Foundation wall ring beam pouring auxiliary device and construction method
By designing a foundation wall ring beam casting auxiliary device including support frame, pouring port and brake parts, the problems of poor stability of the pouring funnel and concrete outflow are solved, and the stability and efficiency of pouring are improved, and construction personnel are guaranteed. safety.
Patent Information
- Application Number
- CN202411767061.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-12-04
- Publication Date
- 2025-02-18
AI Technical Summary
During the pouring process of foundation wall ring beams in industrial factories, the pouring funnel is poor, resulting in the easy flow of concrete and manual straightening, which poses safety hazards.
Design a foundation wall ring beam casting auxiliary device, including a support frame, a casting port and brake parts. The support frame is mounted on the wall and can be moved along the wall. The pouring port is used to place the pouring funnel, and the brake member is used to resist the wall to position the support frame.
Through this device, the pouring funnel can be placed stably, reducing concrete outflow, improving the stability and efficiency of pouring, and ensuring the safety of construction personnel.
Smart Images

Figure CN119465972A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of building construction, and in particular relates to a foundation wall ring beam casting auxiliary device and a construction method. Background Art
[0002] With the rapid development of industry, the number of new and expanded industrial plant projects is increasing. Due to the use of hoisting and equipment, industrial plants have stricter requirements on the construction quality of foundations and underground parts. The foundation wall usually adopts the structure of independent foundation plus brick wall plus concrete beam. However, the height of the masonry exterior wall is generally more than 1.5 meters. When pouring the concrete ring beam, the construction workers need to stand on the ring beam template to pour, vibrate, and smooth. Due to the high height, it is necessary to add external frames on both sides for protection. During the pouring process, the pouring method of the funnel is often used. Since there is no fixed point for the funnel, the funnel needs to be straightened manually, which has problems such as poor stability and concrete outflow. Summary of the invention
[0003] In order to solve the above technical problems, the present invention provides a foundation wall ring beam casting auxiliary device and construction method, which effectively solves the technical problems of poor stability of the casting ring beam funnel and easy outflow of concrete, and overcomes the shortcomings of the prior art.
[0004] The technical solution adopted by the present invention is: a foundation wall ring beam casting auxiliary device, comprising:
[0005] The support frame is mounted on the wall and can move along the wall;
[0006] A pouring port, arranged at the top of the support frame, for placing a pouring funnel;
[0007] A brake component is arranged on the support frame and is used for abutting against the wall to position the support frame.
[0008] Furthermore, the braking members are symmetrically arranged on both sides of the wall.
[0009] Furthermore, the brake component includes a brake shaft, the brake shaft is rotatably connected to the support frame, and a brake connecting rod is provided on the brake shaft, so that the brake connecting rod can be rotated to abut against the wall.
[0010] Furthermore, a supporting plate is provided at one end of the brake connecting rod close to the wall.
[0011] Furthermore, a pedal is provided at one end of the brake connecting rod away from the wall.
[0012] Furthermore, a supporting connecting rod is provided on the top of the supporting frame, and the pouring port is provided on the supporting connecting rod.
[0013] Furthermore, guardrails are provided on both sides of the support frame.
[0014] Furthermore, a roller is provided at the bottom of the support frame.
[0015] A construction method using the foundation wall ring beam pouring auxiliary device as described above comprises the following steps:
[0016] The support frame is installed on the wall, and the support frame is moved along the wall to a pouring position;
[0017] The brake member is made to abut against the wall to position the support frame;
[0018] The pouring funnel is placed at the pouring port for pouring.
[0019] The advantages and positive effects of the present invention are: due to the adoption of the above-mentioned technical scheme, manual labor is replaced, the pouring funnel can be stably placed, the outflow of concrete is reduced, pouring can be performed on different pouring positions, the normal pouring is ensured, the work efficiency is improved, and the operation safety of the construction personnel is guaranteed. BRIEF DESCRIPTION OF THE DRAWINGS
[0020] Figure 1 It is a stereoscopic diagram of a foundation wall ring beam casting auxiliary device according to an embodiment of the present invention.
[0021] Figure 2 It is a side view of a foundation wall ring beam casting auxiliary device according to an embodiment of the present invention.
[0022] Figure 3 The present invention is a schematic diagram of a use of a foundation wall ring beam casting auxiliary device according to an embodiment of the present invention.
[0023] In the figure:
[0024] 1. Support frame 2. Casting port 3. Support connecting rod
[0025] 4. Pedal 5. Brake connecting rod 6. Brake shaft
[0026] 7. Support plate 8. Roller 9. Guardrail DETAILED DESCRIPTION
[0027] An embodiment of the present invention provides a foundation wall ring beam casting auxiliary device and a construction method. The embodiment of the present invention is described below in conjunction with the accompanying drawings.
[0028] In the description of the embodiments of the present invention, it should be understood that the orientation or positional relationship indicated by the terms "top", "bottom", etc. is based on the orientation or positional relationship shown in the accompanying drawings, and is only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present invention. In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "set" and "connect" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be directly connected, or indirectly connected through an intermediate medium, or it can be a connection between the two elements. For those of ordinary skill in the art, the specific meanings of the above terms in the present invention can be understood by specific circumstances.
[0029] like Figure 1 , Figure 2 and Figure 3 As shown, an auxiliary device for pouring a foundation wall ring beam according to an embodiment of the present invention comprises a support frame 1, a pouring port 2 and a brake. The support frame 1 is mounted on a wall and can move along the wall to pour at different pouring positions. The pouring port 2 is arranged at the top of the support frame 1 and is used to place a pouring funnel, and no manual support is required to prevent the pouring funnel from moving during the pouring process. The brake is arranged on the support frame 1 and is used to support the wall to position the support frame 1 and prevent the support frame 1 from moving during the pouring process. The support frame 1 can be formed by welding a profile. The height of the support frame 1 is set according to the height of the wall, and needs to be higher than the wall to reserve a pouring space. The width of the support frame 1 is set according to the thickness of the wall, and it is necessary to ensure that there is a gap between the frame on both sides of the support frame 1 and the wall to facilitate the movement of the support frame 1. The shape of the pouring port 2 is adapted to the shape of the pouring funnel. In order to ensure the balance and stability of the entire device, preferably, the pouring port 2 is arranged at the top center of the support frame 1.
[0030] Preferably, the brakes are symmetrically arranged on both sides of the wall. In order to better position the support frame 1, the symmetrically arranged brakes respectively support the wall on both sides of the wall, which makes the positioning of the support frame 1 more stable compared to unilateral support.
[0031] Specifically, the brake component includes a brake shaft 6, which is rotatably connected to the support frame 1. A brake link 5 is provided on the brake shaft 6, which can make the brake link 5 rotate and abut against the wall. The brake shaft 6 is horizontally arranged on the support frame 1, and is rotatably connected to the support frame 1 by a bearing. The brake link 5 is fixed on the brake shaft 6 and is arranged perpendicular to the brake shaft 6. When no external force is applied, the brake link 5 hangs freely, with one end located at the upper part of the brake shaft 6 and the other end located at the lower part of the brake shaft 6, and will not affect the movement of the support frame 1. When the construction personnel step on the upper end of the brake link 5, the upper end of the brake link 5 rotates toward the outside of the support frame 1, so that the lower end of the brake link 5 rotates toward the wall and abuts against the wall, thereby positioning the support frame 1.
[0032] Preferably, in order to better abut against the wall and ensure the positioning effect, a supporting plate 7 is provided at the lower end of the brake link 5, that is, the end close to the wall.
[0033] Preferably, in order to facilitate construction workers to step on it, a pedal 4 is provided at the upper end of the brake connecting rod 5, that is, the end away from the wall.
[0034] Specifically, in order to facilitate the installation of the pouring port 2 , a supporting connecting rod 3 is provided on the top of the supporting frame 1 , and the pouring port 2 is arranged on the supporting connecting rod 3 .
[0035] Specifically, in order to reduce potential safety hazards, protective railings 9 are provided on both sides of the support frame 1 .
[0036] Specifically, in order to facilitate the movement of the support frame 1, rollers 8 are installed at the bottom of the support frame 1, and the number of the rollers 8 is not specifically limited.
[0037] A construction method using the foundation wall ring beam pouring auxiliary device as described above comprises the following steps:
[0038] The support frame 1 is erected on the wall, and the construction worker stands on the top of the ring beam and pushes the guardrail 9 to move the support frame 1 along the wall to the pouring position through the roller 8 at the bottom;
[0039] The construction worker steps on the pedal 4, and the upper end of the brake link 5 rotates toward the outside of the support frame 1, and the lower end of the brake link 5 rotates toward the wall. When the supporting plate 7 is in contact with the wall, the support frame 1 is positioned.
[0040] The crane places the pouring funnel on the pouring port 2 for pouring to keep the pouring funnel stable. After the pouring is completed, the construction personnel release the pedal 4 and move the support frame 1 to the next pouring position for subsequent pouring.
[0041] Embodiment: A foundation wall ring beam casting auxiliary device comprises a support frame 1, a casting port 2 and a brake. The support frame 1 is formed by welding profiles and is erected on the wall. A roller 8 is installed at the bottom of the support frame 1 and can move along the wall. A support connecting rod 3 is welded to the top of the support member, and a casting port 2 adapted to the casting funnel is welded to the support connecting rod 3. The brake member is arranged on the support frame 1 and symmetrically arranged on both sides of the wall. The brake member comprises a brake shaft 6 and a brake connecting rod 5. The brake shaft 6 is horizontally arranged on the support frame 1 and is rotatably connected to the support frame 1 by a bearing. The brake connecting rod 5 is fixedly welded to the brake shaft 6 and is arranged perpendicular to the brake shaft 6. When no external force is applied, the brake link 5 hangs freely, with one end located above the brake shaft 6 and the other end located below the brake shaft 6. When the construction worker steps on the upper end of the brake link 5, the upper end of the brake link 5 rotates toward the outside of the support frame 1, so that the lower end of the brake link 5 rotates toward the wall and abuts against the wall. A support plate 7 is welded to the lower end of the brake link 5, and a pedal 4 is welded to the upper end of the brake link 5. Guardrails 9 are welded on both sides of the support frame 1.
[0042] The advantages and positive effects of the present invention are:
[0043] 1. By setting up the pouring port, manual labor is replaced, so that the pouring funnel can be placed stably, the outflow of concrete is reduced, the operation is convenient and the waste of materials is reduced.
[0044] 2. By setting rollers, the support frame can be moved along the wall, making it convenient to pour at different pouring positions.
[0045] 3. By setting the brake parts, construction workers can position and fix the support parts at any time to ensure the normal pouring and improve work efficiency.
[0046] 4. By setting up protective railings, the working safety of construction workers is guaranteed.
[0047] The embodiments of the present invention are described in detail above, but the contents described are only preferred embodiments of the present invention and cannot be considered to limit the scope of implementation of the present invention. All equivalent changes and improvements made according to the scope of application of the present invention should still fall within the scope of the patent coverage of the present invention.
Claims
1. A foundation wall ring beam casting auxiliary device, characterized in that: include: The support frame is mounted on the wall and can move along the wall; A pouring port, arranged at the top of the support frame, for placing a pouring funnel; A brake component is arranged on the support frame and is used for abutting against the wall to position the support frame.
2. A foundation wall ring beam pouring auxiliary device according to claim 1, characterized in that: The braking members are symmetrically arranged on both sides of the wall.
3. A foundation wall ring beam pouring auxiliary device according to claim 2, characterized in that: The brake component comprises a brake shaft, which is rotatably connected to the support frame. A brake connecting rod is arranged on the brake shaft, and the brake connecting rod can be rotated to abut against the wall.
4. A foundation wall ring beam pouring auxiliary device according to claim 3, characterized in that: A supporting plate is provided at one end of the brake connecting rod close to the wall.
5. A foundation wall ring beam pouring auxiliary device according to claim 4, characterized in that: A pedal is provided at one end of the brake connecting rod away from the wall.
6. A foundation wall ring beam pouring auxiliary device according to any one of claims 1 to 5, characterized in that: A supporting connecting rod is arranged on the top of the supporting frame, and the pouring port is arranged on the supporting connecting rod.
7. A foundation wall ring beam pouring auxiliary device according to claim 6, characterized in that: Guardrails are arranged on both sides of the support frame.
8. A foundation wall ring beam pouring auxiliary device according to any one of claims 1 to 5 and 7, characterized in that: The bottom of the support frame is provided with rollers.
9. A construction method using a foundation wall ring beam pouring auxiliary device as claimed in any one of claims 1 to 8, characterized in that: The following steps are involved: The support frame is installed on the wall, and the support frame is moved along the wall to a pouring position; The brake member is made to abut against the wall to position the support frame; The pouring funnel is placed at the pouring port for pouring.