Basement ramp construction method

By carrying out waterproofing construction of the basement base plate and pre-embedding of the water-stop steel plate during the construction of the basement ramp, combined with waterproof stubble treatment and the overall pouring method after the soil settles, the waterproofing problems and long construction period in the construction of the basement ramp are solved, and the stability and waterproof performance of the ramp are improved.

CN119553891AInactive Publication Date: 2025-03-04CHINA FIRST METALLURGICAL GROUP
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411817072.5
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-12-11
Publication Date
2025-03-04
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

During the construction process, due to the limitation of construction space, external waterproof construction is difficult to complete the closure, resulting in leakage of the ramp and affecting the service life of the basement.

Method used

A method of building a ramp is adopted, including pouring the concrete cushion layer of the basement and waterproof construction of the basement basement floor, pre-arranged water-stop steel plates on the top of the L-shaped plate of the basement, carrying out waterproof and stubble treatment, and carrying out ramp concrete cushion layer and waterproof construction after the soil is fully settled, and an overall pouring method is adopted without leaving construction joints.

Benefits of technology

By stabilizing soil settlement and waterproof construction, uneven settlement and leakage of the ramps are avoided, the construction period is shortened, and the waterproof performance of the basement is improved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119553891A_ABST
    Figure CN119553891A_ABST
Patent Text Reader

Abstract

The invention discloses a basement ramp construction method and relates to the field of building construction. The basement ramp construction method comprises the steps that basement concrete cushion layer pouring and basement bottom plate waterproof construction are conducted in sequence; a water stop steel plate is arranged on the top of the basement L-shaped plate to be poured in advance, and the basement L-shaped plate is obtained through pouring; waterproof construction of the basement L-shaped plate side wall is conducted, waterproof throwing stubbles are reserved in construction joints of the basement L-shaped plate side wall, and a basement L-shaped plate side wall waterproof protection layer is bricked; plain soil backfilling is conducted on the outer side of the basement L-shaped plate, and the plain soil is tamped to the bottom face of the ramp structure cushion layer in a layered mode; concrete pouring is conducted on the ramp side wall and the ramp top plate; backfilling and tamping soil on the inner side of the ramp of the basement; after the soil body is fully settled, a ramp structure concrete cushion layer is poured, and ramp structure waterproof construction is conducted; and ramp concrete pouring is conducted. According to the basement ramp construction method, the soil body under the ramp can stably settle, uneven settlement is avoided, ramp water leakage is avoided, and the ramp construction period is shortened.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the field of building construction, and in particular, to a method for constructing a basement ramp. Background Art

[0002] At present, the entrance to the basement of a residential area is usually a passage-type building for residents to enter and exit and store their cars, which is generally composed of a downhill ramp-type building; the downhill ramp of the basement entrance and exit, as the main passage connecting the basement to the outside world, needs to have a good waterproof structure.

[0003] However, the basement ramp is limited by the construction space, and it is difficult to complete the closed construction of external waterproofing. The ramp needs to leave construction joints due to construction reasons. If the waterproofing construction is unreasonable, it is very easy to cause ramp leakage, which will seriously affect the service life of the basement. Summary of the invention

[0004] The purpose of the present application is to provide a basement ramp construction method, which can stabilize the settlement of soil under the ramp to avoid uneven settlement, avoid ramp leakage and shorten the ramp construction period.

[0005] This application is implemented as follows:

[0006] The present application provides a basement ramp construction method, which comprises the following steps:

[0007] Carry out the pouring of basement concrete cushion layer and waterproofing of basement floor slab in sequence;

[0008] A water-stop steel plate is pre-arranged on the top of the L-shaped basement slab to be cast, and the L-shaped basement slab is cast;

[0009] Carry out waterproof construction on the side walls of the basement L-shaped slab, reserve waterproof stubble at the construction joints of the side walls of the basement L-shaped slab, and build a waterproof protective layer on the side walls of the basement L-shaped slab with bricks;

[0010] Backfill the outside of the L-shaped basement slab with soil and compact it layer by layer to below the bottom of the ramp cushion layer;

[0011] Carry out concrete pouring of ramp side walls and basement roof;

[0012] Backfill and compact the soil inside the slope of the basement;

[0013] After the soil has fully settled, pour the ramp concrete cushion and carry out ramp waterproofing construction;

[0014] Pour concrete for ramp.

[0015] In some optional implementation schemes, before pouring the basement concrete cushion layer, the basement floor is cleaned, the guide wall of the basement L-shaped slab side wall is bricked, and when the basement concrete cushion layer is constructed, the corners between the basement concrete cushion layer and the guide wall are smoothed into an arc shape.

[0016] In some optional implementation schemes, during the basement floor waterproofing construction, a non-curing asphalt waterproof coating is coated on the basement concrete cushion layer and then an SBS modified asphalt pre-laid anti-adhesive waterproof membrane is laid.

[0017] In some optional embodiments, before applying the non-curing asphalt waterproof coating, an additional layer of internal corner waterproofing is set at the internal corner between the L-shaped basement plate and the ramp to be constructed, and the additional layer of internal corner waterproofing is set 200-300mm on each side of the internal corner between the L-shaped basement plate and the ramp.

[0018] In some optional implementation schemes, when waterproofing the side walls on both sides of the basement L-shaped plate, the side walls on both sides of the basement L-shaped plate are waterproofly overlapped with the bottom plate, and the overlap length is 80-120mm.

[0019] In some optional embodiments, a 400-600mm wide external corner waterproof additional layer is set at the external corner between the basement L-shaped plate and the ramp, and the external corner waterproof additional layer is set 200-300mm on each side of the external corner between the basement L-shaped plate and the ramp structure.

[0020] In some optional implementation schemes, when waterproofing the side walls on both sides of the basement L-shaped slab, waterproof stubble is reserved at the construction joints of the side walls on both sides of the basement L-shaped slab, and the stubble length is 400-600mm. The SBS modified asphalt pre-laid anti-adhesive waterproof membrane is stubbled 200-400mm to the side walls on both sides of the basement L-shaped slab.

[0021] In some optional implementation schemes, after backfilling with bare soil on the outside of the L-shaped slab of the basement and compacting it layer by layer to the bottom surface of the ramp structure cushion layer, the ramp cantilevered bottom slab cushion layer is built, and waterproof stubble is reserved at the construction joint of the ramp cantilevered bottom slab cushion layer, so that the waterproof stubble is thrown to the ramp cantilevered bottom slab cushion layer, and waterproof construction is performed on the ramp cantilevered bottom slab cushion layer.

[0022] In some optional implementation schemes, before pouring concrete of the ramp side walls and the basement top slab, the ramp side walls and the outer side of the ramp are reinforced, and the ramp slab is reinforced longitudinally and transversely. A vertical construction joint is reserved on the ramp side walls of the basement, and a horizontal construction joint of the ramp slab is reserved at the construction site of the ramp cantilever bottom slab.

[0023] In some optional implementation schemes, after the concrete pouring of the ramp side walls and the basement roof, when the basement roof reaches the designed strength, pipes connected to the intercepting ditch are pre-buried on both sides of the ramp, and non-woven geotextiles are wrapped on the pipes after drilling holes at intervals.

[0024] The beneficial effect of the present application is that the basement ramp construction method provided by the present application comprises the following steps: sequentially performing basement concrete cushion pouring and basement bottom slab waterproofing construction; pre-arranging a waterstop steel plate on the top of the basement L-shaped slab to be poured, and pouring the basement L-shaped slab; waterproofing construction of the side walls on both sides of the basement L-shaped slab, reserving waterproof stubble at the construction joints of the side walls on both sides of the basement L-shaped slab, and brick-laying the waterproof protective layer of the side walls of the basement L-shaped slab; backfilling the outer side of the basement L-shaped slab with plain soil and compacting it in layers to below the bottom surface of the ramp cushion; pouring concrete of the ramp side walls and the basement top slab; backfilling and compacting the soil on the inner side of the basement ramp; pouring the ramp concrete cushion and ramp waterproofing construction after the soil has fully settled; and pouring ramp concrete. The basement ramp construction method provided in the present application can stabilize the settlement of the soil under the ramp by pre-embedding a water-stop steel plate on the top of the basement L-shaped plate and backfilling earth on the outside of the basement L-shaped plate in advance, thereby avoiding cracking of the ramp caused by uneven settlement, and allowing the ramp concrete to be constructed without leaving a ramp construction joint and with an overall pouring method, thereby avoiding ramp leakage and solving the problem of long ramp construction period. BRIEF DESCRIPTION OF THE DRAWINGS

[0025] In order to more clearly illustrate the technical solutions of the embodiments of the present application, the drawings required for use in the embodiments will be briefly introduced below. It should be understood that the following drawings only show certain embodiments of the present application and therefore should not be regarded as limiting the scope. For ordinary technicians in this field, other related drawings can be obtained based on these drawings without paying creative work.

[0026] Figure 1 A schematic diagram of the structure of the basement ramp construction method provided in the embodiment of the present application during the pouring of the basement L-shaped plate and the waterproofing of the basement floor;

[0027] Figure 2 A partial perspective structural diagram of the construction of the ramp side wall and the basement roof in the basement ramp construction method provided in an embodiment of the present application;

[0028] Figure 3 This is a schematic diagram of the partial perspective structure after the ramp is constructed in the basement ramp construction method provided in an embodiment of the present application.

[0029] In the figure: 100, basement concrete cushion; 110, basement L-shaped plate; 120, water-stop steel plate; 130, basement L-shaped plate side wall; 140, basement floor; 150, guide wall; 160, ramp side wall; 170, non-curing asphalt waterproof coating; 180, SBS modified asphalt pre-laid anti-adhesive waterproof membrane; 190, additional waterproof layer for inner corners; 200, additional waterproof layer for outer corners; 210, ramp; 220, drainage ditch; 230, basement roof; 240, ramp plate transverse reinforcement; 250, basement side wall horizontal construction joint; 260, ramp plate longitudinal reinforcement; 270, ramp side wall vertical construction joint; 280, ramp plate horizontal construction joint; 290, ramp concrete cushion; 300, plain soil. DETAILED DESCRIPTION

[0030] In order to make the purpose, technical solution and advantages of the embodiments of the present application clearer, the technical solution in the embodiments of the present application will be clearly and completely described below in conjunction with the drawings in the embodiments of the present application. Obviously, the described embodiments are part of the embodiments of the present application, rather than all the embodiments. The components of the embodiments of the present application described and shown in the drawings here can be arranged and designed in various different configurations.

[0031] Therefore, the following detailed description of the embodiments of the present application provided in the accompanying drawings is not intended to limit the scope of the present application for which protection is sought, but merely represents selected embodiments of the present application. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in the field without creative work are within the scope of protection of the present application.

[0032] It should be noted that similar reference numerals and letters denote similar items in the following drawings, and therefore, once an item is defined in one drawing, further definition and explanation thereof is not required in subsequent drawings.

[0033] In the description of the present application, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", etc. indicate positions or positional relationships based on the positions or positional relationships shown in the accompanying drawings, or the positions or positional relationships in which the product of the application is usually placed when in use. They are only for the convenience of describing the present application and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific position, be constructed and operated in a specific position, and therefore cannot be understood as a limitation on the present application. In addition, the terms "first", "second", "third", etc. are only used to distinguish the description, and cannot be understood as indicating or implying relative importance.

[0034] In addition, the terms "horizontal", "vertical", "overhanging" and the like do not mean that the components are required to be absolutely horizontal or overhanging, but can be slightly tilted. For example, "horizontal" only means that its direction is more horizontal than "vertical", and does not mean that the structure must be completely horizontal, but can be slightly tilted.

[0035] In the description of this application, it should also be noted that, unless otherwise clearly specified and limited, the terms "set", "install", "connect", and "connect" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two elements. For ordinary technicians in this field, the specific meanings of the above terms in this application can be understood according to specific circumstances.

[0036] In the present application, unless otherwise clearly specified and limited, a first feature being "above" or "below" a second feature may include that the first and second features are in direct contact, or may include that the first and second features are not in direct contact but are in contact through another feature between them. Moreover, a first feature being "above", "above" and "above" a second feature includes that the first feature is directly above and obliquely above the second feature, or simply indicates that the first feature is higher in level than the second feature. A first feature being "below", "below" and "below" a second feature includes that the first feature is directly below and obliquely below the second feature, or simply indicates that the first feature is lower in level than the second feature.

[0037] The characteristics and performance of the basement ramp construction method of the present application are further described in detail below in conjunction with the embodiments.

[0038] like Figure 1 , Figure 2 and Figure 3 As shown, the embodiment of the present application provides a basement ramp construction method, which includes the following steps:

[0039] Step 1: First, build the guide wall 150 of the basement L-shaped plate side wall 130 with bricks, clean the basement floor 140, then construct the basement concrete cushion layer 100 on the basement floor 140, smooth the inner and outer corners between the basement concrete cushion layer 100 and the guide wall 150 into an arc shape, then perform basement floor waterproofing construction on the surface of the basement concrete cushion layer 100. During the basement floor waterproofing construction, first apply a non-curing asphalt waterproof coating 170 on the basement concrete cushion layer 100, and then lay the SBS modified asphalt pre-laid anti-adhesive waterproofing membrane 180;

[0040] An additional waterproof layer 190 is provided at the inner corner between the basement L-shaped plate 110 and the ramp 210 . The additional waterproof layer 190 is provided with a width of 200-300 mm on each side of the inner corner between the basement L-shaped plate 110 and the ramp 210 .

[0041] Step 2: Tie the steel bars inside the basement L-shaped plate 110, and pre-arrange the water-stop steel plate 120 on the top of the basement L-shaped plate 110 to be cast, and set up the formwork of the basement L-shaped plate 110 to cast the basement L-shaped plate 110;

[0042] Step 3: waterproof the side walls on both sides of the basement L-shaped plate 110, reserve waterproof stubble at the horizontal construction joint 250 of the basement side wall, the stubble length is 400-600mm, pre-lay the SBS modified asphalt anti-adhesive waterproof membrane 180 to the side walls on both sides of the basement L-shaped plate 110, and stubble 200-400mm on the side walls, and the side walls on both sides of the basement L-shaped plate 110 are waterproofly overlapped with the basement floor, and the overlap length is 80-120mm;

[0043] A 400-600mm wide external corner waterproof additional layer 200 is provided at the external corner between the basement L-shaped plate 110 and the ramp 210, and a 200-300mm wide external corner waterproof additional layer 200 is provided on each side of the external corner between the basement L-shaped plate 110 and the ramp 210; a waterproof protective layer for the side wall of the basement L-shaped plate with a brickwork thickness of 80-120mm;

[0044] Step 4: backfill the plain soil 300 outside the basement L-shaped plate 110 and compact it layer by layer to below the bottom surface of the cushion layer of the ramp 210, pour the ramp cantilevered bottom plate cushion layer, and reserve waterproof stubble at the ramp plate horizontal construction joint 280 of the ramp cantilevered bottom plate cushion layer, so that the waterproof stubble is thrown to the ramp cantilevered bottom plate cushion layer, and waterproof construction is performed on the ramp cantilevered bottom plate cushion layer;

[0045] Step 5: tie the outer side reinforcements of the ramp side wall 160 and the ramp 210, and reinforce the ramp slab longitudinally and transversely to obtain the ramp slab transverse reinforcement 240 and the ramp slab longitudinal reinforcement 260, reserve the ramp side wall vertical construction joint 270 on the ramp side wall 160 of the basement, reserve the ramp slab horizontal construction joint 280 on the ramp cantilever bottom plate, set up the formwork and construction support of the basement top plate 230, tie the reinforcements of the basement top plate 230 after acceptance, and pour concrete to obtain the basement top plate 230 and the ramp side wall 160;

[0046] Step 6: When the basement roof 230 reaches the designed strength, PVC pipes connected to the drainage ditch 220 in the basement are pre-buried on both sides of the ramp 210, and non-woven geotextiles are wrapped after drilling holes on the PVC pipes at intervals, and the plain soil 300 inside the ramp 210 of the basement is backfilled and compacted to below the designed ramp concrete cushion 290;

[0047] Step 7: Clean the construction joints by chiseling and roughening, and pour the ramp concrete cushion layer 290 after the plain soil 300 has fully settled;

[0048] Step eight, waterproof the ramp 210 , tie the internal steel bars of the ramp 210 , overlap the internal steel bars of the ramp 210 , the ramp slab transverse reinforcement 240 , and the ramp slab longitudinal reinforcement 260 according to the specification, and pour concrete to obtain the ramp 210 .

[0049] The basement ramp construction method provided in the embodiment of the present application can effectively improve the waterproof performance of the basement and avoid leakage by pre-embedding a water-stop steel plate 120 on the top of the basement L-shaped plate 110 when constructing the basement L-shaped plate 110, and reserving waterproof stubble at the horizontal construction joint 250 of the basement side wall when constructing the side walls on both sides of the basement L-shaped plate 110. At the same time, backfilling the outer side of the basement L-shaped plate 110 and the inner side of the ramp 210 with plain soil before constructing the ramp 210 can stabilize the settlement of the soil under the ramp 210 and avoid cracking of the ramp 210 caused by uneven settlement. The concrete of the ramp 210 adopts the method of integral casting without leaving a ramp construction joint, which solves the problem of long construction period of the ramp 210.

[0050] Among them, a negative corner waterproof additional layer 190 is set at the negative corner between the basement L-shaped plate 110 and the ramp 210, and a positive corner waterproof additional layer 200 is set at the positive corner between the basement L-shaped plate 110 and the ramp 210, which can further improve the waterproof performance between the basement L-shaped plate 110 and the ramp 210 by using the negative corner waterproof additional layer 190 and the positive corner waterproof additional layer 200;

[0051] The ramp cantilevered bottom plate cushion layer is built, and waterproof stubble is reserved at the ramp plate horizontal construction joint 280 of the ramp plate of the ramp cantilevered bottom plate cushion layer, so that the waterproof stubble is thrown to the ramp cantilevered bottom plate cushion layer, which can prevent rainwater from entering the gap of the ramp cantilevered bottom plate cushion layer through the ramp plate horizontal construction joint 280; the ramp plate horizontal stubble reinforcement 240 and the ramp plate longitudinal stubble reinforcement 260 are thrown in advance between the ramp plate and the ramp side walls 160 on both sides, and the ramp 210 is overall reinforced and poured with concrete after the ramp concrete cushion layer 290 is poured, which solves the leakage risk caused by the segmented pouring of the traditional ramp 210, ensures the self-waterproof effect of the concrete, and avoids water leakage of the ramp 210 structure. By pre-burying PVC pipes connected to the drainage ditch 220 on both sides of the ramp 210, and drilling holes in the PVC pipes at intervals and wrapping them with non-woven geotextiles, the water vapor in the basement ramp 210 can be discharged to the drainage ditch 220 through the PVC pipes, avoiding water vapor infiltration and contamination of the floor.

[0052] The embodiments described above are part of the embodiments of the present application, rather than all of the embodiments. The detailed description of the embodiments of the present application is not intended to limit the scope of the present application for protection, but merely represents the selected embodiments of the present application. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present application.

Claims

1. A basement ramp construction method, characterized in that: It includes the following steps: Carry out the pouring of basement concrete cushion layer and waterproofing of basement floor slab in sequence; A water-stop steel plate is pre-arranged on the top of the L-shaped basement slab to be cast, and the L-shaped basement slab is cast; Waterproofing the side walls of the basement L-shaped plate, reserving waterproof stubble at the construction joints of the side walls of the basement L-shaped plate, and brick-laying the waterproof protective layer of the side walls of the basement L-shaped plate; Backfilling the outside of the L-shaped basement slab with soil and compacting it layer by layer to below the bottom surface of the ramp cushion layer; Carry out concrete pouring of ramp side walls and basement roof; Backfill and compact the soil inside the slope of the basement; After the soil has fully settled, pour the ramp concrete cushion and carry out ramp waterproofing construction; Concrete pouring of ramp.

2. The basement ramp construction method according to claim 1, characterized in that: Before pouring the basement concrete cushion layer, the basement floor is cleaned, and the guide wall of the basement L-shaped slab side wall is bricked. When the basement concrete cushion layer is constructed, the positive and negative corners between the basement concrete cushion layer and the guide wall are smoothed into an arc shape.

3. The basement ramp construction method according to claim 2, characterized in that: During the waterproofing construction of the basement floor, a non-curing asphalt waterproof coating is applied on the basement concrete cushion layer, and then an SBS modified asphalt pre-laid anti-adhesive waterproofing membrane is laid.

4. The basement ramp construction method according to claim 3, characterized in that: Before applying the non-curing asphalt waterproof coating, an additional waterproof layer for the inner corner is set at the inner corner between the L-shaped basement plate and the ramp to be constructed. The additional waterproof layer for the inner corner is set 200-300mm on each side of the inner corner between the L-shaped basement plate and the ramp.

5. The basement ramp construction method according to claim 3, characterized in that: When waterproofing the side walls on both sides of the basement L-shaped plate, the side walls on both sides of the basement L-shaped plate are waterproofly overlapped with the bottom plate, and the overlap length is 80-120mm.

6. The basement ramp construction method according to claim 3, characterized in that: A 400-600mm wide external corner waterproof additional layer is set at the external corner between the basement L-shaped plate and the ramp, and the external corner waterproof additional layer is set 200-300mm on each side of the external corner between the basement L-shaped plate and the ramp structure.

7. The basement ramp construction method according to claim 4, characterized in that: When waterproofing the side walls on both sides of the basement L-shaped slab, waterproof stubble is reserved at the construction joints of the side walls on both sides of the basement L-shaped slab, and the stubble length is 400-600mm. The SBS modified asphalt pre-laid anti-adhesive waterproof membrane is stubbled 200-400mm to the side walls on both sides of the basement L-shaped slab.

8. The basement ramp construction method according to claim 1, characterized in that: After backfilling the outside of the L-shaped slab of the basement with bare soil and compacting it layer by layer to the bottom surface of the ramp structure cushion layer, the ramp cantilevered bottom slab cushion layer is built, and waterproof stubble is reserved at the construction joint of the ramp cantilevered bottom slab cushion layer, so that the waterproof stubble is thrown to the ramp cantilevered bottom slab cushion layer, and waterproof construction is carried out on the ramp cantilevered bottom slab cushion layer.

9. The basement ramp construction method according to claim 8, characterized in that: Before pouring concrete of the ramp side walls and the basement top slab, the ramp side walls and the outside of the ramp are reinforced, and the ramp slab is reinforced longitudinally and transversely. A vertical construction joint is reserved on the ramp side walls of the basement, and a horizontal construction joint is reserved on the ramp slab at the construction site of the cantilevered bottom slab of the ramp.

10. The basement ramp construction method according to claim 1, characterized in that: After pouring concrete for the ramp side walls and the basement roof, when the basement roof reaches the designed strength, pipes connected to the intercepting ditch are pre-buried on both sides of the ramp, and non-woven geotextiles are wrapped on the pipes after drilling holes at intervals.