtain the safety and design deviation index. .
[0052] Step 205: Calculate cost-complaint impact index and information communication efficiency indicators The method is: Cost data also includes actual costs and planned costs .
[0053] It should be noted that the actual cost It refers to the total amount of all expenses actually incurred to complete the construction task during the construction project. The acquisition method is: obtain labor cost data by checking financial documents such as payroll, bonus payment records, welfare expenditure records, etc.; obtain material cost data by checking purchase invoices, transportation documents, material storage and outbound records, etc.; obtain machinery use cost data by checking financial documents such as equipment rental contracts, equipment depreciation calculation tables, fuel purchase invoices and maintenance records, etc., and input the above cost data into the cost accounting software system to obtain the actual cost. . Planned cost It refers to the cost standard required to complete the project, which is estimated and formulated in advance based on the project's construction drawings, construction organization design, resource allocation plan, market price information and other materials before the start of the construction project. The method of obtaining it is as follows: first, a bill of quantities is prepared based on the construction drawings and engineering quantity calculation rules, listing in detail the various sub-items and their quantities of the project, and then the comprehensive unit price of each sub-item is determined based on market price information, internal enterprise quotas, etc. Finally, the quantities of each sub-item in the bill of quantities are multiplied by the corresponding comprehensive unit price, and the planned cost is obtained after summarizing. .
[0054] Complaints data including complaint handling difficulty rating .
[0055] It should be noted that the complaint handling difficulty score It is a quantitative assessment of the complexity of handling various types of complaints in construction projects. The determination method is: when it takes 1 to 3 days to resolve a complaint, the complaint handling difficulty score 1 point, when it takes 4 to 10 days to resolve the complaint, the complaint handling difficulty score 3 points, when it takes 11 days or more to resolve a complaint, the complaint handling difficulty score is is 5 points.
[0056] According to actual cost , Planned cost , complaint data and total planned construction days Calculate Cost-Complaint Impact Indicator , the formula based on is: in, For the The difficulty rating of complaints is the serial number corresponding to different complaints, and its value is ; is the total number of complaints, which is a positive integer.
[0057] It should be noted that the operating principle of this formula is: It is used to measure the degree of deviation between actual cost and planned cost. It is used to measure the impact of handling complaints on the construction progress. By comprehensively considering the degree of cost deviation and the difficulty of complaint handling, the cost-complaint impact index is obtained. , Cost-Complaint Impact Indicator The higher it is, the greater the deviation between the actual progress and the planned progress.
[0058] Resource data also includes the number of times suppliers deliver on time , Planned delivery times and the number of qualified materials .
[0059] It should be noted that the supplier's on-time delivery frequency It refers to the actual number of times the supplier delivers the goods to the designated location according to the time agreed in the contract. The method of obtaining it is: by checking the delivery records of the purchasing department or warehouse management department, obtain the actual delivery time of each time, compare the actual delivery time with the delivery time specified in the purchase contract, and count the number of times the actual delivery time is earlier than or equal to the delivery time specified in the purchase contract as the number of on-time delivery by the supplier. . Planned delivery times Refers to the number of times the supplier should deliver according to the project's construction schedule and material demand plan, obtained by reviewing procurement activities. It refers to the number of materials delivered by the supplier that meet the quality standards after inspection. The method of obtaining it is as follows: After the materials are inspected and accepted, an acceptance report will be formed. The report will indicate the name, quantity, inspection results, etc. of the materials. The number of qualified materials in the acceptance report will be summarized as the number of qualified materials. .
[0060] According to the actual material supply , Suppliers deliver on time , Planned delivery times and the number of qualified materials Calculating the Supply Chain Stability Index , the formula based on is: It should be noted that this formula obtains the supply chain stability index by comprehensively considering the proportion of on-time deliveries and the proportion of qualified materials. , Supply Chain Stability Index The higher it is, the more adequate the supply of materials is at the construction site and the higher the possibility of completing the construction plan on time.
[0061] Information delivery data includes the number of people who actually received the information , the number of people who are expected to receive the information , Actual information feedback cycle and plan information feedback cycle .
[0062] It should be noted that the number of people who actually received the information Refers to the total number of people who actually receive construction instructions and other information during the construction process of a construction project. The method of obtaining it is: for instructions or information sent via instant messaging software such as email, the number of people who actually received the information is determined by checking the list of people who have read the message. For information transmission activities such as on-site construction meetings or technical briefings, the number of people who actually receive the information is determined by the on-site sign-in sheet. The number of people who are expected to receive the information Refers to the number of people who should receive construction instructions and other information in advance according to the project's information management plan and communication plan. The method of obtaining it is as follows: When formulating the information management plan, the project management team will prepare an information distribution list, which clearly lists the people or departments who will receive various types of information. By counting the people on these lists, the number of people who are planned to receive information is obtained. . Actual information feedback cycle It refers to the time interval from when the information sender sends the information to when the information receiver receives the feedback. It reflects the timeliness and efficiency of information communication in the project. The acquisition method is: record the time when the information is sent and the time when the feedback is received, calculate the time difference between the two, and use it as the actual information feedback cycle . Plan information feedback cycle It refers to the expected time interval for receiving feedback after the pre-set information is sent out according to the project's communication plan and workflow. It is an important criterion for measuring whether information communication is carried out as planned. It is obtained by querying the project communication plan. The project communication plan clearly stipulates the feedback time requirements for various types of information.
[0063] Calculate information communication efficiency index based on information transmission data , the formula based on is: in, The actual received The number of people who have received the information, It is the serial number corresponding to different information, and its value is ; is the total amount of information, which is a positive integer; Is the plan to receive the The number of people who received the information; It is The actual information feedback cycle of the information; It is Planned information feedback cycle of information; is the weight coefficient of the information dissemination breadth index, ranging from 0.4 to 0.6. The importance of determining is the weight coefficient of the information dissemination efficiency index, with a value of 0.4 to 0.6. The importance of .
[0064] It should be noted that the operating principle of this formula is: It is used to measure the breadth of information dissemination. Used to measure the efficiency of information dissemination, this formula comprehensively considers the breadth of information dissemination and the efficiency of information dissemination to obtain the information communication efficiency index , Information communication efficiency index The higher the value, the faster and more accurately the construction instructions can be conveyed to the construction personnel, which is more conducive to the timely completion of the construction plan. is the base of the natural logarithm in the exponential function.
[0065] Step 206: Calculate the comprehensive operational deviation index The method is: Based on cost-complaint impact indicator , Supply Chain Stability Indicators and information communication efficiency indicators Calculate the comprehensive operational deviation index , the formula based on is: .
[0066] It should be noted that this formula takes into account the cost-complaint impact index , Supply Chain Stability Indicators and information communication efficiency indicators Get comprehensive operational deviation indicators , Cost-Complaint Impact Indicator The higher the supply chain stability index and information communication efficiency indicators The lower it is, the less conducive it is to improving construction progress. Comprehensive operation deviation index The higher.
[0067] Step 207: Calculate the progress deviation index The method is: According to the progress and engineering quantity balance deviation index , quality and resource comprehensive deviation indicators , safety and design deviation indicators and comprehensive operational deviation indicators Calculating Schedule Variance Indicator , the formula based on is: in, The deviation index of progress and engineering quantity balance The weight coefficient is 0.2 to 0.4, based on the progress and engineering quantity balance deviation index. Progress Deviation Indicator The importance of determining Comprehensive deviation index of quality and resources The weight coefficient is 0.2 to 0.3, based on the comprehensive deviation index of quality and resources. Progress Deviation Indicator The importance of determining Safety and design deviation indicators The weight coefficient is 0.2 to 0.3, based on the safety and design deviation indicators. Progress Deviation Indicator The importance of determining Comprehensive operational deviation index The weight coefficient is 0.3 to 0.4, based on the comprehensive operation deviation index. Progress Deviation Indicator The importance of .
[0068] It should be noted that this formula is averaged after weighting, taking into account the progress and engineering quantity balance deviation indicators. , quality and resource comprehensive deviation indicators , safety and design deviation indicators and comprehensive operational deviation indicators Impact on construction progress, obtain progress deviation index .
[0069] Combined with the contents of step 201 to step 207: Calculate progress and engineering quantity balance deviation indicators based on time data, cost data and workload data , can accurately grasp the matching degree between project progress and engineering quantity, help identify potential problems that may arise in engineering quantity, and calculate the comprehensive deviation index of quality and resources based on resource data, construction quality data and workload data , can measure project quality from multiple perspectives, understand whether resources are used effectively, and calculate safety and design deviation indicators based on safety data, design data and time data , which helps to identify potential risks in safety and design in advance, and calculates comprehensive operational deviation indicators based on cost data, complaint data, time data, resource data and information transmission data , can understand the overall benefits of the project, so as to make dynamic adjustments, according to the progress and engineering quantity balance deviation indicators , quality and resource comprehensive deviation indicators , safety and design deviation indicators and comprehensive operational deviation indicators Calculating Schedule Variance Indicator It can evaluate progress deviation from multiple dimensions, solving the problem that the data type for evaluating construction progress deviation is single and lacks diversity, while ignoring the relationship between various factors, resulting in failure to reflect the actual progress deviation, thereby reducing the effectiveness of resource allocation decisions.
[0070] Step 3: Preset the deviation level threshold set; according to the deviation level threshold set and progress deviation indicator Determine the construction progress deviation level and determine the construction progress adjustment method based on the construction progress deviation level.
[0071] Step 3 includes the following steps: Step 301: The method for determining the construction progress deviation level is: Deviation level threshold set includes high deviation level threshold and low deviation level threshold .
[0072] It should be noted that the high deviation level threshold and low deviation level threshold The method for determining the high deviation level is to collect historical data from the construction projects completed by the enterprise in the past and calculate the progress deviation index according to the above method, screen out the higher 20% progress deviation index and calculate its average value as the high deviation level threshold The reference value is used to screen out the lower 20% progress deviation indicators and calculate their average value as the low deviation level threshold reference value.
[0073] Deviation indicators based on deviation level thresholds and progress The standards for judging the construction progress deviation level are: When the construction progress deviation level is a high deviation level, the adjustment method is: hold an emergency meeting to clarify the specific reasons for the deviation and adjust the technical plan, strengthen communication and collaboration between construction teams, and promptly resolve problems arising in cross-operations through daily short meetings or on-site exchanges. According to the actual progress, dynamically adjust the short-term construction plan. For example, if it is found that the progress of some construction processes is lagging behind in a certain week, promptly adjust the construction plan for next week, increase resource input or optimize the construction sequence.
[0074] When the construction progress deviation level is a medium deviation level, the adjustment method is: analyze the construction processes that are lagging behind in progress, and rationally deploy labor from construction areas that are ahead of schedule or relatively loose to lagging areas. At the same time, project management personnel must strengthen the tracking and management of the construction progress, and promptly discover and resolve problems that arise during the construction process.
[0075] When the construction progress deviation level is a low deviation level, the adjustment method is: strengthen the daily maintenance of construction equipment, ensure that the equipment is in good operating condition, improve the utilization rate of equipment, make appropriate adjustments to personnel tasks based on the skills and work efficiency of construction personnel, and assign personnel with high work efficiency to progress-critical activities.
[0076] Combined with the content of step 301: Deviation indicators based on deviation level thresholds and progress Judging the deviation level of construction progress is conducive to accurately determining the degree of deviation. Determining the construction progress adjustment method based on the deviation level of construction progress will help to reasonably allocate resources and make the adjustment measures more in line with the actual situation.
[0077] See also Figure 3 On the other hand, the present invention also discloses a construction progress monitoring system, which is used to implement the above-mentioned construction progress monitoring method, including: Data collection module, which can collect time data, cost data, workload data, resource data, construction quality data, safety data, design data, complaint data and information transmission data; Indicator calculation module, which can calculate time deviation indicators based on time data and cost data , calculate the engineering quantity deviation index based on workload data and cost data , according to the time deviation indicator and quantity deviation index Calculate progress and engineering quantity balance deviation indicators ; Calculate the comprehensive deviation index of quality and resources based on resource data, construction quality data and workload data ; Calculate safety and design deviation indicators based on safety data, design data and time data ; Calculate the cost-complaint impact index based on cost data, complaint data and time data , calculate supply chain stability indicators based on resource data , calculate the information communication efficiency index based on information transmission data , based on the cost-complaint impact indicator , Supply Chain Stability Indicators and information communication efficiency indicators Calculate the comprehensive operational deviation index ; According to the progress and engineering quantity balance deviation index , quality and resource comprehensive deviation indicators , safety and design deviation indicators and comprehensive operational deviation indicators Calculating Schedule Variance Indicator ; The judgment module is used to preset a set of deviation level thresholds; according to the deviation level threshold set and the progress deviation index Determine the construction progress deviation level and determine the construction progress adjustment method based on the construction progress deviation level.
[0078] The above embodiments may be implemented in whole or in part by software, hardware, firmware or any other combination thereof. When implemented using software, the above embodiments may be implemented in whole or in part in the form of a computer program product. A person of ordinary skill in the art may appreciate that the units and algorithm steps of each example described in conjunction with the embodiments disclosed herein may be implemented in electronic hardware or in combination with computer software and electronic hardware. Whether these functions are performed in hardware or software depends on the specific application and design constraints of the technical solution.
[0079] The units described as separate components may or may not be physically separated, and the components shown as units may or may not be physical units, that is, they may be located in one place or distributed on multiple network units. Some or all of the units may be selected according to actual needs to achieve the purpose of the solution of this embodiment.
[0080] The above description is only a specific implementation manner of the present application, but the protection scope of the present application is not limited thereto. Any technician familiar with the technical field can easily think of changes or substitutions within the technical scope disclosed in the present application, which should be included in the protection scope of the present application.
Claims
1. A construction progress monitoring method, characterized in that: The following steps are involved: Collect time data, cost data, workload data, resource data, construction quality data, safety data, design data, complaint data and information transmission data; Calculate time deviation indicators based on time data and cost data , calculate the engineering quantity deviation index based on workload data and cost data , according to the time deviation indicator and quantity deviation index Calculate progress and engineering quantity balance deviation indicators ; Calculate the comprehensive deviation index of quality and resources based on resource data, construction quality data and workload data ; Calculate safety and design deviation indicators based on safety data, design data and time data ; Calculate the cost-complaint impact index based on cost data, complaint data and time data , calculate supply chain stability indicators based on resource data , calculate the information communication efficiency index based on information transmission data ; Based on cost-complaint impact indicator , Supply Chain Stability Indicators and information communication efficiency indicators Calculate the comprehensive operational deviation index ; According to the progress and engineering quantity balance deviation index , quality and resource comprehensive deviation indicators , safety and design deviation indicators and comprehensive operational deviation indicators Calculating Schedule Variance Indicator ; A set of preset deviation level thresholds; Deviation indicators based on deviation level thresholds and progress Determine the construction progress deviation level and determine the construction progress adjustment method based on the construction progress deviation level.
2. A construction progress monitoring method according to claim 1, characterized in that: Calculating the Time Deviation Index The method is: Time data includes employees’ actual working time Plan working hours with employees ; Cost data including earned value and planned value ; Calculate time deviation indicators based on time data and cost data , the formula based on is: in, For the The actual working time of each employee, It is the serial number corresponding to different employees, and its value is ; is the total number of employees, which must be a positive integer; For the The planned working hours of each employee.
3. A construction progress monitoring method according to claim 2, characterized in that: Calculate progress and engineering quantity balance deviation indicators The method is: Workload data includes the actual completion of construction tasks and the planned completion of construction tasks ; Cost data also includes the planned unit price of construction tasks ; Plan unit price based on workload data and construction tasks Calculate the engineering quantity deviation index , the formula based on is: in, No. The actual completion amount of each construction task, is the sequence number corresponding to different construction tasks, and its value is ; is the total amount of construction tasks, which is a positive integer; For the The planned unit price of each construction task; No. The planned completion amount of each construction task; According to the time deviation indicator and quantity deviation index Calculate progress and engineering quantity balance deviation indicators , the formula based on is: 。 4. A construction progress monitoring method according to claim 3, characterized in that: Calculation quality and resource comprehensive deviation index The method is: Resource data includes actual material supply , Planned material supply , Actual equipment utilization and planned equipment utilization ; Construction quality data including rework ; Workload data also includes total engineering work ; Based on resource data, construction quality data and total project volume Calculation quality and resource comprehensive deviation index , the formula based on is: 。 5. A construction progress monitoring method according to claim 4, characterized in that: Calculate safety and design deviation indicators The method is: Safety data includes the number of days of downtime caused by safety incidents and the number of safety hazards ; Design data including design task change delay time scores and the number of design task changes ; Time data also includes the total number of days planned for construction ; Based on safety data, design data and planned total construction days Calculate safety and design deviation indicators , the formula based on is: in, is the weight coefficient of potential safety hazard deviation, ranging from 0.3 to 0.7; is the weight coefficient of the design change deviation, ranging from 0.3 to 0.7; and .
6. A construction progress monitoring method according to claim 5, characterized in that: Calculate Cost-Complaint Impact Indicator and information communication efficiency indicators The method is: Cost data also includes actual costs and planned costs ; Complaints data including complaint handling difficulty rating ; According to actual cost , Planned cost , complaint data and total planned construction days Calculate Cost-Complaint Impact Indicator , the formula based on is: in, For the The difficulty rating of complaints It is the serial number corresponding to different complaints, and its value is ; is the total number of complaints, which is a positive integer; Resource data also includes the number of times suppliers deliver on time , Planned delivery times and the number of qualified materials ; According to the actual material supply , Suppliers deliver on time , Planned delivery times and the number of qualified materials Calculating the Supply Chain Stability Index , the formula based on is: Information delivery data includes the number of people who actually received the information , the number of people who are expected to receive the information , Actual information feedback cycle and plan information feedback cycle ; Calculate information communication efficiency index based on information transmission data , the formula based on is: in, The actual received The number of people who have received the information, It is the serial number corresponding to different information, and its value is ; is the total amount of information, which is a positive integer; Is the plan to receive the The number of people who received the information; It is The actual information feedback cycle of the information; It is Planned information feedback cycle of information; is the weight coefficient of the information dissemination breadth index, ranging from 0.4 to 0.6; is the weight coefficient of the information dissemination efficiency index, ranging from 0.4 to 0.6; and .
7. A construction progress monitoring method according to claim 6, characterized in that: Calculate the comprehensive operational deviation index The method is: Based on cost-complaint impact indicator , Supply Chain Stability Indicators and information communication efficiency indicators Calculate the comprehensive operational deviation index , the formula based on is: 。 8. A construction progress monitoring method according to claim 7, characterized in that: Calculating Schedule Variance Indicator The method is: According to the progress and engineering quantity balance deviation index , quality and resource comprehensive deviation indicators , safety and design deviation indicators and comprehensive operational deviation indicators Calculating Schedule Variance Indicator , the formula based on is: in, The deviation index of progress and engineering quantity balance The weight coefficient is between 0.2 and 0.4; Comprehensive deviation index of quality and resources The weight coefficient is 0.2 to 0.3; Safety and design deviation indicators The weight coefficient is 0.2 to 0.3; Comprehensive operational deviation index The weight coefficient is 0.3 to 0.4; and .
9. A construction progress monitoring method according to claim 8, characterized in that: The method for judging the construction progress deviation level is: Deviation level threshold set includes high deviation level threshold and low deviation level threshold ; Deviation indicators based on deviation level thresholds and progress The standards for judging the construction progress deviation level are: 。 10. A construction progress monitoring system, characterized in that: include: Data collection module, which can collect time data, cost data, workload data, resource data, construction quality data, safety data, design data, complaint data and information transmission data; Indicator calculation module, which can calculate time deviation indicators based on time data and cost data , calculate the engineering quantity deviation index based on workload data and cost data , according to the time deviation indicator and quantity deviation index Calculate progress and engineering quantity balance deviation indicators ; Calculate the comprehensive deviation index of quality and resources based on resource data, construction quality data and workload data ; Calculate safety and design deviation indicators based on safety data, design data and time data ; Calculate the cost-complaint impact index based on cost data, complaint data and time data , calculate supply chain stability indicators based on resource data , calculate the information communication efficiency index based on information transmission data , based on the cost-complaint impact indicator , Supply Chain Stability Indicators and information communication efficiency indicators Calculate the comprehensive operational deviation index ; According to the progress and engineering quantity balance deviation index , quality and resource comprehensive deviation indicators , safety and design deviation indicators and comprehensive operational deviation indicators Calculating Schedule Variance Indicator ; A judgment module, used to preset a set of deviation level thresholds; Deviation indicators based on deviation level thresholds and progress Determine the construction progress deviation level and determine the construction progress adjustment method based on the construction progress deviation level.
Citation Information
Patent Citations
BIM project progress and cost management system based on earned value theory
CN106022587A
Intelligent management method and system for construction progress of power distribution network project
CN118674160A
Method and system for assessing the progress of a project in terms of its schedule
US20110112883A1
Cited By
Engineering supervision intelligent scheduling and collaborative operation system
CN120822747A
Scheduling management system based on pumped storage engineering project multi-source data fusion
CN121882649A