Normal-temperature overspeed pre-rotation test method for prolonging service life of wheel disc of gas turbine

Through the normal temperature overspeed pre-rotation test method, the problem of shortening the life of the gas turbine roulette in high-temperature and high-pressure environment is solved, and the effective increase of the life of the roulette and the reduction of production costs are achieved.

CN119469776AActive Publication Date: 2025-02-18NO 703 RES INST OF CHINA SHIPBUILDING IND CORP
View PDF 6 Cites 0 Cited by

Patent Information

Application Number
CN202411611019.X
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Priority Date
2024-09-08
Filing Date
2024-11-12
Publication Date
2025-02-18
Estimated Expiration
2044-11-12

AI Technical Summary

Technical Problem

The gas turbine roulette is easily damaged by loads such as centrifugal force and thermal stress in high-temperature, high pressure and high speed working environments, resulting in a shortened life. The existing test methods are cumbersome, technical requirements are high, and the cost is high.

Method used

The internal stress distribution and life of the roulette are improved through the steps of rotor assembly and dynamic balance, installation standard judgment, normal temperature test rotation, vibration amplitude standard judgment and normal temperature pre-rotation test.

Benefits of technology

It effectively improves the service life of the roulette, reduces production costs, simplifies the test process, and reduces the requirements for personnel technical level and equipment.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119469776A_ABST
    Figure CN119469776A_ABST
Patent Text Reader

Abstract

The invention aims to provide a normal-temperature overspeed pre-rotation test method for prolonging the service life of a gas turbine wheel disc, which belongs to the field of gas turbines, and comprises the following steps: sequentially carrying out rotor assembly and dynamic balance, rotor installation, normal-temperature test rotation and normal-temperature pre-rotation test, and finally carrying out test result validity analysis. And if the test qualification standard requirement is met, stopping, if the test qualification standard requirement is not met, repeating the steps, re-selecting the test rotating speed to carry out the normal-temperature pre-rotation test, and respectively carrying out dynamic balance standard judgment, installation standard judgment and vibration amplitude standard judgment during the period. The service life of the wheel disc can be effectively prolonged, and the production cost of the wheel disc is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to a gas turbine testing method, in particular to a wheel disc testing method. Background Art

[0002] Ships and industrial gas turbines are developing towards higher power and larger size. In order to make the gas turbine have sufficient strength, its impeller rotating parts are often designed to be thick, which greatly increases its production and manufacturing costs. At the same time, its size also greatly occupies the limited space of ships and factories. The impeller generally works in a high temperature, high pressure, and high speed working environment, and is subjected to the combined effects of various loads such as centrifugal force and thermal stress attached to itself and the blades. Its destructive energy is huge, which will have catastrophic consequences on ships, factories and personal safety. Therefore, how to design a method to effectively increase the life of the impeller is particularly important.

[0003] Generally, it is easier to obtain plasticity in the center of the wheel by heating the wheel and then conducting an overspeed pre-rotation test, but the test process is relatively cumbersome and requires relatively high technical level of the test personnel and test equipment. If the material used for the wheel does not have brittleness within the working temperature range, it can be directly overspeeded at room temperature, which also has the effect of improving the stress distribution inside the wheel by the hot overspeed pre-rotation test. Summary of the invention

[0004] The object of the present invention is to provide a normal temperature overspeed pre-rotation test method for increasing the service life of a gas turbine wheel, which can effectively increase the service life of the wheel and reduce the production cost of the wheel.

[0005] The object of the present invention is achieved in that:

[0006] The present invention provides a normal temperature overspeed pre-rotation test method for improving the service life of a gas turbine wheel disc, which is characterized by comprising the following steps:

[0007] (1) Perform rotor assembly and dynamic balancing;

[0008] (2) Determine the dynamic balance standard. If the unbalance requirement is met, proceed to step (3). If not, repeat step (1) to perform dynamic balancing again.

[0009] (3) Install the rotor;

[0010] (4) Determine the installation standard. If the circular runout requirement is met, proceed to step (5); if not, proceed to step (3);

[0011] (5) Conduct a test run at room temperature;

[0012] (6) Determine the vibration amplitude standard. If the vibration standard is met, proceed to step (7). If not, repeat step (1) to perform dynamic rebalancing.

[0013] (7) Conducting a normal temperature pre-rotation test;

[0014] (8) Analyze the validity of the test results. If the test results meet the requirements of the test qualification standard, stop the test. If not, repeat step (7) and re-select the test speed to perform the normal temperature pre-rotation test.

[0015] The present invention may also include:

[0016] 1. Step (1) After the rotor is assembled, measure the diameter of the center hole of the disk: measure at least 3 different positions along the axial direction of the center hole of the disk, and measure the diameter twice at each position at 90° perpendicular to each other, and mark these positions on the disk. The average value of the measured dimensions is recorded as Dpp, and the temperature when the dimensions are measured is recorded as Ts.

[0017] 2. The dynamic balancing standard of step (2) is that the residual unbalance after dynamic balancing is less than 100 g·mm.

[0018] 3. The installation standard of step (4) is that the circular runout of any circumferential surface of the test piece after installation is less than 0.1 mm.

[0019] 4. The vibration amplitude standard of step (6) is that the vibration amplitude of the test piece is less than 70 μm when it reaches the maximum steady-state speed.

[0020] 5. The calculation method of the normal temperature pre-rotation test speed in step (7) is:

[0021]

[0022] and The calculation is as follows:

[0023]

[0024] Among them, K1 and K2 are coefficients, which are related to the wheel structure and material properties.

[0025] 6. Step (7) Normal temperature pre-rotation test requirements: After the wheel reaches the specified temperature, keep it warm for at least 1 hour before testing. R Spin at high speed for at least 1 minute;

[0026] After the test, the wheel is cooled down. When the wheel is thermally stable, the temperature is measured. The diameter of the center hole of the wheel is measured by the same method at the same position as step (1). The average value is recorded as Duse, and the temperature at which the size is measured is recorded as Te.

[0027] 7. The pass criterion for the test in step (8) is that the difference in the aperture growth Duse-Dpp measured at the center of the wheel before and after the rotation test is between 0.02-0.12 mm.

[0028] 8. The difference in hole diameter growth takes into account the following factors: If the temperature Te when the size is measured after the test differs from the temperature Ts when the size is measured before the rotation test by more than ±5°C, the thermal expansion of the wheel material is taken into account to correct the diameter measurement reading:

[0029] Each diameter measurement should be added with the value Z:

[0030] Z = αD(T s -T e )

[0031] The difference in the corrected aperture growth is recorded as:

[0032] Dxz=Duse-Dpp+Z.

[0033] The advantages of the present invention are that the present invention can effectively increase the service life of the wheel disc and reduce the production cost of the wheel disc. BRIEF DESCRIPTION OF THE DRAWINGS

[0034] Figure 1 is a flow chart of the present invention;

[0035] Figure 2 Schematic diagram of a gas turbine disc. DETAILED DESCRIPTION

[0036] The present invention is described in more detail below with reference to the accompanying drawings:

[0037] Combination Figure 1-2 The present invention provides a normal temperature overspeed pre-rotation test method for improving the service life of a gas turbine wheel disc, and the specific steps are as follows:

[0038] Step 1: Assemble and dynamically balance the rotor, including assembling and dynamically balancing the test piece with the adapter plate, simulated blades and other accompanying test pieces.

[0039] After the rotor is assembled, Figure 2 The diameter of the center hole of the wheel is measured by measuring at least 3 different positions along the axial direction of the center hole. Each position needs to be measured twice at 90° perpendicular to each other, and these positions must be marked on the wheel. The average value of the measured multiple dimensions is recorded as Dpp; and the temperature when the dimension is measured is recorded as Ts.

[0040] Step 2: Determine the dynamic balance standard. If the unbalance requirement is met, proceed to step 3. If not, repeat step 1 to re-balance.

[0041] The dynamic balancing standard is that the residual unbalance after dynamic balancing should be less than 100g·mm.

[0042] Step 3: Install the rotor and connect the rotor test piece to the rotation tester through the intermediate connecting fixture.

[0043] Step 4: Determine the installation standard. If the circular runout requirement is met, proceed to step 5. If not, proceed to step 3.

[0044] The installation standard is that the circular runout of any circumferential surface of the test piece after installation must be less than 0.1mm.

[0045] Step 5: Perform a test run at room temperature.

[0046] Step 6: Determine the vibration amplitude standard. If it meets the vibration standard, proceed to step 7. If it does not meet the standard, repeat step 1 to re-balance.

[0047] The vibration amplitude standard is that the vibration amplitude is less than 70μm when the test piece reaches the maximum steady-state speed.

[0048] Step 7: Conduct a normal temperature pre-rotation test. The key parameters of the test include the normal temperature pre-rotation test speed, the holding time before the normal temperature pre-rotation test, the holding time of the normal temperature pre-rotation test speed, and the normal temperature pre-rotation test temperature. Before the temperature reaches the test requirement, it should be operated at a low speed of 100 to 200 r / min to ensure that the wheel is cooled evenly.

[0049] The calculation method of the normal temperature pre-rotation test speed is: Test speed N R For between and The minimum speed between.

[0050]

[0051] and The calculation is as follows:

[0052]

[0053] Among them, K1 and K2 are coefficients, which are related to the wheel structure and material properties.

[0054] Where:

[0055] - 0.2% yield strength at 20 degrees Celsius, in MPa.

[0056] -The tensile strength at 20 degrees Celsius, in MPa.

[0057] The mechanical properties of the samples collected from the area near the center hole of the disk at a temperature of 20°C were used.

[0058] For the normal temperature pre-rotation test, the holding time before the normal temperature pre-rotation test shall be at least 1 hour, and the holding time of the normal temperature pre-rotation test speed shall be at least 1 minute.

[0059] After the test, the wheel is cooled down. When the wheel is thermally stable, the temperature is measured. The diameter of the center hole of the wheel is measured by the same method at the same position as step 1. The average value is recorded as Duse, and the temperature when the size is measured is recorded as Te.

[0060] Step 8: Analyze the validity of the test results. If the test results meet the requirements of the test qualification standard, stop. If not, repeat step 7 and re-select the test speed to perform the normal temperature pre-rotation test.

[0061] The test pass criterion is that the difference in aperture growth (Duse-Dpp) measured at the center of the wheel before and after the rotation test must be between 0.02-0.12mm.

[0062] If the temperature Te at which the dimensions are measured after the test differs by more than ±5°C from the temperature Ts at which the dimensions are measured before the rotation test, it is necessary to correct the diameter measurement reading to take into account the thermal expansion of the disc material.

[0063] In this case, the value "Z" should be added to each diameter measurement:

[0064] Z = αD(T s -T e ) (4)

[0065] Where:

[0066] α is the linear expansion coefficient of the material, in °C -1 .

[0067] D is the nominal size of the roulette disc center hole diameter, in mm.

[0068] Ts is the temperature when the dimensions are measured before the test, in °C.

[0069] Te is the temperature when the dimensions are measured after the test, in °C.

[0070] The difference in the corrected aperture growth is recorded as:

[0071] Dxz=Duse-Dpp+Z (5).

Claims

1. A normal temperature overspeed pre-rotation test method for improving the service life of a gas turbine disk, characterized by: The following steps are involved: (1) Perform rotor assembly and dynamic balancing; (2) Determine the dynamic balance standard. If the unbalance requirement is met, proceed to step (3). If not, repeat step (1) to perform dynamic balancing again. (3) Install the rotor; (4) Determine the installation standard. If the circular runout requirement is met, proceed to step (5); if not, proceed to step (3); (5) Conduct a test run at room temperature; (6) Determine the vibration amplitude standard. If the vibration standard is met, proceed to step (7). If not, repeat step (1) to perform dynamic rebalancing. (7) Conducting a normal temperature pre-rotation test; (8) Analyze the validity of the test results. If the test results meet the requirements of the test qualification standard, stop the test. If not, repeat step (7) and re-select the test speed to perform the normal temperature pre-rotation test.

2. A normal temperature overspeed pre-rotation test method for improving the service life of a gas turbine disk according to claim 1, characterized in that: Step (1) After the rotor is assembled, measure the diameter of the center hole of the disk: measure at least 3 different positions along the axial direction of the center hole of the disk, and measure the diameter twice at each position at 90° perpendicular to each other, and mark these positions on the wheel. The average value of the measured dimensions is recorded as Dpp, and the temperature when the dimensions are measured is recorded as Ts.

3. A normal temperature overspeed pre-rotation test method for improving the service life of a gas turbine disk according to claim 1, characterized in that: The dynamic balancing standard of step (2) is that the residual unbalance after dynamic balancing is less than 100 g·mm.

4. A normal temperature overspeed pre-rotation test method for improving the service life of a gas turbine disk according to claim 1, characterized in that: The installation standard of step (4) is that the circular runout of any circumferential surface of the test piece after installation is less than 0.1 mm.

5. A normal temperature overspeed pre-rotation test method for improving the service life of a gas turbine disk according to claim 1, characterized in that: The vibration amplitude standard of step (6) is that the vibration amplitude is less than 70 μm when the test piece reaches the maximum steady-state speed.

6. A normal temperature overspeed pre-rotation test method for improving the service life of a gas turbine disk according to claim 1, characterized in that: Step (7) The calculation method of the normal temperature pre-rotation test speed is: and The calculation is as follows: Among them, K1 and K2 are coefficients, which are related to the wheel structure and material properties.

7. A normal temperature overspeed pre-rotation test method for improving the service life of a gas turbine disk according to claim 1, characterized in that: Step (7) Normal temperature pre-rotation test requirements: After the wheel reaches the specified temperature, keep it warm for at least 1 hour before testing. R Spin at high speed for at least 1 minute; After the test, the wheel is cooled down. When the wheel is thermally stable, the temperature is measured. The diameter of the center hole of the wheel is measured by the same method at the same position as step (1). The average value is recorded as Duse, and the temperature at which the size is measured is recorded as Te.

8. A normal temperature overspeed pre-rotation test method for improving the service life of a gas turbine disk according to claim 1, characterized in that: The pass criterion for the test in step (8) is that the difference Duse-Dpp of the aperture growth measured at the center of the wheel before and after the rotation test is between 0.02-0.12 mm.

9. A normal temperature overspeed pre-rotation test method for improving the service life of a gas turbine disk according to claim 8, characterized in that: The difference in hole diameter growth takes into account the following factors: If the temperature Te when the size is measured after the test differs from the temperature Ts when the size is measured before the rotation test by more than ±5°C, the thermal expansion of the wheel material is taken into account to correct the diameter measurement reading: Each diameter measurement should be added with the value Z: Z=αD(T s -T e ) The difference in the corrected aperture growth is recorded as: Dxz=Duse-Dpp+Z.

Citation Information

Patent Citations

  • High-speed dynamic balancing calibration method of gas turbine rotors with power of 254 MW

    CN102374925A

  • Method for improving low cycle fatigue life of wheel disk by pre-rotation

    CN109145335A

  • Test device and method for eliminating residual stress through pre-rotation of turbine blank disc

    CN112016223A

  • Rotor on-site dynamic balance detection method and detection system

    CN112729681A

  • Thermal mechanical and high-cycle composite fatigue test method for turbine blade in rotating environment

    CN118443290A