Formwork lifting and intercepting method for stair flight adaptive steel bars

By pre-assembling the stair formwork and steel mesh on the ground, and using lifting devices to lift and fix the fixing, combined with the automatic fall off of the movable barrier plate, the existing stair construction methods are solved, and an efficient and safe construction process is achieved.

CN119593583AActive Publication Date: 2025-03-11CHINA CONSTR SECOND ENG BUREAU LTD
View PDF 6 Cites 0 Cited by

Patent Information

Application Number
CN202510143596.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2025-02-10
Publication Date
2025-03-11
Estimated Expiration
2045-02-10

AI Technical Summary

Technical Problem

The existing stair construction methods are inefficient, inconvenient to operate and high safety risks, and there are cumbersome processes of secondary pouring and multiple grouting and maintenance.

Method used

The stair formwork and steel mesh are pre-assembled on the ground and the assembled stair structure is lifted to the target position for fixing, and a single grouting molding is achieved. The movable barrier plate automatically falls off through the electromechanical structure to ensure the release of stress after the concrete solidifies.

Benefits of technology

It reduces the time for construction workers to work at high altitudes, reduces the risk of safety accidents, improves construction efficiency, shortens construction cycles, and simplifies construction processes.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119593583A_ABST
    Figure CN119593583A_ABST
Patent Text Reader

Abstract

A formwork lifting and intercepting method for adaptive steel bars of stair flights relates to the technical field of building construction and comprises the following steps: erecting a scaffold below a middle platform construction position, and building a middle platform at the top of the scaffold; the first stair and the second stair are assembled on the ground below the construction positions of the first stair and the second stair; a movable barrier plate is arranged at the lower one-third position of the second stair, and a release agent is smeared on the movable barrier plate; lifting devices are erected at the two ends of the construction positions of the first stairway and the second stairway, and construction waste in the formwork is removed; a lifting device is used for lifting the assembled first stair and second stair to a construction position for fixing; grouting cement mortar from bottom to top by using grouting equipment, and waiting for solidification; and after solidification is completed, the movable barrier plates are automatically separated, and the problems that in the prior art, the efficiency of a secondary pouring mode is low, the whole stair building process is carried out in the air, the working space is limited, and the operation difficulty is large are solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of building construction, and in particular to a method for lifting and intercepting a template of a staircase step adapted to steel bars. Background Art

[0002] As an important component of vertical transportation between floors in a building, the history of stairs can be traced back to the image of a heavy house on bronze ware during the Warring States Period in China. In Italy from the 15th to the 16th century, indoor stairs gradually moved from closed spaces to open spaces, becoming an important part of architecture. In modern buildings, stairs are not only used for transportation between floors, but also serve as an important escape route for fire in high-rise buildings.

[0003] In the existing cast-in-place staircase construction, it is usually necessary to first erect an overall scaffolding, and then successively erect the main keel, lay the formwork, tie the steel mesh, etc. In order to ensure the construction quality, construction joints and wooden beams are set up according to the design requirements. When pouring concrete, a second pouring is carried out with the construction joint as the boundary. Before the second pouring, the construction waste in the rear half of the formwork needs to be cleaned, and the pouring is continued after the construction joint is closed until the wooden beams are removed and the subsequent sealing work is completed.

[0004] However, this secondary pouring construction method is not only inefficient, but also has many operational inconveniences. Since the entire stair construction process is carried out in mid-air, the construction workers' working space is limited, the operation is difficult, and the safety hazards are relatively large. Therefore, it is necessary to explore a more efficient and safe cast-in-place stair formwork construction method. Summary of the invention

[0005] The embodiment of the present invention provides a method for lifting and intercepting a template adapted to steel bars of a staircase step, by assembling the template of the stairs and tying the steel mesh on the ground in advance, and cleaning the assembled stairs to avoid the influence of construction waste on the structural strength during the subsequent grouting process, and further setting up a lifting device between the ground and the middle platform and the roof, and lifting the assembled stairs to the target setting position for fixing, so as to perform a grouting and forming, and the movable barrier plate can automatically fall off the interception plate after a certain period of time through a timer, so as to ensure the stress release after the concrete is solidified and formed, and finally the template can be removed, which solves the problem that the existing staircase construction process is complicated and difficult to operate.

[0006] A method for lifting and intercepting a template for staircase steps adapted to steel bars, comprising the following steps: S1, prepare the construction materials for the first staircase, the middle platform and the second staircase according to the construction drawings; S2, erecting a scaffold below the construction position of the intermediate platform, and building an intermediate platform on top of the scaffold; S3, assembling the first staircase and the second staircase on the ground below the construction positions of the first staircase and the second staircase; S4, install a movable baffle plate at the lower third of the second staircase and apply a release agent to the movable baffle plate; S5, erect lifting devices at both ends of the construction sites of the first staircase and the second staircase, and clean up the construction waste in the formwork to keep the formwork clean; S6, using a lifting device to lift the assembled first staircase and second staircase to the construction site for fixing; S7, pouring cement mortar from bottom to top using grouting equipment and waiting for solidification; S8, after solidification is completed, the movable barrier plate is automatically separated, and the formwork and scaffolding can be removed.

[0007] Furthermore, the middle platform includes two platform plates spliced ​​together, with I-beams arranged around the platform plates. The bottom of the I-beams is fixed to the top of the scaffolding by bolts. The middle platform is the main load-bearing platform connecting the first staircase and the second staircase. The formwork is assembled above the middle platform, and the steel mesh is tied inside the formwork.

[0008] Furthermore, the first staircase includes a first supporting frame, which is composed of two first main purlins arranged in parallel, and a first docking plate and a second docking plate are respectively arranged at relative positions thereof. A first docking groove is opened at the top center of the first docking plate, and a second docking groove is opened at the top center of the second docking plate. A template is arranged on the top of the two first main purlins. After the template is fixed, a steel mesh is tied in the template.

[0009] Furthermore, the second staircase includes a second supporting frame, which is formed by two second main purlins arranged in parallel, and the first docking plate and the second docking plate identical to the first supporting frame are respectively arranged at relative positions thereof. The top of the second supporting frame is constructed by the same process as the first staircase, i.e., the laying of the template and the binding of the steel mesh, wherein the template is provided with a blocking seam in the lower third.

[0010] Furthermore, the movable blocking plate includes a first mounting plate, an electric telescopic rod and an intercepting plate. The first mounting plate is fixedly arranged on the side of the second staircase near the blocking seam, the electric telescopic rod is fixed on the first mounting plate, the intercepting plate is movably arranged in the opening direction of the blocking seam, a connecting arm is vertically arranged at the end of the output shaft of the electric telescopic rod, the top of the connecting arm is arranged together with the bottom of the mounting plate, a sliding rail is arranged on one side of the intercepting plate in the length direction away from the end of the electric telescopic rod, a second mounting plate is arranged at the second main keel near the sliding rail, a limiting block is arranged on the second mounting plate, and the sliding rail is slidably arranged on the limiting block.

[0011] Furthermore, a plurality of movable grooves are provided on the top of the intercepting plate, and a protrusion extending outward is provided on the bottom of the intercepting plate. When the electric telescopic rod is fully retracted, the protrusion contacts the bottom of the second staircase. At this time, the intercepting plate has no contact with the steel mesh on the inner side of the second staircase. When the electric telescopic rod is fully extended, the top of the intercepting plate is located below the barrier seam.

[0012] Furthermore, a timer is arranged on the first mounting plate, and the timer is electrically connected to the electric telescopic rod.

[0013] Furthermore, the lifting device includes a bottom fixed plate, a mounting frame and a square tube are arranged on the top of the bottom fixed plate, a top plate is arranged on the top of the square tube, a transmission assembly is arranged at the intersection of the square tube and the mounting frame, a lifting hook is arranged on the transmission assembly, and the lifting hook is used to hook the docking plates on the first support frame and the second support frame. The height of the lifting device has two different specifications, one is used to be set between the ground and the middle platform, and the other is set between the ground and the roof.

[0014] Furthermore, the transmission assembly includes a first gear fixing plate arranged at the intersection of the mounting frame and the square tube, where a first transmission gear is arranged; a second gear fixing plate is arranged at the intersection of the square tube and the top plate, where a second transmission gear is arranged; a transmission belt is arranged between the two gears; a driving motor is arranged on the mounting frame, and the output shaft of the driving motor is arranged together with the first transmission gear.

[0015] Furthermore, the lifting hook includes a slider slidably set on the square tube, a plurality of rollers are set on the inner side of the slider, the rollers are in contact with the square tube, a first butt joint tube and a second butt joint tube are symmetrically set on the outer side of the slider, the first butt joint tube is fixedly connected to the transmission belt, and a stair butt joint hook is set on the outer side of the second butt joint tube, and the stair butt joint hook is used to hook the first butt joint groove or the second butt joint groove.

[0016] The beneficial effects of the above technical solution provided by the embodiment of the present invention include at least: The present invention prefabricates the stair formwork and the steel mesh on the ground, and then reduces the time that construction workers spend working at heights by using a lifting device, thereby reducing the risk of safety accidents caused by falling from heights. In addition, the assembly on the ground can clean up the construction waste in the formwork in advance, and the grouting can be done at one time during the later grouting, which reduces the cumbersome process of multiple grouting and maintenance and improves the construction efficiency. The movable baffle plate has an electric mechanical structure to control its shedding, which further increases the efficiency of the construction. The lifting device lifts the assembled stair structure from the ground to the target position, and there is no need for manual cumbersome assembly and adjustment at high altitudes, thereby greatly shortening the construction period.

[0017] Other features and advantages of the present invention will be described in the following description, and partly become apparent from the description, or understood by practicing the present invention. The purpose and other advantages of the present invention can be realized and obtained by the structures particularly pointed out in the written description, claims, and drawings.

[0018] The technical solution of the present invention is further described in detail below through the accompanying drawings and embodiments. BRIEF DESCRIPTION OF THE DRAWINGS

[0019] The accompanying drawings are used to provide a further understanding of the present invention and constitute a part of the specification. Together with the embodiments of the present invention, they are used to explain the present invention and do not constitute a limitation of the present invention. In the accompanying drawings: Figure 1 A schematic diagram of the structure of a method for lifting and intercepting a template of a staircase step adapted to a steel bar disclosed in an embodiment of the present invention; Figure 2 for Figure 1 The enlarged view of point A in the middle; Figure 3 for Figure 1 Schematic diagram of the exploded structure of the main frame of the middle staircase; Figure 4 for Figure 3 Schematic diagram of the structure after the template is laid; Figure 5 It is a structural schematic diagram of a lifting device disclosed in an embodiment of the present invention; Figure 6 It is a structural schematic diagram of a lifting hook disclosed in an embodiment of the present invention; Figure 7 It is a schematic diagram of the structure of the transmission assembly disclosed in the embodiment of the present invention; Figure 8 It is a structural schematic diagram of the top of the lifting device disclosed in an embodiment of the present invention; Fig. 9 It is a schematic diagram of the structure of the movable baffle plate disclosed in an embodiment of the present invention.

[0020] Reference numerals: 10. First staircase; 11. First supporting frame; 1101. First main keel; 1102. First docking plate; 11021. First docking groove; 1103. Second docking plate; 11031. Second docking groove; 12. Formwork; 13. Steel mesh; 20. Intermediate platform; 21. Platform plate; 22. I-beam; 30. Scaffolding; 40. Second staircase; 41. Second supporting frame; 4101. Second main keel; 42. Blocking joint; 50. Movable blocking plate; 51. First mounting plate; 52. Electric telescopic rod; 53. Connecting arm; 54. Interceptor plate; 5401. Movable groove; 5402 , raised portion; 5403, slide rail; 55, second mounting plate; 5501, limit block; 56, timer; 60, lifting device; 61, bottom fixing plate; 62, mounting frame; 63, square tube; 64, transmission assembly; 6401, first gear fixing plate; 6402, first transmission gear; 6403, drive motor; 6404, second gear fixing plate; 6405, second transmission gear; 6406, transmission belt; 65, lifting hook; 6501, slider; 6502, roller; 6503, first butt joint pipe; 6504, second butt joint pipe; 6505, stair butt joint hook; 66, top plate. DETAILED DESCRIPTION

[0021] The exemplary embodiments of the present disclosure will be described in more detail below with reference to the accompanying drawings. Although the exemplary embodiments of the present disclosure are shown in the accompanying drawings, it should be understood that the present disclosure can be implemented in various forms and should not be limited by the embodiments set forth herein. On the contrary, these embodiments are provided to enable a more thorough understanding of the present disclosure and to fully convey the scope of the present disclosure to those skilled in the art. Example

[0022] An embodiment of the present invention provides a method for lifting and intercepting a template of a staircase step adapted to a steel bar, comprising the following steps: S1, preparing construction materials for the first staircase 10, the middle platform 20 and the second staircase 40 according to the construction drawings; S2, erecting a scaffold 30 below the construction position of the intermediate platform 20, and building the intermediate platform 20 on top of the scaffold 30; S3, assembling the first staircase 10 and the second staircase 40 on the ground below the construction positions of the first staircase 10 and the second staircase 40; S4, setting a movable blocking plate 50 at the lower third of the second staircase 40, and applying a release agent on the movable blocking plate 50; S5, erecting a lifting device 60 at both ends of the construction position of the first staircase 10 and the second staircase 40, and cleaning the construction waste in the template 12 to keep the template 12 clean; S6, using the lifting device 60 to lift the assembled first staircase 10 and second staircase 40 to the construction site for fixing; S7, pouring cement mortar from bottom to top using grouting equipment and waiting for solidification; S8, after solidification is completed, the movable blocking plate 50 is automatically separated, and the formwork 12 and the scaffold 30 can be removed.

[0023] like Figure 1 , 3 As shown in Figure 4, the middle platform 20 includes two platform plates 21 spliced ​​together, and I-beams 22 are arranged around the platform plates 21. The bottom of the I-beam 22 is fixed to the top of the scaffolding 30 by bolts. The middle platform 20 is the main load-bearing platform connecting the first staircase 10 and the second staircase 40. The formwork 12 is assembled above the middle platform 20, and the steel mesh 13 is tied inside the formwork 12.

[0024] In this embodiment, the first staircase 10 includes a first supporting frame 11, which is composed of two first main purlins 1101 arranged in parallel, and a first docking plate 1102 and a second docking plate 1103 are respectively arranged at relative positions. A first docking groove 11021 is opened at the top center of the first docking plate 1102, and a second docking groove 11031 is opened at the top center of the second docking plate 1103. A template 12 is arranged on the top of the two first main purlins 1101. After the template 12 is fixed, a steel mesh 13 is tied in the template 12.

[0025] Furthermore, the second staircase 40 includes a second supporting frame 41, which is composed of two second main purlins 4101 arranged in parallel, and the first docking plate 1102 and the second docking plate 1103 which are the same as the first supporting frame 11 are respectively arranged at relative positions. The top of the second supporting frame 41 is constructed by the same process as the first staircase 10, that is, the laying of the formwork 12 and the binding of the steel mesh 13, wherein the formwork 12 is provided with a blocking seam 42 at the lower third, and an intercepting plate 54 is provided at the blocking seam 42, in order to provide a stress release interval after the poured concrete is solidified, so as to avoid deformation of the stairs caused by shrinkage and expansion of the concrete.

[0026] like Figure 1 and 9As shown, the movable blocking plate 50 includes a first mounting plate 51, an electric telescopic rod 52 and an intercepting plate 54. The first mounting plate 51 is fixedly arranged on the side of the second staircase 40 near the blocking gap 42, the electric telescopic rod 52 is fixed on the first mounting plate 51, and the intercepting plate 54 is movably arranged in the opening direction of the blocking gap 42. A connecting arm 53 is vertically arranged at the end of the output shaft of the electric telescopic rod 52, and the top of the connecting arm 53 is arranged together with the bottom of the mounting plate. A sliding rail 5403 is arranged at one end of the intercepting plate 54 in the length direction away from the electric telescopic rod 52, and a second mounting plate 55 is arranged at the second main keel 4101 near the sliding rail 5403. A limiting block 5501 is arranged on the second mounting plate 55, and the sliding rail 5403 is slidably arranged on the limiting block 5501. The limiting block 5501 mainly provides a guiding function to ensure the sliding stability of the intercepting plate 54.

[0027] Furthermore, a plurality of movable grooves 5401 are provided on the top of the intercepting plate 54, and a protrusion 5402 extending outward is provided on the bottom of the intercepting plate 54. When the electric telescopic rod 52 is fully retracted, the protrusion 5402 abuts against the bottom of the second staircase 40. At this time, the intercepting plate 54 has no contact with the steel mesh 13 on the inner side of the second staircase 40. When the electric telescopic rod 52 is fully extended, the top of the intercepting plate 54 is located below the blocking seam 42.

[0028] Specifically, after the first staircase 10 and the second staircase 40 are assembled, the electric telescopic rod 52 is fully retracted. At this time, the intercepting plate 54 is located on the inner side of the formwork 12. A release agent is applied to the intercepting plate 54. When pouring concrete, the concrete is poured from bottom to top at one time and vibrated. During this process, there is no need to pour in two stages, which saves construction time. When the hardening standard of the concrete is met, the electric telescopic rod 52 is controlled to extend to move the intercepting plate 54 out from the inside of the formwork 12.

[0029] As a preferred embodiment, a timer 56 is provided on the first mounting plate 51, and the timer 56 is electrically connected to the electric telescopic rod 52. The disengagement time of the intercepting plate 54 is set by the timer 56. At the same time, an audible and visual alarm can be set on the first mounting plate 51. When the timing time is reached, an audible and visual alarm is sounded and the intercepting plate 54 is removed at the same time, reminding the construction personnel to proceed to the next step, thereby increasing the construction efficiency.

[0030] like Figure 5-8As shown, the lifting device 60 includes a bottom fixing plate 61, a mounting frame 62 and a square tube 63 are arranged on the top of the bottom fixing plate 61, a top plate 66 is arranged on the top of the square tube 63, a transmission assembly 64 is arranged at the intersection of the square tube 63 and the mounting frame 62, a lifting hook 65 is arranged on the transmission assembly 64, and the lifting hook 65 is used to hook the docking plates on the first supporting frame 11 and the second supporting frame 41. The height of the lifting device 60 has two different specifications, one is used to be set between the ground and the middle platform 20, and the other is set between the ground and the roof.

[0031] Specifically, when installing the first staircase 10, one of the lifting devices 60 (marked as the first lifting device here) is set at the bottom edge of the middle platform 20, and it is opposite to the vertical docking center point of the opposite end of the first staircase 10 to ensure balanced and stable force during lifting. The lifting hook 65 is set together with the second docking plate 1103 on the first staircase 10, and the drive motor 6403 on the first lifting device is started. The first staircase 10 can be moved to the target position relative to one end of the middle platform 20. In this process, the two ends can be fixed by a bolt structure after the position is corrected using a crowbar. It should be noted that when assembling the first staircase 10, a movable roller 6502 can be placed on the end away from the middle platform 20 to facilitate docking during the lifting process.

[0032] When installing the second staircase 40, two lifting devices 60 of different heights are selected. The shorter one has the same size as the first lifting device (marked as the second lifting device here), and the taller one is the third lifting device. The second lifting device is arranged at the bottom edge of the middle platform 20, and it is opposite to the vertical docking center point of the opposite end of the second staircase 40. The third lifting device is arranged below the edge of the top floor, and it is opposite to the vertical docking center point of the opposite end of the second staircase 40. At this time, the lifting hook 65 on the second lifting device is arranged together with the first docking plate 1102 on the second staircase 40, and at this time, the lifting hook 65 on the third lifting device is arranged together with the second docking plate 1103 on the second staircase 40, and then the driving motors 6403 on the two lifting devices 60 are started to make the second staircase 40 reach the target position. At this time, the crowbar is used again to calibrate the docking position to complete the fixation.

[0033] like Figure 5 and Figure 7-8 As shown, the transmission assembly 64 includes a first gear fixing plate 6401 arranged at the intersection of the mounting frame 62 and the square tube 63, where the first transmission gear 6402 is arranged, a second gear fixing plate 6404 is arranged at the intersection of the square tube 63 and the top plate 66, where the second transmission gear 6405 is arranged, a transmission belt 6406 is arranged between the two gears, and a driving motor 6403 is arranged on the mounting frame 62, and the output shaft of the driving motor 6403 is arranged together with the first transmission gear 6402.

[0034] like Figure 6 As shown, the lifting hook 65 includes a slider 6501 slidably arranged on the square tube 63, a plurality of rollers 6502 are arranged on the inner side of the slider 6501, and the rollers 6502 are in contact with the square tube 63. A first butt joint tube 6503 and a second butt joint tube 6504 are symmetrically arranged on the outer side of the slider 6501, and the first butt joint tube 6503 is fixedly connected to the transmission belt 6406, and a stair butt joint hook 6505 is arranged on the outer side of the second butt joint tube 6504, and the stair butt joint hook 6505 is used to hook the first butt joint groove 11021 or the second butt joint groove 11031: As a preferred embodiment, the mounting frame 62, square tube 63, transmission assembly 64 and lifting hook 65 on the bottom fixed plate 61 are in duplicate and are arranged side by side, wherein the driving motor 6403 shares one, i.e., the output shaft of the driving motor 6403 is respectively connected to the two first transmission gears 6402, and the two lifting hooks 65 can improve stability when applying lifting force to the docking plate on the stairs.

[0035] It should be understood that the specific order or hierarchy of steps in the disclosed process is an example of an exemplary method. Based on design preferences, it should be understood that the specific order or hierarchy of steps in the process can be rearranged without departing from the scope of protection of the present disclosure. The attached method claims present the elements of the various steps in an exemplary order and are not intended to be limited to the specific order or hierarchy described.

[0036] In the above detailed description, various features are grouped together in a single embodiment to simplify the disclosure. This method of disclosure should not be interpreted as reflecting an intention that the embodiments of the claimed subject matter require more features than are clearly stated in each claim. On the contrary, as reflected in the appended claims, the invention is in a state of having less than all the features of the disclosed individual embodiments. Therefore, the appended claims are hereby expressly incorporated into the detailed description, with each claim standing on its own as a separate preferred embodiment of the invention.

[0037] Those skilled in the art will also appreciate that the various illustrative logic blocks, modules, circuits, and algorithmic steps described in conjunction with the embodiments herein can all be implemented as electronic hardware, computer software, or a combination thereof. In order to clearly illustrate the interchangeability between hardware and software, various illustrative components, blocks, modules, circuits, and steps are generally described above around their functions. Whether such functions are implemented as hardware or software depends on specific applications and the design constraints imposed on the entire system. A skilled person can implement the described functions in an alternative manner for each specific application, but such implementation decisions should not be interpreted as departing from the scope of protection of the present disclosure.

[0038] The steps of the method or algorithm described in conjunction with the embodiments herein may be directly embodied as hardware, a software module executed by a processor, or a combination thereof. The software module may be located in a RAM memory, a flash memory, a ROM memory, an EPROM memory, an EEPROM memory, a register, a hard disk, a mobile disk, a CD-ROM, or any other form of storage medium well known in the art. An exemplary storage medium is connected to the processor so that the processor can read information from the storage medium and can write information to the storage medium. Of course, the storage medium may also be an integral part of the processor. The processor and the storage medium may be located in an ASIC. The ASIC may be located in a user terminal. Of course, the processor and the storage medium may also be present in a user terminal as discrete components.

[0039] For software implementation, the techniques described in this application can be implemented with modules (e.g., procedures, functions, etc.) that perform the functions described in this application. These software codes can be stored in a memory unit and executed by a processor. The memory unit can be implemented within the processor or outside the processor. In the latter case, it is coupled to the processor in a communication manner via various means, which are well known in the art.

[0040] The above description includes examples of one or more embodiments. Of course, it is impossible to describe all possible combinations of components or methods for the purpose of describing the above embodiments, but it should be recognized by those skilled in the art that the various embodiments may be further combined and arranged. Therefore, the embodiments described herein are intended to cover all such changes, modifications and variations that fall within the scope of protection of the appended claims. In addition, with respect to the term "comprising" used in the specification or claims, the word is covered in a manner similar to the term "including", just as "including," is explained as a transitional word in the claims. In addition, any term "or" used in the specification of the claims is intended to mean "non-exclusive or".

Claims

1. A method for lifting and intercepting a template for adapting steel bars to stair steps, characterized in that: The following steps are involved: S1, preparing construction materials for the first staircase (10), the middle platform (20) and the second staircase (40) according to the construction drawings; S2, erecting a scaffold (30) below the construction position of the intermediate platform (20), and building the intermediate platform (20) on top of the scaffold (30); S3, assembling the first staircase (10) and the second staircase (40) on the ground below the construction positions of the first staircase (10) and the second staircase (40); S4, arranging a movable blocking plate (50) at the lower third of the second staircase (40), and applying a release agent on the movable blocking plate (50); S5, erecting lifting devices (60) at both ends of the construction sites of the first staircase (10) and the second staircase (40), and cleaning the construction waste in the formwork (12) to keep the formwork (12) clean; S6, using the lifting device (60) to lift the assembled first staircase (10) and the second staircase (40) to a construction site for fixing; S7, pouring cement mortar from bottom to top using grouting equipment and waiting for solidification; S8, after solidification is completed, the movable baffle plate (50) is automatically separated, and the formwork (12) and the scaffolding (30) can be removed.

2. A method for lifting and intercepting a template for staircase-adaptive steel bars as claimed in claim 1, characterized in that: The intermediate platform (20) comprises two platform plates (21) spliced ​​together, an I-beam (22) is arranged around the platform plate (21), the bottom of the I-beam (22) is fixed to the top of the scaffold (30) by bolts, and the intermediate platform (20) is the main load-bearing platform connecting the first staircase (10) and the second staircase (40). A template (12) is assembled above the intermediate platform (20), and a steel mesh (13) is tied inside the template (12).

3. A method for lifting and intercepting a template for staircase-adaptive steel bars as claimed in claim 2, characterized in that: The first staircase (10) comprises a first supporting frame (11), which is formed by two first main keels (1101) arranged in parallel, and a first docking plate (1102) and a second docking plate (1103) are respectively arranged at relative positions of the two first main keels, a first docking groove (11021) is opened at the top center of the first docking plate (1102), and a second docking groove (11031) is opened at the top center of the second docking plate (1103), and a template (12) is arranged on the top of the two first main keels (1101), and after the template (12) is fixed, a steel mesh (13) is tied in the template (12).

4. A method for lifting and intercepting a template for staircase-adaptive steel bars as claimed in claim 3, characterized in that: The second staircase (40) comprises a second supporting frame (41), which is formed by two second main keels (4101) arranged in parallel, and the first butt joint plate (1102) and the second butt joint plate (1103) which are the same as those of the first supporting frame (11) are respectively arranged at relative positions of the second supporting frame (41). The top of the second supporting frame (41) is constructed by the same process as the first staircase (10), namely, the laying of the template (12) and the binding of the steel mesh (13), wherein the template (12) is provided with a blocking seam (42) at the lower third.

5. A method for lifting and intercepting a template for staircase-adaptive steel bars as claimed in claim 4, characterized in that: The movable blocking plate (50) comprises a first mounting plate (51), an electric telescopic rod (52) and an intercepting plate (54); the first mounting plate (51) is fixedly arranged on the side of the second staircase (40) near the blocking gap (42); the electric telescopic rod (52) is fixed on the first mounting plate (51); the intercepting plate (54) is movably arranged in the opening direction of the blocking gap (42); a connecting arm (53) is vertically arranged at the end of the output shaft of the electric telescopic rod (52); the top of the connecting arm (53) is arranged together with the bottom of the mounting plate; a sliding rail (5403) is arranged at one end of one side of the intercepting plate (54) in the length direction away from the electric telescopic rod (52); a second mounting plate (55) is arranged at the second main keel (4101) near the sliding rail (5403); a limiting block (5501) is arranged on the second mounting plate (55); and the sliding rail (5403) is slidably arranged on the limiting block (5501).

6. A method for lifting and intercepting a template for staircase-adaptive steel bars as claimed in claim 5, characterized in that: The top of the intercepting plate (54) is provided with a plurality of movable grooves (5401), and the bottom of the intercepting plate (54) is provided with a protruding portion (5402) extending outward. When the electric telescopic rod (52) is fully retracted, the protruding portion (5402) contacts the bottom of the second staircase (40). At this time, the intercepting plate (54) has no contact with the steel mesh (13) on the inner side of the second staircase (40). When the electric telescopic rod (52) is fully extended, the top of the intercepting plate (54) is located below the blocking gap (42).

7. A method for lifting and intercepting a template for staircase-adaptive steel bars as claimed in claim 6, characterized in that: A timer (56) is provided on the first mounting plate (51), and the timer (56) is electrically connected to the electric telescopic rod (52).

8. A method for lifting and intercepting a template for staircase-adaptive steel bars as claimed in claim 4, characterized in that: The lifting device (60) comprises a bottom fixing plate (61), a mounting frame (62) and a square tube (63) are arranged on the top of the bottom fixing plate (61), a top plate (66) is arranged on the top of the square tube (63), a transmission assembly (64) is arranged at the intersection of the square tube (63) and the mounting frame (62), a lifting hook (65) is arranged on the transmission assembly (64), and the lifting hook (65) is used to hook the docking plates on the first supporting frame (11) and the second supporting frame (41). The height of the lifting device (60) has two different specifications, one for being arranged between the ground and the middle platform (20), and the other for being arranged between the ground and the roof.

9. A method for lifting and intercepting a template for staircase-adaptive steel bars as claimed in claim 8, characterized in that: The transmission assembly (64) comprises a first gear fixing plate (6401) arranged at the intersection of the mounting frame (62) and the square tube (63), wherein a first transmission gear (6402) is arranged thereon; a second gear fixing plate (6404) is arranged at the intersection of the square tube (63) and the top plate (66), wherein a second transmission gear (6405) is arranged thereon; a transmission belt (6406) is arranged between the two gears; a driving motor (6403) is arranged on the mounting frame (62), and an output shaft of the driving motor (6403) is arranged together with the first transmission gear (6402).

10. A method for lifting and intercepting a template for staircase-adaptive steel bars as claimed in claim 9, characterized in that: The lifting hook (65) comprises a slider (6501) slidably arranged on the square tube (63); a plurality of rollers (6502) are arranged on the inner side of the slider (6501); the rollers (6502) are in contact with the square tube (63); a first butt joint tube (6503) and a second butt joint tube (6504) are symmetrically arranged on the outer side of the slider (6501); the first butt joint tube (6503) is fixedly connected to the transmission belt (6406); a stair butt joint hook (6505) is arranged on the outer side of the second butt joint tube (6504); the stair butt joint hook (6505) is used to hook the first butt joint groove (11021) or the second butt joint groove (11031).

Citation Information

Patent Citations

  • Device for continuously pouring concrete at expansion joint of pavement and construction method

    CN115522428A

  • Tool type stair construction joint formwork combined structure and using method

    CN117230991A

  • Stair formwork supporting structure

    CN218758756U

  • Expansion joint shaping mold assembly for concrete floor pouring

    CN221481284U

  • Reverse slip form device capable of being repeatedly used under unfavorable geological conditions

    CN222044266U