Sluice pump station
By setting up a cement soil backfilling layer and stone layer inside the concrete of the sluice pump station, the cement hydration heat is absorbed and cement reinforcement is formed through high-pressure rotary spray piles, the problems of temperature cracks and foundation load in the sluice pump station are solved, and the effect of extending service life and improving safety is achieved.
Patent Information
- Application Number
- CN202510029285.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2025-01-08
- Publication Date
- 2025-03-07
AI Technical Summary
During the construction process, the existing sluice pump stations have caused temperature cracks due to the high temperature generated during concrete hydration, which reduces the service life and poses a threat to the safety of staff.
By setting up a cement soil backfilling layer, stone layer, first cushion layer and second cushion layer inside the concrete of the sluice pump station, the stone and gravel absorb part of the hydration heat of cement, reduce the internal temperature of the concrete, and spray cement slurry into the soil layer through high-pressure rotary spray piles to form reinforcement, sharing the load on the foundation below the gate.
It effectively reduces the generation of temperature cracks, extends the service life of the sluice pump station, reduces engineering costs, and improves safety, avoids foundation settlement and deformation.
Smart Images

Figure CN119571772A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of pump stations, in particular to a sluice pump station. Background Art
[0002] A low-head hydraulic structure built on rivers and channels that uses gates to control flow and adjust water levels. Closing the gates can block floods, tides, or raise the upstream water level to meet the needs of irrigation, power generation, shipping, aquatic products, environmental protection, industry, and domestic water. Opening the gates can discharge floods, waterlogging, abandoned water, or wastewater, and can also supply water to downstream rivers or channels. In water conservancy projects, sluices are widely used as structures for retaining, discharging, or taking in water.
[0003] The existing sluice pump station still has certain deficiencies in actual use: the existing sluice pump station is only suitable for concrete pouring during construction, but cement releases a large amount of heat during the concrete hydration process. If the heat is too high, temperature cracks may occur inside the concrete structure, which reduces the service life of the sluice pump station and poses a threat to the life safety of the staff. Based on the existing technical deficiencies, the present invention designs a sluice pump station. Summary of the invention
[0004] The present invention provides a sluice pump station, which has the advantages of lowering the temperature inside the concrete and reducing the generation of temperature cracks, and solves the problems mentioned in the above background technology.
[0005] The present invention provides the following technical solutions: a sluice pump station, comprising a downstream wall, wherein a right wing wall is arranged on the outer wall of the downstream wall, a left wing wall is arranged on the other side of the outer wall of the downstream wall, the outer wall of the pump station is formed by the downstream wall, the right wing wall and the left wing wall, and a sluice structure is arranged inside the downstream wall; the sluice structure comprises three lock chambers and three breast walls, two winders are arranged on the tops of the three lock chambers, pull ropes are wound around the outer surfaces of the output rollers of the three groups of winders, gates are arranged at one end of the bottoms of the three groups of pull ropes, cement soil backfill layers are laid in the concrete layers of the three breast walls and the downstream walls, stone layers are laid in the concrete layers of the three breast walls and the downstream walls, first cushion layers are laid in the concrete layers of the three breast walls and the downstream walls, second cushion layers are laid in the concrete layers of the three breast walls and the downstream walls, and a plurality of high-pressure rotary jet piles are arranged below the three breast walls.
[0006] As a preferred technical solution of the present invention, an inspection bridge is provided on one side of the outer surface of the three breast walls, and a stainless steel railing is installed on one side of the three inspection bridges.
[0007] As a preferred technical solution of the present invention, a guard apron is arranged between the right wing wall and the left wing wall, and a blanket is arranged on one side of the outer surface of the guard apron.
[0008] As a preferred technical solution of the present invention, an energy dissipation pool is arranged inside the downstream wall, and a diesel engine room is arranged on the left side of the energy dissipation pool.
[0009] As a preferred technical solution of the present invention, a water outlet pool is arranged below the diesel engine room, a first water inlet culvert is arranged inside the downstream wall, and a second water inlet culvert is arranged on one side of the outer surface of the first water inlet culvert.
[0010] As a preferred technical solution of the present invention, a traffic bridge culvert is arranged between the first water inlet box culvert and the second water inlet box culvert, and a main pump room is arranged at one end of the traffic bridge culvert.
[0011] As a preferred technical solution of the present invention, a conference room is arranged inside the downstream wall, and a central control room is arranged on one side of the conference room.
[0012] As a preferred technical solution of the present invention, a low-voltage distribution room is arranged inside the downstream wall, and a high-voltage distribution room is arranged on one side of the low-voltage distribution room.
[0013] As a preferred technical solution of the present invention, a high-pressure control room is arranged inside the downstream wall, a lounge is arranged on one side of the high-pressure control room, and an office is arranged above the lounge.
[0014] As a preferred technical solution of the present invention, three pumps are arranged inside the main pump room, and a plurality of flow separation walls are arranged below the main pump room.
[0015] Compared with the prior art, the present invention has the following beneficial effects:
[0016] 1. The sluice pump station, through the sluice structure, is provided with a cement soil backfill layer, a stone layer, a first cushion layer and a second cushion layer inside the concrete when erecting the downstream wall, so that the stones and gravels can absorb part of the cement hydration heat, reduce the temperature inside the concrete, and thus reduce the generation of temperature cracks. At the same time, adding a proper amount of stones and gravels to the concrete can effectively reduce the amount of cement. At the same time, reducing the amount of cement can significantly reduce the project cost, thereby increasing the service life of the sluice pump station and avoiding danger to the staff;
[0017] 2. This kind of sluice pump station, through the sluice structure, through the setting of multiple high-pressure rotary jet piles, can spray cement slurry into the soil layer through the nozzle to mix with the soil, forming a continuous overlapping cement reinforcement body. This reinforcement body has high strength and can effectively share the load of the foundation under the gate to prevent foundation settlement and deformation;
[0018] 3. The sluice pump station can guide the water flow through the flow barrier wall and the setting of multiple flow barrier walls, so that the water flow can flow more smoothly in the main pump room. This helps to reduce the impact and wear of the water flow on the main pump room and extend the service life of the main pump room. BRIEF DESCRIPTION OF THE DRAWINGS
[0019] Figure 1 This is a schematic diagram of the planar layout structure of the present invention;
[0020] Figure 2 It is a schematic cross-sectional view of the sluice structure of the present invention;
[0021] Figure 3 It is a schematic diagram of the pump structure of the present invention;
[0022] Figure 4 It is a schematic diagram of the stone layer structure of the present invention.
[0023] In the figure: 1. downstream wall; 2. right wing wall; 3. left wing wall; 4. sluice structure; 41. sluice chamber; 42. winder; 43. pull rope; 44. breast wall; 45. cement soil backfill layer; 46. high-pressure jet grouting piles; 47. maintenance bridge; 48. stainless steel railings; 49. stone layer; 410. first cushion layer; 411. second cushion layer; 5. tank guard; 6. blanketing; 7. energy dissipation pool; 8. diesel engine room; 9. outlet pool; 10. first water inlet culvert; 11. second water inlet culvert; 12. traffic bridge culvert; 13. main pump room; 14. conference room; 15. central control room; 16. low-voltage distribution room; 17. high-voltage distribution room; 18. high-voltage control room; 19. lounge; 20. office; 21. pump; 22. flow separation wall. DETAILED DESCRIPTION
[0024] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0025] See also Figure 1-4A sluice pump station comprises a downstream wall 1, a right wing wall 2 is arranged on the outer wall of the downstream wall 1, a left wing wall 3 is arranged on the other side of the outer wall of the downstream wall 1, the outer wall of the pump station is formed by the downstream wall 1, the right wing wall 2 and the left wing wall 3, a sluice structure 4 is arranged inside the downstream wall 1; the sluice structure 4 comprises three lock chambers 41 and three breast walls 44, two winders 42 are arranged on the tops of the three lock chambers 41, pull ropes 43 are wound around the outer surfaces of the output rollers of the three groups of winders 42, gates are arranged at one end of the bottoms of the three groups of pull ropes 43, cement soil backfill layers 45 are laid in the concrete layers of the three breast walls 44 and the downstream wall 1, stone layers 49 are laid in the concrete layers of the three breast walls 44 and the downstream wall 1, first cushion layers 410 are laid in the concrete layers of the three breast walls 44 and the downstream wall 1, second cushion layers 411 are laid in the concrete layers of the three breast walls 44 and the downstream wall 1, and a plurality of high-pressure rotary jet piles 46 are arranged below the three breast walls 44.
[0026] See also Figure 1-3 An inspection bridge 47 is provided on one side of the outer surface of the three breast walls 44, and a stainless steel railing 48 is installed on one side of the three inspection bridges 47. A guardrail 5 is provided between the right wing wall 2 and the left wing wall 3, and a blanket 6 is provided on one side of the outer surface of the guardrail 5. An energy dissipation pool 7 is provided inside the downstream wall 1, and a diesel engine room 8 is provided on the left side of the energy dissipation pool 7. An outlet pool 9 is provided below the diesel engine room 8, and a first water inlet culvert 10 is provided inside the downstream wall 1, and a second water inlet culvert 11 is provided on one side of the outer surface of the first water inlet culvert 10. A traffic bridge culvert 12 is provided between the first water inlet culvert 10 and the second water inlet culvert 11, and a main pump room 13 is provided at one end of the traffic bridge culvert 12. Three pumps 21 are provided inside the main pump room 13, and a plurality of flow separation walls 22 are provided below the main pump room 13.
[0027] The staff can be prevented from falling by the provision of the stainless steel railing 48. The kinetic energy of the water flow can be effectively reduced by the stilling basin 7, and this function enables the water flow to flow out smoothly when passing through the breast wall 44, rather than impacting the river bank or sluice facilities at high speed.
[0028] See also Figure 1 A conference room 14 is arranged inside the downstream wall 1, and a central control room 15 is arranged on one side of the conference room 14. A low-voltage distribution room 16 is arranged inside the downstream wall 1, and a high-voltage distribution room 17 is arranged on one side of the low-voltage distribution room 16. A high-voltage control room 18 is arranged inside the downstream wall 1, and a lounge 19 is arranged on one side of the high-voltage control room 18, and an office 20 is arranged above the lounge 19.
[0029] Through the independent settings of conference room 14, central control room 15, low-voltage distribution room 16, high-voltage distribution room 17, high-voltage control room 18, lounge 19 and office 20, many benefits such as safety, professionalism, efficiency, comfort and management efficiency are improved. These independent settings not only meet the needs of sluice pump station operation, but also provide strong guarantee for its long-term stable operation.
[0030] Working principle: when a sluice pump station is used, when erecting the downstream wall 1, a cement soil backfill layer 45, a stone layer 49, a first cushion layer 410 and a second cushion layer 411 are arranged inside the concrete, so that the stones and gravels can absorb part of the cement hydration heat, reduce the temperature inside the concrete, and thus reduce the generation of temperature cracks. At the same time, adding an appropriate amount of stones and gravels to the concrete can effectively reduce the amount of cement. At the same time, reducing the amount of cement can significantly reduce the project cost, thereby increasing the service life of the sluice pump station and avoiding danger to the staff. At the same time, through the arrangement of multiple high-pressure rotary jet piles 46, cement slurry can be sprayed into the soil layer through the nozzle and mixed with the soil to form a continuous overlapped cement reinforcement body. This reinforcement body has high strength and can effectively share the load of the foundation under the gate to prevent the foundation from settling and deformation. Finally, through the arrangement of multiple flow separation walls 22, the water flow can be guided to flow more smoothly in the main pump room 13. This helps to reduce the impact and wear of the water flow on the main pump room 13 and extend the service life of the main pump room 13.
[0031] It should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device.
[0032] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. A sluice pump station, comprising a downstream wall (1), characterized in that: The outer wall of the downstream wall (1) is provided with a right wing wall (2), and the other side of the outer wall of the downstream wall (1) is provided with a left wing wall (3). The outer wall of the pump station is formed by the downstream wall (1), the right wing wall (2), and the left wing wall (3), and a sluice structure (4) is provided inside the downstream wall (1); The sluice structure (4) comprises three sluice chambers (41) and three breast walls (44); two winders (42) are arranged on the top of the three sluice chambers (41); the outer surfaces of the output rollers of the three groups of winders (42) are wound with pull ropes (43); a gate is arranged at one end of the bottom of the three groups of pull ropes (43); a cement soil backfill layer (45) is laid in the concrete layer between the three breast walls (44) and the downstream wall (1); a stone layer (49) is laid in the concrete layer between the three breast walls (44) and the downstream wall (1); a first cushion layer (410) is laid in the concrete layer between the three breast walls (44) and the downstream wall (1); a second cushion layer (411) is laid in the concrete layer between the three breast walls (44) and the downstream wall (1); and a plurality of high-pressure jet grouting piles (46) are arranged below the three breast walls (44).
2. A sluice pump station according to claim 1, characterized in that: An inspection bridge (47) is provided on one side of the outer surface of the three breast walls (44), and a stainless steel railing (48) is installed on one side of the three inspection bridges (47).
3. A sluice pump station according to claim 1, characterized in that: A guardrail (5) is arranged between the right wing wall (2) and the left wing wall (3), and a blanket (6) is arranged on one side of the outer surface of the guardrail (5).
4. A sluice pump station according to claim 1, characterized in that: An energy dissipation pool (7) is arranged inside the downstream wall (1), and a diesel engine room (8) is arranged on the left side of the energy dissipation pool (7).
5. A sluice pump station according to claim 4, characterized in that: A water outlet pool (9) is arranged below the diesel engine room (8), a first water inlet culvert (10) is arranged inside the downstream wall (1), and a second water inlet culvert (11) is arranged on one side of the outer surface of the first water inlet culvert (10).
6. A sluice pump station according to claim 5, characterized in that: A traffic bridge culvert (12) is arranged between the first water inlet box culvert (10) and the second water inlet box culvert (11), and a main pump room (13) is arranged at one end of the traffic bridge culvert (12).
7. A sluice pump station according to claim 1, characterized in that: A conference room (14) is arranged inside the downstream wall (1), and a central control room (15) is arranged on one side of the conference room (14).
8. A sluice pump station according to claim 1, characterized in that: A low-voltage distribution room (16) is arranged inside the downstream wall (1), and a high-voltage distribution room (17) is arranged on one side of the low-voltage distribution room (16).
9. A sluice pump station according to claim 1, characterized in that: A high-pressure control room (18) is arranged inside the downstream wall (1), a lounge (19) is arranged on one side of the high-pressure control room (18), and an office (20) is arranged above the lounge (19).
10. A sluice pump station according to claim 6, characterized in that: Three pumps (21) are arranged inside the main pump room (13), and a plurality of flow separation walls (22) are arranged below the main pump room (13).