Anti-toppling scaffold for bridge road and building construction and construction method

By designing an anti-tilt scaffolding including an anti-tilt center of gravity adjustment component, an adjustable height-adjustable standing board and guardrail assembly, and a pressure-bearing component, the defects in the anti-tilt mechanism in the prior art are solved, the guardrail and standing board height cannot be adjusted quickly, and the base takes into account both movement convenience and support stability, and higher stability, safety and construction efficiency are achieved.

CN119571994APending Publication Date: 2025-03-07陕西建工集团股份有限公司 +1
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202510002674.3
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2025-01-02
Publication Date
2025-03-07

AI Technical Summary

Technical Problem

The existing anti-tilt scaffolding has unreasonable anti-tilt mechanisms in design, and the height of the guardrail and standing plate cannot be adjusted quickly. The base has shortcomings in terms of both movement convenience and support stability.

Method used

An anti-tilt scaffolding including columns, guardrail assembly, standing plate assembly, roof plate, bottom plate, anti-tilt center of gravity adjustment assembly and pressure bearing assembly is designed. The anti-tilt center of gravity adjustment assembly adjusts the scaffolding center of gravity in real time, the height of the standing plate assembly and guardrail assembly is adjustable, and the pressure bearing assembly provides stable support.

Benefits of technology

It improves the stability and safety of the scaffolding, meets the needs of workers of different heights, enhances the pressure bearing capacity of the base plate, avoids deformation of the base plate, and improves construction efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119571994A_ABST
    Figure CN119571994A_ABST
Patent Text Reader

Abstract

The invention belongs to the technical field of building construction, and particularly relates to an anti-toppling scaffold for bridge road and building construction and a construction method.The anti-toppling scaffold comprises four stand columns, a protective fence assembly, a standing plate assembly, a top plate, a bottom plate, an anti-toppling gravity center adjusting assembly and a pressure bearing assembly; a protective fence assembly and a standing plate assembly are jointly installed at the top ends of the four stand columns, a top plate and a bottom plate are jointly installed at the positions, close to the top ends and the bottom ends, of the four stand columns respectively, a plurality of anti-toppling gravity center adjusting assemblies are installed between the top plate and the bottom plate, and a pressure bearing assembly is jointly installed at the positions, located below the bottom plate, of the four stand columns. The anti-toppling gravity center adjusting assembly is reasonable in design, the linear guide rail pair is used for driving the hanging plate to linearly move, the limiting wheel at the bottom end of the hanging plate slides and moves in the balancing weight, the lug plate at the bottom end of the balancing weight rotates with the axis of the hinge shaft of the lug seat as the rotating center line, and the gravity center is adjusted through rotation of the balancing weight.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of building construction, and in particular relates to an anti-dumping scaffold for bridge, road and building construction and a construction method. Background Art

[0002] Anti-dumping scaffolding plays a vital role in bridge, road and building construction. Its main functions are reflected in the following aspects: 1) Providing stable support: The construction of bridges and roads often involves high-altitude operations, and a stable support structure is required to ensure the safe construction. The anti-dumping scaffolding provides a stable working platform for construction workers through its sturdy structure and connection method, effectively preventing the risk of scaffolding collapse caused by construction vibration, wind and other factors. 2) Ensure construction safety: In bridge and road construction, the safety of workers is of vital importance. The anti-dumping scaffolding effectively prevents the risk of workers falling from heights through its design, such as adding guardrails and anti-slip devices. At the same time, it can also provide a certain amount of buffering and support when workers fall, reducing the degree of injury. 3) Improve construction efficiency: The construction of anti-dumping scaffolding provides construction workers with a more convenient and efficient working environment. Workers can carry out various construction operations on the scaffolding, such as installing formwork, pouring concrete, etc., without frequent movement or adjustment of positions, thereby greatly improving construction efficiency. 4) Prevent scaffolding from tipping over: Especially in bridge construction, due to the high height of the scaffolding, once it tips over, it will pose a great threat to the construction workers and on-site equipment. Anti-tipping scaffolding effectively improves the overall stability of the scaffolding by adding anti-tipping devices and strengthening connections, and prevents the risk of the scaffolding tipping over due to external forces.

[0003] The patent specification with the publication number CN116816054B discloses an anti-dumping scaffold and construction method for bridge, road and building construction, the scaffold includes two supporting frames and a manned frame, the manned frame is fixedly mounted on the top end of the two supporting frames, a guardrail is fixedly mounted on the top end of the manned frame, three standing boards are arranged inside the manned frame, and a limit frame used in conjunction with the three standing boards is arranged inside the manned frame. The present invention is provided with an anti-dumping mechanism, which can not only adaptively adjust the center of gravity of the scaffold according to the combat position of the workers during the use of the scaffold, ensure the stability of the scaffold, and improve the safety of the use of the scaffold, but also eliminate the height difference between the standing boards during the use of the scaffold, and prevent the workers from being tripped by the height difference between the standing boards when moving on the scaffold.

[0004] This anti-dumping scaffolding was found to have some shortcomings during use. First, the design of its anti-dumping mechanism was not reasonable enough, and the anti-dumping effect needed to be improved. Second, the height of its guardrail and the height of the standing board could not be quickly adjusted according to actual needs. Third, its base could not take into account both the convenience of movement and the stability of support. Therefore, it needs to be optimized and improved. Summary of the invention

[0005] The purpose of the present invention is to overcome the above-mentioned problems existing in the traditional technology and to provide an anti-dumping scaffold and a construction method for bridge, road and building construction.

[0006] In order to achieve the above technical objectives and the above technical effects, the present invention is implemented through the following technical solutions:

[0007] The present invention provides an anti-dumping scaffold for bridge, road and building construction, comprising columns, guardrail components, standing board components, top plates, bottom plates, anti-dumping center of gravity adjustment components and pressure-bearing components. There are four columns in total, and the top ends of the four columns are commonly installed with guardrail components and standing board components, the four columns are commonly installed with top plates near the top ends, and the four columns are commonly installed with bottom plates near the bottom ends, a plurality of anti-dumping center of gravity adjustment components are installed between the top plates and the bottom plates, and the four columns are commonly installed with pressure-bearing components at locations below the bottom plates.

[0008] Furthermore, in the above-mentioned anti-dumping scaffolding for bridge, road and building construction, the guardrail assembly includes an integrated guardrail and four first vertical push rods arranged at the four corners of its lower end, and the top end of the column is provided with an installation groove inwardly for facilitating the installation of the first vertical push rods.

[0009] Furthermore, in the above-mentioned anti-dumping scaffolding for bridge, road and building construction, the standing plate assembly includes a standing plate, a second vertical push rod and a first beam plate, the second vertical push rod and the first beam plate are each provided with two, the two ends of each of the first beam plates are fixed on two columns on the same side, the second vertical push rod is installed on the upper side of the corresponding first beam plate, the movable ends of the two second vertical push rods jointly support the standing plate, several rows of pressure detection points with built-in pressure sensors are provided on the standing plate, and through holes are opened at the four corners of the standing plate to facilitate the passage of the movable rod in the first vertical push rod.

[0010] Furthermore, in the above-mentioned anti-dumping scaffolding for bridge, road and building construction, the anti-dumping center of gravity adjustment assembly includes a counterweight block, an ear plate, an ear seat, a linear guide pair, a suspension plate and a limiting wheel, the ear seat is fixed on the upper side of the base plate, the bottom end of the counterweight block is equipped with an ear plate rotatably connected to the ear seat, a limiting groove is provided on the side of the counterweight block, the slide rail of the linear guide pair is fixed on the lower side of the top plate, a suspension plate is fixed on the outer side of the slider of the linear guide pair, and the bottom end of the suspension plate is equipped with a limiting wheel that is slidably limited in the limiting groove.

[0011] Furthermore, in the above-mentioned anti-dumping scaffolding for bridge, road and building construction, the number of the anti-dumping center of gravity adjustment components is equal to the number of rows of pressure detection points on the standing plate.

[0012] Furthermore, in the above-mentioned anti-dumping scaffold for bridge, road and building construction, the cross-section of the limiting groove is a T-shaped structure that is wide inside and narrow outside, and the upper end of the limiting groove extends to the upper end surface of the counterweight block where it is located.

[0013] Furthermore, in the above-mentioned anti-dumping scaffolding for bridge, road and building construction, the pressure-bearing assembly includes an arched pressure-bearing plate, a second beam plate and fasteners, there are two second beam plates in total, both ends of each second beam plate are fixed on two columns on the same side, and a number of arched pressure-bearing plates are installed side by side between the two second beam plates through fasteners, and the positions of the arched pressure plates correspond one-to-one to the positions of the anti-dumping center of gravity adjustment assembly.

[0014] Furthermore, in the above-mentioned anti-dumping scaffolding for bridge, road and building construction, the arched pressure-bearing plate is replaced by a leaf spring.

[0015] Furthermore, the anti-dumping scaffold for bridge, road and building construction also includes a controller, which is respectively connected to each of the first vertical push rods, the second vertical push rods, the pressure sensor, and the linear guide pair.

[0016] The present invention also provides a construction method using an anti-dumping scaffold for bridge, road and building construction, comprising the following steps:

[0017] S1. Before construction, workers use the auxiliary ladder on the construction site to climb up the scaffolding; according to needs, the height of the standing board in the standing board assembly and the integrated guardrail in the guardrail assembly are adjusted, and the workers stand on the standing board to carry out construction;

[0018] S2. When in use, the scaffolding uses the anti-dumping center of gravity adjustment component to adjust the center of gravity of the scaffolding in real time according to the standing position of the workers to ensure the stability of the scaffolding during use.

[0019] The beneficial effects of the present invention are:

[0020] 1. The anti-dumping center of gravity adjustment component of the present invention is reasonably designed, and is mainly composed of a counterweight, an ear plate, an ear seat, a linear guide pair, a suspension plate and a limiting wheel. The linear guide pair is used to drive the suspension plate to move linearly, and the limiting wheel at the bottom end of the suspension plate slides and moves in the counterweight accordingly. The ear plate at the bottom end of the counterweight rotates with the axis of the hinge shaft of the ear seat as the rotation center line, and the rotation of the counterweight is used to achieve the adjustment of the center of gravity.

[0021] 2. The standing board assembly design in the present invention is mainly composed of a standing board, a second vertical push rod and a first beam plate. The first beam plate is used to provide support, and the second vertical push rod is used to drive the standing board to rise and fall, so as to better meet construction needs.

[0022] 3. The guardrail assembly of the present invention is reasonably designed. It is mainly composed of an integrated guardrail and four first vertical push rods arranged at the four corners of its lower end. The first vertical push rods are used to drive the integrated guardrail to rise and fall, thereby meeting the protection needs of workers of different heights and the need for height adjustment of the guardrail brought about by the height adjustment of the standing board.

[0023] 4. The present invention also adds a pressure-bearing component, which is mainly composed of an arched pressure-bearing plate, a second beam plate and fasteners. The second beam plate is used to provide support, and the arched pressure-bearing plate is used to provide a pressure-bearing function for the bottom plate to avoid deformation of the bottom plate.

[0024] Of course, any product implementing the present invention does not necessarily need to achieve all of the above advantages at the same time. BRIEF DESCRIPTION OF THE DRAWINGS

[0025] In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the accompanying drawings required for describing the embodiments will be briefly introduced below. Obviously, the accompanying drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other accompanying drawings can be obtained based on these accompanying drawings without paying creative work.

[0026] Figure 1 It is a schematic diagram of the three-dimensional structure of the anti-dumping scaffold in the present invention;

[0027] Figure 2 It is a schematic diagram of the main structure of the anti-dumping scaffold in the present invention;

[0028] Figure 3 It is a structural schematic diagram of the column, top plate, bottom plate and pressure-bearing components in the present invention;

[0029] Figure 4 It is a structural schematic diagram of the guardrail assembly in the present invention;

[0030] Figure 5 It is a structural schematic diagram of the standing board assembly in the present invention;

[0031] Figure 6 It is a schematic diagram of the arrangement of the anti-dumping center of gravity adjustment component in the present invention;

[0032] Figure 7 It is a schematic diagram of the three-dimensional structure of the anti-dumping center of gravity adjustment component in the present invention;

[0033] Figure 8 It is a schematic diagram of a part of the structure of the anti-dumping center of gravity adjustment component of the present invention;

[0034] Fig. 9 It is a schematic diagram of another part of the structure of the anti-dumping center of gravity adjustment component in the present invention;

[0035] Fig.10 It is a side view structural schematic diagram of the anti-dumping center of gravity adjustment assembly in the present invention;

[0036] In the accompanying drawings, the reference numerals of the various components are as follows:

[0037] 1-column, 2-guardrail assembly, 201-integrated guardrail, 202-first vertical push rod, 3-standing plate assembly, 301-standing plate, 302-second vertical push rod, 303-first beam plate, 304-pressure detection point, 305-perforation, 4-top plate, 5-bottom plate, 6-anti-dumping center of gravity adjustment assembly, 601-counterweight block, 602-ear plate, 603-ear seat, 604-limiting groove, 605-linear guide pair, 606-suspension plate, 607-limiting wheel, 7-pressure-bearing assembly, 701-arched pressure-bearing plate, 702-second beam plate, 703-fastener. DETAILED DESCRIPTION

[0038] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0039] Embodiment 1

[0040] like Figure 1-Figure 3 As shown, this embodiment provides an anti-dumping scaffold for bridge, road and building construction, including a column 1, a guardrail assembly 2, a standing board assembly 3, a top plate 4, a bottom plate 5, an anti-dumping center of gravity adjustment assembly 6 and a pressure-bearing assembly 7. There are four columns 1, and the tops of the four columns 1 are jointly installed with the guardrail assembly 2 and the standing board assembly 3, and the four columns 1 are jointly installed with the top plate 4 near the top, and the four columns 1 are jointly installed with the bottom plate 5 near the bottom. A number of anti-dumping center of gravity adjustment assemblies 6 are installed between the top plate 4 and the bottom plate 5, and the four columns 1 are jointly installed with the pressure-bearing assembly 7 at the bottom of the bottom plate 5.

[0041] like Figure 4 As shown, the guardrail assembly 2 includes an integrated guardrail 201 and four first vertical push rods 202 arranged at the four corners of the lower end thereof, and a mounting groove is provided inwardly at the top end of the column 1 for facilitating the installation of the first vertical push rods 202 .

[0042] like Figure 5 As shown, the standing plate assembly 3 includes a standing plate 301, a second vertical push rod 302 and a first beam plate 303, two second vertical push rods 302 and two first beam plates 303 are respectively provided, and both ends of each first beam plate 303 are fixed on two columns 1 on the same side, and the second vertical push rod 302 is installed on the upper side of the corresponding first beam plate 303, and the movable ends of the two second vertical push rods 302 jointly support the standing plate 301, and a plurality of rows of pressure detection points 304 with built-in pressure sensors are provided on the standing plate 301, and through holes 305 for the movable rods in the first vertical push rods 302 to pass through are opened at the four corners of the standing plate 301.

[0043] like Figure 3 As shown, the pressure-bearing assembly 7 includes an arched pressure-bearing plate 701, a second beam plate 702 and a fastener 703. There are two second beam plates 702, and both ends of each second beam plate 702 are fixed on two columns 1 on the same side. A plurality of arched pressure-bearing plates 701 are installed side by side between the two second beam plates 702 through fasteners 703. The positions of the arched pressure plates 701 correspond one-to-one to the positions of the anti-dumping center of gravity adjustment assembly 6.

[0044] The specific application of this embodiment is as follows: the standing board assembly 3 is reasonably designed, and it is mainly composed of the standing board 301, the second vertical push rod 302 and the first beam 303. The first beam 303 is used to provide support, and the second vertical push rod 302 is used to drive the standing board 301 to rise and fall, so as to better meet the construction needs. The guardrail assembly 2 is reasonably designed, and it is mainly composed of an integrated guardrail 201 and four first vertical push rods 202 arranged at the four corners of its lower end. The first vertical push rod 202 is used to drive the integrated guardrail 201 to rise and fall, so as to meet the protection needs of workers of different heights and the height adjustment needs of the guardrail brought about by the height adjustment of the standing board. This embodiment is additionally provided with a pressure-bearing assembly 7, which is mainly composed of an arched pressure-bearing plate 701, a second beam 702 and a fastener 703. The second beam is used to provide support, and the arched pressure-bearing plate is used to provide a pressure-bearing function for the bottom plate to prevent deformation of the bottom plate.

[0045] Embodiment 2

[0046] like Figure 1-Figure 3As shown, this embodiment provides an anti-dumping scaffold for bridge, road and building construction, including a column 1, a guardrail assembly 2, a standing board assembly 3, a top plate 4, a bottom plate 5, an anti-dumping center of gravity adjustment assembly 6 and a pressure-bearing assembly 7. There are four columns 1, and the tops of the four columns 1 are jointly installed with the guardrail assembly 2 and the standing board assembly 3, and the four columns 1 are jointly installed with the top plate 4 near the top, and the four columns 1 are jointly installed with the bottom plate 5 near the bottom. A number of anti-dumping center of gravity adjustment assemblies 6 are installed between the top plate 4 and the bottom plate 5, and the four columns 1 are jointly installed with the pressure-bearing assembly 7 at the bottom of the bottom plate 5.

[0047] like Figure 4 As shown, the guardrail assembly 2 includes an integrated guardrail 201 and four first vertical push rods 202 arranged at the four corners of the lower end thereof, and a mounting groove is provided inwardly at the top end of the column 1 for facilitating the installation of the first vertical push rods 202 .

[0048] like Figure 5 As shown, the standing plate assembly 3 includes a standing plate 301, a second vertical push rod 302 and a first beam plate 303, two second vertical push rods 302 and two first beam plates 303 are respectively provided, and both ends of each first beam plate 303 are fixed on two columns 1 on the same side, and the second vertical push rod 302 is installed on the upper side of the corresponding first beam plate 303, and the movable ends of the two second vertical push rods 302 jointly support the standing plate 301, and a plurality of rows of pressure detection points 304 with built-in pressure sensors are provided on the standing plate 301, and through holes 305 for the movable rods in the first vertical push rods 302 to pass through are opened at the four corners of the standing plate 301.

[0049] like Figure 3 As shown, the pressure-bearing assembly 7 includes a leaf spring, a second beam plate 702 and a fastener 703. There are two second beam plates 702. Both ends of each second beam plate 702 are fixed on two columns 1 on the same side. A number of leaf springs are installed side by side between the two second beam plates 702 through the fastener 703. The positions of the leaf springs correspond one-to-one to the positions of the anti-dumping center of gravity adjustment assembly 6.

[0050] The specific application of this embodiment is: the leaf spring absorbs and disperses impact energy based on elastic deformation and provides stable suspension support through the synergistic effect of a multi-leaf structure.

[0051] Embodiment 3

[0052] like Figure 1-Figure 3As shown, this embodiment provides an anti-dumping scaffold for bridge, road and building construction, including a column 1, a guardrail assembly 2, a standing board assembly 3, a top plate 4, a bottom plate 5, an anti-dumping center of gravity adjustment assembly 6 and a pressure-bearing assembly 7. There are four columns 1, and the tops of the four columns 1 are jointly installed with the guardrail assembly 2 and the standing board assembly 3, and the four columns 1 are jointly installed with the top plate 4 near the top, and the four columns 1 are jointly installed with the bottom plate 5 near the bottom. A number of anti-dumping center of gravity adjustment assemblies 6 are installed between the top plate 4 and the bottom plate 5, and the four columns 1 are jointly installed with the pressure-bearing assembly 7 at the bottom of the bottom plate 5.

[0053] like Figure 4 As shown, the guardrail assembly 2 includes an integrated guardrail 201 and four first vertical push rods 202 arranged at the four corners of the lower end thereof, and a mounting groove is provided inwardly at the top end of the column 1 for facilitating the installation of the first vertical push rods 202 .

[0054] like Figure 5 As shown, the standing plate assembly 3 includes a standing plate 301, a second vertical push rod 302 and a first beam plate 303, two second vertical push rods 302 and two first beam plates 303 are respectively provided, and both ends of each first beam plate 303 are fixed on two columns 1 on the same side, and the second vertical push rod 302 is installed on the upper side of the corresponding first beam plate 303, and the movable ends of the two second vertical push rods 302 jointly support the standing plate 301, and a plurality of rows of pressure detection points 304 with built-in pressure sensors are provided on the standing plate 301, and through holes 305 for the movable rods in the first vertical push rods 302 to pass through are opened at the four corners of the standing plate 301.

[0055] like Figure 6-Figure 10 As shown, the anti-dumping center of gravity adjustment assembly 6 includes a counterweight 601, an ear plate 602, an ear seat 603, a linear guide pair 605, a suspension plate 606 and a limiting wheel 607. The ear seat 603 is fixed to the upper side of the bottom plate 5. The bottom end of the counterweight 601 is equipped with an ear plate 602 rotatably connected to the ear seat 603. The side of the counterweight 601 is provided with a limiting groove 604. The slide rail of the linear guide pair 605 is fixed to the lower side of the top plate 4. A suspension plate 606 is fixed to the outer side of the slider of the linear guide pair 605. The bottom end of the suspension plate 606 is equipped with a limiting wheel 607 that is slidably limited in the limiting groove 604.

[0056] In this embodiment, the number of the anti-dumping center of gravity adjustment components 6 is equal to the number of rows of the pressure detection points 304 on the standing board 301 .

[0057] In this embodiment, the cross section of the limiting groove 604 is a T-shaped structure that is wide inside and narrow outside, and the upper end of the limiting groove 604 extends to the upper end surface of the counterweight block 601 where it is located.

[0058] In this embodiment, a controller is also included, and the controller is connected to each of the first vertical push rods 202, the second vertical push rods 302, the pressure sensor, and the linear guide rail pair 605 respectively.

[0059] The specific application of this embodiment is: the anti-dumping center of gravity adjustment component 6 is reasonably designed, and it is mainly composed of a counterweight block 601, an ear plate 602, an ear seat 603, a linear guide pair 605, a suspension plate 606 and a limiting wheel 607. The linear guide pair 605 is used to drive the suspension plate 606 to move linearly, and the limiting wheel 607 at the bottom end of the suspension plate 606 slides and moves in the counterweight block 601 accordingly. The ear plate 602 at the bottom end of the counterweight block 601 rotates with the axis of the hinge shaft of the ear seat 603 as the rotation center line, and the rotation of the counterweight block 601 is used to achieve the adjustment of the center of gravity.

[0060] Embodiment 4

[0061] This embodiment also provides a construction method using the anti-dumping scaffold for bridge, road and building construction in the third embodiment, comprising the following steps:

[0062] S1. Before construction, workers use the auxiliary ladder on the construction site to climb up the scaffolding; according to needs, the height of the standing board in the standing board assembly and the integrated guardrail in the guardrail assembly are adjusted, and the workers stand on the standing board to carry out construction;

[0063] S2: When in use, the scaffolding uses the anti-dumping center of gravity adjustment component 6 to adjust the center of gravity of the scaffolding in real time according to the standing position of the worker to ensure the stability of the scaffolding during use. The specific adjustment method is as follows:

[0064] There are five rows of pressure detection points 304, each row has 11 points, and the corresponding relationship between the marks and the adjustment of the anti-dumping center of gravity adjustment component 6 is shown in Table 1 below:

[0065] Table 1

[0066]

[0067] The midpoint of the linear guide pair 605 is recorded as the zero point, the displacement to the left is recorded as "+", and the displacement to the right is recorded as "-". The travel of the slider in the linear guide pair 605 to the left or right is divided into 5 sections. "A+1" represents that the slider in the linear guide pair 605 of the first row of anti-dumping center of gravity adjustment components 6 is displaced to the left by 1 section, "B-2" represents that the slider in the linear guide pair 605 of the second row of anti-dumping center of gravity adjustment components 6 is displaced to the right by 2 sections, and "C0" represents that the linear guide pair 605 of the third row of anti-dumping center of gravity adjustment components 6 keeps the slider at the midpoint.

[0068] When a worker stands, each sole of the foot will touch 1-2 standing points. When two standing points are touched at the same time, the average of the displacement segments of the two is taken as the displacement segment number.

[0069] The preferred embodiments of the present invention disclosed above are only used to help explain the present invention. The preferred embodiments do not describe all the details in detail, nor do they limit the invention to specific implementation methods. Obviously, many modifications and changes can be made according to the content of this specification. This specification selects and specifically describes these embodiments in order to better explain the principles and practical applications of the present invention, so that those skilled in the art can understand and use the present invention well. The present invention is limited only by the claims and their full scope and equivalents.

Claims

1. An anti-dumping scaffold for bridge, road and building construction, characterized in that: It includes columns, guardrail components, standing board components, top plates, bottom plates, anti-dumping center of gravity adjustment components and pressure-bearing components. There are four columns in total. The top ends of the four columns are jointly installed with guardrail components and standing board components. The four columns are jointly installed with top plates near the top ends. The four columns are jointly installed with bottom plates near the bottom ends. Several anti-dumping center of gravity adjustment components are installed between the top plates and the bottom plates. The four columns are jointly installed with pressure-bearing components at the bottom ends of the bottom plates.

2. The anti-dumping scaffold for bridge, road and building construction according to claim 1, characterized in that: The guardrail assembly comprises an integrated guardrail and four first vertical push rods arranged at the four corners of the lower end thereof, and the top end of the column is provided with an installation groove inwardly for facilitating the installation of the first vertical push rods.

3. The anti-dumping scaffold for bridge, road and building construction according to claim 2 is characterized in that: The standing plate assembly includes a standing plate, a second vertical push rod and a first beam plate, the second vertical push rod and the first beam plate are each provided with two, the two ends of each of the first beam plates are fixed on two columns on the same side, the second vertical push rod is installed on the upper side of the corresponding first beam plate, the movable ends of the two second vertical push rods jointly support the standing plate, several rows of pressure detection points with built-in pressure sensors are provided on the standing plate, and through holes are opened at the four corners of the standing plate to facilitate the passage of the movable rod in the first vertical push rod.

4. The anti-dumping scaffold for bridge, road and building construction according to claim 3, characterized in that: The anti-dumping center of gravity adjustment assembly includes a counterweight, an ear plate, an ear seat, a linear guide pair, a suspension plate and a limiting wheel. The ear seat is fixed to the upper side of the base plate, the bottom end of the counterweight is equipped with an ear plate rotatably connected to the ear seat, a limiting groove is provided on the side of the counterweight, the slide rail of the linear guide pair is fixed to the lower side of the top plate, a suspension plate is fixed to the outer side of the slider of the linear guide pair, and the bottom end of the suspension plate is equipped with a limiting wheel that is slidably limited in the limiting groove.

5. The anti-dumping scaffold for bridge, road and building construction according to claim 4, characterized in that: The number of the anti-dumping center of gravity adjustment components is equal to the number of rows of pressure detection points on the standing board.

6. The anti-dumping scaffold for bridge, road and building construction according to claim 5, characterized in that: The cross section of the limiting groove is a T-shaped structure that is wide inside and narrow outside, and the upper end of the limiting groove extends to the upper end surface of the counterweight block where it is located.

7. The anti-dumping scaffold for bridge, road and building construction according to claim 6, characterized in that: The pressure-bearing assembly includes an arched pressure-bearing plate, a second beam plate and fasteners. There are two second beam plates in total, and both ends of each second beam plate are fixed on two columns on the same side. Several arched pressure-bearing plates are installed side by side between the two second beam plates through fasteners, and the positions of the arched pressure plates correspond one-to-one to the positions of the anti-dumping center of gravity adjustment components.

8. The anti-dumping scaffold for bridge, road and building construction according to claim 7, characterized in that: The arched pressure-bearing plate is replaced by a leaf spring.

9. The anti-dumping scaffold for bridge, road and building construction according to claim 8, characterized in that: It also includes a controller, which is respectively connected to each of the first vertical push rods, the second vertical push rods, the pressure sensor, and the linear guide pair.

10. A construction method using the anti-dumping scaffold for bridge, road and building construction according to claim 9, characterized in that: The steps include: S1. Before construction, workers use the auxiliary ladder on the construction site to climb up the scaffolding; according to needs, the height of the standing board in the standing board assembly and the integrated guardrail in the guardrail assembly are adjusted, and the workers stand on the standing board to carry out construction; S2. When in use, the scaffolding uses the anti-dumping center of gravity adjustment component to adjust the center of gravity of the scaffolding in real time according to the standing position of the workers to ensure the stability of the scaffolding during use.