Data-driven distribution transformer actual operation gear accurate identification method and system and medium

Through the data-driven method, the distribution network single-phase trend data and K-means clustering algorithm are used to identify the actual operating gears of the distribution transformer in the distribution network, solving the problems of cumbersome manual verification and inaccurate identification in the existing technology, and achieving high accuracy and low impact gear recognition.

CN119596057AActive Publication Date: 2025-03-11STATE GRID HUBEI ELECTRIC POWER RES INST +2
View PDF 5 Cites 0 Cited by

Patent Information

Application Number
CN202411569663.5
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-11-05
Publication Date
2025-03-11
Estimated Expiration
2044-11-05

AI Technical Summary

Technical Problem

The distribution gear recognition method in the existing distribution network mainly relies on manual offline verification and online identification of transformer windings. There are problems such as busy processes, time-consuming and labor-consuming, potential damage to the transformer, and it is difficult to accurately identify gears when voltage fluctuations are frequent.

Method used

Through a data-driven method, data screening and analysis is performed using single-phase flow data of distribution networks within one month of history, combined with the K-means clustering algorithm, the actual operating gear of distribution transformers is identified, and different recognition steps are used to minimize the impact on power grid operation according to whether the topological structure has wire distance information.

Benefits of technology

It realizes accurate identification of the actual operating gear of the distribution transformer, reduces the workload of manual verification and the impact on the power grid operation, provides sufficient data support for the distribution transformer adjustment, and improves the accuracy of the identification results.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119596057A_ABST
    Figure CN119596057A_ABST
Patent Text Reader

Abstract

The invention relates to a data-driven accurate identification method and system for an actual operation gear of a distribution transformer and a medium, and the method comprises the steps: screening data, selecting a time range corresponding to a single-phase power flow of a distribution network every day in a historical month, and determining a subsequent voltage analysis reference time node; the method comprises the following steps: identifying operation gears of distribution transformers, judging whether the topology has lead distance information or not, judging the operation gear of the head-end distribution transformer and then judging the operation gears of other distribution transformers when the topology has the lead distance information, and calculating the difference between the actual voltage and the theoretical voltage and then judging the operation gears of the distribution transformers when the topology lacks the lead distance information. The actual operation gear of the distribution transformer is accurately identified in a data analysis mode, the influence of the gear identification work of the distribution transformer on the operation of a power grid is minimized, and a sufficient basis is provided for gear shifting of the distribution transformer.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the field of electric power grid technology, and in particular to a data-driven method, system and medium for accurately identifying the actual operating gear position of a distribution transformer. Background Art

[0002] Accurate distribution transformer gear position identification is the basis of distribution transformer gear position adjustment strategy, and it is also the key and difficult point that troubles many researchers. At present, most of the distribution transformers installed in the distribution network are no-load voltage regulating devices, and the distribution transformer gear position identification methods adopted are mainly manual offline verification, verification using verification devices, and online identification based on transformer windings.

[0003] The manual verification method requires first issuing a work ticket, shutting down the distribution transformer, and then carrying the verification device to climb onto the transformer for inspection. Not only is the process busy, but it is also time-consuming and labor-intensive. The method based on the transformer winding is likely to interfere with the normal operation of the transformer and may even damage the transformer. In addition, due to frequent voltage fluctuations, manual offline verification at a certain point in time or the original data of transformer winding identification can hardly truly determine the gear position of the distribution transformer. Summary of the invention

[0004] The purpose of the embodiments of the present application is to provide a data-driven method, system and medium for accurately identifying the actual operating gear of the distribution transformer, accurately identifying the actual operating gear of the distribution transformer through data analysis, minimizing the impact of the distribution transformer gear identification work on the operation of the power grid, and providing sufficient basis for the distribution transformer gear adjustment.

[0005] To achieve the above objectives, this application provides the following technical solutions:

[0006] In a first aspect, an embodiment of the present application provides a data-driven method for accurately identifying the actual operating gear position of a distribution transformer, comprising the following steps:

[0007] Data screening: select the time range corresponding to the single-phase power flow of the distribution network every day in the past month to determine the reference time node for subsequent voltage analysis;

[0008] Identify the operating gear of the distribution transformer to determine whether the topology has wire distance information. When the topology has wire distance information, first determine the operating gear of the first-end distribution transformer and then determine the operating gear of other distribution transformers. When the topology lacks wire distance information, first calculate the difference between the actual voltage and the theoretical voltage and then determine the operating gear of the distribution transformer.

[0009] The data screening is specifically as follows:

[0010] (1) Select the time range T corresponding to the single-phase power flow of the distribution network every day in the history of one month i ′ , where the value range of i is as follows:

[0011] i∈{1,2,3,…,30}(1)

[0012] (2) Calculate all T i The intersection of is used as the reference time range T′ of the single-phase power flow of the distribution network required for subsequent calculations.

[0013] T′=T′1∪T′2∪…∪T′ 30 (2)

[0014] (3) Select the time T″ when the busbar outlet current is the smallest every day in a month i And the bus current I at this moment i Create two-dimensional sample points X i

[0015] X i =(T″ i ,I i ) (3)

[0016] (4) Use K-means clustering algorithm to calculate all sample points X i The center point U of each classification j ,

[0017] a. Randomly select K points from the sample points as the initial cluster centers,

[0018] b. Divide each sample point into the center point U closest to it j , in the cluster represented by j∈{1,…,k},

[0019] c. Replace the original center point with the center point of all samples in each cluster,

[0020] d. Repeat steps b and c until the center point remains unchanged or the predetermined number of iterations is reached, the algorithm terminates, and the objective function of the K-means clustering algorithm is the intra-cluster error sum of squares SSE

[0021]

[0022] (5) Establish the center point U of each classification j The collection U

[0023] U={U1,…,U k} (5)

[0024] (6) Sort all sample points in set U according to the bus current value and establish a new set U I

[0025]

[0026] In formula (6) represents the sample point with the smallest bus current value in the set U, Represents the set U I The sample point with the largest bus current value,

[0027] (7) Select set U I The time corresponding to all sample points in the time set T I

[0028]

[0029] (8) According to the order in formula (7), traverse T I Select the first one that matches the distribution network single-phase flow reference time range T ′ The overlapping data is used as the reference time node T for subsequent voltage analysis.

[0030] T∈T I (8)

[0031] T∈T ′ (9).

[0032] When the topology has the conductor distance information, the operation gear position of the first-end distribution transformer is judged first and then the operation gear positions of other distribution transformers are judged specifically as follows:

[0033] Determination of the running gear of the first-end distribution transformer:

[0034] (1) According to the voltage analysis reference time node T in step 1-(8), the bus or dedicated transformer high-voltage side voltage is used as the line head end distribution transformer high-voltage side voltage, and express,

[0035] (2) Taking the middle gear of the distribution transformer as the first iteration parameter, calculate the theoretical value of the output voltage on the low-voltage side of the first end

[0036]

[0037] (3) Calculate the measured voltage on the low voltage side of the first end target day Theoretical voltage on the low voltage side The difference

[0038]

[0039] (4) Identification of the first end running gear, based on theoretical analysis, It will fluctuate around 0V, ±10V, and ±20V. According to step 2-(3) To determine the first-end operating gear, it should be noted that the 5-speed transformer can be directly determined, while the 3-speed transformer cannot be completely determined and can only be suspected.

[0040]

[0041] The other distribution transformer operating gear position judgment,

[0042] (1) After the above steps to determine the operating gear of the first-end distribution transformer, the actual operating gear of the first-end distribution transformer is obtained, and the PD o Indicates that according to the actual operating gear position PD of the first-end distribution transformer o And the measured voltage on the low voltage side of the head-end distribution transformer on the target day Calculate and infer the actual voltage value of the high voltage side of the head-end distribution transformer on the target day

[0043] In the above formula, ZD3 represents the middle gear of the three-gear transformer, and ZD5 represents the middle gear of the five-gear transformer.

[0044] Based on the topological relationship of the distribution transformers in the distribution network, all the distribution transformers directly connected to the head-end distribution transformer are selected, and the high-voltage side voltage is the actual voltage value of the high-voltage side of the head-end distribution transformer on the target day. Instead, repeat the steps (2)-(4) in the first-end distribution transformer operating gear determination to find out the actual operating gear of all distribution transformers directly connected to the first-end distribution transformer and the actual high-voltage side voltage on the target day.

[0045] By looping the steps of judging the operating gear of the head-end distribution transformer and judging the operating gear of other distribution transformers, the actual operating gear of all distribution transformers in the target distribution network can be obtained.

[0046] When the topology lacks conductor distance information, the actual voltage and theoretical voltage difference is calculated first, and then the distribution transformer operation gear is judged. Specifically,

[0047] ① Calculation of the difference between actual voltage and theoretical voltage

[0048] A. According to the voltage analysis reference time node in step 1-(8), establish the target day transformer high voltage side voltage assignment method,

[0049] a. Obtain the topology diagram of 10kV wiring. Based on the topology diagram, define all FTUs, special transformers, and public transformers as primary center points, secondary center points, and points to be classified.

[0050] b. Assume that the number of primary center points, secondary center points, and points to be classified are P, Q, and N respectively. Calculate the distance between each point to be classified n and each primary center point and secondary center point, respectively. express,

[0051] c. Randomly select a point n to be classified, select The minimum value of Indicates that the high voltage side voltage of classification point n is assigned according to the following formula

[0052]

[0053] In formula (15), They represent the voltages of the point to be classified n, the first-level classification point p, and the second-level classification point q at time T, respectively.

[0054] Repeat the above step c for all remaining points to be classified, and the high-voltage side voltage of all public transformers within the target day can be assigned.

[0055] B. Take each public transformer after assigning the high-voltage side voltage as the reference, take the public transformer intermediate gear (high-voltage side rated voltage 10kV) as the first iteration parameter, and calculate the theoretical value of the low-voltage side outlet voltage of each public transformer

[0056]

[0057] C. Calculate the target daily measured voltage of each public transformer With theoretical voltage The difference

[0058] ② Distribution transformer running gear judgment

[0059] Distribution transformer operating gear identification, based on theoretical analysis, It will fluctuate around 0V, ±10V, and ±20V. Determine the operating gear of each distribution transformer.

[0060]

[0061] By repeating steps ① to ② for multiple target day data, the actual operating gear of the distribution transformer can be determined more accurately.

[0062] In a second aspect, the embodiment of the present application provides a data-driven distribution transformer actual operating gear position accurate identification system, comprising:

[0063] The data screening module selects the time range corresponding to the single-phase power flow of the distribution network every day in the history of one month to determine the reference time node for subsequent voltage analysis;

[0064] The distribution transformer operating gear identification module determines whether the topology has wire distance information. When the topology has wire distance information, the first-end distribution transformer operating gear is judged first and then the other distribution transformer operating gears are judged. When the topology lacks wire distance information, the actual voltage and theoretical voltage difference is calculated first and then the distribution transformer operating gear is judged.

[0065] In a third aspect, an embodiment of the present application provides a computer-readable storage medium, wherein the computer-readable storage medium stores a program code, and when the program code is executed by a processor, the steps of the data-driven method for accurately identifying the actual operating gear position of the distribution transformer are implemented as described above.

[0066] Compared with the prior art, the present invention has the following beneficial effects:

[0067] 1. By selecting the single-phase power flow moment of the power grid and the moment when the current on the bus outlet side is the smallest as the research object, the final gear recognition result has a higher accuracy.

[0068] 2. By constructing a data-driven method for accurately identifying the actual operating gear position of the distribution transformer, it can effectively solve the problem that the traditional manual gear position verification is heavy and affects the normal operation of the distribution transformer, and provide strong data support for the distribution transformer gear adjustment work. BRIEF DESCRIPTION OF THE DRAWINGS

[0069] In order to more clearly illustrate the technical solutions of the embodiments of the present application, the drawings required for use in the embodiments of the present application will be briefly introduced below. It should be understood that the following drawings only show certain embodiments of the present application and therefore should not be regarded as limiting the scope. For ordinary technicians in this field, other related drawings can be obtained based on these drawings without paying creative work.

[0070] Figure 1 It is a flow chart of the method of the present invention. DETAILED DESCRIPTION

[0071] The technical solutions in the embodiments of the present application will be described below in conjunction with the drawings in the embodiments of the present application. It should be noted that similar reference numerals and letters represent similar items in the following drawings, so once an item is defined in one drawing, it does not need to be further defined and explained in the subsequent drawings.

[0072] The terms "comprises," "comprising," or any other variation thereof are intended to encompass non-exclusive inclusion, such that a process, method, article, or apparatus that includes a list of elements includes not only those elements, but also other elements not explicitly listed, or elements inherent to such process, method, article, or apparatus. In the absence of further limitations, an element defined by the phrase "comprising a ..." does not exclude the presence of additional identical elements in the process, method, article, or apparatus that includes the element.

[0073] The terms "first", "second", etc. are only used to distinguish one entity or operation from another entity or operation, and should not be understood as indicating or implying relative importance, nor should they be understood as requiring or implying any such actual relationship or order between these entities or operations.

[0074] like Figure 1 A data-driven method for accurately identifying the actual operating gear position of a distribution transformer is shown, comprising the following steps:

[0075] Data screening: select the time range corresponding to the single-phase power flow of the distribution network every day in the past month to determine the reference time node for subsequent voltage analysis;

[0076] Identify the operating gear of the distribution transformer to determine whether the topology has wire distance information. When the topology has wire distance information, first determine the operating gear of the first-end distribution transformer and then determine the operating gear of other distribution transformers. When the topology lacks wire distance information, first calculate the difference between the actual voltage and the theoretical voltage and then determine the operating gear of the distribution transformer.

[0077] 1. Data screening

[0078] (1) Select the time range T corresponding to the single-phase power flow of the distribution network every day in the history of one month i ′ , where the value range of i is as follows:

[0079] i∈{1,2,3,…,30}(1)

[0080] (2) Calculate all T i The intersection of is used as the reference time range T for the single-phase power flow of the distribution network required for subsequent calculations ′ .

[0081] T′=T′1∪T′2∪…∪T′ 30 (2)

[0082] (3) Select the time T″ when the busbar outlet current is the smallest every day in a month i And the bus current I at this moment i Create two-dimensional sample points X i

[0083] X i =(T″ i ,I i ) (3)

[0084] (4) Use K-means clustering algorithm to calculate all sample points X i The center point U of each classification j

[0085] a. Randomly select K points from the sample points as the initial cluster centers.

[0086] b. Divide each sample point into the center point U closest to it j , in the cluster represented by j∈{1,…,k}.

[0087] c. Replace the original center point with the center point of all samples in each cluster.

[0088] d. Repeat steps b and c until the center point remains unchanged or the predetermined number of iterations is reached, and the algorithm terminates.

[0089] The objective function of the K-means clustering algorithm is the sum of squared errors within the cluster (SSE).

[0090]

[0091] (5) Establish the center point U of each classification j The collection U

[0092] U={U1,…,U k} (5)

[0093] (6) Sort all sample points in set U according to the bus current value and establish a new set U I

[0094]

[0095] In formula (6) represents the sample point with the smallest bus current value in the set U, Represents the set U I The sample point with the largest bus current value.

[0096] (7) Select set U I The time corresponding to all sample points in the time set T I

[0097]

[0098] (8) According to the order in formula (7), traverse T I Select the first one that matches the distribution network single-phase flow reference time range T ′ The overlapping data serves as the reference time node T for subsequent voltage analysis.

[0099] T∈T I (8)

[0100] T∈T ′ (9)

[0101] 2. Distribution transformer operating gear identification

[0102] First, we need to determine whether the topology has wire distance information

[0103] (1) Topology has wire distance information

[0104] ① Determination of the running gear of the first-end distribution transformer

[0105] a. According to the voltage analysis reference time node T in step 1-(8), the bus or dedicated transformer high-voltage side voltage is used as the line head end distribution transformer high-voltage side voltage, and express.

[0106] b. Take the middle gear of the distribution transformer as the first iteration parameter and calculate the theoretical value of the output voltage on the low-voltage side of the first end

[0107]

[0108] c. Calculate the actual voltage on the low voltage side of the first end target day Theoretical voltage on the low voltage side The difference

[0109]

[0110] d. Identification of the first end running gear, based on theoretical analysis, It will fluctuate around 0V, ±10V, and ±20V. According to formula (12), To determine the operating gear position at the first end, it should be noted that the 5-speed transformer can be directly determined, while the 3-speed transformer cannot be completely determined and can only be suspected.

[0111]

[0112] ② Determination of other distribution transformer operating gears

[0113] a. After the above step ①, the actual operating gear of the first-end distribution transformer can be obtained, using PD o Indicates that according to the actual operating gear position PD of the first-end distribution transformer o And the measured voltage on the low voltage side of the head-end distribution transformer on the target day Calculate and infer the actual voltage value of the high voltage side of the head-end distribution transformer on the target day

[0114]

[0115] In the above formula, ZD3 represents the middle gear of the three-speed transformer, and ZD5 represents the middle gear of the five-speed transformer.

[0116] b. Based on the topological relationship of distribution transformers in the distribution network, select all distribution transformers directly connected to the head-end distribution transformer, and use the actual voltage value of the high-voltage side of the head-end distribution transformer on the target day as the voltage on the high-voltage side. Instead, repeat step ①bd to find out the actual operating gear of all distribution transformers directly connected to the head-end distribution transformer and the actual high-voltage side voltage on the target day.

[0117] c. Repeat the above steps to obtain the actual operating gear of all distribution transformers in the target distribution network.

[0118] (2) The topology lacks wire distance information

[0119] ① Calculation of the difference between actual voltage and theoretical voltage

[0120] A. Based on the voltage analysis reference time node in step 1-(8), establish a method for assigning the voltage on the high-voltage side of the public transformer on the target day.

[0121] a. Obtain the topology diagram of 10kV wiring. Based on the topology diagram, define all FTUs, special transformers, and public transformers as primary center points, secondary center points, and points to be classified.

[0122] b. Assume that the number of primary center points, secondary center points, and points to be classified are P, Q, and N respectively. Calculate the distance between each point to be classified n and each primary center point and secondary center point, respectively. (Unit: meter)

[0123] c. Randomly select a point n to be classified, select The minimum value of Indicates that the high voltage side voltage of classification point n is assigned according to the following formula

[0124]

[0125] In formula (15), They represent the voltages of the point to be classified n, the first-level classification point p, and the second-level classification point q at time T respectively.

[0126] Repeat the above step c for all remaining points to be classified, and the high-voltage side voltage of all public transformers within the target day can be assigned.

[0127] B. Take each public transformer after assigning the high-voltage side voltage as the reference, take the public transformer intermediate gear (high-voltage side rated voltage 10kV) as the first iteration parameter, and calculate the theoretical value of the low-voltage side outlet voltage of each public transformer

[0128]

[0129] C. Calculate the target daily measured voltage of each public transformer With theoretical voltage The difference

[0130] ② Distribution transformer running gear judgment

[0131] Distribution transformer operating gear identification, based on theoretical analysis, It will fluctuate around 0V, ±10V, and ±20V. Determine the operating gear of each distribution transformer.

[0132]

[0133] By repeating steps ① to ② for multiple target day data, the actual operating gear of the distribution transformer can be determined more accurately.

[0134] 3. Demonstration by Example

[0135] Taking the distribution networks in several regions of Hubei Province as an example, the actual operating gears of all distribution transformers are identified by combining the distribution transformer gear recognition algorithm in the present invention, and the accuracy of the present invention is verified based on the manual investigation results:

[0136] Table 1 Statistics on the accuracy of gear position recognition in a certain area of ​​Hubei Province

[0137]

[0138]

[0139] It can be seen from the contents in Table 1 that the transmission gear position identification method of the present invention has an extremely high accuracy rate, and the transmission gear position identification accuracy rate in various regions of Hubei Province is as high as 100%, which has a high application value.

[0140] The embodiment of the present application provides a data-driven distribution transformer actual operating gear position accurate identification system, comprising:

[0141] The data screening module selects the time range corresponding to the single-phase power flow of the distribution network every day in the history of one month to determine the reference time node for subsequent voltage analysis;

[0142] The distribution transformer operating gear identification module determines whether the topology has wire distance information. When the topology has wire distance information, the first-end distribution transformer operating gear is judged first and then the other distribution transformer operating gears are judged. When the topology lacks wire distance information, the actual voltage and theoretical voltage difference is calculated first and then the distribution transformer operating gear is judged.

[0143] An embodiment of the present application provides a computer-readable storage medium, wherein the computer-readable storage medium stores program code, and when the program code is executed by a processor, the steps of the data-driven method for accurately identifying the actual operating gear position of a distribution transformer are implemented as described above.

[0144] Those skilled in the art will appreciate that the embodiments of the present application may be provided as methods, systems, or computer program products. Therefore, the present application may adopt the form of a complete hardware embodiment, a complete software embodiment, or an embodiment in combination with software and hardware. Moreover, the present application may adopt the form of a computer program product implemented in one or more computer-usable storage media (including but not limited to disk storage, CD-ROM, optical storage, etc.) that include computer-usable program code.

[0145] The present application is described with reference to the flowcharts and / or block diagrams of the methods, devices (systems), and computer program products according to the embodiments of the present application. It should be understood that each process and / or box in the flowchart and / or block diagram, as well as the combination of the processes and / or boxes in the flowchart and / or block diagram, can be implemented by computer program instructions. These computer program instructions can be provided to a processor of a general-purpose computer, a special-purpose computer, an embedded processor, or other programmable data processing device to generate a machine, so that the instructions executed by the processor of the computer or other programmable data processing device generate instructions for implementing the processes in the flowchart and / or block diagram. Figure 1 A process or multiple processes and / or boxes Figure 1 A device that provides the functions specified in a block or multiple blocks.

[0146] These computer program instructions may also be stored in a computer-readable memory capable of directing a computer or other programmable data processing device to operate in a specific manner, so that the instructions stored in the computer-readable memory produce an article of manufacture comprising an instruction device, which implements the process Figure 1 A process or multiple processes and / or boxes Figure 1 A function specified in one or more boxes.

[0147] These computer program instructions can also be loaded onto a computer or other programmable data processing device so that a series of operating steps are executed on the computer or other programmable device to produce a computer-implemented process, thereby providing instructions for implementing the process. Figure 1 A process or multiple processes and / or boxes Figure 1 The steps for the functions specified in one or more boxes.

[0148] In a typical configuration, a computing device includes one or more processors (CPU), input / output interfaces, network interfaces, and memory.

[0149] The memory may include non-permanent memory in a computer-readable medium, random access memory (RAM) and / or non-volatile memory in the form of read-only memory (ROM) or flash RAM. The memory is an example of a computer-readable medium.

[0150] Computer readable media include permanent and non-permanent, removable and non-removable media that can be implemented by any method or technology to store information. Information can be computer readable instructions, data structures, program modules or other data. Examples of computer storage media include, but are not limited to, phase change memory (PRAM), static random access memory (SRAM), dynamic random access memory (DRAM), other types of random access memory (RAM), read-only memory (ROM), electrically erasable programmable read-only memory (EEPROM), flash memory or other memory technology, compact disk read-only memory (CD-ROM), digital versatile disk (DVD) or other optical storage, magnetic cassettes, magnetic tape magnetic disk storage or other magnetic storage devices or any other non-transmission media that can be used to store information that can be accessed by a computing device. As defined herein, computer readable media does not include temporary computer readable media (transitory media), such as modulated data signals and carrier waves.

[0151] The above description is only an embodiment of the present application and is not intended to limit the protection scope of the present application. For those skilled in the art, the present application may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present application shall be included in the protection scope of the present application.

Claims

1. A data-driven method for accurately identifying the actual operating gear position of a distribution transformer, characterized in that: The steps include: Data screening: select the time range corresponding to the single-phase power flow of the distribution network every day in the past month to determine the reference time node for subsequent voltage analysis; Identify the operating gear of the distribution transformer to determine whether the topology has wire distance information. When the topology has wire distance information, first determine the operating gear of the first-end distribution transformer and then determine the operating gear of other distribution transformers. When the topology lacks wire distance information, first calculate the difference between the actual voltage and the theoretical voltage and then determine the operating gear of the distribution transformer.

2. A data-driven method for accurately identifying the actual operating gear position of a distribution transformer as claimed in claim 1, characterized in that: The data screening is specifically as follows: (1) Select the time range T corresponding to the single-phase power flow of the distribution network every day in the history of one month i ′ , where the value range of i is as follows: i∈{1,2,3,…,30}(1) (2) Calculate all T i The intersection of is used as the reference time range T for the single-phase power flow of the distribution network required for subsequent calculations ′ , T′=T′1∪T′2∪…∪T′ 30 (2) (3) Select the time T″ when the busbar outlet current is the smallest every day in a month i And the bus current I at this moment i Create two-dimensional sample points X i X i =(T″ i ,I i ) (3) (4) Use K-means clustering algorithm to calculate all sample points X i The center point U of each classification j , a. Randomly select K points from the sample points as the initial cluster centers, b. Divide each sample point into the center point U closest to it j , in the cluster represented by j∈{1,…,k}, c. Replace the original center point with the center point of all samples in each cluster, d. Repeat steps b and c until the center point remains unchanged or the predetermined number of iterations is reached, the algorithm terminates. The objective function of the K-means clustering algorithm is the sum of squared errors within the cluster (SSE). (5) Establish the center point U of each classification j The collection U U={U1,…,U k } (5) (6) Sort all sample points in set U according to the bus current value and establish a new set U I In formula (6) represents the sample point with the smallest bus current value in the set U, Represents the set U I The sample point with the largest bus current value, (7) Select set U I The time corresponding to all sample points in the time set T I (8) According to the order in formula (7), traverse T I Select the first one that matches the distribution network single-phase flow reference time range T ′ The overlapping data is used as the reference time node T for subsequent voltage analysis. T∈T I (8) T∈T ′ (9)。 3. A data-driven method for accurately identifying the actual operating gear position of a distribution transformer as claimed in claim 1, characterized in that: When the topology has the conductor distance information, the operation gear position of the first-end distribution transformer is judged first and then the operation gear positions of other distribution transformers are judged specifically as follows: Determination of the running gear of the first-end distribution transformer: (1) According to the voltage analysis reference time node T in step 1-(8), the bus or dedicated transformer high-voltage side voltage is used as the line head end distribution transformer high-voltage side voltage, and express, (2) Taking the middle gear of the distribution transformer as the first iteration parameter, calculate the theoretical value of the output voltage on the low-voltage side of the first end (3) Calculate the measured voltage on the low-voltage side of the first end target day Theoretical voltage on the low voltage side The difference (4) Identification of the first end running gear, based on theoretical analysis, It will fluctuate around 0V, ±10V, and ±20V. According to step 2-(3) To determine the first-end operating gear, it should be noted that the 5-speed transformer can be directly determined, while the 3-speed transformer cannot be completely determined and can only be suspected.

4. A data-driven method for accurately identifying the actual operating gear position of a distribution transformer as claimed in claim 3, characterized in that: The other distribution transformer operating gear position determination is specifically as follows: (1) After the above steps to determine the operating gear of the first-end distribution transformer, the actual operating gear of the first-end distribution transformer is obtained, and the PD o Indicates that according to the actual operating gear PD of the first-end distribution transformer o And the measured voltage on the low voltage side of the head-end distribution transformer on the target day Calculate and infer the actual voltage value of the high voltage side of the head-end distribution transformer on the target day In the above formula, ZD3 represents the middle gear of the three-gear transformer, and ZD5 represents the middle gear of the five-gear transformer. Based on the topological relationship of the distribution transformers in the distribution network, all the distribution transformers directly connected to the head-end distribution transformer are selected, and the high-voltage side voltage is the actual voltage value of the high-voltage side of the head-end distribution transformer on the target day. Instead, repeat the steps (2)-(4) in the first-end distribution transformer operating gear determination to find out the actual operating gear of all distribution transformers directly connected to the first-end distribution transformer and the actual high-voltage side voltage on the target day. By looping the steps of judging the operating gear of the head-end distribution transformer and judging the operating gear of other distribution transformers, the actual operating gear of all distribution transformers in the target distribution network can be obtained.

5. A data-driven method for accurately identifying the actual operating gear position of a distribution transformer as claimed in claim 4, characterized in that: When the topology lacks conductor distance information, the actual voltage and theoretical voltage difference is calculated first, and then the distribution transformer operation gear is judged. Specifically, ① Calculation of the difference between actual voltage and theoretical voltage A. According to the voltage analysis reference time node in step 1-(8), establish the target day transformer high voltage side voltage assignment method, a. Obtain the topology diagram of 10kV wiring. Based on the topology diagram, define all FTUs, special transformers, and public transformers as primary center points, secondary center points, and points to be classified. b. Assume that the number of primary center points, secondary center points, and points to be classified are P, Q, and N respectively. Calculate the distance between each point to be classified n and each primary center point and secondary center point, respectively. express, c. Randomly select a point n to be classified, select The minimum value of Indicates that the high voltage side voltage of classification point n is assigned according to the following formula In formula (15), They represent the voltages of the point to be classified n, the first-level classification point p, and the second-level classification point q at time T, respectively. Repeat the above step c for all remaining points to be classified, and the high-voltage side voltage of all public transformers within the target day can be assigned. B. Take each public transformer after assigning the high-voltage side voltage as the reference, take the public transformer intermediate gear (high-voltage side rated voltage 10kV) as the first iteration parameter, and calculate the theoretical value of the low-voltage side outlet voltage of each public transformer C. Calculate the target daily measured voltage of each public transformer With theoretical voltage The difference ② Distribution transformer running gear judgment Distribution transformer operating gear identification, based on theoretical analysis, It will fluctuate around 0V, ±10V, and ±20V. Determine the operating gear of each distribution transformer. By repeating steps ① to ② for multiple target day data, the actual operating gear of the distribution transformer can be determined more accurately.

6. A data-driven distribution transformer actual operating gear position accurate identification system, characterized in that: include, The data screening module selects the time range corresponding to the single-phase power flow of the distribution network every day in the history of one month to determine the reference time node for subsequent voltage analysis; The distribution transformer operating gear identification module determines whether the topology has wire distance information. When the topology has wire distance information, the first-end distribution transformer operating gear is judged first and then the other distribution transformer operating gears are judged. When the topology lacks wire distance information, the actual voltage and theoretical voltage difference is calculated first and then the distribution transformer operating gear is judged.

7. A computer-readable storage medium, characterized in that: The computer-readable storage medium stores program codes, and when the program codes are executed by a processor, the steps of the data-driven method for accurately identifying the actual operating gear position of a distribution transformer as claimed in any one of claims 1 to 5 are implemented.

Citation Information

Patent Citations

  • Transformer gear determination method and device, and photovoltaic power generation system

    CN110739860A

  • Gear determination method of transformer

    CN112595996A

  • Distribution transformer gear identification method, system and device based on LightGBM classification and load flow calculation

    CN118381019A

  • Test drive for tap changer

    DE202009012198U1

  • Method and apparatus for controlling transformer, device, and storage medium

    WO2022062286A1